Steel structure support leveling and jacking device based on hydraulic servo and construction method
By using a hydraulic servo system and a support leveling and jacking device, the problems of support accuracy, unloading controllability, and ease of assembly and disassembly in steel structure construction have been solved. This has enabled efficient and precise support and unloading of steel structure unit assembly, improving construction efficiency and safety.
Patent Information
- Application Number
- CN202611561454.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-10
- Publication Date
- 2026-11-20
AI Technical Summary
Existing temporary support devices for steel structures suffer from problems such as low support accuracy, poor dynamic adaptability, poor unloading controllability, low level of intelligence, and poor ease of assembly and disassembly during construction, making it difficult to meet the construction requirements of modular assembly of steel structures.
The steel structure support, leveling, and jacking device based on hydraulic servo technology is adopted. It includes a servo system, a jacking support system, and a leveling system. Through the cooperation of hydraulic jacks and the servo system, it can achieve precise dynamic support and multi-level synchronous controllable unloading of the steel structure. The support system consists of a concrete base and an upper leveling system, which is suitable for the modular assembly and segmented hoisting construction of steel structures.
It improves the forming accuracy and installation efficiency of steel structure construction, reduces the amount of manual adjustment work, ensures the smoothness and controllability of the unloading process, adapts to various working conditions, and supports rapid disassembly and relocation.
Smart Images

Figure CN123133606A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building construction technology, specifically relating to a steel structure support leveling and jacking device and construction method based on hydraulic servo. Background Technology
[0002] Large-span stadiums and steel-structured corridors are typically characterized by large spans, large component dimensions, and high requirements for overall installation precision. During construction, steel structures are often installed using modular fabrication, segmented hoisting, and on-site assembly. Because the steel structure has not yet formed a complete and stable load-bearing system during the assembly and welding stages, it is difficult for it to bear the self-weight of the components, hoisting loads, and temporary construction loads on its own. Therefore, temporary support devices are usually required to support the steel structure units to be installed, control settlement and deflection during assembly, and ensure the connection accuracy between adjacent steel structure units.
[0003] Existing temporary support devices for steel structures mostly use fixed steel jigs, which have problems such as poor adaptability and safety hazards. Specifically, these problems are as follows: 1) Low support accuracy and poor dynamic adaptability: Traditional support devices are static rigid supports or manually adjustable supports, which cannot provide micro-dynamic compensation based on real-time settlement and docking deviations during unit assembly. This easily leads to uneven stress distribution and localized stress concentration at multiple support points, resulting in misalignment of steel structure splices and excessive deflection, affecting the forming accuracy; 2) Poor unloading controllability: Traditional support devices do not have precise graded unloading functions. On-site construction often uses methods such as one-time unloading, manual cutting of pads, and rough pressure relief, which can easily cause sudden changes in steel structure load and instantaneous collapse. 3) Low level of intelligence: Traditional support devices do not have the function of real-time monitoring and linkage control throughout the process. During the assembly and support stage, the stress and deformation state cannot be accurately controlled. During the unloading stage, it relies on manual experience and manual monitoring data, which has large errors and strong lag, and is very easy to cause local overload and unloading asynchronous problems. 4) Poor disassembly and assembly convenience: Traditional support structures are fixed and specifically adapted to permanent support conditions. It is difficult to quickly disassemble and transport them, and cannot adapt to the construction needs of modular assembly temporary support and immediate disassembly.
[0004] In summary, existing support equipment methods address the core challenges of precise support and smooth unloading during temporary support in steel structure construction. Therefore, there is an urgent need to develop a servo-driven temporary leveling and jacking device that is adaptable to the modular assembly conditions of steel structures, provides precise dynamic support, enables multi-level synchronous and controllable unloading, and facilitates disassembly and transportation. Summary of the Invention
[0005] The purpose of this invention is to overcome the shortcomings of the prior art and to provide a hydraulic servo-based steel structure support leveling and jacking device and construction method.
