Pressure water supply pipeline grading load transfer suspension system and protection construction method in deep foundation pit construction

The graded load transfer suspension system solves the problem of unstable transfer of loads on existing pressurized water supply pipelines during the excavation of deep foundation pits or shafts, and achieves closed-loop control and stability protection throughout the entire life cycle.

CN123133375APending Publication Date: 2026-11-20SHANGHAI FOUNDATION ENGINEERING GROUP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611464398.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-20
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

During the excavation of deep foundation pits or shafts, existing technologies are unable to smoothly transfer and unload the load of existing pressurized water supply pipelines, which can easily lead to local pressure, uneven stress at the lifting points, longitudinal deflection and lateral swaying of the pipelines, and lack closed-loop control throughout the entire life cycle.

Method used

A graded load transfer suspension system is adopted, including a support foundation, top beam, suspension unit and settlement monitoring point. Through multi-point support and flexible contact, the load is transferred segment by segment and level by level, and unloading is carried out in reverse before the permanent support is restored, forming a closed-loop control throughout the entire life cycle.

Benefits of technology

It enables the planned, adjustable, and traceable transfer of loads on existing pressurized water supply pipelines, reduces impact and local stress concentration, and ensures the safety and stability of the pipelines under conditions of uninterrupted water supply.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133375A_ABST
    Figure CN123133375A_ABST
Patent Text Reader

Abstract

The application discloses a kind of deep foundation pit construction existing pressure water supply pipeline grading load transfer suspension system and protection construction method, first in deep foundation pit both sides construction roof beam load-bearing foundation and set across roof beam, simultaneously stratified excavation and assemble enclosure structure;After excavation to pipeline center line, first excavate to pipe bottom in pipeline both sides and complete enclosure and grouting. Multiple lifting support positions are arranged along the length direction of pipeline, and are constructed point by point from both ends to the center, only one lifting support position is excavated each time and the adjacent soil body is retained, the bottom cross beam and vertical lifting component are immediately installed at the position, so that the pipeline load is transferred from the soil body to the suspension system point by point. After all lifting support units are closed, the remaining soil body is removed and the bottom cross beam is connected. During construction, the settlement of the pipeline and the roof beam and the construction vibration are monitored simultaneously;When backfilling, the vertical lifting component is cut off in stages and the roof beam is removed. The application can avoid the pipeline being suspended at one time, reduce the risk of local stress and uneven settlement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the fields of underground engineering construction, existing pipeline protection, and temporary structure construction technology. Specifically, it relates to a construction method for smoothly transferring an existing pressurized water supply pipeline in operation from its original soil bearing state to a cross-type multi-point suspension system bearing state during the excavation of a deep foundation pit or shaft, and for reverse graded unloading after the permanent support is restored. Background Technology

[0002] Construction of deep foundation pits, shafts, or underground structures often intersects with existing pressurized water supply pipelines. As the soil around the pipeline is gradually excavated, the original continuous foundation reaction force disappears, and the pipeline may become suspended, subject to the combined effects of its own weight, the weight of internal water, fluctuations in operating pressure, construction vibration, and support deformation. If one-time lifting, a small number of rigid lifting points, or temporary supports without feedback adjustment are used, it can easily lead to localized pressure, uneven stress on the lifting points, longitudinal deflection of the pipeline, joint cornering, and lateral swaying.

[0003] Existing measures typically emphasize the strength of the support structure, but rarely consider the excavation sequence, the loading process of the lifting points, the monitoring of pipeline posture, and the unloading process after backfilling as a closed-loop control object.

