Medical logistics track and mineral wool board suspended ceiling fixed transfer method

By introducing a ceiling transition layer system, a flexible isolation layer, and rubber spring shock absorbers into the medical logistics track and mineral wool board ceiling system, the problems of force interference and noise between the logistics track and the mineral wool board ceiling system are solved, achieving force separation and noise reduction effects, and ensuring the stability and airtightness of the ceiling system.

CN123133522APending Publication Date: 2026-11-20BEIJING CHENGJIANQI CONSTRUCT ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611297673.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-25
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

The existing medical logistics track and mineral wool board ceiling system have problems with structural interference and failure to separate forces during installation and handover. This leads to deformation and sagging of the mineral wool board ceiling system and mechanical noise. Furthermore, the assembly gaps cannot absorb displacement, resulting in airtightness failure.

Method used

By arranging a ceiling transition layer system, using fully toothed galvanized independent hangers to fix the main keel cross bracing, installing a flexible isolation layer and rubber spring shock absorbers, suspending and fixing the logistics horizontal track, and installing edge keels and sealant to fill the gaps at the junction interface, stress separation and vibration reduction and noise reduction are achieved.

Benefits of technology

It effectively avoids deformation of the mineral wool board ceiling system due to load, reduces mechanical noise, maintains the flatness and airtightness of the ceiling system, and meets the cleanliness requirements of the medical environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133522A_ABST
    Figure CN123133522A_ABST
Patent Text Reader

Abstract

The application relates to the technical fields of building construction and medical equipment installation, and discloses a medical logistics track and mineral wool board suspended ceiling fixed transfer method, which comprises the following steps: arranging a suspended ceiling conversion layer system, fixing a main keel cross brace on the top of a mineral wool board through a full-tooth galvanized independent suspender, bearing the load of a logistics horizontal track and a logistics trolley by the main keel cross brace, and separating the stress of the mineral wool board suspended ceiling system and the suspended ceiling conversion layer system; deploying a transverse isolation component, installing a flexible isolation layer between the main keel cross brace and the screw rod of the mineral wool board suspended ceiling system; suspending and fixing the logistics horizontal track and deploying a damping component, fixing the screw rod of the logistics system to the main keel cross brace by a connecting piece, installing a rubber spring shock absorber, and connecting the logistics horizontal track to the lower side of the beam of the logistics system by a C-shaped clamp; performing interface closing, installing side keels, and filling the gap between the side keels and the mineral wool board by sealing glue. The application avoids the drooping of the mineral wool board and reduces the vibration and noise generated during the operation of the logistics system.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction and medical equipment installation technology, specifically a method for fixing and connecting medical logistics tracks to mineral wool board ceilings. Background Technology

[0002] In the construction of medical buildings, hospitals are usually equipped with track-type medical logistics systems. The horizontal tracks of the medical logistics system need to be arranged to intersect with the interior ceiling plane. Currently, mineral wool board ceiling systems are commonly used as the interior ceiling structure in medical buildings.

[0003] Existing logistics horizontal tracks and mineral wool board ceiling systems have defects such as structural interference and failure to separate forces during installation and handover. Traditional construction methods often involve the supporting components of the logistics horizontal track and the keel of the mineral wool board ceiling system sharing the load, or the metal components of the logistics horizontal track directly contacting the mineral wool board ceiling system. When the logistics trolley runs on the logistics horizontal track, the gravity load and mechanical vibration generated by the logistics horizontal track are directly transmitted to the mineral wool board ceiling system. The mineral wool board has low structural strength, and after the mineral wool board ceiling system bears the additional load transmitted by the logistics horizontal track, it is prone to deformation and local sagging.

[0004] The lateral and vertical vibrations generated by the operation of the logistics trolley can cause metal-to-metal collisions between the supporting components and the lead screws of the mineral wool ceiling system, producing mechanical noise. Traditional methods of handling the junction rely on direct cutting and assembly, resulting in unsealed assembly gaps between the logistics horizontal track and the mineral wool ceiling. These gaps cannot absorb the relative displacement caused by the forces acting on them, leading to rigid collisions. The unsealed gaps also compromise the airtightness of the mineral wool ceiling system and cause material debris from the cut edges of the mineral wool to scatter, failing to meet the cleanliness requirements of medical environments. Therefore, this invention proposes a method for fixing and connecting medical logistics tracks and mineral wool ceiling panels to address the shortcomings of existing technologies. Summary of the Invention

[0005] The purpose of this invention is to provide a method for fixing and connecting medical logistics tracks and mineral wool board ceilings, which solves the problems in existing construction methods where the mixed stress of the logistics horizontal track and the mineral wool board ceiling system causes the mineral wool board to deform and sag, and the vibration of the logistics trolley causes direct collisions of metal parts, resulting in mechanical noise.

[0006] To achieve the above objectives, the present invention provides the following technical solution:

[0007] A method for fixing and connecting a medical logistics track to a mineral wool board ceiling includes the following steps:

[0008] A ceiling transition layer system is arranged, and the main keel cross bracing is fixed in the space above the mineral wool board by fully toothed galvanized independent hangers. The main keel cross bracing is used to bear the load generated by the logistics horizontal track and logistics trolley, so that the mineral wool board ceiling system and the ceiling transition layer system are structurally separated.

[0009] Deploy a horizontal isolation component and install a flexible isolation layer between the main keel cross brace and the threaded rod of the mineral wool board ceiling system;

[0010] The logistics horizontal track is suspended and fixed, and a vertical shock absorption component is deployed. The logistics system screw is fixed to the main keel cross brace using a connector, and a rubber spring shock absorber is installed at the connection position between the logistics system screw and the connector. The logistics system crossbeam is assembled at the lower end of the logistics system screw, and the logistics horizontal track is connected to the lower part of the logistics system crossbeam using a C-clamp.

[0011] The handover interface is closed by installing side keels along the entire length of the horizontal logistics track at the junction of the horizontal logistics track and the mineral wool board, and filling the gaps between the side keels and the mineral wool board, as well as between the side keels and the horizontal logistics track, with sealant.

[0012] Preferably, the arrangement of the suspended ceiling transition layer system specifically includes:

[0013] Install fully threaded hangers with matching expansion bolts on the bottom surface of the structural floor slab;

[0014] Screw the top of the fully toothed galvanized independent hanger into the expansion bolts that are matched with the fully toothed hanger;

[0015] A matching hanger bracket is fixedly installed at the bottom end of the fully toothed galvanized independent hanger rod. The main keel cross brace is placed inside the matching hanger bracket, and the fastening bolts on the matching hanger bracket are tightened.

[0016] Multiple main keel cross braces are distributed at intervals along the direction of the logistics horizontal track, and the length direction of the main keel cross braces is perpendicular to the direction of the logistics horizontal track and they are arranged parallel to each other.

[0017] The horizontal height of the main keel cross brace is higher than the horizontal height of the mineral wool board, and a physical gap is maintained between the main keel cross brace and the threaded rod and matching keel of the mineral wool board ceiling system;

[0018] The suspended ceiling transfer layer system alters the force transmission path of the logistics trolley's running weight. All forces generated by the horizontal logistics track are transmitted via the main keel cross braces to the fully toothed galvanized independent hangers, and ultimately to the structural floor slab. The mineral wool board ceiling system bears only its own weight, thus separating the source of force and preventing the mineral wool board from sagging due to overload.

[0019] Preferably, after the top end of the fully threaded galvanized independent suspender is screwed into the expansion bolt matched with the fully threaded suspender, the method further comprises:

[0020] Screw in the matched anti-loosening lock nut and push it upward to fasten to the bottom end of the expansion bolt matched with the fully threaded suspender.

