A multi-device collaborative operation intelligent management method for sporadic concrete construction
By dividing the pumping pipeline into main sections, branch sections, and terminal sections and optimizing the pouring sequence, the problem of repeated disassembly and assembly of pipelines during sporadic concrete construction was solved, improving construction efficiency and continuity.
Patent Information
- Application Number
- CN202611644519.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-23
- Publication Date
- 2026-11-20
AI Technical Summary
In sporadic concrete construction, the repeated disassembly and assembly of pumping pipelines leads to low equipment coordination efficiency, poor construction continuity, and increases the workload of pipeline disassembly and connection and damage to the joints.
The pumping pipeline is divided into main sections, branch sections, and terminal sections. Pipeline laying decisions are made based on the pouring sequence and the usage of shared sections to avoid repeated disassembly and assembly. Pipeline usage is optimized through pressure pre-setting and local adjustments.
It improved the efficiency and continuity of multi-device collaborative operation, reduced the workload of pipeline disassembly and connection and interface damage, and ensured the overall efficiency and continuity of construction.
Smart Images

Figure CN123133569A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of construction management technology, and specifically discloses an intelligent management method for multi-device collaborative operation in sporadic concrete construction. Background Technology
[0002] In building construction, the concrete pouring of secondary components such as structural columns, retaining walls, lintels, and ring beams is considered piecemeal concrete work. This type of construction is characterized by the dispersed distribution of components, small volume of each pour, and numerous construction points. Because the components are not in the same location, and some are located in confined spaces or at high elevations, concrete cannot be directly poured from the mixing area into the components. Pumping is required to transport the concrete to the pouring locations of each component. Therefore, transportation equipment, pumping equipment, pumping pipelines, vibrating equipment, and pre-installed inlet components are necessary.
[0003] The transport unit is responsible for moving concrete from the mixing location to the pumping unit. The pumping unit then delivers the concrete through pumping pipes to the pre-reserved openings of each component. The pre-reserved opening assembly forms a pouring channel on the component formwork, connecting the end of the pumping pipe to the inside of the formwork, allowing the concrete to enter the component formwork through the pre-reserved opening. The vibration unit compacts the concrete inside the component during the pouring process. These multiple units need to coordinate their actions around the same pouring objective during the sporadic, point-by-point pouring of concrete.
[0004] The pumping pipeline is the transport path connecting the pumping device and the reserved openings of each component. After the transport device delivers the concrete to the pumping device, the pumping device needs to switch the pipeline according to the current component being poured. Since the components are located in different places, the pipeline branches leading to the reserved openings of different components are different. The traditional operation is that the on-site personnel determine the pipeline route according to the location of each individual component and lay it. After each component is poured, the corresponding pipe section is removed.
[0005] However, the same section of pipeline may be reused in the construction of multiple subsequent components. This method of temporarily determining the route according to individual components will cause the same section of pipeline to be repeatedly disassembled and reassembled. Repeated disassembly and reassembly of the pipeline leads to frequent pipeline adjustments, increases pipeline disassembly and connection time and equipment waiting time, and requires transportation equipment, pumping equipment and vibration equipment to wait for each other, thereby interrupting the continuous coordination between transportation, pumping and vibration. This not only increases the workload of pipeline disassembly and connection and is prone to damage to the interface, but also leads to low coordination efficiency between equipment, poor construction continuity, and affects the overall efficiency of concrete construction. Summary of the Invention
[0006] To overcome the shortcomings of the prior art, embodiments of the present invention provide an intelligent management method for multi-device collaborative operation in sporadic concrete construction, which can effectively solve the problems involved in the prior art.
[0007] The objective of this invention can be achieved through the following technical solution: a multi-device collaborative operation intelligent management method for sporadic concrete construction, comprising the following steps: dividing the pumping pipeline in the construction area into main sections, branch sections and terminal sections.
[0008] Based on the layout of the pumping pipeline, determine the pipe segment that each component to be poured passes through from the starting point of the pumping device to its reserved port, forming a pipe segment set.
[0009] By comparing the pipe segment sets of each component, pipe segments used by two or more components are marked as shared segments, and pipe segments used by only a single component are marked as independent segments.
[0010] The initial decision is made by determining the number of intervals for the shared section according to the pouring sequence. If the number of intervals for the shared section is not zero according to the initial decision, a further decision is made by combining the pipe segment identification of the shared section and the number of branch nodes from the shared section to the corresponding end segments of each component it serves, in order to determine whether the shared section should be laid in the laying stage. Then, the pipeline is laid according to the results of the initial decision and the further decision.
[0011] After the laying is completed, the transport device is connected to the inlet of the pumping device, and the pumping device opens the pipe section through which the component to be poured passes according to the pouring sequence to pump it.
[0012] Vibration and finishing monitoring are carried out at the end of the current component pouring. After entering the finishing stage, the end section of the current component is closed, the independent section is removed, and the shared section used by the current component is pressure-pre-set or removed and flushed in combination with the initial setting time of the concrete. Then, the unlaid pipe section of the next component is connected to complete the local adjustment of the pipeline. The transportation, vibration, reserved port components and pumping devices are coordinated to enter the preparation state for the operation of the next component.
