A high-rise building facade integrated decoration construction method

By integrating the vertical zoning and flow logic of the climbing scaffolding system, the problems of long construction cycles, high safety risks, and numerous leakage hazards in the construction of high-rise building facades have been solved, achieving efficient, safe, and reliable integrated facade decoration construction.

CN123133553APending Publication Date: 2026-11-20SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611647404.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-23
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

The existing construction of high-rise building facade decoration has problems such as long cantilever scaffolding erection period, large material turnover, limited load capacity of suspended scaffolds, limited operating space, high safety risks, long waiting time for procedures, difficulty in guaranteeing quality, and many potential leakage hazards. In addition, there is a lack of system integration and cycle control.

Method used

The exterior facade integrated decoration construction method based on the climbing formwork system is adopted. Through vertical zoning and flow logic, optimization of component connection nodes, and strict control of the interleaving rhythm, the synchronous construction of all-concrete exterior walls, facing bricks, prefabricated components, and aluminum formwork composite system is achieved, forming a five-system integration. The preconditions and triggering time of each process are clearly defined. The system adopts all-steel climbing formwork, pull-plate aluminum formwork, prefabricated components, thin plastering plus facing brick system, and three-layer waterproofing system for exterior windows.

Benefits of technology

It significantly shortens the construction period, ensures reliable high-altitude bonding quality, reduces leakage risk, improves safety and environmental protection, reduces rework and idle time, and achieves efficient, safe and reliable completion of integrated construction of high-rise building facades.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133553A_ABST
    Figure CN123133553A_ABST
Patent Text Reader

Abstract

The application relates to the technical field of building engineering, in particular to a high-rise building outer facade integrated decoration construction method, which comprises the following steps: step one, vertical partitioned flow operation model establishment, the building is divided into three synchronous construction dynamic regions in the vertical direction, the lifting of a climbing frame is used to vacate the operation surface of the lower layer, and flow circulation is formed, wherein the upper structure construction area is N layers, steel bar binding, aluminum mold setting and concrete pouring are carried out, and the middle decoration interspersed area is N-1 to N-2 layers; the building is divided into three synchronous construction dynamic regions, i.e. an upper structure construction area, a middle decoration interspersed area and a lower finishing and removal area in the vertical direction, the lifting of a climbing frame is used to vacate the operation surface of the lower layer, flow circulation is formed, the construction rhythm of a standard layer of structure is 6 days per layer, the climbing frame is lifted once every 6 days, the outer facade decoration is followed layer by layer along with the main body structure, and the overall construction period of the outer facade is significantly shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building engineering technology, specifically to a method for integrated decoration construction of the exterior facade of high-rise buildings. Background Technology

[0002] In the current construction of high-rise building facade decoration, cantilever scaffolds or suspended platforms are commonly used. The erection period of cantilever scaffolds is long, the turnover of materials is large, and they obstruct subsequent facade construction processes. Suspended platforms have limited load-bearing capacity, cannot provide material storage space, restrict the operating space of workers, and are not fully enclosed, so there is a greater risk of falling objects from heights. Traditional facade construction often adopts a serial mode, with plastering, window frame installation, and facing brick laying carried out layer by layer after the main structure is completed. The waiting time between each process is long, and it is difficult to shorten the facade construction period.

[0003] In the construction of facade brick systems, the quality of high-altitude bonding is greatly affected by the flatness of the base layer, the adhesive material, and the construction process, easily leading to problems such as hollowing, detachment, and efflorescence. Exterior windows are high-risk areas for leakage, and traditional single or double-layer waterproofing methods are unreliable under the conditions of high wind pressure and heavy rainfall in high-rise buildings. Inadequate sealing of traditional bolt holes during aluminum formwork construction can also easily create leakage risks. The lack of systematic integration and rhythm control between processes such as precast component installation, thin plastering, exterior window installation, and facade brick laying easily results in rework, idle time, and contamination of finished products. Therefore, this application proposes an integrated decoration construction method for the exterior facade of high-rise buildings. Summary of the Invention

[0004] To address the shortcomings of existing technologies, this solution provides an integrated facade decoration construction method based on a climbing formwork system. By reconstructing the vertical flow logic, optimizing component connection nodes, and strictly controlling the overlapping rhythm, it solves the technical problems of simultaneous, non-interfering, and reliable construction of facades using all-concrete exterior walls, facing bricks, prefabricated components, all-steel climbing formwork, and aluminum formwork composite systems.