[0021] Preferably, deploying a lateral isolation assembly, and installing a flexible isolation layer between the main keel cross brace and the screw rod of the mineral wool ceiling system specifically comprises:

[0022] Select the flexible isolation layer according to the size of the net spatial gap between the end of the main keel cross brace and the adjacent screw rod of the mineral wool ceiling system, and the thickness of the flexible isolation layer in the natural state is less than or equal to the size of the net spatial gap;

[0023] Arrange the flexible isolation layer on the end face of the side of the main keel cross brace facing the screw rod of the mineral wool ceiling system;

[0024] The flexible isolation layer adopts an ethylene propylene diene monomer rubber pad, a silicone rubber pad, a felt buffer layer or a foamed polyurethane pad;

[0025] The flexible isolation layer is used to fill the gap between the main keel cross brace and the screw rod of the mineral wool ceiling system. When the logistics trolley generates a lateral vibration force, the main keel cross brace undergoes lateral displacement and squeezes the flexible isolation layer. The flexible isolation layer prevents direct collision between the end of the main keel cross brace and the screw rod of the mineral wool ceiling system, limits the swing amplitude of the main keel cross brace, and reduces the noise generated by impact.

[0026] Preferably, suspending and fixing the horizontal logistics track and deploying a vertical damping assembly, fixing the logistics system screw rod to the main keel cross brace by using a connecting member, installing a rubber spring shock absorber at the connection position between the logistics system screw rod and the connecting member, and assembling the logistics system cross beam to the lower end of the logistics system screw rod specifically comprises:

[0027] The connecting member is a hollow square frame structure with coaxially corresponding reserved bolt holes machined on both the upper end face and the lower end face, and the connecting member is closely fixed to the side face of the main keel cross brace;

[0028] The top end of the logistics system screw rod sequentially passes through the reserved bolt hole on the lower end face of the connecting member and the reserved bolt hole on the upper end face of the connecting member from bottom to top, the rubber spring shock absorber is sleeved on the logistics system screw rod, and a fastening nut is screwed into the top end of the logistics system screw rod, so that the rubber spring shock absorber is located between the fastening nut and the bottom face of the inner cavity of the connecting member;

[0029] A fastening nut is screwed into the position where the lead screw of the logistics system passes through the lower end face of the connector, and a space gap is reserved for the fastening nut to the downward.

[0030] After the lead screw of the logistics system penetrates the crossbeam of the logistics system, fastening nuts are screwed into the top and bottom of the crossbeam of the logistics system. By rotating the fastening nuts above and below the crossbeam of the logistics system clockwise or counterclockwise, the locking position of the crossbeam of the logistics system on the lead screw of the logistics system is changed, thereby driving the crossbeam of the logistics system to rise or fall as a whole.

[0031] The rubber spring shock absorber is located in the direction perpendicular to the force applied, and undergoes elastic deformation to dissipate vibration energy, blocking the transmission of vibration to the ceiling transfer layer system and the structural floor slab. The rubber spring shock absorber, combined with the flexible isolation layer, provides vibration damping in both vertical and horizontal directions, maintaining the flatness and stability of the mineral wool board.

[0032] Preferably, the logistics system beam is provided with a pressure-resistant metal sleeve pre-welded inside, or a pressure-bearing steel gasket is provided between the fastening nut and the surface of the logistics system beam.

[0033] Preferably, connecting the horizontal logistics track to the underside of the logistics system beam using C-clamps specifically includes:

[0034] The main body of the symmetrically distributed C-shaped clamps is attached to the vertical surface at the intersection of the horizontal logistics track and the crossbeam of the logistics system on both sides.

[0035] The upper edge of the C-clamp is fastened to the upper edge of the crossbeam of the logistics system;

[0036] The lower corner of the C-clamp is inserted into the bottom surface of the pre-formed longitudinal force-bearing flange on both sides of the top of the horizontal logistics track;

[0037] Tighten the transverse fastening bolts on both sides of the C-clamp to force the C-clamp to move outward as a whole, so that the upper end of the C-clamp and the lower end locking corner lock the logistics system beam and the logistics horizontal track.

[0038] Tightening the transverse fastening bolts creates clamping force on both the upper and lower sides of the C-clamp, which, combined with the symmetrical arrangement on both sides, locks the horizontal logistics track and the logistics system beam into a single unit. The C-clamps are used for external connection, avoiding drilling or welding on the logistics system beam and the horizontal logistics track, thus maintaining the flatness of the horizontal logistics track's running surface.

[0039] Preferably, the specific steps of performing the handover interface closing include:

[0040] The vertical side wings of the edge keel are anchored to the side of the metal angle bracket that is pre-fixed to the cross brace of the main keel and extends downward, or the vertical side wings of the edge keel are anchored to the adjacent building wall.

[0041] The horizontal wings of the side keel cover the area below the structural gap formed between the edge of the logistics horizontal track and the edge of the mineral wool board, forming a support space below the edge of the mineral wool board;

[0042] The sealant is continuously squeezed into the assembly gap between the horizontal side wing edge of the side keel and the cut edge of the mineral wool board, and into the assembly gap between the horizontal side wing edge of the side keel and the side wall of the logistics horizontal track.

[0043] The edge keel conceals the threaded rods, crossbeams, C-clamps, and connectors of the logistics system located above the ceiling. The sealant absorbs relative displacements caused by stress or temperature changes in the various systems, preventing rigid collisions between the edge keel and the mineral wool board. The sealant also seals airflow channels, maintaining the airtightness of the ceiling system. The edge keel and the sealant form a support below the edge of the mineral wool board, preventing debris from falling off while preserving the disassembly and maintenance capabilities of the mineral wool board ceiling system.

[0044] Preferably, an L-shaped or U-shaped metal profile is used as the edge keel; when the sealant is squeezed into the assembly gap for filling, the injection depth is controlled to be between 0.5 and 1 times the width of the assembly gap.

[0045] In summary, the present invention has at least one of the following beneficial technical effects:

[0046] 1. This invention arranges a ceiling transition layer system and uses fully toothed galvanized independent hangers to fix the main keel cross brace. The main keel cross brace bears the load generated by the logistics horizontal track and logistics trolley, so that the mineral wool board ceiling system and the ceiling transition layer system are separated in terms of force transmission. The mineral wool board ceiling system only bears the physical weight of the mineral wool board itself, avoiding local sagging of the mineral wool board due to the additional load of the logistics system, and maintaining the overall flatness of the ceiling.

[0047] 2. This invention deploys horizontal isolation components and vertical damping components, installs a flexible isolation layer between the main keel cross brace and the threaded rod of the mineral wool board ceiling system, and simultaneously installs rubber spring shock absorbers at the connection points of the logistics system threaded rods. The flexible isolation layer restricts the lateral displacement of the main keel cross brace and prevents direct metal-to-metal collisions, while the rubber spring shock absorbers dissipate the mechanical vibration energy in the vertical direction. The flexible isolation layer and the rubber spring shock absorbers work together to reduce the mechanical noise generated during the operation of the logistics trolley and block the transmission of vibration to the structural floor slab and the mineral wool board ceiling system.

[0048] 3. In this invention, edge keel is installed at the junction and sealant is used to fill the gap between edge keel, mineral wool board and logistics horizontal track. The edge keel covers the various installation components in the concealed space and forms physical support under the edge of mineral wool board to prevent the edge material of mineral wool board from falling off. The sealant absorbs the relative displacement of each independent system caused by force or temperature difference, avoids rigid collision between edge keel and mineral wool board, and seals the airflow channels above and below mineral wool board to maintain the overall airtightness of ceiling system. Attached Figure Description

[0049] Figure 1 This is a planar schematic diagram of the present invention;

[0050] Figure 2 This is a partial schematic diagram of the sealing structure at the junction of the horizontal logistics track and the mineral wool board according to the present invention;

[0051] Figure 3 This is a schematic diagram of the overall method flow of the present invention;

[0052] Figure 4 This is a schematic diagram of the process for arranging the ceiling transition layer according to the present invention;

[0053] Figure 5 This is a schematic diagram of the process for deploying the vibration damping and isolation components of the present invention.

