A method for time-space intensive rapid demolition construction of viaducts in dense traffic environment
By optimizing the combination of BIM model-based segmentation and dual-machine lifting equipment, setting up anti-overturning structures and multi-index collaborative control, the safety risks and environmental impacts of the demolition of elevated bridges in the urban core area were resolved, achieving efficient construction adaptation.
Patent Information
- Application Number
- CN202611448834.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-17
- Publication Date
- 2026-11-20
AI Technical Summary
The problems include a limited window of opportunity for the demolition of elevated bridges in the city's core area, poor coordination of procedures, insufficient matching of component blocks, high risk of overturning of the last beam, and lack of control measures for sensitive environments.
The segmentation scheme was determined by reverse optimization based on the BIM model. Pre-lifting verification was carried out using a dual-machine lifting device. A double-insurance structure to prevent overturning of the last beam was set up. Double-layer roadbed plates were laid in sensitive environmental areas. Multiple indicators were monitored in real time for coordinated control.
It achieves safe and efficient overpass demolition, adapts to the city's limited off-peak construction window, reduces the time components stay on site, alleviates pressure on confined spaces, and ensures operational safety in sensitive environments.
Smart Images

Figure CN123133285A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of bridge demolition construction technology, and more specifically, relates to a method for the rapid demolition of viaducts in a dense traffic environment that integrates time and space. Background Technology
[0003] The demolition of elevated bridges in the city's core area differs significantly from the demolition of bridges in the field. These bridges span main urban roads, rail transit lines, and densely populated commercial and residential areas, allowing only limited off-peak hours for work. Traditional, fully enclosed, long-term construction methods are no longer suitable for urban operations. Construction sites are adjacent to operating subways, underground utility tunnels, and high-rise buildings, necessitating stringent requirements for vibration, noise, dust, and structural deformation control. Urban work sites are often cramped, lacking space for deploying large machinery and storing components; components must be quickly hoisted and transported after cutting. Blasting and mechanical crushing techniques are limited by safety and environmental regulations, making static cutting and hoisting the mainstream method for urban bridge demolition.
[0004] The existing static cutting and hoisting process still has significant engineering shortcomings. The sequential organization of the process lacks temporal and spatial coordination in cutting, hoisting, and transportation, leading to equipment downtime and limited construction window. The segmentation of the beam is largely determined by experience without reverse optimization based on the performance of the lifting and transportation equipment, easily resulting in unreasonable segment weights. During segmental dismantling, the last beam is left in a cantilevered state, lacking reliable anti-tipping measures, posing significant safety risks.
[0005] Traditional construction methods lack a multi-indicator collaborative management mechanism, and sensitive sections such as those under subway lines lack comprehensive protective measures. Existing publicly available research mainly focuses on single technologies such as BIM simulation and wire saw cutting, and has not yet developed a complete construction plan that covers cutting optimization, collaborative hoisting, logistics and transportation, and protection of sensitive environments. Summary of the Invention
[0006] This invention aims to solve the engineering challenges of limited demolition window for elevated bridges in urban core areas, poor process coordination, insufficient matching of component blocks, high risk of overturning of the last beam, and lack of sensitive environmental control measures. By coupling the entire process of cutting, hoisting, and transportation, it achieves efficient demolition of elevated bridges while ensuring safety and environmental protection.
[0007] To address the aforementioned deficiencies or improvement needs of existing technologies, as a first aspect of this invention, the present invention provides a method for the rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments, comprising: S1. Obtain the BIM model of the elevated bridge to be demolished, and perform reverse optimization on the superstructure of the elevated bridge to be demolished, taking the capacity of the on-site lifting equipment and the weight limit of the transportation equipment as constraints, to determine the cutting and segmentation scheme. S2. According to the cutting and segmentation scheme, first cut the transverse diaphragms, then cut the wet joints, and leave the last transverse diaphragm of the last beam uncut; drill lifting holes within a preset range at the end of the beam, and connect the double-machine lifting equipment through rigging; start the double-machine lifting equipment to make the rigging bear vertical force for pre-lifting verification, and after confirming that the beam is completely separated, cut the last transverse diaphragm of the last beam that is left uncut; S3. After the beam is cut and separated, the beam is lifted off the site by the dual-machine lifting equipment and immediately loaded onto the transportation equipment for removal from the site, realizing the parallel connection of the cutting, lifting and transfer processes; before dismantling the last beam, round logs are used to brace the side wall of the last beam and square timbers are used to padded the bottom of the last beam to form a double insurance structure against overturning. The cutting and lifting of the last beam are carried out after the rigging is under stress. S4. The substructure of the viaduct to be demolished shall be dismantled, including cutting the cap beam into sections using an inverted V-shape and hoisting it, and chiseling grooves at the upper position of the center of gravity of the piers and then laying them down as a whole before hoisting them in sections; in sensitive environmental areas, a double layer of roadbed plate shall be laid under the outriggers of the lifting equipment to spread the load.
