A flexible composite anchoring method and system for the interface area of new and old soil bodies of rammed earth city walls

By using a flexible composite anchoring method, which combines interface interlocking treatment, moisture-regulating grout layer, and composite connection between flexible anchor rods and geogrid, the problems of interface slippage and cracking in the junction area of ​​old and new soil in rammed earth city walls were solved, achieving simultaneous optimization of reinforcement effect and construction control.

CN123133602APending Publication Date: 2026-11-20SHAANXI ACAD OF ARCHITECTONICS +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611278626.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-21
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

During the reinforcement process, the interface slippage, cracking and voiding problems exist in the junction area of ​​the old and new soil of the rammed earth city wall. Existing technologies cannot effectively solve these problems, and rigid reinforcement methods may cause secondary damage to the original wall.

Method used

A flexible composite anchoring method is adopted, which forms an anchoring system that is resistant to shear, tension and coordinated deformation through interface interlocking treatment, moisture-conditioning grout layer, layered lime-soil ramming, and composite connection of flexible anchor rods and geogrid.

Benefits of technology

It significantly reduced the risk of cracking and slippage in the junction area, avoided secondary damage to the original wall, and achieved effective control of construction disturbance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133602A_ABST
    Figure CN123133602A_ABST
Patent Text Reader

Abstract

The application provides a flexible composite anchoring method and system for the joint area of new and old rammed earth walls, which increases the contact area and shear bite cooperation by interface bite groove or roughening treatment, cooperates with interface humidity adjusting coating slurry to form a water content transition layer to avoid dry shrinkage cracks, and combines layered lime-soil ramming to form a layered structure with uniform stress, so that effective shear connection is formed between the new rammed earth body and the original wall body; the flexible anchor rod is used for tie-up, the elastic modulus thereof is in the same order of magnitude as that of the rammed earth material, and in the case of differential deformation, the flexible anchor rod can coordinate the displacement of both sides by bending deformation, avoiding the risk of local crushing and splitting of the rigid anchoring end; the method anchors one end of the flexible anchor rod into the original wall body, overlaps or penetrates the other end with the geogrid, and then covers and tamps the soil, to form a compression composite connection, meanwhile, the bite groove treatment is performed between the layers of lime-soil, and the adjacent construction sections are staggered and overlapped, to ensure the continuity of the anchoring system in the full height range.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of anchor reinforcement technology for rammed earth city wall ruins, specifically to a flexible composite anchoring method and system for the junction area of ​​old and new soil in rammed earth city walls. Background Technology

[0002] Rammed earth city walls were an important component of ancient Chinese city defense systems. Their walls were typically constructed by layering and ramming loess, sand, lime-soil, or a mixture of these materials. Due to the high porosity, low tensile strength, and significant softening upon contact with water, rammed earth city wall ruins are highly susceptible to damage from long-term wind erosion, rain erosion, freeze-thaw cycles, root penetration, and human disturbance. This damage includes wall fragmentation, internal erosion, partial collapse, gullies, and cavities. In emergency reinforcement and site display projects, it is often necessary to construct new lime-soil supports on the inner side of the remaining original wall or in missing sections to provide support, constraint, and structural markers. However, after long-term weathering, the original rammed earth wall exhibits significant differences in strength, density, moisture content, and deformation modulus compared to the newly reinforced earth. The interface between the two becomes the weakest link in the entire reinforcement system.

[0003] Currently, the reinforcement projects for rammed earth city walls and earthen ruins mainly employ three approaches: first, direct bonding and compaction, relying on the friction and adhesion between the old and new interfaces to transfer the load; second, using anchor bolts or concrete components for tying; and third, laying reinforcing materials such as geogrids to improve the integrity of the newly added soil. However, each of these three approaches has its own technical shortcomings.

[0004] In the direct bonding and compaction method, due to the mismatch in deformation modulus between the old and new soils, when interlayer shear stress is generated at the interface due to temperature and humidity changes or load, the displacement on both sides of the interface is not coordinated, and stress concentration and relative slippage tend to form at the junction, which may eventually lead to interface cracking or even delamination.

[0005] When using existing anchor bolts for connection, severe stress concentration occurs near the anchorage end. In addition, the tensile strength of rammed earth is extremely low, making it very easy for local crushing or splitting to occur around the anchorage end, which in turn causes irreversible secondary damage to the original wall.

[0006] While geogrids can improve the tensile strength and integrity of newly compacted soil, their effect is limited to the interior of the new soil. Their reinforcement cannot be transferred across the interface between the old and new soil layers to the original wall. When shear stress occurs at the interface, although the interior of the newly compacted soil remains intact, the interface between the old and new soil layers still slips and cracks due to the lack of binding restraint.

