A dynamic sounding detection device and method for ultra-deep stone piles
By using a dynamic penetration testing device and a segmented alternating overlapping testing method, the problems of distorted test results and lack of data support for construction parameter optimization in ultra-deep crushed stone piles have been solved. This has enabled high-precision, real-time testing and construction parameter optimization, ensuring project quality and safety.
Patent Information
- Application Number
- CN202611427576.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-15
- Publication Date
- 2026-11-20
AI Technical Summary
Existing technologies cannot achieve real-time quality inspection of ultra-deep crushed stone piles, and excessive slenderness ratio leads to distorted inspection results. Optimization of construction parameters lacks data support, and the impact of the construction process on existing pile sections cannot be quantified.
A dynamic penetration testing device, including a vibratory compactor, a dynamic penetration mechanism, a frictionless universal support, and a data acquisition mechanism, is adopted. By using a segmented alternating overlapping testing method, the influence of probe friction is eliminated, enabling simultaneous construction and testing, and quantifying the impact of construction on existing pile sections.
It has enabled high-precision detection of ultra-deep crushed stone piles, shortened the construction and testing period, reduced the safety risks of probes, provided dynamic optimization data support for construction parameters, and improved the real-time performance and accuracy of the detection.
Smart Images

Figure CN123133431A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to quality testing technology for foundation treatment engineering, and more particularly to a dynamic penetration testing device and method for ultra-deep crushed stone piles. Background Technology
[0002] Vibro-compacted stone piles are a common method to improve the bearing capacity and liquefaction resistance of soft soil foundations. In major projects such as offshore wind power and cross-sea bridges, the length of stone piles often exceeds 30 meters or even reaches more than 60 meters, which are classified as ultra-deep stone piles. The construction quality inspection of these piles is a key guarantee for the safety of the project.
[0003] Currently, the testing of ultra-deep crushed stone piles mainly employs ultra-heavy dynamic penetration tests (such as N120), evaluating compaction based on the number of blows required for every 10cm of penetration. However, conventional testing requires a single, full-length penetration test with equipment moved separately after the entire pile is completed and left to stand for several days. This lack of real-time quality feedback leads to significant delays in adjusting construction parameters. If deep, loose sections are discovered, rework necessitates removing the upper crushed stone and re-compacting it, which is costly, easily disturbs the strata, and may even render the entire pile unusable. Furthermore, ultra-deep penetration test probes can reach lengths of tens of meters, resulting in excessively high slenderness ratios. These probes are prone to deflection, bending, or breakage during hammering. Simultaneously, the long probes are in close contact with the surrounding crushed stone, and the enormous lateral friction accumulates with depth, consuming most of the hammering energy. This leads to inflated and dispersed blow counts, resulting in severely distorted test results. Loose layers are often misjudged as dense layers, posing safety hazards to the project. Furthermore, the ultra-deep crushed stone piles employ a bottom-up segmented vibration compaction process. The strong vibrations of subsequent construction sections inevitably cause compaction or loosening disturbances to adjacent completed pile sections. The degree and scope of this construction impact cannot be quantitatively evaluated using existing methods, resulting in a lack of basis for optimizing parameters such as vibration frequency and vibration duration. Quality control remains at a rudimentary stage based on experience. Therefore, there is an urgent need to develop a method and device for detecting ultra-deep crushed stone piles that can perform high-fidelity segmented testing as construction progresses and quantitatively analyze the mutual influence between pile sections. Summary of the Invention
[0004] To overcome the aforementioned shortcomings and deficiencies of the prior art, the primary objective of this invention is to provide a dynamic penetration testing device for ultra-deep crushed stone piles. This dynamic penetration testing device for ultra-deep crushed stone piles can be performed simultaneously with vibratory compaction and can eliminate the influence of probe friction.
[0005] A second objective of this invention is to provide a detection method based on a dynamic penetration testing device for ultra-deep crushed stone piles.
[0006] The objective of this invention is achieved through the following technical solution: This invention provides a dynamic penetration testing device for ultra-deep crushed stone piles, including a vibratory compactor, a dynamic penetration mechanism, a frictionless universal support, and a data acquisition mechanism;
[0007] An axial channel is constructed on one side of the discharge port of the vibratory compactor; multiple sets of frictionless universal supports are installed in the central channel of the vibratory compactor and are distributed sequentially along the depth direction of the central channel; the probe of the vibratory compactor passes through multiple sets of frictionless universal supports from top to bottom; the power penetration mechanism is set in the central moving channel of the vibratory compactor to provide power to the vibratory compactor; the data acquisition mechanism includes a counter for collecting the number of hammer blows of the power penetration mechanism, an encoder for collecting the probe penetration depth of the vibratory compactor, and a data recording and analysis terminal, wherein the counter and the encoder are both connected to the data recording and analysis terminal.