[0013] Combining all the above technical solutions, the positive effects of this invention are as follows: 1. This invention divides the pumping pipeline into main sections, branch sections, and terminal sections. Based on the layout of the pumping pipeline, a set of pipe sections for the components to be poured is formed, and shared sections and independent sections are identified by comparison. The number of intervals is determined by the pouring sequence for initial decision-making. When the number of intervals for the shared sections is not zero, further decision-making is made by combining the pipe section identification and the number of branch nodes from the shared section to the corresponding terminal sections of each component it serves. Thus, the pipeline laying range is planned for the entire construction area, so that the pipeline laying serves the overall pouring sequence. This can effectively avoid repeated disassembly and assembly of the same pipe section between multiple components, reducing the workload of disassembly and assembly and the damage to the interfaces.
[0014] 2. This invention, after the pipeline section is laid, opens the pipeline section through which the component to be poured will pass according to the pouring sequence for pumping. At the end of the current component pouring, vibration monitoring is performed. After entering the final stage, based on the comparison between the estimated waiting time of the currently used shared section and the initial setting time of the concrete, local adjustments are made to the laid pipeline section. Simultaneously, the transportation, vibration, reserved outlet components, and pumping devices move into the preparation state for the next component. Thus, the pipeline section adjustments and the actions of each device are connected in the same sequence, avoiding mutual waiting between devices, ensuring continuous coordination of transportation, pumping, and vibration, and improving the efficiency of multi-device collaboration and construction continuity. Attached Figure Description
[0015] The present invention will be further described with reference to the accompanying drawings, but the embodiments in the drawings do not constitute any limitation on the present invention. For those skilled in the art, other drawings can be obtained based on the following drawings without creative effort.
[0016] Figure 1 This is a diagram illustrating the implementation steps of the method of the present invention;
[0017] Figure 2 This is a schematic diagram of the pumping pipeline segments and transport path in this invention;
[0018] Figure 3 This is a flowchart illustrating the implementation process of determining whether the decision-making sharing segment is in the deployment phase in this invention.
[0019] Figure 4 This is a schematic diagram of multiple devices connected together to implement pumping and casting in this invention. Detailed Implementation
[0020] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0021] This invention addresses the shortcomings of traditional pipeline laying methods in sporadic concrete construction, which involve determining the route of individual components on a temporary basis, lacking overall analysis of pipe segment reuse, and easily leading to repeated disassembly and assembly of pipe segments, thus affecting the efficiency of equipment coordination. It provides an intelligent management method for multi-device collaborative operations in sporadic concrete construction. Figure 1 This is a flowchart of an embodiment of the present invention, including the following steps: S1, dividing the pumping pipeline in the construction area into a main section, a branch section and an end section.
[0022] The pumping pipeline is not a single, continuous pipeline that runs directly from the pumping device to the component. Instead, it is composed of multiple pipe sections connected by branch nodes. To facilitate the identification of the reuse relationships between pipe sections of each component, the pumping pipeline needs to be divided into sections first.
[0023] In this embodiment of the invention, the pipe segment division is carried out as follows: the pipe segment division is based on the physical layout of the pumping pipeline in the construction area, including the overall direction of the pumping pipeline, the bifurcation position and the connection relationship, as well as the position of the pumping device and the reserved opening position of each component to be poured in the construction area.
[0024] The intersection of the pipe branches that lead to different components to be poured is defined as the branch node.
[0025] The pipe sections between the starting point of the pumping device and the first branch node, as well as the sections between adjacent branch nodes without branch nodes, are classified as main sections because they are common transport sections and do not change with the switching of individual components.
[0026] Pipe sections that branch off from a branch node, do not connect to the next branch node, but lead to the component to be poured and do not directly connect to the reserved opening are classified as branch sections because they undertake the function of transporting from the common section to the specific component.
[0027] The pipe section that is directly connected to the reserved opening of the component to be poured is divided into the terminal section because it is disassembled and reconnected as the component is replaced.
[0028] Based on the above division, each pipeline segment has clearly defined start and end points and functional attributes.
[0029] S2. Based on the layout of the pumping pipeline, determine the pipe segment that each component to be poured passes through from the starting point of the pumping device to its reserved port, forming a pipe segment set.
[0030] After the pipe segments are divided, the delivery path of each component to be poured can be tracked in the whole, the pipe segments it passes through can be determined, and a pipe segment set can be formed.
[0031] In this embodiment of the invention, the pipe segment assembly is formed according to the following process: See [link / document / contact information] Figure 2 As shown, in the pumping pipeline layout, for each component to be poured, start from the starting point of the pumping device and trace along the main section to the branch node. Select the branch section according to the direction of the reserved opening of the component to be poured, and then trace along the branch section to the end section until the reserved opening of the component to be poured is reached.