[0004] Existing related patent technologies, such as the existing pipeline protection system and method for deep foundation pits disclosed in patent document (CN121710103A), have significant technical blind spots in terms of dynamic spatiotemporal coupling, multi-objective collaborative optimization, and full life-cycle closed loop, which could lead to safety hazards in practical engineering applications. The controller in this patent is merely a "passive response" based on sensor feedback (i.e., detecting excessive settlement / stress and fine-tuning the hydraulic cylinder extension / retraction). Although the method mentions "excavating to the bottom of the pipeline" and "continuing excavation," the excavation sequence (a spatiotemporal variable) is not used as an input parameter for the control model. Deep foundation pit excavation is a continuous soil unloading process. Different excavation sequences can lead to asymmetry in the stress release of the soil on the pit sidewalls, resulting in uneven deformation of the soil around the pipeline. If only post-exposure feedback adjustment is relied upon, the hydraulic cylinder's action will always lag behind soil deformation, easily causing instantaneous changes in the load on the lifting point (i.e., the "whipping effect"). This patent does not incorporate "excavation sequence / working conditions" as a feedforward variable into the control model. Furthermore, it lacks a multi-objective collaborative optimization algorithm for the overall pipeline alignment (global attitude) and the stress on local lifting points. This patent isolates "protection" during the construction phase, failing to create a complete lifecycle closed loop of "excavation unloading and suspension - structural construction - backfilling and loading - collaborative unloading and recovery."

[0005] Therefore, a construction method is needed that can transfer the load segment by segment and level by level according to the excavation progress without interrupting water supply, and reduce the additional stress on the pipeline through multi-point support, flexible contact and condition verification. Summary of the Invention

[0006] The present invention provides a graded load transfer suspension system and protection construction method for existing pressurized water supply pipelines in deep foundation pit construction, which makes the pipeline load transfer process planable, adjustable, monitorable and traceable, reduces the impact and local stress concentration caused by the one-time loss of soil support, and smoothly restores the pipeline to the design support state after the permanent support is formed.

[0007] To achieve the above objectives, the present invention adopts the following technical solution: A graded load transfer suspension system for existing pressurized water supply pipelines during deep foundation pit construction includes: a supporting foundation set in the stable bearing zone on both sides of the deep foundation pit; at least two top crossbeams spanning the deep foundation pit and supported on the supporting foundation; multiple suspension units spaced apart along the length of the pipeline; and settlement monitoring points set on the main bearing beams and the pipeline. Each suspension unit includes vertical support channel steel located on both sides of the pipeline and connected to the top crossbeams, a bottom crossbeam connecting the two vertical support channel steels and located below the pipeline, an elastic buffer pad set between the pipeline and the bottom crossbeams and / or the vertical support channel steels, and longitudinal connecting steel bars connecting adjacent bottom crossbeams. Each suspension unit is immediately installed and closed after the soil at its corresponding position is removed, so that the load is transferred point by point according to spatial location.

[0008] Furthermore, the main load-bearing beam includes at least two H-shaped steel composite beams arranged in parallel, and the plurality of lifting units are distributed between or on both sides of the two steel beams; the main load-bearing beam is also provided with a connecting plate corresponding to the vertical lifting member, and stiffeners are provided between the vertical lifting member and the transverse support member; the plurality of vertical lifting members include channel steel members; the transverse support member includes a steel beam located below the pipeline.

[0009] Furthermore, the elastic buffer pad is provided at least at the bottom of the pipeline and on both sides of the pipeline.

[0010] Furthermore, the supporting foundation includes a concrete support slab disposed on undisturbed soil.

[0011] A method for graded load transfer and suspension protection of existing pressurized water supply pipelines during deep foundation pit construction, employing the aforementioned system, includes: measuring the axis of the existing pressurized water supply pipeline; excavating both sides of the deep foundation pit to the elevation of the top beam foundation; constructing the top beam load-bearing foundation and the top horizontal beam spanning the deep foundation pit; simultaneously excavating and assembling the deep foundation pit retaining structure in layers; after excavating to the depth of the existing pressurized water supply pipeline's centerline, excavating both sides of the pipeline to the pipe bottom depth and completing the corresponding retaining structure and grouting the gaps on the outer side of the retaining structure; setting multiple suspension positions along the pipeline length, and sequentially excavating from both ends of the pipeline towards the center at each suspension position, each time... The soil at only one support location is removed while the soil at adjacent support locations remains to support the pipeline. After excavation to the bottom of the pipe at each support location, a bottom crossbeam located below the pipeline and a vertical support member connecting the bottom crossbeam and the top crossbeam are immediately installed, transferring the pipeline load at that support location from the removed soil to the bottom crossbeam, the vertical support member, and the top crossbeam. After the support units at all support locations are installed, the remaining soil between adjacent support locations is excavated, and each bottom crossbeam is connected. Settlement monitoring of the top crossbeam and the existing pressurized water supply pipeline is conducted during continued deep excavation of the foundation pit, and construction vibration is also monitored.