[0008] Furthermore, in step S1, the superstructure of the elevated bridge to be demolished undergoes reverse optimization to determine a segmentation scheme, specifically including: Based on the BIM model, a spatiotemporal simulation platform was constructed. With the goal of controlling the demolition time of a single-span viaduct to 4-6 hours, the weight of the cut blocks was matched and calculated with the rated lifting capacity of the on-site lifting equipment and the weight limit of the transportation equipment. Through iterative optimization, a cutting block scheme that balances the capabilities of the three processes of cutting, hoisting and transportation was determined.
[0009] Furthermore, the iterative optimization process specifically includes: Extract the geometric boundaries and material density distribution of the single-span beam to be demolished from the BIM model, and establish a linear density distribution function along the longitudinal axis of the beam. ,in These are the position coordinates along the longitudinal axis of the beam; Set the initial cutting section position set Cut two adjacent sections and The beam between them is treated as a segmented section, and the formula is used to divide it into sections. Calculate the first The actual weight of each cut piece ; According to the The lifting point position of each segment. and Static equilibrium equations through dual-machine lifting and Calculate the load distribution for a single machine, where For the first The centroid coordinates of each segment. and The load is distributed to each of the two lifting devices individually; Pick As the first Maximum distributed load per unit of the segmented block ,Will With the rated lifting capacity Compare and put Weight limit of the transport equipment Compare and dynamically adjust the cutting cross section Location; When all the cutting blocks meet the preset conditions, it is then determined whether the total process time of the current block scheme meets the upper limit of the 4-6 hour window period. If the timeout occurs, the block merging mechanism is triggered.
[0010] Furthermore, the dynamic adjustment of the cutting cross section The process of positioning is as follows: like or This triggers the cross-sectional adaptive displacement mechanism, according to the formula. Adjust the cutting section The location, among which In order to make Reduce the displacement step size, adjust, and return to execute the above. and The calculation, until and .
[0011] Furthermore, the determination of whether the total process time of the current block-based scheme meets the upper limit of the 4-6 hour window period, and if it exceeds the timeout, triggering the block merging mechanism, specifically includes: When all the cut blocks satisfy and At that time, through the formula Calculate the total process time of the current block-based scheme. ,in , and The first The time required for cutting, hoisting, and transporting each segment; like ,in If the upper limit of the 4-6 hour window period is reached, the block merging mechanism is triggered, and the block merging mechanism is selected to meet the criteria. And after the merger Adjacent blocks and Merge them to eliminate the cutting section between them. Make the total number of blocks Reduce, and re-execute the above. , The calculation and comparison and the above The calculation, until Output the final set of cutting section positions. This is the cutting and segmentation scheme.
[0012] Furthermore, the block merging mechanism also includes the following process when no merging block meets the requirements: Extract the three-dimensional spatial contour and centroid coordinates of each segment in the current segmentation scheme, and construct the dynamic spatial envelope of each segment on the hoisting trajectory; Calculate the two adjacent cut blocks and Spatial-temporal interference boundary distance between Based on the aforementioned spatiotemporal interference boundary distance Calculate the limit flow step distance between adjacent sub-processes. ,in For cutting into blocks The cutting time For cutting into blocks The hoisting time The average slewing linear velocity of the lifting equipment; The total process time The calculation formula has been changed from a serial accumulation model to a flow overlap model, and the total process time after the change has been adjusted. Through formula The calculation yielded, where The transfer time for the last cut piece; like Then output the current block partitioning scheme and the limit flow step size. As a benchmark for construction sequence control; if This triggers the adaptive fine-tuning mechanism of the cutting section, causing the section to adjust along the longitudinal axis of the beam. The direction of increase is used to shift the position of the cutting section and recalculate. , and until The final cutting and segmentation scheme and construction sequence control benchmark are output.
[0013] Furthermore, in S2, the diaphragm is cut first, and then the wet joint is cut. Specifically, the diaphragm is cut with a wire saw, and the wet joint is cut with a circular saw. At the same time, the hoisting hole is drilled within a preset range at the end of the beam. Specifically, the hoisting hole is drilled within a range of 0.2 times the beam length at the end of the beam.
[0014] Furthermore, the rigging in S2 is a bottom-support rigging, which includes a steel wire rope, a high-strength chain, and a shackle. The rigging is used to connect the dual-machine lifting equipment, specifically by: wrapping the steel wire rope around the bottom of the beam, connecting both ends of the steel wire rope to one end of the high-strength chain through the shackle, and connecting the other end of the high-strength chain to the hook of the dual-machine lifting equipment.
[0015] Furthermore, in step S4, the cap beam is cut into sections using an inverted V-shape and then hoisted, specifically as follows: The cap beam is cut into sections by an inverted V-shape, and grooves are chiseled or steel bars are inserted into the cut slopes. The beam is then hoisted using the grooves or steel bars. Meanwhile, in sensitive environmental areas, a double-layer roadbed plate is laid under the outriggers of the lifting equipment to spread the load. Specifically, in the sensitive environmental areas, a double-layer roadbed plate is laid under the outriggers of the lifting equipment so that the pressure transmitted from the double-layer roadbed plate to the foundation is less than 20 kPa.