[0006] The specific technical solution adopted in this invention is as follows:
[0007] In a first aspect, the present invention provides a steel structure support leveling and jacking device based on hydraulic servo, comprising a servo system, and a jacking support system and a leveling system respectively disposed below and above a concrete structure; the jacking support system comprises a concrete base and a plurality of jacking support components disposed between the concrete base and the concrete structure; each jacking support component comprises a first embedded plate, a first sleeve, at least one first support rod, and a first inner nested cylinder end plate arranged coaxially from bottom to top; the bottom of the first embedded plate is pre-embedded on the concrete base, and the bottom end of the first sleeve is fixedly connected to the first embedded plate; a first hydraulic jack is provided inside the first sleeve; the bottom end of the lowest first support rod is inserted into the first sleeve and supported on the top of the first hydraulic jack; the bottom of the first inner nested cylinder end plate is detachably connected to the top end of the highest first support rod, and the top of the first inner nested cylinder end plate abuts against the lower surface of the concrete structure;
[0008] The leveling system includes a support base and several leveling components disposed between the support base and the concrete structure. Each leveling component includes a second embedded plate, a second sleeve, a second support column, and a second inner nested cylinder end plate arranged coaxially from bottom to top. The second embedded plate is pre-embedded in the upper part of the concrete structure. The bottom end of the second sleeve is fixedly connected to the second embedded plate. A second hydraulic jack is provided inside the second sleeve, and the bottom end of the second support column is inserted into the second sleeve and supported on the top of the second hydraulic jack. The second inner nested cylinder end plate is disposed at the top of the second support column and is detachably connected to the support base. An upper support structure for supporting the steel structure to be installed is detachably connected to the support base.
[0009] The servo system is hydraulically connected to each of the first hydraulic jacks and the second hydraulic jacks.
[0010] Preferably, the first sleeve and the second sleeve are respectively provided with pipeline holes for hydraulic lines to pass through; the first hydraulic jack and the second hydraulic jack are both connected to the servo system through hydraulic conduits.
[0011] Preferably, the number of first support columns in each backfill support assembly is selected according to the height between the concrete base and the concrete structure; a first column sleeve is provided between adjacent first support columns and is detachably connected to the first support column through a first connector.
[0012] Furthermore, the first connecting member is a bolt; the first upright sleeve and the first support upright inserted into the first upright sleeve are respectively provided with corresponding connecting holes, and the bolt passes through the corresponding connecting holes.
[0013] Preferably, a sealing plate is provided at the bottom end of the first support column located at the bottom. The sealing plate is fixedly connected to the first support column and abuts against the top of the first hydraulic jack.
[0014] Preferably, the first inner nested tube end plate includes a plug pipe section and an end plate fixedly connected to the top of the plug pipe section; the plug pipe section is inserted into the top of the uppermost first support pole, and the end plate abuts against the lower surface of the concrete structure.
[0015] Preferably, the concrete base is provided with a double-layer bidirectional steel mesh to ensure that the distance between the edge of the concrete base and the outer edge of the first support column is not less than 150mm.
[0016] Preferably, the support base is formed by connecting several I-beams end to end to form a frame structure. The support base has base connection holes corresponding to the end plates of each second inner nested cylinder. The end plates of the second inner nested cylinders are detachably connected to the support base through second connectors that pass through the base connection holes.
[0017] Preferably, the upper support structure is a standard tower crane section or a welded steel structure frame.
[0018] Secondly, the present invention provides a construction method using the steel structure support leveling and jacking device described in the first aspect, as follows:
[0019] S1: Based on the support height and support position at the construction site, process the first embedded plate, the first sleeve, the first support pole, the first inner nested tube end plate, the second embedded plate, the second sleeve, the second support pole, the second inner nested tube end plate, and the support base, and select the length and quantity of the first support pole according to the required jacking height;
[0020] S2: Measure and lay out the lines according to the setting positions of the top support component and the leveling component, pre-embed the first embedded plate in the concrete base, pre-embed the second embedded plate in the concrete structure, and pour concrete after the positioning is completed.
