Adaptive bored pile construction method under complex and variable geology
By employing an adaptive relay-type composite drilling process, layered modified mud wall protection, and pressure-bearing continuous underwater concrete grouting, the construction challenges of large-diameter bored piles under complex geological conditions in the Yangtze River Basin have been solved. This has achieved efficient and stable drilling and pile formation, adaptable to various construction scenarios, and meets the quality and safety requirements of large-span bridge foundations.
Patent Information
- Application Number
- CN202611113047.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-25
- Publication Date
- 2026-11-20
AI Technical Summary
The existing construction technology for large-diameter bored piles cannot adapt to the complex geological and hydrological conditions of the Yangtze River Basin. It suffers from problems such as low drilling efficiency, poor drilling accuracy, insufficient hole wall stability, uncontrollable pile quality, poor environmental compliance, and limited adaptability to different scenarios, and cannot meet the construction requirements of the main tower foundation of long-span bridges.
An adaptive relay-type composite drilling process is adopted, combining rotary drilling rigs and gyratory drilling rigs in a relay-type composite drilling manner, with the real-time geological monitoring system during drilling to dynamically match the drilling mode and parameters; layered modified mud is used for wall protection, and the mud performance indicators are adjusted in real time; a long-line matching method for steel cages and a pressure-bearing continuous underwater concrete pouring process are adopted, combined with intelligent management and control of the entire process.
It achieves efficient drilling and precise pile formation under complex geological conditions in the Yangtze River Basin, ensuring borehole stability and pile quality, reducing construction risks and costs, adapting to construction needs in multiple scenarios, and meeting the 100-year design life requirement.
Smart Images

Figure CN123133348A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of bored pile technology, and in particular to an adaptive bored pile construction method under complex and variable geological conditions. Background Technology
[0002] With the rapid development of large-span bridge projects across rivers and seas in my country, the Yangtze River trunk line, as a core inland waterway in the national comprehensive three-dimensional transportation network, generally adopts large-diameter, ultra-long, and deep-embedded rock bored pile structures for the main tower foundations of newly built high-speed and railway bridges across the river. The core construction area, represented by the Wuhu section of the middle and lower reaches of the Yangtze River, exhibits a complex geological condition characterized by "thick overburden + alternating soft and hard strata + fault fracture zones + high-strength moderately weathered hard rock." The hydrological environment is directly affected by the irregular semi-diurnal shallow sea tides of the Yangtze River, and the groundwater level is closely connected to the hydraulic system of the Yangtze River, exhibiting large fluctuations. During construction, quality and safety accidents such as borehole collapse, grout leakage, borehole deviation, stuck drill bits, and broken piles are highly likely to occur, placing extremely high demands on the accuracy of pile foundation drilling, borehole wall stability, pile quality, and risk management throughout the entire process.
[0003] Currently, the industry commonly uses traditional methods for this type of pile foundation construction, such as single rotary drilling rig drilling, single gyratory drilling rig drilling combined with conventional bentonite mud wall protection, and underwater tremie pipe grouting. However, when applied to the complex geological and hydrological conditions of the Yangtze River Basin, these methods have the following significant technical drawbacks: 1. Single rotary drilling rigs have high drilling efficiency in silty clay and sand layers, but when drilling in ultra-deep moderately weathered hard rock, they suffer from insufficient drilling pressure, severe drill bit wear, and a sharp drop in drilling efficiency, and are prone to borehole deviation and stuck drill accidents. Single rotary drilling rigs have good stability in hard rock sections, but their drilling efficiency in overburden sections is extremely low, leading to a significant extension of the overall project duration. Existing staged borehole enlargement technology relies heavily on pre-set parameters based on construction experience and is not combined with real-time geological monitoring technology while drilling. It cannot adjust the drilling mode in real time for the complex strata with varying layers in the Yangtze River Basin. When encountering soft-hard interfaces or fault fracture zones, borehole collapse and deviation are prone to occur, resulting in high costs for correction and rework, and serious project delays.
[0004] 2. Existing processes mostly use conventional bentonite slurry with fixed proportions, which cannot dynamically adjust the slurry performance indicators to meet the different borehole protection requirements of various strata such as silty clay, deep sand layers, fault fracture zones, and hard rock sections. This leads to borehole wall collapse in deep sand layers and large-scale slurry leakage in fault fracture zones and densely jointed zones, compromising borehole stability. Furthermore, the lack of real-time closed-loop control of slurry levels due to the fluctuations in the Yangtze River's tidal water level makes it impossible to maintain stable hydrostatic pressure within the borehole, further exacerbating the risks of borehole collapse and slurry leakage. In addition, existing slurry circulation systems are mostly open-loop, making them prone to slurry leakage that pollutes the Yangtze River, resulting in large volumes of waste slurry discharge that do not comply with the ecological and environmental protection regulations for the protection of the Yangtze River.
[0005] 3. For ultra-long diameter steel cages, existing hoisting processes are prone to steel cage deformation and poor main reinforcement connection accuracy. During the pouring process, there is a lack of effective rigid fixing measures, resulting in a high risk of steel cage floating. During underwater concrete pouring, existing processes rely heavily on manual experience to control the initial pouring volume, tremie pipe burial depth, and pouring rate. In the context of the deep-water and high-pressure environment of the Yangtze River, the initial pouring success rate is low, and quality defects such as pipe blockage, pile breakage, and excessive sediment at the pile bottom are prone to occur. This leads to poor pile integrity and substandard single pile bearing capacity, which cannot meet the 100-year design life requirement of the main tower foundation of large-span bridges.
[0006] 4. Existing technologies are mostly only suitable for land construction or a single water construction scenario, and cannot simultaneously address the two core scenarios common to the main tower foundations of the Yangtze River Bridge: land construction in tidal flat areas and construction on water platforms in waterways. In response to special working conditions such as floods, tidal fluctuations, and navigation control during the Yangtze River flood season, there is a lack of supporting dynamic management and emergency response measures. As a result, the safety risks during construction are high, the construction period is uncontrollable, and it cannot meet the standardized and refined management requirements for the construction of bridges on the Yangtze River main line.
[0007] In summary, existing large-diameter bored pile construction techniques cannot fully meet the construction needs of ultra-long rock-socketed piles under the complex geological and hydrological conditions of the Yangtze River Basin. They suffer from numerous technical pain points, such as low drilling efficiency, poor drilling accuracy, insufficient borehole wall stability, uncontrollable pile quality, poor environmental compliance, and limited adaptability to various scenarios. There is an urgent need to develop an adaptive construction technique that combines high efficiency, stability, safety, environmental friendliness, and adaptability to multiple scenarios. Summary of the Invention
[0008] In order to overcome the shortcomings of the existing technology, one of the objectives of this invention is to provide an adaptive drilling and grouting pile construction method under complex and variable geological conditions.
