Combined underpinning structure of profile steel and reinforced concrete piles

By adopting a combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles in foundation pit projects in the western loess region, the problems of high engineering cost and strength redundancy have been solved. This has enabled the recycling of materials and a significant reduction in construction costs, expanding the applicability of the construction method to foundation pit support in the western loess and northern hard soil regions.

CN123133376APending Publication Date: 2026-11-20CHINA CONSTR EIGHTH BUREAU NORTHWEST CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611267869.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-20
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

In deep foundation pit projects in the western loess region, conventional interlocking pile support methods suffer from high engineering costs, serious material waste, limited applicability, and redundant strength, making them particularly difficult to apply effectively in the hard soil areas of the north.

Method used

The structure employs a combination of steel-filled soil piles and reinforced concrete piles in an interlocking pile configuration. This involves setting multiple solid piles and pile units at intervals along the outline of the foundation pit. Each pile unit consists of three interlocking solid piles with a steel frame inserted into the middle solid pile. A cap beam is then poured on top of the pile unit. Positioning supports are used to control the position of the steel frame. The steel frame is inserted during construction and removed and recycled after the foundation pit is backfilled.

Benefits of technology

It significantly reduces engineering costs, enables material recycling, broadens the scope of application of construction methods, eliminates strength redundancy, reduces material costs, adapts to construction in hard soil strata, and achieves a balance between economy and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133376A_ABST
    Figure CN123133376A_ABST
Patent Text Reader

Abstract

The application discloses a combined bite pile supporting structure of profile steel fluid soil pile and reinforced concrete pile, which comprises a plurality of real piles, which are arranged at intervals along the contour line of a foundation pit; a plurality of pile units, the pile unit comprising three real piles which are sequentially bitten, the pile unit being arranged between two adjacent real piles, the first real pile of the pile unit being bitten with the last real pile, the last real pile of the pile unit being bitten with the next real pile, and the real piles being fluid solidified soil piles; and profile steel bones which are inserted into the middle real piles. The application solves the problems of high engineering cost and strength redundancy of conventional bite piles in the construction of deep foundation pit projects in western loess areas.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of foundation pit support structure technology, specifically to a combined interlocking pile support structure of steel flow soil piles and reinforced concrete piles. Background Technology

[0002] In deep foundation pit projects in the western Loess Plateau region, if the groundwater level is higher than the bottom of the pit, dewatering is necessary. To reduce the adverse effects of dewatering on the surrounding environment, such as uneven settlement and cracking, a support system using interlocking piles and anchor cables is typically chosen.

[0003] Interlocking piles are a type of support structure for deep foundation pits, serving the dual functions of seepage prevention and water stopping, as well as retaining soil support for the pit. Conventional interlocking piles (such as...) Figure 1 As shown, a continuous pile wall retaining structure is formed by alternating arrangements of one reinforced concrete pile 5 and one plain concrete pile 6.

[0004] However, the above-mentioned conventional interlocking pile support method has the following shortcomings in practical applications: Firstly, the engineering cost is relatively high. Conventional interlocking piles with reinforcing ribs are made of reinforced concrete. After the foundation pit is backfilled, these supporting piles are often buried and no longer used. The reinforced concrete material cannot be recycled, resulting in significant material waste. Plain concrete piles, on the other hand, present difficulties in cutting, further increasing construction costs.

[0005] Secondly, the applicability of SMW (Steel-Mounted Cement-Soil Mixing) piles is limited in hard soil areas of northern China. SMW piles offer advantages such as simple construction technology, economic reliability, and low environmental pollution. Furthermore, the steel sections can be removed and recycled after backfilling the foundation pit, significantly reducing construction costs. However, while this method is widely used in soft soil areas, its application in hard soil areas of northern China is still limited. Moreover, the standards and technical specifications are not yet fully developed, making direct promotion and application difficult.

[0006] Third, the loess strata in Northwest China have unique characteristics. The water and soil pressure in Northwest China is relatively low, and the conventional 1:1 arrangement of reinforced concrete piles and plain concrete piles in interlocking piles results in a certain strength redundancy in this region. This approach fails to fully consider the specific regional characteristics and therefore needs to be optimized, with economic efficiency needing improvement.

