A base plane self-adaptive waterproof coating construction method
By implementing full-coverage testing and zoned construction, and by differentiating the primer system, the problem of insufficient identification of substrate areas in existing technologies has been solved, thereby improving the consistency and durability of coating quality and meeting the high-quality waterproofing construction requirements of complex substrates.
Patent Information
- Application Number
- CN202611536516.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-20
AI Technical Summary
Existing waterproof coating construction techniques cannot identify differences in the substrate area, resulting in uneven coating quality. Problems include blistering and delamination in damp areas, cracking in defective areas, and poor adhesion in loose areas. Furthermore, the single curing method leads to inconsistent curing speeds, making it difficult to meet the high-quality waterproofing requirements of complex and uneven substrates.
By conducting comprehensive inspection of the graded substrate area, it is divided into four categories: standard, damp, micro-defect, and loose. Physical zoning construction is carried out, and the primer system is differentiated and matched with the coating thickness and curing method to achieve synchronous and stable coating formation.
It achieves substrate-adaptive and zone-matching waterproofing construction, improves the quality consistency and durability of the coating, avoids local defects, and meets the high-quality waterproofing requirements of complex substrates.
Smart Images

Figure CN123133541A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building waterproofing construction technology, and in particular to a method for applying an adaptive waterproof coating to a substrate. Background Technology
[0002] During the construction of building waterproofing, the working conditions of the substrate surface to be constructed on the construction site are generally uneven. The same substrate surface often has dry standard areas, locally damp areas, minor defect areas and slightly loose and sandy areas at the same time. The moisture content, density, flatness and defect status of each area are quite different.
[0003] Most existing waterproof coating construction adopts a standardized construction model with uniform mixing, uniform application, and uniform curing. Before construction, only a general rough inspection of the substrate is carried out. There is a lack of full-coverage parameter testing and precise grading methods, which makes it impossible to identify the differences in working conditions in different areas of the substrate, and also fails to carry out fine-grained zoning treatment for complex substrates.
[0004] Traditional processes use a single primer formulation and uniform application parameters for all substrate areas, which cannot adapt to the different substrate needs of damp, defective, and porous areas. This can easily lead to quality problems such as coating blistering and detachment in damp areas, coating cracking in defective areas, and poor adhesion in porous areas.
[0005] Meanwhile, the existing construction adopts a uniform curing method for the entire area, without differentiated control based on the curing characteristics of different substrate areas. This results in inconsistent curing speeds and uneven forming quality in different areas, which can easily lead to defects such as localized hollowing, leakage, and poor durability.
[0006] In summary, existing waterproofing construction technologies suffer from drawbacks such as low accuracy in substrate identification, lack of zoned construction mechanisms, poor coating compatibility, and limited curing methods, making it difficult to meet the high-quality waterproofing requirements of complex and uneven substrates. Summary of the Invention
[0007] The purpose of this invention is to provide a substrate-adaptive waterproof coating construction method, which aims to solve the technical problems of low substrate identification accuracy, lack of zoning construction mechanism, poor coating compatibility, and single curing method in the prior art, making it difficult to meet the high-quality waterproof construction requirements of complex and uneven substrates.
[0008] To achieve the above objectives, the present invention employs a substrate-adaptive waterproof coating application method, comprising the following steps: A full-coverage inspection is conducted on the entire substrate surface to be constructed, collecting parameters such as moisture content, surface density, flatness, and minor defects. Based on the inspection parameters, the substrate surface is divided into four working condition areas: standard substrate area, damp substrate area, micro-defect substrate area, and loose substrate area. The working condition classification and area marking of the substrate surface are completed, and the substrate surface classification and marking results are output. Based on the results of the base surface classification and marking, the overall construction surface is physically divided into zones. The base surfaces under different working conditions are independently divided into separate construction zones, and the boundary markings of each zone are retained. Special areas such as inside and outside corners, pipe roots, and crack nodes are separately designated as key reinforcement zones. For each type of independent zone of substrate conditions, the corresponding primer system is adjusted in a differentiated and adaptive manner. The solid content, penetration aid, elastic reinforcing component and curing component of the primer are dynamically adjusted according to the moisture content and density parameters of each zone to achieve precise matching between the primer performance and the substrate conditions of each zone. Based on the zoning results, corresponding adaptive primers are applied to different substrate zones, matching differentiated coating thicknesses, number of coats, and construction methods. After the primers in each zone are surface dry, a compatible topcoat waterproof coating is applied cross-coated. Differentiated curing is implemented for different zones, matching the curing rate of the coating in each zone to achieve synchronous and stable forming of the coating across the entire area.
