Karst area cast-in-place pile construction structure and construction method
By using steel casing connectors and filling pipe systems in the construction of cast-in-place piles in karst areas, the problem of difficulty in filling the annular gap after the casing sinks has been solved, thereby improving the stability of the pile foundation and ensuring the construction quality.
Patent Information
- Application Number
- CN202611467417.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-21
- Publication Date
- 2026-11-20
AI Technical Summary
In the construction of cast-in-place piles in karst areas, irregular annular gaps or voids formed after the casing sinks result in poor stability of the pile foundation, making it difficult to fill and affecting the construction quality.
A steel casing connector and filling pipe system are used to fix adjacent steel casings through connectors, and filling material is put into the karst cave through filling pipes and extension pipes to fill the annular gap and ensure that the area around the steel casing is dense.
It effectively fills karst cavities, improves the stability of pile foundations, prevents collapses caused by excessive gaps during construction, and ensures construction quality.
Smart Images

Figure CN123133352A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building construction technology, specifically to a construction structure and method for cast-in-place piles in karst areas. Background Technology
[0002] Karst areas are characterized by complex geological structures such as caves, fissures, solution channels, and underground rivers. The strata are unstable and groundwater is frequently active. During the construction of cast-in-place piles, problems such as borehole instability, borehole collapse, grout leakage, and difficulty in controlling sediment are very likely to occur. Therefore, the construction of cast-in-place piles in karst areas has always been a key and difficult point in foundation engineering.
[0003] In karst areas, the construction of cast-in-place piles often employs a casing rolling machine in conjunction with steel casing installation. The principle behind this process is that a hydraulic system generates rolling torque and downward pressure to gradually sink the casing into the ground. However, karst areas have complex geological conditions, with irregularly distributed karst cavities often present in the bedrock. After the casing is in place, several irregular annular gaps or voids often form between its outer wall and the cavities. In subsequent construction, these annular gaps or voids cannot be filled, resulting in a large number of gaps around the steel casing and affecting the stability of the subsequent pile foundation.
[0004] Therefore, we propose a construction structure and method for cast-in-place piles in karst areas to address the problems mentioned above. Summary of the Invention
[0005] The purpose of this invention is to solve the aforementioned technical problems.
[0006] To achieve the above objectives, the present invention adopts the following technical solution: A construction structure for cast-in-place piles in karst areas includes several steel casings buried within the karst area, arranged vertically. Adjacent steel casings are connected by fasteners to secure them. The two lowest steel casings are connected by a connector located within a karst cave below the karst area. A filling pipe is fixed inside the connector, with one end extending into the karst cave for depositing filling material into it. An extension pipe is installed at the top of the filling pipe, with one end extending outside the steel casing to allow filling material to be deposited into the filling pipe through the extension pipe.
[0007] Furthermore: the connector includes a tube, and a thickened sleeve is fixed on the outer circumferential surface of the tube. When the two ends of the tube are respectively inserted into the interior of the steel sleeve, the two ends of the thickened sleeve abut against the ends of the steel sleeve.
[0008] Furthermore: both ends of the insertion tube are provided with a plurality of mounting holes 1, and one end of the steel sleeve is provided with mounting hole 2. The mounting holes 1 and mounting holes 2 are connected by bolt thread connectors to fix adjacent steel sleeves.
[0009] Furthermore, the inner circumferential surface of the insertion tube is fixed with a fixing sleeve, and the upper part of several filling tubes is fixed on the fixing sleeve to reinforce the several fixing sleeves.
[0010] Furthermore, a clamp is fixed at the connection between the filling tube and the extension tube, and the clamp is used to reinforce the filling tube and the extension tube.
[0011] Furthermore: several limiting supports are fixed at equal intervals on the circumferential surface of the karst area, and the limiting supports are arranged in several columns, with several extended tubes respectively fitted onto the limiting supports.