[0054] The components include: 1. Structural floor slab; 2. Mineral wool board ceiling system; 3. Mineral wool board; 4. T-shaped keel; 5. Ceiling transition layer system; 6. Rubber spring shock absorber; 7. Logistics system threaded rod; 8. Logistics system crossbeam; 9. Logistics horizontal track; 10. Logistics trolley; 11. EPDM rubber pad; 12. Edge keel; 13. Sealant; 14. C-clamp; 15. Connector; 21. Expansion bolt; 22. Threaded rod; 23. Matching keel; 51. Fully threaded hanger with matching expansion bolt; 52. Fully threaded galvanized independent hanger; 53. Main keel cross brace. Detailed Implementation

[0055] The following is in conjunction with the appendix Figure 1 -Appendix Figure 5 The present invention will be further described in detail below.

[0056] Please see Figures 1-2 This invention provides a medical logistics track and mineral wool board ceiling fixing and connection device, including: structural floor slab 1, mineral wool board ceiling system 2, mineral wool board 3, T-shaped keel 4, ceiling transition layer system 5, rubber spring shock absorber 6, logistics system screw rod 7, logistics system crossbeam 8, logistics horizontal track 9, logistics trolley 10, EPDM rubber pad 11, edge keel 12, sealant 13, C-clamp 14, and connector 15.

[0057] The mineral wool board ceiling system 2 includes expansion bolts 21, threaded rods 22, matching keel 23, and T-shaped keel 4. The threaded rods 22 are fixed to the structural floor slab 1 by the expansion bolts 21. The threaded rods 22 are connected to the matching keel 23 by matching hangers. The matching keel 23 adopts a 38-type large keel. The T-shaped keel 4 is suspended below the matching keel 23 to form a grid frame. The mineral wool board 3 is connected to the structural floor slab 1 by the expansion bolts 21, threaded rods 22, matching keel 23, and T-shaped keel 4. The mineral wool board 3 is flush with the edge of the logistics horizontal track 9.

[0058] The ceiling transition layer system 5 is set above the mineral wool board 3. The ceiling transition layer system 5 includes a fully threaded hanger with expansion bolts 51, a fully threaded galvanized independent hanger 52, and a main keel cross brace 53. The fully threaded galvanized independent hanger 52 is fixed to the structural floor slab 1 by the fully threaded hanger with expansion bolts 51, and the fully threaded galvanized independent hanger 52 is connected to the main keel cross brace 53 by matching hangers.

[0059] The logistics system lead screw 7 is connected to the main keel cross brace 53 of the ceiling conversion layer system 5 through the connector 15. The connector 15 is an aluminum alloy square frame. Bolt holes are provided on the upper and lower ends of the connector 15. The logistics system lead screw 7 passes through the connector 15 and is fixed to the connector 15 by nuts and washers set on the upper and lower ends of the connector 15.

[0060] The logistics system crossbeam 8 is a square steel made according to the width of the logistics horizontal track 9. Symmetrical through holes are set on the logistics system crossbeam 8 according to the position of the logistics system screw 7. The logistics system screw 7 passes through the through holes on the logistics system crossbeam 8. The logistics system screw 7 is fixed above and below the logistics system crossbeam 8 with nuts and washers. C-clamp 14 is used to connect the logistics horizontal track 9 and the logistics system crossbeam 8. The upper opening of the C-clamp 14 hooks onto the logistics system crossbeam 8, and the lower opening of the C-clamp 14 uses a corner clamp to clamp the longitudinal force-bearing flanges on both sides of the upper edge of the logistics horizontal track 9.

[0061] Rubber spring shock absorber 6 is installed between the threaded rod 7 and the connector 15 of the logistics system. EPDM rubber pad 11 is installed at one end of the main keel cross brace 53. The end of the main keel cross brace 53 with EPDM rubber pad 11 is adjacent to the threaded rod 22 of the mineral wool board ceiling system 2.

[0062] The edge keel 12 is arranged at the junction of the logistics horizontal track 9 and the mineral wool board 3. The edge keel 12 is an L-shaped metal profile or a U-shaped metal profile. One side of the edge keel 12 is fixed to the main keel cross brace 53 of the ceiling conversion layer system 5 or the wall surface by a downward extending metal corner bracket or secondary keel. The other side of the edge keel 12 covers the gap between the logistics horizontal track 9 and the mineral wool board 3. The sealant 13 is filled between the edge keel 12 and the mineral wool board 3.

[0063] Please see Figure 1 , Figure 2 and Figure 3 This invention provides a method for fixing and connecting a medical logistics track to a mineral wool board ceiling, comprising the following steps:

[0064] S10, the ceiling transition layer system 5 is arranged. The main keel cross brace 53 is fixed in the space above the mineral wool board 3 by the fully toothed galvanized independent hanger 52. The main keel cross brace 53 is used to bear the load generated by the logistics horizontal track 9 and the logistics trolley 10, so that the mineral wool board ceiling system 2 and the ceiling transition layer system 5 are structurally separated.

[0065] S20, deploy shock absorption and isolation components, install EPDM rubber pads 11 between the main keel cross brace 53 and the screw rod 22 of the mineral wool board ceiling system 2, and install rubber spring shock absorbers 6 at the connection position between the screw rod 7 of the logistics system and the connector 15.

[0066] S30, suspend and fix the horizontal logistics track 9, use the connector 15 to fix the logistics system screw 7 to the main keel cross brace 53, assemble the logistics system cross beam 8 at the lower end of the logistics system screw 7, and use the C-clamp 14 to connect the logistics horizontal track 9 to the lower part of the logistics system cross beam 8.

[0067] S40, perform the junction interface sealing, install side keel 12 on both sides of the logistics horizontal track 9 at the junction of logistics horizontal track 9 and mineral wool board 3, and use sealant 13 to fill the gap between side keel 12 and mineral wool board 3 and between side keel 12 and logistics horizontal track 9.

[0068] See attached document Figure 4 Step S10 specifically includes the following sub-steps:

[0069] S11, install the full-threaded hanger expansion bolt 51 on the bottom surface of the structural floor slab 1. In the concealed space above the mineral wool board 3, the construction personnel determine a series of installation and fixing points according to the planned direction of the horizontal logistics track 9. The construction personnel drill holes in the structural floor slab 1 at the determined installation and fixing points, and insert the full-threaded hanger expansion bolt 51 into the holes drilled in the structural floor slab 1, with the threaded end of the full-threaded hanger expansion bolt 51 facing downwards. For the construction process of drilling holes and inserting fasteners in solid concrete floor slabs, those skilled in the art can operate in accordance with conventional building electromechanical installation specifications. The specific drilling action and the tightening and fixing action of the full-threaded hanger expansion bolt 51 are well-known technologies in the field and will not be described in detail.

[0070] The expansion bolt 51 of the fully threaded hanger serves as the top stress point of this connection system. The expansion bolt 51 of the fully threaded hanger bears all the dynamic and static loads transmitted from the logistics horizontal track 9 and the logistics trolley 10. The expansion bolt 51 of the fully threaded hanger achieves the anchoring effect of preventing downward pull-out by the huge friction and mechanical locking force generated by the expansion of its internal expansion tube and the concrete hole wall of the floor slab.