[0008] The frictionless universal bracket includes an outer ring fixed seat and an inner retainer. The outer ring fixed seat is fixed to the inner wall of the axial channel, and the inner retainer is disposed inside the outer ring fixed seat. The inner side of the inner retainer is provided with a plurality of spherical mounting holes, and universal balls are installed in each spherical mounting hole.
[0009] Preferably, the inner wall of the outer ring fixing seat is provided with a spherical groove track, and the outer wall of the inner holder is provided with an arc-shaped flange that matches the spherical groove track, and the arc-shaped flange is connected to the spherical groove track.
[0010] Preferably, the vibratory compactor includes a main body, a discharge pipe, a probe, a probe rod, and a striking head. The discharge pipe is arranged around the main body, and the axial channel is arranged on the outside of the main body and on one side of one of the discharge pipes. The probe, probe rod, and striking head are all arranged in the axial channel. The probe is installed at the lower end of the probe rod, and the striking head is installed at the upper end of the probe rod.
[0011] Preferably, the bottom end of the axial channel is provided with a protective mechanism, which includes a one-way opening flexible valve.
[0012] Preferably, the bottom end of the axial channel is provided with a protective mechanism, which includes an annular elastic retaining ring.
[0013] Preferably, the power probe mechanism includes a drop hammer, a guide rod, a winch-type lifting mechanism, an electromagnet, and a controller. The lower end of the guide rod is connected to the probe head, the drop hammer is sleeved on the guide rod, the winch-type lifting mechanism is located above the guide rod, and the winch-type lifting mechanism is connected to the controller. When it is necessary to lift the drop hammer to its original position height, the winch-type lifting mechanism uses an electromagnet to hold the drop hammer in place.
[0014] The detection method, implemented using the dynamic penetration testing device for ultra-deep crushed stone piles as described in the first objective, includes the following steps:
[0015] S1. Construction and Testing Segmentation Planning: Based on the length of the crushed stone piles, the entire pile is divided into n construction segments along the depth direction from bottom to top. Each construction segment is sequentially numbered S1, S2…S…n ;
[0016] S2, First Section Construction and Benchmark Testing: The lowest construction section, namely construction section S1, is tested using a dynamic penetration test device for ultra-deep crushed stone piles to obtain the N120 benchmark data curve of construction section S1.
[0017] S3, Alternating Overlapping Detection Cycle: For the i-th construction segment S i Overlap detection is performed, where 2≤i≤n. Overlap detection is performed after construction is completed, ensuring that the probe's initial penetration depth covers at least S. i Segment whole segment and S i-1 At least a portion of the segment, to obtain simultaneously containing S i Section and S i-1 N120 data curve including the overlapping area of segments;
[0018] S4. Data Analysis and Impact Assessment: Based on the overlap detection data, extract S... i-1 The corresponding N120 value for the segment, and the S measured in S2 or the previous loop. i-1 The values of segment benchmark N120 are compared to evaluate S. i Section construction on S i-1 The influence of segments, and the separation of S from overlapping data. i The segment's own net N120 value;
[0019] S5. Loop Check: Let i = i + 1, repeat S3 and S4 until the topmost construction segment S is completed. n Construction and testing.
[0020] Preferably, step S3 includes the following specific steps:
[0021] S31, Lift the vibratory beater to the construction section S i The bottom elevation was determined, and crushed stone was filled and compacted to complete construction section S. i Construction;
[0022] S32. Turn off the vibratory compactor and let the vibratory compactor remain stationary as a fixed structural point;
[0023] S33. Lower the probe rod and probe, ensuring that the initial penetration depth of the probe at least covers the construction section S. i The whole segment and S i-1 At least a portion of the segment, to achieve S i and S i-1 The overlapping detection of segments is performed to obtain overlapping detection data;
[0024] S34. The data acquisition mechanism collects and analyzes the overlap detection data to obtain the construction section S. i The N120 data curve.
[0025] Preferably, step S4 includes the following specific steps:
[0026] S41. Extract S from the overlap detection data. i-1 The N120 value corresponding to the segment is the same as the S value in step S2 or the previous loop. i-1 The baseline N120 value measured immediately after the section construction was carried out point by point, and the rate of change of hammer blows at each depth point was calculated.
[0027] S42. If the rate of change is positive and exceeds the preset threshold, then determine S i Section construction on S i-1 The segment produced a compaction enhancement effect; if the rate of change is negative and exceeds the preset threshold, it is determined that a relaxation perturbation effect has occurred; if the rate of change is within the threshold range, it is determined that there is no significant impact.