[0012] A construction method for cast-in-place pile structures in karst areas includes the following steps: S1: First, drive the first steel casing into the interior of the karst area; A hydraulic pipe rolling machine is used to apply downward pressure to the first steel casing so that the steel casing can be slowly inserted into the interior of the karst area; S2: Install a connector between the bottom steel sleeve and the adjacent steel sleeve above it; After the first steel sleeve is driven into the ground, a connector is installed between the bottom steel sleeve and the adjacent steel sleeve above it. The connector is used to fix the two adjacent steel sleeves to prevent them from becoming loose. S3: When the connector extends to the location of the karst cave, the karst cave shall be filled. Apply further pressure to the upper steel sleeve in the same manner as S1 to make the connector continue to move downward into the karst area; when the connector is pressed downward into the area of the karst cavity, fill the cavity. Filling material is placed into several different extension tubes, and the filling material is successively placed into the interior of the cave through the extension tubes and the filling tubes to fill the cave. S4: Further drive the steel casing into the karst area; The steel casing is further pressurized in the same manner as in S1 to insert it to the specified depth in the ground. S5: Remove the soil from inside the steel casing; The soil inside several steel casings was removed using a rotary drilling rig for subsequent reinforcement treatment. S6: Place a steel cage inside several steel sleeves; After the soil inside the steel casing is removed, a steel reinforcement frame is placed inside several steel casings, and the steel reinforcement frame is set coaxially with the steel casing. S7: Pour concrete into the interior of several steel casings; Concrete is poured into the interior of several steel sleeves. Once the concrete and the reinforcing steel frame have solidified, the operation is complete.
[0013] Furthermore: before step S4, the bottom ends of several extension tubes are respectively sealed and connected to the top end of the filling tube for subsequent filling; and the extension tubes pass through several of the fixing sleeves, and the fixing sleeves limit the extension tubes.
[0014] The beneficial effects of this invention are: The present invention provides a connector between the bottom steel sleeve and the adjacent steel sleeve above it, and provides several filling tubes on the connector. Through the cooperation of several extended tubes and filling tubes, filling material can be put into the annular gap or void area, thereby filling the area around the steel sleeve densely and preventing the stability of the pile foundation from being affected by the excessive gap during subsequent construction.
[0015] This invention involves sealing and installing extension tubes at the top of several filling tubes, allowing these extension tubes to extend to the ground. This enables workers to stand on the ground and deposit filling material into the extension tubes, allowing the filling material inside the extension tubes to be deposited into the cavern. This makes the operation convenient and provides convenience for workers. Attached Figure Description
[0016] Figure 1 This is a schematic diagram of the structure in use of the present invention; Figure 2 This is a cross-sectional structural diagram of the present invention; Figure 3 This is a three-dimensional structural schematic diagram of the present invention; Figure 4 This is a schematic cross-sectional view of the steel sleeve in this invention; Figure 5 This is a cross-sectional structural diagram of the connector in this invention.
[0017] The names corresponding to each mark in the diagram: 1. Karst area; 2. Steel sleeve; 201. Mounting hole two; 4. Connector; 401. Insert pipe; 402. Thickened sleeve; 403. Mounting hole one; 404. Fixing sleeve; 5. Cavern; 6. Filling pipe; 7. Extended pipe; 8. Bolt threaded connector; 9. Limiting support; 10. Reinforcing cage. Detailed Implementation
[0018] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention are within the scope of protection of the present invention.
[0019] A construction structure for cast-in-place piles in karst areas includes several steel sleeves 2, which are installed vertically into the ground. Adjacent steel sleeves 2 are connected by fasteners. The fasteners serve to connect and fix the two adjacent steel sleeves 2, preventing them from loosening during use and providing strong stability.
[0020] It should be noted that a connector 4 is installed between the bottommost steel sleeve 2 and the adjacent steel sleeve 2 above it. The connector 4 usually needs to be extended to the area of the karst cave 5 for use. With the installation of the connector 4, filling material can be put into the karst cave 5 in the karst area 1. The filling material can be concrete to ensure that the area around the steel sleeve 2 is filled densely, thereby improving the stability of the device and preventing subsequent collapse.
[0021] The connector 4 has a fixed filling tube 6 inside. It should be noted that there are several filling tubes 6. By setting several filling tubes 6, filling material can be filled into different areas of the cave 5. It should be noted that the bottom ends of several filling tubes 6 extend into the interior of the cave 5, and the bottommost steel sleeve 2 has an opening, which is set to correspond with the filling tube 6 to ensure that it can be put into the interior of the cave 5. The top ends of several filling tubes 6 are sealed with extension tubes 7. Under normal circumstances, the filling tubes 6 and extension tubes 7 are connected by clamps. The extension tubes 7 allow one end to extend to the ground, so that workers can stand on the ground to put filling material into the filling tubes 6, thus providing convenience for workers.