[0071] S12, Install the fully threaded galvanized independent hanger 52. The fully threaded galvanized independent hanger 52 serves as the vertical load-bearing member in this handover method. Screw the top of the fully threaded galvanized independent hanger 52 into the internal thread of the fully threaded hanger expansion bolt 51. To prevent the mechanical vibration generated during long-term operation of the logistics trolley 10 from causing the threaded connection to loosen, after screwing the fully threaded hanger expansion bolt 51 into the top of the fully threaded galvanized independent hanger 52, screw in the matching anti-loosening lock nut and tighten it upwards to the bottom end of the fully threaded hanger expansion bolt 51. Utilizing the continuous thread structure on the surface of the fully threaded galvanized independent hanger 52, the construction personnel can achieve stepless vertical adjustment of the horizontal height of the bottom end of the fully threaded galvanized independent hanger 52 by cutting the length of the fully threaded galvanized independent hanger 52 or by rotating and adjusting the engagement depth of the fully threaded galvanized independent hanger 52 in the fully threaded hanger expansion bolt 51, according to the actual net height of the internal space of the mineral wool board ceiling system 2.

[0072] S13, Install the main keel cross brace 53. The main keel cross brace 53 serves as the horizontal load-bearing transfer component in this handover method. A matching hanger is fixedly assembled at the bottom end of the fully toothed galvanized independent hanger 52. The matching hanger typically uses U-shaped or C-shaped metal clips. The main keel cross brace 53 is placed inside the matching hanger, and the fastening bolts on the matching hanger are tightened. The main keel cross brace 53 is securely suspended from the bottom end of the fully toothed galvanized independent hanger 52 via the matching hanger. Multiple main keel cross braces 53 are spaced apart along the direction of the horizontal logistics track 9, and their length direction is perpendicular to the horizontal track. The horizontal logistics track 9 runs parallel to each other. Before tightening the matching hanging brackets, the construction personnel need to use the original plane height of the mineral wool board 3 as the elevation positioning benchmark. By fine-tuning the position of the fastening nut at the lower end of the fully toothed galvanized independent hanger 52, all the main keel cross braces 53 are on the same horizontal plane. This ensures that the edge of the subsequently installed horizontal logistics track 9 can be flush with the edge of the mineral wool board 3. The multiple main keel cross braces 53 together form a secondary force conversion platform that is independent of the mineral wool board ceiling system 2.

[0073] The secondary force conversion platform formed by the main keel cross brace 53 is set independently in space. The fully toothed galvanized independent hanger 52 and the main keel cross brace 53 are not intersected or penetrated with the threaded rod 22 and the matching keel 23 of the mineral wool board ceiling system 2 in spatial arrangement. The working principle of this structure is to cut off the force transmission path of the running weight of the logistics trolley 10. In the traditional ceiling connection process, the auxiliary equipment is usually directly hung on the ceiling keel, which causes the lighter ceiling panel to sag or even crack locally because it cannot withstand the concentrated load.

[0074] By setting up the main keel cross brace 53, the force generated by the logistics horizontal track 9 is transmitted from the main keel cross brace 53 to the fully toothed galvanized independent hanger 52, and finally transmitted to the structural floor slab 1 by the fully toothed galvanized independent hanger 52. The mineral wool board ceiling system 2 only bears the physical weight of the mineral wool board ceiling system 2 itself, so that the force network of the logistics system is completely separated from the force network of the ceiling system, and the structural separation of the load source is achieved.

[0075] S14. Establish the independent spatial position of the main keel cross brace 53. The construction personnel arrange the main keel cross brace 53 in the concealed space above the mineral wool board 3. The horizontal height of the main keel cross brace 53 is higher than that of the mineral wool board 3. A physical gap is maintained between the main keel cross brace 53 and the threaded rod 22 and matching keel 23 of the mineral wool board ceiling system 2. The main keel cross brace 53 does not have direct rigid physical contact with the metal components of the mineral wool board ceiling system 2 in space. The spatial physical gap ensures that the main keel cross brace 53 will not squeeze the internal components of the mineral wool board ceiling system 2 downward when it undergoes slight deformation under load.

[0076] S15, construct an independent force transmission path for the main keel cross brace 53. The secondary conversion layer refers to the intermediate force isolation layer added between the structural floor slab 1 and the logistics horizontal track 9. The logistics horizontal track 9 is fixedly suspended below the main keel cross brace 53. When the logistics trolley 10 runs on the logistics horizontal track 9, the vertical downward gravity load generated by the logistics trolley 10 and the horizontal side load brought by the operation of the logistics trolley 10 are all transferred to the logistics horizontal track 9. The logistics horizontal track 9 transfers the above loads upward to the main keel cross brace 53. The main keel cross brace 53, as a horizontal load-bearing node, converts the received load into a vertical upward tensile force and transfers the tensile force to the fully toothed galvanized independent hanger 52. The fully toothed galvanized independent hanger 52 transmits all the loads to the structural floor slab 1. The above independent mechanical arrangement realizes the force separation between the logistics track system and the mineral wool board ceiling system 2 with limited load-bearing capacity, preventing the mineral wool board from sagging due to overload.

[0077] See attached document Figure 5 Step S20 specifically includes the following sub-steps:

[0078] S21, Install EPDM rubber pads 11. The main keel cross brace 53 and the threaded rod 22 of the mineral wool ceiling system 2 are spatially close to each other. Before installation, the construction personnel select EPDM rubber pads 11 of appropriate thickness based on the actual net spatial clearance between the end of the main keel cross brace 53 and the adjacent threaded rod 22 of the mineral wool ceiling system 2. The natural thickness of the EPDM rubber pad 11 should be less than or equal to the aforementioned net spatial clearance to ensure that the EPDM rubber pad 11 will not exert a continuous initial lateral compressive force on the threaded rod 22 of the mineral wool ceiling system 2 after installation. The EPDM rubber pad 11 is arranged on one end face of the threaded rod 22 of the main keel cross brace 53 facing the mineral wool board ceiling system 2. The EPDM rubber pad 11 can be fixed to the end face of the main keel cross brace 53 by adhesive, or the EPDM rubber pad 11 can be fixed to the end face of the main keel cross brace 53 by mechanical fasteners. For the construction process of pasting or snapping rubber buffer pads on the surface of metal components, those skilled in the art can operate in accordance with conventional building electromechanical vibration reduction specifications. The specific pasting or snapping actions are well known in the art and will not be described in detail here.

[0079] The EPDM rubber pad 11 fills the gap between the main keel cross brace 53 and the lead rod 22 of the mineral wool ceiling system 2. The EPDM rubber pad 11 acts as a flexible buffer layer between the main keel cross brace 53 and the lead rod 22 of the mineral wool ceiling system 2. When the logistics trolley 10 starts to accelerate, brakes to decelerate, or passes through the curved track section on the logistics horizontal track 9, the instantaneous inertial force generated by the logistics trolley 10 is converted into a horizontal lateral excitation force. The above-mentioned lateral excitation force is transmitted upward, causing the main keel cross brace 53 to undergo a slight lateral swing displacement. When the main keel cross brace 53 undergoes lateral displacement, the main keel cross brace 53 preferentially squeezes the EPDM rubber pad 11. The EPDM rubber pad 11 prevents the metal end of the main keel cross brace 53 from directly colliding with the lead rod 22 of the mineral wool ceiling system 2, thus eliminating the mechanical noise and wear caused by the metal impact.

[0080] S22, assemble the rubber spring shock absorber 6. The connector 15 is an aluminum alloy square frame with bolt holes at both the upper and lower ends. The construction personnel place the rubber spring shock absorber 6 at the assembly node between the logistics system screw 7 and the connector 15. The top end of the logistics system screw 7 passes through the bolt holes at the lower and upper ends of the connector 15. The construction personnel then fit the rubber spring shock absorber 6 onto the logistics system screw 7. The rubber spring shock absorber 6 is located between the fastening nut at the top of the logistics system screw 7 and the bottom surface of the inner cavity of the connector 15. During tightening, the construction personnel need to control the depth to which the fastening nut is screwed down into the logistics system screw 7 to ensure that the rubber spring shock absorber 6 is in the initial pre-compression state but has not reached the compression limit, thereby reserving an effective elastic compression stroke for absorbing dynamic vibrations.

