Adjustable concrete pipe joint troweling device and troweling method thereof

The adjustable concrete pipe joint sealing device enables rapid positioning, precise alignment, and automatic closing. High-frequency vibration removes air bubbles, solving the problems of time-consuming, labor-intensive, and poor adaptability of traditional devices, thus improving construction efficiency and quality.

CN123134282APending Publication Date: 2026-11-20ANHUI FANHENG CONSTRUCTION ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611319438.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-28
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Traditional concrete pipe joint sealing devices are time-consuming and labor-intensive in the process of handling, alignment and fixing. They cannot effectively remove air bubbles inside the concrete, cannot flexibly adapt to different pipe joints, and the construction quality depends on the operator's experience, which increases construction costs and preparation time.

Method used

An adjustable concrete pipe joint sealing device is adopted, including a frame plate, moving wheels, connecting plate, lifting platform, cylinder and vibration structure, to achieve rapid positioning, precise alignment and automatic closing. High-frequency vibration removes air bubbles, adapts to different pipe joint directions and sizes, and reduces manual labor.

Benefits of technology

It significantly shortens the preparation time for the application of the sealing tape, improves construction efficiency, ensures compactness and strength, reduces labor intensity, adapts to different pipe interface requirements, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123134282A_ABST
    Figure CN123134282A_ABST
Patent Text Reader

Abstract

The application discloses a kind of adjustable concrete pipeline interface smearing device and its smearing method, it is related to pipeline installation field, including frame plate, the lower end four corners of the frame plate are fixedly installed with moving wheel, the rear of the upper end of the frame plate is welded with push-pull rod, the upper end of the frame plate is installed with the connecting disc of all directions rotation, the upper end center of the connecting disc is welded with vertical plate, one side of the vertical plate is welded with two chassis, the upper end of the chassis is fixedly installed with guide rail.The application discloses a kind of adjustable concrete pipeline interface smearing device and its smearing method, realize the quick in position of device, accurate alignment and automatic closing package, high frequency vibration can effectively discharge the air bubble in the interior of concrete, promote aggregate particle to rearrange, tightly packed, make concrete slurry even package aggregate surface, realize the lifting, closing and separation of smearing frame, replace the high-strength physical labor of traditional artificial holding, splicing mould.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of pipeline installation, and in particular to an adjustable concrete pipe joint sealing device and its sealing method. Background Technology

[0002] The concrete pipe joint sealing strip device is a device that connects concrete pipes by pouring concrete to form a ring-shaped sealing strip. It is a key process to ensure the pipe's sealing and structural strength.

[0003] Traditional concrete pipe joint sealing tape devices are time-consuming and labor-intensive to handle, align, and fix the sealing tape. These tedious steps must be repeated after each joint is completed, and the inconvenient assembly and disassembly of the molds severely hinders construction progress. Furthermore, manual filling and compaction of concrete cannot effectively remove air bubbles, leading to uneven aggregate distribution and quality defects such as honeycomb, pitting, and voids in the sealing tape layer, affecting the sealing and durability of the pipe joint. Secondly, the lifting, splicing, and fixing of the sealing tape, as well as the segmented filling of concrete, are all physically demanding tasks, easily causing operator fatigue. Construction quality is also highly dependent on the operator's experience and condition, making standardized operation difficult. Finally, traditional sealing tapes are typically of fixed dimensions, unable to flexibly adapt to pipe joints of different diameters, orientations, and burial depths. When pipe specifications or joint directions change, molds must be replaced or remade, increasing construction costs and preparation time. Summary of the Invention

[0004] The main objective of this invention is to provide an adjustable concrete pipe joint sealing device and sealing method, which can effectively solve the technical problems mentioned in the background art, such as the time-consuming and labor-intensive process of mold handling, alignment and fixing, the inability to effectively remove air bubbles inside the concrete, and the inability to flexibly adapt to different pipes.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows:

[0006] An adjustable concrete pipe joint troweling device includes a frame plate. Four casters are fixedly mounted at the lower corners of the frame plate. A push-pull rod is welded to the rear of the upper end of the frame plate. A fully rotating connecting plate is mounted on the upper end of the frame plate. A vertical plate is welded to the center of the upper end of the connecting plate. Two base frames are welded to one side of the vertical plate. A guide rail is fixedly mounted on the upper end of the base frames. A linearly sliding slider is mounted on the outer side of the guide rail. A crossbar is fixedly mounted on the upper end of the slider. A central rod passes through the center of the crossbar. A horizontal bar is fixedly mounted on the upper end of the central rod. A troweling structure for positioning the concrete is provided on the outer side of the horizontal bar. Extension plates are provided on both sides of the top of the troweling structure. A cylinder is movably mounted on the upper end of the extension plates. Vibration structures for vibrating the concrete are provided on both sides of the bottom of the troweling structure.

