Alternating mining method with cantilever type heading machine with inter-column inner stepped drift

By constructing stepped passages and local expansion spaces within the pillars, efficient and continuous mining of inclined ore bodies by cantilever tunneling machines is achieved, solving the problem of difficulty in ascending slopes for cantilever tunneling machines in gently inclined ore bodies, and improving equipment utilization and ore extraction efficiency.

CN123133799APending Publication Date: 2026-11-20CENT SOUTH UNIV +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611644903.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-23
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Cantilever tunneling machines have difficulty independently completing steep-angle uphill mining in gently inclined to inclined ore bodies. Traditional inclined roadway or segmented roadway layout methods involve large amounts of preparation work, low mining-to-cutting ratio, low equipment utilization, and long relocation paths.

Method used

A stepped passage, including a stepped platform and an inclined section, is constructed within the pillar of the inclined ore body. The mining equipment moves downhill to the target mining layer and adjusts its posture to enter the target mining area by expanding the local space, using gravitational potential energy to simplify transportation.

Benefits of technology

It avoids the problem of insufficient uphill climbing ability of cantilever tunneling machines, shortens the relocation path, improves equipment utilization and the continuity of mining operations, and reduces equipment operating energy consumption and transportation costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123133799A_ABST
    Figure CN123133799A_ABST
Patent Text Reader

Abstract

The application provides an alternating mining method of a boom-type tunneling machine with a stepwise access in a pillar, and belongs to the field of mine exploitation, and comprises the following steps: constructing a stepwise channel in a pillar; the pillar is located between an adjacent one-step stope and a two-step stope, the stepwise channel comprises a step platform and an inclined section connecting the step platform; a mining device moves to a target mining layer corresponding to the step platform in a downhill direction along the stepwise channel; the posture of the mining device is adjusted in a local expanded space at the step platform; the mining device penetrates the pillar to enter a target stope for stoping, and the target stope is the one-step stope or the two-step stope. In the technical scheme of the application, the stepwise channel comprising a step platform and an inclined section is arranged in the pillar between the adjacent one-step stope and the two-step stope, so that the mining device can move to a target mining layer in a downhill direction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of underground mining technology, specifically to an alternating mining method using a cantilever tunneling machine with a stepped approach within columns. Background Technology

[0002] Currently, drill-and-blast mining is still the primary method used in both metallic and non-metallic hard rock mines. Traditional drill-and-blast methods suffer from inherent drawbacks such as poor safety, fragmented and discontinuous operations, high labor intensity, and harsh working environments. Non-explosive mechanical rock breaking mining, which replaces explosive blasting with mechanical cutting, offers advantages such as high safety, minimal damage to the surrounding rock, continuous operation, and ease of automation and intelligentization, making it an important development direction for metallic mining.

[0003] Cantilever roadheaders are one of the key pieces of equipment for non-explosive rock breaking. However, cantilever roadheaders are large in size and heavy in weight, and their walking mechanisms are relatively cumbersome. Their tracked climbing ability is limited, making it difficult to independently complete steep-angle slope mining in gently dipping to inclined ore bodies. Traditional inclined ramp or segmented roadway layouts involve large amounts of preparation work, low mining-to-cut ratios, long auxiliary times, and low efficiency, which restricts the application of cantilever roadheaders in inclined ore bodies.

[0004] In addition, in conventional mining methods, the first and second step mining areas are constructed independently with separate preparation roadways. The connecting roadways between the mining areas need to be frequently topped and bottomed to meet the passage requirements of large equipment. Equipment needs to detour through external ramps when moving from one mining area to another, resulting in long transfer routes and low equipment utilization. Summary of the Invention

[0005] In view of the technical problems existing in the background art, this application provides a cantilever tunneling machine alternating mining method with a stepped approach within the pillar, which realizes the purpose of the mining equipment going downhill into the working face and completing rapid reversal and alternating mining within the pillar.

[0006] To achieve the above objectives, in a first aspect, embodiments of this application provide an alternating mining method using a cantilever tunneling machine with a stepped approach within a pillar, comprising the following steps: constructing a stepped passage within a pillar of an inclined ore body; the pillar is located between adjacent first-stage and second-stage stopes, the stepped passage including a stepped platform and an inclined section connecting the stepped platform; the mining equipment moves downhill along the stepped passage to the stepped platform corresponding to the target mining layer; adjusting the attitude of the mining equipment within a local expansion space at the stepped platform; the mining equipment penetrates the pillar to enter the target stope for mining, the target stope being either the first-stage or the second-stage stope.

[0007] Furthermore, the stepped passage is composed of multiple stepped platforms and inclined sections connecting adjacent stepped platforms alternately; the mining equipment moves downhill along the stepped passage within the pillar to the stepped platform corresponding to the target mining layer, including: the mining equipment moves downhill along the inclined section, passing through the stepped platforms step by step, until it reaches the stepped platform corresponding to the target mining layer.