[0081] The high-frequency micro-amplitude vibration generated by the rolling friction between the wheels of the logistics trolley 10 and the surface of the logistics horizontal track 9 is transmitted upward along the logistics system screw 7. The above vibration causes the logistics system screw 7 to move at high frequency in the vertical direction, and generates an alternating vertical compressive force on the rubber spring shock absorber 6. The rubber polymer material inside the rubber spring shock absorber 6 undergoes repeated elastic deformation under the action of alternating stress. Due to the inherent viscoelastic hysteresis characteristics of the rubber material, the mechanical vibration energy is converted into heat energy and dissipated during the friction process inside the rubber material. In this way, the rubber spring shock absorber 6 cuts off the physical path for the high-frequency vibration to continue to be transmitted to the ceiling conversion layer system 5 and the structural floor slab 1, thereby achieving the overall vibration reduction and noise reduction purpose of the system.

[0082] S23, Spatial Position of the Dual Vibration Damping and Isolation Components. The rubber spring shock absorber 6 installed at the top of the lead screw 7 of the logistics system and the EPDM rubber pad 11 installed at the end of the main keel cross brace 53 together constitute the dual vibration damping and isolation components in this handover method. The rubber spring shock absorber 6 is arranged on the main force path of the vertical suspension of the logistics horizontal track 9, and the EPDM rubber pad 11 is arranged at the boundary position of the lateral deformation margin of the ceiling transfer layer system 5. The rubber spring shock absorber 6 and the EPDM rubber pad 11 form a composite vibration interception system with orthogonal vertical and horizontal directions in spatial distribution.

[0083] S24 utilizes dual shock-absorbing isolation components for coordinated shock absorption. When the logistics trolley 10 travels on the logistics horizontal track 9, the system simultaneously faces two types of dynamic disturbances: one is the continuous medium-to-high frequency vertical micro-vibration caused by the continuous rolling of the wheels; the other is the occasional low-frequency lateral large displacement sway caused by the trolley's acceleration, braking, or cornering. The rubber spring shock absorber 6 connected in series on the main load-bearing chain is specifically used to filter and dissipate the medium-to-high frequency vertical structural noise transmitted upward along the logistics system screw 7 through the compressive hysteresis deformation of its internal rubber material.

[0084] S25, while the rubber spring shock absorber 6 absorbs vertical vibration, the EPDM rubber pad 11 should handle the lateral displacement. The horizontal load is transmitted to the main keel cross brace 53, causing the main keel cross brace 53 to swing laterally in the horizontal plane. Since the metal end of the main keel cross brace 53 is close to the lead screw 22 of the mineral wool board ceiling system 2, the EPDM rubber pad 11 acts as an elastic stop structure when the main keel cross brace 53 undergoes lateral displacement. The end of the main keel cross brace 53 preferentially squeezes the EPDM rubber pad 11. The EPDM rubber pad 11 uses the elastic reaction force generated by the compression of its own rubber material to gradually consume the lateral kinetic energy of the main keel cross brace 53 and limit the swing amplitude of the main keel cross brace 53. The setting of the EPDM rubber pad 11 makes up for the lack of lateral impact resistance of the rubber spring shock absorber 6 and avoids the main keel cross brace 53 from having a rigid metal collision with the lead screw 22 of the mineral wool board ceiling system 2.

[0085] S26, forming an overall isolation system effect. Through the combined application of rubber spring shock absorbers 6 and EPDM rubber pads 11, this handover method establishes a clear flexible physical isolation boundary between the logistics track system and the mineral wool ceiling system 2. This combined arrangement achieves comprehensive interception of vibration energy in different frequency bands and directions. The dual shock absorption and isolation components ensure that the mineral wool ceiling system 2 will not be disturbed by high-frequency vibration or mechanical impact under the high-load operation of the logistics trolley 10, so that the mineral wool board 3 always maintains a flat and stable state without vibration or abnormal noise.

[0086] Step S30 specifically includes the following sub-steps:

[0087] S31, fix the connector 15 to the main keel cross brace 53. The connector 15 is a hollow square frame structure made of aluminum alloy. The upper and lower ends of the connector 15 are machined with corresponding pre-drilled bolt holes. The construction personnel press the connector 15 tightly against the side of the main keel cross brace 53 and firmly anchor the connector 15 to the main keel cross brace 53 with metal clamps or through-type fastening bolts. The above assembly operation establishes the suspension force origin of the entire logistics track system. The aluminum alloy square frame structure of the connector 15 can disperse the single-point concentrated tension transmitted from the logistics system screw 7 to the surface of the main keel cross brace 53, avoiding material yielding or deformation of the main keel cross brace 53 due to local stress concentration.

[0088] S32, Assemble the logistics system lead screw 7 and adjust its height. The construction personnel pass the top of the logistics system lead screw 7 through the pre-drilled bolt holes on the lower and upper surfaces of the connector 15, from bottom to top. After the lead screw 7 exits the pre-drilled bolt holes on the upper surface of the connector 15, the construction personnel install washers and screw in fastening nuts. The logistics system lead screw 7 is mechanically locked and suspended by the fastening nuts located on the upper and lower surfaces of the connector 15 in conjunction with the rubber spring shock absorber 6. A certain physical gap must be left at the lower surface of the fastening nut to ensure that when the track is loaded and pulls the logistics system lead screw 7 downwards, compressing the top rubber spring shock absorber 6, the fastening nut at the lower surface will not prematurely jam against the bottom surface of the connector 15, thus hindering the elastic compression stroke of the shock absorber.

[0089] S33, Assemble the logistics system crossbeam 8 and the logistics system lead screw 7. The logistics system crossbeam 8 is a horizontal load-bearing component made of square steel profile. The length of the logistics system crossbeam 8 is matched and cut according to the physical width of the logistics horizontal track 9. The construction personnel pre-process two sets of symmetrically distributed through holes on the top and bottom surfaces of the logistics system crossbeam 8. The distance between the two sets of symmetrically distributed through holes matches the span between the two logistics system lead screws 7. The construction personnel vertically pass the bottom ends of the two logistics system lead screws 7 through the two sets of symmetrical through holes on the logistics system crossbeam 8.

[0090] S34, Perform the connection and tightening operation of the logistics system crossbeam 8. After the logistics system screw rod 7 penetrates the logistics system crossbeam 8, the construction personnel insert metal washers above and below the logistics system crossbeam 8 and screw in fastening nuts. The fastening nuts screwed in above and below form a vertical mechanical clamp on the square steel tube wall of the logistics system crossbeam 8. A pressure-resistant metal sleeve is pre-welded inside the through hole of the logistics system crossbeam 8, or a thickened and enlarged pressure-bearing steel washer is set between the fastening nut and the surface of the square steel to prevent the square steel tube wall from yielding and collapsing under pressure, thereby securing the logistics system. The crossbeam 8 and the logistics system screw 7 are rigidly combined into an integral frame structure that cannot be relatively deflected, which improves the lateral torsional stiffness of the system. The construction personnel use the lower surface of the mineral wool board 3 as the elevation reference benchmark, and change the locking position of the logistics system crossbeam 8 on the logistics system screw 7 by rotating the fastening nuts above and below the logistics system crossbeam 8 clockwise or counterclockwise. This causes the logistics system crossbeam 8 to rise or fall as a whole, ensuring that the lower edge of the finally suspended logistics horizontal track 9 is on the same horizontal plane as the lower surface of the mineral wool board 3.