[0007] Therefore, it is necessary to improve the conventional interlocking pile support system based on the hydrogeological characteristics of the Loess Plateau in Northwest China, while ensuring that the support requirements and foundation pit deformation are within the permissible range of the specifications. The goal is to find an interlocking pile support system that can meet the support requirements, reduce engineering costs, and is suitable for application in hard soil areas in the north. Summary of the Invention

[0008] To overcome the shortcomings of existing technologies, a combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles is provided to solve the problems of high engineering cost and strength redundancy in the construction of deep foundation pits in the western loess region using conventional interlocking piles.

[0009] To achieve the above objectives, a combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles is provided, comprising: Multiple piles are spaced out along the outline of the foundation pit; Multiple pile units, each pile unit comprising three interlocking plain piles, wherein the pile unit is disposed between two adjacent plain piles, the first plain pile of the pile unit interlocks with the previous plain pile, and the last plain pile of the pile unit interlocks with the next plain pile, wherein the plain piles are fluidized solidified soil piles. The steel frame is inserted into the intermediate root pile.

[0010] Furthermore, a capping beam is cast on the top of the multiple pile units and the pile, and the steel frame passes through the capping beam and extends above the capping beam.

[0011] Furthermore, the top of each of the pile units is provided with a positioning bracket for limiting the position of the steel frame in the intermediate root pile.

[0012] Furthermore, the positioning bracket includes: Multiple spreader beams are provided, which are laid across the trench of the support structure and spaced apart along the length of the trench. Two support beams are arranged opposite each other, the support beams are laid on multiple spreader beams, and the two support beams are arranged on opposite sides of the trench; Multiple positioning units, each positioning unit including two opposing crossbeams laid on two supporting beams, with opposite sides of the two crossbeams extending in opposite directions to form limiting rods, and the limiting rods on the two crossbeams respectively abutting against opposite sides of the steel frame.

[0013] Furthermore, the steel frame is an I-beam, and two limiting rods are formed on one side of the crossbeam. The limiting rods on the two crossbeams abut against the opposite sides of the web of the steel frame, and the two limiting rods abut against the inner sides of the flanges on the opposite sides of the web.

[0014] This invention provides a construction method for a combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles, comprising the following steps: Multiple pile units are constructed at intervals along the outline of the foundation pit. Three interlocking plain piles are constructed at the pile position of each pile unit. The three plain piles are arranged along the length direction of the outline of the foundation pit. During the construction of each pile unit, steel frame is inserted into the intermediate root pile of the pile unit; Construct a pile between two adjacent pile units, such that one side of the pile engages with the last pile of the previous pile unit, and the other side of the pile engages with the first pile of the next pile unit.

[0015] Furthermore, before the step of inserting the steel frame into the intermediate root pile of the pile unit, a positioning bracket is installed on the top of the plurality of pile units. After the steel frame is inserted into the intermediate root pile of the pile unit, the positioning bracket restricts the position of the steel frame in the intermediate root pile.

[0016] Furthermore, after the pile unit is solidified, the positioning bracket is removed and a capping beam is poured on top of the multiple pile units and the pile, so that the upper end of the steel frame passes through the capping beam and extends above the capping beam.

[0017] The beneficial effects of this invention are that the combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles significantly reduces engineering costs and achieves material recycling. This invention uses steel reinforcement + fluidized solidified soil piles to replace some of the reinforced concrete piles (non-concrete piles), greatly reducing the number of non-concrete piles while meeting the stress requirements of the support structure. Simultaneously, the steel reinforcement can be removed and recycled after backfilling the foundation pit, eliminating underground obstacles; the steel recycling rate is generally up to 100%, significantly reducing material costs. Furthermore, the fluidized solidified soil can be prepared using excavated loess, further reducing material procurement costs and significantly lowering the overall project cost.