[0028] S43. Based on the structural judgment in step S42, adjust the construction parameters such as the vibration frequency, vibration retention time, and filling amount of the subsequent construction section to achieve dynamic optimization control of the construction process.
[0029] S44. Separate S from the overlapping segment detection data using the difference method or the segmented truncation method. i The net N120 value of the segment itself, as S i The criteria for evaluating the quality of a section.
[0030] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0031] 1. It enables simultaneous construction and testing of ultra-deep crushed stone piles. Construction and testing share the same equipment and drilling ducts in the soil, eliminating the need to lift and change drills. Dynamic penetration tests can be conducted immediately after compaction is completed. The overall construction and testing period for a single pile can be shortened by more than 30%. Quality information feedback is real-time, and problems can be reworked immediately, avoiding the enormous difficulties of post-processing deep defects.
[0032] 2. It fundamentally eliminates the influence of probe side friction in ultra-deep penetration tests. The frictionless universal bracket converts the sliding friction between the probe and the retaining wall into rolling friction, reducing the frictional force to a negligible level. It can also adapt to probe deflection without generating additional bending moment, ensuring that the hammering energy is transmitted to the probe with high fidelity. This enables the testing accuracy of ultra-deep dynamic penetration tests to reach or approach the level of shallow tests, completely solving the problem of data distortion caused by long probes.
[0033] 3. For the first time, a quantitative evaluation of the impact of the construction process on existing pile segments has been achieved. Through an original segmented alternating overlapping detection method, two sets of detection data for the same pile segment before and after the construction of adjacent segments can be obtained. By comparing and quantitatively revealing the degree and scope of construction disturbance, precise data support is provided for the dynamic optimization of vibro-compaction parameters, promoting the leap from experience-based extensive construction to data-driven scientific construction of ultra-deep crushed stone piles.
[0034] 4. Effectively avoids the safety risks of ultra-long probes. By transforming high-risk, one-time full-length testing into segmented, low-risk testing, the probe's slenderness ratio remains within a safe range, preventing probe skewness, bending, and breakage accidents, and ensuring the safety of testing operations.
[0035] 5. High equipment integration and strong engineering applicability. This invention only requires modification of conventional vibratory compactors and the addition of components, making the modification cost controllable and easy to deploy and promote quickly on existing pile frame systems.
[0036] 6. This invention is also applicable to the construction quality inspection of ultra-deep crushed stone piles in projects such as high pile foundations of offshore wind farms, anchorages of cross-river and cross-sea suspension bridges, and high embankment roadbeds in deep soft soil areas. Its advantages of micro-disturbance and high precision detection are even more significant for near-shore projects and foundation treatment projects near existing buildings that are sensitive to construction environment and have high requirements for controlling ground disturbance. Attached Figure Description
[0037] Figure 1 This is a frontal view of the vibratory impactor according to Embodiment 1 of the present invention.
[0038] Figure 2 This is a cross-sectional schematic diagram of the vibratory impactor according to Embodiment 1 of the present invention.
[0039] Figure 3 This is a schematic diagram of the overall structure of the ultra-heavy dynamic penetration drilling detection device according to Embodiment 1 of the present invention.
[0040] Figure 4 This is a schematic diagram of the automatic unhooking and dropping hammer system of Embodiment 1 of the present invention.
[0041] Figure 5 This is a schematic diagram of the ultra-heavy dynamic penetration test operation in Embodiment 1 of the present invention.
[0042] Figure 6 This is a schematic diagram of the frictionless universal bracket of Embodiment 1 of the present invention.
[0043] Figure 7 This is a schematic diagram of the connection between the inner support and the outer ring fixing seat in Embodiment 1 of the present invention.
[0044] Figure 8 This is a flowchart of the detection method of the present invention.
[0045] Among them, 1 is the axial channel, 2 is the main body of the vibratory impactor, 3 is the discharge pipe, 4 is the probe, 5 is the head, 6 is the connector, 7 is the winch-type lifting mechanism, 8 is the drop hammer, 9 is the guide rod, 10 is the frictionless universal bracket, 11 is the probe rod, 12 is the electromagnet, 13 is the cable, 14 is the elastic valve, 15 is the inner cage, 16 is the universal ball bearing, and 17 is the outer ring fixing seat. Detailed Implementation
[0046] The present invention is further described below through specific embodiments, but the scope of protection of the present invention is not limited thereto.