[0009] One of the objectives of this invention is achieved through the following technical solution: An adaptive relay construction method for large-diameter, ultra-long bored piles in deep waters of the Yangtze River includes the following steps: pre-construction preparation, borehole drilling, mud wall protection, borehole cleaning, reinforcement cage installation, underwater concrete pouring, and pile testing. Specifically, the method includes the following steps: S1 Construction Pre-construction Survey and Preparation: Advanced drilling combined with detailed geological exploration was used to complete the detailed survey of pile locations, to determine the stratigraphic distribution, fault fracture zones, densely jointed zones, groundwater and Yangtze River tidal hydrological parameters within the pile location range of the Yangtze River tidal flat area and the water operation area, and to draw pile-by-pile geological profile maps; site hardening was completed for the north bank tidal flat area, and the construction of the water drilling platform was completed for the south bank Yangtze River water area, and the steel casing of the corresponding pile locations was installed in sections and precisely positioned simultaneously; the real-time geological monitoring system and intelligent mud preparation equipment for the rotary drilling rig and the gyratory drilling rig were debugged and calibrated, the construction measurement control network was set up and the three-level technical briefing was completed; S2 Adaptive Relay Composite Hole Formation Construction: After the accurate layout of the pile position and the positioning and fixing of the drilling rig are completed, a rotary drilling + gyratory drilling relay composite drilling process is adopted for construction. During the drilling process, the geological sensors built into the hole collect data on the hardness of the formation, porosity, groundwater pressure, and mud level in real time. Based on the collected real-time geological data, the three stages of normal drilling of the rotary drilling rig, multi-stage hole enlargement of the rotary drilling rig, and relay drilling into the rock by the gyratory drilling rig are executed in sequence. The drilling mode and corresponding drilling parameters of each stage are intelligently matched. During the drilling process, the verticality of the borehole is monitored in real time and the deviation of the borehole is corrected. After the borehole reaches the designed rock embedment elevation, the hole quality is inspected and the unqualified sections are re-drilled and repaired. The mud skin cleaning operation of the inner wall of the steel casing is completed simultaneously. S3 Layered Dynamic Modified Mud Wall Protection and Circulation Cleaning: High-quality PHP bentonite modified mud with corresponding proportions is pre-formulated to address the complex geological characteristics of the Yangtze River basin. During drilling, the modified mud is dynamically matched to the appropriate ratio based on real-time geological data for wall protection. The mud level and leakage are monitored simultaneously, and the mud supply, proportion, and circulation parameters are dynamically adjusted to construct a closed-loop mud circulation and purification system. After the borehole quality is qualified, the initial cleaning is completed using an air-lift reverse circulation process. A secondary cleaning operation is completed after the reinforcement cage and guide pipe are installed. S4 Large Diameter Extra-Long Rebar Cage Precision Installation and Positioning: The rebar cage is manufactured in sections on a standardized jig using a long-line matching method. The main reinforcement bars are connected using Class I mechanical sleeves, and the sonic logging pipe and rebar cage are fixed and installed simultaneously. The rebar cage is lowered smoothly using a four-point hoisting method with a special steel hanger. A special docking platform is set at the borehole opening to complete the precise docking of the rebar cage sections. After being lowered into place, a continuous lifting bar is used to rigidly fix the rebar cage to the steel casing / drilling platform, completing the center positioning and anti-buoyancy limit of the rebar cage. S5 Pressure-bearing Continuous Underwater Concrete Pouring Construction: After completing the lowering and installation of the sealed tremie pipe and the water tightness test, C35 underwater concrete construction is carried out using a continuous pouring process; before pouring, the volume of the first batch of concrete is accurately calculated based on the pile diameter, pile length and Yangtze River water level parameters to ensure that the initial burial depth of the tremie pipe is ≥1.0m after the first pour; during the pouring process, the burial depth of the tremie pipe, the concrete surface elevation and the pouring pressure in the hole are monitored in real time, and the concrete pouring rate and pouring pressure are dynamically adjusted. The burial depth of the tremie pipe is controlled within the range of 2 to 6m throughout the process. After pouring to the design elevation of the pile top, the over-pouring is ≥1.0m. The entire pouring process is continuous and uninterrupted. S6 pile quality control and special working condition adaptation construction: After the pile concrete reaches the design strength, the integrity of the pile body is tested along the entire length of the pile using ultrasonic transmission method; special adaptation construction measures are implemented for construction conditions during the flood season, rainy season, high temperature, winter and night in the Yangtze River Basin, and the safety control of navigation and ecological and environmental protection of water operations in the Yangtze River Basin are implemented simultaneously.
[0010] As a further improvement to the above technical solution: In S1, the site of the north bank tidal flat area is hardened with 30cm thick 4% lime-soil + 30cm thick double-layer steel mesh concrete; the inner diameter of the steel casing is larger than the designed pile diameter, where the Φ2.8m pile diameter corresponds to a steel casing inner diameter of 3.2m and a wall thickness of 24mm, and the Φ2.2m pile diameter corresponds to a steel casing inner diameter of 2.5m; the center deviation of the steel casing is ≤5cm and the inclination is ≤1 / 150. The top of the casing in the tidal flat area is 30cm higher than the site elevation, and the top of the casing in the water operation area is 50cm lower than the platform elevation; the perimeter of the casing is backfilled and compacted with clay in layers, and the steel casing in the water operation area is driven into a stable stratum in sections using an APE600 hydraulic vibratory hammer.
[0011] In S2, the specific execution rules for the three stages of adaptive relay composite hole forming are as follows: The first stage is the normal drilling section of the rotary drilling rig: the XR580HD rotary drilling rig is used for drilling in the soil layers inside and outside the casing. For silty clay layers, medium-low speed and light pressure drilling is used, with the drilling speed controlled at 4-8 m / h; for silty sand and fine sand layers, depressurized low-speed drilling is used, with the drilling pressure controlled below 80% of the drill bit weight and the drilling speed controlled at 2-4 m / h; within 1m above and below the bottom of the casing, the lowest speed and light pressure are used to slowly pass through. The second stage is the multi-stage reaming section of the rotary drilling rig: when the drilling pressure reaches 80% of the rated value of the rotary drilling rig and before entering the moderately weathered bearing layer, the multi-stage reaming process is started. The "small diameter guide, graded reaming" mode is adopted, and the reaming is carried out in stages by centering drills / tube drills of Φ1.5m, Φ2.0m, Φ2.5m and Φ2.8m in sequence. The corresponding specification slag removal bucket is used for cleaning. Each stage of reaming adopts depressurization drilling, and the drilling pressure is controlled at 50% to 70% of the rated value and the rotation speed is 4 to 8 rpm. The third stage is the relay drilling section of the rotary drilling rig: When the drilling depth reaches the top interface of the moderately weathered sandstone or the Φ1.5m small-diameter drill pressure reaches 80% of the rated value, switch to the KTY4000 rotary drilling rig for full-face relay drilling. For moderately weathered sandstone, high drill pressure and slow speed drilling are adopted, with the drill pressure controlled at 70% to 90% of the rated value and the speed at 3 to 10 rpm. Air lift reverse circulation is used for slag removal. When drilling reaches 0.5 to 1.0m above the design elevation, adjust the mud index to the final hole standard, and after the final hole is reached, lift the drill and clean the hole.
[0012] In S2, during the drilling process, every 10-20m or when entering a new stratum, an ultrasonic borehole detector is used to check the verticality of the borehole, and the overall verticality deviation is controlled to be ≤1 / 150. If borehole deviation is detected, drilling is immediately stopped, and rubble is backfilled to more than 0.5m above the deviated section. Low-stroke, low-speed drilling is then used to correct the deviation. After the borehole is completed, an ultrasonic borehole detector is used to check the hole depth, hole diameter, verticality, and hole wall integrity, wherein the hole depth is not less than the design value, and the hole diameter is not less than the design pile diameter.
[0013] In S3, the dynamic matching rule between the proportion and performance indicators of the layered modified mud is as follows: For silty clay and soft soil layers, use basic bentonite slurry with a density controlled at 1.05–1.15 g / cm³, viscosity at 18–22 s, and sand content ≤4%. For easily collapsible strata such as silt, fine sand, and medium-coarse sand, a bentonite + polyacrylamide thickening composite mud is used, with a density controlled at 1.1–1.2 g / cm³, a viscosity of 22–28 s, and a sand content ≤4%. For strata prone to grout leakage, such as gravel, fault fracture zones, and densely jointed zones, a high-viscosity composite mud consisting of bentonite, a plugging agent, and cellulose is used, with a density controlled at 1.15–1.25 g / cm³ and a viscosity ≥25 s. During the hole cleaning stage, the mud density should be controlled at 1.03–1.10 g / cm³, viscosity at 17–20 s, sand content at <2%, and colloid content at >98%. During drilling, ensure that the mud level inside the casing is always 1.5 to 2.0 meters higher than the external Yangtze River water level / groundwater level. If leakage occurs, immediately replenish the mud and add plugging material. The mud is purified by a mud separator and then recycled. Waste drill cuttings and mud are disposed of in accordance with regulations after sedimentation and drying. Direct discharge into the Yangtze River is strictly prohibited.