[0018] The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles of this invention breaks through the bottleneck of construction in hard soil strata and broadens the scope of application of the construction method. This combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles adopts a construction method of pre-drilling holes, grouting fluidized solidified soil, and then inserting steel sections. It is not limited by hard strata such as old clay and soft rock, and can achieve a structurally stable foundation pit support structure in hard soil areas, successfully overcoming the applicability limitations of the SMW method in hard soil areas of northern China.

[0019] The combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles of this invention is specifically optimized for support structures in loess areas, eliminating strength redundancy. This combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles is specifically optimized for the hydrogeological characteristics of the western loess region. It adopts an alternating arrangement of "three plain piles + one solid pile," with only the middle plain pile having a steel frame inserted, making the structural stress more rational. While ensuring support requirements and controlling foundation pit deformation within the permissible range of specifications, it eliminates unnecessary strength redundancy, achieving a balance between economy and safety. Attached Figure Description

[0020] Other features, objects, and advantages of this application will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings: Figure 1 This is a schematic diagram of the interlocking post structure in the prior art.

[0021] Figure 2 This is a schematic diagram of the combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles according to an embodiment of the present invention.

[0022] Figure 3 This is a schematic diagram of the positioning bracket according to an embodiment of the present invention.

[0023] Figure label: Meat pile 1; Pile unit 2, plain pile 21; 3. Steel frame, 31. Web plate, 32. Positioning bracket 4, spreader beam 41, support beam 42, positioning unit 43, crossbeam 431, limiting rod 432; 5 reinforced concrete piles; Plain concrete pile 6. Detailed Implementation

[0024] The present application will now be described in further detail with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and not intended to limit it. Furthermore, it should be noted that, for ease of description, only the parts relevant to the invention are shown in the accompanying drawings.

[0025] It should be noted that, unless otherwise specified, the embodiments and features described in this application can be combined with each other. This application will now be described in detail with reference to the accompanying drawings and embodiments.

[0026] Reference Figure 2 and Figure 3 As shown, the present invention provides a combined interlocking pile support structure of steel-filled soil pile and reinforced concrete pile, including: a pile 1, a pile unit 2 and a steel frame 3.

[0027] In this embodiment, multiple piles 1 and multiple pile units 2 are alternately arranged along the length of the outline of the foundation pit.

[0028] The pile unit 2 comprises three interlocking plain piles 21. The pile unit 2 is positioned between two adjacent plain piles 1. The first plain pile 21 of the pile unit 2 interlocks with the preceding plain pile 1. The last plain pile 21 of the pile unit 2 interlocks with the next plain pile 1. The plain piles 21 are fluidized solidified soil piles.

[0029] The steel frame 3 is inserted into the intermediate root pile 21.

[0030] In a preferred embodiment, a capping beam is cast atop multiple pile units 2 and pile 1. A steel frame 3 penetrates the capping beam and extends above it.

[0031] In this embodiment, the top of the multiple pile units 2 is provided with a positioning bracket 4 for restricting the position of the steel frame 3 in the intermediate root pile 21.

[0032] Specifically, the positioning bracket 4 includes: a spreader beam 41, a support beam 42, and a positioning unit 43.

[0033] In this embodiment, refer to Figure 3 As shown, there are multiple spreader beams 41. Each spreader beam 41 is positioned across the trench of the support structure. The trench is set along the outline of the foundation pit. Multiple spreader beams 41 are spaced apart along the length of the trench. Each spreader beam is set along the width of the trench. The two ends of each spreader beam rest on the foundation on opposite sides of the trench. Multiple spreader beams are spaced apart along the length of the trench.

[0034] There are two support beams. The two support beams 42 are arranged opposite each other. The support beams 42 are laid on one end of the multiple spreader beams 41. The two support beams 42 are arranged on opposite sides of the trench.

[0035] The number of positioning units 43 is adapted to the number of steel frame members. Specifically, the positioning unit 43 includes a crossbeam 431 and a limiting rod 432.