[0032] All pipe sections that each component to be poured passes through are classified and recorded as main sections, branch sections, and terminal sections, forming a set of pipe sections for the component to be poured.
[0033] The above-mentioned pipe segment set is used for subsequent comparison of the pipe segment usage relationships between various components to identify shared segments and independent segments.
[0034] S3. Compare the pipe segment sets of each component. Pipe segments used by two or more components are marked as shared segments, and pipe segments used by only a single component are marked as independent segments.
[0035] Since the components are constructed sequentially rather than simultaneously, and the transport paths of different components from the pumping device to the reserved port may partially overlap, the pipe section traversed by one component may be reused in the construction of subsequent components. By comparing the sets of pipe sections of each component to be poured, it is possible to determine which components use each pipe section, thereby identifying shared sections and independent sections.
[0036] In this embodiment of the invention, shared segments and independent segments are determined as follows: the intersection of the pipe segment sets of any two components to be poured is calculated, and if the intersection contains the same pipe segment, then the pipe segment is used by both components to be poured.
[0037] If a pipe segment is used by two or more components to be poured, it is marked as a shared segment, indicating that the pipe segment has a reuse relationship among multiple components and can be retained during subsequent switching to avoid repeated disassembly and assembly.
[0038] If a pipe section is used by only one component to be poured, it is marked as an independent section, indicating that the pipe section serves only a single component and can be removed or recycled after the component is poured.
[0039] In the example applied to the above operation, there are five components to be poured in the construction area: structural column A, structural column B, inverted curb C, structural column D, and ring beam E. The pouring sequence is set as structural column A → structural column B → inverted curb C → structural column D → ring beam E.
[0040] In the pumping pipeline layout, the starting point of the pumping device is P. The pipeline is divided into main sections M1 and M2, branch sections F1, F2, F3, F4, F5, and F6, and terminal sections E1, E2, E3, E4, and E5.
[0041] The main section M1 extends from the starting point P of the pumping device to the branch node N1; branch section F2 branches off from branch node N1 to structural column A, and branch section F1 branches off to branch node N2; the main section M2 extends from branch node N1 to branch node N3; branch section F5 branches off from branch node N3 to the reverse wall C, and branch section F6 branches off to structural column D; branch section F3 branches off from branch node N2 to structural column B, and branch section F4 branches off to ring beam E; the end section E1 connects to the reserved opening of structural column A, the end section E2 connects to the reserved opening of structural column B, the end section E3 connects to the reserved opening of reverse wall C, the end section E4 connects to the reserved opening of structural column D, and the end section E5 connects to the reserved opening of ring beam E.
[0042] Based on the above pipe segment division, the pipe segment sets for each component to be poured are determined as shown in Table 1 below.
[0043] Table 1. Classification of Pipe Segment Attributes for Components to be Cast
[0044]
[0045] Therefore, we can conclude that:
[0046] The main segment M1 is shared by five components and is marked as a shared segment.
[0047] Main section M2 is shared by the reverse wall C and structural column D, and is marked as a shared section;
[0048] Branch segment F1 is shared by structural column B and ring beam E, and is marked as a shared segment;
[0049] Branch segments F2, F3, F4, F5, F6 and terminal segments E1 to E5 each serve only one component and are marked as independent segments.
[0050] S4. Make a preliminary decision by determining the number of intervals for the shared section according to the pouring sequence. If the number of intervals for the shared section is not zero according to the preliminary decision, make a further decision by combining the pipe segment identification of the shared section and the number of branch nodes from the shared section to the corresponding end segments of each component it serves, so as to determine whether the shared section should be laid in the laying stage, and then lay the pipeline according to the results of the preliminary decision and the further decision.
[0051] Since concrete needs to be transported to the reserved openings of each component through pumping pipelines, the pipelines must be laid before pouring to form a transport path from the starting point of the pumping device to the reserved opening of the component to be poured. However, the components are scattered and the pipeline branches leading to the reserved openings of different components are different. The traditional operation is that the on-site personnel determine the pipeline route according to the location of each individual component and lay it. After each component is poured, the corresponding pipe section is removed, which results in some reusable pipe sections being repeatedly disassembled and reassembled, causing an increase in the amount of disassembly and reassembly work, damage to the joints, and poor construction continuity.
[0052] To address the aforementioned issues, this invention takes a holistic approach, considering the components to be poured in the construction area, and plans shared sections uniformly during the pipeline laying phase to avoid repeated disassembly and reassembly later. However, if all sections are laid during the laying phase, some sections may remain idle for extended periods, occupying work space. Therefore, it is necessary to determine whether to lay shared sections during the laying phase based on the intervals between them in the pouring sequence and their section identification, thus achieving overall planning for pumping pipeline laying.
[0053] See Figure 3 As shown, the following detailed description is provided in conjunction with a specific embodiment, which includes the following steps: Step 1: Arrange the components to be poured in the same shared section in sequence according to the pouring order, and determine the currently used component and the next component to be used in the shared section.
[0054] Step 2: Determine the number of components to be poured between the currently used component and the next component to be used as the interval number of the shared section. This number reflects how many components must be between the current and next components before the shared section can be used again.