[0007] Preferably, a support frame is fixedly installed on the upper end of the connecting plate, and the upper end of the support frame is fixedly connected to the side of the upright plate.

[0008] Preferably, two side rods are fixedly installed on the outer side of the central rod, and two guide rods are movably installed on one side of the upright plate above the base frame. The guide rods pass through the side rods and are slidably connected to them.

[0009] Preferably, the smearing tape structure includes a lifting platform, a connecting rod, a guide box, and a smearing tape frame. The lifting platform is fixedly installed at the upper end of the crossbar, the connecting rod is fixedly installed at the lower end of the screw of the lifting platform, the guide box is fixedly installed at the lower end of the connecting rod, and the smearing tape frame is movably installed on both sides of the guide box via a rotating shaft.

[0010] Preferably, the guide box and the inner side of the wiping belt frame are connected through each other, and the two wiping belt frames are arranged symmetrically around the guide box, with the guide box and the wiping belt frame arranged in a circle.

[0011] Preferably, the extension plate is fixedly installed on both sides of the guide box, and the lower end of the piston rod of the cylinder is movably connected to the top of the smear frame.

[0012] Preferably, the vibration structure includes a vibrating rod shell, an eccentric rod, a fixed base, and a mounting frame. The fixed base is fixed to the outside of the smear frame, the mounting frame is fixedly installed on one side of the fixed base, the vibrating rod shell is inserted into the mounting frame, and the eccentric rod is rotatably installed inside the vibrating rod shell.

[0013] Preferably, the vibratory rod shell extends through the fixing base and the wiping frame, and the two vibratory rod shells are arranged in parallel.

[0014] Preferably, motors are fixedly installed on both sides of the upper end of the crossbar, and a transmission pipe is fixedly installed on the lower end of the motor shaft. The lower end of the transmission pipe is fixedly connected to the vibrating rod shell, and the steel wire rope inside the transmission pipe passes through the vibrating rod shell and is fixedly connected to the eccentric rod.

[0015] A method for using an adjustable concrete pipe joint sealing tape device, the method specifically includes the following steps:

[0016] Step 1, Device placement and initial calibration:

[0017] The operator holds the push-pull rod and applies pushing force. Using the movable wheels installed at the four corners of the lower end of the frame plate, the entire device is smoothly pushed to the position in front of the concrete pipe interface to be constructed. Then, the operator steps on the parking brake mechanism on the movable wheels to lock it and prevent the device from being accidentally displaced during operation.

[0018] Step 2, Adjusting the working direction and angle:

[0019] Manually rotate the connecting plate mounted on the upper part of the frame plate. The connecting plate drives the welded vertical plate above it, as well as the guide rail, slider, cross, center rod, cross bar and trowel structure connected to one side of the vertical plate through the base frame, to rotate 360° in all directions until the axis of the trowel structure is aligned with the center axis of the pipe interface to be constructed. After adjustment, tighten the positioning bolts on the connecting plate to ensure that the direction does not deviate during subsequent operations.

[0020] Step 3, precise horizontal alignment:

[0021] The operator pushes the slider horizontally along the guide rail, causing the cross-shaped part fixed at its upper end and the central rod passing through the cross-shaped part to slide linearly along the guide rail. The upper end of the central rod is fixedly connected to a horizontal rod, and a smearing structure is set on the outside of the horizontal rod. By continuously fine-tuning the position of the slider, the two smearing frames below the smearing structure are positioned exactly above the center of the pipe interface. At the same time, the two side rods on the outside of the central rod slide synchronously along the two guide rods on one side of the vertical plate, providing guidance and limiting for the entire lateral movement, ensuring the smoothness and straightness of the movement process.

[0022] Step 4, Vertical descent and insertion:

[0023] Start the lifting machine fixedly installed on the upper end of the crossbar. The screw of the lifting machine extends downward and drives the guide box and the two smearing frames that are movably connected to the guide box through the connecting rod fixedly connected to the lower end of the screw to slowly descend as a whole. The operator visually monitors the lower edge of the smearing frame. When the smearing frame descends to the appropriate height of the outer wall of the pipe interface, stop the lifting machine so that the two smearing frames are in the ready-to-fit position outside the pipe interface.