[0005] This application provides a method for integrated decoration construction of the exterior facade of high-rise buildings, including the following steps: Step 1: Establishment of a vertical zoning flow operation model. The building is divided into three dynamic areas for simultaneous construction in the vertical direction. The climbing formwork is used to create working surfaces for the lower level, forming a flow cycle. The upper structure construction area is level N, where steel reinforcement binding, aluminum formwork erection, and concrete pouring are carried out. The middle decoration and interspersed area is level N-1 to N-2, where base treatment, thin plastering, window frame installation, railing installation, and external pipe installation are carried out from bottom to top under the protection of the climbing formwork. The lower finishing and demolition area is level N-3 and below, where facing brick laying, grouting, cleaning, and preparation for climbing formwork dismantling are carried out. Step 2: Integration and coordination of five major systems, integrating the all-steel climbing formwork, pull-tab aluminum formwork, prefabricated components, thin plastering with facing brick system, and three-layer waterproofing system for exterior windows, so that each system creates the preconditions for the next process. Step 3: Control the interleaving and meshing of processes, clarify the preconditions and triggering time of each process, and transfer the base layer after the aluminum mold is demolded and the strength reaches 1.2MPa; After the base layer passes inspection, the thin plastering work begins; after the water spraying of the grouting of the exterior window frames passes inspection, the edge finishing of the exterior window frames begins. After the thin plaster has been cured and its strength meets the specifications, the exterior wall tiles will be laid. After the exterior wall tiles are laid and the strength meets the standards, and after the laying, grouting, curing and wall washing of this layer are completed, the climbing scaffold is used for lifting.

[0006] Furthermore, in step one, the standard floor height is 3m, the construction rhythm of the standard floor is one floor every 6 days, and the climbing scaffold is lifted once every 6 days.

[0007] Furthermore, with a standard construction cycle of one floor every 6 days, when the Nth floor concrete pouring is completed, the N-1th floor thin plaster base treatment is completed, the N-2th floor thin plastering is completed and the exterior window frames, railings and bay windows are installed, and the N-3th floor exterior facade facing brick laying is completed and the climbing scaffold is ready for climbing.

[0008] Furthermore, in step two, the pull-plate aluminum formwork incorporates all secondary structures and electromechanical points in the structural columns, door lintels, electrical boxes, composite slab grooves, and window frame grooves into the main body for one-time casting during the detailed design stage. The exterior walls use a tie-plate system instead of traditional bolts; After the template is installed, the empty formwork is measured. The verticality deviation of the wall and column is controlled within 4mm, and the deviation of the top plate is controlled within 10mm. The actual measured data after demolding is used as the basis for acceptance of the thin plaster base layer.

[0009] Furthermore, the thin plastering and facing brick laying process includes: checking the base layer with a 2m straightedge, and grinding or repairing any areas with a flatness greater than 4mm in advance; Use special polymer mortar WP-M15 for thin plastering, with the total thickness controlled within 5mm, applied in layers, and cured for 3 days; For bonding the facing tiles, use C2 grade or higher tile adhesive, apply grout to both sides, use a notched trowel to comb through the stripes, press and rub after application to the wall, and achieve a full adhesion rate of no less than 95%. Grouting is carried out 48 to 72 hours after laying, using CG2WA grade anti-alkali grout, and implementing a secondary pressing process.

[0010] Furthermore, during the installation of prefabricated components, the prefabricated bay window should be equipped with at least two adjustable diagonal braces with an angle of 45° to 60°. The verticality should be finely adjusted using a laser total station to ensure that it does not exceed 3mm per floor. The hooks must not be removed if the supports are not securely fixed. Before closing the formwork, check the anchorage length of the reinforcing bars and the stirrup reinforcement zone at the connection between the precast components and the cast-in-place structure.