[0047] Example 1
[0048] like Figures 1 to 5 As shown, the dynamic penetration testing device for ultra-deep crushed stone piles includes a vibratory compactor, a dynamic penetration mechanism, a frictionless universal support, and a data acquisition mechanism.
[0049] An axial channel is constructed on one side of the discharge port of the vibratory compactor; multiple sets of frictionless universal supports are installed in the central channel of the vibratory compactor and are distributed sequentially along the depth direction of the central channel; the probe of the vibratory compactor passes through multiple sets of frictionless universal supports from top to bottom; the power penetration mechanism is set in the central moving channel of the vibratory compactor to provide power to the vibratory compactor; the data acquisition mechanism includes a counter for collecting the number of hammer blows of the power penetration mechanism, an encoder for collecting the probe penetration depth of the vibratory compactor, and a data recording and analysis terminal, wherein the counter and the encoder are both connected to the data recording and analysis terminal.
[0050] Specifically, the inner diameter of the axial channel is larger than the maximum outer diameter of the heavy-duty power penetrometer probe, preferably 30mm to 50mm larger than the probe's outer diameter. For example, for a probe with an outer diameter of 74mm, the inner diameter of the axial channel is 104mm to 124mm to ensure that the probe rod and probe can pass through smoothly.
[0051] The data acquisition mechanism includes a counter, a depth encoder, and a data recording and analysis terminal. The counter collects the number of hammer blows from the dynamic penetration test mechanism. The depth encoder, mounted on the pile frame, tracks the penetration depth of the probe in real time via a measuring rope or laser. Both the counter and the depth encoder are connected to the data recording and analysis terminal. The data recording and analysis terminal receives the hammer blow count and depth signals, automatically calculates and records the number of hammer blows (N120) per 10cm penetration, and can generate a curve of N120 versus depth in real time to evaluate the compaction of the crushed stone pile. This achieves synchronous automatic acquisition and real-time analysis of the hammer blow count and penetration depth, avoiding the subjective errors and lags of manual reading and recording, ensuring objective and reliable test results. Simultaneously, it can generate the N120 curve during the testing process, providing intuitive and timely data support for on-site quality assessment and adjustment of construction parameters.
[0052] Multiple sets of frictionless universal supports are installed within the axial channel, and are distributed sequentially along the depth direction of the axial channel, with a preferred installation spacing of 2m to 5m. The probe rod passes through the multiple sets of frictionless universal supports sequentially from top to bottom. Figure 6 As shown, each set of the frictionless universal joint bracket includes an outer ring fixing seat and an inner retainer. The outer ring fixing seat is fixed to the inner wall of the axial channel, and the inner retainer is disposed inside the outer ring fixing seat. The inner side of the inner retainer is provided with multiple spherical mounting holes, and universal balls are installed in each spherical mounting hole. Figure 7 As shown, the inner wall of the outer ring fixing seat is provided with a spherical groove track, and the outer wall of the inner holder is provided with an arc-shaped flange that matches the spherical groove track. The arc-shaped flange is connected to the spherical groove track.
[0053] When the probe enters the guide hole formed by the universal ball bearings, the outer wall of the probe only makes point contact with each ball bearing. This transforms the sliding friction between the traditional probe and the retaining wall into extremely low rolling friction, reducing the frictional force to a negligible level. This ensures that almost all the hammering energy is transferred to the soil resistance at the probe tip, enabling the testing accuracy of ultra-deep dynamic penetration tests to reach or approach the level of shallow tests. This completely solves the industry problem of data distortion caused by the huge side friction of long probes. Simultaneously, the spherical groove track between the outer ring fixing seat and the inner retainer allows the inner retainer to float axially and radially within the outer fixing seat. This allows the inner retainer to adapt to minor deflections and lateral vibrations during probe movement, ensuring reliable guidance without introducing additional bending moments and avoiding the safety risks of probe bending or breakage.
[0054] like Figure 2 and Figure 3 As shown, the vibratory compactor includes a main body, a discharge pipe, a probe, a probe rod, and a striking head. The discharge pipe is arranged around the main body, and the axial channel is located on the outside of the main body and on one side of one of the discharge pipes. The probe, probe rod, and striking head are all located in the axial channel. The probe is installed at the lower end of the probe rod, and the striking head is installed at the upper end of the probe rod. This configuration sets the vibratory compactor in a ring or split layout, that is, the probe, probe rod, and striking head are all located in the axial channel eccentrically distributed with respect to the main body. This allows vibratory compaction and dynamic penetration testing to share the same main body and the same drilling channel, eliminating the need to lift and change drills, and providing a structural basis for simultaneous construction and testing. The discharge pipe and the axial channel are arranged in parallel, without interference, ensuring the efficiency of vibratory compaction construction while integrating testing functions. The equipment is compact and has a high space utilization rate.