[0024] Step 5, closing and wrapping:

[0025] The cylinder mounted on the upper part of the extension plate is activated. The piston rod of the cylinder extends downward and pushes the two trowel frames to rotate synchronously and close around their respective axes. The two trowel frames are symmetrically arranged around the guide box and are set in a circle. After closing, they form a complete annular closed space, which tightly wraps around the outer periphery of the concrete pipe interface. The cylinder continuously applies a certain pressure to ensure that the inner wall of the trowel frame and the outer wall of the pipe maintain a uniform gap. This gap is the forming thickness of the subsequent concrete trowel. At this time, the guide box and the inner sides of the two trowel frames are connected to form a continuous concrete conveying and forming channel.

[0026] Step Six, Concrete Pouring and Filling:

[0027] The operator pours the pre-mixed concrete mortar into the material box through the top opening. Under the action of gravity, the concrete flows down along the inner cavity of the material box and is evenly distributed into the troweling frames on both sides. As the concrete is continuously poured in, the annular cavity inside the troweling frame is gradually filled. The concrete completely covers the gap at the pipe joint and is initially formed under the constraint of the inner wall of the troweling frame.

[0028] Step 7: High-frequency vibration compaction:

[0029] Two motors, fixedly installed on the upper end of the crossbar and located on both sides of the elevator, are started. The motor shafts rotate at high speed, transmitting the rotational power to the vibratory rod housing fixedly connected to the lower end of the transmission tube through the transmission tube fixedly connected to the lower end of the transmission tube. The steel wire rope inside the transmission tube rotates with the shaft. The steel wire rope passes through the vibratory rod housing and is fixedly connected to the eccentric rod installed inside the vibratory rod housing, thereby driving the eccentric rod to rotate at high speed eccentrically inside the vibratory rod housing. The high-speed eccentric motion of the eccentric rod generates centrifugal force, causing the vibratory rod housing to generate high-frequency mechanical vibration. The vibratory rod housing passes through the fixed seat and the trowel frame. The two vibratory rod housings are arranged in parallel between each other. The vibration generated directly acts on the concrete mortar inside the trowel frame. Under the action of high-frequency vibration, air bubbles inside the concrete are expelled, aggregate particles are rearranged and compacted, and concrete paste evenly coats the surface of aggregate, thereby achieving full compaction of concrete. The vibration duration is 30 to 60 seconds.

[0030] Step 8, Demolding and Resetting:

[0031] After the concrete in the trowel frame has initially set and gained a certain self-supporting strength, the piston rod of the control cylinder retracts upward, pulling the two trowel frames to open and separate outward around the axis, releasing the constraint on the formed concrete. Then, the elevator is restarted, and the elevator screw retracts upward, driving the guide box and the two opened trowel frames to rise as a whole through the connecting rod, so that the trowel frames are completely separated from the pipe interface of the formed trowel. Finally, the positioning bolts of the connecting plate are loosened, the trowel structure is rotated to the non-working position, and the slider is slid to the initial position along the guide rail, completing one complete cycle of adjustable concrete pipe interface troweling operation.

[0032] The above embodiments of the present invention can achieve the following beneficial effects: the movable platform composed of the frame plate, moving wheels and push-pull rod, combined with the 360° rotation adjustment of the connecting plate, the lateral sliding of the slider along the guide rail, the vertical lifting of the elevator and the opening and closing action of the trowel frame driven by the cylinder, realizes the device's rapid positioning, precise alignment and automatic closing and wrapping, eliminating the tedious process of repeated manual handling and mold adjustment in the traditional way, greatly shortening the preparation time for a single troweling operation, and significantly improving the construction efficiency of troweling pipe joints;

[0033] By setting a vibration structure inside the grouting frame, the eccentric rod is driven by a steel wire rope in the transmission tube by a motor to rotate at high speed eccentrically inside the vibrator shell, generating high-frequency vibration that directly acts on the concrete mortar inside the grouting frame. The high-frequency vibration can effectively expel air bubbles inside the concrete, promote the rearrangement and compaction of aggregate particles, and make the concrete paste evenly coat the surface of the aggregate, thereby completely eliminating common quality defects such as honeycomb and pitting, and ensuring the compactness and overall strength of the grouting at the pipe joint.

[0034] The automated control of the elevator and cylinders enables the lifting, closing and separation of the troweling frame, replacing the traditional manual labor of lifting and assembling molds. At the same time, the setting of the material guide box allows the concrete to be automatically diverted into the troweling frame on both sides under the action of gravity after being poured, eliminating the need for manual filling in sections, greatly reducing the workload of operators and reducing the dependence on skilled workers.

