Steel structure corridor system and construction method thereof

By installing inclined tie rods at both ends of the steel structure corridor and connecting them with the hanging columns, the problems of vertical deformation and space occupation of the large-span steel structure corridor were solved, achieving high structural rigidity and visual transparency.

CN123133485APending Publication Date: 2026-11-20BEIJING URBAN CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202610928658.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-06-25
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Large-span steel structure corridors are prone to significant vertical deformation under gravity loads. Traditional support methods occupy space, increase self-weight, and cause visual obstruction.

Method used

The steel structure corridor is connected to the main structure by installing a first and a second cable-stayed assembly at both ends, which are connected to the main structure through hanging columns. This enhances the overall linear stiffness, reduces the amount of steel structure used and its own weight, and avoids the space occupied by the support columns.

Benefits of technology

Effectively control vertical deformation at mid-span, ensure pedestrian comfort, reduce structural safety hazards, and improve spatial permeability and structural stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133485A_ABST
    Figure CN123133485A_ABST
Patent Text Reader

Abstract

The application relates to the technical field of building engineering, and discloses a steel structure corridor system and a construction method thereof, which comprises a first main body structure, a second main body structure and a steel structure corridor; the steel structure corridor is connected with the first main body structure and the second main body structure; the steel structure corridor comprises at least two layers and a plurality of hanging columns; the at least two layers are arranged at intervals along the height direction; the layer comprises a plurality of steel beams and is arranged horizontally, one end of the layer is connected with the first main body structure, and the other end of the layer is connected with the second main body structure; the plurality of hanging columns pass through the plurality of steel beams along the height direction and are fixedly connected with the steel beams; a first cable-stayed component is arranged on the top end surface of the first main body structure along the height direction and is connected with the top ends of the plurality of hanging columns along the height direction; and a second cable-stayed component is arranged on the top end surface of the second main body structure along the height direction and is connected with the top ends of the plurality of hanging columns along the height direction. The vertical deformation in the middle of the span is effectively controlled, the self weight is reduced, and the visual permeability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building engineering technology, specifically to a steel structure connecting corridor system and its construction method. Background Technology

[0002] With the rapid development of high-density urban development and building complexes, connecting multiple high-rise buildings through corridors to achieve spatial connectivity and functional integration has become a mainstream design trend. Steel structure corridors, with their advantages of light weight, high strength, good ductility, convenient construction, and high degree of industrialization, are gradually replacing traditional concrete corridors and becoming the preferred structural form for large-span, high-level connected buildings. However, the linear stiffness of large-span steel structure corridors decreases significantly with increasing span. Under gravity loads, large vertical deformations are prone to occur at the mid-span, which can reduce pedestrian comfort and may also lead to structural safety hazards due to excessive stress.

[0003] To address the vertical deformation issue of long-span steel structure corridors, common solutions include adding supporting columns beneath the corridor or employing large truss structures. However, adding supporting columns can encroach on the space beneath the corridor, and columns with excessively high slenderness ratios are prone to instability and failure, posing safety hazards. Large truss structures, on the other hand, significantly increase the amount of steel used and the structural weight, and the diagonal web members of large trusses can obstruct the view. Summary of the Invention

[0004] This invention provides a steel structure corridor system and its construction method to solve the problems of excessive vertical deformation at mid-span of the steel structure corridor, the occupation of the space below the steel structure corridor by traditional support methods, increased self-weight, and visual obstruction.

[0005] In a first aspect, the present invention provides a steel structure corridor system, comprising: a first main structure; a second main structure; a steel structure corridor adapted to connect the first main structure and the second main structure; the steel structure corridor includes at least two levels and multiple hanging columns; the at least two levels are arranged at intervals along the height direction; each level includes multiple steel beams, which are arranged horizontally, with one end connected to the first main structure and the other end connected to the second main structure; multiple hanging columns pass through the multiple steel beams along the height direction and are fixedly connected to the steel beams; a first inclined bracing assembly is disposed on the top surface of the first main structure along the height direction and connected to the top surfaces of the multiple hanging columns along the height direction; a second inclined bracing assembly is disposed on the top surface of the second main structure along the height direction and connected to the top surfaces of the multiple hanging columns along the height direction.

[0006] Beneficial effects: The steel structure corridor, connected to the first and second main structures along the top surface of the first and second main structures along the height direction by the first and second inclined tie components, significantly improves the overall linear stiffness of the steel structure corridor and effectively controls the vertical deformation at mid-span. This ensures pedestrian comfort and reduces structural safety hazards caused by excessive deformation. There is no need to add supporting columns under the corridor, avoiding the occupation of the space below. By connecting multiple vertically installed hanging columns to the first and second inclined tie components, compared to large truss structures, there is no need for a large number of diagonal braces, significantly reducing the amount of steel used and the structural weight. Furthermore, there is no issue of obstructing the view, balancing structural practicality and spatial visual transparency.

[0007] In one optional embodiment, the first cable-stayed assembly includes: a first support, a plurality of first balancing cables, and a plurality of first tension cables; the first support is disposed on the top surface of the first main structure along the height direction and connected to the first main structure; one end of the plurality of first tension cables is connected to the first support and the other end is connected to a hanging column; each first tension cable is connected to a corresponding hanging column; the plurality of first balancing cables are disposed on the side of the first support away from the plurality of first tension cables; one end of the plurality of first balancing cables is connected to the first main structure and the other end is connected to the first support.