[0009] The process includes: conducting a full-coverage inspection of the entire substrate surface to be constructed, collecting parameters such as moisture content, surface density, flatness, and minor defects; dividing the substrate surface into four working condition areas based on the inspection parameters: standard substrate area, damp substrate area, micro-defect substrate area, and loose substrate area; completing the substrate working condition classification and area marking; and outputting the substrate classification and marking results. A comprehensive inspection and testing of the entire building surface to be constructed was conducted, and core working condition parameters of the surface were collected. These core working condition parameters include moisture content, surface density, flatness, and minor defects. The core working condition parameters of the base surface are summarized and compared with the preset base surface working condition judgment standard. The working condition of the construction base surface is classified and identified. Based on the parameter identification results, the overall base surface is divided into four independent working condition areas: standard base surface area, damp base surface area, micro-defect base surface area, and loose base surface area.
[0010] The process involves summarizing the core working condition parameters of the base surface, comparing them with the preset base surface working condition judgment standards, classifying and identifying the working condition of the construction base surface, and dividing the overall base surface into four independent working condition areas based on the parameter identification results: standard base surface area, damp base surface area, micro-defect base surface area, and loose base surface area. Mark the on-site locations and outlines of the various working areas that have been divided, record the location, range and working condition attributes of each area, and generate and output the base surface hierarchical marking results.
[0011] Among them, in the steps of physically dividing the overall construction surface based on the base surface classification and marking results, dividing the base surface under different working conditions into separate construction zones, retaining the boundary markings of each zone, and separately classifying special areas such as inside and outside corners, pipe roots, and crack nodes as key reinforcement zones: Obtain the datum surface classification and marking results, obtain the distribution location, area range and boundary contour of each working condition area, and determine the area boundary line of the datum surface under different working conditions; The overall construction surface is physically divided by a partitioning and isolation method. Base surfaces with the same working conditions are integrated into independent construction zones, and the boundaries of each construction zone are marked to distinguish the scope of each construction zone.
[0012] The process involves physically dividing the overall construction surface using a zone isolation method, integrating base surfaces with the same working conditions into independent construction zones, and marking the boundaries of each construction zone to distinguish its extent. Identify special nodes such as the inside and outside corners of the construction surface, pipe roots, and cracks in the base surface, and designate them as key reinforcement zones.
[0013] Among these steps, for each type of independent zone of substrate conditions, the corresponding primer system is differentiated and adaptively adjusted. This involves dynamically adjusting the solid content, penetrating agent, elastic reinforcing component, and curing component ratio of the primer based on the moisture content and density parameters of each zone, to achieve precise matching of primer performance with the zone's substrate conditions. Check the core working parameters of the base surface moisture content and surface density of each independent construction zone one by one to obtain the construction shortcomings and performance requirements of the base surface of each zone. To meet the specific needs of different working conditions and zones, we match differentiated primer formulation schemes and adjust the solid content of the primer base system accordingly to adapt to the penetration and adhesion requirements of different substrates. Add functional components specifically based on the operating conditions of each zone.
[0014] Among them, in the step of adding functional components specifically according to the operating conditions of the zones: Add a penetrating agent to damp substrate areas, add an elastic reinforcing component to defective substrate areas, and add a curing component to loose substrate areas.
[0015] After the step of adding functional components specifically according to the zoning conditions: According to the mixing plan, the primer for each zone is mixed in proportion and stirred. After thorough mixing, it is allowed to stand and mature so that the performance indicators of the primer are adapted to the corresponding zone substrate, thus achieving adaptive matching between the primer and the substrate working conditions.
[0016] The process involves several steps, including: applying adaptively formulated primers to different substrate zones based on the zoning results; matching differentiated coating thicknesses, number of coats, and application methods; applying a compatible topcoat waterproofing coating after the primers in each zone are surface dry; and implementing differentiated curing for different zones to match the curing rate of the coating in each zone, thus achieving synchronous and stable formation of the coating across the entire area. Based on the construction division results of each zone, an adaptive primer suitable for the corresponding working conditions is selected, and a specific coating thickness, number of coats and coating operation method are set for different zones; in particular, the zones with the most emphasis are given priority for thicker coating construction. Complete the primer application in each zone to ensure that the primer in each zone fully penetrates the pores of the substrate and seals the defects on the substrate surface. Wait until the primer in all construction zones reaches the touch dry state. A uniform, compatible waterproof coating is used to apply a cross-shaped coating to the entire construction surface.
[0017] After uniformly applying a compatible waterproof coating to the entire construction surface in a cross-shaped pattern: Based on the original substrate conditions of each zone, a zone-specific maintenance plan is developed, and the maintenance time, ventilation conditions and moisturizing maintenance methods are adjusted differently for each zone. By using zoned differentiated curing to adapt to the curing speed of coatings in different areas, the overall coating forming rhythm is balanced.