[0055] The bottom end of the axial channel is equipped with a protective mechanism, which includes a one-way opening elastic valve. During vibro-compaction pile driving, the protective mechanism remains closed or compressed under the external pressure of gravel and mud to prevent gravel from entering the axial channel; when testing is required, the probe can be inserted downwards to push open the valve and extend it.
[0056] The power penetration mechanism includes a drop hammer, a guide rod, a winch-type lifting mechanism, an electromagnet, and a controller. The lower end of the guide rod is connected to the head, the drop hammer is sleeved on the guide rod, the winch-type lifting mechanism is located above the guide rod, and the winch-type lifting mechanism is connected to the controller. When it is necessary to lift the drop hammer to its original position height, the winch-type lifting mechanism uses an electromagnet to hold the drop hammer in place.
[0057] Specifically, after the vibratory compactor completes the vibratory pile driving operation and stops vibrating, the power penetration mechanism enters the working preparation state. At this time, the electromagnet is energized, attracting and holding the drop hammer at the initial height position. When the detection operation begins, the controller de-energizes the electromagnet, the drop hammer disengages from the electromagnet, and the drop hammer falls freely along the guide rod under the action of gravity, with a falling distance of 1000mm. The drop hammer impacts the bearing surface of the head, and the hammering energy is transferred to the probe through the probe rod, driving the probe to penetrate into the crushed stone pile body.
[0058] After a single hammer strike, the winch-type lifting mechanism drives the cable to descend. An electromagnet is connected to the end of the cable, and the descent distance is 1000mm, bringing the electromagnet into contact with the top surface of the hammer. The electromagnet is then energized, attracting the hammer through magnetic force. The winch-type lifting mechanism then reverses its rotation, lifting both the electromagnet and the attracted hammer to the initial height.
[0059] The above-described cyclical process of "electromagnet de-energization—free-falling hammer impact—cable descent and electromagnet energization and attraction—cable lifting and resetting" is repeated until the probe penetrates to the designed testing depth, completing the dynamic penetration test. This automatic release hammer system, combining electromagnet attraction and winch lifting, achieves automatic cyclic lifting and release of the hammer, with precise control, rapid response, and stable output of hammering energy conforming to the N120 standard, ensuring the standardization and comparability of test data. Simultaneously, it eliminates the need for manual hammer hanging or release, reducing labor intensity and improving the safety and automation of the testing operation.
[0060] like Figure 8 As shown, the detection method, implemented using the aforementioned dynamic penetration testing device for ultra-deep crushed stone piles, includes the following steps:
[0061] S1. Construction and Testing Segmentation Planning: Based on the length of the crushed stone piles, the entire pile is divided into n construction segments along the depth direction from bottom to top. Each construction segment is sequentially numbered S1, S2…S… n ;
[0062] S2, First Section Construction and Benchmark Testing: The lowest construction section, namely construction section S1, is tested using a dynamic penetration test device for ultra-deep crushed stone piles to obtain the N120 benchmark data curve of construction section S1.
[0063] S3, Alternating Overlapping Detection Cycle: For the i-th construction segment S i Overlap detection is performed, where 2≤i≤n. Overlap detection is performed after construction is completed, ensuring that the probe's initial penetration depth covers at least S. i Segment whole segment and S i-1 At least a portion of the segment, to obtain simultaneously containing S i Section and S i-1 The N120 data curve includes the overlapping area of the segment; Step S3 includes the following specific steps:
[0064] S31, Lift the vibratory beater to the construction section S i The bottom elevation was determined, and crushed stone was filled and compacted to complete construction section S. i Construction;
[0065] S32. Turn off the vibratory compactor and let the vibratory compactor remain stationary as a fixed structural point;
[0066] S33. Lower the probe rod and probe, ensuring that the initial penetration depth of the probe at least covers the construction section S. i The whole segment and S i-1 At least a portion of the segment, to achieve S i and S i-1 The overlapping detection of segments is performed to obtain overlapping detection data;
[0067] S34. The data acquisition mechanism collects and analyzes the overlap detection data to obtain the construction section S. i The N120 data curve.
[0068] S4. Data Analysis and Impact Assessment: Based on the overlap detection data, extract S... i-1 The corresponding N120 value for the segment, and the S measured in S2 or the previous loop. i-1 The values of segment benchmark N120 are compared to evaluate S. i Section construction on S i-1 The influence of segments, and the separation of S from overlapping data. i The segment's own net N120 value; Step S4 includes the following specific steps:
[0069] S41. Extract S from the overlap detection data. i-1 The N120 value corresponding to the segment is the same as the S value in step S2 or the previous loop. i-1 The baseline N120 value measured immediately after the section construction was carried out point by point, and the rate of change of hammer blows at each depth point was calculated.