[0012] Furthermore, the deep foundation pit retaining structure is a steel formwork well wall panel assembled layer by layer according to the excavation depth, and multiple steel walers are installed along the depth direction; the grouting of the over-excavated gaps on the outside of the retaining structure is completed after the pipeline is excavated to the bottom of the pipe on both sides and the corresponding retaining structure is completed, and before the lifting position is excavated point by point from both ends to the center.

[0013] Furthermore, the next support location is excavated only after each support unit is installed, so that the soil support area and the suspension support area along the length of the pipeline are alternately distributed and gradually replaced; after all support units are installed, longitudinal connecting steel bars are welded between adjacent bottom crossbeams.

[0014] Furthermore, the existing pressurized water supply pipeline will continue to operate during construction.

[0015] Furthermore, when the monitored value reaches the warning value, the cause is assessed and control measures are taken; when the monitored value reaches the alarm value, operations in the affected area are stopped and a response plan is developed.

[0016] Further, after the deep foundation pit is excavated downwards, backfill to the height of the pipeline centerline, retain the bottom crossbeam and longitudinal connecting steel bars, cut off the vertical supporting components, and then continue backfilling to the bottom of the top crossbeam and remove the top crossbeam.

[0017] Compared with the prior art, the present invention has the following significant advantages: 1. Establish a sequential correspondence between soil excavation and the load-bearing unit to reduce the impact caused by sudden loss of soil support.

[0018] 2. Employ multi-point support along the pipeline and alternating / symmetrical adjustment of adjacent points to reduce single-point overload and local curvature of the pipeline.

[0019] 3. Local compressive stress on the pipe wall is reduced by elastic buffer pads and a wider support area, and lateral movement is controlled by limiting components.

[0020] 4. Incorporate each stage of loading, attitude verification, anomaly handling, and reverse unloading into a closed loop to facilitate construction under conditions of uninterrupted water supply.

[0021] 5. The structural components can be adjusted according to pipe diameter, span and load, and are suitable for the construction of vertical shafts, deep foundation pits and underground structures. Attached Figure Description

[0022] Figure 1 This is a plan and longitudinal layout diagram of the suspension protection system of the present invention; Figure 2 This is a cross-sectional view of the suspension protection system of the present invention; Figure 3 Detailed drawings of the main beam, connecting plates, and vertical components; Figures 4-6 This is a diagram showing the relationship between the on-site circular shaft and the existing pipeline suspension system; Detailed Implementation The present invention will now be described in further detail with reference to the accompanying drawings and embodiments.

[0023] like Figures 1 to 6 As shown, the present invention provides a graded load transfer suspension system for existing pressurized water supply pipelines during deep foundation pit construction, comprising: a supporting foundation set in the stable bearing zone on both sides of the deep foundation pit; at least two top crossbeams spanning the deep foundation pit and supported on the supporting foundation; multiple lifting units spaced apart along the pipeline length direction; and settlement monitoring points set on the main beams and the pipeline; each lifting unit is immediately installed and closed after the soil at its corresponding position is removed, so that the load is transferred point by point according to spatial location.

[0024] Preferably, each support unit includes vertical support channels located on both sides of the pipeline and connected to the top crossbeam, a bottom crossbeam connecting the two vertical support channels and located below the pipeline, an elastic buffer pad disposed between the pipeline and the bottom crossbeam and / or the vertical support channels, and longitudinal connecting steel bars connecting adjacent bottom crossbeams.

[0025] Preferably, the main load-bearing beam includes two H-shaped steel composite beams, multiple vertical lifting components include channel steel components, and the transverse support components include steel beams located below the pipeline.

[0026] Preferably, the elastic buffer pad is provided at least at the bottom of the pipeline and on both sides of the pipeline.

[0027] Preferably, the supporting foundation includes a concrete support slab disposed on undisturbed soil.

[0028] Preferably, the main load-bearing beam is provided with a connecting plate corresponding to the vertical hanging member, and a stiffening member is provided between the vertical hanging member and the transverse support member.

