A transformer real-time residual capacity dynamic calculation method

By acquiring the transformer synchronous current waveform, removing the background current waveform to form the upper bound, and calculating the branch occupancy envelope, the problem of overestimation of remaining capacity caused by asynchronous measurement filtering and instruction execution is solved, thus achieving accuracy and stability in capacity measurement.

CN123136245APending Publication Date: 2026-11-20DONGGUAN XUSEN INTELLIGENT TECHNOLOGY CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611443593.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-17
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

In the existing technology, the problem of overestimation of the remaining capacity of the transformer is caused by the asynchronous measurement filtering and command execution during the power adjustment of the heating branch.

Method used

By acquiring the synchronous current waveforms of the transformer's low-voltage main incoming line and each controllable heating branch, the background current waveform is removed to form an upper limit. The larger value of the actual current effective value and the upper limit of the heating command current is taken for each branch to form the branch occupancy envelope. The sum of the background current upper limit and the occupancy envelope is deducted for each phase to calculate the remaining current and finally form the real-time remaining capacity.

Benefits of technology

This reduces the overestimation of remaining capacity caused by asynchronous measurement filtering and command execution during the power adjustment of the heating branch, ensuring that the output capacity matches the actual current and achieving accuracy and stability in capacity calculation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123136245A_ABST
    Figure CN123136245A_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of power load monitoring, and discloses a transformer real-time residual capacity dynamic calculation method. The synchronous current waveforms of the total incoming line and each controllable heating branch are obtained, the heating branch current is removed from each phase and each sampling point, and the background current waveform is formed; the background current upper limit in the control response time domain is determined based on the background current effective value sequence; the greater value of the actual current and the current upper limit corresponding to the still effective heating instruction is taken for each branch, and the single-branch occupation envelope is formed; the background current upper limit, the measurement margin and the branch occupation are deducted for each phase, and the new load capacity is output. The occupation is registered before the load increase instruction is sent, the occupation is released after the load reduction is executed and the feedback and the measurement window are confirmed, and the calculation result is updated cyclically. By separating the background load and the controlled heating load and continuously receiving the instruction occupation, the residual capacity overestimation caused by the measurement filtering and the instruction execution asynchronization during the power adjustment of the heating branch is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power load monitoring technology, specifically a method for dynamically calculating the real-time remaining capacity of a transformer. Background Technology

[0002] In heating scenarios where surplus capacity of a factory's distribution transformer is used to drive electric heating equipment, the production load and heating load share the same transformer, and the controller determines the heating load limit based on current measurement results. Publication CN121216418A describes a technical solution for adjusting the controllable load based on the transformer's real-time total load, predicted load, and dynamic safety margin. This type of capacity calculation converts load monitoring results into a basis for equipment adjustment, allowing the controllable load to change with the power supply margin.

[0003] When the heating branch adjusts its power, the capacity is calculated based on the total load filter value including the heating load. However, the issued heating command has not yet been fully reflected in the measurement results. There is a time difference between the load state used for measurement and the command execution state, which can easily lead to an overestimation of the remaining capacity, causing the same part of the capacity to be redistributed during continuous adjustment. Summary of the Invention

[0004] To address the shortcomings of existing technologies, this invention provides a method for dynamically calculating the real-time remaining capacity of transformers, solving the problem of overestimation of transformer remaining capacity caused by asynchronous measurement filtering and command execution during the power adjustment period of the heating branch in existing technologies.