[0011] Furthermore, the three-layer waterproofing system for exterior windows includes: the first layer is sealing the gap, which is controlled at 5 to 15 mm after the window frame is fixed. It is filled and compacted in layers with polymer waterproof mortar with an impermeability grade of not less than P6, and cured for 48 hours. The second coat of paint extends 150mm outward from the junction of the window frame and the exterior wall, and 200mm outward from the bottom frame. Polymer waterproof coating is applied, with a dry film thickness of not less than 1.5mm. The third coat of sealant is applied after the paint dries. Weather-resistant sealant has a displacement capacity of not less than ±20%, a joint width of 6 to 10mm, a thickness of not less than 3mm, and is formed into a crescent-shaped concave surface. After all three processes are completed and the sealant has cured for 24 hours, a water spray test is conducted with a water pressure of 0.1 to 0.2 MPa for 2 hours. If the test fails, the work must be reworked immediately.

[0012] Furthermore, fully enclosed rigid partitions are installed at the bottom of the 1st, 4th, and 6th floors of the climbing scaffold from bottom to top; The bottom flap of the climbing scaffold is made of bent steel plate, with a gap of no more than 20mm between it and the wall, and an overlap length of no less than 150mm. The hoisting time for the exterior facade materials of each tower is fixed at night or during the intervals between concrete pouring, and a weekly coordination meeting is held to dynamically adjust the schedule.

[0013] Furthermore, after each process is completed, handover and acceptance are completed within 24 hours and the process is handed over to the next process, and a visual list of completed items is established for management; before the climbing scaffold is lifted, ensure that the tiling, grouting and maintenance and wall washing of the floor are completed.

[0014] Furthermore, the all-steel climbing formwork provides protection and a working platform for the pull-plate aluminum formwork, precast components, thin plastering and facing brick system, and the three-layer waterproofing system for exterior windows. Each system creates preconditions for each other according to the vertical zone flow rhythm, forming a replicable interleaved process model.

[0015] The technical solution provided in this application has at least the following technical effects or advantages: 1. This invention divides the building vertically into three dynamic areas for simultaneous construction: the upper structure construction area, the middle decoration interleaving area, and the lower finishing demolition area. The climbing formwork is used to create working surfaces for the lower floors, forming a continuous flow cycle. The construction rhythm of the standard structural floor is one floor every 6 days, and the climbing formwork is raised once every 6 days. The exterior decoration is carried out layer by layer in conjunction with the main structure, which significantly shortens the overall construction period of the exterior facade. 2. This invention achieves deep integration of all-steel climbing formwork, pull-plate aluminum formwork, prefabricated components, thin plastering and facing brick system, and three waterproofing systems for exterior windows. Each system forms clear preconditions and triggering times. The aluminum alloy formwork enables thin plastering of shear walls, with flatness controlled within 4mm, providing a high-precision base surface for thin plastering without the need for thick leveling. The thickness of the thin plastering is controlled within 5mm, with strong adhesion, providing a solid and flat bonding base for facing bricks. This breakthrough overcomes the integrated construction problem of the facing brick system for high-rise building facades and ensures reliable high-altitude bonding quality. 3. The exterior window of this invention adopts a three-layer waterproofing system consisting of caulking, coating, and sealant. The first layer of caulking uses polymer waterproof mortar with an impermeability grade of not less than P6. The second layer of coating has a dry film thickness of not less than 1.5mm. The third layer of sealant has a displacement capacity of not less than ±20%. After the three processes are completed, a water spray test is conducted. The waterproofing of the exterior window structure is completed before the exterior wall tiles are laid, which significantly reduces the risk of leakage of exterior windows in high-rise buildings. 4. In the detailed design stage, the pull-tab aluminum formwork of this invention incorporates all secondary structures and electromechanical points such as structural columns, door lintels, electrical boxes, composite slab grooves, and window frame grooves into the main body for one-time casting. The exterior wall adopts a pull-tab system instead of traditional bolts, eliminating the leakage risk caused by incomplete sealing of bolt holes. After demolding, the actual measured data can be directly used as the basis for acceptance of the thin plaster base layer, reducing the workload of secondary structure construction and base layer treatment. 5. This invention enables high-precision factory production of prefabricated bay windows, stairs, and composite slabs, reducing cast-in-place joints on the exterior facade and providing a stable base for the facing bricks. Prefabricated bay windows are installed with at least two adjustable diagonal braces, and verticality is precisely adjusted using a laser total station. Hooks must not be removed if the supports are not securely fixed, ensuring the installation accuracy and connection safety of the prefabricated components. 6. This invention's all-steel climbing scaffold provides a fully enclosed, liftable working platform and material handling space, offering protection against falling objects and an all-weather working surface for the lower decoration work. Fully enclosed rigid partitions are installed at the bottom of the 1st, 4th, and 6th layers of the climbing scaffold. The bottom flaps are made of bent steel plates, with the gap between them and the wall controlled within 20mm. The overlap length of the flaps is no less than 150mm, effectively preventing grinding dust and poured cement slurry from falling and contaminating the brick surface, thus ensuring both safety and environmental protection. Attached Figure Description