[0021] S3: Place the first hydraulic jack into the first sleeve and connect it to the servo system via hydraulic lines; assemble the first support pole according to the jacking height, and fix adjacent first support poles through the first pole sleeve and the first connector; install the first inner nested tube end plate on the top of the uppermost first support pole, then insert the assembled first support pole into the first sleeve and support it on the first hydraulic jack; control the first hydraulic jack to lift through the servo system, so that the first inner nested tube end plate presses against the lower surface of the concrete structure;
[0022] S4: Place the second hydraulic jack into the second sleeve and connect it to the servo system through the hydraulic pipeline; insert the second support rod into the second sleeve and support it on the second hydraulic jack; install the second inner nested cylinder end plate on the top of the second support rod and connect it to the support base;
[0023] S5: Install the upper support structure onto the support base, adjust each second hydraulic jack through the servo system to make the support base reach the predetermined height and level, and adjust the verticality of the upper support structure and the position of the top support.
[0024] S6: Hoist the steel structure to be installed onto the upper support structure, and position, splice and connect it; during the installation process, adjust the corresponding second hydraulic jack through the servo system according to the support height, docking position and support status of the steel structure to adjust the position of the upper support structure;
[0025] S7: After the steel structure is installed and a stable load-bearing system is formed, maintain the support state of the top support system, and control each second hydraulic jack to fall synchronously in the predetermined order through the servo system; after each unloading is completed and the steel structure deformation is stabilized, the next unloading is carried out until the construction load is transferred from the upper support structure to the steel structure.
[0026] Compared with the prior art, the present invention has the following advantages:
[0027] (1) The steel structure support leveling and jacking device provided by the present invention is suitable for the unit-by-unit, segment-by-segment hoisting and splicing construction of steel structures. It can provide temporary support during the steel structure assembly process and implement graded unloading after the steel structure forms a stable stress system. Each support component adopts a modular and detachable structure, which is convenient for the layout, dismantling and transportation according to the support height and support position on the construction site, and can be reused repeatedly, with good adaptability to working conditions.
[0028] (2) The present invention provides a top support system and a leveling system at the bottom and top of the concrete structure, respectively. The construction load of the steel structure can be transferred to the concrete base in sequence through the upper support structure, support base, leveling components, concrete structure and top support components, which helps to reduce the deformation of the concrete structure under concentrated construction load and improve the overall stability of the temporary support system.
[0029] (3) This invention uses a servo system to control multiple hydraulic jacks, which can adjust each leveling component according to the support height, docking position, and support status during the steel structure assembly process. This adjusts the height and levelness of the support base, improves the problem of uneven force distribution among multiple support positions, and helps reduce steel structure deflection deviation and splicing position deviation, thereby improving the installation and forming accuracy of the steel structure. Compared with the prior art, this invention can reduce the amount of manual repeated adjustments during steel structure assembly, support adjustment, and unloading, simplify the construction operations such as temporary support layout, leveling, unloading, and dismantling, and improve the construction efficiency of steel structures.
[0030] (4) After the steel structure is installed, multiple second hydraulic jacks can be controlled by the servo system to unload synchronously in a predetermined manner, so that the construction load is gradually transferred from the upper support structure to the steel structure. This reduces the problems of sudden changes in structural stress, springback deformation, and node offset that may be caused by one-time unloading, and improves the stability, uniformity and controllability of the unloading process of the temporary support of the steel structure. Attached Figure Description
[0031] Figure 1 This is a schematic diagram of the overall steel structure support leveling and jacking device in this embodiment;
[0032] Figure 2 This is a front view of the steel structure support leveling and jacking device in this embodiment;
[0033] Figure 3 This is a schematic diagram of the overall top support system in this embodiment;
[0034] Figure 4 This is a schematic diagram of the leveling system in this embodiment;
[0035] Reference numerals in the attached drawings: 1. Concrete structure; 2. Backfill support system; 2. Concrete base; 2-1. First embedded plate; 2-2. First sleeve; 2-3. First hydraulic jack; 2-4. First support pole; 2-5. First pole sleeve; 2-6. First connector; 2-7. First inner nested cylinder end plate; 2-8. Leveling system; 3. Second embedded plate; 3-1. Second sleeve; 3-2. Second hydraulic jack; 3-3. Second support pole; 3-4. Second inner nested cylinder end plate; 3-5. Second connector; 3-6. Support base; 3-7. Servo system; 4. Upper support structure; 5. Detailed Implementation
[0036] The present invention will be further described and illustrated below with reference to the accompanying drawings and specific embodiments. The technical features of each embodiment of the present invention can be combined accordingly, provided that there is no mutual conflict.