[0036] The two crossbeams 431 are arranged opposite each other. The crossbeams and the spreader beams are arranged in the same direction. The crossbeams are located above the support beams, while the spreader beams are located below the support beams. The crossbeams 431 are laid on the two support beams 42.

[0037] The two crossbeams 431 extend in opposite directions to form limiting rods 432. The limiting rods 432 on the two crossbeams 431 abut against the opposite sides of the steel frame 3.

[0038] In this embodiment, the steel frame 3 is an I-beam. The steel frame includes a web and flanges. Flanges are formed on opposite sides of the web. The flanges are perpendicular to the web. The web is centrally located in the middle of the flanges.

[0039] Two limiting rods 432 are formed on one side of the crossbeam 431. The limiting rods 432 on the two crossbeams 431 abut against the opposite sides of the web plate 31 of the steel frame 3. The two limiting rods 432 abut against the inner sides of the flange plates 32 on the opposite sides of the web plate 31.

[0040] The first distance between the two limiting rods on each crossbeam is adapted to the distance between the two flange plates of the steel frame. The second distance between the limiting rods on the two crossbeams is adapted to the thickness of the web plate of the steel frame.

[0041] During the construction of the pile unit, steel reinforcement is inserted before the initial setting of the fluidized solidified soil in the intermediate root pile. Before inserting the steel reinforcement into the intermediate root pile, its flatness is checked to ensure smooth insertion. After the steel reinforcement is lifted, its verticality is adjusted with a weight to meet the verticality requirements before insertion. The top elevation of the steel reinforcement is controlled using a level to ensure the insertion depth. The steel reinforcement is inserted downwards into the fluidized solidified soil of the intermediate root pile through the space between the limiting rods of the two crossbeams. The upper elevation of the steel reinforcement is higher than the top elevation of the capping beam. Subsequently, the steel reinforcement is pulled out from the root pile.

[0042] To reduce project costs while ensuring the structural integrity of the support structure, a combination of steel profiles and fluidized soil piles is used to replace some of the reinforced concrete piles (non-concrete piles). The steel profiles can be removed and recycled after backfilling following the completion of the underground structure construction, eliminating underground obstacles while simultaneously reducing project costs and achieving optimal economic efficiency. During construction, auxiliary measures are employed to ensure construction progress and verticality, reducing the difficulty of recycling. This technology can significantly reduce project costs and has broad application prospects.

[0043] During construction, multiple spreader beams are first placed perpendicular to the length of the trench. Then, positioning units are made according to the dimensions of the steel profiles to ensure the verticality of the steel profile insertion. Next, two support beams, approximately 8–20 m long, are placed parallel to the trench. The positioning of the steel profiles is achieved using positioning units.

[0044] This invention provides a construction method for a combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles, comprising the following steps: S1. Multiple pile units 2 are constructed at intervals along the outline of the foundation pit. Three interlocking plain piles 21 are constructed at the pile position of each pile unit 2. The three plain piles 21 are set along the length direction of the outline of the foundation pit.

[0045] Before constructing the pile units, survey and lay out the outline of the foundation pit to determine the planar position of each solid and plain pile. The allowable deviation of the pile position should not exceed ±20 mm. Excavate the guide wall trench along the pile position line and pour reinforced concrete guide walls. The top surface of the guide wall should be level, serving as a benchmark for drilling rig positioning and pile top elevation control. The net width of the guide wall should be 40–60 mm larger than the pile diameter, and the centerline of the guide wall should coincide with the pile position axis with a deviation of less than 10 mm.

[0046] During the construction of pile units, multiple pile units are spaced apart along the length of the foundation pit outline. Each pile unit contains three interlocking plain piles, and the specific construction is as follows: Hole Formation: Dry drilling or mud-wall drilling is performed using rotary drilling rigs or long spiral drilling rigs. Dry drilling is preferred in loess areas, while mud-wall drilling is used if the groundwater level is high. The verticality of the pile is monitored in real time using a theodolite or ultrasonic borehole gauge.