[0018] This invention discloses a method for applying an adaptive waterproof coating to a substrate. The method involves a full-coverage inspection of the entire substrate to be treated, collecting parameters such as moisture content, surface density, flatness, and minor defects. Based on these parameters, the substrate is divided into four condition zones: standard, damp, slightly defective, and loose. The method completes the substrate condition classification and zone marking, and outputs the classification and marking results. Based on these results, the entire construction surface is physically divided into zones, with different conditions defined as separate construction zones. Boundary markers for each zone are retained, and special areas such as corners, pipe roots, and crack joints are designated as key reinforcement zones. For each independent zone, different treatment methods are applied to address the substrate conditions. The adaptive formulation of the corresponding primer system dynamically adjusts the solid content, penetration aid, elastic reinforcing component, and curing component ratio of the primer based on the moisture content and density parameters of each zone, achieving precise matching between the primer performance and the working conditions of the substrate in each zone. According to the zone division results, corresponding adaptively formulated primers are used for different substrate zones, matching differentiated coating thicknesses, number of coats, and construction methods. After the primers in each zone are surface dry, a compatible topcoat waterproofing coating is applied cross-coated, and differentiated curing is implemented for different zones, matching the curing rate of the coating in each zone to achieve synchronous and stable forming of the coating across the entire area. Through the above methods, substrate self-adaptation, zone matching, and differentiated construction and curing are achieved, meeting the high-quality waterproofing construction requirements for complex and uneven substrates. Attached Figure Description
[0019] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0020] Figure 1 This is a flowchart of the steps of the substrate adaptive waterproof coating construction method of the present invention.
[0021] Figure 2 This is a flowchart of steps S100 of the present invention.
[0022] Figure 3 This is a flowchart of steps S200 of the present invention.
[0023] Figure 4 This is a flowchart of steps S300 of the present invention.
[0024] Figure 5 This is a flowchart of steps S400 of the present invention.
[0025] Figure 6 This is a schematic diagram of the structural principle of the substrate adaptive waterproof coating application system of the present invention.
[0026] Figure 7 This is a schematic diagram of the electronic device of the present invention. Detailed Implementation
[0027] Exemplary embodiments will now be described in detail, examples of which are illustrated in the accompanying drawings. When the following description relates to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with this application.
[0028] The terminology used in this application is for the purpose of describing particular embodiments only and is not intended to be limiting of the application. The singular forms “a,” “the,” and “the” used in this application and the appended claims are also intended to include the plural forms unless the context clearly indicates otherwise. It should also be understood that the term “and / or” as used herein refers to and includes any or all possible combinations of one or more of the associated listed items.
[0029] It should be understood that although the terms first, second, third, etc., may be used in this application to describe various information, such information should not be limited to these terms. These terms are only used to distinguish information of the same type from one another. For example, without departing from the scope of this application, first information may also be referred to as second information, and similarly, second information may also be referred to as first information. Depending on the context, the word "if" as used herein may be interpreted as "when," "when," or "in response to determination."
[0030] Please see Figures 1-5 This invention provides a method for applying an adaptive waterproof coating to a substrate, comprising the following steps: S100: Conduct a full-coverage inspection of the entire substrate surface to be constructed, collecting parameters such as moisture content, surface density, flatness, and minor defects. Based on the inspection parameters, the substrate surface is divided into four working condition areas: standard substrate area, damp substrate area, micro-defect substrate area, and loose substrate area. The substrate working condition is then classified and the areas are marked, and the classification and marking results are output. The specific process is as follows: S101: Conduct a comprehensive inspection and testing of the entire building surface to be constructed, and collect core working condition parameters of the surface; among which, the core working condition parameters of the surface include moisture content, surface density, flatness, and minor defect parameters; S102: Summarize the core working condition parameters of the base surface, compare them with the preset base surface working condition judgment standards, classify and identify the working condition of the construction base surface, and divide the overall base surface into four independent working condition areas: standard base surface area, damp base surface area, micro-defect base surface area, and loose base surface area according to the parameter identification results. S103: Mark the on-site points and outlines of the various working areas that have been divided, record the location, range and working condition attributes of each area, and generate and output the base surface hierarchical marking results.
[0031] In this embodiment, the substrate surfaces such as roofs, basements, kitchens, and bathrooms to be constructed are pre-cleaned to remove large particles and scum, preventing interference with testing accuracy. A grid-based method is used to divide the substrate into several grid units, with at least three testing points per square meter. Points are denser at corners, around pipes, and near cracks. A moisture content meter is used to collect surface moisture content data, a surface strength meter to obtain substrate density data, a 2-meter straightedge and feeler gauge to obtain flatness deviation data, and visual inspection and defect observation tools to record minor defects such as crack width, holes, sandblasting, and unevenness. The original testing data is recorded point by point, mapping each point location to its corresponding measured value to create an original testing data table. All original collected information is completely preserved without any pre-editing.
[0032] Retrieve the original test data table of all points obtained in step S101 and perform data preprocessing: identify and remove obvious abnormal outlier point data caused by local stains and foreign objects; perform regional aggregation processing on a group of spatially adjacent points with similar parameters, calculate the comprehensive representative values of moisture content, density, and flatness of the area, and use the comprehensive regional value to represent the overall working condition of the area, rather than directly judging based on a single point. Retrieve the pre-set base surface working condition judgment criteria and compare and match the comprehensive value of each aggregated area with the judgment criteria one by one. According to the comparison results, group continuous areas with consistent working condition attributes into the same type of working condition area, forming standard base surface area, damp base surface area, micro-defect base surface area, and loose base surface area, respectively, to obtain preliminary regional division results; for the boundary areas where working condition parameters change transitionally, appropriately increase the number of sampling points and recalculate the comprehensive parameters to avoid misclassification across working conditions.