[0037] like Figure 1 and Figure 2 As shown in the illustration, this embodiment provides a hydraulic servo-based steel structure support leveling and jacking device, comprising a concrete structure 1, a jacking support system 2, a leveling system 3, and a servo system 4. The jacking support system 2 is positioned below the concrete structure 1 to support it from below. The leveling system 3 is positioned above the concrete structure 1 to support and adjust the support height, levelness, and support status of the upper support structure 5. The servo system 4 is connected to the hydraulic jacks in the jacking support system 2 and the leveling system 3 to control the movement of each hydraulic jack.
[0038] like Figure 3 As shown, in this embodiment, the backfill support system includes a concrete base 2-1 and four backfill support components disposed between the concrete base 2-1 and the concrete structure 1. The concrete base 2-1 has a thickness of 200mm and a planar dimension of 2500mm × 2500mm, and its interior is provided with a double-layer bidirectional steel mesh. The steel mesh is formed by binding steel bars with a diameter of 8mm at intervals of 200mm, and the steel bar protective layer thickness is 25mm. The placement of the four backfill support components is determined according to the plane of the concrete base 2-1, and the distance between the edge of the concrete base 2-1 and the outer edge of each backfill support component is not less than 150mm.
[0039] Each top support assembly includes, from bottom to top, a first embedded plate 2-2, a first sleeve 2-3, a first hydraulic jack 2-4, at least one first support column 2-5, and a first inner nested cylinder end plate 2-8, all coaxially arranged. It should be noted that those skilled in the art can select one first support column 2-5 or multiple first support columns 2-5 sequentially spliced vertically, depending on the height between the concrete base 2-1 and the concrete structure 1. Various specifications of first support columns 2-5 with heights of 0.5m, 1m, 1.5m, or 2m can be selected.
[0040] The bottom of the first embedded plate 2-2 is pre-embedded in the concrete base 2-1, with its upper surface exposed. In this embodiment, the first embedded plate 2-2 is a 300mm×300mm steel plate with a thickness of 12mm. Before the concrete base 2-1 is poured, the first embedded plate 2-2 is positioned according to the arrangement of the top support assembly and connected to the steel mesh inside the concrete base 2-1 to reduce the possibility of displacement of the first embedded plate 2-2 during the concrete pouring process.
[0041] The first sleeve 2-3 is vertically mounted on the first embedded plate 2-2, with its bottom end fixedly connected to the first embedded plate 2-2. In this embodiment, the first sleeve 2-3 is formed by bending and welding a 10mm thick steel plate, with an inner diameter of 239mm and a length of 500mm. The bottom end of the first sleeve 2-3 is fully welded to the first embedded plate 2-2 on both sides. A 50mm diameter pipeline hole is provided at the lower part of the first sleeve 2-3 for the hydraulic pipeline connected to the first hydraulic jack 2-4 to pass through. The first hydraulic jack 2-4 is installed inside the first sleeve 2-3. In this embodiment, the first hydraulic jack 2-4 has a rated load capacity of 50t and is connected to the servo system 4 through a hydraulic pipeline.
[0042] In this embodiment, two first support rods 2-5 are provided. The first support rod 2-5 is made of a round steel pipe with an outer diameter of 219mm and a wall thickness of 12mm. The inner diameter of the first sleeve 2-3 is 20mm larger than the outer diameter of the first support rod 2-5, so that the lower end of the first support rod 2-5 can be inserted into the first sleeve 2-3. A 15mm thick sealing plate is welded to the bottom end of the lower first support rod 2-5. This sealing plate abuts against the top of the first hydraulic jack 2-4, so that the lifting force generated by the first hydraulic jack 2-4 can be transmitted to the first support rod 2-5 through the sealing plate.