[0016] Furthermore, S4 also includes: real-time monitoring of stress, deformation, vibration, noise and dust indices during construction, and establishing a multi-indicator collaborative control threshold; when the monitoring data approaches the multi-indicator collaborative control threshold, dynamically adjusting construction parameters, including cutting speed, hoisting speed and lifting equipment outrigger pressure; wherein, the control standard for the deformation index is to control the deformation of the underpass subway structure within 2mm.
[0017] In summary, compared with the prior art, the above-described technical solutions conceived by this invention can achieve the following beneficial effects: 1. The present invention provides a method for the rapid, spatiotemporal demolition of elevated bridges in dense traffic environments. This method utilizes a BIM model combined with constraints from lifting and transportation equipment to perform reverse optimization of beam segmentation. Based on the determined segmentation scheme, it systematically carries out the cutting of diaphragms and wet joints, and includes a pre-lifting verification step to confirm the beam separation status. This approach changes the previous work mode that relied on experience to divide the cutting blocks, ensuring that the weight of each block matches the load-bearing capacity of the on-site equipment. It avoids the problems of overweight components that cannot be lifted after cutting or frequent hook changes caused by excessively small block sizes. This provides reasonable preconditions for the connection between cutting, lifting, and transportation processes, and is suitable for the limited off-peak construction windows in cities.
[0018] 2. The present invention provides a time- and space-intensive rapid demolition method for elevated bridges in dense traffic environments. This method employs a double-insurance structure to prevent overturning of the final beam segment, and executes a pre-lifting sling stress before completing the cutting and hoisting of the final beam segment, achieving parallel connection between the cutting, hoisting, and transportation processes. After the beam is cut and separated, a dual-crane lifting system directly loads the components onto transport equipment for timely transport, reducing the time components remain on the construction site, alleviating the construction pressure caused by limited space and lack of component storage areas in urban core areas, avoiding the overturning safety hazard caused by single-beam cantilever construction, and improving the overall operational safety of the upper beam demolition process.
[0019] 3. The present invention provides a method for the rapid and intensive demolition of elevated bridges in dense traffic environments. This method employs differentiated demolition techniques for the cap beams and piers, and uses double-layer roadbed plates to spread the load at the outrigger locations of lifting equipment in sensitive areas. Simultaneously, it conducts real-time monitoring of multiple environmental indicators and dynamically adjusts construction parameters. Specific protective measures are implemented for sensitive structures such as subway underpasses to control the impact of vibration and deformation caused by construction, compensating for the shortcomings of traditional methods in protecting sensitive sections. This ensures the operational safety of surrounding important buildings and structures during the demolition process while simultaneously completing the dismantling and hoisting of the substructure. Attached Figure Description
[0020] Figure 1 This is a flowchart illustrating a method for the rapid, spatiotemporally integrated demolition of elevated bridges in a dense traffic environment, according to an embodiment of the present invention. Figure 2 This is a schematic diagram of the T-beam being cut into sections according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the cutting and hoisting sequence according to an embodiment of the present invention; Figure 4 This is a schematic diagram of the T-beam lifting point location according to an embodiment of the present invention; Figure 5 This is a schematic diagram of the transportation and binding of prefabricated T-beams according to an embodiment of the present invention; Figure 6 This is a schematic diagram of the double-insurance anti-overturning system of "round timber diagonal bracing + square timber padding" for the last beam in an embodiment of the present invention; Figure 7 This is a schematic diagram of the segmented cutting and hoisting of the cap beam according to an embodiment of the present invention; Figure 8 This is a schematic diagram of the pier column cutting and hoisting according to an embodiment of the present invention. Detailed Implementation
[0021] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention. Furthermore, the technical features involved in the various embodiments of this invention described below can be combined with each other as long as they do not conflict with each other.
[0022] Example 1 Please refer to Figure 1 This embodiment 1 provides a method for the rapid and intensive demolition of elevated bridges in dense traffic environments, including: S1. Obtain the BIM model of the elevated bridge to be demolished, and perform reverse optimization on the superstructure of the elevated bridge to be demolished, taking the capacity of the on-site lifting equipment and the weight limit of the transportation equipment as constraints, to determine the cutting and segmentation scheme. S2. According to the cutting and segmentation scheme, first cut the transverse diaphragms, then cut the wet joints, and leave the last transverse diaphragm of the last beam uncut; drill lifting holes within a preset range at the end of the beam, and connect the double-machine lifting equipment through rigging; start the double-machine lifting equipment to make the rigging bear vertical force for pre-lifting verification, and after confirming that the beam is completely separated, cut the last transverse diaphragm of the last beam that is left uncut; S3. After the beam is cut and separated, the beam is lifted off the site by the dual-machine lifting equipment and immediately loaded onto the transportation equipment for removal from the site, realizing the parallel connection of the cutting, lifting and transfer processes; before dismantling the last beam, round logs are used to brace the side wall of the last beam and square timbers are used to padded the bottom of the last beam to form a double insurance structure against overturning. The cutting and lifting of the last beam are carried out after the rigging is under stress. S4. The substructure of the viaduct to be demolished shall be dismantled, including cutting the cap beam into sections using an inverted V-shape and hoisting it, and chiseling grooves at the upper position of the center of gravity of the piers and then laying them down as a whole before hoisting them in sections; in sensitive environmental areas, a double layer of roadbed plate shall be laid under the outriggers of the lifting equipment to spread the load.