[0008] Furthermore, the elevation of each stepped platform corresponds one-to-one with the elevation of each mining layer; the slope of the inclined section is not greater than the rated maximum downslope of the mining equipment; and the length of the stepped platform is not less than the body length of the mining equipment.

[0009] Furthermore, the mining equipment penetrates the pillar to enter the target stope for mining, including: the mining equipment penetrates the pillar to enter the first-step stope for mining; after mining is completed, the mining equipment turns in the goaf area and penetrates the pillar to enter the second-step stope for mining.

[0010] Furthermore, the local expansion space is formed by the mining equipment itself or by auxiliary excavation; the mining equipment penetrates the pillar to form an outlet.

[0011] Furthermore, during the mining process at the target mining site, the cut ore is transported out downhill through the ore outlet and the stepped passage.

[0012] Furthermore, after the target stope has been mined and ore has been extracted, a backfilling retaining wall is constructed at the ore outlet, and the target stope is backfilled.

[0013] Furthermore, after the target mining layer is completed, the mining equipment descends along the stepped passage to the lower middle section along the vein, ascends via the external ramp to the upper middle section along the vein, and then re-enters the stepped passage to descend to the stepped platform corresponding to the next mining layer.

[0014] Furthermore, the mining equipment is a cantilever mining equipment; the mining equipment penetrates the pillar to enter the target stope for mining, including: the cantilever mining equipment uses a cutting head to mechanically cut and break the rock of the inclined ore body.

[0015] Furthermore, the inclined ore body is a gently inclined medium-thick ore body; the mining sequence is from bottom to top.

[0016] The beneficial technical effects of this application are as follows: In the technical solution of this application, a stepped passage containing a stepped platform and an inclined section is set inside the pillar between adjacent first-step and second-step mining areas, so that mining equipment can move downhill to the target mining layer. The engineering arrangement of the stepped passage ensures that the mining equipment always enters the working face in downhill conditions, avoiding the bottleneck of insufficient uphill climbing ability of the cantilever tunneling machine and reducing the energy consumption of equipment operation. Meanwhile, by setting up a local expansion space at the stepped platform for mining equipment to turn into the mining area, it is possible to quickly switch between adjacent mining areas, shorten the transfer path, improve equipment utilization and the continuity of mining operations. In addition, ore can be transported out through the ore outlet and stepped passage along the downhill direction, further utilizing gravitational potential energy, which helps to simplify the transportation process and improve ore extraction efficiency.

[0017] The above description is only an overview of the technical solution of this application. In order to better understand the technical means of this application and to implement it in accordance with the contents of the specification, and to make the above and other objects, features and advantages of this application more obvious and understandable, the following are specific embodiments of this application. Attached Figure Description

[0018] To more clearly illustrate the technical solutions of this application, the accompanying drawings used in this application will be briefly described below. Obviously, the drawings described below are merely some embodiments of this application. For those skilled in the art, other drawings can be obtained from these drawings without any creative effort.

[0019] Figure 1 This is a schematic diagram of the plan layout of the mining method according to an embodiment of this application; Figure 2 This is an embodiment of the present application. Figure 1 Schematic diagram of section II-II; Figure 3 This is an embodiment of the present application. Figure 1 Schematic diagram of section III-III; Figure 4 This is a cross-sectional schematic diagram of a mining method according to an embodiment of this application; Figure 5 This is an embodiment of the present application. Figure 4 Schematic diagram of section II-II; Figure 6 This is an embodiment of the present application. Figure 4 Schematic diagram of section III-III; Figure 7 This is a schematic cross-sectional view of the roadway layout and mining structure of the mining method according to an embodiment of this application; Figure 8 This is an embodiment of the present application. Figure 7 Schematic diagram of section II-II; Figure 9 This is an embodiment of the present application. Figure 7 Schematic diagram of section III-III; Figure 10 This is a schematic diagram of the layout of the mine roadway in the mining method according to an embodiment of this application; Figure 11 This is an embodiment of the present application. Figure 10 Schematic diagram of section II-II; Figure 12 This is an embodiment of the present application. Figure 10 Schematic diagram of section III-III; Figure 13 This is a schematic diagram of the main flow of the mining method according to an embodiment of this application; Figure 14 This is a schematic flowchart of sub-step S200 in an embodiment of this application; Figure 15 This is a schematic diagram of the S400 sub-step process in an embodiment of this application.

[0020] Explanation of reference numerals in the attached figures: 1. Pillar; 2. Backfill body; 3. Ore body; 4. Intermediate roadway along the vein; 5. Stepped passage; 6. Backfill retaining wall; 7. Mining equipment; 8. Backfill return air shaft; 9. Local expansion space. Detailed Implementation

[0021] The embodiments of the technical solution of this application will now be described in detail with reference to the accompanying drawings. These embodiments are only used to more clearly illustrate the technical solution of this application and are therefore merely examples, and should not be used to limit the scope of protection of this application.