[0043] A first pole sleeve 2-6 is provided between the lower first support pole 2-5 and the upper first support pole 2-5. The first pole sleeve 2-6 and the first support pole 2-5 into which it is inserted have three corresponding connecting holes, and are fixed by three M14 bolts as first connecting parts 2-7, thereby forming a detachable pole splicing structure.
[0044] In this embodiment, the first inner nested cylinder end plate 2-8 includes a pipe section and an end plate fixedly connected to the top of the pipe section. The pipe section is a steel pipe with an outer diameter of 219mm, a wall thickness of 12mm, and a length of 250mm. The end plate is a steel plate with dimensions of 250mm×250mm and a thickness of 12mm. The pipe section and the end plate are welded and fixed together. The pipe section of the first inner nested cylinder end plate 2-8 is inserted into the top of the first support pole 2-5 above it, and the upper surface of the end plate abuts against the lower surface of the concrete structure 1.
[0045] After installation, the servo system 4 supplies hydraulic medium to each of the first hydraulic jacks 2-4. The first hydraulic jacks 2-4 apply lifting force to the first inner nested cylinder end plate 2-8 through the sealing plate and the first support rod 2-5 in sequence, so that each of the first inner nested cylinder end plates 2-8 presses against the lower surface of the concrete structure 1, thereby transferring the construction load borne by the concrete structure 1 to the concrete base 2-1 through each back-top support component.
[0046] like Figure 4 As shown, in this embodiment, the leveling system 3 includes a support base 3-7 and four leveling components disposed between the support base 3-7 and the concrete structure 1. Each leveling component includes a second embedded plate 3-1, a second sleeve 3-2, a second hydraulic jack 3-3, a second support rod 3-4, and a second inner nested cylinder end plate 3-5, all coaxially arranged from bottom to top.
[0047] The second embedded plate 3-1 is pre-embedded on the concrete structure 1, with its upper surface exposed. In this embodiment, the second embedded plate 3-1 is a steel plate with a size of 300mm×300mm and a thickness of 12mm, and is positioned according to the setting position of each leveling component before the concrete structure 1 is poured.
[0048] The second sleeve 3-2 is vertically mounted on the second embedded plate 3-1, and its bottom end is fixedly connected to the second embedded plate 3-1 by double-sided full welding. The second sleeve 3-2 is formed by bending and welding a 10mm thick steel plate, with an inner diameter of 239mm and a length of 500mm. A pipeline hole is provided at the lower part of the second sleeve 3-2 for hydraulic lines to pass through. The second hydraulic jack 3-3 is installed inside the second sleeve 3-2 and is connected to the servo system 4 through the hydraulic lines passing through the pipeline hole. In this embodiment, the rated load capacity of the second hydraulic jack 3-3 is 50t.
[0049] In this embodiment, the second support rod 3-4 is made of a round steel tube with an outer diameter of 219 mm and a wall thickness of 12 mm. Its lower end is inserted into the second sleeve 3-2 and supported on the top of the second hydraulic jack 3-3. The second sleeve 3-2 has an inner diameter of 239 mm, a wall thickness of 10 mm, and a length of 500 mm. The inner diameter of the second sleeve 3-2 is 20 mm larger than the outer diameter of the second support rod 3-4, allowing the second support rod 3-4 to move axially along the second sleeve 3-2 under the drive of the second hydraulic jack 3-3. At the same time, the second sleeve 3-2 limits and guides the lower part of the second support rod 3-4.
[0050] The second inner nested tube end plate 3-5 is located at the top of the second support column 3-4, and also includes a connector section and an end plate welded to the top of the connector section. The connector section is made of steel pipe with an outer diameter of 219mm, a wall thickness of 12mm, and a length of 250mm. The end plate is made of steel plate with dimensions of 250mm × 250mm and a thickness of 12mm. The connector section is inserted into the top of the second support column 3-4, and the end plate has end plate connection holes for connecting to the support base 3-7.