[0022] In detail: Connector 4 includes a tube 401. Normally, both ends of the tube 401 are inserted into the steel sleeve 2, serving as the initial connection. A thickened sleeve 402 is fixed to the outer circumference of the tube 401. When both ends of the tube 401 are inserted into the steel sleeve 2, the two ends of the thickened sleeve 402 abut against the ends of the steel sleeve 2, thus achieving a sealing effect. Several mounting holes 403 are provided at both ends of the tube 401, and a mounting hole 201 is provided at one end of the steel sleeve 2. When mounting holes 403 and 201 are aligned, they are connected by a threaded bolt connector 8. It should be noted that the threaded bolt connector 8 consists of a bolt and a nut. Through the cooperation of the bolt and nut, adjacent steel sleeves 2 can be fixed, preventing loosening and providing strong stability.
[0023] It should be noted that a fixing sleeve 404 is fixed to the inner circumferential surface of the insertion tube 401, and the upper part of several filling tubes 6 is fixed to the fixing sleeve 404. The fixing sleeve 404 serves to reinforce the filling tubes 6 and prevent them from becoming loose or shaking during use, thus providing strong stability.
[0024] Several limiting supports 9 are fixed at equal intervals on the inner circumference of the karst area 1, and the limiting supports 9 are arranged in several columns. Several extension tubes 7 are respectively fitted onto the limiting supports 9. The limiting supports 9 serve to reinforce the extension tubes 7 and prevent them from loosening or shaking during use, thus providing strong stability.
[0025] A construction method for cast-in-place pile structures in karst areas includes the following steps: S1: First, drive the first steel casing 2 (that is, the bottommost steel casing 2) into the interior of the karst area 1; A hydraulic pipe rolling machine (not shown in the figure) is used to apply downward pressure to the first steel sleeve 2 so that the steel sleeve 2 can be slowly inserted into the interior of the karst area 1.
[0026] S2: Install connector 4 between the bottommost steel sleeve 2 and the adjacent steel sleeve 2 above it; After the first steel casing 2 is driven into the ground, a connector 4 is installed between the bottom steel casing 2 and the adjacent steel casing 2 above it. The connector 4 fixes the two adjacent steel casings 2. On the one hand, it reinforces the adjacent steel casings 2 and prevents them from loosening. On the other hand, it allows filling material to be put into the area of the karst cave 5 to ensure that the area around the steel casing 2 is filled densely.
[0027] S4: When the connector 4 extends to the position of the cave 5, the cave 5 is filled. Apply further pressure to the upper steel sleeve 2 in the same manner as S1, so that the connector 4 continues to move downward into the karst area 1; when the connector 4 applies downward pressure to the area of the karst cave 5, the karst cave 5 is filled. The filling material is injected into the interior of several extension pipes 7 by a delivery pump. The filling material is injected into the interior of the karst cave 5 through the extension pipes 7 and the filling pipes 6 in sequence, which can fill the karst cave 5 and effectively reduce the gaps around the steel casing 2.
[0028] It should be noted that the bottom ends of several extension tubes 7 are sealed and connected to the top end of the filling tube 6 for subsequent filling; and the extension tubes 7 pass through several fixing sleeves 404, which limit the extension tubes 7.
[0029] It should be noted that when the height of the karst cave 5 is less than the length of the steel sleeve 2, the steel sleeve 2 needs to be continuously pressurized by a hydraulic pipe rolling machine so that the bottom end of the steel sleeve 2 is driven into the lower part of the karst cave, while the connector 4 is located in the upper part of the karst cave 4, which facilitates the subsequent pouring of the karst cave 5 and provides convenience for the staff.
[0030] S5: Further drive the steel casing 2 into the karst area 1; The steel casing 2 is further pressurized in the same manner as in S1 so that it is inserted into the karst area 1 at the specified depth.
[0031] S6: Remove the soil from inside steel casing 2; The soil inside several steel casings 2 was removed using a rotary drilling rig (not shown in the figure) for subsequent reinforcement treatment.
[0032] S7: Place a steel cage 10 inside several steel sleeves 2; After the soil inside the steel sleeve 2 is removed, a steel reinforcement frame 9 is placed inside several steel sleeves 2, and the steel reinforcement frame 9 is coaxially set with the steel sleeve 2. S7: Pour concrete into the interior of several steel sleeves 2; Concrete is poured into the interior of several steel sleeves 2. Once the concrete and the reinforcing steel frame 9 have solidified, the operation is complete.