[0014] In S3, the initial hole cleaning is completed after the hole is closed by using a rotary drilling rig air lift reverse circulation system to continuously suck up slag for 5 to 15 minutes; the secondary hole cleaning is carried out after the reinforcement cage and guide pipe are installed by using an air compressor air lift reverse circulation process. After hole cleaning, the thickness of sediment at the bottom of the hole is ≤50mm. Hole cleaning is strictly prohibited by increasing the drilling depth.
[0015] In S4, the length of the rebar cage sections matches the standard length of the rebar, with a single section length ≤ 12m, and the length of the bottom section of the rebar cage matches the final hole elevation. The number of rebar joints in the same cross-section does not exceed 50% of the total number of rebars, and the joints are staggered by ≥ 35d. The rebar cage is hoisted using a double-hook rotating hoisting process to avoid hoisting deformation. When the rebar cage is connected, the reference rebar marking method is used to control the connection accuracy, and the installation elevation error is controlled within ±50mm. Four concrete protective layer pads are arranged circumferentially every 2m along the pile body of the rebar cage, and four sonic logging pipes are symmetrically arranged along the inner side of the rebar cage. They are connected by sleeve welding, and the entire process is sealed to prevent grout leakage. After the rebar cage is lowered, the pipe is filled with clean water and the pipe opening is sealed.
[0016] In S5, the guide pipe is made of seamless steel pipe with an inner diameter ≥300mm, and the quick threaded joint is equipped with double sealing rings. Before use, water tightness pressure and joint tensile tests are completed. After the guide pipe is installed, the bottom is 30-50cm away from the bottom of the hole. The volume of the first batch of concrete is reserved according to 1.1 times the hole expansion coefficient to ensure that the burial depth of the guide pipe is ≥1.0m after the first pour. During the pouring process, when the concrete surface rises to 2-3m above the bottom of the reinforcing cage, the guide pipe is raised to reduce the burial depth to 2m to reduce the lifting force of the concrete and prevent the reinforcing cage from floating. The entire pouring process shall not exceed the initial setting time of the first batch of concrete, and the over-pour height of the concrete at the top of the pile shall be ≥1.0m to ensure that the strength of the concrete at the top of the pile meets the design requirements after the laitance is removed.
[0017] In S6, pile integrity testing is divided into four categories: I, II, III, and IV. The integrity of each pile must meet the standard of Class I piles and be no lower than that of Class II piles. For construction during the Yangtze River flood season, a real-time hydrological and meteorological linkage mechanism is established, the platform and casing reinforcement is completed in advance, and an emergency evacuation plan for personnel and equipment is formulated. For construction in winter, special insulation measures are taken for mud preparation, concrete mixing, transportation, and pouring. For water operations, a navigation notice is issued to the maritime authorities, warning buoys and warning vessels are set up, and emergency measures for ship collision prevention and personnel falling into the water are implemented.
[0018] In S2, adjacent pile foundations shall not be drilled or poured with concrete at the same time. Drilling of adjacent piles can only be carried out after the concrete strength of adjacent piles reaches more than 75% of the design strength, so as to avoid accidents such as cross-hole and hole collapse.
[0019] Compared with the prior art, the beneficial effects of the present invention are as follows: 1. This invention adopts an adaptive relay composite drilling process of "high-efficiency drilling of overburden + staged hole enlargement for hard rock transition + rotary drilling relay rock embedding", combined with a real-time geological monitoring system while drilling, to realize real-time acquisition of formation parameters and automatic matching of drilling mode and process parameters, perfectly adapting to the drilling needs of overburden-hard rock composite formations in the Yangtze River Basin.
[0020] 2. This invention employs a layered dynamic modified mud wall protection process. Addressing the wall protection risks of different strata in the Yangtze River basin, it precisely matches differentiated mud ratios and performance indicators, coupled with real-time closed-loop mud level control, ensuring that the mud level inside the casing is always 1.5~2.0m higher than the groundwater level / Yangtze River water level, forming a stable hydrostatic pressure inside the borehole. For the high risk of slurry leakage in fault fracture zones and densely jointed zones, high-viscosity plugging composite mud can achieve rapid sealing, effectively solving the industry-wide problems of borehole collapse and slurry leakage in complex strata. The borehole wall remains intact and without collapse throughout the entire construction process.
[0021] 3. This invention effectively solves the problems of deformation during hoisting of ultra-long steel cages, poor docking accuracy, and floating during the pouring process by using a long-line matching method for segmented fabrication of steel cages, double-hook flipping for precise hoisting, and rigid fixing at the orifice. It also adopts a pressure-bearing continuous underwater concrete pouring process to accurately calculate the initial pouring volume and dynamically control the burial depth of the guide pipe and the concrete pouring rate throughout the process, effectively avoiding quality defects such as pipe blockage, pile breakage, and excessive sediment at the pile bottom.
[0022] 4. This technology can be adapted to both land construction in the tidal flats of the Yangtze River Basin and water platform construction in the waterway area. It is equipped with dynamic control and emergency response measures for the whole process to address special working conditions such as the fluctuation of the Yangtze River tide level, floods during the flood season, and navigation control, thus solving the problem of the single adaptability of traditional technology scenarios. Through intelligent control of the whole process, including geological monitoring while drilling, real-time borehole detection, and dynamic monitoring of injection pressure, construction risks can be predicted in advance and dealt with in real time, avoiding rework afterward, greatly improving the controllability of the construction period, and ensuring that there are no major quality and safety accidents throughout the construction process.
[0023] 5. The core processes, equipment configurations, and parameter standards of this invention can all be standardized and replicated. It is applicable to the construction of large-diameter, ultra-long, rock-socketed bored piles under various complex geological and hydrological conditions such as the Yangtze River main line, inland rivers, and coastal areas, which greatly reduces the cost of construction rework, equipment wear and tear, and construction delay.
[0024] The above description is merely an overview of the technical solution of the present invention. In order to better understand the technical means of the present invention and to implement it in accordance with the contents of the specification, and to make the above and other objects, features and advantages of the present invention more apparent and understandable, preferred embodiments are described in detail below with reference to the accompanying drawings. Attached Figure Description
[0025] Figure 1 This is a framework diagram of the construction method in this embodiment. Detailed Implementation
[0026] The present invention will now be further described in conjunction with the accompanying drawings and specific embodiments. It should be noted that, without conflict, the various embodiments or technical features described below can be arbitrarily combined to form new embodiments.
[0027] It should be noted that when a component is described as "fixed to" another component, it can be directly on the other component or may have a component in between. When a component is described as "connected to" another component, it can be directly connected to the other component or may have a component in between. When a component is described as "set on" another component, it can be directly set on the other component or may have a component in between. The terms "vertical," "horizontal," "left," "right," and similar expressions used in this document are for illustrative purposes only.
[0028] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains. The terminology used herein in the description of the invention is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0029] Example 1: Construction of large-diameter, ultra-long rock-socketed piles in the Yangtze River tidal flat area (left pile foundation of main pier No. 3 of the North Channel Bridge, core example). 1. Project Overview and Geological and Hydrological Conditions This embodiment applies to the left-side pile foundation project of Pier 3, North Main Tower, Section 2 of the S24 Hangzhou-Hefei Expressway Wuhu Taishan Road Yangtze River Bridge and Connecting Line Project. The pile is designed as a Class I highway load-bearing rock-socketed pile, with a design strength grade of C35 underwater concrete, a design pile diameter of 2.8m, a design effective pile length of 112m, a drilling depth of 121.1m, and the bearing stratum at the pile tip is moderately weathered sandstone. The pile tip is embedded in the moderately weathered sandstone to a depth of not less than twice the pile diameter (5.6m). The total weight of the single pile reinforcement cage is 50.71t, with main reinforcement using Φ32mm HRB400E steel bars, and sonic logging pipes using Φ60×3.5mm Q255C seamless steel pipes. The design volume of single pile concrete is 716m³.