[0029] This invention also provides a method for graded load transfer and suspension protection of existing pressurized water supply pipelines during deep foundation pit construction, the construction steps of which are as follows: S1. Measure and determine the axis of the 508 mm steel pipe and lay it out on the ground; excavate downwards to the elevation of the top beam foundation on both sides of the shaft, pour the bottom plate of the top beam load-bearing foundation and place the top crossbeam, and at the same time excavate downwards, assemble the liner plates well wall panels and install the steel walers.

[0030] S2. Continue excavating downwards and assembling the shaft retaining structure until the depth of the 508 mm steel pipe centerline is reached.

[0031] S3. First, excavate to the bottom depth on both sides of the steel pipe, assemble the corresponding liner plates, install the steel walers, and complete the grouting of the over-excavated voids outside the well wall.

[0032] S4. Divide the pipeline length into multiple local excavation positions corresponding to the bottom crossbeam, and construct from both ends of the pipeline toward the center in sequence; excavate only one position of the bottom crossbeam and vertical channel steel at a time, and retain the original soil support at adjacent positions.

[0033] S5. After reaching the bottom of the pipe at each excavation location, immediately install the bottom crossbeam, rubber pad, and vertical support channel steel on both sides, and connect the vertical channel steel to the top crossbeam to transfer the pipeline load at that location to the suspension system; only then can the next excavation location be moved on.

[0034] S6. After all vertical suspension units are installed and closed, excavate the remaining soil between adjacent suspension points and weld longitudinal connecting steel bars between the bottom crossbeams to form an overall constraint between the bottom crossbeams.

[0035] S7. Continue excavating the vertical shaft downwards. Vibration monitoring and settlement monitoring will be carried out simultaneously during construction, and the elevation of the top crossbeam and 508 mm steel pipe will be measured daily.

[0036] S8. When backfilling and dismantling, first backfill to the height of the 508 mm steel pipe centerline, retaining the bottom crossbeam and connecting steel bars; then cut off the vertical support channel steel by gas cutting; continue backfilling to the bottom of the top crossbeam and then remove the top crossbeam to complete the temporary suspension release. Specific implementation examples: Taking the circular shaft shown in the attached diagram as an example, the existing pipeline is a 508 mm outer diameter steel pipe with a built-in 450 mm DR11 HDPE water-carrying pipe, operated by EPCOR. During construction, it remains in place and is temporarily supported. The pipeline crosses the shaft, forming a protection zone of approximately 12 m. Approximately 500 mm thick concrete support slabs are installed on the stable soil on both sides of the shaft. The main load-bearing components are two H500×300×11×18 composite beams. Multiple sets of C150×19 vertical channel steels are installed along the pipeline direction, forming a suspension unit through S200×34 bottom crossbeams and connecting plates.

[0038] Rubber pads are placed between the pipeline and the supporting or lateral restraint components to prevent the metal components from directly pressing against the pipe wall, while also taking into account friction limiting and adapting to minor deformations. On-site photos show that the double main beams span the circular shaft, and multiple sets of vertical components connect downwards from the main beams to the supporting components below the pipeline, maintaining the continuity of the pipeline.

[0039] The structural calculations are based on a span of approximately 11,000 mm for the double main beams: the total dead load is approximately 4.35 kN / m, the live load is approximately 4.33 kN / m, the mid-span service load deflection is approximately 5.75 mm, and the third-point service load deflection is approximately 5.00 mm; the strength verification results in an actual load of approximately 13.02 kN / m, a bending moment of approximately 197 kN·m, and a shear force of approximately 71.5 kN. The pipeline loads used in the calculations include approximately 1.20 kN / m for 508 mm steel pipe, approximately 0.53 kN / m for 450 mm DR11 HDPE pipe, and approximately 1.60 kN / m for water inside the pipes.

[0040] Project monitoring response: The early warning value for settlement displacement at pipeline monitoring points is 12.5 mm, and the alarm value is 25 mm. If the early warning value is exceeded, the cause will be assessed and control measures will be taken, with a written record submitted to the construction unit / owner. If the alarm value is exceeded, work will be immediately suspended except for operations necessary to ensure safety, and a response plan will be developed in conjunction with the construction unit / owner. Settlement monitoring records during construction show that no settlement exceeding the early warning value was recorded.