[0023] This embodiment 1 further elaborates on the above steps.
[0024] (1) BIM reverse optimization Please refer to Figure 2After obtaining the BIM model of the elevated bridge to be demolished, the superstructure needs to be reverse-optimized based on the capacity of the on-site lifting equipment and the weight limit of the transportation equipment to determine the cutting and segmentation scheme. This process relies on the established "cutting-lifting-transfer" spatiotemporal simulation platform. This platform integrates the BIM model of the bridge superstructure, the lifting capacity database of the on-site lifting equipment, and the load specifications of the transportation vehicles. The aim is to control the demolition time of a single-span elevated bridge to 4 to 6 hours. The weight of the cutting segments is matched and calculated with the rated lifting capacity of the on-site lifting equipment and the weight limit of the transportation equipment. Through iterative optimization, the capabilities of the three processes of cutting, lifting, and transfer are balanced, thereby determining the optimal combination of cutting sequence, cutting direction, and lifting sequence.
[0025] During the iterative optimization process, the geometric boundaries and material density distribution of the single-span beam to be demolished are extracted from the BIM model, and a linear density distribution function is established along the longitudinal axis of the beam. ,in These are the position coordinates along the longitudinal axis of the beam.
[0026] Set the initial cutting section position set Cut two adjacent sections and The beam between them is treated as a segmented section, and the formula is used to divide it into sections. Calculate the first The actual weight of each cut piece .
[0027] According to the The lifting point position of each segment. and Static equilibrium equations through dual-machine lifting and Calculate the load distribution for a single machine, where For the first The centroid coordinates of each segment. and The load is distributed to each of the two lifting devices individually.
[0028] Pick The maximum single-machine distributed load of this segment and compare it with the rated lifting capacity. Compare with the rated lifting capacity. It is 70% of the rated lifting capacity of the lifting equipment. At the same time, Weight limit for transportation equipment By comparison, it can be determined whether the current block meets the actual load-bearing capacity of the field equipment.
[0029] If it appears or This situation indicates that the current cutting section position is causing the segment to be too heavy or the hoisting force to exceed the limit. At this time, the section adaptive displacement mechanism is triggered, according to the formula. Adjust the cutting section The location, among which In order to make Reduced displacement step size. This gradient-direction-based adjustment guides the cutting interface to move in a direction that reduces the peak load, avoiding overweight problems caused by excessive local beam thickness or dense reinforcement.
[0030] After adjustment, the weight and load calculations and comparisons need to be re-executed until all blocks meet the requirements. and This ensures that each component has the physical requirements for hoisting and transport.
[0031] Once all cut segments meet the preset stress and weight conditions, it is necessary to further verify whether the total process time meets the upper limit of the 4 to 6 hour window period. At this point, the formula is used. Calculate the total process time of the current block-based scheme. ,in , and The first The time spent cutting, hoisting, and transporting each segment.
[0032] like This indicates that the excessive number of blocks has caused the cumulative time for process connections to exceed the window period, necessitating the triggering of the block merging mechanism. Selecting blocks that meet the requirements... And after the merger Adjacent blocks and Merge them to eliminate the cutting section between them. To reduce the total number of blocks And re-execute the aforementioned calculations and comparisons until... The purpose of this step is to reduce unproductive waiting time by decreasing the number of cuts, thus bringing the theoretical construction period back to within the actual usable traffic closure time.
[0033] When no merged block meets the weight and stress requirements, simply reducing the number of blocks is no longer sufficient. Instead, a flow overlap model must be adopted to explore the potential for parallel processing. In this case, the 3D spatial contour and centroid coordinates of each cutting block in the current segmentation scheme are extracted, a dynamic spatial envelope of each cutting block on the hoisting trajectory is constructed, and the values of adjacent cutting blocks are calculated. and Spatial-temporal interference boundary distance between The calculation formula is as follows: ,in and Cut into blocks respectively and The coordinates of the center of gravity, and Cut into blocks respectively and The circumscribed sphere radius. This distance reflects the minimum safe distance between the front and rear sections to prevent collisions during hoisting movements, and is a key geometric parameter determining whether processes can overlap.