[0030] This pile location is situated in the tidal flat area on the north bank of the northern branch of the Yangtze River, with a ground elevation of 6.45~9.13m. The geological stratification from top to bottom is as follows, covering all complex geological scenarios to which this invention is applicable: 1. Layer ②11: Silty clay, 3.6m thick, in a plastic state, with a standard value of 25kPa for ultimate lateral friction resistance; 2. Layer ②41-②43: Silt layer, cumulative layer thickness 37.75m, slightly dense to dense state, standard value of ultimate side friction resistance 30~50kPa, prone to hole collapse and grout leakage; 3. Layers ②51-②54: Fine sand layer, with a cumulative thickness of 20.69m, in a medium-dense to dense state, with a standard value of 30~60kPa for ultimate side friction resistance, which is prone to borehole wall collapse; 4. Layers ②62-②82: Medium sand, coarse sand, gravelly sand, and rounded gravel layers, with a cumulative layer thickness of 12.58m. They are in a dense state, with a standard value of 55~150kPa for ultimate side friction resistance. Drilling resistance is high, and hole deviation is likely to occur. 5. Layers ⑥11-⑥13: Muddy sandstone layer, with a cumulative thickness of 24.12m, strongly weathered to moderately weathered, with a standard value of 70~140kPa for ultimate side friction resistance; 6. Layers ⑥22-⑥23: Sandstone layer, moderately weathered, 25.72m thick, with a maximum uniaxial compressive strength of 1200kPa, serving as the design bearing layer; 7. Layers ⑧1-⑧21: Fault gouge, tectonic breccia, layer thickness 3.5m, development depth 71.0-82.4m, rock mass is broken, prone to grout leakage and hole collapse; 8. Layer ⑨1: Densely developed joint zone, 9.57m thick, with highly developed joints and fissures, prone to pore wall instability.
[0031] Hydrological conditions of the site: The Yangtze River tide is an irregular semi-diurnal shallow sea tide. During the construction period, the highest tide level is +11.05m and the lowest tide level is 0.29m. The groundwater is closely connected with the Yangtze River water body. During the detailed exploration, the water level depth is 0.50~2.00m. The construction process is significantly affected by the fluctuation of the Yangtze River water level.
[0032] 2. Configuration of core construction equipment and monitoring system 1. Drilling equipment: 2 XR580HD rotary drilling rigs and 4 KTY4000 rotary drilling rigs, equipped with interchangeable rotary drilling buckets, tubular drills, and roller cone rock-socketing drill bits, suitable for relay drilling in different formations; 2. Steel casing construction equipment: QUY150t crawler crane, APE600 hydraulic vibratory hammer, and matching steel casing guide frame; 3. Real-time geological monitoring system: The drill pipe is equipped with an integrated geological sensor (formation hardness sensor, porosity monitoring probe, groundwater pressure sensor, mud level monitor), and a ground intelligent control terminal. The data acquisition frequency is 1 time / 10cm drilling depth. It can collect formation data in real time and automatically match the drilling mode and mud ratio. 4. Mud System: ZX-250 mud separator, intelligent mud preparation equipment, 25m×40m×2.5m seepage-proof mud tank, and matching mud three-piece testing equipment; 5. Hole cleaning and pouring equipment: SF160 air compressor, Φ326mm spiral sealed steel pipe, 15m³ large hopper + 1m³ small hopper, concrete pouring control system with pressure sensor; 6. Lifting and rebar processing equipment: QUY150t crawler crane, GRL3000A rebar rolling machine, CNC rebar sawing and threading machine; Testing equipment: Nikon DTM-352C total station, DSZ2 level, TS-K100 series ultrasonic borehole tester, torque tester, ultrasonic pile foundation integrity tester.
[0033] 3. Specific construction steps and process parameters S1 Pre-construction survey and preparation 1. Refined geological survey: Advanced horizontal drilling is adopted, and an advanced borehole is set up along the center of the pile location. The borehole depth exceeds the designed pile bottom elevation by 3m. With the help of in-hole camera imaging, the location and thickness of fault fracture zone and dense joint zone are accurately determined, as well as the boundaries of each soil layer, the Yangtze River water level and groundwater pressure. A pile-by-pile geological profile map is drawn, and the depth and treatment priority of each risk point are marked. 2. Site Hardening and Pretreatment: The area of 42m×103.5m around the pile location will be hardened using a 30cm thick layer of 4% lime-soil + 30cm thick double-layer D8 steel mesh concrete. A 0.3m×0.3m mud ditch will be reserved between the piles. A 0.5m×0.4m intercepting drainage ditch will be set up around the platform to flow into the sedimentation tank and then into the mud tank. Steel sheet piles will be used for the riverside enclosure to prevent the site from becoming unstable due to the erosion of the Yangtze River. 3. Steel casing installation: Q355C steel casings with an inner diameter of 3.2m and a wall thickness of 24mm were used. The length of a single section was 14.2m + 9.1m, with a total length of 23.3m and a weight of 43.92t per casing. A QUY150t crawler crane and an APE600 hydraulic vibratory hammer were used for segmented installation. A steel guide frame was used for guidance during the installation process, and the verticality of the casing was monitored throughout. The final casing center deviation was 3cm, and the inclination was 1 / 200, which meets the design requirement of ≤1 / 150. The top of the casing was 30cm above the site elevation. The perimeter of the casing was backfilled and compacted in layers with high-quality clay. Each layer of backfill was ≤30cm thick, and the compaction coefficient was ≥0.95. 4. Equipment Commissioning and Technical Preparation: Complete the online commissioning of rotary drilling rig, gyratory drilling rig, intelligent mud equipment, and monitoring system; calibrate all sensors and pressure gauges; and calibrate the matching logic of drilling parameters, mud ratio, and geological data. Complete the review of construction drawings, verification of pile location coordinates, and verification of C35 underwater concrete mix design. Conduct three-level technical briefings and pre-job training. Establish the construction survey control network, complete the surveying and protection of traverse points and leveling points, use a total station for pile location layout, and set up cross-shaped protective piles with a layout error ≤5mm.
[0034] S2 Adaptive Relay Composite Hole Formation Construction 1. Drilling rig positioning and initial calibration: The XR580HD rotary drilling rig is positioned and calibrated using a total station and electronic inclinometer to ensure that the center of the drill bit, the center of the casing, and the center of the pile position are aligned. The drilling rig base is leveled and fixed, and the initial verticality deviation of the drill rod is ≤0.3%. The drilling rig position is locked to prevent displacement during drilling. 2. Three-stage adaptive relay drilling construction: Phase 1: Normal drilling section of rotary drilling rig (0~70m depth, inside casing + soil layer section) The intelligent control system identifies the soil as silty clay, silt, and fine sand layers and automatically adopts rotary drilling mode. When drilling inside the casing, the drill bit applies pressure with its own weight, operates at a low speed of 5-8 rpm, and controls the drilling speed at 4-6 m / h. Within 1 m above and below the bottom of the casing, the drill bit passes through slowly with the lowest speed and light pressure to avoid the hole from collapsing. In silty clay layers, use light pressure (30%~50% of drilling pressure), medium-low speed (8~12 rpm), and a drilling speed of 6~8 m / h to maintain mud viscosity and prevent drill bit clogging. For silty and fine sand layers, depressurized drilling (drilling pressure less than 80% of the drill bit weight), low speed of 6~10 rpm, and drilling speed controlled at 2~4 m / h are adopted to simultaneously increase the mud viscosity and density and reduce disturbance to the borehole wall. For medium sand, coarse sand, and gravel layers, appropriately increase the drilling pressure (40%~60% of the rated value), maintain a medium-low speed of 8~12 rpm, and a drilling speed ≤2m / h. Use high-viscosity mud to ensure effective suspension and discharge of drill cuttings. Every 10 meters of drilling, the verticality of the borehole was checked once using an ultrasonic borehole detector, and there were no deviations or collapses throughout the entire process.
