Underwater pier construction method

By using ground anchors, horizontal steel strands, and vertical steel strands combined with through-hole jacks in underwater pier construction, the problems of low positioning accuracy and difficulty in controlling verticality in traditional underwater pier construction have been solved, achieving efficient and accurate pier positioning and improved construction safety.

CN123133374APending Publication Date: 2026-11-20SHANGHAI MECHANIZED CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611533434.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-30
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Traditional underwater pier construction suffers from low positioning accuracy, difficulty in controlling verticality, high construction costs, and low efficiency.

Method used

By using a combination of ground anchors, horizontal steel strands, and vertical steel strands with through-hole jacks, and by pre-excavating foundation trenches and using detection components and navigation equipment, the piers are actively sunk and precisely guided, ensuring that the piers land firmly on the flat cushion layer.

Benefits of technology

It significantly improved the positioning accuracy and verticality of the piers, reduced the sinking resistance, shortened the construction time, reduced costs, and improved construction safety and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133374A_ABST
    Figure CN123133374A_ABST
Patent Text Reader

Abstract

The application discloses a kind of underwater pier construction methods, comprising: preparation ground anchor, horizontal steel strand, vertical steel strand and pier, and horizontal through jack and vertical through jack are respectively arranged on the both sides of pier;Excavate base groove in sinking area, lay cushion on groove bottom;Ground anchor is sunk in base groove, horizontal steel strand is arranged on ground anchor, and the bottom end of vertical steel strand is fixed to ground anchor, and the top end is temporarily fixed to buoyancy device;Horizontal steel strand is inserted into horizontal through jack, and pier is driven to move horizontally to above base groove by horizontal through jack;Vertical steel strand is inserted into vertical through jack, and pier is sunk to cushion by vertical through jack;Pile foundation construction is carried out to the bottom of pier.During sinking process, jack and steel strand are cooperated to guide pier to move, ensure horizontal positioning accuracy and moving stability, and positioning accuracy of pier is greatly improved on the basis of pre-excavated base groove.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of underwater foundation construction technology, and in particular to a method for constructing underwater piers. Background Technology

[0002] Underwater concrete piers are crucial structures in deep-water foundations for bridges spanning rivers and seas, port terminals, and water intake projects. Traditional underwater pier construction often relies on crane vessels for lifting, which is limited by lifting capacity and is extremely expensive; or tugboats are used for towing, resulting in poor accuracy and a lack of active driving mechanisms, making precise positioning difficult. Furthermore, traditional sinking processes require piers to be sunk while simultaneously removing soil from the undisturbed soil, leading to high sinking resistance and slow speed. Uneven soil removal, uneven soil layers traversed by the pier, and uneven landing areas can all cause pier tilting, making correction difficult and affecting the stability of subsequent bridges, terminals, and other structures. Summary of the Invention

[0003] The purpose of this invention is to provide a method for constructing underwater piers, which effectively improves positioning accuracy and verticality.

[0004] To achieve this objective, the present invention adopts the following technical solution: a method for constructing underwater piers, comprising: Prepare ground anchors, horizontal steel strands, vertical steel strands, and supports. Set up horizontal and vertical through-hole jacks on each side of the supports. The ground anchors, vertical steel strands, and vertical through-hole jacks correspond one-to-one. Use dredging equipment to excavate foundation trenches in the sinking area, lay a cushion layer at the bottom of the trench and level it; The construction vessel is used to sink the ground anchor into the foundation trench. The horizontal steel strand is laid across the liquid surface above the ground anchor and anchored according to the design tension. The bottom end of the vertical steel strand is fixed to the ground anchor, and the top end is temporarily fixed to the buoyancy device. The horizontal steel strand is threaded into the horizontal through-hole jack and re-fixed. The support is then driven to move horizontally above the foundation trench by the horizontal through-hole jack. The vertical steel strand is threaded into the vertical through-hole jack and re-fixed, and the support is driven to sink into the cushion layer by the vertical through-hole jack; The bottom of the support pier is constructed with pile foundations.

[0005] Preferably, the support is equipped with a first detection component, and the step of driving the support horizontally to move it above the foundation trench using the horizontal through-hole jack includes the following steps: Obtain the current position of the support pier as detected by the first detection component; The speed of the horizontal through-hole jack is controlled according to the current position of the support to adjust the final position of the support.