[0047] Preparation and grouting of fluidized solidified soil: Soil (which can be excavated loess), cement (the dosage is determined according to the design strength, generally 8%–15% of the soil mass), water, and admixtures (such as early-strength agents and water-reducing agents) are thoroughly mixed in a mixing plant according to the mix proportion to form fluidized solidified soil. The slump is controlled at 180–220 mm, and the fluidity meets pumping requirements. The fluidized solidified soil is continuously grouted into the pile hole in one go using either the tremie method or pumping method. The top elevation of the grouting surface should be 300–500 mm higher than the design pile top elevation to ensure that the pile strength meets requirements after the laitance at the pile top is removed. Interruptions should be prevented during grouting to ensure the integrity of the pile body.

[0048] Interlocking formation: The three plain piles in each pile unit are constructed sequentially, and the later-constructed plain pile interlocks with the adjacent plain pile constructed earlier through cutting or ultra-retarded setting. Preferably, the two side piles are constructed first, and the middle plain pile is constructed before the initial setting of its fluidized solidified soil (the initial setting time is extended to 48-72 hours by using an ultra-retarder). The sidewalls of the adjacent side piles are cut with a drill bit to form an effective interlocking width.

[0049] In this step, three plain piles are arranged continuously along the length of the foundation pit outline, and the center distance between adjacent plain piles is determined according to the pile diameter and the amount of interlocking.

[0050] S2. When constructing each pile unit 2, insert the steel frame 3 into the middle root pile 21 of the pile unit 2.

[0051] Before the step of inserting the steel frame 3 into the intermediate root pile 21 of the pile unit 2, a positioning bracket 4 is installed on the top of the pile unit 2. After the steel frame 3 is inserted into the intermediate root pile 21 of the pile unit 2, the positioning bracket 4 restricts the position of the steel frame 3 in the intermediate root pile 21.

[0052] After all three plain piles of the pile unit have been poured, the steel frame will be inserted immediately, as follows: Positioning bracket installation: At the top of the trench in the construction section, multiple spreader beams (using I-beams or channel steel) are laid perpendicular to the length of the trench. The ends of the spreader beams rest on solid ground on both sides of the trench, spaced 1.5–2.0 m apart. Two parallel support beams (using square steel or I-beams) are installed on the spreader beams along the length of the trench, located on both sides of the trench, to support the positioning units. Then, the positioning units are installed according to the designed steel section positions. Each positioning unit consists of a pair of crossbeams placed on the support beams. Two limiting rods (using round steel or angle steel) are welded to opposite sides of the two crossbeams. The space formed by the limiting rods on the two crossbeams precisely accommodates the web and flanges of the I-beam. During installation, a spirit level and a horizontal level are used to adjust the elevation of the crossbeams, ensuring that the bottom elevation of the limiting rods matches the top elevation of the designed steel section.

[0053] Steel frame preparation and verticality control: The steel frame uses I-beams, made of Q235B or Q345B. Upon arrival, its straightness is checked, with a bending degree not exceeding 1 / 1000 and a total bending degree not exceeding 10 mm. When the steel frame is welded in sections, full penetration welding with a bevel is used, and the weld quality grade is level II. Ultrasonic testing is performed on random samples according to specifications. A friction-reducing agent (such as graphite grease) is applied to the surface of the steel frame to facilitate later extraction and recycling.

[0054] Inserting the steel section: The steel section is vertically lifted using a crane. Two theodolites are used to observe the verticality of the steel section in mutually perpendicular directions. The verticality deviation is kept less than 1 / 300 by adjusting the lifting points or adding counterweights. The lower end of the steel section is aligned with the guide hole of the positioning unit's limiting rod and slowly lowered using its own weight. If resistance is encountered, a vibratory hammer or static pressure device can be used. During the lowering process, the top elevation of the steel section is monitored with a level, ensuring that its top is at least 500 mm above the designed top surface of the capping beam (to ensure that the exposed length after the capping beam construction meets the removal requirements). After the steel section is inserted into place, the web and flange of the steel section are clamped using the limiting rod of the positioning bracket to prevent it from tilting or sinking. After insertion, the deviation between the centerline of the steel section and the centerline of the pile position is checked and should not exceed 20 mm.