[0007] In recent years, some projects have begun to experiment with combining the above methods. However, these combinations are mostly simple superpositions of various measures, with each reinforcement component working independently. The reinforcement effect of geogrids cannot be effectively transferred to the original rammed earth wall across the interface between the old and new soil; the rigidity of grouting anchors and drilling disturbances still exist. Therefore, even when the above methods are used in combination, the problems of interface slippage, cracking, and voids at the junction of the old and new soil have not been fundamentally solved.

[0008] In view of this, the inventor has designed a flexible composite anchoring method and system for the junction area of ​​old and new soil in rammed earth city walls, which leads to this invention. Summary of the Invention

[0009] To solve the above problems, the technical solution of the present invention is as follows: A flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall includes the following steps: Before construction, a current status survey of the original rammed earth wall was conducted and the surface was cleaned. Based on the degree of damage, the construction area was divided into a slightly weathered area, a moderately damaged area, and a severely unstable area. For the lightly weathered area, an interface interlocking treatment is performed at the junction of the original rammed earth wall and the newly reinforced rammed earth to form an interface interlocking layer; for the moderately damaged area and the severely unstable area, only surface roughening treatment is performed. After the interlocking layer or surface roughening treatment is performed on the wall surface, a moisture conditioning treatment is carried out to make the interface reach a stable state of surface moisture and internal moisture. Then, plain soil slurry or yellow mud slurry is applied to form an interface moisture conditioning slurry layer. Within the design boundary of the newly reinforced soil, layered lime-soil is laid and compacted layer by layer to form a lime-soil rammed layer. Every two steps of the layered lime-soil rammed layer are compacted. A layer of bidirectional geogrid is laid horizontally within the newly reinforced soil. The end of the bidirectional geogrid closest to the original rammed earth wall extends to the interface interlocking layer or the surface of the wall after surface roughening treatment. Flexible anchors are installed between the original rammed earth wall and the newly reinforced rammed earth. One end of the flexible anchor is placed inside the original rammed earth wall, and the other end is placed inside the newly reinforced rammed earth and overlapped or penetrated with the bidirectional geogrid. Then, lime soil is covered and compacted to form a press-fit composite connection between the flexible anchor and the bidirectional geogrid. Repeat the steps of laying and compacting lime-soil, laying bidirectional geogrids, and arranging flexible anchors until the newly compacted soil reaches the design height. Interlocking treatment is applied between each layer of lime-soil, and staggered joints are made between adjacent construction sections.

[0010] Preferably, the anchoring depth of one end of the flexible anchor rod inserted into the original rammed earth wall is controlled to be not less than 1.5m, the horizontal spacing of the flexible anchor rod is controlled to be 0.8-1.2m, and the vertical spacing is controlled to be 0.5-0.8m.

[0011] Preferably, the flexible anchor rod is any one of ash wood, bamboo, or wood.

[0012] Preferably, the flexible anchor bolts are arranged horizontally, obliquely, or in a combination of horizontal and oblique arrangements.

[0013] Preferably, the interlocking depth of the interface interlocking layer is 30-80mm, and the interface interlocking layer is toothed.

[0014] Preferably, the thickness of the single-layer rammed earth layer is controlled to be 180-200mm.

[0015] Preferably, the following steps are also included: Throughout the construction process, monitoring points for settlement, cracks, horizontal displacement, and bulging are set up. If the monitoring finds that the cracks in the original rammed earth wall have expanded or the horizontal displacement exceeds the preset threshold, construction should be suspended and the ramming thickness, ramming energy, anchor spacing, or construction zones should be adjusted. After reinforcement is completed, the newly compacted soil should be kept moist for no less than 7 to 14 days. After curing, check whether cracks, voids or differential settlement appear in the junction area, and carry out local grouting, compaction or sealing treatment according to the check results.

[0016] This invention also provides a flexible composite anchoring system for the junction area of ​​old and new rammed earth walls, including the original rammed earth wall and the newly reinforced rammed earth, and further comprising: An interlocking layer is provided on the inner side or in the missing part of the original rammed earth wall; the interlocking layer is toothed and grooved, and an interlocking moisture-regulating slurry layer is provided on the surface of the interlocking layer. The rammed earth layer is constructed in layers within the newly reinforced soil, with each layer having a thickness of 180–200 mm. A bidirectional geogrid is laid in layers inside the rammed earth layer. A layer of bidirectional geogrid is laid every two layers of rammed earth layer. The end of the bidirectional geogrid closest to the original rammed earth wall extends to the interface interlocking layer. The flexible anchor rod has one end extending into the original rammed earth wall and the other end extending into the newly rammed earth and overlapping or penetrating the bidirectional geogrid. The flexible anchor rod and the bidirectional geogrid are connected by a press-fit composite connection. The horizontal spacing of the flexible anchor rod is 0.8 to 1.2 m, and the vertical spacing is 0.5 to 0.8 m.