[0016] Figure 1 This is a flowchart illustrating the construction process of the integrated decoration of the high-rise building facade in this application. Detailed Implementation

[0017] This application discloses a method for integrated decoration construction of the exterior facade of a high-rise building. The technical solutions of the embodiments of this invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this invention, and not all of them. Based on the embodiments of this invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this invention.

[0018] To better understand the above technical solution, the following will provide a detailed explanation of the above technical solution in conjunction with the accompanying drawings and specific implementation methods.

[0019] The building is divided vertically into three dynamic zones for simultaneous construction. The upper structure construction zone is the Nth floor, where steel reinforcement binding, aluminum formwork erection, and concrete pouring are carried out. The middle decoration interlude zone is the N-1 to N-2 floors, where base treatment, thin plastering, window frame installation, railing installation, and external pipe installation are carried out from bottom to top under the protection of climbing scaffolding.

[0020] The lower finishing demolition area is floors N-3 and below, where paving bricks, grouting, cleaning, and preparation for dismantling the climbing scaffold are carried out. The standard floor height is about 3m, and the construction rhythm of the standard structural floor is about one floor every 6 days. The climbing scaffold is raised once every 6 days. The lifting and lowering of the climbing scaffold makes room for the work surface of the lower floor, forming a continuous flow.

[0021] The system integrates all-steel climbing formwork, pull-tab aluminum formwork, precast components, thin plastering with facing brick system, and three-layer waterproofing system for exterior windows. The all-steel climbing formwork provides a fully enclosed working platform and safety protection. The pull-tab aluminum formwork enables the main structure to be formed in one go and eliminates the risk of leakage through bolt holes. The precast components are connected to the cast-in-place structure. The thin plastering with facing brick system is constructed layer by layer under the protection of the climbing formwork. The three-layer waterproofing system for exterior windows is implemented sequentially after the window frames are installed. Each system creates the preconditions for the next process.

[0022] Clearly define the prerequisites and triggering times for each process. After the aluminum formwork is demolded and the strength reaches 1.2MPa, the base layer is handed over. After the base layer passes inspection, the thin plastering construction begins. After the external window frame is sealed and water sprayed and passes inspection, the external window frame edge finishing begins. After the thin plastering is cured and the strength meets the specifications, the external wall tiles are laid. After the external wall tiles are laid and the strength meets the standards, and after the laying, grouting, curing, and wall washing of this layer are completed, the climbing scaffold is lifted.

[0023] The detailed design and installation of pull-tab aluminum formwork involves incorporating all secondary structures and electromechanical points, such as structural columns, door lintels, electrical boxes, composite slab grooves, and window frame grooves, into the main structure for one-time casting. The exterior wall uses a tie-plate system instead of traditional screw rods. After the formwork is installed, the empty formwork is measured. The verticality deviation of the wall and column is controlled within 4mm, and the deviation of the top plate is controlled within 10mm. The actual measured data after demolding is directly used as the basis for acceptance of the thin plaster base layer.

[0024] For thin plastering and tile laying, the base layer is checked with a 2m straightedge. Areas with flatness greater than 4mm are ground or repaired in advance. Use special polymer mortar WP-M15 for thin plastering, with the total thickness controlled within 5mm. Apply in layers and cure for 3 days. Use C2 grade or higher tile adhesive for bonding the tiles, strictly follow the double-sided slurry application, use a notched trowel to comb the stripes, and press firmly after application to the wall to achieve a full adhesion rate of no less than 95%. Grouting is carried out 48 to 72 hours after laying, using CG2WA grade anti-alkali grout and implementing a secondary pressing process.