[0055] S3. Construct a bare pile 1 between two adjacent pile units 2, such that one side of the bare pile 1 engages with the last bare pile 21 of the previous pile unit 2, and the other side of the bare pile 1 engages with the first bare pile 21 of the next pile unit 2.

[0056] After the solidified soil in each pile unit reaches a certain strength (usually more than 30% of the design strength, approximately 3-5 days), the concrete piles are constructed. These concrete piles are reinforced concrete piles and are arranged between adjacent pile units. Specific procedures are as follows: Hole Formation and Interlocking: A rotary drilling rig is used to form holes at the pre-designated pile locations. During drilling, the sidewalls of the last and first plain piles of adjacent pile units need to be cut to form an interlocking surface. The interlocking width between the plain and hard piles should be no less than 200 mm, and the interlocking surface should be continuous and free of mud. Mud slurry is used for wall protection during hole formation; the mud slurry properties are the same as those required for the plain piles.

[0057] Reinforcing cage fabrication and lowering: The reinforcing cage is fabricated according to the design reinforcement, using HRB400 grade main reinforcement and HPB300 grade stirrups. The reinforcing cage is fabricated in sections, with joints connected using straight threaded sleeves. The percentage of joint area at the same cross-section should not exceed 50%. The protective layer thickness of the reinforcing cage is as designed (generally not less than 50 mm), controlled using concrete spacers. The reinforcing cage is hoisted into the borehole, aligned with the center, and slowly lowered to avoid collision with the borehole wall. After lowering, the top elevation of the cage is fixed.

[0058] Concrete pouring: Underwater concrete is poured using the tremie pipe method, and the concrete strength grade meets the design requirements. The initial pouring volume should ensure that the tremie pipe is buried at a depth of not less than 1.0 m. The pouring process is continuous, with the tremie pipe buried at a depth of 2–6 m. The concrete is poured to a depth of 0.5–1.0 m above the design pile top elevation, ensuring that fresh concrete is exposed after the laitance layer is removed.

[0059] S4. After the pile unit 2 is cured, the positioning bracket 4 is removed and the capping beam is poured on top of multiple pile units 2 and pile 1, so that the upper end of the steel frame 3 passes through the capping beam and extends above the capping beam.

[0060] After all pile units and pile concrete have reached more than 70% of their design strength (generally cured for 7-14 days), the capping beam construction can proceed. Remove the laitance from the top of the piles: chisel away the laitance layer from the top of each pile down to the design elevation to expose solid concrete or solidified soil. The top of the piles should be flat.

[0061] Remove the positioning supports: Remove the crossbeams, support beams, and spreader beams in sequence, taking care not to disturb the steel frame. After removal, check the position and verticality of the steel frame; if there is any slight deviation, it should be corrected before the cap beam is poured.

[0062] Binding the capping beam reinforcement and setting up the formwork: Bind the capping beam reinforcement along the outline of the foundation pit at the top of the piles. Weld or sleeve connections are used at the intersections of the reinforcement and the steel frame to ensure that the steel frame and the capping beam form an integral whole. Wooden or steel formwork is used for the side forms, ensuring they are firmly reinforced.

[0063] Pouring the capping beam concrete: The capping beam concrete should be poured continuously in one go. During the pouring process, ensure that the upper end of the steel frame penetrates through the capping beam and extends above the top surface of the capping beam by at least the designed exposed length to facilitate subsequent steel frame removal. The top surface of the capping beam should be smoothed, with an elevation error of ±10 mm. Curing should last at least 7 days. Once the capping beam reaches its design strength, foundation pit excavation and subsequent support work can proceed.

[0064] The 28-day unconfined compressive strength of the solidified soil for plain piles should meet the design requirements (generally ≥1.5 MPa), and the concrete strength of solid piles should be determined by taking test specimens according to the specifications.

[0065] The insertion depth, top elevation, and verticality of the steel frame must be checked and recorded.