[0022] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains; the terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the application; the terms “comprising” and “having”, and any variations thereof, in the specification, claims, and foregoing description of the drawings are intended to cover non-exclusive inclusion.

[0023] In the description of the embodiments of this application, technical terms such as "first" and "second" are used only to distinguish different objects and should not be construed as indicating or implying relative importance or implicitly specifying the number, specific order, or primary and secondary relationship of the indicated technical features. In the description of the embodiments of this application, "multiple" means two or more, unless otherwise explicitly defined.

[0024] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a separate or alternative embodiment mutually exclusive with other embodiments. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.

[0025] In the description of the embodiments in this application, the term "and / or" is merely a description of the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can represent: A existing alone, A and B existing simultaneously, and B existing alone. Additionally, the character " / " in this document generally indicates that the preceding and following related objects have an "or" relationship.

[0026] In the description of the embodiments of this application, the term "multiple" refers to two or more (including two), similarly, "multiple sets" refers to two or more (including two sets), and "multiple pieces" refers to two or more (including two pieces).

[0027] In the description of the embodiments of this application, the technical terms "center," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," "counterclockwise," "axial," "radial," and "circumferential" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing the embodiments of this application and simplifying the description, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the embodiments of this application.

[0028] In the description of the embodiments of this application, unless otherwise expressly specified and limited, technical terms such as "installation," "connection," "joining," and "fixing" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. For those skilled in the art, the specific meaning of the above terms in the embodiments of this application can be understood according to the specific circumstances.

[0029] Currently, drill-and-blast mining is still the primary method used in both metallic and non-metallic hard rock mines. Traditional drill-and-blast methods suffer from inherent drawbacks such as poor safety, fragmented and discontinuous operations, high labor intensity, and harsh working environments. Non-explosive mechanical rock breaking mining, which replaces explosive blasting with mechanical cutting, offers advantages such as high safety, minimal damage to the surrounding rock, continuous operation, and ease of automation and intelligentization, making it an important development direction for metallic mining.

[0030] Cantilever roadheaders are one of the key pieces of equipment for non-explosive rock breaking. However, cantilever roadheaders are large in size and heavy in weight, and their walking mechanisms are relatively cumbersome. Their tracked climbing ability is limited, making it difficult to independently complete steep-angle slope mining in gently dipping to inclined ore bodies. Traditional inclined ramp or segmented roadway layouts involve large amounts of preparation work, low mining-to-cut ratios, long auxiliary times, and low efficiency, which restricts the application of cantilever roadheaders in inclined ore bodies.

[0031] In addition, in conventional mining methods, the first and second step mining areas are constructed independently with separate preparation roadways. The connecting roadways between the mining areas need to be frequently topped and bottomed to meet the passage requirements of large equipment. Equipment needs to detour through external ramps when moving from one mining area to another, resulting in long transfer routes and low equipment utilization.

[0032] To solve the above technical problems, such as Figure 13 As shown, this application provides an alternating mining method using a cantilever tunneling machine with a stepped approach within the column. This method achieves efficient and continuous mining in the inclined ore body 3 by optimizing the travel path and working space layout of the mining equipment. The following is a detailed description of this embodiment with reference to the accompanying drawings.

[0033] Step S100: Construct a stepped passage within the pillar of the inclined ore body; the pillar is located between adjacent first-stage and second-stage mining areas, and the stepped passage includes a stepped platform and an inclined section connecting the stepped platform.

[0034] Specifically, inside the pillar 1 between adjacent first-stage and second-stage mining areas, a stepped passage 5 is formed through excavation. The two ends of the stepped passage 5 are connected to the upper and middle sections of the vein roadway 4 and the lower and middle sections of the vein roadway 4, respectively, forming a stepped transportation and communication system that runs through the pillar along the dip of the ore body 3. The stepped passage 5 is not a continuous single inclined road, but is composed of multiple horizontal stepped platforms and inclined sections connecting adjacent platforms. Its construction can be completed by drilling and blasting or mechanical excavation.

[0035] It can be noted that the construction method of the stepped passage 5 is not unique. In one implementation, the cutting head of the mining equipment 7 (such as a cantilever tunneling machine) can be used to cut the stepped platform and inclined section layer by layer from bottom to top along the vein 4 starting from the lower middle section. In another implementation, a rock drilling rig can be used in conjunction with blasting to excavate layer by layer from bottom to top.

[0036] Regardless of the construction technique used, as long as a channel entity consisting of alternating horizontal platforms and inclined sections is ultimately formed within the pillar 1, it falls within the scope of the stepped channel 5 referred to in this application. The bottom-up selection of the construction direction facilitates the use of gravity for slag removal and provides a free surface for upper-level construction. However, this construction sequence does not constitute a limitation on the final structural form of the stepped channel 5.