[0091] S35, Position the horizontal logistics track 9 in space. Construction workers use lifting equipment to lift the horizontal logistics track 9 directly below the logistics system beam 8. The construction workers adjust the horizontal direction of the horizontal logistics track 9 so that the top center line of the horizontal logistics track 9 is aligned with the bottom center point of the logistics system beam 8, and the top of the horizontal logistics track 9 is in close contact with the bottom of the logistics system beam 8.

[0092] S36, the upper mounting structure of the C-clamp 14. To ensure the physical balance of the suspension force, at least one pair of C-clamps 14 need to be symmetrically configured on both sides of the intersection of the logistics system beam 8 and the logistics horizontal track 9. The C-clamp 14 is a one-piece metal clamping component with an inwardly bent buckle at its upper end. The construction workers attach the main body of the symmetrically distributed C-clamps 14 to the vertical surfaces at the intersection of the logistics horizontal track 9 and the logistics system beam 8 on both sides. The construction workers fasten the upper buckle of the C-clamp 14 to the upper edge of the logistics system beam 8. The inner contour of the upper buckle of the C-clamp 14 is physically matched with the outer contour of the square steel profile of the logistics system beam 8. The upper buckle of the C-clamp 14 hooks the top and side surfaces of the logistics system beam 8.

[0093] S37, the lower corner clamping structure of the C-clamp 14 is assembled. The lower end of the C-clamp 14 is machined with an inwardly protruding lower corner clamping. The top two sides of the logistics horizontal track 9 are pre-formed with outwardly extending longitudinal load-bearing flanges. The construction personnel clamp the lower corner clamping of the two C-clamps 14 into the bottom surface of the longitudinal load-bearing flange at the top of the logistics horizontal track 9, and the lower corner clamping of the C-clamp 14 and the longitudinal load-bearing flange form a mechanical clamping connection in the vertical direction.

[0094] S38, Tighten the C-clamp 14 to form a rigid clamping node. Normally, the C-clamp 14 is equipped with transverse fastening bolts on its side. The construction personnel tighten the transverse fastening bolts on both sides of the C-clamp 14. The top of the transverse fastening bolts gradually presses against the side wall of the logistics system beam 8. The thrust applied by the transverse fastening bolts forces the C-clamp 14 to move slightly outward, thereby making the upper edge of the C-clamp 14 and the lower corner of the C-clamp 14 tightly lock the logistics system beam 8 and the logistics horizontal track 9.

[0095] The mechanical thrust generated by tightening the bolts is converted into clamping force in the vertical direction on both sides of the C-clamp 14. This clamping force generates a large static friction force on the metal contact surface. Combined with the torque balance effect generated by the symmetrical arrangement on both sides, the logistics horizontal track 9 and the logistics system beam 8 are rigidly locked into a whole, preventing the logistics horizontal track 9 from axially slipping or laterally falling off under the action of the inertia of the logistics trolley 10. At the same time, the use of C-clamp 14 for external clamping avoids drilling damage or high-temperature welding operations on the logistics system beam 8 and the logistics horizontal track 9, eliminates the risk of stress concentration, and maintains the flatness of the internal running surface of the logistics horizontal track 9. The specific torque value required for the transverse fastening bolts to reach the locking state can be set by those skilled in the art according to the standard mechanical fastener technical manual and verified using a torque wrench. The specific torque verification operation is a well-known technology in this field and will not be described in detail here.

[0096] Step S40 specifically includes the following sub-steps:

[0097] S41, Install and physically fix the edge keel 12. At the spatial junction of the horizontal logistics track 9 and the mineral wool board 3, i.e., on both sides of the horizontal logistics track 9, install the edge keel 12 along the longitudinal extension direction of the horizontal logistics track 9. During installation and positioning, use the lower surface of the mineral wool board 3 and the lower surface of the horizontal logistics track 9 as a common elevation reference to adjust the height of the edge keel 12, ensuring that the bottom surface of the edge keel 12 is flush with the surrounding components. The edge keel 12 is made of L-shaped or U-shaped metal profiles. The installer attaches the vertical side wings of the edge keel 12 tightly to the side of the metal angle bracket pre-fixed to the main keel cross brace 53 and extending downwards to the ceiling elevation, and uses metal self-tapping screws to anchor the vertical side wings of the edge keel 12 to the metal angle bracket. In extreme cases where the horizontal logistics track 9 is located close to the building wall, the installer uses expansion bolts to directly anchor the vertical side wings of the edge keel 12 to the adjacent building wall.

[0098] S42 forms a horizontal covering and shielding structure for the side keel 12. After the vertical wings of the side keel 12 are firmly anchored, the horizontal wings of the side keel 12 extend towards the logistics horizontal track 9 and the mineral wool board 3. The horizontal wings of the side keel 12 directly cover the area below the structural gap formed between the edge of the logistics horizontal track 9 and the edge of the mineral wool board 3. The horizontal wings of the side keel 12 shield the metal suspension components such as the logistics system screw 7, logistics system crossbeam 8, C-clamp 14, and connector 15 located in the concealed space above the mineral wool board 3. The aforementioned side keel 12, which extends along its length and covers the gap, establishes a visually converging boundary, making the originally fragmented junction area present a neat and smooth straight-line appearance.

[0099] S43, Apply sealant 13. After the edge keel 12 is installed, due to metal processing tolerances and cutting errors of the mineral wool board 3, there will inevitably be small assembly gaps between the horizontal side edges of the edge keel 12 and the cut edges of the mineral wool board 3. At the same time, there are also small assembly gaps between the horizontal side edges of the edge keel 12 and the side walls of the logistics horizontal track 9. Generally, the width of the assembly gaps needs to be controlled within the size range where the sealant 13 can effectively adhere and is not prone to dripping. Construction personnel use a pneumatic caulking gun or a manual caulking gun to continuously squeeze the sealant 13 into all the above-mentioned assembly gaps. For the caulking and filling process of interior decoration gaps in buildings, those skilled in the art can operate according to the conventional medical space cleanroom decoration specifications. The specific continuous caulking action is a well-known technology in this field and will not be described in detail here.

[0100] S44 forms a flexible sealing and displacement compensation structure at the interface. After the sealant 13 is fully cured at room temperature, it adheres tightly to the surfaces of the edge keel 12, the mineral wool board 3, and the horizontal logistics track 9. The logistics track system bears dynamic loads during operation, while the mineral wool board system only bears its static self-weight. These two independent mechanical systems will produce differential micro-displacements when subjected to force. If a rigid connection is used for sealing, it is easy to cause stress concentration at the contact surface and thus cracking. The cured sealant 13, as an elastic polymer colloid, uses its own tensile and compressive deformation capabilities to absorb the relative displacement caused by the above-mentioned differential displacements in real time, avoiding the rigid edge keel 12 from directly scratching or hard impacting the fragile edge of the mineral wool board 3.

[0101] Meanwhile, in response to the environmental requirements of hospital public corridors, sealant 13 has anti-mildew and antibacterial properties. Since HVAC pipes are usually installed inside the ceiling, local condensation is easily generated under temperature difference, creating a humid environment. The anti-mildew component can effectively inhibit the growth of mold on the surface of the sealant. The continuously arranged sealant 13 seals the airflow communication channels between the upper and lower parts of the mineral wool board 3, preventing dust particles in the concealed space from leaking into the medical corridor under the action of air conditioning wind pressure, thereby ensuring the overall airtightness and environmental cleanliness of the ceiling system.