[0017] The technical solution provided by this invention has the following beneficial effects: This invention increases the contact area and shear-resistant bonding effect through interface interlocking or roughening treatment, and forms a moisture-content transition layer with interface moisture-regulating slurry to avoid drying shrinkage cracks. Combined with layered lime-soil ramming, a uniformly stressed layered structure is formed, creating an effective shear-resistant connection between the newly rammed soil and the original wall. Flexible anchor rods are used for connection, and their elastic modulus is on the same order of magnitude as the rammed soil material. During differential deformation, they can coordinate the displacement on both sides through their own bending deformation, avoiding the risk of local crushing and splitting at the rigid anchor end. This method forms a press-fit composite connection by anchoring one end of the flexible anchor rod into the original wall and overlapping or penetrating the other end with the geogrid and then covering it with soil and ramming it. This allows the reinforcement effect of the geogrid to be effectively transferred to the original rammed soil wall through the anchor rod across the interface between the old and new layers. At the same time, interlocking treatment is performed between each layer of lime-soil, and adjacent construction sections are staggered to ensure the continuity of the anchoring system throughout the entire height range. Therefore, this method creates a flexible composite anchoring system between the original rammed earth wall and the newly reinforced rammed earth, which integrates shear resistance, tensile strength and coordinated deformation capacity. This significantly reduces the risk of cracking, slippage and voiding in the junction area, while avoiding secondary damage to the cultural relic due to rigid reinforcement, and effectively controlling construction disturbance. Attached Figure Description

[0018] The accompanying drawings, which are provided to further illustrate the invention and constitute a part of this invention, are illustrative embodiments of the invention and their descriptions are used to explain the invention and do not constitute an undue limitation of the invention.

[0019] in: Figure 1 This is a schematic diagram of the flexible composite anchoring method in this invention; Figure 2 This is a schematic diagram of the monitoring feedback location and control in this invention; Figure 3 This is a schematic cross-sectional view of the flexible composite anchoring reinforcement method for the junction area of ​​old and new soil in this invention. Figure 4 This is a schematic diagram of the interface bonding treatment between the original rammed earth wall and the newly reinforced rammed earth in this invention. Figure 5 This is a schematic diagram of the composite connection between geogrid and natural flexible anchor in this invention.

[0020] Label Explanation: In the diagram: 1. Original rammed earth wall; 2. Newly rammed earth; 3. Interface interlocking layer; 4. Lime-soil rammed layer; 5. Two-way geogrid; 6. Natural flexible anchor; 7. Interface moisture-regulating slurry layer; 8. Junction zone; 9. Settlement monitoring point; 10. Crack monitoring point; 11. Horizontal displacement monitoring point; 12. Design cutting line. Detailed Implementation

[0021] To make the technical problems, solutions, and beneficial effects of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the scope of the invention.

[0022] Please see Figures 1-5 This is a flexible composite anchoring method for the junction zone 8 of old and new soil in a rammed earth city wall, which is a preferred embodiment of the present invention, and includes the following steps: Step 1: Current situation survey and zoning determination.

[0023] Before construction, a current status survey was conducted on the original rammed earth wall 1, recording the extent of wall damage, location of collapse surfaces, crack width, gully depth, moisture content, surface weathering thickness, and wall stability. Based on the degree of damage, the construction area was divided into a slightly weathered zone, a moderately damaged zone, and a severely unstable zone, and the boundaries, thickness, height, and anchor bolt arrangement parameters of the newly reinforced rammed earth 2 were determined.

[0024] Step 2: Surface cleaning and low-disturbance shaping.

[0025] Remove loose soil, plant roots, and later-added soil from the surface of the original rammed earth wall 1. For locally unstable soil, manually remove it, avoiding the use of strong vibration machinery to disturb the site. After cleaning, preserve the stable original rammed earth structural surface.

[0026] Step 3: Handling the interlocking joints at the interface.

[0027] An interface interlocking layer 3 is constructed at the junction 8 between the original rammed earth wall 1 and the newly reinforced rammed earth 2. In this scheme, the interface interlocking layer 3 is toothed. For the original wall in the slightly weathered area, the interlocking depth is controlled at 30-80mm. For the wall in the moderately damaged area and the severely unstable area, only surface roughening treatment is performed, without deep chiseling or expanding the damaged area.

[0028] Step 4: Interface conditioning and slurry treatment.

[0029] Before compaction, the interface of the original rammed earth wall 1 is moderately moistened by sprinkling or misting water to achieve a surface-moistened and internally stable state. Then, a thin layer of plain soil slurry or modified yellow mud slurry is applied to form an interface moisture-regulating slurry layer 7, which prevents the moisture in the newly added lime soil from being quickly absorbed by the original wall and reduces the risk of interface shrinkage and cracking. The modified yellow mud slurry is a yellow mud slurry modified by a composite of lime and glutinous rice paste.

[0030] Step 5: Laying and compacting the first layer of lime-soil.