[0006] Preferably, the step of using the vertical through-hole jack to drive the support pier into the cushion layer includes the following steps: Obtain the current posture of the support pier as detected by the first detection component; The speed of the vertical through-hole jacks on both sides is controlled according to the current posture of the support to adjust the final posture of the support.

[0007] Preferably, a tension displacement sensor is installed on the vertical steel strand, and a second detection component is installed on the ground anchor. The step of driving the pier to sink into the cushion layer by the vertical through-hole jack includes the following steps: Obtain the anchor position information detected by the second detection component, and establish anchor reference coordinates based on the anchor position information; The tension information and jack displacement information detected by the tension displacement sensor are obtained. The real-time position of the vertical through-hole jack is calculated based on the ground anchor reference coordinates and the jack displacement information. The current posture of the support is calculated based on the tension information and the real-time position of the vertical through-hole jack. The speed of the vertical through-hole jack is controlled according to the current posture of the support to adjust the final posture of the support.

[0008] Preferably, the dredging equipment is equipped with a navigation device and a depth sounder. The process of using the dredging equipment to excavate a foundation trench in the sinking area includes the following steps: obtaining the excavation position detected by the navigation device and the excavation depth detected by the depth sounder, and controlling the dredging equipment to excavate the foundation trench according to the excavation position and the excavation depth.

[0009] Preferably, in a projection plane parallel to the horizontal plane, the projection of the foundation trench is based on the projection of the support pier and extends outward by 1-2m through each side of the support pier.

[0010] Preferably, the base trench has a bucket-shaped shape with its inner diameter gradually decreasing from top to bottom.

[0011] Preferably, after the pile foundation construction is carried out on the bottom of the support, the following steps are also included: backfilling the gap between the support and the inner wall of the foundation trench.

[0012] Preferably, after backfilling the gap between the support and the inner wall of the foundation trench, the method further includes the following steps: disassembling the horizontal through-hole jack and the vertical through-hole jack.

[0013] Preferably, multiple vertical through-hole jacks are provided at intervals on the same side of the support pier.

[0014] The beneficial effects of this invention are as follows: Pre-excavation of the foundation trench before settlement solves the problem of uneven soil hardness causing pier tilt. The pier sinks within the uniform, low-resistance trench, requiring no soil removal from the hull or only a small amount of counterweight adjustment, significantly reducing sinking resistance and greatly improving sinking speed and stability. During the sinking process, the cooperation of horizontal through-hole jacks and horizontal steel strands, as well as vertical through-hole jacks and vertical steel strands, guides the movement of the pier, achieving continuous guidance and active drive for horizontal transportation and vertical sinking. This ensures horizontal positioning accuracy and movement stability, significantly improving pier positioning accuracy based on the pre-excavated foundation trench. Simultaneously, the pier rests on a flat cushion layer, effectively controlling the pier's bottom elevation accuracy and verticality, providing a reliable foundation for subsequent pile foundation construction. Attached Figure Description

[0015] Figure 1 This is a flowchart illustrating the steps of the underwater support pier construction method according to an embodiment of this application; Figure 2 This is a schematic diagram of the base trench according to an embodiment of this application; Figure 3 This is a top view of the support pier according to an embodiment of this application.

[0016] In the diagram: 1. Foundation trench; 11. Subbase; 2. Ground anchor; 3. Horizontal steel strand; 4. Vertical steel strand; 41. Buoyancy device; 5. Support pier; 51. Horizontal through-hole jack; 52. Vertical through-hole jack; 53. First detection component. Detailed Implementation

[0017] The present invention will now be described in further detail with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and not intended to limit it. Furthermore, it should be noted that, for ease of description, the accompanying drawings show only the parts relevant to the present invention, and not all of the structures.

[0018] In the description of this invention, unless otherwise explicitly specified and limited, the terms "connected," "linked," and "fixed" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.

[0019] In this invention, unless otherwise explicitly specified and limited, "above" or "below" the second feature can include direct contact between the first and second features, or contact between the first and second features through another feature between them. Furthermore, "above," "over," and "on top" of the second feature includes the first feature directly above or diagonally above the second feature, or simply indicates that the first feature is at a higher horizontal level than the second feature. "Below," "below," and "under" the second feature includes the first feature directly below or diagonally below the second feature, or simply indicates that the first feature is at a lower horizontal level than the second feature.