[0055] Step 3: Make a preliminary decision using the number of intervals in a shared segment: When the number of intervals in a shared segment is zero, it means that the shared segment will be reused immediately after the current component is poured. It is determined that the shared segment is laid during the laying stage to ensure that it does not need to be reconnected when subsequent components are poured.
[0056] When the number of intervals in a shared section is not zero, it means that the shared section needs to be used again after a certain number of components are installed. If it is directly determined that it was installed during the laying stage, it may lead to the shared section being idle for a long time and occupying working space. Therefore, it is necessary to further judge based on the pipe segment identification of the shared section.
[0057] Step 4: Obtain the pipe segment identifier of the shared segment: a) If the pipe segment identifier is a main segment, it means that the shared segment is a public transmission segment. Even if the number of intervals is not zero and it will not be used immediately, the shared segment is determined to be laid during the laying stage because the cost of reconnecting to the main segment is high.
[0058] b) If the pipe segment is identified as a branch segment, it means that the shared segment undertakes the function of transporting from the common segment to the specific component. It can be laid during the laying stage or not laid temporarily.
[0059] Considering that even though they are both branch sections, their different locations within the pipeline can affect the laying decisions.
[0060] Specifically, the end section is located on the outermost side of the pipeline, directly connected to the reserved opening of the component and disconnected when the component is replaced. The closer the branch section is to the end section, the fewer interfaces are required for reconnection, making reconnection more convenient; the farther away from the end section, the more interfaces are required for reconnection, making reconnection less convenient.
[0061] In addition, if a shared branch segment serves multiple components, and it is easy to access each of the end segments it serves, it can be deployed later when needed; if the access convenience to each end segment is uneven, it indicates that there are end segments with inconvenient access, and these should be deployed first during the deployment phase.
[0062] Based on the above considerations, for shared segments identified as branch segments, the first step is to obtain each component to be poured served by the shared segment and then determine the corresponding end segment for each component to be poured.
[0063] Starting from the shared segment with a non-zero interval, trace along the pipeline towards the end segments of each component to be poured that it serves, and obtain the number of branch nodes from the shared segment to each end segment. The number of branch nodes represents the number of branch nodes traversed along the route from the shared segment to the corresponding end segment, excluding the branch nodes at the starting point of the shared segment and the connection point between the end segment and the reserved port. The larger the number of branch nodes, the more nodes the shared segment needs to pass through to reach the end segment, which means that the farther away from the end segment, the more interfaces need to be passed during temporary access, and the higher the access cost.
[0064] Extract the maximum and minimum values from the number of branch nodes from the shared segment to each end segment, and calculate the difference between the maximum and minimum values. This difference reflects the balance of access convenience when the shared segment serves each component. The larger the difference, the greater the difference in access level between the shared segment and different end segments, that is, the more unbalanced the access convenience, and the existence of end segments with high access costs.
[0065] At this point, the difference and the maximum number of branch nodes are used together as the basis for judging the access cost: the difference is used to judge whether the access convenience between each end segment is balanced, and the maximum value is used to judge whether the number of interfaces from the shared segment to the most unfavorable end segment is too large.
[0066] When the difference is greater than the allowable threshold or the maximum number of branch nodes is greater than the preset number of nodes, it indicates that there are many interfaces or uneven access between the shared segment and the end segments it serves, which poses a risk of high access cost. It is determined that the shared segment is deployed during the deployment phase. Conversely, it indicates that there are few interfaces between the shared segment and the end segments it serves, and the distribution is even. Temporary access is more convenient when needed in the future. It is determined that the shared segment is not deployed during the deployment phase.
[0067] Since the number of branch nodes actually reflects the number of levels from the branch segment to the end segment, the allowable threshold is actually the allowable level difference, and the preset number of nodes is actually used to limit the maximum allowable access level from the shared segment to the end segment.
[0068] As a preferred option, the allowable threshold can be set to 2, which is suitable for scenarios in routine sporadic concrete construction where the pumping pipeline has no more than 5 levels from the main section to the terminal section. When the difference in the number of branch nodes from the branch section to each terminal section exceeds 2, it indicates that at least one terminal section needs to pass through more than 2 more branch nodes than other terminal sections, and the difference in access convenience is significant. Therefore, 2 is taken as the allowable threshold. For construction scenarios with more complex pipeline levels, the allowable threshold can be appropriately increased.
[0069] As another preferred option, the preset number of nodes can be obtained by acquiring the maximum number of levels in the pumping pipeline from the main section to the end section. The maximum number of levels is the total number of branch nodes along the route from the starting point of the pumping device to the reserved opening of the farthest component to be poured. Half of the maximum number of levels is taken as the preset number of nodes. This setting is because if the number of branch nodes from a certain shared section to the end section exceeds half of the maximum number of levels in the entire pipeline system, it means that the number of interfaces that need to be passed through when connecting has exceeded half of the farthest connection level in the pipeline system. The connection cost is relatively high, and it should be laid first during the laying stage.