[0025] For the installation of precast components, precast bay windows should be installed with at least two adjustable diagonal braces at an angle of 45° to 60°. The verticality should be finely adjusted using a laser total station to ensure it does not exceed 3mm per floor. Hooks must not be removed if the supports are not securely fixed. Before closing the formwork, carefully check the anchorage length of the reinforcing bars and the area with reinforced stirrups at the connection between the precast components and the cast-in-place structure.

[0026] The exterior window frame undergoes a three-layer waterproofing installation. The first layer involves sealing the gaps, ensuring they are 5-15mm after the window frame is fixed. Polymer waterproof mortar with a waterproofing grade of at least P6 is used for layered filling and compaction, followed by 48 hours of curing. The second layer is a coating, applied 150mm outwards from the junction of the window frame and the exterior wall, and 200mm outwards from the bottom frame. The dry film thickness is at least 1.5mm. The third layer is a sealant, applied after the coating dries. This sealant has a displacement capacity of at least ±20%, with a sealant joint width of 6-10mm and a thickness of at least 3mm, forming a crescent-shaped concave surface. After all three layers are completed and the sealant has cured for 24 hours, a water spray test is conducted at a water pressure of 0.1-0.2MPa for 2 hours. Any work that fails the test is immediately reworked.

[0027] Fully enclosed rigid partitions are installed at the bottom of the 1st, 4th and 6th floors of the climbing scaffold from bottom to top to prevent grinding dust and cement slurry from falling and contaminating the brick surface. The bottom flaps of the climbing scaffold are made of bent steel plates with a gap of no more than 20mm from the wall and an overlap length of no less than 150mm. The hoisting time for the exterior materials of each tower is fixed at night or during the interval of concrete pouring, and a weekly coordination meeting is held to dynamically adjust the schedule.

[0028] With a standard construction cycle of one floor every six days, when the Nth floor concrete pouring is completed, the N-1th floor thin plaster base treatment must be completed, the N-2th floor thin plastering and the installation of exterior window frames, railings, and bay windows must be completed, and the N-3th floor exterior facade cladding brick laying must be completed and the climbing scaffolding must be ready for climbing. After each process is completed, handover and acceptance must be completed within 24 hours and the process must be handed over to the next process, and a visual checklist management system must be established.

[0029] The collaborative relationships between the various systems are shown in Table 1 below:

[0030] Table 1

[0031] Obviously, those skilled in the art can make various modifications and variations to this invention without departing from its spirit and scope. Therefore, if these modifications and variations fall within the scope of the claims of this invention and their equivalents, this invention also intends to include these modifications and variations.

[0032] The above description is merely a preferred embodiment of the present application, but the scope of protection of the present application is not limited thereto. Any equivalent substitutions or modifications made by those skilled in the art within the scope of the technology disclosed in the present application, based on the technical solution and concept of the present application, should be covered within the scope of protection of the present application.

Claims

1. A method for integrated exterior decoration construction of high-rise buildings, characterized in that, Includes the following steps: Step 1: Establishment of a vertical zoning flow operation model. The building is divided into three dynamic areas for simultaneous construction in the vertical direction. The climbing formwork is used to create working surfaces for the lower level, forming a flow cycle. The upper structure construction area is level N, where steel reinforcement binding, aluminum formwork erection, and concrete pouring are carried out. The middle decoration and interspersed area is level N-1 to N-2, where base treatment, thin plastering, window frame installation, railing installation, and external pipe installation are carried out from bottom to top under the protection of the climbing formwork. The lower finishing and demolition area is level N-3 and below, where facing brick laying, grouting, cleaning, and preparation for climbing formwork dismantling are carried out. Step 2: Integration and coordination of five major systems, integrating the all-steel climbing formwork, pull-tab aluminum formwork, prefabricated components, thin plastering with facing brick system, and three-layer waterproofing system for exterior windows, so that each system creates the preconditions for the next process. Step 3: Control the interleaving and meshing of processes, clarify the preconditions and triggering time of each process, and transfer the base layer after the aluminum mold is demolded and the strength reaches 1.2MPa; After the base layer passes inspection, the thin plastering work begins; after the water spraying of the grouting of the exterior window frames passes inspection, the edge finishing of the exterior window frames begins. After the thin plaster has been cured and its strength meets the specifications, the exterior wall tiles will be laid. After the exterior wall tiles are laid and the strength meets the standards, and after the laying, grouting, curing and wall washing of this layer are completed, the climbing scaffold is used for lifting.

2. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, In step one, the standard floor height is 3m, the construction rhythm of the standard floor is one floor every 6 days, and the climbing scaffold is lifted once every 6 days.

3. The integrated decoration construction method for the facade of high-rise buildings according to claim 2, characterized in that, With a standard construction cycle of one floor every 6 days, when the concrete pouring of the Nth floor is completed, the thin plastering base treatment of the N-1th floor is completed, the thin plastering of the N-2nd floor is completed, and the window frames, railings, and bay windows of the exterior facade are installed. When the exterior facade cladding bricks of the N-3rd floor are laid, the climbing scaffold is ready to climb.

4. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, In step two, the pull-plate aluminum formwork incorporates all secondary structures and electromechanical points in the structural columns, door lintels, electrical boxes, composite slab grooves, and window frame grooves into the main body for one-time casting during the detailed design stage. The exterior walls use a tie-plate system instead of traditional bolts; After the template is installed, the empty formwork is measured. The verticality deviation of the wall and column is controlled within 4mm, and the deviation of the top plate is controlled within 10mm. The actual measured data after demolding is used as the basis for acceptance of the thin plaster base layer.

5. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, Thin plastering and facing brick laying include: checking the base layer with a 2m straightedge, and grinding or repairing areas with flatness greater than 4mm in advance; Use special polymer mortar WP-M15 for thin plastering, with the total thickness controlled within 5mm, applied in layers, and cured for 3 days; For bonding the facing tiles, use C2 grade or higher tile adhesive, apply grout to both sides, use a notched trowel to comb through the stripes, press and rub after application to the wall, and achieve a full adhesion rate of no less than 95%. Grouting is carried out 48 to 72 hours after laying, using CG2WA grade anti-alkali grout, and implementing a secondary pressing process.

6. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, When installing precast components, precast bay windows should be equipped with at least two adjustable diagonal braces with an angle of 45° to 60°. Use a laser total station to finely adjust the verticality to no more than 3mm per floor. Do not remove the hooks if the supports are not securely fixed. Before closing the formwork, check the anchorage length of the reinforcing bars and the stirrup reinforcement zone at the connection between the precast components and the cast-in-place structure.

7. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, The three-layer waterproofing system for exterior windows includes: the first layer is sealing the gap, which is controlled at 5 to 15 mm after the window frame is fixed. It is filled and compacted in layers with polymer waterproof mortar with a seepage resistance grade of not less than P6, and cured for 48 hours. The second coat of paint extends 150mm outward from the junction of the window frame and the exterior wall, and 200mm outward from the bottom frame. Polymer waterproof coating is applied, with a dry film thickness of not less than 1.5mm. The third coat of sealant is applied after the paint dries. Weather-resistant sealant has a displacement capacity of not less than ±20%, a joint width of 6 to 10mm, a thickness of not less than 3mm, and is formed into a crescent-shaped concave surface. After all three processes are completed and the sealant has cured for 24 hours, a water spray test is conducted with a water pressure of 0.1 to 0.2 MPa for 2 hours. If the test fails, the work must be reworked immediately.

8. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, Fully enclosed rigid partitions are installed at the bottom of the 1st, 4th, and 6th floors of the climbing scaffold from bottom to top; The bottom flap of the climbing scaffold is made of bent steel plate, with a gap of no more than 20mm between it and the wall, and an overlap length of no less than 150mm. The hoisting time for the exterior facade materials of each tower is fixed at night or during the intervals between concrete pouring, and a weekly coordination meeting is held to dynamically adjust the schedule.

9. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, After each process is completed, handover and acceptance shall be completed within 24 hours and the process shall be handed over to the next process. A visual list of items to be sold shall be established for management. Before the climbing scaffold is lifted, ensure that the tiling, grouting and maintenance and wall washing of the floor are completed.

10. The integrated decoration construction method for the facade of high-rise buildings according to claim 1, characterized in that, The all-steel climbing formwork provides protection and a working platform for the pull-plate aluminum formwork, precast components, thin plastering and facing brick system, and the three-layer waterproofing system for exterior windows. Each system creates preconditions for each other according to the vertical zone flow rhythm, forming a replicable interleaved process model.