[0066] The interlocking pile wall should be continuous and leak-free. The interlocking effect can be verified by excavation inspection or core sampling.

[0067] The removal of the steel frame should be carried out after the foundation pit has been backfilled and compacted, using a special pile puller. Before removal, the connection between the steel frame and the cap beam should be cut and separated.

[0068] By implementing the above detailed steps, the construction quality of the combined interlocking pile support structure of steel-filled soil piles and reinforced concrete piles can be effectively guaranteed, the project cost can be reduced, and the special conditions of deep foundation pit projects in the western loess region can be adapted.

[0069] The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles of this invention significantly reduces engineering costs and achieves material recycling. Conventional interlocking piles use an alternating arrangement of one reinforced concrete pile (hard pile) and one plain concrete pile. The horizontal resistance of the foundation pit is mainly borne by the hard pile, while the plain pile is primarily used to form a continuous retaining wall. This arrangement doubles the amount of concrete used, resulting in higher costs. The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles of this invention uses steel reinforcement + fluidized solidified soil piles to replace part of the reinforced concrete piles (hard piles), significantly reducing the number of hard piles while still meeting the load-bearing requirements of the support structure. Simultaneously, the steel reinforcement can be removed and recycled after backfilling the foundation pit, eliminating underground obstacles. The steel recycling rate is generally up to 100%, significantly reducing material costs. Furthermore, the fluidized solidified soil can be prepared using excavated loess on-site, further reducing material procurement costs and significantly lowering the overall project cost.

[0070] The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles of this invention overcomes the bottleneck of construction in hard soil strata and broadens the scope of application of the construction method. Although the SMW method pile (steel-cement-soil mixing wall) has advantages such as simple construction process, economic reliability, and low environmental pollution, its application in hard soil areas in the north is still limited. The main reason is that conventional cement-soil mixing pile machines cannot drill into hard soil layers, and the triaxial mixer equipment is large and heavy, requiring high site conditions, and the specifications and technical regulations are not yet perfect. The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles of this invention adopts a construction method of pre-drilling holes, grouting fluidized solidified soil, and then inserting steel. It is not limited by hard strata such as old clay and soft rock, and can obtain a structurally stable foundation pit support structure in hard soil areas, successfully overcoming the applicability limitations of the SMW method in hard soil areas in the north.

[0071] The profile steel fluid soil pile and reinforced concrete pile combined occlusal pile support structure of the present invention is purposefully optimized for the support structure in loess areas to eliminate strength redundancy. In the northwest loess area, the water and earth pressure is relatively low, and the 1:1 arrangement of conventional occlusal piles has certain strength redundancy in this area. The profile steel fluid soil pile and reinforced concrete pile combined occlusal pile support structure of the present invention is purposefully optimized for the hydrogeological characteristics of the western loess area, adopting an alternating arrangement mode of "three plain piles + one reinforced pile". Among the three plain piles, profile steel reinforcement is only inserted into the middle plain pile, which makes the stress of the structure more reasonable. On the premise of ensuring the support requirements and controlling the deformation of the foundation pit within the allowable range of the specifications, unnecessary strength redundancy is eliminated, and the unity of economy and safety is realized.

[0072] The profile steel fluid soil pile and reinforced concrete pile combined occlusal pile support structure of the present invention can consume engineering muck to prepare fluid solidified soil during the construction process, reducing the environmental burden caused by the outward transportation of abandoned soil. The profile steel reinforcement can be recycled and reused, avoiding material waste caused by the reinforced concrete piles being buried underground. At the same time, compared with traditional plain concrete piles, fluid solidified soil piles consume less cement and have lower carbon emissions, with significant advantages in low-carbon economy and environmental protection.

[0073] The profile steel fluid soil pile and reinforced concrete pile combined occlusal pile support structure of the present invention is convenient in construction and easy in quality control. The fluid solidified soil has the advantages of high strength, good fluidity, fast construction speed, good stability, good impermeability and the like. The plain piles are poured at one time with fluid solidified soil, and the overall pile forming quality is reliable. The positioning support matched with the profile steel fluid soil pile and reinforced concrete pile combined occlusal pile support structure of the present invention has a simple structure and is convenient to disassemble and assemble, which can effectively control the insertion perpendicularity and top elevation of the profile steel reinforcement and ensure the construction accuracy. Compared with the problem of difficult cutting of plain concrete piles in conventional occlusal pile construction, fluid solidified soil piles are easier for later occlusal construction, which reduces the construction difficulty.