[0005] To achieve the above objectives, the present invention provides the following technical solution: A method for dynamically calculating the real-time remaining capacity of a transformer; wherein the method includes: S1: acquiring the synchronous current waveform, allowable current of each phase, and heating command records of the transformer's low-voltage main incoming line and each controllable heating branch; S2: subtracting the synchronous current waveform from the sampled points of each phase to obtain the background current waveform after excluding each controllable heating branch, and forming an upper bound of the background current covering the control response time domain based on its effective value sequence; S3: taking the larger value between the actual effective current value and the upper bound of the current corresponding to the still effective heating command for each branch to form a branch occupancy envelope that is counted only once. S4: Subtract the upper limit of the background current, the metering margin, and the sum of the occupancy envelopes of each branch from the allowable current for each phase to obtain the remaining current. Compare the minimum value of the remaining current of each phase with zero and take the larger value to form the real-time remaining capacity. Output the new load quota for the heating controller. S5: Before issuing a new heating command, include it in the heating command record and update the branch occupancy envelope. Update the still valid heating commands according to the execution feedback and the corresponding measurement window so that the implemented load increase is carried by the actual current. After the load reduction is confirmed by measurement, release the occupancy and repeat the calculation.

[0006] Preferably, in step S1, the synchronous current waveform is obtained by a common sampling clock acquisition channel. Each channel has the same current direction, phase, and transformer ratio, and uses a complete power frequency cycle with the same start and end time as the measurement window. In each update cycle, the maximum value of the current effective value of each measurement window is taken as the actual current effective value.

[0007] Preferably, in step S1, the allowable current is the minimum value among the transformer's low-voltage side rated current, the current calculated based on rated capacity and the upper limit of allowable phase voltage, and the continuous operation limiting current. The continuous operation limiting current is preset based on the transformer derating conditions and the low-voltage main incoming current limit.

[0008] Preferably, in step S2, the formation of the upper bound of the background current includes: calculating the effective value of the background current waveform in each measurement window, taking the maximum value of the same update cycle as the background current observation value; performing exponential smoothing on the background current observation value, taking the larger value between the current background current observation value and the smoothed value, and adding the rise reserve in the control response time domain.

[0009] Preferably, in step S2, the rising reserve is obtained by multiplying the maximum positive rate of change of the background current observation within the historical window by the control response time domain length; the control response time domain length covers the age of the measurement data, the next update cycle, and the maximum delay from command communication to execution completion.

[0010] Preferably, in step S3, the branch occupancy envelope is formed according to phase; the maximum value of the upper limit of the current corresponding to the still valid heating command of the same branch is taken, and the larger value is compared with the actual effective value of the current of the branch; multiple commands of the same branch are not accumulated; the upper limit of the current includes the command setting current and the execution deviation limit.

[0011] Preferably, in step S3, when reducing the occupancy envelope of the branch, the upper limit of the command current before the reduction is retained until the execution completion feedback of the load reduction command is received, and the effective value of the branch current does not exceed the upper limit of the command current after the load reduction within a consecutive preset number of complete measurement windows after the feedback completion time, the replaced command is removed.

[0012] Preferably, in step S4, the real-time remaining capacity is applied to the three-phase equal current new load: the minimum value of the remaining current of each phase is compared with zero and the larger value is taken as the new current limit, which is then multiplied by the sum of the effective phase voltages of the three phases and converted into kilovolt-amperes; the new load limit also carries the remaining current of each phase and the effective cutoff time.

[0013] Preferably, in step S5, the inclusion of the new heating command and the update of the branch occupancy envelope are completed within the same critical zone. Based on the updated phase occupancy review allowable current constraints, if the constraints are met, the record is submitted and the command is sent; if the constraints are not met, the new command is revoked. No new load increase command is accepted for the same branch before the previous adjustment command is completed.

[0014] Preferably, in step S5, when the synchronous current waveform is missing, the measurement data exceeds the effective cutoff time, or the command execution exceeds the delay limit of the control response time domain, the newly added load quota is set to zero, the occupancy corresponding to the still effective heating command is retained, and a stop heating command is sent; after obtaining the stop feedback and the effective measurement window after the stop, the upper limit of the background current and the branch occupancy envelope are re-established.

[0015] This invention provides a method for dynamically calculating the real-time remaining capacity of a transformer. It has the following beneficial effects: 1. This invention forms an independent upper limit of background current by eliminating heating branches from the synchronous current waveform. Then, the upper limit of the actual current of each branch and the upper limit of the still valid command current are combined into a single occupancy, so that the unrealized load increase continues to occupy the quota, and the occupancy is carried by the actual current, reducing the overestimation of the remaining capacity caused by the asynchronous measurement filtering and command execution during the power adjustment of the heating branch.