[0102] S45, establish a combined shielding structure at the junction. The edge keel 12, as a rigid basic frame, spans across the structural gap between the horizontal logistics track 9 and the mineral wool board 3. The horizontal wings of the edge keel 12 extend outwards, not only shielding the metal components above but also forming a support space below the exposed edges of the mineral wool board 3 due to on-site cutting. Combined with the filling of sealant 13, this achieves a flexible support for the edges of the mineral wool board 3. This support structure prevents debris from falling off due to loose material at the edges of the mineral wool board 3 and provides a flat and solid surface for subsequent sealant 13 application. On the bottom base surface, sealant 13, as an elastic filler, is continuously distributed at the overlapping edges of the side keel 12 and the logistics horizontal track 9, as well as at the overlapping edges of the side keel 12 and the mineral wool board 3. The side keel 12 and sealant 13 are physically combined to form a continuous shielding structure. This shielding structure encloses the logistics system threaded rod 7, logistics system crossbeam 8, C-clamp 14 and connector 15 and other suspended components in the concealed space of the ceiling from view, solving the problem of visual clutter caused by exposed internal steel components.

[0103] S46 achieves flexible sealing of the joint gap. In the joint arrangement, the edge keel 12 is anchored to the ceiling transition layer system 5 or the wall surface by mechanical fasteners, but the horizontal wings of the edge keel 12 do not have direct metal contact or rigid connection with the logistics horizontal track 9 or mineral wool board 3. The sealant 13, as the only contact medium, is located between the edges of the above-mentioned rigid components. In order to ensure that the sealant 13 has sufficient elastic deformation space, the injection depth is usually controlled between 0.5 and 1 times the gap width during construction. The specific value is determined by the size of the gap on site and the mechanical elongation parameter of the selected sealant 13.

[0104] When the logistics trolley 10 generates dynamic disturbances while running on the logistics horizontal track 9, or when the building structure expands and contracts due to temperature differences, a small relative displacement will occur between the logistics horizontal track 9 and the mineral wool board 3. Since the sealant 13 has viscoelasticity, when external stress is applied to the sealant, the polymer chain segments inside the sealant slip and stretch, converting the mechanical stress into its own tensile or compressive deformation, thereby absorbing the displacement difference between the two independent systems and avoiding gap tearing or squeezing damage that may occur under rigid connection. This combination arrangement not only ensures the airtightness requirements of the medical corridor environment, but also cuts off the solid sound bridge transmission path of mechanical vibration transmitted to the mineral wool board ceiling system 2 through the junction edge.

[0105] S47 retains the detachable function of the mineral wool board system. In the junction arrangement of the edge keel 12 and the sealant 13, the sealant 13 is only attached to a local area of ​​the cut edge of the mineral wool board 3, without changing the original T-shaped keel 4 hanging structure of the mineral wool board ceiling system 2. Since the load of the logistics horizontal track 9 is entirely borne by the independent ceiling transfer layer system 5, the mineral wool board ceiling system 2 only bears its own static self-weight. When maintenance personnel need to inspect the electromechanical pipelines or logistics track components inside the ceiling, the construction personnel only need to use a utility knife to cut the sealant 13 on the edge of the edge keel 12, and then, following the conventional ceiling maintenance procedure, lift and remove the mineral wool board 3 piece by piece from the T-shaped keel 4. The construction personnel can then reposition the mineral wool board 3 and refill the sealant 13 to restore the original state. The above-mentioned junction arrangement avoids the destructive demolition drawbacks of traditional whole-board replacement of gypsum board ceilings and ensures the convenience of later maintenance of the track system.

[0106] In the construction process of actual medical building environments, in order to adapt to the engineering requirements of different spans, different loads, and different budgets, this invention provides a variety of equivalent alternative implementation methods, specifically including the following detailed alternative steps:

[0107] Regarding alternative implementation methods for the load-bearing structure: In medical building scenarios with larger spans or heavier logistics track loads, construction workers can replace the main keel cross brace 53 in the ceiling transfer layer system 5 with a steel space frame or steel composite beam. The steel space frame, through its spatially multi-directionally distributed mesh metal rod structure, disperses the concentrated force transmitted by the logistics track system to multiple structural suspension points. The steel composite beam utilizes its large cross-sectional moment of inertia to resist the huge bending deformation in the vertical direction. The working principle of the aforementioned steel space frame or steel composite beam is completely consistent with that of the main keel cross brace 53, thus forming a secondary force transfer layer independent of the mineral wool board ceiling system 2, achieving independent load bearing of the logistics track load. Replacing the main keel cross brace 53 with a steel space frame or steel composite beam demonstrates clear technical equivalence in terms of physical and mechanical load-bearing functions.

[0108] Regarding the replacement implementation of the vibration damping and isolation components: For logistics systems with different vibration frequency characteristics, construction personnel can replace the rubber spring vibration damper 6 with a metal coil spring vibration damper, a polyurethane elastomer, or an air spring. Since the metal coil spring vibration damper and the air spring cannot directly rely on the nut for force like rubber parts, construction personnel need to add two parallel pressure-bearing flanges to the lead screw 7 of the logistics system, and clamp the replacement vibration damping component between the two pressure-bearing flanges. The metal coil spring vibration damper absorbs low-frequency high-amplitude vibrations by the torsional deformation of the metal wire, the polyurethane elastomer dissipates mechanical kinetic energy by utilizing the internal damping of the polymer material, and the air spring provides adjustable support stiffness by compressing the gas in the sealed rubber bladder.

[0109] Meanwhile, construction workers can replace the EPDM rubber pad 11 with a silicone rubber pad, a felt buffer layer, or a polyurethane foam pad. The silicone rubber pad, felt buffer layer, or polyurethane foam pad are also arranged between the end of the ceiling transition layer system 5 and the threaded rod 22 of the mineral wool board ceiling system 2, serving as a flexible isolation layer to prevent hard collisions between metal components. The application of these different elastic media can achieve the purpose of absorbing vertical vibrations and preventing lateral collisions.

[0110] Regarding the replacement implementation of the junction interface finishing components: To adapt to the needs of project cost control or special-shaped logistics horizontal tracks 9, such as the curved track sections at the bends in the corridor, construction personnel can replace the straight-extending metal edge keel 12 with PVC finishing strips, stainless steel bent parts, or flexible rubber baffles. PVC finishing strips have the physical characteristics of being lightweight and easy to cut on-site. Stainless steel bent parts have a smooth and dense surface, meeting the anti-corrosion and cleaning requirements of high-level medical clean areas. Flexible rubber baffles can rely on the bending deformation capacity of the material itself to closely fit the curved contour of the curved logistics horizontal track 9 for continuous arrangement. The above-mentioned PVC finishing strips, stainless steel bent parts, or flexible rubber baffles can all be used with sealant 13 to cover the suspended metal components hidden inside the ceiling.

[0111] Regarding alternative implementation methods for logistics track connection components: Under construction conditions that prioritize lightweight structure or rapid installation, construction personnel can replace the aluminum alloy square frame connector 15 with a U-shaped metal clamp or an adjustable turnbuckle. The bottom groove of the U-shaped metal clamp directly grips and supports the load-bearing members of the ceiling transition layer system 5, and the vertical lugs on both sides of the U-shaped metal clamp are secured to the logistics system threaded rod 7 with through-hole bolts.

[0112] When using adjustable turnbuckles, construction workers pre-weld metal lugs to the bottom of the main load-bearing members of the ceiling transition layer system 5, and hinge the upper end of the adjustable turnbuckle to the metal lugs via a pin. At the same time, the lower end of the adjustable turnbuckle is threaded to the logistics system screw 7. The middle part of the adjustable turnbuckle is a rotating sleeve with internal threads. By using a wrench to rotate the middle sleeve of the adjustable turnbuckle, construction workers can directly lengthen or shorten the overall geometric length of the connection system, thereby achieving precise height adjustment of the bottom edge of the logistics horizontal track 9 to be flush with the mineral wool board 3. The aforementioned U-shaped metal clamp and adjustable turnbuckle also realize the mechanical anchoring and elevation adjustment functions between the logistics system screw 7 and the ceiling transition layer system 5.