[0074] In conclusion, on the premise of ensuring the safety of foundation pit support, the profile steel fluid soil pile and reinforced concrete pile combined occlusal pile support structure of the present invention achieves multiple beneficial effects such as cost reduction, expanded application scope, optimized structural arrangement, and green environmental protection, and is particularly suitable for popularization and application in foundation pit projects with large depth in the western loess area.

[0075] The above description is only a preferred embodiment of the present application and an illustration of the applied technical principles. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solutions formed by the specific combination of the above technical features, and should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, a technical solution formed by mutually replacing the above features with (but not limited to) technical features disclosed in the present application that have similar functions.

Claims

1. A combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles, characterized in that, include: Multiple piles are spaced out along the outline of the foundation pit; Multiple pile units, each pile unit comprising three interlocking plain piles, wherein the pile unit is disposed between two adjacent plain piles, the first plain pile of the pile unit interlocks with the previous plain pile, and the last plain pile of the pile unit interlocks with the next plain pile, wherein the plain piles are fluidized solidified soil piles. The steel frame is inserted into the intermediate root pile.

2. The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles according to claim 1, characterized in that, A capping beam is cast on the top of the multiple pile units and the piles, and the steel frame passes through the capping beam and extends above the capping beam.

3. The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles according to claim 2, characterized in that, The top of each of the pile units is provided with a positioning bracket for limiting the position of the steel frame in the intermediate root pile.

4. The combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles according to claim 3, characterized in that, The positioning bracket includes: Multiple spreader beams are provided, which are laid across the trench of the support structure and spaced apart along the length of the trench. Two support beams are arranged opposite each other, the support beams are laid on multiple spreader beams, and the two support beams are arranged on opposite sides of the trench; Multiple positioning units, each positioning unit including two opposing crossbeams laid on two supporting beams, with opposite sides of the two crossbeams extending in opposite directions to form limiting rods, and the limiting rods on the two crossbeams respectively abutting against opposite sides of the steel frame.

5. The combined interlocking pile support structure of steel-reinforced fluid soil piles and reinforced concrete piles according to claim 4, characterized in that, The steel frame is an I-beam, and two limiting rods are formed on one side of the crossbeam. The limiting rods on the two crossbeams abut against the opposite sides of the web of the steel frame, and the two limiting rods abut against the inner sides of the flanges on the opposite sides of the web.

6. A construction method for a combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles as described in any one of claims 1 to 5, characterized in that, Includes the following steps: Multiple pile units are constructed at intervals along the outline of the foundation pit. Three interlocking plain piles are constructed at the pile position of each pile unit. The three plain piles are arranged along the length direction of the outline of the foundation pit. During the construction of each pile unit, steel frame is inserted into the intermediate root pile of the pile unit; Construct a pile between two adjacent pile units, such that one side of the pile engages with the last pile of the previous pile unit, and the other side of the pile engages with the first pile of the next pile unit.

7. The construction method of the combined interlocking pile support structure of steel-framed fluidized soil piles and reinforced concrete piles according to claim 6, characterized in that, Before the step of inserting the steel frame into the intermediate root pile of the pile unit, a positioning bracket is installed on the top of the pile units. After the steel frame is inserted into the intermediate root pile of the pile unit, the positioning bracket restricts the position of the steel frame in the intermediate root pile.

8. The construction method of the combined interlocking pile support structure of steel-reinforced fluid soil piles and reinforced concrete piles according to claim 7, characterized in that, After the pile unit is cured, the positioning bracket is removed and a capping beam is poured on top of the pile units and the pile, so that the upper end of the steel frame passes through the capping beam and extends above the capping beam.