[0016] 2. This invention establishes permissible current constraints phase by phase, taking the larger of the current background observation value and the smoothed value and adding a rising reserve to avoid the background current rise being masked by the smoothing process; the three-phase equal current increase is determined by the constrained phase, so that the output capacity corresponds to the current carrying conditions of each phase.

[0017] 3. This invention allows for the submission of load increases before transmission, and the release of load decreases in conjunction with execution feedback and complete measurement window. Combined with zero new quota and cessation of heating processing in case of anomalies, this invention ensures that quota changes in continuous measurement have clear effective conditions. Attached Figure Description

[0018] Figure 1 A flowchart of the method for dynamically calculating the real-time remaining capacity of a transformer; Figure 2 A data relationship diagram for synchronous current separation and phase-separated capacity calculation; Figure 3 This is a state transition diagram for heating command occupancy and measurement feedback. Detailed Implementation

[0019] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0020] Example 1 like Figure 1 and Figure 2 As shown, this method is executed by a measurement host that connects the current acquisition unit and the heating controller. The low-voltage busbar of the transformer supplies power to the production load and multiple controllable heating branches. The measurement host classifies the current generated by the production load into the background current and registers the heating branches under unified control separately.

[0021] In this embodiment, the current relationship is established within the same low-voltage busbar and the same metering boundary. The main incoming line sampling point is located before all controlled branch branches branch, and the sampling points of each branch are located after the corresponding branch; there is no other transformer connected in parallel for power supply or independent power generation injection between the sampling points. When the circulating pump is not included in the heating regulation, its current is included in the background current.

[0022] In this method, remaining capacity represents the new load quota that has not yet been consumed by background load and effective heating, expressed in kilovolt-amperes (kVA). The total allowable quota for controllable heating branches also includes the already occupied portion; these two are stored separately, and the new quota is not included in the total target value for heating equipment.

[0023] Each branch circuit uses a heating controller with a current limiting interface, and the controlled object of the branch circuit covers all heating units in that branch circuit. The controller adjusts according to the effective value current limit of the command, and the actual occupancy of a single branch circuit is not replaced by the nameplate thermal output power; the current changes caused by the start and stop of the pump, contactor and heating unit are included by the measured or command upper limit.

[0024] S1: Obtain the synchronous current waveform, allowable current of each phase, and heating command record of the transformer's low-voltage main incoming line and each controllable heating branch.

[0025] Preferably, in step S1, the synchronous current waveform is obtained from a common sampling clock acquisition channel. Each channel has a unified current direction, phase, and transformer ratio, and uses a complete power frequency cycle with the same start and end times as the measurement window. In each update cycle, the maximum value of the effective current value from each measurement window is taken as the actual effective current value. In step S1, the allowable current is the minimum value among the transformer's low-voltage side rated current, the current calculated based on rated capacity and the upper limit of allowable phase voltage, and the continuous operation limiting current. The continuous operation limiting current is preset based on the transformer derating conditions and the low-voltage main incoming current limit.

[0026] Specifically, the acquisition unit is configured with three-phase current channels for the main incoming line and each heating branch, and all channels share the sampling clock and synchronous trigger signal. First, phases A, B, and C are fixed according to the wiring markings, and the positive direction of the current is uniformly from the transformer to the load. Then, the secondary sampling values ​​of the current transformers are multiplied by their respective turns ratios to convert them into the primary current on the low-voltage side, in amperes.

[0027] Each current sample retains its sign, and the absolute value is not taken point by point on the waveform. During installation, the channel gain and channel delay are calibrated with the same injection current, and the total input line and branch sampling points correspond to the same moment after calibration; waveform separation is prohibited if the phase is incorrect, the current transformer polarity is reversed, or the channel is saturated.