[0031] Within the design boundary, lay the first layer of 3:7 lime-soil or compatible modified lime-soil, with a thickness controlled at 180-200mm. Compact it in layers using manual tamping or small low-vibration tampers. Within 1300-500mm of the original rammed earth wall, use low-energy compaction to avoid impact damage to the original wall. Low-energy compaction involves using a 5-10kg wooden or rubber tamper, with a drop distance of 0.10-0.30m, 3-6 blows per point, and a single blow energy controlled at 5-30J.

[0032] Step 6: Lay bidirectional geogrid 5.

[0033] After every two steps of compaction, a bidirectional geogrid 5 is laid horizontally within the newly compacted soil 2. The end of the geogrid closest to the original rammed earth wall 1 extends to the vicinity of the interface interlocking layer 3, with reserved positions for pressing or through-feeding with the natural flexible anchor rod 6; the end furthest from the original wall extends into the interior of the newly compacted soil 2, forming a reinforced load-bearing layer.

[0034] Step 7: Install natural flexible anchor bolt 6.

[0035] Natural flexible anchors 6 are installed between the original rammed earth wall 1 and the newly reinforced rammed earth 2. The natural flexible anchors 6 are preferably 3-4m long ash wood poles, but bamboo or wooden poles can also be used. One end of the anchor enters the original rammed earth wall 1, with an anchoring depth of not less than 1.5m; the other end extends into the newly reinforced rammed earth 2 and overlaps or penetrates the geogrid layer. The horizontal spacing of the natural flexible anchors 6 is preferably 1m, and the vertical spacing is preferably 0.6m.

[0036] Step 8: Composite connection of anchor bolts and grid.

[0037] The natural flexible anchor 6 is placed between adjacent geogrid layers, or the anchor is passed through the geogrid mesh before being covered and compacted with lime-soil, so that the natural flexible anchor 6, geogrid, and lime-soil compacted layer 4 form a composite load-bearing unit. For areas with large wall height or severe damage, a combination of horizontal and diagonal anchors can be used.

[0038] Step Nine: Layered compaction and staggered joint continuation.

[0039] Repeat the steps of laying and compacting lime-soil, laying geogrid, and installing natural flexible anchors 6 until the newly compacted soil 2 reaches the design height. Interlocking treatment should be applied between each layer of lime-soil, and adjacent construction sections should be staggered to avoid forming continuous vertical construction joints. The initial compaction width of the newly compacted soil 2 should extend beyond the design boundary line; after the overall compaction is completed and stabilized, it should be cut to the design width and slope.

[0040] Step 10: Surface shaping and aging treatment.

[0041] After the newly reinforced earthwork 2 is completed, the exposed surface is manually cut, trimmed, and compacted to ensure that its slope, shape, and color are in harmony with the original rammed earth wall 1. If necessary, a yellow clay slurry similar to the original wall is used for surface sealing and aging treatment.

[0042] Step 11: Construction monitoring and feedback adjustments.

[0043] Throughout the construction process, monitoring points for settlement, cracks, horizontal displacement, and bulging are set up. If monitoring reveals that cracks in the original rammed earth wall 1 have expanded, horizontal displacement exceeds the preset threshold, or local bulging has intensified, construction should be suspended, and the ramming thickness, ramming energy, anchor spacing, or construction zones should be adjusted.

[0044] Step 12: Maintenance and follow-up inspection.

[0045] After reinforcement, the newly compacted soil 2 should be kept moist for no less than 7 to 14 days to avoid exposure to sunlight, rain, and rapid drying and shrinkage. After curing, check the junction area 8 for cracks, voids, or differential settlement, and perform local grouting, compaction, or sealing treatment based on the check results.

[0046] This invention also provides a flexible composite anchoring system for the junction zone 8 of old and new soil in a rammed earth city wall, comprising: Original rammed earth wall 1: refers to the existing rammed earth city wall ruins that need to be protected and supported. Its surface may have weathered layers, cracks, gullies, collapsed surfaces or local loose areas. Newly reinforced earthwork 2: refers to the newly constructed rammed earth wall set inside the original rammed earth wall 1, at the missing part or the support part, used to support the original rammed earth wall 1 and restore or mark the shape of the city wall. Interface interlocking layer 3: It is set on the inner side or missing part of the original rammed earth wall 1, and the interface is treated as a toothed groove to increase the contact area between the new and old soil and the anti-shear interlocking effect. The interface moisture-regulating slurry layer 7 is set on the surface of the interface interlocking layer 3 to form a moisture content transition interface between the interface interlocking layer 3 and the layered lime-soil rammed layer 4, so as to prevent the moisture in the newly added lime-soil from being quickly absorbed by the original rammed earth wall 1. Layered rammed soil layer 4: The newly added rammed soil body 2 is constructed by layering 3:7 lime-soil or improved lime-soil compatible with the original rammed soil material. The thickness of a single layer is preferably 180-200mm, and interlocking treatment is carried out between each layer of lime-soil. Bidirectional geogrid 5: It is laid inside the newly compacted soil 2, with one layer installed every two compaction steps, to enhance the integrity of the newly compacted soil 2 and to form a tie-in reinforcement structure with the natural flexible anchor 6. The end of the bidirectional geogrid 5 near the original rammed earth wall 1 extends to the vicinity of the interface interlocking layer 3. Flexible anchors: These are made of ash wood, bamboo, wood, or other natural materials and are installed between the original rammed earth wall 1 and the newly reinforced rammed earth 2. They are used to connect the geogrid layer, the newly reinforced rammed earth 2, and the original rammed earth wall 1 into a whole. One end extends into the original rammed earth wall 1 with an anchoring depth of not less than 1.5m, and the other end extends into the newly reinforced rammed earth 2 and overlaps or penetrates the bidirectional geogrid 5. The natural flexible anchors 6 and the bidirectional geogrid 5 form a press-fit composite connection under the action of lime-soil compaction. This press-fit composite connection allows the reinforcement effect of the bidirectional geogrid 5 to be transferred across the old and new interfaces to the original rammed earth wall 1. The horizontal spacing of the natural flexible anchors 6 is 1m, and the vertical spacing is 0.6m. Monitoring points: set up near the original rammed earth wall 1, the newly added rammed earth 2 and the junction area 8, to monitor settlement, cracks, horizontal displacement and wall bulging changes.