[0035] The omnidirectional rotation of the connecting plate allows it to adapt to different pipe interface directions. The linear sliding of the slider along the guide rail allows for flexible adjustment of the trowel structure's lateral position, adapting to the construction needs of different pipe diameters and interface positions. The lifting adjustment of the hoist allows it to adapt to pipe interfaces of different burial depths and heights. The opening and closing of the trowel frame driven by the cylinder allows it to adapt to pipe interface sizes of different diameters. The combination of multiple adjustment functions enables this device to be widely used in concrete pipe interface troweling construction in various municipal drainage, water conservancy and other projects. Attached Figure Description

[0036] Figure 1This is a schematic diagram of the overall structure of an adjustable concrete pipe joint sealing tape device according to the present invention.

[0037] Figure 2 This is an enlarged view of the connecting plate in an adjustable concrete pipe joint troweling device of the present invention.

[0038] Figure 3 This is an enlarged view of the central rod in an adjustable concrete pipe joint sealing device of the present invention.

[0039] Figure 4 This is an enlarged view of the troweling structure in an adjustable concrete pipe joint troweling device of the present invention.

[0040] Figure 5 This is an enlarged view of the trowel frame in an adjustable concrete pipe joint troweling device of the present invention.

[0041] Figure 6 This is a structural diagram of the unfolded trowel frame in an adjustable concrete pipe joint troweling device of the present invention;

[0042] Figure 7 This is a cross-sectional view of the trowel frame in an adjustable concrete pipe joint troweling device of the present invention.

[0043] Figure 8 This is a cross-sectional view of the vibration structure in an adjustable concrete pipe joint applicator of the present invention.

[0044] In the diagram: 1. Frame plate; 2. Moving wheel; 3. Push-pull rod; 4. Connecting plate; 5. Support frame; 6. Upright plate; 7. Base frame; 8. Guide rail; 9. Slider; 10. Cross; 11. Center rod; 12. Side rod; 13. Guide rod; 14. Cross rod; 15. Wiping belt structure; 16. Lifting machine; 17. Connecting rod; 18. Material guide box; 19. Wiping belt frame; 20. Extension plate; 21. Cylinder; 22. Motor; 23. Transmission pipe; 24. Vibration structure; 25. Vibrator housing; 26. Eccentric rod; 27. Fixed seat; 28. Mounting bracket. Detailed Implementation

[0045] To make the technical means, creative features, objectives and effects of this invention easier to understand, the invention will be further described below in conjunction with specific embodiments.

[0046] like Figures 1-8 As shown, an adjustable concrete pipe joint sealing tape device, referring to... Figures 1-8The system includes a frame plate 1, with four fixed casters 2 at the lower corners of the frame plate 1. A push-pull rod 3 is welded to the upper rear of the frame plate 1. A fully rotating connecting plate 4 is installed at the upper end of the frame plate 1. A vertical plate 6 is welded to the center of the upper end of the connecting plate 4. Two base frames 7 are welded to one side of the vertical plate 6. A guide rail 8 is fixedly installed at the upper end of the base frame 7. A linear sliding slider 9 is installed on the outer side of the guide rail 8. A cross 10 is fixedly installed at the upper end of the slider 9. A central rod 11 passes through the center of the cross 10. A cross bar 14 is fixedly installed at the upper end of the central rod 11. A troweling structure 15 for positioning concrete is set on the outer side of the cross bar 14. Extension plates 20 are set on both sides of the top of the troweling structure 15. A cylinder 21 is movably installed on the upper end of the extension plate 20. A vibration structure 24 for vibrating concrete is set on both sides of the bottom of the troweling structure 15.

[0047] Reference Figure 1 A support frame 5 is fixedly installed on the upper end of the connecting plate 4, and the upper end of the support frame 5 is fixedly connected to the side of the upright plate 6.

[0048] Reference Figure 2 and Figure 3 Two side rods 12 are fixedly installed on the outside of the center rod 11. Two guide rods 13 are movably installed on one side of the upright plate 6 above the base frame 7. The guide rods 13 pass through the side rods 12 and are slidably connected to them.

[0049] Reference Figures 4-6 The smearing structure 15 includes a lifting platform 16, a connecting rod 17, a guide box 18, and a smearing frame 19. The lifting platform 16 is fixedly installed on the upper end of the crossbar 14, the connecting rod 17 is fixedly installed on the lower end of the screw of the lifting platform 16, the guide box 18 is fixedly installed on the lower end of the connecting rod 17, and the smearing frame 19 is movably installed on both sides of the guide box 18 via a rotating shaft.