[0008] Beneficial effects: The first cable-stayed assembly evenly transmits the tension of the first cable to the first main structure through the first support, while the first balance cable counteracts the lateral tension of the first cable on the first support, effectively avoiding the risk of deformation or overturning of the first support due to excessive force on one side, and ensuring the structural stability of the first cable-stayed assembly; each first cable is connected to a corresponding hanging column, realizing the precise distribution of tension on each hanging column, further enhancing the overall linear stiffness of the steel structure corridor, and synergistically controlling the vertical deformation of the steel structure corridor in the middle of the span.

[0009] In one optional embodiment, at least one first connecting node is provided on the first support; the first connecting node is adapted to be connected to the first balancing cable and the first tension cable; when the number of first connecting nodes is ≥2, the number of first connecting nodes is even and they are symmetrically distributed on both sides of the center line of the steel structure corridor; multiple hanging columns located on one side of the center line of the steel structure corridor are connected to the first connecting node on the same side.

[0010] Beneficial effects: The setting of the first connection node provides a unified connection carrier for the first balance cable and the first tension cable, ensuring a clear and concentrated tension transmission path and improving the force transmission efficiency; when the number of first connection nodes is not less than 2, the design of even-numbered symmetrical distribution on both sides of the center line of the steel structure corridor can make the tension on both sides of the first support mutually restrain each other. Combined with the connection method of the same side hanging column and the corresponding first connection node, the force distribution of each hanging column is further optimized, effectively avoiding the instability of the tension on both sides of the first support, thereby enhancing the overall force balance of the first cable-stayed assembly.

[0011] In one optional embodiment, the second cable-stayed assembly includes: a second support, a plurality of second balancing cables, and a plurality of second tension cables; the second support is disposed on the top surface of the second main structure along the height direction and connected to the second main structure; one end of the plurality of second tension cables is connected to the second support, and the other end is connected to a hanging column; each second tension cable is connected to a corresponding hanging column; the plurality of second balancing cables are disposed on the side of the second support away from the plurality of second tension cables; one end of the plurality of second balancing cables is connected to the second main structure, and the other end is connected to the second support.

[0012] Beneficial effects: The second cable-stayed assembly evenly transmits the tension of the second cable to the second main structure through the second support, while the second balance cable counteracts the lateral tension of the second cable on the second support, effectively avoiding the risk of deformation or overturning of the second support due to excessive force on one side, and ensuring the structural stability of the second cable-stayed assembly; each second cable is connected to a corresponding hanging column, realizing the precise distribution of tension on each hanging column, further enhancing the overall linear stiffness of the steel structure corridor, and synergistically controlling the vertical deformation of the steel structure corridor in the middle of the span.

[0013] In one optional embodiment, the second cable-stayed assembly includes: at least one second connection node provided on the second support; the second connection node is adapted to connect with the second balance cable and the second cable; when the number of second connection nodes is ≥2, the number of second connection nodes is even and symmetrically distributed on both sides of the center line of the steel structure corridor; multiple hanging columns located on one side of the center line of the steel structure corridor are connected to the second connection node on the same side.

[0014] Beneficial effects: The setting of the second connection node provides a unified connection carrier for the second balance cable and the second tension cable, ensuring a clear and concentrated tension transmission path and improving the force transmission efficiency; the number and distribution of the second connection nodes are reasonably set according to the structural self-weight of the steel structure corridor and the bearing capacity of the second main structure; when the number of second connection nodes is not less than 2, the design of even-numbered symmetrical distribution on both sides of the center line of the steel structure corridor can make the tension on both sides of the second support mutually restrain each other. Combined with the connection method of the same side hanging column and the corresponding second connection node, the force distribution of each hanging column is further optimized, effectively avoiding the instability of the tension on both sides of the second support, thereby enhancing the overall force balance of the second cable-stayed assembly.

[0015] In one optional implementation, a seismic isolation component is provided between the steel structure corridor and the first main structure; a seismic isolation component is provided between the steel structure corridor and the second main structure.

[0016] Beneficial effects: By setting up seismic isolation components, the steel structure corridor can slide and deform slightly to dissipate energy when encountering earthquakes or strong winds, avoiding structural damage caused by rigid collisions or excessive stress concentration between the first main structure, the second main structure and the corridor.

[0017] In one alternative implementation, the steel beam is provided with multiple stiffening ribs at the connection with the hanging column.

[0018] Beneficial effects: The addition of multiple stiffening ribs can effectively enhance the local stiffness of the connection between the steel beam and the hanging column. The stiffening ribs can restrain the local buckling of the steel beam at the connection, thereby improving the load-bearing capacity and stability of the connection node.

[0019] In one alternative embodiment, a support is provided at the lower end of the column along the height direction, the support being adapted to support the lowest steel beam along the height direction; each level is provided with floor concrete.

[0020] Beneficial effects: The installation of support components can effectively enhance the support stability of the lowest steel beam and evenly transfer the vertical load of the steel beam to the hanging column.