[0033] Based on the area division results obtained in step S102, return to the construction site and use a marking tool to outline a complete closed area contour along the actual boundaries of each working condition area. Mark the working condition type number within each area. Simultaneously record the site location, geometric range, area, corresponding comprehensive working condition parameters, and main defect types of each partition in the ledger. Verify the site contour marking information against the ledger records to ensure a one-to-one correspondence between the paper records and the actual site partitions, preventing misalignment. Integrate the contour location, area range, working condition parameters, and defect information to form a complete base surface grading marking result file, which is then output as input for subsequent physical zoning processes.
[0034] S200: Based on the basal surface grading and marking results, the overall construction surface is physically divided into zones, and the basal surface under different working conditions is independently divided into separate construction zones. The boundary markings of each zone are retained, and special areas such as internal and external corners, pipe roots, and crack joints are separately designated as key reinforcement zones; the specific process is as follows: S201: Obtain the datum surface classification marking results, obtain the distribution location, area range and boundary contour of each working condition area, and determine the area boundary line of different working condition datum surfaces; S202: The overall construction surface is physically divided using a zone isolation method. Base surfaces with the same working conditions are integrated into independent construction zones, and the boundaries of each construction zone are marked to distinguish the scope of each construction zone. S203: Identify special nodes such as the inside and outside corners of the construction surface, pipe roots, and cracks in the base surface, and designate them as key construction zones for reinforcement.
[0035] In this embodiment, the base surface grading and marking results output in step S103 are read, and the spatial location, area size, and contour coordinate information of each working condition partition are extracted. For adjacent areas with different working conditions, boundary calibration processing is performed on the boundary contour between them to correct jagged and fragmented boundaries, and to merge extremely small and fragmented working condition patches into adjacent main partitions, avoiding the construction difficulties caused by a large number of small and fragmented partitions. After calibration, a clear and continuous regional boundary line is determined between each different working condition, ensuring that the base surface working condition attributes on both sides of the boundary line are clearly distinguishable, and that the working conditions within each partition are relatively homogeneous. At the same time, the coordinates of all node positions are identified, providing a location basis for delineating key reinforcement partitions.
[0036] Following the area boundary lines determined in step S201, masking and isolation tape is applied along the boundary lines at the construction site to achieve physical isolation between substrates with different working conditions. Substrates with similar working conditions are integrated into an independent construction zone. The isolation tape acts as a physical barrier, preventing the mixing of different prepared primer coatings across zones during application. After the isolation tape is applied, each independent construction zone is marked with a site number, and the zone number is clearly marked at the zone boundary, retaining easily identifiable boundary markers. The site markings are then re-verified against the zone numbers, ranges, and working conditions in the logbook to ensure complete correspondence between the logbook records, marking numbers, and on-site physical isolation, forming a physically independent construction zone layout that provides physical boundaries for zoned material preparation and application.
[0037] Based on the node coordinates identified in step S201, locate all internal and external corners, pipe roots, and crack locations on site. Extend the reinforcement area outwards from the node location, forming a closed area 100mm outwards. Separate this area from the original substrate partition and designate it as a separate key reinforcement zone. Use release tape to demarcate the boundary of this key reinforcement zone, assign it an independent partition number, and record the node type, spatial range, and original substrate condition corresponding to this key reinforcement zone in the logbook. This key reinforcement zone independently participates in subsequent primer mixing and application operations to achieve reinforcement treatment of the node areas.
[0038] S300: For each independent zone of substrate conditions, a differentiated adaptive adjustment of the corresponding primer system is implemented. Based on the moisture content and density parameters of each zone, the solid content, penetration enhancer, elastic reinforcing component, and curing component addition ratios of the primer are dynamically adjusted to achieve precise matching of primer performance with the zone's substrate conditions. The specific process is as follows: S301: Check the core working parameters of the base surface moisture content and surface density of each independent construction zone one by one to obtain the construction shortcomings and performance requirements of the base surface of each zone. S302: To meet the specific needs of different working conditions and zones, a differentiated primer formulation scheme is matched, and the solid content of the primer base system is adjusted accordingly to adapt to the penetration and adhesion requirements of different substrates. S303: Add functional components according to the specific working conditions of each zone; for example, add a penetrating agent to damp substrate areas, add an elastic reinforcing component to substrate areas with defects, and add a curing component to loose substrate areas. S304: According to the mixing plan, complete the mixing ratio of the primer for each zone, and after thorough mixing, let it stand to mature so that the various performance indicators of the primer are adapted to the corresponding zone substrate, and achieve adaptive matching between the primer and the substrate working conditions.