[0020] In the description of this embodiment, the terms "upper," "lower," "right," etc., refer to the orientation or positional relationship shown in the accompanying drawings. They are used only for ease of description and simplification of operation, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the present invention. In addition, the terms "first" and "second" are used only for distinction in description and have no special meaning.

[0021] Reference Figures 1 to 3 As shown, a construction method for an underwater support pier 5 according to an embodiment of this application includes: S1. Prepare ground anchor 2, horizontal steel strand 3, vertical steel strand 4 and support 5. Set up horizontal through jack 51 and vertical through jack 52 on each side of support 5. Ground anchor 2, vertical steel strand 4 and vertical through jack 52 correspond one-to-one. Specifically, in this embodiment, the ground anchor 2 is a helical anchor, and there are four ground anchors 2. There are two horizontal steel strands 3 and four vertical steel strands 4. The support pier 5 is symmetrically provided with two horizontal through-hole jacks 51 and four vertical through-hole jacks 52 on both sides in its width direction (that is, one horizontal through-hole jack 51 and two vertical through-hole jacks 52 are provided on each side).

[0022] S2. Use dredging equipment to excavate the foundation trench 1 in the sinking area according to the design elevation, and lay a sand or gravel or concrete cushion layer 11 at the bottom of the trench and level it. Alternatively, the dredging equipment may be a cutter suction / grab dredger.

[0023] S3. Use a construction vessel to sink the ground anchor 2 into the foundation trench 1, place the horizontal steel strand 3 across the liquid surface above the ground anchor 2 and anchor it according to the design tension, fix both ends of the horizontal steel strand 3 to the anchoring points on the shore (or dock side), fix the bottom end of the vertical steel strand 4 to the ground anchor 2, and temporarily fix the top end to the buoyancy device 41. Optionally, the buoyancy device 41 is a floating platform or a construction vessel.

[0024] S4. The support pier 5 is transported to the waters near the sinking area by means of airbag towing, floating dock transportation or floating crane lifting. The horizontal steel strand 3 is manually threaded into the horizontal through-hole jack 51 and re-fixed. The support pier 5 is driven to move horizontally above the foundation trench 1 by the horizontal through-hole jack 51. S5. After the support 5 reaches the top of the cushion layer 11, the vertical steel strand 4 is manually threaded into the vertical through-hole jack 52 and re-fixed. The support 5 is then driven to sink into the cushion layer 11 by the vertical through-hole jack 52. S6. Carry out pile foundation construction on the bottom of pier 5.

[0025] Specifically, the support 5 is sealed with a steel casing. The steel casing is equipped with a vertical underwater construction sleeve that passes through the support 5. After the support 5 reaches the bottom of the cushion layer 11, the water inside the support 5 can be drained through the steel casing to form a dry environment. Then, the steel casing is manually entered, and pile foundation construction equipment (such as a vibratory hammer or a grouting machine) is used to guide the pile foundation into the underwater construction sleeve and insert it into the ground below the support 5. After the pile foundation is installed, the steel casing is disassembled and retrieved.

[0026] Understandably, pre-excavating the foundation trench 1 before settlement transforms the traditional passive sinking method of removing soil while sinking into an active sinking method with controlled resistance within the pre-excavated foundation trench 1. This solves the problem of uneven soil hardness causing the support pier 5 to tilt. The support pier 5 sinks within the uniform, low-resistance foundation trench 1, requiring no soil removal from the chamber or only a small amount of counterweight adjustment, significantly reducing sinking resistance and greatly improving sinking speed and stability. During the sinking process, the cooperation of horizontal through-hole jacks 51 and horizontal steel strands 3, as well as vertical through-hole jacks 52 and vertical steel strands 4, guides the movement of the support pier 5, achieving continuous guidance and active drive for horizontal transportation and vertical sinking. This ensures horizontal positioning accuracy and movement stability, significantly improving the positioning accuracy of the support pier 5 based on the pre-excavated foundation trench 1. Simultaneously, the support pier 5 rests on the flat cushion layer 11, effectively controlling the accuracy of the support pier 5's bottom elevation and verticality, providing a reliable foundation for subsequent pile foundation construction. In addition, the ground anchor 2, the cushion layer 11, the horizontal steel strand 3 and the vertical steel strand 4 can be pre-arranged on the support 5 and then laid down for cable threading and sinking, eliminating the waiting time of the process, greatly shortening the on-site operation time, reducing the dependence on large-scale water hoisting equipment, reducing construction costs, and improving construction safety and efficiency.