[0021] Secondly, the present invention also provides a construction method suitable for constructing a steel structure corridor system, comprising: S1. constructing a first main structure and a second main structure; S2. dividing the steel beams of the uppermost layer along the height direction into a first steel beam segment and a second steel beam segment; installing a first inclined tie assembly, the first steel beam segment and the corresponding hanging column; and connecting the first inclined tie assembly to the hanging column; S3. installing a second inclined tie assembly, the second steel beam segment and the corresponding hanging column; and fixing the second inclined tie assembly to the hanging column; simultaneously, closing the second steel beam segment with the first steel beam segment in step S2; S4. sequentially installing the remaining steel beams along the height direction from top to bottom, and fixing the hanging column to the remaining steel beams.

[0022] In one alternative implementation, floor concrete is provided on each level; after step S4, the floor concrete of the lowest level along the height direction is poured first. After the floor concrete of the lowest level is poured, the first and second inclined tie components are subjected to the first prestressing tension; after the first prestressing tension is completed, the floor concrete of each level is poured sequentially from bottom to top along the height direction; after the floor concrete of the top level along the height direction is completed, the first and second inclined tie components are subjected to the second prestressing tension.

[0023] Beneficial effects: By pouring floor concrete in a bottom-up construction sequence, and coordinating with two prestressing tensioning operations on the first and second cable-stayed components, the structural stability is ensured during the pouring of floor concrete on each level, reducing cumulative deformation and improving construction safety and controllability. At the same time, secondary adjustments can be made based on the actual stress situation after the steel structure corridor is fully formed, further optimizing the internal force distribution between the cable-stayed components, steel beams, and hanging columns, so that the rigidity and load-bearing capacity of the entire steel structure corridor can be fully utilized, ultimately ensuring the long-term stability and safety of the structure during the service phase. Attached Figure Description

[0024] To more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the specific embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.

[0025] Figure 1 This is a front view of a steel structure corridor system according to an embodiment of the present invention; Figure 2 This is a top view of a steel structure connecting corridor system according to an embodiment of the present invention; Figure 3 This is a partially enlarged three-dimensional schematic diagram of a steel structure corridor system according to an embodiment of the present invention; Figure 4 This is a structural schematic diagram of a double-connection node in a steel structure corridor system according to an embodiment of the present invention; Figure 5 This is a schematic diagram of the first type of support structure for a steel structure corridor system according to an embodiment of the present invention; Figure 6 This is a schematic diagram of a second type of support structure for a steel structure corridor system according to an embodiment of the present invention; Figure 7 This is a schematic diagram of a third type of support structure for a steel structure corridor system according to an embodiment of the present invention; Figure 8 for Figure 5 , Figure 6 , Figure 7 A front view of the support structure; Figure 9 This is a first schematic diagram of the construction process of another construction method according to an embodiment of the present invention; Figure 10 This is a second schematic diagram illustrating the construction process of another construction method according to an embodiment of the present invention; Figure 11 This is a third schematic diagram illustrating the construction process of another construction method according to an embodiment of the present invention; Figure 12 This is a fourth schematic diagram illustrating the construction process of another construction method according to an embodiment of the present invention; Figure 13 This is a fifth schematic diagram illustrating the construction process of another construction method according to an embodiment of the present invention; Figure 14 This is a sixth schematic diagram illustrating the construction process of another construction method according to an embodiment of the present invention; Figure 15 This is a seventh schematic diagram illustrating the construction process of another construction method according to an embodiment of the present invention; Figure 16 This is the eighth schematic diagram of the construction process of another construction method according to an embodiment of the present invention.

[0026] Explanation of reference numerals in the attached figures: 1. First main structure; 101. Vertical component of the first main structure; 102. Horizontal component of the first main structure; 2. Second main structure; 201. Vertical component of the second main structure; 202. Horizontal component of the second main structure; 3. Steel structure connecting corridor; 301. Steel beam; 3011. Stiffening rib; 302. Hanging column; 3021. Support component; 3022. First hanging column; 3023. Second hanging column; 303. Floor; 304. Floor concrete; 4. First inclined cable assembly; 401. First support; 4011. First connection node; 402. First balance cable; 403. First cable; 5. Second inclined cable assembly; 501. Second support; 5011. Second connection node; 502. Second balance cable; 503. Second cable; 6. Seismic isolation assembly; 7. Centerline of the steel structure connecting corridor. Detailed Implementation

[0027] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0028] The following is combined with Figures 1 to 16 The following describes embodiments of the present invention.

[0029] According to an embodiment of the present invention, a steel structure corridor system is provided, comprising: a first main structure 1, a second main structure 2, a steel structure corridor 3, a first cable-stayed assembly 4, and a second cable-stayed assembly 5. The steel structure corridor 3 is adapted to connect the first main structure 1 and the second main structure 2; the steel structure corridor 3 includes at least two levels 303 and a plurality of hanging columns 302; the at least two levels 303 are arranged at intervals along the height direction; each level 303 includes a plurality of steel beams 301, which are arranged horizontally, one end connected to the first main structure 1, and the other end connected to the second main structure 2; the plurality of hanging columns 302 pass through the plurality of steel beams 301 along the height direction and are fixedly connected to the steel beams 301. The first cable-stayed assembly 4 is disposed on the top surface of the first main structure 1 along the height direction and is connected to the top surfaces of the plurality of hanging columns 302 along the height direction. The second cable-stayed assembly 5 is disposed on the top surface of the second main structure 2 along the height direction and is connected to the top surfaces of the plurality of hanging columns 302 along the height direction.