[0039] In this embodiment, the comprehensive moisture content and surface density parameters corresponding to each construction zone (including key reinforcement zones) completed in step S200 are retrieved sequentially. A working condition analysis is performed on each zone: For damp zones with high moisture content, the construction weakness is that moisture easily causes the coating to blister and detach, requiring the primer to have good sealing and moisture penetration resistance; for zones with micro-defects such as minor cracks and unevenness, the weakness is that the substrate is prone to minor deformation, requiring the primer to have elastic deformation-following ability; for loose substrate zones with low density, the weakness is that the surface layer is powdery and loose, requiring the primer to have penetration, reinforcement, and anchoring capabilities; standard substrate areas have no obvious weaknesses and only require conventional bonding and sealing. The construction weaknesses and required performance requirements corresponding to each zone are compiled and recorded as input conditions for primer formulation.
[0040] Based on the performance requirements of each zone obtained in step S301, a corresponding primer base system is selected for each zone. For standard substrate areas, a water-based primer base material with conventional solids content is used directly; for damp substrate areas, the amount of water added for dilution is reduced, the primer solids content is increased, and the sealing effect on substrate pores is strengthened; for micro-defect substrate areas, a medium-to-high solids content primer base material is selected to ensure filling and film formation capabilities; for porous substrate areas, a medium-to-high solids content primer base material is selected to ensure that the components can penetrate into the interior of the porous substrate surface. An independent mixing plan is developed for each zone, specifying the base primer system and solids content adjustment method. Different zones are mixed separately and do not share the same container of primer material.
[0041] According to the formulation plan for each zone, add the corresponding functional components to the base material of the primer. No additional functional components are added to the standard substrate area; a set proportion of hydrophilic penetrating agent is added to the primer for the damp substrate area; a set proportion of elastic reinforcing emulsion component is added to the primer for the micro-defect substrate area; a set proportion of silicone penetrating curing component is added to the primer for the porous substrate area; the component addition plan for the key reinforcement zones is inherited from the original substrate area. During the component addition process, the materials are metered according to the proportions to avoid deviations in component ratios caused by arbitrary visual estimation. After the materials are added, preliminary mixing is performed.
[0042] Thoroughly mix the primer for each zone after all materials have been added, ensuring uniform mixing of the base material and functional components without localized agglomeration or stratification. After mixing, allow the prepared primer to stand for curing, allowing the functional components to fully disperse and activate, forming a stable primer. The curing time for each zone's primer is set differently depending on the specific working condition. Once curing is complete, the material should not stratify or show significant clumping, indicating an adaptive primer suitable for that zone's working conditions. Each zone's prepared primer should be stored separately and clearly labeled to prevent mixing.
[0043] S400: Based on the zoning results, corresponding adaptive primers are applied to different substrate zones, matching differentiated coating thicknesses, number of coats, and application methods. After the primers in each zone are surface dry, a compatible topcoat waterproofing coating is applied cross-coated across the entire surface. Differentiated curing is implemented for different zones, matching the curing rate of the coating in each zone to achieve synchronous and stable forming of the coating across the entire area. The specific process is as follows: S401: Based on the construction division results of each zone, take the adaptive primer that is suitable for the corresponding working conditions, and set the exclusive coating thickness, number of construction coats and coating operation method for different zones; among them, the zone with the most emphasis is to prioritize thicker coating construction. S402: Complete the primer application in each zone, ensuring that the primer in each zone fully penetrates the pores of the substrate and seals the defects on the substrate surface. Wait until the primer in all construction zones reaches the touch dry state. S403: Use a uniform, compatible surface waterproof coating to apply a cross-shaped, overall coating to the entire construction substrate. S404: Based on the original substrate conditions of each zone, develop a zone-specific maintenance plan and adjust the maintenance time, ventilation conditions and moisturizing maintenance methods for each zone accordingly. S405: By using zoned differentiated curing to adapt to the curing speed of coatings in different areas, the overall coating forming rhythm is balanced.
[0044] In this embodiment, the adaptive primer prepared in step S300 is used according to the numbering of each construction zone on site. Using the wrong primer material across zones is strictly prohibited. For each type of zone, a pre-set target dry film thickness, number of coats, and application method are established. A single cross-coat is applied to standard substrate areas; two coats are applied to damp substrate areas; a thicker, filling-type coat is applied to slightly defective substrate areas; a slower, more penetrating coat is used to reduce the spraying / brushing speed in porous substrate areas; and an additional reinforcing coat is applied to key reinforcement zones based on the original coating parameters. The primer application to key reinforcement zones is prioritized, followed by the primer application to other zones in sequence. During application, the amount of primer applied at one time is controlled using the application tools to ensure the target dry film thickness is achieved.
[0045] Apply the primer layer section by section, working within the designated area defined by the release tape, ensuring the paint does not overflow the release tape boundary. Observe the primer's wetting status during the application process to ensure it penetrates and covers the pores and micro-cracks in the substrate, sealing the voids and defects. After all sections have been primed, allow them to dry naturally under ambient conditions; do not use forced drying. Perform a touch-dry test periodically: lightly touch the primer surface with your finger; if there is no noticeable stickiness or paint adhering to your finger, it is considered touch-dry. The topcoat application can only proceed after all sections have reached touch-dry status; the topcoat application will not begin if any section has not reached touch-dryness.