[0027] Optionally, the support 5 is equipped with a first detection component 53, and step S4 includes: S41. Obtain the current position of the support 5 detected by the first detection component 53; Specifically, the first detection component 53 includes a transponder installed on the pier 5, an RTK / GNSS receiver installed on the top of the pier 5, an inertial navigation system (INS) installed inside the pier 5, a Doppler velocity meter (DVL) installed at the bottom of the pier 5, and multiple depth gauges installed on the outside of the pier 5. The transponder and the shipborne array on the construction vessel form an ultra-short baseline USBL. The first detection component 53 is signal-connected to a remote data fusion controller. The data fusion controller uses Kalman filtering to tightly couple and fuse various signals detected by the first detection component 53 to calculate the position (positioning information) and attitude (angle tilt information) of the pier 5. The data fusion controller is signal-connected to the horizontal through-hole jack 51 and the vertical through-hole jack 52 respectively to control the movement of the horizontal through-hole jack 51 and the vertical through-hole jack 52.

[0028] S42. Control the speed of the horizontal through-hole jack 51 according to the current position of the support 5 to adjust the final position of the support 5.

[0029] Specifically, during the horizontal movement of the support 5, the first detection component 53 detects and calculates the current position of the support 5 in real time, compares the detected current position information with the design position to calculate the position deviation, and controls the speed of the horizontal through-hole jack 51 according to the position deviation. When the deviation is large, the speed is increased, and when the deviation is small, the speed is decreased until the current position coincides with the design position (or the position deviation is within the design range). The support 5 is driven to translate along the horizontal steel strand 3 through the jack's push-back cycle action, so as to achieve precise horizontal positioning.

[0030] By cooperating with the first detection component 53 and the horizontal through-hole jack 51, the current position of the support 5 is obtained and adjusted in real time, realizing active closed-loop control in the horizontal transportation stage. This enables the support 5 to be accurately aligned with the top of the foundation trench 1 during the horizontal transportation stage, avoiding deviation caused by external interference such as water flow and waves. The horizontal positioning accuracy can reach ±5 centimeters, which is much more accurate than the ±0.5 meter accuracy of traditional tugboat towing.

[0031] Further, step S5 includes: S51. Obtain the current posture of the support 5 detected by the first detection component 53; Referring to the description of the first detection component 53 above, the data fusion controller can calculate the inclination angle of the pier 5 based on the detection signals from multiple depth gauges and the signal from the ultra-short baseline USBL, thereby determining the current posture of the pier 5.

[0032] S52. Control the speed of the vertical through-hole jacks 52 on both sides according to the current posture of the support 5 to adjust the final posture of the support 5.

[0033] Specifically, during the vertical sinking process, the first detection component 53 detects the current posture of the support 5 in real time, compares the detected posture information with the target posture to calculate the posture deviation, controls the speed of the vertical through-hole jacks 52 on both sides according to the posture deviation, and adjusts the tilt deviation by the stroke difference of each jack, so that the support 5 always maintains a stable posture during the sinking process.

[0034] By cooperating with the first detection component 53 and the vertical through-hole jack 52, the current posture of the support 5 is obtained and adjusted in real time, realizing active closed-loop control in the vertical settlement stage. This ensures that the support 5 maintains a stable posture during the vertical settlement stage, avoiding deviation caused by external interference such as water flow and waves. The verticality deviation can be controlled within 0.2 percent, greatly improving the verticality of the support 5 after it hits the bottom.

[0035] In some embodiments, a tension displacement sensor is installed on the vertical steel strand 4, and a second detection component is installed on the ground anchor 2. Step S5 further includes: S53. Obtain the position information of the ground anchor 2 detected by the second detection component, and establish the reference coordinates of the ground anchor 2 based on the position information of the ground anchor 2; The second detection component is installed on the ground anchor 2 to detect the position information of the ground anchor 2, including an RTK / GNSS receiver, a USBL transponder, a tilt sensor, etc., which will not be described in detail here.