[0051] The support base 3-7 is constructed from four 2.7m long No. 16 I-beams welded end to end to form a frame structure. Four base connection holes are made on the support base 3-7 at positions corresponding to the four second inner nested cylinder end plates 3-5. The end plates of the second inner nested cylinder end plates 3-5 are attached to the lower surface of the support base 3-7 and are detachably connected to the support base 3-7 via four M18 bolts serving as second connecting parts 3-6. This allows the four leveling components to jointly support the support base 3-7.
[0052] An upper support structure 5 is provided above the support base 3-7. In this embodiment, the upper support structure 5 is a standard tower crane section with a planar dimension of 2500mm × 2500mm, and its bottom is detachably connected to the support base 3-7 by bolts. In other embodiments, the upper support structure 5 can also be a welded steel structure frame, the specific shape and size of which can be set according to the support position of the steel structure to be installed and the construction load.
[0053] After installation, the servo system 4 controls the operation of the four second hydraulic jacks 3-3. The second hydraulic jacks 3-3 apply lifting force to the support base 3-7 through the second support rod 3-4 and the second inner nested cylinder end plate 3-5. By adjusting the lifting amount of each second hydraulic jack 3-3, the overall height and levelness of the support base 3-7 can be adjusted, and the support height and verticality of the upper support structure 5 can be further adjusted.
[0054] This embodiment also provides a construction method using the above-mentioned steel structure support leveling and jacking device, as detailed below:
[0055] Step 1: Component fabrication.
[0056] Based on the support height and support position at the construction site, process the first embedded plate 2-2, the first sleeve 2-3, the first support pole 2-5, the first inner nested tube end plate 2-8, the second embedded plate 3-1, the second sleeve 3-2, the second support pole 3-4, the second inner nested tube end plate 3-5, and the support base 3-7, and select the length and quantity of the first support pole 2-5 according to the required jacking height.
[0057] Step 2: Construction of embedded structures.
[0058] Based on the location of the top support component and the leveling component, the measurement and layout are carried out. The first embedded plate 2-2 is pre-embedded in the concrete base 2-1, and the second embedded plate 3-1 is pre-embedded in the concrete structure 1. After the positioning is completed, the concrete is poured.
[0059] Step 3: Install the top support system.
[0060] The first hydraulic jack 2-4 is inserted into the first sleeve 2-3 and connected to the servo system 4 via hydraulic lines. The first support pole 2-5 is assembled according to the jacking height, with adjacent first support poles 2-5 fixed by the first pole sleeve 2-6 and the first connector 2-7. The first inner nested cylinder end plate 2-8 is installed on the top of the uppermost first support pole 2-5, and then the assembled first support pole 2-5 is inserted into the first sleeve 2-3 and supported on the first hydraulic jack 2-4. The servo system 4 controls the first hydraulic jack 2-4 to lift, causing the first inner nested cylinder end plate 2-8 to press tightly against the lower surface of the concrete structure 1.
[0061] Step 4: Install the leveling system.
[0062] The second hydraulic jack 3-3 is placed inside the second sleeve 3-2 and connected to the servo system 4 via hydraulic lines. The second support rod 3-4 is inserted into the second sleeve 3-2 and supported on the second hydraulic jack 3-3. The second inner nested cylinder end plate 3-5 is installed on the top of the second support rod 3-4 and connected to the support base 3-7 via the second connector 3-6.
[0063] Step 5: Install the upper support structure.
[0064] The upper support structure 5 is installed on the support base 3-7. The second hydraulic jacks 3-3 are adjusted by the servo system 4 to make the support base 3-7 reach the predetermined height and level. The verticality and top support position of the upper support structure 5 are also adjusted.
[0065] Step 6: Steel structure installation.
[0066] The steel structure to be installed is hoisted onto the upper support structure 5, and then positioned, spliced, and connected. During installation, the position of the upper support structure 5 is adjusted by regulating the corresponding second hydraulic jacks 3-3 through the servo system 4, based on the support height, docking position, and support status of the steel structure.