[0030] The steel structure corridor 3 typically has a large span. As the main load-bearing component, the steel beams 301 are prone to significant vertical deformation under large spans, affecting the structure's stability and operational safety. Multiple hanging columns 302 penetrate multiple steel beams 301 along the height direction and are fixedly connected to them. This connects the steel beams 301 at different levels 303 into a cohesive load-bearing structure, effectively distributing the vertical load borne by the steel beams 301 at each level 303 and suppressing vertical deformation of the steel beams 301 under large span conditions. Furthermore, the first and second inclined tie components 4 and 5, respectively installed at the top of the first main structure 1 and the second main structure 2 along the height direction, apply a tension force to the top of the hanging columns 302 along the height direction, further counteracting the downward deflection tendency of the hanging columns 302 and steel beams 301 under vertical loads, effectively improving the overall rigidity of the steel structure corridor 3. This ensures pedestrian comfort and reduces structural safety hazards caused by excessive deformation. It eliminates the need for additional support columns under the connecting corridor, avoiding the occupation of the space below. Through the cooperation of multiple vertically installed hanging columns 302 with the first and second diagonal bracing components 4 and 5, a large number of diagonal bracing members are unnecessary, significantly reducing the amount of steel used and the structural weight. Furthermore, it avoids visual obstruction, balancing structural practicality with spatial visual transparency. The absence of diagonal bracing members results in a transparent and aesthetically pleasing overall structure. The elimination of ground-mounted support columns maximizes the release of lower passage and visual space, preventing support columns from disrupting or obstructing the building facade and spatial form. More specifically, the first main structure 1 includes a vertical member 101 and a horizontal member 102. The second main structure 2 includes a vertical member 201 and a horizontal member 202. One end of the steel beam 301 along its length is connected to the vertical member 101 of the first main structure, and the other end is connected to the vertical member 201 of the second main structure.

[0031] More specifically, such as Figure 10 As shown, the hanging column 302 is divided into a first hanging column 3022 and a second hanging column 3023. The plurality of hanging columns 302 facing one end of the first main structure 1 are the first hanging columns 3022, and the remaining plurality of hanging columns 302 facing one end of the second main structure 2 are the second hanging columns 3023. The first inclined tension assembly 4 is connected to the second hanging column 3023, and the second inclined tension assembly 5 is also connected to the second hanging column 3023.

[0032] In one embodiment, the first cable-stayed assembly 4 includes: a first support 401, a plurality of first balancing cables 402, and a plurality of first tension cables 403; the first support 401 is disposed on the top surface of the first main structure 1 along the height direction and connected to the first main structure 1; one end of the plurality of first tension cables 403 is connected to the first support 401, and the other end is connected to the hanging column 302; each first tension cable 403 is connected to a corresponding hanging column 302; the plurality of first balancing cables 402 are disposed on the side of the first support 401 away from the plurality of first tension cables 403; one end of the plurality of first balancing cables 402 is connected to the first main structure 1, and the other end is connected to the first support 401. The first cable-stayed assembly 4 transmits the tension of the first cable 403 evenly to the first main structure 1 through the first support 401. At the same time, the first balance cable 402 counteracts the lateral tension of the first cable 403 on the first support 401, effectively avoiding the risk of deformation or overturning of the first support 401 due to excessive force on one side, and ensuring the structural stability of the first cable-stayed assembly 4. Each first cable 403 is connected to a corresponding hanging column 302, realizing the precise distribution of tension on each hanging column 302, further enhancing the overall linear stiffness of the steel structure corridor 3, and coordinating the control of vertical deformation in the middle of the span of the steel structure corridor 3.

[0033] More specifically, such as Figure 1 The first support 401 shown is a spindle-shaped column structure. The first support 401 can also be as follows: Figure 5 The arched support structure shown can also be as follows: Figure 6 The A-shaped support structure shown can also be as follows: Figure 7The portal frame structure is shown. The specific form of the first support 401 can be determined comprehensively based on factors such as the actual project's stress requirements, site space limitations, architectural design requirements, and construction feasibility, including but not limited to the aforementioned support structure forms. The first support 401 can adopt various shapes such as spindle, arch, and portal, which can coordinate with the overall architectural design style, ensuring structural strength while maintaining the flexibility of the architectural space, presenting a light and transparent visual effect, suitable for landmark key projects.

[0034] More specifically, the first cable 403 is connected to the first column 3022. The lower end of each first cable 403 is firmly hinged to the corresponding first column 3022 at the top of the pre-set connection node through a special rigging. This hinged method not only ensures the effective transmission of tension, but also adapts to the slight rotation of the column 302 under load, thus avoiding stress concentration.

[0035] More specifically, the first cable 403 and the first balancing cable 402 can be made of steel strand or high-strength synthetic fiber materials such as carbon fiber or aramid fiber. These materials are lightweight, high-strength, and corrosion-resistant, meeting the mechanical performance and durability requirements of the cables and balancing cables under long-term loads. Steel strand is relatively inexpensive and technologically mature, making it suitable for projects with strict cost control. Carbon fiber and aramid fiber materials are lighter and have higher tensile strength, making them particularly suitable for large-span steel structure corridors or projects sensitive to structural weight, effectively reducing the overall structural load and improving the structure's span capacity and seismic performance. In practical engineering applications, the material types of the cables and balancing cables can be rationally selected based on factors such as the project's span, load conditions, cost budget, and operating environment to ensure an optimal balance between structural safety and economy.