[0037] For example, the cross-sectional shape of the stepped passage can be rectangular, arched, or other shapes adapted to the stability of the ore and rock. The inclined section can be a straight ramp or a ramp with a curved transition, as long as it satisfies the function of alternating stepped platforms and inclined sections to allow mining equipment 7 to pass down the slope step by step.

[0038] In step S200, the mining equipment moves downhill along the stepped passage inside the pillar to the stepped platform corresponding to the target mining layer.

[0039] Specifically, such as Figure 1 Section II and Figure 13 The main process shown is that during the mining operation, the mining equipment 7 enters the stepped passage 5 completed in step S100 from the upper and middle sections along the vein roadway 4, and moves downhill along the inclined section with the help of gravity.

[0040] It should be noted that although the mining equipment 7 moves downhill, the overall mining sequence is preferably from bottom to top. That is, the mining equipment 7 first moves downhill along the stepped passage 5, passing through the intermediate stepped platforms without stopping, and directly downhill to the stepped platform corresponding to the lowest target mining layer to start work. After the mining of this layer is completed, it then moves uphill layer by layer to the next layer. This ensures that the mining equipment 7 is in a downhill working condition when entering each working layer, thereby avoiding the problem of insufficient uphill climbing ability of large tracked mining equipment and reducing the energy consumption of equipment operation.

[0041] Step S300: Adjust the posture of the mining equipment within the local expansion space at the stepped platform.

[0042] Specifically, such as Figure 2 and Figure 13As shown, a local expansion space 9 is provided at the stepped platform. This space is an additional area formed by expanding outward from the basic dimensions of the stepped platform. It is specifically used to accommodate the mining equipment 7 for turning or attitude correction operations. When the mining equipment 7 descends along the inclined section to reach the stepped platform corresponding to the target mining layer, it enters the local expansion space 9. Since the stepped channel 5 is usually arranged along the strike or dip of the ore body 3, and the mining face is often perpendicular to the channel axis, the mining equipment 7 needs to complete the angle adjustment within the local expansion space 9, such as making a 90° turn so that its cutting head or working end faces the target mining direction. By setting the local expansion space 9 at the stepped platform inside the pillar 1 as a reversing node, the transfer path is shortened, the ineffective transportation time is reduced, thereby improving the continuity of mining operations and equipment utilization.

[0043] In step S400, the mining equipment penetrates the pillars and enters the target stope for mining. The target stope is either a one-step stope or a two-step stope.

[0044] Specifically, after completing its attitude adjustment, the mining equipment 7 starts from the partially expanded space 9 at the stepped platform, directly cutting or breaking through the rock mass on the sidewall of pillar 1 to form a connection and penetrate into the target stope. According to the current mining plan, the target stope can be a one-step stope located on one side of pillar 1 or a two-step stope located on the other side. After entering the target stope, the mining equipment 7 performs full-face or partial-face mining operations along the strike or dip of ore body 3.

[0045] It is understandable that penetration includes both the mining equipment 7 using its own cutting head to directly mechanically break through the rock and penetrate the pillar, and the construction of connecting passages in advance within the pillar or the gradual widening of the opening during the mining process. As long as the function of connecting the stepped passage 5 into the stope is achieved, this method of directly changing direction and penetrating into the stope reduces the amount of work required to arrange separate external roadways for each stope in traditional mining methods, thereby reducing the amount of preparatory work and improving the ore recovery rate.

[0046] Through the coordination of steps S100 to S400 above, this embodiment adopts a downhill entry and pillar-reversing mining mode based on the stepped passage inside the mine pillar.

[0047] On the one hand, by setting up a stepped passage 5 containing a stepped platform and an inclined section within the pillar 1, the mining equipment 7 can always move downhill to each target layer. By using the gravity component to offset part of the walking resistance, the problem of large mining equipment having difficulty moving upward in the inclined ore body 3 can be alleviated. On the other hand, by setting up a local expansion space 9 at the stepped platform, the necessary turning space is provided for the equipment, allowing the mining equipment to make a 90° turn within the pillar and directly enter the mining area for operation, shortening the transfer path. This coordinated design of spatial structure and operation sequence not only reduces equipment energy consumption and maintenance costs, but also provides reliable technical support for the mechanized continuous mining of inclined ore bodies.

[0048] In some embodiments, in the stepped passage 5 constructed in step S100, the elevation of each stepped platform corresponds one-to-one with the elevation of each mining layer; the slope of the inclined section is not greater than the rated maximum downslope of the mining equipment 7; and the length of the stepped platform is not less than the body length of the mining equipment 7.