[0035] Phase Two: Rotary drilling multi-stage reaming section (70~100m depth, hard rock transition section) When drilling reached a depth of 70m, the geological sensor indicated a sudden increase in formation hardness, and the drilling pressure reached 80% of the rotary drilling rig's rated value. The system automatically initiated a multi-stage reaming process, following the principle of "small-diameter guidance and staged reaming," and sequentially changed the drilling tools to complete the staged reaming. Step 1: Use a Φ1.5m tubular drill and a slag removal bucket for relay drilling. Control the drilling pressure at 50%~70% of the rated value and the rotation speed at 4~8 rpm. Pull up the drill and remove slag every 50~60cm of drilling. Step 2: Replace the Φ2.0m centering drill to enlarge the hole and clean the slag with a slag hopper, and repeat the hole enlargement and slag removal process; Step 3: Replace the Φ2.5m centering drill to enlarge the hole and clean the slag with a slag hopper, and repeat the hole enlargement and slag removal process; Step 4: Replace with a Φ2.8m core drill for reaming and use a slag hopper for cleaning to complete the full-section reaming; During the hole enlargement process, the verticality of the borehole was checked after each stage of enlargement. The verticality deviation at a depth of 90m was 1 / 180, which meets the design requirement of ≤1 / 150.
[0036] Phase 3: Rotary drilling rig relay drilling section (100~121.1m depth, moderately weathered sandstone entry section) When the drilling depth reaches 100m at the top interface of moderately weathered sandstone, the system automatically switches to the KTY4000 rotary drilling rig for full-face relay drilling. For moderately weathered sandstone, high drilling pressure (70%~90% of the rated value) and slow speed of 3~10rpm are used, and air lift reverse circulation is used for slag removal and simultaneous cooling of the drill bit are employed. When drilling to 0.5~1.0m above the design elevation, adjust the mud index to the final hole standard to reduce the hole cleaning time after the final hole is drilled; after drilling to the design pile bottom elevation of 121.1m, raise the drill bit 30~50cm away from the bottom of the hole, clean the hole continuously for 5~15min, slowly rotate the drill bit, add high-quality mud, and complete the pretreatment before the final hole is drilled.
[0037] Hole deviation correction and hole inspection: During drilling, a verticality deviation of 1 / 160 was detected at a depth of 110m. Drilling was immediately stopped, and rubble was backfilled to 0.5m above the deviation section. Low-stroke, low-speed drilling was then resumed to correct the deviation. After correction, the verticality deviation was 1 / 220, meeting the design requirements. After the hole was completed, a TS-K100 ultrasonic hole inspection instrument was used to complete the full hole inspection. The measured hole depth was 121.12m, which was not less than the design value. The hole diameter was ≥2.8m, the overall verticality deviation of the hole was 1 / 200, and the hole wall was intact without collapse or diameter reduction. After passing the inspection, the next process was initiated. Cleaning the inner wall of the steel casing: After the hole is inspected and approved, a special disc wire brush is used in conjunction with a high-pressure water gun to repeatedly scrub the inner wall of the casing from top to bottom to remove mud and residue. An endoscope is used to check and confirm that the inner wall is in its natural metallic color and free of mud, which provides a guarantee for the subsequent bonding of the pile concrete and the casing.
[0038] S3 Layered Dynamic Modified Mud Wall Protection and Circulation Cleaning Layered modified mud pre-mixing: High-quality PHP bentonite mud is automatically mixed according to corresponding proportions by intelligent mud mixing equipment. The proportions and performance indicators are dynamically matched for different formations, as detailed below: 1. Silty clay and soft soil layer: Base bentonite slurry, with a mixing ratio of water:bentonite = 100:8, 0.2% soda ash added, density 1.05~1.15g / cm³, viscosity 18~22s, sand content ≤4%, colloid content >98%; 2. For easily collapsible strata such as silt, fine sand, and medium-coarse sand: use a viscosity-enhancing composite mud with a mixing ratio of water:bentonite = 100:10, adding 0.3% soda ash and 0.1% polyacrylamide, with a density of 1.1~1.2 g / cm³, viscosity of 22~28s, and sand content ≤4%. 3. For strata prone to grout leakage, such as gravel, fault fracture zones, and densely jointed zones: use high-viscosity composite plugging mud with a mixing ratio of water:bentonite = 100:12, and add 0.3% soda ash, 0.1% cellulose, and 2% plugging agent while drilling. The density is 1.15~1.25g / cm³, and the viscosity is ≥25s. 4. Special mud for hole cleaning stage: density 1.03~1.10g / cm³, viscosity 17~20s, sand content <2%, colloid content >98%.
[0039] 5. Dynamic wall protection and circulation control: During drilling, the level sensor monitors the mud level in the hole in real time to ensure that the mud level in the casing is always 1.5~2.0m higher than the external groundwater level, forming a stable hydrostatic pressure; when crossing the fault fracture zone at a depth of 72m, the mud level drops rapidly, drilling is immediately stopped, the drill string is raised to a safe section, high-viscosity plugging composite mud is injected at a large flow rate, and clay balls + small stones are put into the hole at the same time. After standing for 2 hours, the hole wall is completely sealed, and there is no re-leakage after drilling resumes; 6. The drilling mud adopts a closed-loop circulation system of "mud pit → pile hole → mud trench → sedimentation tank → mud separator → mud pit". After purification by the mud separator, it is recycled. The waste drilling cuttings and mud are transported to the designated waste disposal site by dump truck after sedimentation and drying. Direct discharge into the Yangtze River is strictly prohibited.
[0040] Graded hole cleaning operation: Initial hole cleaning: After the hole is completed, the rotary drilling rig air lift reverse circulation system is used to continuously suck up the slag for 10 minutes to complete the initial hole cleaning. After cleaning, the mud sand content is ≤4% and the thickness of the sediment at the bottom of the hole is ≤100mm. Secondary hole cleaning: After the reinforcement cage and guide pipe are installed, the SF160 air compressor is used for secondary hole cleaning using air lift reverse circulation process. After the hole cleaning is completed, the actual measured thickness of sediment at the bottom of the hole is 32mm, which meets the design requirement of ≤50mm. The mud density is 1.06g / cm³, the sand content is 1.2%, and the viscosity is 18s, which fully meets the requirements for underwater concrete pouring.
[0041] Precise installation and positioning of S4 large-diameter ultra-long steel cage 1. Segmented Fabrication of Reinforcing Cage: The reinforcing cage is fabricated in segments on a standardized jig using the "long-line matching method." Each segment is 12m long, the bottom segment is 10m long, and there are a total of 10 segments. The main reinforcement uses Φ32mm HRB400E steel bars, and the joints use Class I mechanical sleeve connections. The number of steel bar joints in the same cross-section does not exceed 50% of the total number, and the staggered distance between joints is ≥35d. The reinforcing stirrups use Φ20mm steel bars, spaced at 2m, and triangular stiffening braces are installed on the inner side to prevent deformation during hoisting. The spiral stirrups use Φ10mm HPB300 steel bars, spaced at 200mm. 2. After the steel cage is fabricated, four Φ60×3.5mm sonic logging tubes are symmetrically arranged along the inner side of the steel cage. They are connected by sleeve welding, and the joints are sealed to prevent grout leakage. Four circular C40 concrete protective layer pads are arranged every 2m around the steel cage to ensure that the protective layer thickness meets the design requirements. After the steel cage passes the acceptance test, it is numbered and labeled in sections, and plastic protective sleeves are added to the thread ends. It is then stored on a special support.