[0036] In one embodiment, at least one first connecting node 4011 is provided on the first support 401; the first connecting node 4011 is adapted to be connected to the first balance cable 402 and the first tension cable 403; when the number of first connecting nodes 4011 is ≥2, the number of first connecting nodes 4011 is even and symmetrically distributed on both sides of the center line 7 of the steel structure corridor; multiple hanging columns 302 located on one side of the center line 7 of the steel structure corridor are connected to the first connecting node 4011 on the same side.

[0037] The number and distribution of the first connecting nodes 4011 are reasonably set according to the structural self-weight of the steel structure corridor 3 and the bearing capacity of the first main structure 1. When the number of the first connecting nodes 4011 is 1, the first connecting node 4011 is set on the center line 7 of the steel structure corridor. At this time, the first cable 403 and the first balance cable 402 are both connected to the first connecting node 4011, so that the tension of the first cable 403 is evenly transmitted to the first support 401 through the first connecting node 4011. At the same time, the first balance cable 402 can effectively counteract the lateral component force generated by the first cable 403, ensuring that the first support 401 remains structurally stable under the force of a single node. The correspondingly connected hanging columns 302 are also distributed symmetrically with the center line 7 of the steel structure corridor as the center, further ensuring the uniformity of load transfer of the steel structure corridor 3 and improving the deformation resistance of the overall structure.

[0038] When the number of first connecting nodes 4011 is not less than 2, the number of first connecting nodes 4011 is even and they are symmetrically distributed on both sides of the center line 7 of the steel structure corridor. Each first connecting node 4011 on each side is connected to multiple hanging columns 302 on the same side, so that the load borne by the first connecting node 4011 is evenly transferred to the first main structure 1 through the first support 401. The first balance cable 402 on the same side is also connected to the first connecting node 4011 on that side. Through the symmetrical arrangement of the first tension cable 403 and the first balance cable 402 working together, the lateral component force generated by the first tension cable 403 on the first support 401 can be effectively offset, avoiding deformation of the support caused by unilateral force. The use of an even number of first connecting nodes 4011 and their symmetrical distribution on both sides of the center line 7 of the steel structure corridor further optimizes the force distribution of each hanging column 302, effectively avoiding the instability of the tension on both sides of the first support 401, thereby enhancing the overall force balance of the first inclined cable assembly 4.

[0039] More specifically, the first connecting node 4011 is a node plate set on the first support 401. The node plate has multiple bolt holes for threading the connectors of the first balance cable 402 and the first tension cable 403, respectively, to ensure that the tension of the first balance cable 402 and the first tension cable 403 can be stably transmitted to the support structure.

[0040] In one embodiment, the second cable-stayed assembly 5 includes: a second support 501, a plurality of second balancing cables 502, and a plurality of second tension cables 503; the second support 501 is disposed on the top surface of the second main structure 2 along the height direction and connected to the second main structure 2; one end of the plurality of second tension cables 503 is connected to the second support 501, and the other end is connected to the hanging column 302; each second tension cable 503 is connected to a corresponding hanging column 302; the plurality of second balancing cables 502 are disposed on the side of the second support 501 away from the plurality of second tension cables 503; one end of the plurality of second balancing cables 502 is connected to the second main structure 2, and the other end is connected to the second support 501. The second cable-stayed assembly 5 transmits the tension of the second cable 503 evenly to the second main structure 2 through the second support 501. At the same time, the second balance cable 502 counteracts the lateral tension of the second cable 503 on the second support 501, effectively avoiding the risk of deformation or overturning of the second support 501 due to excessive force on one side, and ensuring the structural stability of the second cable-stayed assembly 5. Each second cable 503 is connected to a corresponding hanging column 302, realizing the precise distribution of tension on each hanging column 302, further enhancing the overall linear stiffness of the steel structure corridor 3, and coordinating the control of vertical deformation in the middle of the span of the steel structure corridor 3.

[0041] More specifically, such as Figure 1 The second support 501 shown is a spindle-shaped column structure. The second support 501 can also be as follows: Figure 5 The arched support structure shown can also be as follows: Figure 6 The A-shaped support structure shown can also be as follows: Figure 7 The portal frame structure is shown. The specific form of the second support 501 can be determined comprehensively based on factors such as the actual project's stress requirements, site space limitations, architectural design requirements, and construction feasibility, including but not limited to the aforementioned support structure forms. The second support 501 can adopt various shapes such as spindle, arch, and portal, which can coordinate with the overall architectural design style, ensuring structural strength while maintaining the flexibility of the architectural space, presenting a light and transparent visual effect, suitable for landmark key projects.

[0042] More specifically, the second cable 503 is connected to the second column 3023. The lower end of each second cable 503 is firmly hinged to the corresponding second column 3023 at the top of the pre-set connection node through a special rigging. This hinged connection method not only ensures the effective transmission of tension, but also adapts to the slight rotation of the column 302 under load, thus avoiding stress concentration.

[0043] More specifically, the second cable 503 and the second balancing cable 502 can be made of steel strand or high-strength synthetic fiber materials such as carbon fiber or aramid fiber. These materials are lightweight, high-strength, and corrosion-resistant, meeting the mechanical performance and durability requirements of the cables and balancing cables under long-term loads. Steel strand is relatively inexpensive and technologically mature, making it suitable for projects with strict cost control. Carbon fiber and aramid fiber materials are lighter and have higher tensile strength, making them particularly suitable for large-span steel structure corridors or projects sensitive to structural weight, effectively reducing the overall structural load and improving the structure's span capacity and seismic performance. In practical engineering applications, the material types of the cables and balancing cables can be rationally selected based on factors such as the project's span, load conditions, cost budget, and operating environment to ensure an optimal balance between structural safety and economy.