[0070] It should be noted that since the end section is directly connected to the reserved opening of the component and is disassembled when the component is replaced, it needs to be disassembled after the pouring is completed. Therefore, when obtaining the pipe segment identification of the shared section, the end section was not included as a shared section in the decision.
[0071] Furthermore, in this embodiment of the invention, after the decision is made, the pipeline section is laid according to the decision result.
[0072] Specifically, the first component to be poured is determined according to the pouring sequence. This component is the next component to be poured, so it needs to be laid from the starting point of the pumping device along the main section, branch section and end section to its reserved opening to ensure that its conveying path is complete.
[0073] The shared section, determined to be laid during the laying phase, is then laid, and a pressure-preserving setting is maintained after laying. This pressure-preserving setting refers to filling the pipeline with compressed air or water, or other pressurized media, after the shared section is laid, and maintaining a pre-set pressure of 0.2-0.5 MPa to ensure the shared section is always ready for operation, avoiding the need for reconnection during subsequent use.
[0074] Continuing with the example in S3, the pouring sequence is: structural column A → structural column B → retaining wall C → structural column D → ring beam E. The shared sections are main section M1, main section M2, and branch section F1.
[0075] For M1: The current component used is structural column A, the next component used is structural column B, the interval is 0, the pipe segment is identified as the main section, and it is determined that it is being laid during the laying stage.
[0076] For M2: The current component used is the inverted curb C, the next component used is the structural column D, the interval number is 0, the pipe segment is identified as the main section, and it is determined that it is being laid during the laying stage.
[0077] For F1: The components used are structural column B and ring beam E, arranged in the pouring sequence. Structural column B is the 2nd pour, and ring beam E is the 5th pour. They are separated by a retaining wall C and structural column D, a total of 2 components. Therefore, the interval number for F1 is 2. The pipe segment of F1 is identified as a branch segment. The end segments corresponding to the components served by F1 are E2 and E5. Tracing from F1 towards E2, passing through branch node N2, the number of branch nodes is 1; tracing towards E5, passing through branch node N2, the number of branch nodes is 1. The difference between the maximum and minimum values is 0, which is not greater than the set threshold of 2; the maximum number of branch nodes is 1, which is not greater than the preset number of nodes of 1. Therefore, based on the shared segment decision, F1 is not to be laid during the laying phase.
[0078] After the decision is made, the first component to be poured is structural column A. It is laid from the starting point P of the pumping device along the main section M1 to the branch node N1, and then along the branch section F2 to the end section E1, reaching the reserved opening of structural column A. M1 and M2, which are determined to be laid in the laying stage, are laid and pressure is maintained in advance.
[0079] S5. After the laying is completed, the transport device is connected to the inlet of the pumping device, and the pumping device opens the pipe section through which the component to be poured passes in the pouring sequence to pump.
[0080] Following the aforementioned decision-making and construction, the pumping pipeline has formed a transport path from the starting point of the pumping device to the reserved opening of the component to be poured, thus meeting the conditions for carrying out pumping pouring.
[0081] See Figure 4 As shown, in this embodiment of the invention, the specific operation of pumping and pouring by connecting multiple devices is as follows: After the pipeline section is laid, the transport device receives the concrete from the mixing device. The mixing device is used to store and mix the concrete to prevent the concrete from settling and segregating during storage. After the transport device receives the concrete, the mixing components in the hopper continue to run during the transport process to prevent the concrete from solidifying.
[0082] After the transport device arrives at the pumping device, it connects its outlet with the pumping inlet, allowing concrete to enter the pumping device from the transport device.
[0083] The pumping device opens the main section, branch section and end section through which the current component passes, so that the pipeline section from the starting point of the pumping device to the reserved port of the current component is connected, forming a complete transportation path.
[0084] The pumping device is first tested at a low speed. Specifically, the pumping device is started at a low speed, and the transport device supplies material to the pumping inlet with a small discharge baffle opening. During the test pump, the pumping pressure changes and the discharge situation at the end section are observed. If the pumping pressure is stable, concrete flows continuously from the end section, and there is no leakage at any branch nodes and joints, the pipeline is confirmed to be unobstructed and the joints are sealed. If the pumping pressure rises abnormally, there is no discharge at the end section, or leakage occurs at the joints, the pump is stopped for inspection and troubleshooting. After the problem is resolved, the pumping is tested again. After confirming that everything is normal, the pumping speed is gradually increased to the normal pumping state. The transport device adjusts the discharge rate according to the pumping suction rhythm to continuously transport the concrete to the reserved opening of the current component.
[0085] S6. Conduct vibration and finishing monitoring at the end of the current component pouring. After entering the finishing stage, close the end section of the current component, remove the independent section, and, in conjunction with the initial setting time of the concrete, perform pressure pre-setting or removal and flushing of the shared section used by the current component. Connect to the unlaid pipe section of the next component to complete the local adjustment of the pipeline, and coordinate with the transportation, vibration, reserved port components and pumping devices to enter the preparation state for the next component operation.