[0067] Step 7: Staged unloading.
[0068] After the steel structure is installed and forms a stable load-bearing system, maintain the support state of the top support system 2, and control each second hydraulic jack 3-3 to fall synchronously in predetermined stages through the servo system 4. After each stage of unloading is completed and the steel structure deformation stabilizes, the next stage of unloading is carried out until the construction load is transferred from the upper support structure 5 to the steel structure. Unloading is carried out in stages according to the internal force of the support, at 10%, 30%, 50%, 75%, and 100% respectively, ensuring synchronous and uniform unloading.
[0069] Step 8: Dismantle the device.
[0070] After unloading is completed, the upper support structure 5, support base 3-7 and leveling components are removed in sequence; then the supporting force of each first hydraulic jack 2-4 is gradually released through the servo system 4, and then the first inner nested cylinder end plate 2-8, the first support pole 2-5, the first hydraulic jack 2-4 and other detachable parts are removed in sequence.
[0071] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the invention. Those skilled in the art can make various changes and modifications without departing from the spirit and scope of the invention. Therefore, all technical solutions obtained through equivalent substitution or transformation fall within the protection scope of the present invention.
Claims
1. A steel structure support leveling and jacking device based on hydraulic servo, characterized in that, The system includes a servo system (4), and a top support system (2) and a leveling system (3) respectively located below and above the concrete structure (1); the top support system includes a concrete base (2-1) and a plurality of top support components located between the concrete base (2-1) and the concrete structure (1); each top support component includes a first embedded plate (2-2), a first sleeve (2-3), at least one first support column (2-5), and a first inner nested cylinder end plate (2-8) arranged coaxially from bottom to top; the bottom of the first embedded plate (2-2) is pre-embedded in the concrete. On the base (2-1), the bottom end of the first sleeve (2-3) is fixedly connected to the first embedded plate (2-2); the first sleeve (2-3) is provided with a first hydraulic jack (2-4); the bottom end of the first support rod (2-5) located at the bottom is inserted into the first sleeve (2-3) and supported on the top of the first hydraulic jack (2-4); the bottom of the first inner nested cylinder end plate (2-8) and the top of the uppermost first support rod (2-5) are detachably connected, and the top of the first inner nested cylinder end plate (2-8) abuts against the lower surface of the concrete structure (1); The leveling system (3) includes a support base (3-7) and several leveling components disposed between the support base (3-7) and the concrete structure (1); each leveling component includes a second embedded plate (3-1), a second sleeve (3-2), a second support pole (3-4), and a second inner nested tube end plate (3-5) arranged coaxially from bottom to top; the second embedded plate (3-1) is pre-embedded in the upper part of the concrete structure (1); the bottom end of the second sleeve (3-2) is connected to the second embedded plate (3-1) The second sleeve (3-2) is fixedly connected to the second hydraulic jack (3-3), and the bottom end of the second support rod (3-4) is inserted into the second sleeve (3-2) and supported on the top of the second hydraulic jack (3-3); the second inner nested cylinder end plate (3-5) is set on the top of the second support rod (3-4) and forms a detachable connection with the support base (3-7); the support base (3-7) is detachably connected to an upper support structure (5) for supporting the steel structure to be installed. The servo system (4) is hydraulically connected to each of the first hydraulic jacks (2-4) and the second hydraulic jacks (3-3).
2. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, The first sleeve (2-3) and the second sleeve (3-2) are respectively provided with pipeline holes for hydraulic lines to pass through; the first hydraulic jack (2-4) and the second hydraulic jack (3-3) are both connected to the servo system (4) through hydraulic lines.
3. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, Based on the height between the concrete base (2-1) and the concrete structure (1), select the number of first support poles (2-5) in each back support assembly; a first pole sleeve (2-6) is provided between adjacent first support poles (2-5), and is detachably connected to the first support pole (2-5) through a first connector (2-7).