[0046] Remove the masking tape used for physical isolation on site to eliminate physical barriers between zones and ensure the overall continuity of the substrate. Select a suitable topcoat waterproofing coating for this project, following the construction sequence of vertical surfaces first, then horizontal surfaces, and then key nodes before large areas. Apply the first coat by brushing or rolling along one direction to cover the entire substrate. After the first coat is surface dry, apply the second coat in a cross-hatching pattern perpendicular to the first coat. Ensure the coating is continuous during application, paying special attention to filling in any seams left after tape removal to eliminate weak points in the coating. The overall topcoat should be complete and continuous, without any missed areas or exposed substrate.
[0047] The original substrate condition attributes for each zone are retrieved, and an independent curing plan is set for each zone. The curing plan includes the total curing time required for that zone, ventilation control conditions, and whether moisturizing measures are needed. Standard substrate areas are cured using conventional natural ventilation; damp substrate areas are cured with weak ventilation combined with moisturizing measures to prevent rapid surface dehydration and crusting; slightly defective substrate areas are protected from light to reduce excessive shrinkage of the coating caused by sunlight; and loose substrate areas are cured with sealed moisturizing to ensure sufficient penetration and curing reaction. On-site, corresponding curing control is implemented for different zones, using different methods such as wind protection, moisturizing coverage, and light-blocking, rather than a uniform ventilation and moisturizing mode for the entire area.
[0048] During the curing process, the curing status of the coating in different zones is continuously observed. The curing reaction cycle is longer on damp or porous substrates. Moisturizing and reducing ventilation rates slow down the surface film formation, ensuring sufficient time for internal moisture and reaction components to release and react. For substrates with minor defects, light exposure is controlled to prevent excessive shrinkage and cracking of the coating. Standard substrates cure at a normal pace. By using differentiated curing methods for each zone, the inconsistent curing speed caused by differences in the original substrate conditions is offset, allowing the curing progress of each zone to be synchronized. This ensures the overall stability and formation of the waterproof coating, reducing localized quality defects such as blistering, cracking, and incomplete curing.
[0049] Corresponding to the aforementioned embodiments of the substrate adaptive waterproof coating construction method, this application also provides embodiments of the substrate adaptive waterproof coating construction system.
[0050] Figure 6 This is a structural schematic diagram illustrating a substrate-adaptive waterproof coating application system according to an exemplary embodiment. (Refer to...) Figure 6 The system may include: a substrate grading and detection module, a primer area zoning module, a regional primer mixing adaptive module, and a regional differentiated curing module; wherein: The base surface classification and detection module is used to perform full-coverage detection on the entire base surface to be constructed, collect parameters such as moisture content, surface density, flatness, and minor defects of the entire base surface to be constructed, divide the base surface into four working condition areas based on the detection parameters: standard base surface area, damp base surface area, micro-defect base surface area, and loose base surface area, complete the base surface working condition classification and area marking, and output the base surface classification and marking results. The primer area zoning module is used to physically divide the overall construction surface based on the base surface grading and marking results, and to independently divide the base surface under different working conditions into separate construction zones, retain the boundary markings of each zone, and separately divide special areas such as inside and outside corners, pipe roots, and crack nodes into key reinforcement zones. The adaptive module for regional primer formulation is used to adaptively formulate the corresponding primer system for each type of independent zone substrate condition. It dynamically adjusts the solid content, penetration aid, elastic reinforcing component, and curing component addition ratio of the primer according to the moisture content and density parameters of each zone, so as to achieve precise matching between primer performance and zone substrate condition. The regional differentiated curing module is used to apply corresponding adaptive primers to different substrate zones according to the zoning results, match differentiated coating thickness, number of coatings and construction methods. After the primers of each zone are surface dry, the adaptive top-layer waterproof coating is applied cross-coated, and differentiated curing is implemented for different zones to match the curing rate of the coating in each zone, so as to achieve synchronous and stable forming of the coating throughout the entire area.