[0086] When the current component is nearing completion of its pouring, it is crucial to promptly identify the finishing touches to facilitate rapid pipe section switching and preparation for the next component. If the finishing touches are identified too late, hasty pipe section adjustments and equipment preparation can easily lead to pumping interruptions and equipment waiting times. Conversely, if the identification is too early, it may affect the normal pouring of the current component. Therefore, this invention performs vibration finishing monitoring at the end of the current component's pouring process.
[0087] In this embodiment of the invention, the vibration finishing monitoring process is as follows: during the pouring process of the current component to be poured, the cumulative pumping volume of the pumping device needs to be obtained. The cumulative pumping volume can be obtained from the operating parameters of the pumping device and is used to determine the amount of concrete that has been poured into the current component.
[0088] When the cumulative pumping volume reaches the preset proportion of the total volume of the component to be poured, it indicates that the pouring of the current component is nearing completion and is about to enter the final stage. At this time, the vibration finishing monitoring is triggered. The preset proportion is determined according to the degree to which the pouring of the current component is nearing completion, for example 80%-90%. It is used to start monitoring in advance before the pouring enters the final stage, rather than continuously monitoring from the beginning of the pouring, so as to reduce unnecessary monitoring actions.
[0089] After the concrete is transported through the pipeline to the reserved opening of the component, it enters the formwork. Since the concrete needs to be vibrated and compacted inside the formwork, in order to facilitate the vibrator to work in layers according to the pouring height, the attached vibrator is fixed to the outside of the component formwork and used to vibrate and compact the concrete inside the formwork during the pouring process.
[0090] The template height segment corresponding to the vibrator indicates the height range of the template to which the vibrator is attached. The current vibration layer is obtained based on the template height segment. This layer reflects the height of the concrete currently being vibrated, as well as the number of layers that have been vibrated and the number of layers remaining.
[0091] When the remaining pumping capacity of the pumping device corresponds to the amount of concrete required for the last layer of vibration of the attached vibrating device, and the attached vibrating device completes the vibration of the current layer, it indicates that the concrete pouring capacity of the current component has reached the amount required for the last layer, and the vibration of that layer has been completed. Therefore, it is identified that the current component to be poured has entered the final stage.
[0092] Furthermore, local adjustments to the pipeline can be made during the final stage, specifically following the procedure below: First, close the connection between the end section of the current component to be poured and the branch node, disconnecting the current component from the pipeline system and stopping the supply of materials to the current component.
[0093] Then, the independent sections of the laid pipe that only serve the current component to be poured are dismantled. These independent sections will not be used by subsequent components after the current component is poured. They can be recycled or reused after dismantling.
[0094] Next, considering that there is residual concrete in the shared section of the currently used component in the laid pipe section, if it is left until the next component is used, the concrete may initially set due to the long standing time, leading to pipe blockage.
[0095] Based on the above considerations, the initial setting time of concrete is introduced as a criterion. The initial setting time refers to the time required for concrete to lose its plasticity from the start of mixing with water. Given a fixed concrete mix design, its initial setting time is mainly affected by ambient temperature, exhibiting a regular pattern: the higher the ambient temperature, the faster the cement hydration reaction rate, and the shorter the initial setting time; the lower the ambient temperature, the slower the hydration reaction rate, and the longer the initial setting time. This pattern can be determined experimentally, for example, by using the penetration resistance method to determine the initial setting time of the same type of concrete under different temperature conditions. Therefore, the initial setting time corresponding to the actual construction ambient temperature can be selected based on the concrete mix design and experimental determination.
[0096] Since the shared section serves multiple components in the pouring sequence, the waiting time of the shared section can be estimated based on the number of components between the currently used component and the next used component.
[0097] Specifically, in the construction design, the planned pouring time for each component to be poured can be obtained from the construction schedule. Based on the number of components in the shared section interval, the planned pouring times of these components are added together to estimate the waiting time from the end of the current use of the shared section to the next use. This estimated waiting time reflects the longest time that the residual concrete in the shared section may remain still.
[0098] When the expected waiting time is less than the initial setting time of the concrete, it means that the residual concrete in the shared section will not set before the next component is used, and the shared section should continue to be pre-pressed under pressure.
[0099] When the expected waiting time is greater than or equal to the initial setting time of the concrete, it indicates that the residual concrete in the shared section will initially set and block the pipe before the next component is used. The shared section should be removed and flushed, and then reconnected before the next use.
[0100] It's important to understand that the comparison between the aforementioned waiting time and the initial setting time of concrete is a prediction based on the worst-case scenario. In actual construction, due to factors such as changes in ambient temperature and fluctuations in the actual initial setting time of concrete, the residual concrete may not have set precisely at the initial setting time, but there is still a possibility of pipe blockage due to initial setting. Since the purpose of local adjustments is to plan the dismantling and connection of pipe sections in advance to avoid pipe blockage and pumping interruption caused by the initial setting of concrete, this conservative judgment method is adopted. When the expected waiting time reaches or exceeds the initial setting time, the pipes are dismantled and flushed to ensure unobstructed pipe flow when the next component is poured.