[0070] S42. If the rate of change is positive and exceeds the preset threshold, then determine S i Section construction on S i-1 The segment produced a compaction enhancement effect; if the rate of change is negative and exceeds the preset threshold, it is determined that a relaxation perturbation effect has occurred; if the rate of change is within the threshold range, it is determined that there is no significant impact.
[0071] S43. Based on the structural judgment in step S42, adjust the construction parameters such as the vibration frequency, vibration retention time, and filling amount of the subsequent construction section to achieve dynamic optimization control of the construction process.
[0072] S44. Separate S from the overlapping segment detection data using the difference method or the segmented truncation method. i The net N120 value of the segment itself, as S i The criteria for evaluating the quality of a section.
[0073] S5. Loop Check: Let i = i + 1, repeat S3 and S4 until the topmost construction segment S is completed. n Construction and testing.
[0074] The detection method of this invention has for the first time achieved refined quality control of the entire construction process of ultra-deep crushed stone piles, which includes "drilling and inspection, segment-by-segment evaluation, and impact quantification". This has completely changed the traditional extensive mode of separating construction and detection, and provided accurate data support for the dynamic optimization of construction parameters such as vibration frequency and vibration time. It has promoted the transformation of ultra-deep crushed stone pile construction from experience-based extensive mode to data-driven scientific mode.
[0075] The following is a detailed explanation of the testing method using a specific engineering example: In the foundation treatment project of an approach bridge section of a cross-sea bridge, the foundation soil is a thick layer of silty soft soil, and the design adopts vibro-compacted crushed stone piles for reinforcement. The crushed stone piles have a designed diameter of 1.0m and a designed length of 55m, belonging to typical ultra-deep crushed stone piles. The design requires the pile body to reach a medium-dense to dense state, corresponding to an N120 hammer blow count of not less than 8 blows / 10cm.
[0076] (a) Equipment Configuration
[0077] The dynamic penetration testing device for ultra-deep crushed stone piles described in this invention is used. The vibratory compactor has a power of 130kW and an axial channel inner diameter of 115mm. A set of frictionless universal supports is installed every 3m along the inner wall of the axial channel, for a total of approximately 18 sets. The universal ball bearings are made of silicon nitride ceramic, and the guide hole inner diameter is 50.5mm.
[0078] The dynamic penetrometer mechanism uses a high-strength alloy steel probe rod with an outer diameter of 50mm, a single rod length of 3m, and a tapered thread connection. The probe is a standard ultra-heavy-duty dynamic penetrometer probe with a 60° cone angle and an outer diameter of 74mm. The drop hammer has a mass of 120kg and a drop distance of 1000mm.
[0079] The depth encoder in the data acquisition mechanism is a wire-type depth encoder, and the data recording and analysis terminal is a portable data recording and analysis terminal with a sampling frequency of 10Hz.
[0080] (II) Construction and Testing Process
[0081] According to the detection method described in this invention, the 55m pile length is divided into 11 construction sections, each with a length H=5m. These sections are numbered from bottom to top as S1 (50-55m), S2 (45-50m), S3 (40-45m)...S 11 (0~5m). Then:
[0082] S1. Construction and Testing Segmentation Planning:
[0083] Based on the designed pile length of 55m for the crushed stone pile, the entire pile is divided into 11 construction sections along the depth direction from bottom to top. These sections are numbered sequentially from bottom to top as S1, S2…S… 11 .
[0084] S2. Initial Construction and Benchmark Testing:
[0085] After drilling to a depth of 55m, the vibratory compactor is raised to the bottom elevation of 50m in section S1. Graded crushed stone is then filled in, and the vibratory compactor is started to compact section S1 (50-55m) at a frequency of 1450 r / min and a vibration duration of 15s. After construction is completed, the vibration is turned off, and the vibratory compactor remains stationary as a fixed structural point.
[0086] Lower the probe rod, and the probe penetrates the bottom of the vibratory impactor. Start the drop hammer system to perform dynamic penetration testing on section S1 (50-55m) to obtain the baseline N120 curve for section S1.