[0044] The vertical load of the steel structure corridor 3 is systematically transferred to the first main structure vertical component 101 and the second main structure vertical component 201 via the hanging column 302, the first cable 403, the second cable 503, the first support 401, and the second support 501. The mechanical transfer path is simple and direct, with no redundant stress links. At the same time, prestress is applied to the first cable 403 and the second cable 503 to effectively control the vertical deflection and structural deformation of the large-span steel structure corridor 3. Without adding ground supports, the overall rigidity of the structure is significantly improved, ensuring the long-term stress safety and service performance of the steel structure corridor 3. Compared to traditional solutions that involve adding diagonal bracing for connecting corridors or additional vertical support columns, which are prone to instability due to excessive slenderness ratios and susceptibility to unexpected lateral impact loads, thus affecting the overall structural safety, the cable used in this invention, as a tension member, possesses positive geometric stiffness. Under stress, the system's stress state can be further optimized by adjusting its own tension, eliminating concerns about instability. This achieves more efficient and reliable stress performance from a mechanical perspective, significantly improving the structure's stability and load-bearing efficiency.

[0045] In one embodiment, at least one second connecting node 5011 is provided on the second support 501; the second connecting node 5011 is adapted to be connected to the second balance cable 502 and the second tension cable 503; when the number of second connecting nodes 5011 is ≥2, the number of second connecting nodes 5011 is even and symmetrically distributed on both sides of the center line 7 of the steel structure corridor; multiple hanging columns 302 located on one side of the center line 7 of the steel structure corridor are connected to the second connecting node 5011 on the same side.

[0046] The number and distribution of the second connection nodes 5011 are reasonably set according to the structural self-weight of the steel structure corridor 3 and the bearing capacity of the second main structure 2. When the number of the second connection nodes 5011 is 1, the second connection node 5011 is set on the center line 7 of the steel structure corridor. At this time, the second cable 503 and the second balance cable 502 are both connected to the second connection node 5011, so that the tension of the second cable 503 is evenly transmitted to the second support 501 through the second connection node 5011. At the same time, the second balance cable 502 can effectively offset the lateral component force generated by the second cable 503, ensuring that the second support 501 remains structurally stable under the force of a single node. The correspondingly connected hanging columns 302 are also distributed symmetrically with the center line 7 of the steel structure corridor as the center, further ensuring the uniformity of load transfer of the steel structure corridor 3 and improving the deformation resistance of the overall structure.

[0047] When the number of second connection nodes 5011 is not less than 2, the number of second connection nodes 5011 is even and they are symmetrically distributed on both sides of the center line 7 of the steel structure corridor. Each side of the second connection node 5011 is connected to multiple hanging columns 302 on the same side, so that the load borne by the second connection node 5011 is evenly transferred to the second main structure 2 through the second support 501. The second balance cable 502 on the same side is also connected to the second connection node 5011 on that side. Through the symmetrical arrangement of the second cable 503 and the second balance cable 502, the lateral component force generated by the second cable 503 on the second support 501 can be effectively offset, avoiding deformation of the support caused by unilateral force. The use of an even number of second connection nodes 5011 and their symmetrical distribution on both sides of the center line 7 of the steel structure corridor further optimizes the force distribution of each hanging column 302, effectively avoiding the instability of the tension on both sides of the second support 501, thereby enhancing the overall force balance of the second cable tie assembly 5.

[0048] More specifically, the second connection node 5011 is a node plate set on the second support 501. The node plate has multiple bolt holes for threading the connectors of the second balance cable 502 and the second tension cable 503, respectively, to ensure that the tension of the second balance cable 502 and the second tension cable 503 can be stably transmitted to the support structure.

[0049] In one embodiment, a seismic isolation component 6 is provided between the steel structure corridor 3 and the first main structure 1; a seismic isolation component 6 is also provided between the steel structure corridor 3 and the second main structure 2. By providing the seismic isolation component 6, the steel structure corridor 3 can slide and deform slightly to dissipate energy when encountering earthquakes or strong winds, thus avoiding structural damage caused by rigid collisions or excessive stress concentration between the first main structure 1, the second main structure 2, and the corridor.

[0050] More specifically, the seismic isolation component 6 includes: seismic isolation bearings and damping energy dissipation devices. The seismic isolation bearings are arranged between the end steel beams 301 of the steel structure corridor 3 and the corbels of the first main structure vertical member 101 and the second main structure vertical member 201. The upper end of each seismic isolation bearing is rigidly connected to the bottom plate of the corresponding steel beam 301, and the lower end is rigidly connected to the corresponding corbel. The seismic isolation bearings are suitable for bearing all the vertical loads of the steel structure corridor 3 and allow the steel structure corridor 3 to have free displacement relative to the main structure in the horizontal X and Y directions, so as to isolate the seismic action transmitted from the main structure to the steel structure corridor 3, as well as the small-amplitude sliding of the steel structure corridor 3 caused by strong winds; at the same time, they release the additional internal stress caused by temperature deformation, concrete shrinkage and creep, and uneven settlement of the foundation. Damping energy dissipation devices are arranged between the steel beams 301 at the ends of the steel structure corridor 3 and the vertical members 101 and 201 of the first main structure and the second main structure, respectively. One end of the damping energy dissipation device is hinged to the steel beams 301 through the first hinge support, and the other end is hinged to the vertical members 101 or 201 of the first main structure through the second hinge support. The damping energy dissipation devices do not bear any vertical loads. They are only stretched or compressed when there is a relative horizontal displacement between the steel structure corridor 3 and the first main structure 1 or the second main structure 2. They dissipate seismic energy and wind vibration energy through their own deformation and limit the maximum relative displacement between the steel structure corridor 3 and the first main structure 1 or the second main structure 2 to a preset safety range.