[0101] For shared sections in which the next component to be poured is still needed but the current component has not been used, the pressure-preserving setting should continue.
[0102] Then, the shared section that overlaps with the already laid section in the next set of pipe segments to be poured is identified as the direct connection section. This section can be used without adjustment when the next component is poured.
[0103] Finally, the unlaid pipe sections in the next set of components to be poured are identified as the sections to be connected. The sections to be connected are connected according to the pipe section markings to ensure that the transportation path of the next component from the starting point of the pumping device to its reserved port is complete.
[0104] Because the pipe sections to be laid have been planned as a whole based on the shared section decision during the laying phase, the subsequent pouring and adjustment of components can be carried out only locally, without the need for complete disassembly and reconnection, thus reducing the workload of pipe section disassembly and reconnection and the waiting time for equipment.
[0105] After adjustment, the coordinated transportation, vibration, reserved port components and pumping devices enter the preparation state for the next component operation, so that each device can be put into the construction of the next component after the pipe section is switched.
[0106] The specific operation is as follows: During the local adjustment, the transport device remains connected to the pump inlet, and the mixing components in the hopper continue to run, so that the concrete does not settle and solidify while waiting for the pipe section to be adjusted. After the adjustment is completed, the material can be supplied to the pumping device immediately.
[0107] The attached vibratory device pre-fixes the vibrator of the next component to be poured according to the layer position, so that the vibrator can be started according to the layer position after the next component is poured.
[0108] The pre-installed standard components will pre-install the pre-installed openings of the next component to be poured according to the specifications and confirm their interface with the end section. The specifications refer to the diameter, connection form and compatible component type of the pre-installed opening, which must match the interface of the end section of the next component.
[0109] After local adjustments are completed, the pumping device opens the pipeline section through which the next component to be poured passes, performs a low-speed test pump, and then officially pumps, realizing continuous switching and pumping connection from the current component to the next component.
[0110] The above embodiments can be implemented, in whole or in part, by software, hardware, firmware, or any other combination thereof. When implemented using software, the above embodiments can be implemented, in whole or in part, in the form of a computer program product.
[0111] Those skilled in the art will recognize that the modules and algorithm steps of the various examples described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.
[0112] The above description is merely a specific embodiment of this application, but the scope of protection of this application is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this application should be included within the scope of protection of this application. Therefore, the scope of protection of this application should be determined by the scope of the claims.
[0113] Finally, the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A smart management method for multi-device collaborative operation in sporadic concrete construction, characterized in that, include: The pumping pipeline within the construction area is divided into main sections, branch sections, and terminal sections; Based on the layout of the pumping pipeline, determine the pipe segment that each component to be poured passes through from the starting point of the pumping device to its reserved port, forming a set of pipe segments; By comparing the pipe segment sets of each component, pipe segments used by two or more components are marked as shared segments, and pipe segments used by only a single component are marked as independent segments. The number of intervals for the shared section is determined according to the pouring sequence to make a preliminary decision. If the number of intervals for the shared section is not zero according to the preliminary decision, a further decision is made by combining the pipe segment identification of the shared section and the number of branch nodes from the shared section to the corresponding end segments of each component it serves, so as to determine whether the shared section should be laid in the laying stage. Then, the pipeline is laid according to the results of the preliminary decision and the further decision. After the laying is completed, the transport device is connected to the inlet of the pumping device, and the pumping device opens the pipe section through which the component to be poured passes according to the pouring sequence to pump it. Vibration and finishing monitoring are carried out at the end of the current component pouring. After entering the finishing stage, the end section of the current component is closed, the independent section is removed, and the shared section used by the current component is pressure-pre-set or removed and flushed in combination with the initial setting time of the concrete. Then, the unlaid pipe section of the next component is connected to complete the local adjustment of the pipeline. The transportation, vibration, reserved port components and pumping devices are coordinated to enter the preparation state for the operation of the next component.
2. The intelligent management method for multi-device collaborative operation in sporadic concrete construction as described in claim 1, characterized in that: The division of the pumping pipeline within the construction area into main sections, branch sections, and terminal sections includes the following: In the layout of pumping pipelines, the intersection of pipelines that branch off and lead to different components to be poured is identified as a branch node; The pipe sections between the starting point of the pumping device and the first branch node, as well as the pipe sections between adjacent branch nodes without branch nodes, are designated as the main trunk sections. A pipe segment that branches off from a branch node, does not connect to the next branch node, but leads to the component to be poured and does not directly connect to the reserved opening is classified as a branch segment. The pipe section that is directly connected to the reserved opening of the component to be poured is divided into the terminal section.
3. The intelligent management method for multi-device collaborative operation for sporadic concrete construction as described in claim 1, characterized in that: The assembly of pipe segments is obtained through the following process: In the layout of the pumping pipeline, for each component to be poured, start from the starting point of the pumping device and trace along the main section to the branch node. Select the branch section according to the direction of the reserved opening of the component to be poured, and then trace along the branch section to the end section until the reserved opening of the component to be poured is reached. All pipe segments that each component to be poured passes through are classified and recorded as main sections, branch sections, and terminal sections, forming a set of pipe segments for the component to be poured.