[0051] In this embodiment, the substrate grading and detection module performs full-coverage detection on the entire substrate to be constructed, collecting parameters such as moisture content, surface density, flatness, and minor defects. Based on the detection parameters, the substrate is divided into four working condition areas: standard substrate area, damp substrate area, micro-defect substrate area, and loose substrate area, completing the substrate working condition grading and area marking, and outputting the substrate grading and marking results. The primer area zoning module, based on the substrate grading and marking results, physically divides the entire construction surface into separate construction zones, independently dividing the substrate under different working conditions into separate construction zones, retaining the boundary markings of each zone, and separately classifying special areas such as corners, pipe roots, and crack nodes as key reinforcement zones. The regional primer mixing adaptive module is designed for each type of independent zone of substrate. The system employs a differentiated adaptive formulation to adjust the corresponding primer system. Based on the moisture content and density parameters of each zone, the solids content, penetration aids, elastic reinforcing components, and curing component addition ratios of the primer are dynamically adjusted to achieve precise matching between primer performance and the working conditions of the substrate in each zone. The differentiated curing module, according to the zone division results, uses corresponding adaptively formulated primers for different substrate zones, matching differentiated coating thickness, number of coats, and construction methods. After the primers in each zone are surface dry, a compatible topcoat waterproofing coating is applied cross-coated, and differentiated curing is implemented for different zones, matching the curing rate of the coating in each zone to achieve synchronous and stable forming of the coating across the entire area. Through the above methods, substrate self-adaptation, zone matching, and differentiated construction and curing are achieved, meeting the high-quality waterproofing construction requirements for complex and uneven substrates.
[0052] Regarding the system in the above embodiments, the specific ways in which each module performs operations have been described in detail in the embodiments related to the method, and will not be elaborated here.
[0053] For the system embodiments, since they basically correspond to the method embodiments, the relevant parts can be referred to in the description of the method embodiments. The device embodiments described above are merely illustrative. The units described as separate components may or may not be physically separate, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed across multiple network units. Some or all of the modules can be selected to achieve the purpose of this application according to actual needs. Those skilled in the art can understand and implement this without creative effort.
[0054] Accordingly, this application also provides an electronic device, comprising: one or more processors; a memory for storing one or more programs; and, when the one or more programs are executed by the one or more processors, causing the one or more processors to implement the substrate adaptive waterproof coating application method as described above. Figure 7The diagram shown is a hardware structure diagram of any device with data processing capabilities, which is part of a substrate adaptive waterproof coating construction system provided in an embodiment of the present invention. (Except for...) Figure 7 In addition to the processor, memory, and network interface shown, any data processing device in the embodiment may also include other hardware depending on the actual function of the data processing device, which will not be described in detail here.
[0055] Accordingly, this application also provides a computer-readable storage medium storing computer instructions, which, when executed by a processor, implement the aforementioned method for applying an adaptive waterproof coating to a substrate. The computer-readable storage medium can be an internal storage unit of any data-processing device as described in any of the foregoing embodiments, such as a hard disk or memory. The computer-readable storage medium can also be an external storage device, such as a plug-in hard disk, smart media card (SMC), SD card, flash card, etc., mounted on the device. Furthermore, the computer-readable storage medium can include both internal storage units of any data-processing device and external storage devices. The computer-readable storage medium is used to store the computer program and other programs and data required by the data-processing device, and can also be used to temporarily store data that has been output or will be output.
[0056] Other embodiments of this application will readily occur to those skilled in the art upon consideration of the specification and practice of the disclosure herein. This application is intended to cover any variations, uses, or adaptations of this application that follow the general principles of this application and include common knowledge or customary techniques in the art not disclosed herein.
[0057] It should be understood that this application is not limited to the precise structure described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from its scope.
Claims
1. A method for applying an adaptive waterproof coating to a substrate, characterized in that, Includes the following steps: A full-coverage inspection is conducted on the entire substrate surface to be constructed, collecting parameters such as moisture content, surface density, flatness, and minor defects. Based on the inspection parameters, the substrate surface is divided into four working condition areas: standard substrate area, damp substrate area, micro-defect substrate area, and loose substrate area. The working condition classification and area marking of the substrate surface are completed, and the substrate surface classification and marking results are output. Based on the results of the base surface classification and marking, the overall construction surface is physically divided into zones. The base surfaces under different working conditions are independently divided into separate construction zones, and the boundary markings of each zone are retained. Special areas such as inside and outside corners, pipe roots, and crack nodes are separately designated as key reinforcement zones. For each type of independent zone of substrate conditions, the corresponding primer system is adjusted in a differentiated and adaptive manner. The solid content, penetration aid, elastic reinforcing component and curing component of the primer are dynamically adjusted according to the moisture content and density parameters of each zone to achieve precise matching between the primer performance and the substrate conditions of each zone. Based on the zoning results, corresponding adaptive primers are applied to different substrate zones, matching differentiated coating thicknesses, number of coats, and construction methods. After the primers in each zone are surface dry, a compatible topcoat waterproof coating is applied cross-coated. Differentiated curing is implemented for different zones, matching the curing rate of the coating in each zone to achieve synchronous and stable forming of the coating across the entire area.
2. The method for applying an adaptive waterproof coating to a substrate as described in claim 1, characterized in that, The process involves conducting a full-coverage inspection of the entire substrate surface to be constructed, collecting parameters such as moisture content, surface density, flatness, and minor defects. Based on these parameters, the substrate surface is divided into four working condition areas: standard substrate area, damp substrate area, micro-defect substrate area, and loose substrate area. The resulting substrate working condition classification and area labeling are then output. A comprehensive inspection and testing of the entire building surface to be constructed was conducted, and core working condition parameters of the surface were collected. These core working condition parameters include moisture content, surface density, flatness, and minor defects. The core working condition parameters of the base surface are summarized and compared with the preset base surface working condition judgment standard. The working condition of the construction base surface is classified and identified. Based on the parameter identification results, the overall base surface is divided into four independent working condition areas: standard base surface area, damp base surface area, micro-defect base surface area, and loose base surface area.