[0028] A complete power frequency cycle is identified by the continuous zero-crossing points of the bus voltage in the same direction, and current data at the same start and end times are extracted. When a fixed sampling rate is used, the actual number of samples is retained for each window; the sum of the squares of the current samples within the window, divided by the number of samples, and then the square root is taken to obtain the effective value of the current in that window, without directly using the instantaneous peak value as the effective value.

[0029] The host is updated once per second. One update cycle contains multiple complete power frequency cycles. The effective current value of each phase of each branch is calculated in each complete cycle, and the maximum value in the update cycle is taken as the actual effective current value. This statistical method retains the full cycle conduction occupancy caused by cycle switching, and does not use the one-second average power to suppress the current occupancy of intermittent heating.

[0030] The sampling frequency is determined by both the metering bandwidth and the anti-aliasing filter. For example, if the sampling frequency is set to 6400 Hz, one power frequency cycle contains 128 samples when running at 50 Hz. The acquisition channel synchronously performs anti-aliasing filtering, and residual errors outside the bandwidth are included in the metering margin; when the field distortion exceeds the channel calibration range, a failure status is output and load increase is stopped.

[0031] The original sampling buffer records the cycle number, window start and end times, phase, channel number, number of samples, transformation ratio, and quality flag. A window is only passed to the next step when all corresponding windows for all in-use branches and the main input are complete and of valid quality. The time when the controller receives data does not replace the window's own acquisition time.

[0032] The allowable current is configured before operation. Read the transformer's rated capacity and low-voltage side rated current, convert the rated capacity to volt-amperes (VA), divide by three times the upper limit of the allowable phase voltage to obtain the capacity-converted current; then compare this with the rated current and the continuous operation limit current, taking the smaller value. The upper limit of the phase voltage is taken as the upper boundary of the allowable voltage range, without increasing the allowable current when there is a momentary voltage drop.

[0033] The continuous operating current limit is obtained by minimizing the derating limit of the transformer under specified environmental, cooling, and harmonic conditions, as well as the continuous current carrying limit of the low-voltage main incoming conductor and switch. The above configuration is based on the equipment technical documents and on-site settings, and the calculation process does not take short-term overload capacity as long-term allocable capacity.

[0034] The main unit simultaneously reads the effective phase voltage of each phase and checks that it is within the configured range. The allowable current for each phase is stored separately; when the rated capacity is the total three-phase capacity, it is not reused as a separate three-phase capacity. Metering margins are stored phase-by-phase, covering metering errors other than those related to current transformers, synchronization calibration, quantization, and branch command execution deviations.

[0035] Heating command records are maintained by the measurement host and include branch number, command sequence number, set current for each phase, current upper limit, submission time, execution feedback time, and whether it is still valid. Upon startup, the target value and actual current of the current branch are obtained first, and an initial record is established after a consistency check is completed. It is not permissible to assume that the equipment is not using capacity simply because the host memory is empty.

[0036] S1 establishes a unified metering boundary, time boundary, and current unit, ensuring that subsequent point-by-point subtraction and command current comparisons apply to the same electrical object. When synchronization conditions are not met, an effective window is not created by filling in the old values ​​of the main incoming line or branches.

[0037] S2: Subtract the synchronous current waveform from each phase sampling point to obtain the background current waveform after removing each controllable heating branch, and form the upper bound of the background current covering the control response time domain based on its effective value sequence.

[0038] Preferably, in step S2, the formation of the upper bound of the background current includes: calculating the effective value of the background current waveform within each measurement window, taking the maximum value of the same update cycle as the background current observation value; performing exponential smoothing on the background current observation value, taking the larger value between the current background current observation value and the smoothed value, and adding the rise reserve in the control response time domain. In step S2, the rise reserve is obtained by multiplying the maximum positive rate of change of the background current observation value within the historical window by the control response time domain length; the control response time domain length covers the age of the measurement data, the next update cycle, and the maximum delay from command communication to execution completion.