[0049] The above three conditions improve the safe operation of the stepped passage 5 in different ways. First, the correspondence between the elevation of the stepped platform and the elevation of the mining layer means that each stepped platform is a dedicated working entrance for a specific layer. After the mining equipment 7 reaches the platform, it can directly penetrate the pillar 1 and enter the corresponding layer for mining without having to make additional vertical lifting adjustments at the platform, which simplifies the operation process and reduces auxiliary time. Secondly, limiting the slope of the inclined section to the rated maximum downhill slope range of the mining equipment 7 is a safety constraint based on the dynamic performance of the equipment. This ensures that when the mining equipment 7 descends along the inclined section under its own weight, its braking system can effectively control the vehicle speed, preventing slippage or loss of control accidents caused by excessively steep slopes, thus ensuring the inherent safety of the descent process. Furthermore, the length of the stepped platform is limited to the length of the machine body, which is a geometric guarantee to provide sufficient dwelling space for the mining equipment 7. This ensures that the equipment can be completely parked within the platform range, avoiding the inability of the equipment to stay stably due to limited space. This is conducive to maintaining the continuity and smoothness of the mining operation. The attitude adjustment of the mining equipment 7 (such as 90° turning) is accomplished by the additional turning margin provided by the local expansion space 9 at the stepped platform. By binding the geometric parameters of the channel with the performance parameters of the mining equipment 7, safety accidents caused by excessive slope or insufficient space are reduced, ensuring the safe operation of the mining equipment 7 throughout the channel within the pillar 1.

[0050] like Figure 14 As shown, in some embodiments, in step S200, the stepped passage 5 is alternately composed of multiple stepped platforms and inclined sections connecting adjacent stepped platforms; the mining equipment 7 moves downhill along the stepped passage 5 within the pillar 1 to the stepped platform corresponding to the target mining layer, including: Step S201: The mining equipment 7 moves downhill along the inclined section; Step S202: Pass through the stepped platform step by step; Step S203, until the target mining layer corresponding to the stepped platform is reached.

[0051] Specifically, such as Figure 3 and Figure 4 , Figure 5 , Figure 6 As shown, the stepped passage 5 has a stepped geometric shape in the longitudinal direction, rather than a continuous single ramp. Each stepped platform is a horizontal or near-horizontal stopping surface. Adjacent stepped platforms are connected by an inclined section, forming a passage structure in which stepped platforms and inclined sections alternate sequentially. In the actual descent process, after the mining equipment 7 enters the stepped passage 5 from the upper-middle section along the vein roadway 4, it slides or travels in a controlled manner downhill along the first inclined section. After reaching the first stepped platform, it stops briefly or continuously, and then continues to descend along the next inclined section. This process is repeated step by step through the intermediate stepped platforms, and finally reaches the stepped platform corresponding to the target mining layer of this operation. By alternately setting horizontal platforms and inclined sections in the continuous descent path, a definite horizontal working reference surface can be constructed inside the pillar 1, so that the mining equipment 7 is in a horizontal and stable state when it reaches any target layer. This is beneficial to improving the positioning accuracy of the equipment at the stepped platform and the safety of the turning operation, and avoiding the risk of increased braking burden or center of gravity instability caused by being in an inclined posture for a long time.

[0052] like Figure 15 As shown, in some embodiments, in step S400, the mining equipment 7 penetrates the pillar 1 to enter the target stope for mining, including: Step S401: The mining equipment 7 penetrates the pillar 1 and enters the first-stage stope for mining; the cut ore is transported out through the outlet and the stepped passage 5 downhill. Specifically, combined Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 7 , Figure 8 as well as Figure 9 The mining sequence shown constitutes a complete alternating mining operation cycle.

[0053] First, after the mining equipment 7 completes its posture adjustment in the local expansion space 9 at the stepped platform, it directly cuts and breaks one side wall of the pillar 1 from that position, forming a connection and penetrating into the first-step stope located on one side of the pillar 1, and performs cutting and ore-dropping operations along the strike or dip of the ore body 3.

[0054] Step S402: After the mining is completed, the mining equipment 7 turns around in the goaf area; Specifically, after the current layer mining in the first-step mining area is completed, the mining equipment 7 turns around in the formed goaf area, so that its working end changes from facing the first-step mining area to facing the second-step mining area. Step S403: Penetrate pillar 1 to enter the second-stage stope for mining. The cut ore is transported out through the outlet and the stepped passage 5 downhill. Subsequently, the mining equipment 7 performs another penetration action, penetrating the other side of pillar 1 to enter the second-stage stope for continued mining. Since the goaf provides sufficient turning space, the mining equipment 7 does not need to leave pillar 1 or detour around the external ramp to complete the switching between adjacent stops. This helps to shorten the transfer path, reduce non-productive operating time, improve equipment utilization and the continuity of mining operations.