[0047] To verify the superiority of this solution, experimental verification and performance comparison were conducted: (1) Comparative test of anchor bolt material properties Ash wood, bamboo, wood, and steel reinforcement were selected as anchor bolt samples to test their elastic modulus, ultimate tensile bearing capacity, deformation capacity after peak load, and failure mode. The test results were used to compare the differences in deformation compatibility between natural flexible anchor bolts and steel reinforcement anchor bolts. The test results are shown in Table 1.

[0048] Table 1. Differences in deformation compatibility among different anchor bolts Anchor materials Diameter / mm Elastic modulus / MPa or GPa Ultimate tensile load / kN Post-peak deformation characteristics Destruction Form Ash 35 8.5 GPa 18.6 A relatively long plastic deformation segment remains after the peak value. Bending, fiber tearing or progressive damage bamboo pole 32 11.2 GPa 21.4 It exhibits a certain degree of lingering after reaching its peak. Splitting or progressive destruction wooden pole 35 7.3 GPa 16.8 After the peak, there is a certain degree of buffer deformation. Shearing or bending damage Reinforcing steel 16 200 GPa 36.5 High stiffness, poor deformation compatibility The soil at the anchorage end is crushed, brittlely pulled out, or there is localized stress concentration. The above comparison shows that the stiffness of the natural flexible anchor rod 6 is lower than that of the steel anchor rod. It can produce moderate bending and tensile deformation when the newly compacted soil 2 and the original rammed earth wall 1 undergo slight differential deformation, thereby reducing local stress concentration at the anchoring end. Although the steel anchor rod has higher tensile strength, its deformation modulus differs greatly from that of the rammed earth material. Under pull-out or shearing action, it is more likely to cause the soil near the anchoring end to be crushed, cracked, or brittlely pulled out.

[0049] (2) Pull-out test at different anchoring depths Six natural flexible anchor bolt specimens with anchoring depths of 0.5m, 1.0m, 1.5m, and 2.0m were prepared, and single anchor bolt pull-out tests were conducted. The pull-out load-displacement curves, ultimate pull-out force, and failure modes were recorded. The test results are shown in Table 2.

[0050] Table 2 Pull-out test results for different anchoring depths Anchoring depth / m Ultimate pull-out force / kN Peak displacement / mm Residual bearing capacity after peak value / kN Destruction Form evaluate 0.5 5.8 6.5 1.6 The anchor rod was pulled out as a whole, and the soil around the borehole wall loosened. The anchorage length is too short, resulting in insufficient pull-out bearing capacity. 1 10.9 10.8 4.2 The anchor bolt was partially pulled out, and shear slippage occurred in the soil around the borehole. Increased load-bearing capacity, but limited safety margin. 1.5 16.7 18.6 8.5 Anchor bolts become embedded in the soil through friction, and gradually fail after local bending deformation. It has better load-bearing capacity and deformation compatibility. 2 18.4 21.3 9.1 The anchor bolts exhibited significant bending deformation, and localized soil shear failure occurred. Bearing capacity continues to increase or growth slows, but construction disturbance increases. Based on the pull-out load-displacement curves at different anchoring depths, when the anchoring depth is small, the anchor rod is prone to being pulled out as a whole, and the anchoring end's binding effect on the original rammed earth wall 1 is insufficient. When the anchoring depth increases to about 1.5m, a more stable frictional and embedding effect is formed between the anchor rod and the original rammed earth wall 1, and the pull-out bearing capacity, residual bearing capacity after peak value, and deformation coordination are all significantly improved. Although further increasing the anchoring depth can further improve or maintain the pull-out bearing capacity, it will increase the drilling depth and the disturbance to the cultural relic itself. Therefore, this application preferably sets the anchoring depth of the natural flexible anchor rod 6 into the original rammed earth wall 1 to be not less than 1.5m, and can be adjusted within the range of 1.5 to 2.0m according to the preservation status of the wall.