[0039] Specifically, for each phase and each complete measurement window, the signed current values ​​of all controlled heating branches are accumulated point by point. This accumulated value is then subtracted from the signed current value of the same sampling point in the main incoming line to form the background current waveform. This calculation is based on the current relationship at the same node and is completed before calculating the effective value.

[0040] The effective value of the total incoming current cannot be directly subtracted from the effective value of the branch current to replace the background current waveform calculation. For example, when the power factor is different or the current is distorted, the effective values ​​are not algebraically additiveable; point-by-point subtraction preserves the phase and waveform relationship, and only the separated effective value can represent the background load itself.

[0041] For each background current window, the effective value is calculated by taking the square root of the average of the sample squares. Then, the maximum value of all complete windows within the same update cycle is taken as the background current observation value for that phase. The background data buffer only writes this observation value and its update time, without mixing the total incoming line observation value into the historical sequence.

[0042] During exponential smoothing, the current background current observation is multiplied by a preset smoothing weight, and the previous smoothing value is multiplied by the value of the weight minus one. The sum of these two values ​​is used as the current smoothing value. Initialization directly uses the first valid observation value, and the smoothing weight is a value greater than zero and not greater than one. The three phases are updated separately according to the same rule.

[0043] When establishing the base value for the upper bound of the background current, the current observation value is compared with the current smoothed value, and the larger value is taken. When the background current suddenly increases, the current observation value directly enters the upper bound; when the background current decreases, the smoothed value gradually releases the allowance. The heater's own power adjustment has been eliminated in the waveform stage and does not drive the background smoothed value to generate corresponding false fluctuations.

[0044] The control response time domain starts from the end of the currently used measurement window and covers the data age up to the measurement time, the next update cycle, and the maximum delay from new instruction communication to execution completion. The measurement host adds these three time periods to obtain the time domain length, and sets the protection range not only based on the communication round-trip time.

[0045] The difference between adjacent background current observations within the historical window is calculated. Positive differences are divided by the time interval between the two observations, and non-positive differences are recorded as zero. The maximum value is taken as the maximum positive rate of change. This rate of change is multiplied by the length of the control response time domain to obtain the rise reserve, which is then added to the largest background baseline value to form the upper bound of the background current.

[0046] The historical window is composed of the most recent consecutive valid update cycle, and the window length is set during initialization. When the historical data is insufficient, the time is discontinuous, or the system has just recovered, the system will not rely on the change rate that has not yet formed to open up the load, but will first continuously collect data until the historical window is complete; during normal operation, the earliest observation is removed and the latest observation is added each time.

[0047] The escalation reserve describes the continuation of historically observed growth rates within the response time domain, and is not considered a physical upper limit for any future sudden load. When the current observed value is detected to exceed the previous upper limit, the current cycle is recalculated and load increases are prohibited, and the heating controller is notified to reduce the load; existing overcurrent protection continues to operate independently.

[0048] When new production loads are continuously connected, the background current observation value is first raised to a larger base value, and then the positive rate of change is updated. When the change stops and the old change leaves the historical window, the increased reserve amount decreases accordingly. The above two time processes correspond to the increments within the current occupancy and response time, respectively, and the same current current is not repeatedly added as an additional reserve amount.

[0049] S2 outputs the upper bound of the background current for each phase, the end time of the data window, and the length of the response time domain. This upper bound is independent of the heating control target, and subsequent changes in the branch target will not reversely modify the historical background observation values.

[0050] S3: Take the larger value between the actual effective value of the current and the upper limit of the current corresponding to the still effective heating command for each branch, and form a branch occupancy envelope that is counted only once.

[0051] Preferably, in step S3, the branch occupancy envelope is formed by phase; the maximum value of the upper limit of the current corresponding to the still valid heating command of the same branch is taken, and compared with the actual effective value of the current of the branch, the larger value is taken; multiple commands of the same branch are not accumulated; the upper limit of the current includes the command setting current and the execution deviation limit. In step S3, when reducing the branch occupancy envelope, the command current upper limit before the reduction is retained until the execution completion feedback of the load reduction command is received, and the effective value of the current of the branch does not exceed the command current upper limit after the load reduction within a consecutive preset number of complete measurement windows after the feedback completion time, then the replaced command is removed.