[0034] Based on the spatiotemporal interference boundary distance Calculate the limit flow step distance between adjacent sub-processes. : ,in, For cutting into blocks The cutting time For cutting into blocks The hoisting time This represents the average rotational linear velocity of the lifting equipment. This step distance indicates the maximum amount of time that the subsequent segment cutting operation can start before the previous segment lifting is completely completed. Its value directly depends on the coupling relationship between the equipment's movement speed and the spatial safety distance.
[0035] Subsequently, the calculation of the total process time was replaced from the serial accumulation model to the flow overlap model, and the total process time after the replacement was... Through formula The calculation yielded, where This is the time required for transporting the last cut piece. This calculation method more realistically reflects the actual time required for multiple overlapping operations, avoiding the overly conservative estimate of the project duration by the serial model.
[0036] If the calculation yields Then output the current block partitioning scheme and the limit flow step size. As a benchmark for construction sequence control; if This triggers the adaptive fine-tuning mechanism of the cutting section, causing the section to adjust along the longitudinal axis of the beam. The direction of increase is used to shift the position of the cutting section and recalculate. , and until The final cutting and segmentation scheme and construction sequence control benchmark are output. The essence of this fine-tuning is to increase the safety distance during the hoisting process by changing the geometry of the segments, thereby allowing for a more compact flow step and further compressing the overall construction period without increasing equipment investment.
[0037] The final output of the cutting and segmentation scheme and the construction sequence control benchmark not only met the hard constraints of equipment capacity and transportation weight limits, but also ensured that the overall operation time strictly fell within the prescribed traffic closure window period, providing a reliable basis for the parallel and efficient connection of subsequent cutting, hoisting and transfer processes.
[0038] (2) Refined cutting and pre-verification Please refer to Figure 3 According to the determined cutting and segmentation plan, wire sawing was used for the separation of the transverse diaphragms between precast concrete beams during the cutting stage. Wire sawing is a static cutting process that uses a hydraulic motor to drive a diamond wire at high speed to grind the concrete. It can cut the internal reinforcing steel without generating severe vibration, avoiding disturbance to adjacent retained structures or the underlying support system.
[0039] After the diaphragms are cut, a circular saw is used to longitudinally cut along the joints of the slab beams or the wet joints of the T-beams, ensuring that each precast beam is physically independent both laterally and longitudinally. The circular saw is suitable for cutting long, straight, flat joints, guaranteeing complete separation of the wet joint section. During this process, the final diaphragm between the retained last precast beam and the preceding beam is not cut. The purpose of retaining this diaphragm is to maintain lateral restraint on the last beam before hoisting, preventing it from becoming unstable and overturning after the adjacent beams are lifted.
[0040] Once the beam cutting and separation process has progressed to a point where hoisting conditions are met, hoisting holes are drilled at both ends of each precast beam within a range of no more than 0.2 times the beam length (within 1.5m). The hoisting points are located in this area because it falls within a reasonable stress range for the beam, ensuring that the internal bending moment of the beam remains controllable during hoisting and preventing beam end sagging and cracking due to the hoisting points being too close to the mid-span. The specific location of the hoisting holes must avoid the prestressed steel strands and be set in the section with denser reinforcement at the bottom of the precast beam. The restraining effect of the stirrups in the denser zone enhances the local compressive strength of the concrete at the hole opening, preventing crushing and spalling at the edge of the hole during hoisting.
[0041] After the lifting hole is formed, the bottom-supporting lifting sling is inserted into the hole and connected to the hook of the dual-machine lifting equipment, which includes a truck crane of 200t or above or a crawler crane of 350t. This bottom-supporting sling is composed of wire rope and high-strength chain combined with shackles. During installation, the wire rope is wrapped around the bottom of the beam, with both ends connected to one end of the high-strength chain via shackles. The other end of the high-strength chain is then hooked onto the hook of the lifting equipment. Using a wire rope bottom-supporting sling adapts to the geometry of the beam's bottom and provides stable lifting force, while the high-strength chain has low elongation and does not stretch under stress, which helps maintain the relative elevation of the lifting points at both ends during dual-machine lifting, reducing the twisting and swaying of the beam during lifting.
[0042] Please refer to Figure 4 After the rigging is connected, the lifting equipment is started for pre-lifting operations. Two cranes are raised slowly and synchronously, and the lifting operation is stopped once the rigging is under vertical stress. At this time, it is necessary to check whether there are any uncut concrete residues or steel reinforcements connecting the precast beam to the bridge structure, confirming that the beam has been completely separated and has no reliable connection. This pre-lifting verification effectively eliminates sudden impact loads caused by incomplete cutting, preventing the beam from becoming unstable and falling when forcibly detached from residual connections.
[0043] After confirming that the beams were completely separated, the last beam's last transverse diaphragm, which had been previously retained, was cut and separated, so that the last beam was completely detached from the main body of the bridge.