Claims
1. A construction structure for cast-in-place piles in karst areas, comprising a plurality of steel casings (2) embedded in a karst area (1), wherein the plurality of steel casings (2) are arranged vertically; adjacent steel casings (2) are connected by fasteners to secure the adjacent steel casings (2), characterized in that: The two steel sleeves (2) at the bottom are connected by a connector (4), and the connector (4) is located in the cave (5) below the karst area (1); a filling tube (6) is fixed inside the connector (4), and one end of the filling tube (6) extends into the cave (5), and the filling tube (6) is used to put filling material into the cave (5); an extension tube (7) is installed at the top of the filling tube (6), and one end of the extension tube (7) extends to the outside of the steel sleeve (2) so that the filling material is put into the filling tube (6) through the extension tube (7).
2. The construction structure for cast-in-place piles in karst areas according to claim 1, characterized in that: The connector (4) includes a tube (401), and a thickened sleeve (402) is fixed on the outer circumference of the tube (401). When the two ends of the tube (401) are respectively inserted into the steel sleeve (2), the two ends of the thickened sleeve (402) abut against the ends of the steel sleeve (2).
3. The construction structure for cast-in-place piles in karst areas according to claim 2, characterized in that: The insertion tube (401) has several mounting holes 1 (403) at both ends, and the steel sleeve (2) has a mounting hole 2 (201) at one end. The mounting holes 1 (403) and mounting holes 2 (201) are connected by bolt thread connectors (8) to fix the adjacent steel sleeves (2).
4. The construction structure for cast-in-place piles in karst areas according to claim 2, characterized in that: The inner circumferential surface of the insertion tube (401) is fixed with a fixing sleeve (404), and the upper part of several filling tubes (6) is fixed on the fixing sleeve (404) to reinforce the several fixing sleeves (404).
5. The construction structure for cast-in-place piles in karst areas according to claim 1, characterized in that: The connection between the filling tube (6) and the extension tube (7) is fixed with a clamp, which is used to reinforce the filling tube (6) and the extension tube (7).
6. The construction structure for cast-in-place piles in karst areas according to claim 1, characterized in that: The karst area (1) has several equidistant limiting supports (9) fixed on the inner circumference surface, and the limiting supports (9) are arranged in several columns, and the several extended tubes (7) are respectively fitted on the limiting supports (9).
7. A construction method for a karst area cast-in-place pile construction structure: applied to the karst area cast-in-place pile construction structure according to any one of claims 1-6, characterized in that: Includes the following steps: S1: First, drive the first steel casing (2) into the interior of the karst area (1); A hydraulic pipe rolling machine is used to apply downward pressure to the first steel sleeve (2) so that the steel sleeve (2) can be slowly inserted into the interior of the karst area (1); S2: Install a connector (4) between the bottommost steel sleeve (2) and the adjacent steel sleeve (2) above it. After the first steel sleeve (2) is driven into the ground, a connector (4) is installed between the bottom steel sleeve (2) and the adjacent steel sleeve (2) above it. The two adjacent steel sleeves (2) are fixed by the connector (4) to prevent the adjacent steel sleeves (2) from becoming loose. S4: When the connector (4) extends to the position of the karst cave (5), the karst cave (5) is filled; Apply further pressure to the upper steel sleeve (2) in the same manner as S1 so that the connector (4) continues to move towards the lower part of the karst area (1); when the connector (4) applies downward pressure to the area of the karst cave (5), the karst cave (5) is filled. Filler material is placed into several different extension tubes (7), and the filler material is placed into the interior of the cave (5) through the extension tubes (7) and the filling tubes (6) in turn to fill the cave (5); S5: Further drive the steel casing (2) into the karst area (1); The steel casing (2) is further pressurized in the same manner as in S1 so that it is inserted to the specified depth on the ground. S6: Remove the soil from inside the steel casing (2); The soil inside several steel casings (2) was removed using a rotary drilling rig for subsequent reinforcement treatment; S7: Place a steel cage (10) inside several steel sleeves (2); After the soil inside the steel casing (2) is removed, a steel reinforcement frame (9) is placed inside several steel casings (2), and the steel reinforcement frame (9) is coaxially set with the steel casing (2); S7: Pour concrete into the interior of several steel sleeves (2); Concrete is poured into the interior of several steel sleeves (2). After the concrete and the reinforcing steel frame (9) have solidified, the operation is completed.
8. A construction method for a karst area cast-in-place pile structure according to claim 7: characterized in that: Before step S4, the bottom ends of several extension tubes (7) are sealed and connected to the top end of the filling tube (6) for subsequent filling; and the extension tubes (7) pass through several fixing sleeves (404) respectively, and the fixing sleeves (404) limit the position of the extension tubes (7).