[0087] S3, Alternating Overlap Detection Loop
[0088] S31. Raise the vibratory compactor to the bottom elevation of S2 section 45m, fill with crushed stone and compact it to complete the construction of S2 section (45-50m);
[0089] S32. Turn off the vibratory compactor and let the vibratory compactor remain stationary as a fixed structural point;
[0090] S33. Lower the probe rod and probe so that the initial penetration depth of the probe covers the entire S2 section (45-50m) and the top part of the S2 section (50-52m), that is, perform dynamic penetration testing on the overlapping section (45-55m) of S1+S2 to obtain overlapping test data.
[0091] S34. The data acquisition mechanism collects and analyzes the overlapping detection data to obtain the N120 data curve of construction section S2.
[0092] S4. Data Analysis and Impact Assessment:
[0093] S41. Extract the N120 values corresponding to section S1 (50-55m) in this test, and compare them point by point with the baseline N120 values of section S1 measured in step S2. Calculate the rate of change of hammer blows at each depth point. The data acquisition terminal automatically compared and found that, affected by the construction vibration of section S2, the N120 values within a range of approximately 2m at the top of section S1 (50-52m) increased by an average of 17%, with a positive rate of change exceeding the preset threshold (the preset threshold is set to ±10%).
[0094] S42. It is determined that the construction of section S2 had a significant compaction and strengthening effect on the top 2m range of section S1; the change in the range of 52-55m was less than 5%, which is within the threshold range, and it is determined that there was no significant impact.
[0095] S43. Based on the above judgment results, the vibration retention time for subsequent S3 section construction should be appropriately reduced to 12s to save energy.
[0096] S44. Using the difference method or segmented interception method, separate the net N120 value of segment S2 (45-50m) from the detection data of the overlapping segment (45-55m) and use it as the basis for quality evaluation of segment S2.
[0097] S5. Loop Check: Let i=3, repeat S3 and S4, and complete segment S3 (40~45m) to S in sequence. 11 Construction, overlap detection, and data analysis of sections (0-5m) were carried out until the topmost construction section S was completed. 11 Construction and testing.
[0098] (III) Test Results
[0099] After alternating testing of all pile sections, the net N120 hammer blow count for all construction sections was greater than 8 blows / 10cm, meeting the design compaction requirements. Through segment-by-segment overlapping data analysis, the impact of each section's construction on adjacent sections was accurately understood. Based on this, construction parameters were dynamically adjusted, resulting in a cumulative energy saving of approximately 12%, without any probe deviation or data anomalies.
[0100] The device and method of this invention enable simultaneous construction and testing of 55m ultra-deep crushed stone piles, reducing the overall construction and testing period of a single pile by more than 30% compared to traditional methods. By using segmented, alternating, and overlapping testing, the compaction and strengthening effect of subsequent construction on existing pile segments is quantified, thereby optimizing subsequent construction parameters and saving energy while ensuring quality. Throughout the testing process, the slenderness ratio of the probe remains within a safe range, without any deviation, bending, or breakage, verifying the safety and reliability of the device of this invention.
[0101] Example 2
[0102] This embodiment is the same as Embodiment 1 except for the following features: the bottom end of the axial channel is provided with a protective mechanism, which includes an annular elastic retaining ring.
[0103] Those skilled in the art will readily understand that the above description is merely an embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A dynamic penetration testing device for ultra-deep crushed stone piles, characterized in that, Includes vibratory impactor, powered penetration mechanism, frictionless universal support, and data acquisition mechanism; An axial channel is constructed on one side of the discharge port of the vibratory compactor; multiple sets of frictionless universal supports are installed in the central channel of the vibratory compactor and are distributed sequentially along the depth direction of the central channel; the probe of the vibratory compactor passes through multiple sets of frictionless universal supports from top to bottom; the power penetration mechanism is set in the central moving channel of the vibratory compactor to provide power to the vibratory compactor; the data acquisition mechanism includes a counter for collecting the number of hammer blows of the power penetration mechanism, an encoder for collecting the probe penetration depth of the vibratory compactor, and a data recording and analysis terminal, wherein the counter and the encoder are both connected to the data recording and analysis terminal.
2. The dynamic penetration testing device for ultra-deep crushed stone piles according to claim 1, characterized in that, The frictionless universal bracket includes an outer ring fixed seat and an inner retainer. The outer ring fixed seat is fixed to the inner wall of the axial channel, and the inner retainer is disposed inside the outer ring fixed seat. The inner side of the inner retainer is provided with a plurality of spherical mounting holes, and universal balls are installed in each spherical mounting hole.
3. The dynamic penetration testing device for ultra-deep crushed stone piles according to claim 2, characterized in that, The inner wall of the outer ring fixing seat is provided with a spherical groove track, and the outer wall of the inner holder is provided with an arc-shaped flange that matches the spherical groove track. The arc-shaped flange is connected to the spherical groove track.