[0051] In one embodiment, the steel beam 301 is provided with a plurality of stiffening ribs 3011 at the connection between it and the hanging column 302. The provision of the plurality of stiffening ribs 3011 can effectively enhance the local stiffness of the connection between the steel beam 301 and the hanging column 302. The stiffening ribs 3011 can restrain the local buckling of the steel beam 301 at the connection, thereby improving the load-bearing capacity and stability of the connection node.

[0052] In one embodiment, a support member 3021 is provided at the lower end of the hanging column 302 along the height direction, the support member 3021 being adapted to support the lowest steel beam 301 along the height direction; each layer 303 is provided with floor concrete 304. The provision of the support member 3021 can effectively enhance the supporting stability of the lowest steel beam 301 and evenly transfer the vertical load of the steel beam 301 to the hanging column 302.

[0053] According to an embodiment of the present invention, another aspect provides a construction method suitable for constructing a steel structure connecting corridor system, comprising: S1. Construction of the first main structure 1 and the second main structure 2; S2. Divide the steel beam 301 of the uppermost layer 303 along the height direction into a first steel beam segment and a second steel beam segment; install the first inclined tie assembly 4, the first steel beam segment and the corresponding hanging column 302; and connect the first inclined tie assembly 4 to the hanging column 302; S3. Install the second inclined cable assembly 5, the second steel beam segment, and the corresponding hanging column 302; and fix the second inclined cable assembly 5 to the hanging column 302; at the same time, close the second steel beam segment with the first steel beam segment in step S2; S4. Install the remaining steel beams 301 of the remaining layer 303 sequentially from top to bottom along the height direction, and fix the hanging column 302 to the remaining steel beams 301.

[0054] It should be noted that when installing steel beam 301, the pre-camber value of steel beam 301 should be set in advance. This pre-camber value can be determined by the reverse dismantling method. The reverse dismantling method is to start from the structural construction form and gradually remove the installation components and corresponding loads from back to front in the reverse installation step. The internal forces and deformations of each stage calculated are the internal forces and deformations of the structure under the corresponding forward installation step.

[0055] In one embodiment, each layer 303 is provided with floor concrete 304; after step S4, the floor concrete 304 of the lowest layer 303 along the height direction is poured first. After the floor concrete 304 of the lowest layer 303 is poured, the first inclined tie assembly 4 and the second inclined tie assembly 5 are subjected to the first prestress tensioning; after the first prestress tensioning is completed, the floor concrete 304 of each layer 303 is poured sequentially from bottom to top along the height direction; after the floor concrete 304 of the top layer 303 along the height direction is completed, the first inclined tie assembly 4 and the second inclined tie assembly 5 are subjected to the second prestress tensioning.

[0056] In one embodiment, the steel components of the steel structure corridor 3, the first cable 403, the second cable 503, the first balance cable 402, the second balance cable 502, the first support 401, and the second support 501 can all be prefabricated in the factory and assembled on site, eliminating the need for complex formwork and large-scale cast-in-place work. The tension of the first cable 403 and the second cable 503 can automatically increase in real time with the progress of concrete pouring, eliminating the need for manual tensioning with specialized equipment. Combined with real-time monitoring data during construction, the deflection of the steel beam 301 and the floor concrete 304 can be more precisely controlled, effectively improving construction accuracy.

[0057] After the bottommost layer 303 floor concrete 304 is poured first, the first prestressing tensioning is carried out. This relies on the reliable support of the lower concrete layer to effectively transfer the prestress of the cable-stayed components to the main structure, preventing excessive deformation or stress concentration due to insufficient bottom stiffness during tensioning. The remaining layers 303 floor concrete 304 are poured in a bottom-up sequence, combined with the pre-stressed cable-stayed components, ensuring a stable stress state for each layer 303 during pouring, reducing cumulative deformation during construction, and improving the safety and controllability of the construction process. Finally, after the topmost layer 303 floor concrete 304 is completed, a second prestressing tensioning is carried out. This allows for secondary adjustments based on the actual stress conditions after the steel structure corridor 3 is fully formed, further optimizing the internal force distribution between the cable-stayed components, steel beams 301, and hanging columns 302. This ensures that the stiffness and load-bearing capacity of the entire steel structure corridor 3 are fully utilized, ultimately guaranteeing the long-term stability and safety of the structure during its service life.

[0058] Although embodiments of the invention have been described in conjunction with the accompanying drawings, those skilled in the art can make various modifications and variations without departing from the spirit and scope of the invention, and such modifications and variations all fall within the scope defined by the appended claims.