[0044] (3) Parallel operation and end-piece protection After the beams are cut and separated, two cranes are used to lift the precast beams to the ground as a whole. Once lifted, the components are immediately loaded onto flatbed trucks and transported away from the construction site, allowing the cutting, hoisting, and transportation processes to be carried out in parallel.
[0045] Please refer to Figure 5 On the flatbed truck, steel saddles are installed at the support points of each beam. Rubber pads and wooden blocks are laid on top of the saddles, and the bottom of the beam is in direct contact with the rubber pads. The steel saddles provide positioning and support for the beams. A soft material is used to transition between the rubber pads and the beams to prevent damage from rigid contact during transportation.
[0046] After the beams are loaded into place, they are secured to the flatbed truck using specialized steel wire rope lugs and rubber pads at no fewer than four points to ensure that the components do not slip due to vehicle braking or road bumps during transportation. This immediate cutting, lifting, and transport logistics method allows the total time from cutting a single beam to its removal from the construction site to within two hours. This significantly reduces the time components spend on site and the amount of space occupied, which is crucial for ensuring the overall demolition progress meets traffic restoration timelines, especially given the limited working window in a high-traffic environment.
[0047] Please refer to Figure 6 Before the last beam was hoisted, because all its adjacent diaphragms had been removed, the beam was in a single-beam cantilever state and lost the lateral restraint provided by the adjacent beams. Direct cutting and hoisting would easily cause lateral overturning. Round logs were used to brace the sidewalls of the cap beam containing the beam, and the logs were firmly packed between the logs and the inclined surface of the cap beam. The horizontal support provided by the logs resisted the potential lateral overturning moment of the beam.
[0048] Meanwhile, square timber is used to support the bottom of the transverse diaphragm of the beam. The square timber bears the vertical load generated by the beam's own weight, preventing the beam from suddenly sinking due to the loss of bottom support when the last transverse diaphragm is cut. The round timber diagonal bracing and the square timber support together form a double-insurance anti-overturning structure with support and padding. The two lines of defense are respectively aimed at the two risk modes of lateral instability and vertical fall.
[0049] After the double-safety structure is erected, the lifting equipment is activated to bring the bottom rigging under slight stress. At this point, the rigging bears part of the beam's weight but is not yet fully lifted, and the beam is still primarily supported by square and round timber braces. In this state, the final transverse diaphragm is cut and separated. Even if there are slight changes in the beam's posture during the cutting process, the rigging and double-safety structure together restrain it, preventing uncontrolled overturning that might occur if the beam is directly cut in a cantilevered state.
[0050] After the last diaphragm was cut, the lifting equipment continued to lift the beam completely off the cap beam. Then, following the aforementioned process, it was loaded onto a flatbed truck and transported away from the site, completing the dismantling of the entire span of the beam.
[0051] (4) Substructure demolition and environmental control Please refer to Figure 7 After the upper beam is removed, the cap beam is dismantled. A wire saw is used to cut the central section of the cap beam in an inverted V-shape, creating sloping sections. The cutting sequence involves first processing the central section, then hoisting and removing it, followed by cutting the cantilever and pier top sections. This step-by-step dismantling method gradually releases the cap beam's self-weight load, preventing excessive single-cut volumes from causing instantaneous overload of the lifting equipment.
[0052] When the bottom surface of the cap beam is sloping, the wire rope is prone to slippage if it is directly wrapped around it. Therefore, a groove is chiseled manually in conjunction with machinery at the wire rope binding position. The groove depth is not less than 5cm. The sling is inserted into the groove and then tied tightly. The shear resistance of the concrete on the side wall of the groove is used to prevent the sling from sliding along the sloping surface during the lifting process.
[0053] When the cross-sectional dimensions of the cap beam are large or the concrete strength is high, resulting in insufficient bearing capacity of the slot, four holes with a diameter of 63mm and a depth of 30cm are drilled in the cap beam. Q355 steel bars, each 60cm long and 60mm in diameter, are inserted into these holes, with the exposed portions serving as lifting points for connection to the slings. Q355 steel is chosen because its yield strength meets the lifting requirements for large-tonnage sections, and the 30cm drilling depth ensures sufficient anchorage length between the steel bars and the concrete. The cap beam cutting is performed using a staged unloading and multi-point synchronous method to avoid structural imbalance or cumulative vibration impact on the substructure caused by sudden release from a single point.
[0054] Please refer to Figure 8The dismantling of piers employs different techniques depending on their height and structural form. For piers taller than 6 meters, they are cut into sections no larger than 6 meters for hoisting. This size restriction is consistent with the loading limits of conventional transport vehicles and the lifting height of the hoisting equipment.