[0036] S54. Obtain the tension information and jack displacement information detected by the tension displacement sensor. Calculate the real-time position of the vertical through-hole jack 52 based on the reference coordinates of the ground anchor 2 and the jack displacement information. Calculate the current posture of the support pier 5 based on the tension information and the real-time position of the vertical through-hole jack 52. The tension displacement sensor can be a combination of a force gauge and a wire encoder. The jack displacement information can be measured by a wire encoder or a laser displacement meter. Specifically, since the coordinates of the ground anchor 2 are known and fixed, the stroke of the vertical through-hole jack 52 along the vertical steel strand 4 corresponds to the vertical displacement of the support 5. Combined with the coordinates of the ground anchor 2, the absolute position of the support 5 and the position of each vertical through-hole jack 52 can be calculated. If the tension of the steel strand on a certain side of the support 5 is too large, it indicates that the load on that side is concentrated, and the support 5 tilts to that side; if the tension on a certain side of the support 5 decreases, it indicates that the side may have partially bottomed out or the jack may have slipped. By analyzing and calculating the positional relationship between the tension of different steel strands and the position of the vertical through-hole jack 52 according to the preset formula, the tilt direction and tilt angle of the support 5 can be obtained, and the current posture of the support 5 can be obtained from the electrode lug.

[0037] S55. Control the speed of the vertical through-hole jack 52 according to the current posture of the support 5 to adjust the final posture of the support 5.

[0038] By cooperating with the tension displacement sensor and the second detection component, a mechanical back-calculation path is established between the tension displacement data of the steel strand and the position and posture of the support 5. This path, combined with the multi-source fusion detection scheme of the first detection component 53, forms a dual verification. The reference coordinates of the ground anchor 2 provide an absolute reference for underwater multi-source fusion positioning, solving problems such as cumulative drift of the inertial navigation system and velocity integration error of the Doppler velocity meter. This ensures that the position calculation of the support 5 has absolute accuracy. The tension information directly reflects the load distribution and tilt state of the support 5, while the jack displacement information directly reflects the vertical displacement of the support 5. The combination of these two methods can back-calculate the current posture of the support 5, and is unaffected by factors such as acoustic propagation, water depth, and water temperature, resulting in high reliability. Step S5 uses two schemes to detect and calculate the position and posture of the support 5, and the results are mutually verified. When one path fails or the deviation exceeds the limit, the other path can still provide reliable data, significantly improving the fault tolerance and reliability of the system.

[0039] In some embodiments, the dredging equipment is equipped with a navigation device and a depth sounder. The navigation device can use an RTK / GNSS receiver to provide centimeter-level planar positioning accuracy. The depth sounder is used to detect the water depth in the excavation area in real time and calculate the bottom elevation of the trench. The dredging equipment is used to control the excavation trajectory and excavation depth based on the detection results. Step S2 includes the following steps: S21. Obtain the excavation location detected by the navigation device and the excavation depth detected by the depth sounder, and control the dredging equipment to excavate the foundation trench 1 according to the excavation location and excavation depth.

[0040] Specifically, during the excavation of trench 1, the navigation equipment monitors the planar position of the dredging equipment in real time, the depth sounder monitors the water depth in the excavation area in real time, and the dredging equipment controls the excavation trajectory and excavation depth according to the excavation position and excavation depth, so that the planar edge position and bottom elevation of trench 1 meet the design requirements.

[0041] By installing navigation equipment and depth sounders on the dredging equipment, precise control of the excavation process of trench 1 was achieved, enabling the dredging equipment to excavate strictly according to the design boundary line, avoiding over-excavation or under-excavation, ensuring that the planar dimensions of trench 1 meet the design requirements of support 5, and the bottom elevation deviation can be controlled within ±10 centimeters, providing a stable foundation for the subsequent laying of the cushion layer 11 and the bottoming of support 5, effectively ensuring the forming quality of trench 1.

[0042] In the projection plane parallel to the horizontal plane, the projection of the foundation trench 1 is based on the projection of the support 5, and is formed by extending outward by 1~2m through each side of the support 5.

[0043] Specifically, the planar dimensions of the foundation trench 1 are determined based on the planar dimensions of the support 5. The length of the foundation trench 1 is equal to the length of the support 5 plus 2 to 4 meters, and the width of the foundation trench 1 is equal to the width of the support 5 plus 2 to 4 meters. The dredging equipment excavates the foundation trench 1 according to these dimensions.