[0051] (3) Experiment on the effect of different anchor bolt spacing on interface shear resistance and crack control Anchor bolts were installed at horizontal spacings of 0.5m, 0.8m, 1.0m, 1.2m, and 1.5m. The thickness of the rammed soil layer, the spacing of the geogrid, and the anchoring depth were kept consistent. Shear tests and crack development observation tests were conducted at the interface between the old and new soil layers (as shown in Table 3). Tests included peak shear force, interface shear stiffness, initial crack load, maximum crack width, and void area.

[0052] Table 3 Results of Anchor Bolt Arrangement at Different Horizontal Spacings Horizontal spacing / m Peak shear strength at the interface / kN Interface shear stiffness / kN / mm Initial crack load / kN Maximum crack width / mm evaluate 0.5 31.6 4.8 25.4 0.42 The reinforcement effect is good, but the number of anchor bolts is large, and the construction disturbance is significant. 0.8 29.2 4.4 23.7 0.55 The reinforcement effect is good and the disturbance is controllable. 1 27.5 4.1 22.1 0.68 A good balance between shear resistance and minimally disturbed construction. 1.2 24.3 3.5 18.9 0.96 The reinforcement effect is slightly reduced, making it suitable for areas with mild damage. 1.5 18.6 2.6 14.2 1.48 Insufficient anchor bolt restraint reduces crack control capability. Based on the above test results, while a small horizontal spacing of the anchor bolts is beneficial for improving the interfacial shear stiffness and crack control, it also increases the number of holes and construction disturbance. Conversely, a large horizontal spacing makes it difficult for the natural flexible anchor bolts 6 and the geogrid to form a continuous and effective bond, increasing the risk of interfacial cracks and local voids. Therefore, this application preferably sets the horizontal spacing of the natural flexible anchor bolts 6 to 0.8–1.2 m, more preferably 1.0 m; and the vertical spacing to 0.5–0.8 m, more preferably 0.6 m. For severely unstable areas, the horizontal and vertical spacing of the anchor bolts can be appropriately reduced; for mildly weathered areas, the anchor bolt spacing can be appropriately increased to reduce construction disturbance to the original rammed earth wall 1.

[0053] This embodiment focuses on reinforcing a rammed earth wall section with a length of 12m, a remaining height of 5.2m, and a wall thickness of 2.6–3.1m. The original rammed earth wall 1 has continuous damaged concave surfaces on its inner side, with a damaged area length of approximately 10m, a maximum concavity depth of approximately 1.0m, a surface weathering thickness of 30–60mm, and vertical cracks with a width of 0.5–2.0mm distributed throughout. Based on the current situation survey results, the construction area was divided into a lightly weathered area and a moderately damaged area. A new rammed earth support structure with a length of 10m and a height of 4.5m was installed on the inner side of the original wall. The construction surface was divided into 5 construction sections of 2m each along the length of the wall, and the work was carried out in the order of alternating sections, with adjacent sections being subsequently completed.

[0054] Before construction, crack monitoring point 10, horizontal displacement monitoring point 11, and settlement monitoring point 9 were set at the top of the original rammed earth wall 1, the middle of the junction area 8, and the foot of the wall, respectively. Continuous observation was conducted for no less than 2 days to obtain initial values. Temporary wooden supports were used to protect the locally loose but not yet collapsed soil. Then, wooden shovels, brushes, and small hand tools were used to remove loose soil, loose soil, and plant roots. Impact drills, pneumatic picks, or strong vibration machinery were not used.

[0055] For lightly weathered areas, a toothed interface interlocking layer 3 is constructed, with a tooth depth of 50 mm and a single tooth height of 80–120 mm. For moderately damaged areas, only the loose surface layer is removed and artificially roughened, without deep chiseling into the stable undisturbed soil. After the interface is cleaned, water is sprayed 2–3 times using a misting nozzle to condition the interface, with an interval of about 10 minutes between adjacent sprays, until there is no standing water on the interface, it is slightly damp to the touch, and no mud falls off. Then, a 2–3 mm thick layer of plain soil slurry is applied to form a continuous interface conditioning slurry layer 7.

[0056] The newly reinforced rammed earth 2 was prepared using a lime-soil mixture with a volume ratio of 3:7, consisting of sieved undisturbed soil. The moisture content of the lime-soil was controlled within ±2% of the optimum moisture content determined by compaction tests. Each layer of lime-soil was laid loosely to a thickness of 190mm. The area adjacent to the original rammed earth wall, 400mm away, was compacted using an 8kg wooden rammer with a drop distance of 0.20m, four blows per point, and a single blow energy of approximately 15.7J. The blows were performed from the interface outwards. Areas beyond 400mm were compacted in layers using a manual rammer. During compaction, a gap was maintained between the rammer and the original rammed earth wall 1, and direct impact on the site itself was avoided.