[0050] Reference Figures 4-6 The inner sides of the guide box 18 and the wiping frame 19 are connected through each other, and the two wiping frames 19 are symmetrically arranged around the guide box 18. The guide box 18 and the wiping frame 19 are arranged in a circle.

[0051] Specifically, the lifting platform 16 is operated by hand or by power drive. The lifting platform 16 uses an internal worm gear structure to lift the screw. Therefore, the operation of the lifting platform 16 causes the screw to lift and move the lower guide box 18 and the smear frame 19.

[0052] Reference Figures 4-6 The extension plate 20 is fixedly installed on both sides of the guide box 18, and the lower end of the piston rod of the cylinder 21 is movably connected to the top of the smear frame 19.

[0053] Specifically, cylinder 21 is a standard cylinder, which is connected to an external air source and driven by a solenoid valve, causing the air to push the piston rod in cylinder 21 to extend. Therefore, the simultaneous operation of the two cylinders 21 causes the piston rod to extend and drive the two wiping frames 19 to rotate synchronously. The wiping frames 19 are made of metal.

[0054] Reference Figure 7 and Figure 8 The vibration structure 24 includes a vibrating rod housing 25, an eccentric rod 26, a fixed base 27, and a mounting bracket 28. The fixed base 27 is fixed to the outside of the smear frame 19, and the mounting bracket 28 is fixedly installed on one side of the fixed base 27. The vibrating rod housing 25 is inserted into the mounting bracket 28, and the eccentric rod 26 is rotatably installed inside the vibrating rod housing 25.

[0055] Reference Figure 7 and Figure 8 The vibrating rod housing 25 passes through the fixing seat 27 and the wiping frame 19, and the two vibrating rod housings 25 are arranged in parallel.

[0056] Reference Figure 4 , Figure 7 and Figure 8 The upper end of the crossbar 14 is fixedly installed with motors 22 on both sides of the elevator 16. The lower end of the shaft of the motor 22 is fixedly installed with a transmission pipe 23. The lower end of the transmission pipe 23 is fixedly connected to the vibrating rod shell 25. The steel wire rope inside the transmission pipe 23 passes through the vibrating rod shell 25 and is fixedly connected to the eccentric rod 26.

[0057] Specifically, the motor 22 is connected to an external power source and runs. The operation of the motor 22 drives the steel wire rope in the transmission tube 23 to rotate. The steel wire rope then drives the eccentric rod 26 in the vibrating rod shell 25 to rotate. The eccentric structure of the eccentric rod 26 causes the vibrating rod shell 25 to vibrate.