[0055] For single-column piers, a whole-piece lowering process is adopted. First, a groove with a depth of no less than 5cm is chiseled at the upper part of the pier's center of gravity. The slings are tied to the groove, and the lifting equipment is used to lift and bear the load. Then, the bottom of the pier is cut. After cutting, the lifting equipment slowly releases the hook, allowing the pier to be lowered smoothly to the ground as a whole. The lowered pier is then transported in sections. Setting the lifting point at the upper part of the center of gravity ensures that the pier remains in a controlled tilt state during the lowering process. With the lifting point above the center of gravity, the pier naturally tilts towards the lifting point after being cut at the bottom. The lowering rate can be adjusted by controlling the release speed of the hook, avoiding the impact and vibration of the pier falling freely on the surrounding environment.
[0056] In sensitive areas such as those under subway lines, a double-layered roadbed slab is laid beneath the outriggers of lifting equipment to distribute the load. The double-layered slab increases the contact area between the outriggers and the foundation, ensuring that the pressure transmitted to the foundation is less than 20 kPa. This pressure control value is determined based on the subway tunnel structure's ability to withstand additional loads, effectively reducing the additional stress on the subway structure caused by construction loads and preventing excessive deformation or cracking of the subway tunnel. The roadbed slab is used in a double-layered stacked manner instead of a single layer because the double-layered structure better adapts to uneven ground conditions. The upper roadbed slab distributes the concentrated load from the outriggers to the lower roadbed slab, which then evenly transfers the load to the foundation. This two-stage distribution results in a more uniform stress distribution on the foundation.
[0057] Throughout the entire cutting, hoisting, and transportation process, key indicators such as structural stress, deformation, vibration, noise, and dust are monitored in real time, and multi-indicator collaborative control thresholds are established. These indicators are not controlled independently but are interrelated; for example, increased cutting speed leads to a simultaneous increase in vibration and noise, while excessively fast hoisting speed may cause structural stress concentration and increased deformation.
[0058] When any monitoring indicator approaches the collaborative control threshold, a tiered early warning is triggered, and the corresponding construction parameters, including cutting speed, hoisting speed, and outrigger pressure of the lifting equipment, are dynamically adjusted according to the type of exceeding the limit. If the vibration index is close to the threshold, the cutting speed is reduced to decrease the intensity of the vibration source; if the deformation index is close to the threshold, the hoisting rate and synchronization are adjusted to avoid the accumulation of structural deformation due to excessive loading rate.
[0059] The deformation control standard for the structure passing under the subway is within 2mm. This limit comprehensively considers the normal use requirements of the subway tunnel structure and the safety clearance for train operation. Through multi-index coordinated control and dynamic parameter adjustment, vibration and noise interference can be reduced by more than 20%, and the impact of demolition work on subway operation and the lives of surrounding residents is effectively controlled.
[0060] Those skilled in the art will readily understand that the above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A method for the rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments, characterized in that: include: S1. Obtain the BIM model of the elevated bridge to be demolished, and perform reverse optimization on the superstructure of the elevated bridge to be demolished, taking the capacity of the on-site lifting equipment and the weight limit of the transportation equipment as constraints, to determine the cutting and segmentation scheme. S2. According to the cutting and segmentation scheme, first cut the transverse diaphragms, then cut the wet joints, and leave the last transverse diaphragm of the last beam uncut; drill lifting holes within a preset range at the end of the beam, and connect the double-machine lifting equipment through rigging; start the double-machine lifting equipment to make the rigging bear vertical force for pre-lifting verification, and after confirming that the beam is completely separated, cut the last transverse diaphragm of the last beam that is left uncut; S3. After the beam is cut and separated, the beam is lifted off the site by the dual-machine lifting equipment and immediately loaded onto the transportation equipment for removal from the site, realizing the parallel connection of the cutting, lifting and transfer processes; before dismantling the last beam, round logs are used to brace the side wall of the last beam and square timbers are used to padded the bottom of the last beam to form a double insurance structure against overturning. The cutting and lifting of the last beam are carried out after the rigging is under stress. S4. The lower structure of the viaduct to be demolished shall be demolished, wherein the cap beam shall be cut into sections by an inverted V-shape and hoisted, and the piers shall be slotted at the upper position of the center of gravity and then laid down as a whole before being hoisted in sections. In sensitive environmental areas, a double-layer roadbed plate is laid under the outriggers of the lifting equipment to spread the load.
2. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 1, characterized in that, In step S1, the superstructure of the elevated bridge to be demolished is reverse-optimized to determine a segmentation scheme, specifically including: Based on the BIM model, a spatiotemporal simulation platform was constructed. With the goal of controlling the demolition time of a single-span viaduct to 4-6 hours, the weight of the cut blocks was matched and calculated with the rated lifting capacity of the on-site lifting equipment and the weight limit of the transportation equipment. Through iterative optimization, a cutting block scheme that balances the capabilities of the three processes of cutting, hoisting and transportation was determined.