[0057] After each two layers of rammed earth are completed, a layer of bidirectional geogrid 5 is laid horizontally. The overlap length between adjacent geogrids is not less than 300mm. One end of the geogrid closest to the original rammed earth wall 1 is laid to the vicinity of the interface interlocking layer 3, and the other end extends into the newly rammed earth 2. After the geogrid is laid, it is flattened and temporarily fixed to prevent curling, folding, or suspension.

[0058] The natural flexible anchor rod 6 uses 3.5m long, 35-50mm diameter white wax rods. Before construction, the rods are checked for straightness and loose surface is removed, and cracked, insect-infested, or obviously bent rods are discarded. Anchor holes with a diameter of 50-60mm and a depth of 1.5m are pre-drilled in the original rammed earth wall 1 using a manual rotary soil drill, with the drilling direction primarily horizontal; at locations with more severe local damage, oblique anchor holes are set at an angle of 10°-20° to the horizontal plane. After the anchor holes are completed, the loose soil inside the holes is removed, and then a thick slurry compatible with the original wall soil is applied. The white wax rod is then slowly screwed into the anchor hole, so that its length into the original rammed earth wall 1 is 1.5m and its length into the newly compacted soil 2 is approximately 2.0m.

[0059] The natural flexible anchor bolts 6 are arranged at a horizontal spacing of 1.0m and a vertical spacing of 0.6m, with adjacent rows of anchor bolts staggered horizontally by 0.5m. One end of the anchor bolt extends into the newly compacted soil 2 through the mesh of the bidirectional geogrid 5, or is placed between two adjacent layers of geogrid. After covering the anchor bolts and geogrid with a layer of lime-soil with a thickness of not less than 50mm, manual compaction is carried out to form a press-fit composite connection between the anchor bolts, geogrid, and lime-soil compaction layer 4.

[0060] After completing the paving, compaction, grid laying, and anchor bolt installation of one construction section, the interval section is constructed. The vertical construction joints between adjacent construction sections are made in a stepped shape, with each level overlapping by no less than 300mm; the construction joints of the upper and lower layers are staggered to avoid forming continuous vertical joints. The above construction process is repeated until the newly compacted soil 2 reaches the design height, and then manual cutting and surface compaction are carried out according to the design cutting line 12.

[0061] During construction, monitoring is conducted twice daily, once before commencement and once after completion. In this embodiment, based on a specific monitoring plan, construction is suspended when the original crack expands by more than 0.2 mm within 24 hours, the horizontal displacement increases by more than 2 mm within 24 hours, or the differential settlement between the old and new soil reaches 3 mm. Upon meeting any of these warning conditions, work on the current construction section is immediately halted, the stability of the original wall is checked, and construction parameters are adjusted by reducing the tamping drop distance, decreasing the number of tamping blows at a single point, shortening the construction section length, or increasing the density of anchor bolts.

[0062] After the newly compacted soil 2 is completed, it is covered with breathable and moisture-retaining material and cured for 14 days. For the first 7 days, misting water is used to keep the surface moist, avoiding direct sunlight and rain. After curing, the joint area 8 is re-inspected for cracks, local voids, and differential settlement. The acceptance criteria for the completion of this construction section are that there are no through cracks at the joint surface, no obvious hollow areas when tapped, and the monitoring data remain stable for 3 consecutive days. This forms a flexible composite anchoring system composed of the original rammed earth wall 1, the interface interlocking layer 3, the interface moisture-regulating slurry layer 7, the natural flexible anchor 6, the bidirectional geogrid 5, and the layered lime-soil rammed layer 4.

[0063] In summary, this invention increases the contact area and shear-resistant bonding effect through interface interlocking or roughening treatment, and forms a moisture-content transition layer with interface moisture-regulating slurry to avoid drying shrinkage cracks. Combined with layered lime-soil ramming to form a uniformly stressed layered structure, an effective shear-resistant connection is formed between the newly rammed soil 2 and the original wall. By using flexible anchor rods for tying, their elastic modulus is on the same order of magnitude as the rammed soil material. Under differential deformation, they can coordinate the displacement on both sides through their own bending deformation, avoiding the risk of local crushing and splitting at the rigid anchor end. This method forms a press-fit composite connection by anchoring one end of the flexible anchor rod into the original wall and overlapping or penetrating the other end with the geogrid and then covering it with soil and ramming it. This allows the reinforcement effect of the geogrid to be effectively transferred to the original rammed soil wall 1 through the anchor rod across the new and old interfaces. At the same time, the interlocking treatment between each layer of lime-soil and the staggered overlap of adjacent construction sections ensure the continuity of the anchoring system throughout the entire height range. Therefore, this method creates a flexible composite anchoring system between the original rammed earth wall 1 and the newly reinforced rammed earth 2, which integrates shear resistance, tensile strength and coordinated deformation capabilities. This significantly reduces the risk of cracking, slippage and voiding in the junction area 8, while avoiding secondary damage to the cultural relic due to rigid reinforcement, and effectively controlling construction disturbance.