4. The intelligent management method for multi-device collaborative operation in sporadic concrete construction as described in claim 1, characterized in that: The initial decision-making process for determining the number of intervals for shared sections based on the pouring sequence is as follows: Arrange the components to be poured in the same shared section according to the pouring sequence, and determine the currently used components and the next components to be used in the shared section; The number of components to be poured between the currently used component and the next used component is determined as the interval number of the shared section; When the number of intervals for a certain shared segment is zero, the decision is made to lay that shared segment during the laying phase. When the number of intervals in a shared segment is not zero, obtain the segment identifier of that shared segment.
5. The intelligent management method for multi-device collaborative operation in sporadic concrete construction as described in claim 4, characterized in that: The process for determining whether the shared segment is to be laid during the laying phase is as follows: If the pipe segment is identified as a main section, then the shared section is determined to be laid during the laying phase. If the pipe segment is identified as a branch segment, then obtain each component to be poured served by the shared segment, and determine the end segment corresponding to each component to be poured. Starting from the shared segment with a non-zero interval, trace along the pipeline towards the end segments of each component to be poured that it serves, and obtain the number of branch nodes from the shared segment to each end segment; Extract the maximum and minimum values from the number of branch nodes from the shared segment to each terminal segment, and calculate the difference between the maximum and minimum values; When the difference is greater than the allowable threshold or the maximum number of branch nodes is greater than the preset number of nodes, it is determined that the shared segment is being laid during the laying phase; otherwise, it is determined that the shared segment is not being laid during the laying phase.
6. The intelligent management method for multi-device collaborative operation for sporadic concrete construction as described in claim 5, characterized in that: The pipeline laying based on the results of the initial and further decisions includes the following: Determine the first component to be poured according to the pouring sequence, and lay it from the starting point of the pumping device along the main section, branch section and end section to its reserved opening; The shared sections to be laid during the decision-making phase are to be laid, and pressure is to be maintained after laying.
7. The intelligent management method for multi-device collaborative operation for sporadic concrete construction as described in claim 1, characterized in that: The pumping device opens the pipe section through which the component to be poured passes according to the pouring sequence to pump the following: After the pipeline is laid, the transport unit receives the concrete from the mixing unit. After the transport device arrives at the pumping device, its discharge port is connected to the pumping inlet. The pumping device opens the main section, branch section and end section through which the current component passes, so that the pipeline section from the starting point of the pumping device to the reserved opening of the current component to be poured is connected; After the pumping device performs a low-speed test pump, it pumps the current component.
8. The intelligent management method for multi-device collaborative operation in sporadic concrete construction as described in claim 1, characterized in that: The final monitoring of vibration compaction is carried out according to the following procedure: During the current component pouring process, when the cumulative pumping volume of the pumping device reaches the preset proportion of the expected total volume of the current component, the vibration finishing monitoring is triggered. The current vibration layer is obtained based on the template height section corresponding to the vibrator in the attached vibratory device. When the remaining pumping capacity of the pumping device corresponds to the pouring volume required for the last layer of vibration of the attached vibrating device, and the attached vibrating device completes the vibration of the current layer, the current component is identified as entering the final stage.
9. The intelligent management method for multi-device collaborative operation in sporadic concrete construction as described in claim 1, characterized in that: The local adjustment of the pipeline is as follows: Close the connection between the current component's end segment and the branch node; Remove independent sections of the existing pipeline that serve only the current component; For the shared section of the pipeline that has been used by the current component, the initial setting time of the concrete is determined according to the concrete mix ratio and the ambient temperature of the construction environment. The estimated waiting time of the shared section is obtained by adding up the number of components between the current and next used components and the planned pouring time of each component in the construction schedule. When the expected waiting time is less than the initial setting time of the concrete, the shared section should continue to be pre-pressed under pressure. When the expected waiting time is greater than or equal to the initial setting time of the concrete, the shared section should be dismantled and flushed. The shared segment that overlaps with the already laid segment in the next set of pipe segments to be poured is identified as the direct connection segment; The unlaid pipe segments in the next set of pipe segments to be poured are identified as the segments to be connected, and the segments to be connected are connected according to the pipe segment identification.
10. The intelligent management method for multi-device collaborative operation in sporadic concrete construction as described in claim 1, characterized in that: The coordinated transport, vibration, pre-reserved opening assembly, and pumping device shall proceed as follows to enter the preparation state for the next component operation: The transport device remains connected to the pump inlet during partial adjustments; The attached vibratory device pre-fixes the vibrator of the next component to be poured according to the layer position; The pre-installed standard components will pre-install the pre-installed openings of the next component to be poured according to specifications and confirm their interface with the end section. After the pumping device has been partially adjusted, it opens the pipe section through which the next component to be poured will pass, performs a low-speed test pump, and then pumps.