4. The dynamic penetration testing device for ultra-deep crushed stone piles according to claim 1, characterized in that, The vibratory impactor includes a main body, a discharge pipe, a probe, a probe rod, and a striking head. The discharge pipe is arranged around the main body, and the axial channel is arranged on the outside of the main body and on one side of one of the discharge pipes. The probe, probe rod, and striking head are all arranged in the axial channel. The probe is installed at the lower end of the probe rod, and the striking head is installed at the upper end of the probe rod.
5. The dynamic penetration testing device for ultra-deep crushed stone piles according to claim 1, characterized in that, The bottom end of the axial channel is provided with a protective mechanism, which includes a one-way opening flexible valve.
6. The dynamic penetration testing device for ultra-deep crushed stone piles according to claim 1, characterized in that, The bottom end of the axial channel is provided with a protective mechanism, which includes an annular elastic retaining ring.
7. The dynamic penetration testing device for ultra-deep crushed stone piles according to claim 1, characterized in that, The power penetration mechanism includes a drop hammer, a guide rod, a winch-type lifting mechanism, an electromagnet, and a controller. The lower end of the guide rod is connected to the head, the drop hammer is sleeved on the guide rod, the winch-type lifting mechanism is located above the guide rod, and the winch-type lifting mechanism is connected to the controller. When it is necessary to lift the drop hammer to its original position height, the winch-type lifting mechanism uses an electromagnet to hold the drop hammer in place.
8. A detection method, characterized in that, The method employs the dynamic penetration testing device for ultra-deep crushed stone piles as described in any one of claims 1-7, comprising the following steps: S1. Construction and Testing Segmentation Planning: Based on the length of the crushed stone piles, the entire pile is divided into n construction segments along the depth direction from bottom to top. Each construction segment is sequentially numbered S1, S2…S… n ; S2, First Section Construction and Benchmark Testing: The lowest construction section, namely construction section S1, is tested using a dynamic penetration test device for ultra-deep crushed stone piles to obtain the N120 benchmark data curve of construction section S1. S3, Alternating Overlapping Detection Cycle: For the i-th construction segment S i Overlap detection is performed, where 2≤i≤n. Overlap detection is performed after construction is completed, ensuring that the probe's initial penetration depth covers at least S. i Segment whole segment and S i-1 At least a portion of the segment, to obtain simultaneously containing S i Section and S i-1 N120 data curve including the overlapping area of segments; S4. Data Analysis and Impact Assessment: Based on the overlap detection data, extract S... i-1 The corresponding N120 value for the segment, and the S measured in S2 or the previous loop. i-1 The values of segment benchmark N120 are compared to evaluate S. i Section construction on S i-1 The influence of segments, and the separation of S from overlapping data. i The segment's own net N120 value; S5. Loop Check: Let i = i + 1, repeat S3 and S4 until the topmost construction segment S is completed. n Construction and testing.
9. The detection method according to claim 8, characterized in that, Step S3 includes the following specific steps: S31, Lift the vibratory beater to the construction section S i The bottom elevation was determined, and crushed stone was filled and compacted to complete construction section S. i Construction; S32. Turn off the vibratory compactor and let the vibratory compactor remain stationary as a fixed structural point; S33. Lower the probe rod and probe, ensuring that the initial penetration depth of the probe at least covers the construction section S. i The whole segment and S i-1 At least a portion of the segment, to achieve S i and S i-1 The overlapping detection of segments is performed to obtain overlapping detection data; S34. The data acquisition mechanism collects and analyzes the overlap detection data to obtain the construction section S. i The N120 data curve.
10. The detection method according to claim 8, characterized in that, Step S4 includes the following specific steps: S41. Extract S from the overlap detection data. i-1 The N120 value corresponding to the segment is the same as the S value in step S2 or the previous loop. i-1 The baseline N120 value measured immediately after the section construction was carried out point by point, and the rate of change of hammer blows at each depth point was calculated. S42. If the rate of change is positive and exceeds the preset threshold, then determine S i Section construction on S i-1 The segment produced a compaction enhancement effect; if the rate of change is negative and exceeds the preset threshold, it is determined that a relaxation perturbation effect has occurred; if the rate of change is within the threshold range, it is determined that there is no significant impact. S43. Based on the structural judgment in step S42, adjust the construction parameters such as the vibration frequency, vibration retention time, and filling amount of the subsequent construction section to achieve dynamic optimization control of the construction process. S44. Separate S from the overlapping segment detection data using the difference method or the segmented truncation method. i The net N120 value of the segment itself, as S i The criteria for evaluating the quality of a section.