[0055] In some embodiments, the local expansion space 9 is formed by the mining equipment 7 expanding itself or by auxiliary excavation; the mining equipment 7 penetrates the pillar 1 to form the ore outlet.

[0056] Specifically, the formation method of the local expansion space 9 can be flexibly selected according to the on-site rock and ore conditions. In a preferred embodiment, the cutting head of the mining equipment 7 is used directly to expand and shape the sidewalls of the stepped platform. This method does not require additional drilling rigs or blasting equipment, reduces the amount of auxiliary roadway engineering and lowers the preparation cost, and is particularly suitable for scenarios where the rock and ore hardness is moderate and allows for direct mechanical cutting.

[0057] In another implementation, if the rock hardness is too high or a regular space needs to be formed quickly, assisted blasting or manual excavation can be used to form a local expansion space.

[0058] Regardless of the method used, the shape of the local expansion space 9 is usually designed as rectangular or trumpet-shaped, and its size must meet the spatial envelope requirements for the mining equipment 7 to turn at 90° or other required angles.

[0059] Meanwhile, the opening formed by the mining equipment 7 when penetrating the pillar 1 to enter the mining area not only serves as a gateway for equipment passage but also as an outlet for subsequent ore transportation. The simultaneous completion of channel expansion and outlet construction using the mining equipment 7's own operating capabilities helps simplify construction procedures and shorten the mining preparation cycle.

[0060] Specifically, in the operations of steps S401 and S403, the ore transportation and mining equipment share the same path. The ore cut off by the mining equipment 7 in the target mining area falls vertically and is collected by the supporting shovel and transport equipment to the vicinity of the ore outlet. Then it is loaded by the transportation equipment (such as ore trucks or shovels) and enters the stepped passage 5 through the ore outlet.

[0061] Because the stepped passage 5 slopes downwards or descends in a step-like manner, the transport equipment, under heavy load, mainly travels downhill to the lower-middle section along the vein 4, and then merges into the main mine transport system to be transported to the surface. In actual operation, after the mining equipment 7 enters the mining area, there is sufficient working space inside the mining area, and the transport equipment can simultaneously enter the stepped passage 5 for loading and unloading operations. Mining and transportation can be carried out in parallel, which is conducive to improving the coordination efficiency of mining and ore extraction. By constructing a continuous downhill transport path through the ore outlet and the stepped passage 5, the gravitational potential energy can be fully utilized to assist ore transportation, reduce fuel consumption or power consumption of transport equipment, simplify the underground transportation process, and improve the overall ore extraction efficiency.

[0062] Step S404: After the target stope has been mined and ore has been extracted, a backfilling retaining wall 6 is constructed at the ore outlet and the target stope is backfilled.

[0063] Specifically, after a stope (such as a first-stage stope) completes the mining and ore extraction operations for the current layer, a backfill retaining wall 6 is constructed at the connection between the ore outlet and the stepped passage 5 to seal the stope entrance. Subsequently, backfill slurry (such as tailings slurry or paste) is injected into the stope void through a backfill return air shaft 8 pre-constructed during the pre-mining stage. This backfill return air shaft 8 connects from the top of the stope to the upper-middle section return airway. After the backfill slurry solidifies, it forms a backfill body 2, providing support for the stope roof and sidewalls. During this process, the backfill return air shaft 8 can also serve as a... The return air passage in the mining area improves the ventilation conditions of the working environment. Due to the use of a small-section, high-layer filling method, the impact on ground pressure is small. After the first-step mining area is mined and filled, the second-step mining operation can be carried out directly without waiting for the filling body to reach the preset strength, which is conducive to improving mining efficiency. By constructing the filling retaining wall 6 and filling it in time at the ore outlet, it is conducive to maintaining the stability of the surrounding rock of the mining area and the structural integrity of the pillar 1 and the stepped passage 5, thereby providing safe and reliable working conditions for subsequent layered mining and continuous mining of adjacent mining areas.

[0064] After the target mining layer is completed, the mining equipment 7 descends along the stepped passage 5 to the lower horizontal roadway, ascends via the external ramp to the upper horizontal roadway, and then enters the stepped passage 5 again to descend to the stepped platform corresponding to the next mining layer.

[0065] Specifically, combined Figure 3 Section III-III and Figure 10 , Figure 11 , Figure 12As shown, this step constructs a U-shaped circular transfer path for the mining equipment 7 between multi-layer operations. After the mining equipment 7 completes the backfilling and filling operations of the first and second step mining areas of the current mining layer, it is located at the step platform corresponding to that layer. At this time, the mining equipment 7 does not directly climb up to the next layer in the step-type passage 5 inside the pillar 1, but continues to travel downhill along the step-type passage 5 until it reaches the lower middle section vein roadway 4 (i.e., the lower horizontal roadway). Subsequently, the mining equipment 7 enters the middle section ramp road arranged outside the ore body 3 or outside the vein, climbs uphill along the external ramp road, and returns to the upper middle section vein roadway 4 (i.e., the upper horizontal roadway).