[0042] 3. Rebar cage hoisting and docking: Double-section I14 I-beam special steel scaffolding is used, with a 4-point hoisting method, combined with the double hook tilting hoisting process of QUY150t crawler crane. The main hook lifts the top reinforcing hoop of the rebar cage, and the auxiliary hook lifts the bottom reinforcing hoop of the rebar cage. After synchronous hoisting, the main hook is slowly raised and the auxiliary hook cooperates to turn the rebar cage from a flat position to a vertical position. After removing the auxiliary hook, it is vertically hoisted to the hole opening. 4. A dedicated HM588×300 steel docking platform is set up at the orifice. During the lowering of the reinforcing cage, the benchmark reinforcing bar marking method is used to control the docking accuracy. The torque of the main reinforcing bar sleeve connection meets the specification requirements. After the docking is completed, the extension and sealing test of the sonic logging pipe are completed simultaneously, and the sonic logging pipe is filled with clean water. 5. During the process of lowering the steel cage section by section, the internal temporary triangular stiffening brace is cut off to avoid obstruction of the subsequent lowering of the guide pipe. After it is lowered into place, four Φ32mm continuous lifting bars are used to rigidly weld and fix the steel cage to the steel casing. The deviation between the center of the steel cage and the center of the pile position is ≤20mm, and the installation elevation error is ±30mm, which effectively prevents the steel cage from floating during the concrete pouring process.
[0043] S5 Pressure-bearing continuous underwater concrete pouring construction 1. Conduit installation and verification: Φ326mm seamless steel conduit is used, with quick threaded joints and double sealing rings. Before use, the conduit undergoes water tightness pressure test and joint tensile test. The test pressure is 1.0MPa, and the pressure is stabilized for 15 minutes without leakage. The conduit is installed section by section, lowered in the center throughout to avoid snagging on the reinforcing cage. After installation, the bottom of the conduit is 40cm from the bottom of the hole, which meets the design requirement of 30~50cm.
[0044] 2. Concrete mix proportion and supply: C35 underwater concrete is used, with a mix proportion of cement: fly ash: mineral powder: sand: crushed stone: admixture: water = 0.8:0.1:0.1:1.66:2.59:0.01:0.41, slump 210±20mm, initial setting time ≥8h, and workability and anti-dispersion properties meeting the requirements for underwater grouting; the amount of concrete prepared for each pile is reserved according to 1.1 times the hole expansion coefficient, and 10 10m³ concrete transport trucks are used for transportation to ensure continuous and uninterrupted grouting process.
[0045] 3. First batch of concrete pouring: Based on the pile diameter, pile length and Yangtze River water level parameters, the theoretical volume of the first batch of concrete was calculated to be 13.2 m³. After reserving 1.1 times the hole expansion coefficient, the volume of the first pour was determined to be 15 m³. The first pouring was carried out using a 15 m³ large hopper in conjunction with the ball pressing method. Before the first pouring, a water-proof ball was placed in the guide pipe to isolate the mud and concrete. After the concrete storage in the hopper met the requirements of the first pouring, the water-proof plug was pulled out and the material was continuously discharged at the same time. After the first pouring was completed, the actual buried depth of the guide pipe was 1.4 m, which met the design requirement of ≥1.0 m. The first pouring was successful.
[0046] 4. Continuous grouting and dynamic control: After the first grouting is completed, replace the 1m³ small hopper and switch to the normal continuous grouting stage. During the grouting process, after each truckload of concrete is poured, the concrete surface elevation is measured once with a measuring rope. The burial depth of the guide pipe is dynamically calculated and adjusted. The burial depth of the guide pipe is controlled within the range of 2~6m throughout the process. It is strictly forbidden to pull the guide pipe out of the concrete surface. 5. When the concrete surface rises to 2-3m above the bottom of the reinforcing cage, the guide pipe should be raised appropriately to reduce the embedment depth to 2m, thereby reducing the upward lifting force of the concrete and preventing the reinforcing cage from floating. During the pouring process, the pouring pressure in the hole and the rising speed of the concrete surface should be monitored in real time, and the pouring rate should be dynamically adjusted to ensure that the concrete surface rises evenly and that there are no pipe blockages, pipe burials, or reinforcing cage floating phenomena throughout the process. 6. After pouring to the design elevation of the pile top, over-pour by 1.0m to ensure that the concrete strength at the pile top meets the design requirements after removing the laitance; the total concrete pouring time for a single pile is 12 hours, which does not exceed the initial setting time of the first batch of concrete, and the entire process is continuous without interruption.
[0047] S6 Pile Construction Quality Control and Special Working Condition Adaptation Construction 1. Pile formation test: After the pile concrete reaches the design strength, the integrity of the pile is tested along the entire length using ultrasonic transmission method. The measured wave velocity of the pile is uniform and there are no defective reflected waves. The integrity of the pile is judged as Class I pile. The 28-day compressive strength of the concrete test blocks all meet the C35 design requirements, and the bearing capacity of the single pile meets the design and specification requirements.
[0048] 2. Special Working Condition Adaptation Measures: For construction during the flood season in the Yangtze River Basin, a real-time linkage mechanism with hydrological and meteorological departments will be established. The site drainage system will be reinforced in advance, and casings and equipment will be anchored. Emergency evacuation plans for personnel and equipment will be developed, and sufficient flood control and disaster relief materials will be prepared. For water operations, navigation notices will be issued to the maritime authorities, warning buoys will be set up, patrol boats will be arranged, and emergency measures for ship collision prevention and personnel falling into the water will be implemented. For nighttime construction, sufficient lighting equipment will be provided, a leadership duty system will be implemented, and high-risk hoisting operations will be strictly prohibited at night. For winter construction, mud pits will be insulated, hot water will be used for concrete mixing, and transport tank trucks will be insulated to ensure that the concrete temperature upon placement is ≥5℃.
[0049] 3. Environmental Protection Management: During the construction process, the ecological protection requirements of the Yangtze River waters will be strictly implemented. The mud will be circulated in a closed loop throughout the process. Waste drilling cuttings and mud will be disposed of in compliance with regulations after drying, and discharge into the Yangtze River is strictly prohibited. Construction vessels will be equipped with oil collection tanks and emergency supplies such as oil-absorbing blankets to prevent oil leaks from polluting the water. Sedimentation tanks will be set up in the construction area, and construction wastewater will be discharged after sedimentation to meet standards, minimizing the impact on the ecological environment of the Yangtze River waters.
[0050] 4. Construction effect of this embodiment In this embodiment, the total construction period for a single pile is 12 days, which meets the project's efficiency plan of 12 days per pile. This shortens the construction period by 30% compared to pile foundations using the traditional single rotary drilling process at the same site. There were no quality and safety accidents such as hole collapse, drill bit burial, drill bit jamming, large-area grout leakage, rebar cage floating, or pile breakage during the entire construction process. The verticality of the borehole, pile position deviation, thickness of sediment at the bottom of the hole, and concrete strength all exceeded the design and specification requirements. The integrity of the pile reached 100% of the Class I pile standard. The mud recycling rate reached 85%, reducing waste mud discharge by 60%, which takes into account the construction quality, efficiency, safety, and ecological and environmental protection requirements of the Yangtze River basin.
[0051] Example 2: Construction of large-diameter rock-socketed piles in the Yangtze River (Pile foundation of main pier No. 4 of the North Channel Bridge) 1. Project Overview and Construction Conditions This embodiment is applied to the pile foundation project of Pier 4 of the south main tower of the North Channel Bridge of the Wuhu Taishan Road Yangtze River Bridge on the S24 Hangzhou-Hefei Expressway. The pile is located in the water on the south bank of the North Channel of the Yangtze River, with a riverbed elevation of 0.32~0.68m. The designed pile diameter is 2.8m, the designed pile length is 78m, the drilling depth is 84.41m, the bearing layer at the pile end is moderately weathered sandstone, the embedment depth is not less than 2 times the pile diameter, the designed concrete volume of a single pile is 481m³, and the total weight of the steel cage is 40.52t.
[0052] The geological conditions at this pile site, from top to bottom, consist of silty clay, silt, fine sand, gravel, and completely to moderately weathered sandstone. The site is directly affected by the Yangtze River tides, with the highest tide level during construction at +11.05m and the lowest tide level at 0.29m. The maximum flow rate of the left branch is approximately 20,600 m³ / s, and the construction water area is 300m × 500m, posing high risks to navigation safety and water operations.