[0064] The present invention has been described above by way of example with reference to the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-described manner. Any non-substantial improvements made using the inventive concept and technical solution of the present invention, or the direct application of the inventive concept and technical solution of the present invention to other occasions without modification, are all within the protection scope of the present invention.

Claims

1. A flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall, characterized in that, Includes the following steps: Before construction, a current status survey of the original rammed earth wall was conducted and the surface was cleaned. Based on the degree of damage, the construction area was divided into a slightly weathered area, a moderately damaged area, and a severely unstable area. For the lightly weathered area, an interface interlocking treatment is performed at the junction of the original rammed earth wall and the newly reinforced rammed earth to form an interface interlocking layer; for the moderately damaged area and the severely unstable area, only surface roughening treatment is performed. After the interlocking layer or surface roughening treatment is performed on the wall surface, a moisture conditioning treatment is carried out to make the interface reach a stable state of surface moisture and internal moisture. Then, plain soil slurry or yellow mud slurry is applied to form an interface moisture conditioning slurry layer. Within the design boundary of the newly reinforced soil, layered lime-soil is laid and compacted layer by layer to form a lime-soil rammed layer. Every two steps of the layered lime-soil rammed layer are compacted. A layer of bidirectional geogrid is laid horizontally within the newly reinforced soil. The end of the bidirectional geogrid closest to the original rammed earth wall extends to the interface interlocking layer or the surface of the wall after surface roughening treatment. Flexible anchors are installed between the original rammed earth wall and the newly reinforced rammed earth. One end of the flexible anchor is placed inside the original rammed earth wall, and the other end is placed inside the newly reinforced rammed earth and overlapped or penetrated with the bidirectional geogrid. Then, lime soil is covered and compacted to form a press-fit composite connection between the flexible anchor and the bidirectional geogrid. Repeat the steps of laying and compacting lime-soil, laying bidirectional geogrids, and arranging flexible anchors until the newly compacted soil reaches the design height. Interlocking treatment is applied between each layer of lime-soil, and staggered joints are made between adjacent construction sections.

2. The flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall according to claim 1, characterized in that, The anchoring depth of one end of the flexible anchor rod inserted into the original rammed earth wall is controlled to be no less than 1.5m, the horizontal spacing of the flexible anchor rod is controlled to be 0.8-1.2m, and the vertical spacing is controlled to be 0.5-0.8m.

3. The flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall according to claim 1, characterized in that, The flexible anchor rod can be any one of ash wood, bamboo, or wood.

4. A flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall according to claim 1, characterized in that, The flexible anchor bolts are arranged horizontally, obliquely, or in a combination of both.

5. A flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall according to claim 1, characterized in that, The interlocking depth of the interface interlocking layer is 30-80mm, and the interface interlocking layer is toothed.

6. A flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall according to claim 1, characterized in that, The thickness of a single layer of rammed earth is controlled to be 180-200mm.

7. A flexible composite anchoring method for the junction area of ​​old and new soil in a rammed earth city wall according to claim 1, characterized in that, It also includes the following steps: Throughout the construction process, monitoring points for settlement, cracks, horizontal displacement, and bulging are set up. If the monitoring finds that the cracks in the original rammed earth wall have expanded or the horizontal displacement exceeds the preset threshold, construction should be suspended and the ramming thickness, ramming energy, anchor spacing, or construction zones should be adjusted. After reinforcement is completed, the newly compacted soil should be kept moist for no less than 7 to 14 days. After curing, check whether cracks, voids or differential settlement appear in the junction area, and carry out local grouting, compaction or sealing treatment according to the check results.

8. A flexible composite anchoring system for the junction area of ​​old and new rammed earth city walls, comprising the original rammed earth wall and the newly reinforced rammed earth, characterized in that... Also includes: An interlocking layer is provided on the inner side or in the missing part of the original rammed earth wall; the interlocking layer is toothed and grooved, and an interlocking moisture-regulating slurry layer is provided on the surface of the interlocking layer. The rammed earth layer is constructed in layers within the newly reinforced soil, with each layer having a thickness of 180–200 mm. A bidirectional geogrid is laid in layers inside the rammed earth layer. A layer of bidirectional geogrid is laid every two layers of rammed earth layer. The end of the bidirectional geogrid closest to the original rammed earth wall extends to the interface interlocking layer. The flexible anchor rod has one end extending into the original rammed earth wall and the other end extending into the newly rammed earth and overlapping or penetrating the bidirectional geogrid. The flexible anchor rod and the bidirectional geogrid are connected by a press-fit composite connection. The horizontal spacing of the flexible anchor rod is 0.8 to 1.2 m, and the vertical spacing is 0.5 to 0.8 m.