Claims

1. A graded load transfer suspension system for existing pressurized water supply pipelines during deep foundation pit construction, characterized in that, include: The system includes a support foundation located in the stable bearing zone on both sides of the deep foundation pit, at least two top crossbeams spanning the deep foundation pit and supported on the support foundation, multiple hanging units spaced apart along the length of the pipeline, and settlement monitoring points set on the main bearing beam and the pipeline. Each hanging unit includes vertical bearing channel steel located on both sides of the pipeline and connected to the top crossbeam, a bottom crossbeam connecting the two vertical bearing channel steels and located below the pipeline, an elastic buffer pad set between the pipeline and the bottom crossbeam and / or the vertical bearing channel steel, and longitudinal connecting steel bars connecting adjacent bottom crossbeams. Each hanging unit is immediately installed and closed after the soil at its corresponding position is removed, so that the load is transferred point by point according to the spatial position.

2. The system according to claim 1, characterized in that, The main load-bearing beam includes at least two H-shaped steel composite beams arranged in parallel, and the plurality of lifting units are distributed between or on both sides of the two steel beams; the main load-bearing beam is also provided with a connecting plate corresponding to the vertical lifting member, and stiffeners are provided between the vertical lifting member and the transverse support member; the plurality of vertical lifting members include channel steel members; the transverse support member includes a steel beam located below the pipeline.

3. The system according to claim 1, characterized in that, The elastic buffer pads are provided at least at the bottom of the pipeline and on both sides of the pipeline.

4. The system according to claim 1, characterized in that, The supporting foundation includes a concrete support slab set on undisturbed soil.

5. A method for graded load transfer and suspension protection of existing pressurized water supply pipelines during deep foundation pit construction, employing the system described in any one of claims 1-4, characterized in that... include: The axis of the existing pressurized water supply pipeline was measured, and excavation was carried out on both sides of the deep foundation pit to the elevation of the top beam foundation. The load-bearing foundation of the top beam and the top horizontal beam spanning the deep foundation pit were constructed. At the same time, the deep foundation pit retaining structure was excavated and assembled in layers. After the excavation reached the depth of the centerline of the existing pressurized water supply pipeline, excavation was carried out on both sides of the pipeline to the depth of the bottom of the pipeline, and the corresponding retaining structure and the grouting of the voids on the outside of the retaining structure were completed. Multiple hanging positions were set along the length of the pipeline. Local excavation was carried out at each hanging position from both ends of the pipeline toward the center. At each time, only the soil at one hanging position was removed and the adjacent hanging positions were preserved. The soil supports the pipeline; after excavating to the bottom of the pipe at each support position, immediately install the bottom crossbeam located below the pipeline and the vertical support member connecting the bottom crossbeam and the top crossbeam, so that the pipeline load at that support position is transferred from the removed soil to the bottom crossbeam, the vertical support member and the top crossbeam; after the support units at all support positions are installed, excavate the remaining soil between adjacent support positions and connect each bottom crossbeam; and monitor the settlement of the top crossbeam and the existing pressurized water supply pipeline and the construction vibration during the continued excavation of the deep foundation pit.

6. The method according to claim 5, characterized in that, The deep foundation pit retaining structure consists of steel formwork well wall panels assembled layer by layer according to the excavation depth, and multiple steel walers are installed along the depth direction; the grouting of the over-excavated gaps on the outside of the retaining structure is completed after the pipeline is excavated to the bottom of the pipe on both sides and the corresponding retaining structure is completed, and before the lifting position is excavated point by point from both ends to the center.

7. The method according to claim 5, characterized in that, After each support unit is installed, the next support location is excavated, so that the soil support area and the suspension support area along the length of the pipeline are alternately distributed and gradually replaced; after all support units are installed, longitudinal connecting steel bars are welded between adjacent bottom crossbeams.

8. The method according to claim 5, characterized in that, The existing pressurized water supply pipeline will continue to operate during construction.

9. The method according to claim 5, characterized in that, When the monitored value reaches the warning value, the cause is assessed and control measures are taken. When the monitored value reaches the alarm value, operations in the affected area are stopped and a response plan is developed.

10. The method according to claim 5, characterized in that, After the deep foundation pit is excavated further downwards, backfill to the height of the pipeline centerline, retain the bottom crossbeam and longitudinal connecting steel bars, cut off the vertical supporting components, and then continue backfilling to the bottom of the top crossbeam and remove the top crossbeam.