[0053] 2. Core construction steps and process parameters 1. Pre-construction preparation: Before construction, a 98m×50m offshore drilling platform will be erected. The platform structure will be specially designed and calculated to meet the construction load and scour resistance requirements. An application will be made to the maritime administration for an underwater operation permit, a navigation notice will be issued, and warning buoys and warning vessels will be set up. The steel casing will be made of Q355C steel with an inner diameter of 3.2m and a wall thickness of 24mm. The total length will be 41.3m. A QUY150t crawler crane will be used in conjunction with an APE600 hydraulic vibratory hammer to drive the casing in sections. The top of the casing will be 50cm lower than the platform elevation, the center deviation will be ≤5cm, the inclination will be ≤1 / 150, and the bottom of the casing will be embedded in a stable stratum to avoid the risk of riverbed scour and grout leakage.
[0054] 2. Adaptive Hole Formation Construction: The XR580HD rotary drilling rig is used for construction. During the drilling process, geological sensors collect formation data in real time and dynamically adjust drilling parameters. Medium-low speed and light pressure drilling is used inside the casing and in soft soil sections, with a drilling speed of 4~6m / h. In sandy sections, depressurized low-speed drilling is used, with a drilling speed of 2~4m / h, while simultaneously increasing the mud viscosity and density to ensure that the mud level inside the casing is more than 2.0m above the Yangtze River water level. In moderately weathered sandstone sections, staged reaming drilling is used with roller cone drills, with drilling pressure controlled at 60%~80% of the rated value and a rotation speed of 4~8rpm to ensure that the rock penetration depth meets the design requirements. After the hole is completed, an ultrasonic hole detection instrument is used to check that the hole verticality deviation is ≤1 / 180, and the hole diameter and depth meet the design requirements.
[0055] 3. Mud wall protection and borehole cleaning: Considering the characteristics of underwater construction, a closed-loop mud circulation system consisting of a mud tank and a mud separator is adopted to prevent mud leakage into the river. The mud ratio is dynamically adjusted according to different strata. High-viscosity composite mud with a density of 1.15~1.20g / cm³ and a viscosity of 22~28s is used in sandy sections to effectively prevent borehole collapse and mud leakage. After the borehole is completed, a rotary drilling rig with a slag hopper and air lift reverse circulation are used to complete the initial borehole cleaning. After the reinforcement cage and guide pipe are installed, a secondary borehole cleaning is carried out. After cleaning, the thickness of sediment at the bottom of the borehole is ≤50mm, and the mud indicators meet the specifications.
[0056] 4. Reinforcing cage installation and concrete pouring: The reinforcing cage is fabricated in 7 sections, each 12m long. It is hoisted at four points using a special gantry crane and connected to the borehole opening on the water platform. The main reinforcement sleeve connection quality meets the requirements of Class I joints. After being lowered into place, it is rigidly fixed to the drilling platform to prevent floating. Underwater concrete is poured using a Φ326mm sealed duct. The initial concrete volume is calculated to be 12m³. After the first pour, the duct burial depth is ≥1.0m. During the pouring process, the duct burial depth is controlled at 2~6m throughout the process. The pouring is continuous without interruption, with an over-pouring of 1.0m at the pile top. The total pouring time for a single pile is 10 hours, which does not exceed the initial setting time of the concrete.
[0057] 5. Pile Inspection and Safety Management: After pile completion, ultrasonic testing showed that the pile integrity was classified as Class I pile, and the concrete strength met the design requirements. Navigation safety management was implemented throughout the water operations, with warning boats patrolling 24 hours a day. All personnel wore life jackets, and the platform was equipped with continuous protective railings and safety nets, as well as emergency supplies such as lifeboats and life rings. No water safety accidents or water pollution incidents occurred during the entire construction process.
[0058] The above embodiments are merely preferred embodiments of the present invention and should not be construed as limiting the scope of protection of the present invention. Any non-substantial changes and substitutions made by those skilled in the art based on the present invention shall fall within the scope of protection claimed by the present invention.
Claims
1. An adaptive relay construction method for large-diameter, ultra-long bored piles in deep water along the Yangtze River, comprising the steps of pre-construction preparation, hole drilling, mud wall protection, hole cleaning, reinforcement cage installation, underwater concrete pouring, and pile testing, characterized in that, Specifically, the steps include the following: S1 Construction Pre-construction Survey and Preparation: Advanced drilling combined with detailed geological exploration was used to complete the detailed survey of pile locations, to determine the stratigraphic distribution, fault fracture zones, densely jointed zones, groundwater and Yangtze River tidal hydrological parameters within the pile location range of the Yangtze River tidal flat area and the water operation area, and to draw pile-by-pile geological profile maps; site hardening was completed for the north bank tidal flat area, and the construction of the water drilling platform was completed for the south bank Yangtze River water area, and the steel casing of the corresponding pile locations was installed in sections and precisely positioned simultaneously; the real-time geological monitoring system and intelligent mud preparation equipment for the rotary drilling rig and the gyratory drilling rig were debugged and calibrated, the construction measurement control network was set up and the three-level technical briefing was completed; S2 Adaptive Relay Composite Hole Formation Construction: After the pile position is accurately laid out and the drilling rig is positioned and fixed, a rotary drilling + gyratory drilling relay composite drilling process is adopted for construction. During the drilling process, the geological sensors built into the hole collect data on the hardness of the formation, porosity, groundwater pressure and mud level in real time. Based on the collected real-time geological data, the three stages of normal drilling of the rotary drilling rig, multi-stage hole enlargement of the rotary drilling rig and relay drilling into the rock are executed in sequence. The drilling mode and corresponding drilling parameters of each stage are intelligently matched. During the drilling process, the verticality of the borehole is monitored in real time and the deviation correction is completed simultaneously. After drilling to the designed rock-embedded elevation, the hole quality is inspected and unqualified sections are re-drilled and repaired. At the same time, the mud cake cleaning operation on the inner wall of the steel casing is completed. S3 Layered Dynamic Modified Mud Wall Protection and Circulation Cleaning: High-quality PHP bentonite modified mud with corresponding proportions is pre-formulated to address the complex geological characteristics of the Yangtze River basin. During drilling, the modified mud is dynamically matched to the appropriate ratio based on real-time geological data for wall protection. The mud level and leakage are monitored simultaneously, and the mud supply, proportion, and circulation parameters are dynamically adjusted to construct a closed-loop mud circulation and purification system. After the borehole quality is qualified, the initial cleaning is completed using an air-lift reverse circulation process. A secondary cleaning operation is completed after the reinforcement cage and guide pipe are installed. S4 Large Diameter Extra-Long Rebar Cage Precision Installation and Positioning: The rebar cage is manufactured in sections on a standardized jig using a long-line matching method. The main reinforcement bars are connected using Class I mechanical sleeves, and the sonic logging pipe and rebar cage are fixed and installed simultaneously. The rebar cage is lowered smoothly using a four-point hoisting method with a special steel hanger. A special docking platform is set at the borehole opening to complete the precise docking of the rebar cage sections. After being lowered into place, a continuous lifting bar is used to rigidly fix the rebar cage to the steel casing / drilling platform, completing the center positioning and anti-buoyancy limit of the rebar cage. S5 Pressure-bearing Continuous Underwater Concrete Pouring Construction: After completing the lowering and installation of the sealed tremie pipe and the water tightness test, C35 underwater concrete construction is carried out using a continuous pouring process; before pouring, the volume of the first batch of concrete is accurately calculated based on the pile diameter, pile length and Yangtze River water level parameters to ensure that the initial burial depth of the tremie pipe is ≥1.0m after the first pour; during the pouring process, the burial depth of the tremie pipe, the concrete surface elevation and the pouring pressure in the hole are monitored in real time, and the concrete pouring rate and pouring pressure are dynamically adjusted. The burial depth of the tremie pipe is controlled within the range of 2~6m throughout the process. After pouring to the design elevation of the pile top, the over-pouring is ≥1.0m. The entire pouring process is continuous and uninterrupted. S6 pile quality control and special working condition adaptation construction: After the pile concrete reaches the design strength, the integrity of the pile body is tested along the entire length of the pile using ultrasonic transmission method; special adaptation construction measures are implemented for construction conditions during the flood season, rainy season, high temperature, winter and night in the Yangtze River Basin, and the safety control of navigation and ecological and environmental protection of water operations in the Yangtze River Basin are implemented simultaneously.
2. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S1, the site of the north bank tidal flat area is hardened with 30cm thick 4% lime-soil + 30cm thick double-layer steel mesh concrete; the inner diameter of the steel casing is larger than the designed pile diameter, where the Φ2.8m pile diameter corresponds to a steel casing inner diameter of 3.2m and a wall thickness of 24mm, and the Φ2.2m pile diameter corresponds to a steel casing inner diameter of 2.5m; the center deviation of the steel casing is ≤5cm and the inclination is ≤1 / 150. The top of the casing in the tidal flat area is 30cm higher than the site elevation, and the top of the casing in the water operation area is 50cm lower than the platform elevation; the perimeter of the casing is backfilled and compacted with clay in layers, and the steel casing in the water operation area is driven into a stable stratum in sections using an APE600 hydraulic vibratory hammer.
3. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S2, the specific execution rules for the three stages of adaptive relay composite hole forming are as follows: The first stage is the normal drilling section of the rotary drilling rig: the soil layer inside and outside the casing is drilled using the XR580HD rotary drilling rig. For silty clay layers, medium-low speed and light pressure drilling is used, with the drilling speed controlled at 4~8m / h; for silty sand and fine sand layers, depressurized low-speed drilling is used, with the drilling pressure controlled below 80% of the drill bit weight and the drilling speed controlled at 2~4m / h; within 1m above and below the bottom of the casing, the lowest speed and light pressure are used to slowly pass through. The second stage is the multi-stage reaming section of the rotary drilling rig: when the drilling pressure reaches 80% of the rated value of the rotary drilling rig and before entering the moderately weathered bearing layer, the multi-stage reaming process is started. The "small diameter guide, graded reaming" mode is adopted, and the reaming is carried out in stages by centering drills / tube drills of Φ1.5m, Φ2.0m, Φ2.5m and Φ2.8m in sequence. The corresponding specification slag removal bucket is used for cleaning. Each stage of reaming adopts depressurization drilling, and the drilling pressure is controlled at 50%~70% of the rated value and the rotation speed is 4~8 rpm. The third stage is the relay drilling section of the rotary drilling rig: When the drilling depth reaches the top interface of the moderately weathered sandstone or the Φ1.5m small-diameter drill pressure reaches 80% of the rated value, switch to the KTY4000 rotary drilling rig for full-face relay drilling. For moderately weathered sandstone, high drill pressure and slow speed drilling are adopted, with the drill pressure controlled at 70%~90% of the rated value and the speed at 3~10 rpm. Air lift reverse circulation is used for slag removal. When drilling reaches 0.5~1.0m above the design elevation, adjust the mud index to the final hole standard, and after the final hole is reached, lift the drill and clean the hole.
4. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1 or 3, characterized in that, In S2, during the drilling process, every 10-20m or when entering a new stratum, an ultrasonic borehole detector is used to check the verticality of the borehole, and the overall verticality deviation is controlled to be ≤1 / 150. If borehole deviation is detected, drilling is immediately stopped, and rubble is backfilled to more than 0.5m above the deviated section. Low-stroke, low-speed drilling is then used to correct the deviation. After the borehole is completed, an ultrasonic borehole detector is used to check the hole depth, hole diameter, verticality, and hole wall integrity, wherein the hole depth is not less than the design value, and the hole diameter is not less than the design pile diameter.
5. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S3, the dynamic matching rule between the proportion and performance indicators of the layered modified mud is as follows: For silty clay and soft soil layers, use basic bentonite slurry with a density controlled at 1.05~1.15 g / cm³, viscosity at 18~22s, and sand content ≤4%. For easily collapsible strata such as silt, fine sand, and medium-coarse sand, a bentonite + polyacrylamide thickening composite mud is used, with a density controlled at 1.1~1.2 g / cm³, a viscosity of 22~28s, and a sand content ≤4%. For strata prone to grout leakage, such as gravel, fault fracture zones, and densely jointed zones, a high-viscosity composite mud consisting of bentonite, a plugging agent, and cellulose is used, with a density controlled at 1.15~1.25 g / cm³ and a viscosity ≥25s. During the hole cleaning stage, the mud density should be controlled at 1.03~1.10 g / cm³, viscosity at 17~20s, sand content at <2%, and colloid content at >98%. During drilling, ensure that the mud level inside the casing is always 1.5~2.0m higher than the external Yangtze River water level / groundwater level. If leakage occurs, immediately replenish the mud and add plugging material. The mud is purified by a mud separator and then recycled. Waste drill cuttings and mud are disposed of in accordance with regulations after sedimentation and drying. Direct discharge into the Yangtze River is strictly prohibited.
6. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S3, the initial hole cleaning is completed after the hole is closed by using a rotary drilling rig air lift reverse circulation system to continuously suck up slag for 5 to 15 minutes; the secondary hole cleaning is carried out after the steel cage and guide pipe are installed by using an air compressor air lift reverse circulation process. After hole cleaning, the thickness of sediment at the bottom of the hole is ≤50mm. It is strictly forbidden to replace hole cleaning by increasing the drilling depth.
7. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S4, the length of the rebar cage sections matches the standard length of the rebar, with a single section length ≤ 12m, and the length of the bottom section of the rebar cage matches the final hole elevation. The number of rebar joints in the same cross-section does not exceed 50% of the total number of rebars, and the joints are staggered by ≥ 35d. The rebar cage is hoisted using a double-hook rotating hoisting process to avoid hoisting deformation. When the rebar cage is connected, the reference rebar marking method is used to control the connection accuracy, and the installation elevation error is controlled within ±50mm. Four concrete protective layer pads are arranged circumferentially every 2m along the pile body of the rebar cage, and four sonic logging pipes are symmetrically arranged along the inner side of the rebar cage. They are connected by sleeve welding, and the entire process is sealed to prevent grout leakage. After the rebar cage is lowered, the pipe is filled with clean water and the pipe opening is sealed.
8. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S5, the guide pipe is made of seamless steel pipe with an inner diameter ≥300mm, and the quick threaded joint is equipped with double sealing rings. Before use, water tightness pressure and joint tensile tests are completed. After the guide pipe is installed, the bottom is 30~50cm away from the bottom of the hole. The volume of the first batch of concrete is reserved according to 1.1 times the hole expansion coefficient to ensure that the burial depth of the guide pipe is ≥1.0m after the first pour. During the pouring process, when the concrete surface rises to 2~3m above the bottom of the reinforcing cage, the guide pipe is raised to reduce the burial depth to 2m to reduce the concrete lifting force and prevent the reinforcing cage from floating. The entire pouring process shall not exceed the initial setting time of the first batch of concrete, and the over-pour height of the pile top concrete shall be ≥1.0m to ensure that the strength of the pile top concrete meets the design requirements after the laitance is removed.
9. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S6, pile integrity testing is divided into four categories: I, II, III, and IV. The integrity of each pile must meet the standard of Class I piles and be no lower than that of Class II piles. For construction during the Yangtze River flood season, a real-time hydrological and meteorological linkage mechanism is established, the platform and casing reinforcement is completed in advance, and an emergency evacuation plan for personnel and equipment is formulated. For construction in winter, special insulation measures are taken for mud preparation, concrete mixing, transportation, and pouring. For water operations, a navigation notice is issued to the maritime authorities, warning buoys and warning vessels are set up, and emergency measures for ship collision prevention and personnel falling into the water are implemented.
10. The adaptive relay construction method for large-diameter, ultra-long bored piles in deep water of the Yangtze River according to claim 1, characterized in that, In S2, adjacent pile foundations shall not be drilled or poured with concrete at the same time. Drilling of adjacent piles can only be carried out after the concrete strength of adjacent piles reaches more than 75% of the design strength, so as to avoid accidents such as cross-hole and hole collapse.