[0058] It should be noted that this invention is an adjustable concrete pipe joint troweling device and its troweling method. During use, the operator holds the push-pull rod 3, applies pushing force, and uses the movable wheels 2 installed at the four corners of the lower end of the frame plate 1 to smoothly push the entire device to the position directly in front of the concrete pipe joint to be constructed. Then, the parking brake mechanism on the movable wheels 2 is depressed to lock it, preventing accidental displacement of the device during operation. The connecting plate 4 installed on the upper end of the frame plate 1 is manually rotated. The connecting plate 4 drives the welded upright plate 6 above it, as well as the guide rail 8, slider 9, cross 10, center rod 11, cross bar 14, and troweling structure 15 connected to one side of the upright plate 6 via the base frame 7, to rotate 360° in all directions until the axis of the troweling structure 15 is aligned with the central axis of the pipe joint to be constructed. After adjustment, the positioning bolts on the connecting plate 4 are tightened to ensure that the direction does not deviate during subsequent operations. The operator pushes the slider 9 horizontally along the guide rail 8. The slider 9 drives the cross 10 fixed at its upper end and the central rod 11 passing through the cross 10 to slide linearly along the guide rail 8. The upper end of the central rod 11 is fixedly connected to the cross bar 14. The outer side of the cross bar 14 is provided with a wiping strip structure 15. By continuously fine-tuning the position of the slider 9, the two wiping strip frames 19 below the wiping strip structure 15 are positioned exactly above the center of the pipe interface. At the same time, the two side rods 12 on the outer side of the central rod 11 slide synchronously along the two guide rods 13 on one side of the vertical plate 6, providing guidance and limiting for the entire lateral movement, ensuring the smoothness and straightness of the movement process. Start the lifting machine 16 fixedly installed on the upper end of the crossbar 14. The screw of the lifting machine 16 extends downward and drives the guide box 18 and the two smearing frames 19 movably connected to the guide box 18 through the connecting rod 17 fixedly connected to the lower end of the screw to slowly descend as a whole. The operator visually monitors the lower edge of the smearing frame 19. When the smearing frame 19 descends to the appropriate height of the outer wall of the pipe interface, the lifting machine 16 is paused, so that the two smearing frames 19 are in the ready-to-fit position outside the pipe interface. The cylinder 21 installed on the upper end of the extension plate 20 is activated. The piston rod of the cylinder 21 extends downward and pushes the two trowel frames 19 to rotate synchronously and close around their respective axes. The two trowel frames 19 are symmetrically arranged around the guide box 18 and are set in a circle. After closing, they form a complete annular closed space, which tightly wraps around the outer periphery of the concrete pipe interface. The cylinder 21 continuously applies a certain clamping force to ensure that the inner wall of the trowel frame 19 and the outer wall of the pipe maintain a uniform gap. This gap is the forming thickness of the subsequent concrete trowel. At this time, the guide box 18 is connected to the inner side of the two trowel frames 19 to form a continuous concrete conveying and forming channel.The operator pours pre-mixed concrete mortar into the material guide box 18 through the upper opening. Under the action of gravity, the concrete flows downward along the inner cavity of the material guide box 18 and is evenly distributed into the trowel frames 19 on both sides. As the concrete is continuously poured in, the annular cavity inside the trowel frame 19 is gradually filled, and the concrete completely covers the gap at the pipe joint and is initially formed under the constraint of the inner wall of the trowel frame 19. The two motors 22, which are fixedly installed on the upper end of the crossbar 14 and located on both sides of the elevator 16, are started. The shaft of the motor 22 rotates at high speed, and the rotational power is transmitted to the vibrating rod housing 25 fixedly connected to the lower end of the shaft through the transmission pipe 23. The steel wire rope inside the transmission pipe 23 rotates with the shaft. The steel wire rope passes through the vibrating rod housing 25 and is fixedly connected to the eccentric rod 26 installed inside the vibrating rod housing 25, thereby driving the eccentric rod 26 to rotate at high speed eccentrically inside the vibrating rod housing 25. The motion generates centrifugal force, causing the vibrator shell 25 to produce high-frequency mechanical vibration. The vibrator shell 25 passes through the fixed base 27 and the trowel frame 19. The two vibrator shells 25 are arranged in parallel. The vibration generated directly acts on the concrete mortar in the trowel frame 19. Under the action of high-frequency vibration, the air bubbles inside the concrete are expelled, the aggregate particles are rearranged and compacted, and the concrete paste evenly coats the surface of the aggregate, thereby achieving full compaction of the concrete and eliminating quality defects such as honeycomb and pitting. The vibration duration is 30 to 60 seconds. After the concrete in the trowel frame 19 has initially set and gained a certain self-supporting strength, the piston rod of the control cylinder 21 retracts upward, pulling the two trowel frames 19 to open and separate around the outer axis, releasing the constraint on the formed concrete. Then, the elevator 16 is restarted, and the screw of the elevator 16 retracts upward, driving the guide box 18 and the two opened trowel frames 19 to rise as a whole through the connecting rod 17, so that the trowel frames 19 are completely separated from the pipe interface of the formed trowel. Finally, the positioning bolts of the connecting plate 4 are loosened, the trowel structure 15 is rotated to the non-working position, and the slider 9 is slid to the initial position along the guide rail 8, completing one complete cycle of adjustable concrete pipe interface troweling operation.

[0059] In actual construction, the functional modules corresponding to the above steps do not operate in isolation, but can be combined and adjusted in real time and dynamically according to the site conditions. For example, when painting the exterior walls, the horizontal movement function can be used to send the workers to the designated wall area, the rotation function can be used to adjust the facing angle, and finally the traction function can be used to hoist the paint buckets. Throughout the process, the base platform always provides stable protection. The functional modules are highly integrated and work together to form an organic and efficient construction safety protection and operation system. Construction personnel can complete a variety of complex operations such as movement, lifting, rotation, and hoisting without leaving the safety platform.

[0060] The above embodiments are only used to illustrate the technical methods of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical methods of the present invention without departing from the spirit and scope of the technical methods of the present invention.