[0066] It should be noted that the slope design of the external ramp is usually relatively gentle, within the rated climbing capacity of the mining equipment 7's own power system. Therefore, the equipment can safely ascend by its own power without the need for additional auxiliary lifting measures such as winch traction. After the mining equipment 7 returns to the upper and middle section along the vein 4, it enters the stepped passage 5 again from the entrance and moves downhill to the stepped platform corresponding to the next target mining layer, ready to start a new round of mining operations.

[0067] In the bottom-up mining sequence adopted in this application, the next mining layer refers to the layer adjacent to the currently completed layer. After completing the current layer's work, the mining equipment 7 returns to the upper-middle section along the vein 4, which is located above all mining layers, via the external ramp. Therefore, when it re-enters the stepped passage 5 from this position, it still moves downhill to the stepped platform corresponding to the adjacent layer above, thus maintaining the consistent working condition of entering the working face downhill. That is to say, after completing the work of the lowest layer, the mining equipment 7 advances upward layer by layer through the aforementioned U-shaped transfer path. Each inter-layer transfer repeats the U-shaped transfer process of descending along the stepped passage 5, moving up via the external ramp, and then descending into the next layer of stepped passage 5. In coordination with this, the ore trucks or loaders responsible for ore transportation, after completing the ore extraction task of this layer, also ascend via the external ramp to the upper-middle section along the vein 4 to wait or resupply, so as to enter the next layer's work together with the mining equipment 7.

[0068] This setup, by constructing a combined transfer path that includes a downhill section of stepped passage 5 and an uphill section of external ramp, ensures that the mining equipment 7 travels downhill every time it enters the working face throughout the entire multi-layer mining cycle. This avoids high-load climbing in the narrow passages inside the pillar 1, thereby reducing non-productive time caused by climbing difficulties or waiting for auxiliary hoisting. At the same time, the gravity assistance during downhill travel also helps to reduce the energy consumption of the equipment.

[0069] In some embodiments, the mining equipment 7 is a cantilever mining equipment; the mining equipment 7 penetrates the pillar 1 to enter the target stope for mining, including: the cantilever mining equipment uses a cutting head to mechanically cut and break the rock of the inclined ore body 3.

[0070] Specifically, such as Figure 2 As shown, the mining equipment 7 is preferably a cantilever tunneling machine, with a rotatable cutting head mounted at the front end of its body. During the mining operation, the cutting head directly acts on the surface of the ore and rock through the mechanical impact force generated by high-speed rotation, and cuts the ore into the ore body 3 in full section or layer by layer. The cutting head usually has the freedom to move up and down and swing left and right, and can flexibly adjust the cutting trajectory according to the shape of the mining area cross section to achieve the layer-by-layer stripping of the rock body in the target area.

[0071] In some embodiments, the inclined ore body 3 is a gently inclined medium-thick ore body 3; the mining sequence is from bottom to top.

[0072] Specifically, this mining method is particularly suitable for geological conditions with gentle dips and moderate thicknesses in ore bodies. In such ore bodies, if conventional upward mining is used, the equipment faces high resistance to climbing and is prone to slippage. This application adopts a bottom-up mining sequence. After the mining equipment 7 enters the stepped passage 5 along the vein roadway 4 from the upper middle section, it moves downhill to each target layer working face, using gravity assistance to avoid the problem of insufficient uphill climbing ability of large tracked mining equipment.

[0073] Therefore, the cantilever tunneling machine can descend the slope through the stepped passage 5 to enter each layer of working face, replacing the traditional drilling and blasting method in gently inclined medium-thick ore bodies where mechanized and efficient mining is originally difficult, which is conducive to improving the degree of mechanization and production efficiency of the mine.

[0074] It should be noted that, in order to ensure the safety and comfort of the working environment, this application is also equipped with a complete ventilation system. Fresh air flows in from the lower middle section along the vein roadway 4 and enters each working face of the mining area through the stepped channel 5. The sludge after cleaning the working face is discharged to the upper middle section return air roadway through the filling return air shaft 8. Local fans can be used to assist ventilation.

[0075] Among them, the filling return air shaft 8 serves as a slurry conveying channel during the filling stage and as a dedicated return air channel for the mining area during the non-filling stage, thus realizing the reuse of engineering facilities, reducing the amount of roadway excavation, and optimizing the ventilation network structure.

[0076] For example, in addition to cantilever tunneling machines, mining equipment 7 can also be continuous coal mining machines, coal planers or other non-explosive mining equipment with mechanical rock breaking capabilities. The typical applicable range for gently inclined medium-thick ore bodies 3 is an ore body 3 dip angle of 5° to 25° and an ore body 3 thickness of 5m to 15m, but this application is not limited to the above numerical range.