[0044] The planar dimensions of the foundation trench 1 are limited to extend 1 to 2 meters outward on each side of the outer contour of the support 5, providing sufficient operating space for the sinking of the support 5, avoiding collisions and friction between the support 5 and the sidewall of the foundation trench 1, ensuring the stability of the sinking process, and the extended area can provide space for the arrangement of the ground anchor 2 and the vertical steel strand 4, so that the ground anchor 2 and the vertical steel strand 4 can be arranged in the foundation trench 1 or the surrounding area outside the contour of the support 5, without being disturbed by the position occupied by the support 5, avoiding structural interference between the ground anchor 2 and the vertical steel strand 4 and the support 5, which would affect the positioning accuracy of the support 5.

[0045] Reference Figure 2 As shown, it can be understood that the outer shape of the foundation trench 1 is a bucket shape with the inner diameter gradually decreasing from top to bottom, that is, the longitudinal section of the foundation trench 1 is an inverted trapezoid or funnel shape.

[0046] By designing the foundation trench 1 in a bucket shape, the sloping sidewalls of the bucket-shaped foundation trench 1 are conducive to soil stability, reducing the risk of sidewall collapse after excavation and ensuring construction safety. Furthermore, the inclined sidewalls of the foundation trench 1 can guide the sinking of the supports 5. If the supports 5 experience slight misalignment during sinking, they can be naturally aligned by the slope, reducing the difficulty of correction. In addition, the smaller bottom dimension of the bucket-shaped foundation trench 1 reduces the amount of excavation at the bottom of the foundation trench 1 and the amount of subbase 11 laid, thus lowering construction costs.

[0047] In some embodiments, after step S6, the following steps are included: S7. Backfill the gap between the support 5 and the inner wall of the trench 1. The backfill material can be discrete solid materials such as sand, gravel, or pebbles, or grouting materials such as cement slurry or cement mortar, or a combination of solid materials and grouting materials, which will not be elaborated here.

[0048] After the pile foundation construction, the cavity gap on the outside of the support 5 is backfilled, forming an effective force transmission path between the support 5 and the sidewall of the foundation trench 1. The horizontal force borne by the support 5 can be transferred to the soil of the sidewall of the foundation trench 1 through the backfill material, improving the horizontal bearing capacity and overturning stability of the support 5. Furthermore, the backfill protects the sidewall of the support 5 and the connection between the pile foundation and the support 5, reducing underwater erosion and damage to the support 5 and extending the service life of the structure. It should be noted that in underwater environments with complex and intense water flow, a natural backfilling scheme can also be adopted, that is, natural backfilling is achieved by the water flow driving the sand and gravel near the support 5. This will not be elaborated further here.

[0049] Furthermore, following step S7, the following steps are included: S8. Disassemble the horizontal through-hole jack 51 and the vertical through-hole jack 52 (hereinafter referred to as jacks), and at the same time disassemble the vertical steel strand 4 and the horizontal steel strand 3 (hereinafter referred to as steel strands) corresponding to the jacks.

[0050] After backfilling is completed, the jacks and corresponding steel strands can be disassembled underwater by divers or through a pre-installed disassembly channel on pier 5. The disassembled jacks and steel strands can be reused at the next pier location, significantly reducing construction costs. The jacks can be modularly designed for quick assembly and disassembly. Similarly, the first sensor assembly on pier 5 and the second sensor assembly on ground anchor 2 can be designed as detachable structures for easy recycling after the construction of pier 5 is completed, further reducing construction costs.

[0051] It is understandable that, in the vertical direction, the depth of the foundation trench 1 is less than or equal to the total height of the support 5 and the cushion layer 11.

[0052] Specifically, before excavating foundation trench 1, the depth of foundation trench 1 can be determined based on the height of the support pier 5, the thickness of the cushion layer 11, the original mud surface elevation, and the designed sinking elevation. The excavation depth of foundation trench 1 from the original ground surface to the bottom of the trench (foundation trench 1 elevation) is less than or equal to the sum of the height of the support pier 5 and the thickness of the cushion layer 11. This ensures that after the support pier 5 is sunk to the cushion layer 11, the top of the support pier 5 can be exposed above the top of foundation trench 1 or flush with the top of foundation trench 1. This facilitates subsequent pile foundation construction, jack disassembly, and equipment turnover, and avoids construction difficulties caused by the support pier 5 being lower than the surrounding ground.

[0053] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the implementation of the present invention. Those skilled in the art will be able to make various obvious changes, readjustments, and substitutions without departing from the scope of protection of the present invention. It is neither necessary nor possible to exhaustively describe all embodiments here. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the claims of the present invention.