Claims

1. An adjustable concrete pipe joint applicator, comprising a frame plate (1), wherein movable wheels (2) are fixedly installed at the four corners of the lower end of the frame plate (1), and a push-pull rod (3) is welded to the rear of the upper end of the frame plate (1), characterized in that: The upper end of the frame plate (1) is equipped with a omnidirectional rotating connecting plate (4). A vertical plate (6) is welded to the center of the upper end of the connecting plate (4). Two base frames (7) are welded to one side of the vertical plate (6). A guide rail (8) is fixedly installed on the upper end of the base frame (7). A linear sliding slider (9) is installed on the outer side of the guide rail (8). A cross (10) is fixedly installed on the upper end of the slider (9). A central rod (11) passes through the center of the cross (10). A cross bar (14) is fixedly installed on the upper end of the central rod (11). A trowel structure (15) for positioning concrete is provided on the outer side of the cross bar (14). Extension plates (20) are provided on both sides of the top of the trowel structure (15). A cylinder (21) is movably installed on the upper end of the extension plate (20). A vibration structure (24) for vibrating concrete is provided on both sides of the bottom of the trowel structure (15).

2. The adjustable concrete pipe joint sealing tape device according to claim 1, characterized in that: A support frame (5) is fixedly installed on the upper end of the connecting plate (4), and the upper end of the support frame (5) is fixedly connected to the side of the upright plate (6).

3. The adjustable concrete pipe joint sealing tape device according to claim 1, characterized in that: Two side rods (12) are fixedly installed on the outside of the central rod (11), and two guide rods (13) are movably installed on one side of the upright plate (6) above the base frame (7). The guide rods (13) pass through the side rods (12) and are slidably connected to them.

4. The adjustable concrete pipe joint sealing tape device according to claim 1, characterized in that: The smearing structure (15) includes a lifting platform (16), a connecting rod (17), a guide box (18), and a smearing frame (19). The lifting platform (16) is fixedly installed on the upper end of the crossbar (14), the connecting rod (17) is fixedly installed on the lower end of the screw of the lifting platform (16), the guide box (18) is fixedly installed on the lower end of the connecting rod (17), and the smearing frame (19) is movably installed on both sides of the guide box (18) through a rotating shaft.

5. The adjustable concrete pipe joint sealing tape device according to claim 4, characterized in that: The guide box (18) is connected to the inner side of the wiping frame (19), and the two wiping frames (19) are arranged symmetrically around the guide box (18). The guide box (18) and the wiping frame (19) are arranged in a circle.

6. The adjustable concrete pipe joint sealing tape device according to claim 4, characterized in that: The extension plate (20) is fixedly installed on both sides of the guide box (18), and the lower end of the piston rod of the cylinder (21) is movably connected to the top of the smearing frame (19).

7. The adjustable concrete pipe joint sealing tape device according to claim 4, characterized in that: The vibration structure (24) includes a vibrating rod shell (25), an eccentric rod (26), a fixed seat (27), and a mounting bracket (28). The fixed seat (27) is fixed on the outside of the smear frame (19), and the mounting bracket (28) is fixedly installed on one side of the fixed seat (27). The vibrating rod shell (25) is inserted into the mounting bracket (28), and the eccentric rod (26) is rotatably installed inside the vibrating rod shell (25).

8. The adjustable concrete pipe joint sealing tape device according to claim 7, characterized in that: The vibratory rod housing (25) passes through the fixed base (27) and the wiping frame (19), and the two vibratory rod housings (25) are arranged in parallel.

9. An adjustable concrete pipe joint sealing tape device according to claim 7, characterized in that: The upper end of the crossbar (14) is fixedly installed with motors (22) on both sides of the elevator (16). The lower end of the shaft of the motor (22) is fixedly installed with a transmission pipe (23). The lower end of the transmission pipe (23) is fixedly connected to the vibrating rod shell (25). The steel wire rope in the transmission pipe (23) passes through the vibrating rod shell (25) and is fixedly connected to the eccentric rod (26).