3. The method for rapid, spatiotemporally intensive demolition of elevated bridges in a dense traffic environment according to claim 2, characterized in that, The iterative optimization process specifically includes: Extract the geometric boundaries and material density distribution of the single-span beam to be demolished from the BIM model, and establish a linear density distribution function along the longitudinal axis of the beam. ,in These are the position coordinates along the longitudinal axis of the beam; Set the initial cutting section position set Cut two adjacent sections and The beam between them is treated as a segmented section, and the formula is used to divide it into sections. Calculate the first The actual weight of each cut piece ; According to the The lifting point position of each segment. and Static equilibrium equations through dual-machine lifting and Calculate the load distribution for a single machine, where For the first The centroid coordinates of each segment. and The load is distributed to each of the two lifting devices individually; Pick As the first Maximum distributed load per unit of the segmented block ,Will With the rated lifting capacity Compare and put Weight limit of the transport equipment Compare and dynamically adjust the cutting section Location; When all the cutting blocks meet the preset conditions, it is then determined whether the total process time of the current block scheme meets the upper limit of the 4-6 hour window period. If the timeout occurs, the block merging mechanism is triggered.
4. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 3, characterized in that, The dynamic adjustment of the cutting section The process of positioning is as follows: like or This triggers the cross-sectional adaptive displacement mechanism, according to the formula. Adjust the cutting section The location, among which In order to make Reduce the displacement step size, adjust, and return to execute the above. and The calculation, until and .
5. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 4, characterized in that, The step involves determining whether the total process time of the current block-based scheme meets the upper limit of the 4-6 hour window period. If the timeout occurs, a block merging mechanism is triggered, specifically including: When all the cut blocks satisfy and At that time, through the formula Calculate the total process time of the current block-based scheme. ,in , and The first The time required for cutting, hoisting, and transporting each segment; like ,in If the upper limit of the 4-6 hour window period is reached, the block merging mechanism is triggered, and the block merging mechanism is selected to meet the criteria. And after the merger Adjacent blocks and Merge them to eliminate the cutting section between them. Make the total number of blocks Reduce, and re-execute the above. , The calculation and comparison and the above The calculation, until Output the final set of cutting section positions. This is the cutting and segmentation scheme.
6. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 5, characterized in that, The block merging mechanism also includes the following process when no merging block meets the requirements: Extract the three-dimensional spatial contour and centroid coordinates of each segment in the current segmentation scheme, and construct the dynamic spatial envelope of each segment on the hoisting trajectory; Calculate the two adjacent cut blocks and Spatial-temporal interference boundary distance between Based on the aforementioned spatiotemporal interference boundary distance Calculate the limit flow step distance between adjacent sub-processes. ,in For cutting into blocks The cutting time For cutting into blocks The hoisting time The average slewing linear velocity of the lifting equipment; The total process time The calculation formula has been changed from a serial accumulation model to a flow overlap model, and the total process time after the change has been adjusted. Through formula The calculation yielded, where The transfer time for the last cut piece; like Then output the current block partitioning scheme and the limit flow step size. As a benchmark for construction sequence control; if This triggers the adaptive fine-tuning mechanism of the cutting section, causing the section to adjust along the longitudinal axis of the beam. The direction of increase is used to translate the cutting section position and recalculate. , and until The final cutting and segmentation scheme and construction sequence control benchmark are output.
7. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 1, characterized in that, In step S2, the diaphragm is cut first, and then the wet joint is cut. Specifically, the diaphragm is cut with a wire saw, and the wet joint is cut with a circular saw. At the same time, the hoisting hole is drilled within a preset range at the end of the beam. Specifically, the hoisting hole is drilled within a range of 0.2 times the beam length at the end of the beam.
8. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 1, characterized in that, The rigging in S2 is a bottom-support rigging, which includes a wire rope, a high-strength chain, and a shackle. The rigging is used to connect the dual-machine lifting equipment. Specifically, the wire rope is wrapped around the bottom of the beam, and the two ends of the wire rope are connected to one end of the high-strength chain through the shackle. The other end of the high-strength chain is connected to the hook of the dual-machine lifting equipment.
9. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 1, characterized in that, In step S4, the cap beam is cut into sections using an inverted V-shape and then hoisted, specifically as follows: The cap beam is cut into sections by an inverted V-shape. A groove is chiseled or a steel bar is inserted into the cut slope. The beam is then hoisted using the groove or the steel bar. Meanwhile, in sensitive environmental areas, a double-layer roadbed plate is laid under the outriggers of the lifting equipment to spread the load. Specifically, in the sensitive environmental areas, a double-layer roadbed plate is laid under the outriggers of the lifting equipment so that the pressure transmitted from the double-layer roadbed plate to the foundation is less than 20 kPa.
10. The method for rapid, spatiotemporally intensive demolition of elevated bridges in dense traffic environments according to claim 1, characterized in that, The S4 further includes: real-time monitoring of stress, deformation, vibration, noise and dust indices during construction, and establishing a multi-indicator collaborative control threshold; when the monitoring data approaches the multi-indicator collaborative control threshold, dynamically adjusting the construction parameters, including cutting speed, hoisting speed and lifting equipment outrigger pressure; wherein, the control standard for the deformation index is to control the deformation of the underpass subway structure within 2mm.