[0077] In one specific embodiment, the mining of a gently dipping, medium-thick, hard rock phosphate mine is used as an example for detailed explanation. The ore body 3 has an average dip angle of approximately 15° and an average thickness of approximately 12m. The ore firmness coefficient f = 8~10, classifying it as a moderately stable rock stratum. Considering these geological conditions, the ore body 3 is vertically divided into a first-stage stope and a second-stage stope, with an 8m wide pillar 1 between them. A stepped passage 5 is constructed within the pillar 1, with its inclined section slope controlled within the rated maximum downhill slope range of the mining equipment 7. The mining equipment 7 enters the stepped passage 5 from the upper-middle section along the vein roadway 4, descending to the stepped platform corresponding to the target stratum.

[0078] At this platform, the cutting head expands and brushes to form a funnel-shaped local expansion space 9, providing sufficient 90° turning margin for the machine body. After the turning is completed, the mining equipment 7 penetrates the 8m wide pillar 1 and enters the first-step mining area for mechanical cutting and mining. The cut ore is transported out downhill through the ore outlet along the stepped passage 5.

[0079] After the first-stage stope is completed, the equipment turns within the goaf and penetrates pillar 1 again to enter the second-stage stope. Simultaneously, the 8m wide pillar 1 ensures ground pressure safety during alternating stope mining on both sides while also accommodating the stepped passage 5 and the expansion space, achieving a balance between safety and efficiency. In this specific scenario, non-explosive mechanical mining, compared to traditional drill-and-blast methods, reduces the risk of blasting dust contaminating the phosphate ore quality, while maintaining a stable stope production capacity.

[0080] It should be noted that this application is not limited to the above-described embodiments. The above embodiments are merely examples, and any embodiments with the same structure and effect as the technical concept within the scope of this application are included in the technical scope of this application. Furthermore, various modifications that can be conceived by those skilled in the art to the embodiments, and other ways of constructing by combining some of the constituent elements of the embodiments, without departing from the spirit of this application, are also included in the scope of this application.

Claims

1. A cantilever tunneling machine alternating mining method with a stepped approach within inter-column sections, characterized in that, Includes the following steps: Construct stepped passages within the pillars of the inclined ore body; The pillar is located between adjacent first-stage and second-stage mining areas, and the stepped passage includes a stepped platform and an inclined section connecting the stepped platform. The mining equipment moves downhill along the stepped passage to the stepped platform corresponding to the target mining layer; Adjust the posture of the mining equipment within the local expansion space at the stepped platform; The mining equipment penetrates the pillar and enters the target stope for mining, the target stope being either the first-step stope or the second-step stope.

2. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 1, characterized in that, The stepped passageway is composed of multiple stepped platforms and inclined sections connecting adjacent stepped platforms, alternating between them; The mining equipment moves downhill along the stepped passage within the pillar to the stepped platform corresponding to the target mining layer, including: The mining equipment moves downhill along the inclined section, passing through the stepped platforms one by one, until it reaches the stepped platform corresponding to the target mining layer.

3. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 2, characterized in that, The elevation of each stepped platform corresponds one-to-one with the elevation of each mining layer; The slope of the inclined section shall not exceed the rated maximum downslope slope of the mining equipment; The length of the stepped platform is not less than the body length of the mining equipment.

4. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 1, characterized in that, The mining equipment penetrates the pillar to enter the target stope for mining, including: The mining equipment penetrates the pillar and enters the first-step mining area for extraction. After the mining is completed, the mining equipment turns around in the goaf and penetrates the pillar to enter the second-stage mining area for mining.

5. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 4, characterized in that, The local expansion space is formed by the mining equipment itself or by auxiliary excavation. The mining equipment penetrates the pillar to form an outlet.

6. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 5, characterized in that, During the mining process at the target mining site, the cut ore is transported out downhill through the ore outlet and the stepped passage.

7. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 6, characterized in that, After the target stope has been mined and ore has been extracted, a backfilling retaining wall is constructed at the ore outlet, and the target stope is backfilled.

8. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 1, characterized in that, After the target mining layer is completed, the mining equipment descends along the stepped passage to the lower middle section along the vein, ascends via the external ramp to the upper middle section along the vein, and then re-enters the stepped passage to descend to the stepped platform corresponding to the next mining layer.

9. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 1, characterized in that, The mining equipment is a cantilever mining equipment; The mining equipment penetrates the pillar to enter the target stope for mining, including: The cantilever mining equipment uses a cutting head to mechanically cut and break the rock of the inclined ore body.

10. The alternating mining method of cantilever tunneling machine with stepped approach within inter-column as described in claim 1, characterized in that, The inclined ore body is a gently inclined, medium-thick ore body; The mining sequence is from bottom to top.