10. A method for applying a sealing tape using an adjustable concrete pipe joint sealing tape device as described in any one of claims 1-9, characterized in that, The method specifically includes the following steps: Step 1, Device placement and initial calibration: The operator holds the push-pull rod (3) and applies the push force. Using the movable wheels (2) installed at the four corners of the lower end of the frame plate (1), the entire device is smoothly pushed to the position in front of the concrete pipe interface to be constructed. Then, the operator steps on the parking brake mechanism on the movable wheel (2) to lock it and prevent the device from being accidentally displaced during the operation. Step 2, Adjusting the working direction and angle: Manually rotate the connecting plate (4) installed on the upper end of the frame plate (1). The connecting plate (4) drives the welded vertical plate (6) above it and the guide rail (8), slider (9), cross (10), center rod (11), cross bar (14) and troweling structure (15) connected to one side of the vertical plate (6) through the base frame (7) to rotate 360° in all directions until the axis of the troweling structure (15) is aligned with the central axis of the pipe interface to be constructed. After adjustment, tighten the positioning bolts on the connecting plate (4) to ensure that the direction does not deviate in subsequent operations. Step 3, precise horizontal alignment: The operator pushes the slider (9) horizontally along the guide rail (8). The slider (9) drives the cross (10) fixed at its upper end and the central rod (11) passing through the cross (10) to slide in a straight line along the guide rail (8). The upper end of the central rod (11) is fixedly connected to the cross rod (14). The outer side of the cross rod (14) is provided with a wiping strip structure (15). By continuously fine-tuning the position of the slider (9), the two wiping strip frames (19) below the wiping strip structure (15) are positioned exactly above the center of the pipe interface. At the same time, the two side rods (12) on the outer side of the central rod (11) slide synchronously along the two guide rods (13) on one side of the vertical plate (6), providing guidance and limit for the entire horizontal movement, ensuring the smoothness and straightness of the movement process. Step 4, Vertical descent and insertion: Start the elevator (16) fixedly installed on the upper end of the crossbar (14). The screw of the elevator (16) extends downward and drives the guide box (18) and the two smearing frames (19) connected to the guide box (18) through the rotating shaft to slowly descend as a whole. The operator visually monitors the lower edge of the smearing frame (19). When the smearing frame (19) descends to the appropriate height of the outer wall of the pipe interface, stop the elevator (16) so that the two smearing frames (19) are in the ready-to-fit position outside the pipe interface. Step 5, closing and wrapping: The cylinder (21) installed on the upper end of the extension plate (20) is activated. The piston rod of the cylinder (21) extends downward and pushes the two trowel frames (19) to rotate synchronously around their respective axes and close together. The two trowel frames (19) are symmetrically arranged around the guide box (18) and are set in a circle. After closing, they form a complete annular closed space, which tightly wraps around the outer periphery of the concrete pipe interface. The cylinder (21) continuously applies a certain pressure to ensure that the inner wall of the trowel frame (19) and the outer wall of the pipe maintain a uniform gap. This gap is the forming thickness of the subsequent concrete trowel. At this time, the guide box (18) and the inner side of the two trowel frames (19) are connected to form a continuous concrete conveying and forming channel. Step Six, Concrete Pouring and Filling: The operator puts the pre-mixed concrete mortar into the upper opening of the guide box (18). Under the action of gravity, the concrete flows down along the inner cavity of the guide box (18) and is evenly distributed into the troweling frames (19) on both sides. As the concrete is continuously injected, the annular cavity inside the troweling frame (19) is gradually filled. The concrete completely covers the gap at the pipe interface and is initially formed under the constraint of the inner wall of the troweling frame (19). Step 7: High-frequency vibration compaction: Two motors (22) fixedly installed on the upper end of the crossbar (14) and located on both sides of the elevator (16) are started. The shaft of the motor (22) rotates at high speed, and the rotational power is transmitted to the vibrating rod shell (25) fixedly connected to the lower end of the transmission tube (23) through the transmission tube (23). The steel wire rope inside the transmission tube (23) rotates together with the shaft. The steel wire rope passes through the vibrating rod shell (25) and is fixedly connected to the eccentric rod (26) installed inside the vibrating rod shell (25), thereby driving the eccentric rod (26) to rotate at high speed eccentrically inside the vibrating rod shell (25). The high-speed eccentric motion of the eccentric rod (26) generates centrifugal force, causing the vibrator shell (25) to generate high-frequency mechanical vibration. The vibrator shell (25) passes through the fixed seat (27) and the trowel frame (19). The two vibrator shells (25) are arranged in parallel. The vibration generated by them directly acts on the concrete mortar in the trowel frame (19). Under the action of high-frequency vibration, the air bubbles inside the concrete are discharged, the aggregate particles are rearranged and compacted, and the concrete paste evenly coats the surface of the aggregate, thereby achieving full compaction of the concrete. The vibration duration is 30 to 60 seconds. Step 8, Demolding and Resetting: After the concrete in the trowel frame (19) has initially set and has a certain self-supporting strength, the piston rod of the control cylinder (21) retracts upward, pulling the two trowel frames (19) to open and separate around the outer side of the rotation axis, releasing the constraint on the formed concrete. Then, the elevator (16) is started again, and the screw of the elevator (16) retracts upward, driving the guide box (18) and the two opened trowel frames (19) to rise as a whole through the connecting rod (17), so that the trowel frame (19) completely separates from the pipe interface of the formed trowel. Finally, the positioning bolt of the connecting plate (4) is loosened, the trowel structure (15) is rotated to the non-working position, and the slider (9) is slid to the initial position along the guide rail (8) to complete a complete cycle of adjustable concrete pipe interface troweling operation.