Claims

1. A steel structure connecting corridor system, characterized in that, include: First main structure (1); Second main structure (2); A steel structure corridor (3) is adapted to connect the first main structure (1) and the second main structure (2); the steel structure corridor (3) includes at least two levels (303) and multiple hanging columns (302); the at least two levels (303) are arranged at intervals along the height direction; each level (303) includes multiple steel beams (301), the multiple steel beams (301) are arranged horizontally, one end is connected to the first main structure (1), and the other end is connected to the second main structure (2); the multiple hanging columns (302) pass through the multiple steel beams (301) along the height direction and are fixedly connected to the steel beams (301); The first inclined cable assembly (4) is disposed on the top surface of the first main structure (1) along the height direction and is connected to the top surface of the plurality of hanging columns (302) along the height direction. The second inclined cable assembly (5) is disposed on the top surface of the second main structure (2) along the height direction and is connected to the top surface of the plurality of hanging columns (302) along the height direction.

2. The steel structure connecting corridor system according to claim 1, characterized in that, The first cable-stayed assembly (4) includes: a first support (401), a plurality of first balancing cables (402) and a plurality of first tension cables (403); the first support (401) is disposed on the top surface of the first main structure (1) along the height direction and is connected to the first main structure (1); one end of the plurality of first tension cables (403) is connected to the first support (401) and the other end is connected to the hanging column (302); each first tension cable (403) is connected to one hanging column (302); the plurality of first balancing cables (402) are disposed on the side of the first support (401) away from the plurality of first tension cables (403); one end of the plurality of first balancing cables (402) is connected to the first main structure (1) and the other end is connected to the first support (401).

3. A steel structure connecting corridor system according to claim 2, characterized in that, The first support (401) is provided with at least one first connecting node (4011); the first connecting node (4011) is adapted to be connected to the first balance cable (402) and the first cable (403); when the number of first connecting nodes (4011) is ≥2, the number of first connecting nodes (4011) is even and symmetrically distributed on both sides of the center line (7) of the steel structure corridor; multiple hanging columns (302) located on one side of the center line (7) of the steel structure corridor are connected to the first connecting node (4011) on the same side.

4. The steel structure connecting corridor system according to claim 1, characterized in that, The second cable-stayed assembly (5) includes: a second support (501), a plurality of second balancing cables (502) and a plurality of second tension cables (503); the second support (501) is disposed on the top surface of the second main structure (2) along the height direction and is connected to the second main structure (2); one end of the plurality of second tension cables (503) is connected to the second support (501) and the other end is connected to the hanging column (302); each second tension cable (503) is connected to one hanging column (302); the plurality of second balancing cables (502) are disposed on the side of the second support (501) away from the plurality of second tension cables (503); one end of the plurality of second balancing cables (502) is connected to the second main structure (2) and the other end is connected to the second support (501).

5. A steel structure connecting corridor system according to claim 4, characterized in that, The second support (501) is provided with at least one second connection node (5011); the second connection node (5011) is adapted to be connected to the second balance cable (502) and the second cable (503); when the number of second connection nodes (5011) is ≥2, the number of second connection nodes (5011) is even and symmetrically distributed on both sides of the center line (7) of the steel structure corridor; multiple hanging columns (302) located on one side of the center line (7) of the steel structure corridor are connected to the second connection node (5011) on the same side.

6. A steel structure connecting corridor system according to claim 1, characterized in that, A vibration damping and isolation component (6) is provided between the steel structure corridor (3) and the first main structure (1); a vibration damping and isolation component (6) is provided between the steel structure corridor (3) and the second main structure (2).

7. A steel structure connecting corridor system according to claim 1, characterized in that, The steel beam (301) is provided with a plurality of stiffening ribs (3011) at the connection with the hanging column (302).

8. A steel structure connecting corridor system according to claim 1, characterized in that, The lower end of the hanging column (302) along the height direction is provided with a support member (3021), which is adapted to support the steel beam (301) at the lowest level along the height direction; each level (303) is provided with floor concrete (304).

9. A construction method, characterized in that, A steel structure connecting corridor system suitable for construction according to any one of claims 1 to 8, comprising: S1. Construct the first main structure (1) and the second main structure (2); S2. The steel beam (301) of the uppermost layer (303) along the height direction is divided into a first steel beam segment and a second steel beam segment; Install the first cable-stayed assembly (4), the first steel beam segment and the corresponding hanging column (302); and connect the first cable-stayed assembly (4) to the hanging column (302); S3. Install the second inclined cable assembly (5), the second steel beam segment and the corresponding hanging column (302); and fix the second inclined cable assembly (5) to the hanging column (302); at the same time, close the second steel beam segment with the first steel beam segment in step S2; S4. Install the remaining steel beams (301) of the remaining layer (303) sequentially from top to bottom along the height direction, and fix the hanging column (302) to the remaining steel beams (301).

10. A construction method according to claim 9, characterized in that, Each of the aforementioned layers (303) is provided with floor concrete (304); after step S4, the floor concrete (304) of the lowest layer (303) along the height direction is poured first. After the floor concrete (304) of the lowest layer (303) is poured, the first inclined tie assembly (4) and the second inclined tie assembly (5) are subjected to the first prestress tensioning; after the first prestress tensioning is completed, the floor concrete (304) of each layer (303) is poured sequentially from bottom to top along the height direction; after the floor concrete (304) of the top layer (303) along the height direction is completed, the first inclined tie assembly (4) and the second inclined tie assembly (5) are subjected to the second prestress tensioning.