Claims

1. A method for fixing and connecting a medical logistics track to a mineral wool board ceiling, characterized in that, Includes the following steps: The ceiling transition layer system (5) is arranged, and the main keel cross brace (53) is fixed in the space above the mineral wool board (3) by the fully toothed galvanized independent hanger (52). The main keel cross brace (53) is used to bear the load generated by the logistics horizontal track (9) and the logistics trolley (10), so that the mineral wool board ceiling system (2) and the ceiling transition layer system (5) are structurally separated. Deploy a horizontal isolation component and install a flexible isolation layer between the main keel cross brace (53) and the threaded rod (22) of the mineral wool board ceiling system (2); The logistics horizontal track (9) is suspended and fixed and a vertical shock absorption component is deployed. The logistics system screw (7) is fixed to the main keel cross brace (53) using a connector (15). A rubber spring shock absorber (6) is installed at the connection position between the logistics system screw (7) and the connector (15). The logistics system beam (8) is assembled at the lower end of the logistics system screw (7). The logistics horizontal track (9) is connected to the lower part of the logistics system beam (8) using a C-clamp (14). To complete the handover interface sealing, side keel (12) is installed along the entire length of both sides of the horizontal logistics track (9) at the handover position between the horizontal logistics track (9) and the mineral wool board (3). The gaps between the side keel (12) and the mineral wool board (3) and between the side keel (12) and the horizontal logistics track (9) are filled with sealant (13).

2. The method for fixing and connecting a medical logistics track to a mineral wool ceiling as described in claim 1, characterized in that, The arrangement of the ceiling transition layer system (5) specifically includes: Install full-tooth hanger with expansion bolts (51) on the bottom surface of the structural floor slab (1); Screw the top of the fully toothed galvanized independent hanger rod (52) into the expansion bolt (51) that matches the fully toothed hanger rod; A matching hanger is fixedly assembled at the bottom end of the fully toothed galvanized independent hanger (52), the main keel cross brace (53) is placed inside the matching hanger, and the fastening bolts on the matching hanger are tightened. Multiple main keel cross braces (53) are distributed at intervals along the direction of the logistics horizontal track (9), and the length direction of the main keel cross braces (53) is perpendicular to the direction of the logistics horizontal track (9) and they are arranged parallel to each other. The horizontal height of the main keel cross brace (53) is higher than that of the mineral wool board (3), and a physical gap is maintained between the main keel cross brace (53) and the threaded rod (22) and matching keel (23) of the mineral wool board ceiling system (2).

3. The method for fixing and connecting a medical logistics track to a mineral wool board ceiling according to claim 1, characterized in that, Deploying the horizontal isolation component and installing a flexible isolation layer between the main keel cross brace (53) and the threaded rod (22) of the mineral wool board ceiling system (2) specifically includes: The flexible isolation layer is selected according to the net gap size between the end of the main keel cross brace (53) and the threaded rod (22) of the adjacent mineral wool board ceiling system (2), and the natural thickness of the flexible isolation layer is less than or equal to the net gap size. The flexible isolation layer is arranged on one end face of the threaded rod (22) of the main keel cross brace (53) facing the mineral wool board ceiling system (2); The flexible isolation layer is made of EPDM rubber pad (11), silicone rubber pad, felt buffer layer or foamed polyurethane pad.

4. The method for fixing and connecting a medical logistics track to a mineral wool ceiling as described in claim 1, characterized in that, The logistics horizontal track (9) is suspended and fixed, and a vertical shock absorption assembly is deployed. The logistics system screw (7) is fixed to the main keel cross brace (53) using a connector (15). A rubber spring shock absorber (6) is installed at the connection position between the logistics system screw (7) and the connector (15). The logistics system crossbeam (8) is assembled at the lower end of the logistics system screw (7). Specifically, this includes: The connector (15) is a hollow square frame structure with pre-reserved bolt holes on both the upper and lower ends. The connector (15) is tightly fixed to the side of the main keel cross brace (53). The top end of the logistics system screw (7) is passed through the reserved bolt hole on the lower end face of the connector (15) and the reserved bolt hole on the upper end face of the connector (15) from bottom to top, and the rubber spring shock absorber (6) is sleeved on the logistics system screw (7). A fastening nut is screwed into the top end of the logistics system screw (7) so that the rubber spring shock absorber (6) is located between the fastening nut and the bottom surface of the inner cavity of the connector (15). A fastening nut is screwed into the lower end face of the connector (15) of the lead screw (7) in the logistics system, and the fastening nut leaves a space gap downwards; After the lead screw (7) of the logistics system penetrates the crossbeam (8) of the logistics system, fastening nuts are screwed into the top and bottom of the crossbeam (8) of the logistics system. By rotating the fastening nuts above and below the crossbeam (8) of the logistics system clockwise or counterclockwise, the locking position of the crossbeam (8) on the lead screw (7) of the logistics system changes, thereby causing the crossbeam (8) of the logistics system to rise or fall as a whole.

5. The method for fixing and connecting a medical logistics track to a mineral wool board ceiling according to claim 1, characterized in that, Connecting the horizontal logistics track (9) to the lower part of the logistics system beam (8) using C-clamps (14) specifically includes: The main body of the symmetrically distributed C-shaped clips (14) is attached to the two sides of the intersection surface of the logistics horizontal track (9) and the logistics system beam (8); The upper edge of the C-clamp (14) is fastened to the upper edge of the crossbeam (8) of the logistics system; The lower corner of the C-clamp (14) is inserted into the bottom surface of the pre-formed longitudinal force-bearing flange on both sides of the top of the horizontal logistics track (9); Tighten the transverse fastening bolts on the sides of the C-clamps (14) to force the C-clamps (14) to move outward as a whole, so that the upper end of the C-clamps (14) and the lower end locking corner lock the logistics system beam (8) and the logistics horizontal track (9).

6. The method for fixing and connecting a medical logistics track to a mineral wool board ceiling according to claim 1, characterized in that, The specific steps of executing the handover interface closing include: The vertical side wings of the side keel (12) are anchored to the side of the metal angle bracket that is pre-fixed to the main keel cross brace (53) and extends downward, or the vertical side wings of the side keel (12) are anchored to the adjacent building wall. The horizontal wings of the side keel (12) cover the area below the structural gap formed between the edge of the logistics horizontal track (9) and the edge of the mineral wool board (3), forming a support space below the edge of the mineral wool board (3); The sealant (13) is continuously squeezed into the assembly gap between the horizontal side wing edge of the side keel (12) and the cut edge of the mineral wool board (3), and into the assembly gap between the horizontal side wing edge of the side keel (12) and the side wall of the logistics horizontal track (9).

7. The method for fixing and connecting a medical logistics track to a mineral wool board ceiling according to claim 2, characterized in that, After screwing the top of the fully toothed galvanized independent hanger (52) into the fully toothed hanger's matching expansion bolt (51), the process further includes: Screw in the matching anti-loosening lock nut and tighten it upwards to the bottom end of the expansion bolt (51) of the full-tooth hanger.

8. The method for fixing and connecting a medical logistics track to a mineral wool board ceiling according to claim 4, characterized in that, The threaded rod (7) of the logistics system penetrates the crossbeam (8) of the logistics system, specifically including: The logistics system beam (8) is provided with a pre-welded pressure-resistant metal sleeve inside, or a pressure-bearing steel gasket is provided between the fastening nut and the surface of the logistics system beam (8).

9. The method for fixing and connecting a medical logistics track to a mineral wool ceiling as described in claim 6, characterized in that, L-shaped or U-shaped metal profiles are used as the edge keel (12).

10. The method for fixing and connecting a medical logistics track to a mineral wool ceiling as described in claim 6, characterized in that, When the sealant (13) is squeezed into the assembly gap for filling, the injection depth is controlled to be between 0.5 and 1 times the width of the assembly gap.