3. The method for applying an adaptive waterproof coating to a substrate as described in claim 2, characterized in that, After summarizing the core working condition parameters of the base surface, comparing them with the preset base surface working condition judgment standards, classifying and identifying the working condition of the construction base surface, and dividing the overall base surface into four independent working condition areas based on the parameter identification results: standard base surface area, damp base surface area, slightly defective base surface area, and loose base surface area: Mark the on-site locations and outlines of the various working areas that have been divided, record the location, range and working condition attributes of each area, and generate and output the base surface hierarchical marking results.
4. The method for applying an adaptive waterproof coating to a substrate as described in claim 1, characterized in that, In the steps of physically dividing the overall construction surface based on the base surface grading and marking results, dividing the base surface under different working conditions into separate construction zones, retaining the boundary markings of each zone, and separately designating special areas such as inside and outside corners, pipe roots, and crack nodes as key reinforcement zones: Obtain the datum surface classification and marking results, obtain the distribution location, area range and boundary contour of each working condition area, and determine the area boundary line of the datum surface under different working conditions; The overall construction surface is physically divided by a partitioning and isolation method. Base surfaces with the same working conditions are integrated into independent construction zones, and the boundaries of each construction zone are marked to distinguish the scope of each construction zone.
5. The substrate adaptive waterproof coating construction method as described in claim 4, characterized in that, After physically dividing the overall construction surface using a partitioning and isolation method, integrating base surfaces with the same working conditions into independent construction zones, and marking the boundaries of each construction zone to distinguish the scope of each construction zone: Identify special nodes such as the inside and outside corners of the construction surface, pipe roots, and cracks in the base surface, and designate them as key reinforcement zones.
6. The method for applying an adaptive waterproof coating to a substrate as described in claim 1, characterized in that, In the process of tailoring the primer system to the specific substrate conditions of each independent zone, and dynamically adjusting the solid content, penetration aid, elastic reinforcing component, and curing component ratio of the primer according to the moisture content and density parameters of each zone, the following steps are taken to achieve precise matching between the primer performance and the substrate conditions of each zone: Check the core working parameters of the base surface moisture content and surface density of each independent construction zone one by one to obtain the construction shortcomings and performance requirements of the base surface of each zone. To meet the specific needs of different working conditions and zones, we match differentiated primer formulation schemes and adjust the solid content of the primer base system accordingly to adapt to the penetration and adhesion requirements of different substrates. Add functional components specifically based on the operating conditions of each zone.
7. The method for applying an adaptive waterproof coating to a substrate as described in claim 6, characterized in that, In the step of adding functional components based on the specific operating conditions of each zone: Add a penetrating agent to damp substrate areas, add an elastic reinforcing component to defective substrate areas, and add a curing component to loose substrate areas.
8. The method for applying an adaptive waterproof coating to a substrate as described in claim 6, characterized in that, After adding functional components based on the specific operating conditions of each zone: According to the mixing plan, the primer for each zone is mixed in proportion and stirred. After thorough mixing, it is allowed to stand and mature so that the performance indicators of the primer are adapted to the corresponding zone substrate, thus achieving adaptive matching between the primer and the substrate working conditions.
9. The method for applying an adaptive waterproof coating to a substrate as described in claim 1, characterized in that, In the process of dividing the substrate into zones according to the zoning results, applying corresponding adaptive primers to different substrate zones, matching differentiated coating thicknesses, number of coats, and construction methods, and after the primers in each zone are surface dry, applying a compatible topcoat waterproofing coating in a cross-coating manner, and implementing differentiated curing for different zones to match the curing rate of the coating in each zone, the following steps are taken to achieve synchronous and stable formation of the coating across the entire area: Based on the construction division results of each zone, an adaptive primer suitable for the corresponding working conditions is selected, and a specific coating thickness, number of coats and coating operation method are set for different zones; in particular, the zones with the most emphasis are given priority for thicker coating construction. Complete the primer application in each zone to ensure that the primer in each zone fully penetrates the pores of the substrate and seals the defects on the substrate surface. Wait until the primer in all construction zones reaches the touch dry state. A uniform, compatible waterproof coating is used to apply a cross-shaped coating to the entire construction surface.
10. The method for applying an adaptive waterproof coating to a substrate as described in claim 9, characterized in that, After uniformly applying a compatible waterproof coating to the entire construction surface in a cross-shaped pattern: Based on the original substrate conditions of each zone, a zone-specific maintenance plan is developed, and the maintenance time, ventilation conditions and moisturizing maintenance methods are adjusted differently for each zone. By using zoned differentiated curing to adapt to the curing speed of coatings in different areas, the overall coating forming rhythm is balanced.