4. The hydraulic servo-based steel structure support leveling and jacking device according to claim 3, characterized in that, The first connector (2-7) is a bolt; the first pole sleeve (2-6) and the first support pole (2-5) inserted into the first pole sleeve (2-6) are respectively provided with corresponding connecting holes, and the bolt passes through the corresponding connecting holes.
5. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, The bottom end of the first support pole (2-5) located at the bottom is provided with a sealing plate, which is fixedly connected to the first support pole (2-5) and abuts against the top of the first hydraulic jack (2-4).
6. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, The first inner nested tube end plate (2-8) includes a pipe section and an end plate fixedly connected to the top of the pipe section; the pipe section is inserted into the top of the uppermost first support pole (2-5), and the end plate abuts against the lower surface of the concrete structure (1).
7. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, The concrete base (2-1) is provided with a double-layer bidirectional steel mesh to ensure that the distance between the edge of the concrete base (2-1) and the outer edge of the first support pole (2-5) is not less than 150mm.
8. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, The support base (3-7) is formed by connecting several I-beams end to end to form a frame structure. The support base (3-7) has base connection holes corresponding to each second inner nested cylinder end plate (3-5). The second inner nested cylinder end plate (3-5) is detachably connected to the support base (3-7) through a second connector (3-6) passing through the base connection hole.
9. The hydraulic servo-based steel structure support leveling and jacking device according to claim 1, characterized in that, The upper support structure (5) is a standard tower crane section or a welded steel structure frame.
10. A construction method using the steel structure support leveling and jacking device according to any one of claims 1 to 9, characterized in that, Specifically as follows: S1: Based on the support height and support position at the construction site, process the first embedded plate (2-2), the first sleeve (2-3), the first support pole (2-5), the first inner nested tube end plate (2-8), the second embedded plate (3-1), the second sleeve (3-2), the second support pole (3-4), the second inner nested tube end plate (3-5), and the support base (3-7), and select the length and quantity of the first support pole (2-5) according to the required jacking height; S2: Measure and lay out the lines according to the setting position of the top support component and the leveling component, pre-embed the first pre-embedded plate (2-2) in the concrete base (2-1), pre-embed the second pre-embedded plate (3-1) in the concrete structure (1), and pour concrete after the positioning is completed. S3: Place the first hydraulic jack (2-4) into the first sleeve (2-3) and connect it to the servo system (4) through the hydraulic pipeline; splice the first support pole (2-5) according to the jacking height, and fix the adjacent first support poles (2-5) through the first pole sleeve (2-6) and the first connector (2-7); install the first inner nested tube end plate (2-8) on the top of the uppermost first support pole (2-5), and then insert the assembled first support pole (2-5) into the first sleeve (2-3) and support it on the first hydraulic jack (2-4); control the first hydraulic jack (2-4) to lift through the servo system (4) so that the first inner nested tube end plate (2-8) presses against the lower surface of the concrete structure (1); S4: Place the second hydraulic jack (3-3) into the second sleeve (3-2) and connect it to the servo system (4) through the hydraulic pipeline; insert the second support rod (3-4) into the second sleeve (3-2) and support it on the second hydraulic jack (3-3); install the second inner nested cylinder end plate (3-5) on the top of the second support rod (3-4) and connect it to the support base (3-7); S5: Install the upper support structure (5) on the support base (3-7), adjust each second hydraulic jack (3-3) through the servo system (4) to make the support base (3-7) reach the predetermined height and level, and adjust the verticality and top support position of the upper support structure (5); S6: Hoist the steel structure to be installed onto the upper support structure (5) and position, splice and connect it; During the installation process, adjust the corresponding second hydraulic jack (3-3) through the servo system (4) according to the support height, docking position and support status of the steel structure to adjust the position of the upper support structure (5); S7: After the steel structure is installed and a stable force system is formed, maintain the support state of the top support system (2), and control each second hydraulic jack (3-3) to fall back synchronously according to the predetermined level through the servo system (4); after each level of unloading is completed and the steel structure deformation is stabilized, the next level of unloading is carried out until the construction load is transferred from the upper support structure (5) to the steel structure.