Claims

1. A method for constructing underwater piers, characterized in that, include: Prepare ground anchors (2), horizontal steel strands (3), vertical steel strands (4) and supports (5). On each side of the supports (5), set up horizontal through jacks (51) and vertical through jacks (52). The ground anchors (2), the vertical steel strands (4) and the vertical through jacks (52) correspond one-to-one. The foundation trench (1) is excavated in the sinking area using dredging equipment, and a cushion layer (11) is laid and leveled at the bottom of the trench; The construction vessel is used to sink the ground anchor (2) into the foundation trench (1), the horizontal steel strand (3) is laid across the liquid surface above the ground anchor (2) and anchored according to the design tension, the bottom end of the vertical steel strand (4) is fixed to the ground anchor (2), and the top end is temporarily fixed to the buoyancy device (41). The horizontal steel strand (3) is threaded into the horizontal through-hole jack (51) and re-fixed. The support (5) is then driven to move horizontally above the foundation trench (1) by the horizontal through-hole jack (51). The vertical steel strand (4) is threaded into the vertical through-hole jack (52) and re-fixed. The support (5) is driven to sink into the cushion layer (11) by the vertical through-hole jack (52). The bottom of the support pier (5) is constructed with pile foundation.

2. The underwater support construction method according to claim 1, characterized in that, The support (5) is equipped with a first detection component (53). The step of driving the support (5) horizontally above the foundation trench (1) by the horizontal through-hole jack (51) includes the following steps: Obtain the current position of the support (5) detected by the first detection component (53); The speed of the horizontal through-hole jack (51) is controlled according to the current position of the support (5) to adjust the final position of the support (5).

3. The underwater support pier construction method according to claim 2, characterized in that, The process of lowering the support (5) into the cushion layer (11) by driving the vertical through-hole jack (52) includes the following steps: Obtain the current posture of the support (5) detected by the first detection component (53); The speed of the vertical through-hole jacks (52) on both sides is controlled according to the current posture of the support (5) to adjust the final posture of the support (5).

4. The underwater support construction method according to claim 1 or 3, characterized in that, A tension displacement sensor is installed on the vertical steel strand (4), and a second detection component is installed on the ground anchor (2). The process of driving the support pier (5) to sink into the cushion layer (11) by the vertical through-hole jack (52) includes the following steps: Obtain the position information of the ground anchor (2) detected by the second detection component, and establish the reference coordinates of the ground anchor (2) based on the position information of the ground anchor (2); Acquire the tension information and jack displacement information detected by the tension displacement sensor, calculate the real-time position of the vertical through-hole jack (52) based on the reference coordinates of the ground anchor (2) and the jack displacement information, and calculate the current posture of the support pier (5) based on the tension information and the real-time position of the vertical through-hole jack (52). The speed of the vertical through-hole jack (52) is controlled according to the current posture of the support (5) to adjust the final posture of the support (5).

5. The underwater support construction method according to claim 1, characterized in that, The dredging equipment is equipped with a navigation device and a depth sounder. The process of using the dredging equipment to excavate a foundation trench (1) in the sinking area includes the following steps: obtaining the excavation position detected by the navigation device and the excavation depth detected by the depth sounder, and controlling the dredging equipment to excavate the foundation trench (1) according to the excavation position and the excavation depth.

6. The underwater support construction method according to claim 5, characterized in that, In a projection plane parallel to the horizontal plane, the projection of the foundation trench (1) is based on the projection of the support (5) and extends outward by 1~2m through each side of the support (5).

7. The underwater support construction method according to claim 5 or 6, characterized in that, The base trench (1) has a bucket-shaped shape with its inner diameter gradually decreasing from top to bottom.

8. The underwater support pier construction method according to claim 7, characterized in that, After the pile foundation construction is carried out on the bottom of the support (5), the following steps are also included: backfilling the gap between the support (5) and the inner wall of the foundation trench (1).

9. The underwater support construction method according to claim 8, characterized in that, After backfilling the gap between the support (5) and the inner wall of the foundation trench (1), the method further includes the following steps: disassembling the horizontal through-hole jack (51) and the vertical through-hole jack (52).

10. The underwater support construction method according to claim 5 or 6, characterized in that, In the vertical direction, the depth of the foundation trench (1) is less than or equal to the total height of the support (5) and the cushion layer (11).