[0052] Specifically, for each heating branch and each phase, the actual effective value of the current obtained by S1 is read, and all still valid commands for that branch are extracted from the heating command record. The upper limit of the current for each command is formed by adding the set current to the deviation limit of the actuator, which is given by the actuator technical specifications or commissioning verification.

[0053] The upper limit of the current corresponds to the effective value that can occur within a complete power frequency cycle, and is not directly replaced by multiplying the duty cycle by the rated current. For heating equipment that switches on and off in full cycles, the upper limit of the current during the conduction cycle should be registered; the controller ensures that this upper limit is enforceable through current limiting or heating group switching, and the calculation end does not assume that the average power limit is naturally equivalent to the cycle current limit.

[0054] The maximum value of the upper bound of the current for all still valid commands in the same branch is taken, and then the larger value is taken with the actual effective value of the current in that branch to obtain the branch occupancy envelope for that phase. The three phases are calculated separately, and the actual values ​​of different branches are not first aggregated and then combined with all commands to obtain a total maximum value, so as to avoid the under-execution of one branch masking the pending load increase of another branch.

[0055] When a newly submitted load increase is not yet reflected in the current measurement, the upper bound of the command assumes the occupancy of that branch; as the current gradually rises to the set range, the larger value between the actual value and the upper bound of the same command continues to assume the occupancy. There is no other full load increase reservation in the envelope, so an increase in the measured value will not cause the same command to be deducted repeatedly.

[0056] For example, if the actual current of a branch is 80 amps, the original instruction upper limit is 82 amps, and the new instruction upper limit is 102 amps, then the envelope is 102 amps. If the actual current rises to 100 amps, the envelope remains 102 amps, instead of adding 100 amps and 102 amps together. The execution deviation has already entered the instruction upper limit and will not be added again in this step.

[0057] After an instruction is completed, the valid instruction corresponding to the latest setting value is retained as the upper bound for subsequent continuous operation. When an old load instruction is replaced by a larger and already completed instruction, removing the old record does not change the maximum upper bound; duplicate arrival feedback is merged according to the same instruction sequence number and cannot be recreated and occupied.

[0058] During deloading, both the old and new instructions are retained. Even if the upper bound of the new instruction is smaller, the old upper bound should not be deleted simply because the host has sent a deloading message; the actuator may still maintain its original output, and message reception confirmation is not considered as feedback that the deloading process is complete.

[0059] The feedback indicating completion of the load reduction operation should be sent by the heating controller after the output adjustment is finished, carrying the actual completion time. The measurement host only uses complete measurement windows with a start time no earlier than the completion time for counting; windows that span completion times, missing windows, and invalid quality windows cannot be used for release confirmation.

[0060] When the preset number of confirmation windows is reached consecutively, and the effective value of the three-phase branch current in each window does not exceed the upper limit of the new instruction, the old instruction is removed. If any phase exceeds the upper limit, the continuous count is reset to zero; if the confirmation conditions are not met, the old envelope is maintained until confirmation is successful or a timeout occurs.

[0061] Stopping heating is a load reduction operation where the target current is zero. The upper limit of the stop command still includes the residual limit of the actuator corresponding to the measurement. The host releases the old occupancy according to the same feedback and window rules. The actual stop of the branch cannot be replaced by a closed interface or a successful serial port transmission.

[0062] S3 outputs an envelope array indexed by branch and phase, with envelope updates and instruction removal both applied to the same record. Figure 3 The states of "waiting for execution," "waiting for measurement confirmation," and "effective operation" correspond to the states of "instruction already occupied," "old occupation not released," and "new occupation already accepted," respectively.

[0063] S4: Subtract the upper limit of the background current, the metering margin, and the sum of the envelope occupied by each branch from the allowable current for each phase to obtain the residual current. Compare the minimum value of the residual current of each phase with zero and take the larger value to form the real-time residual capacity. Output the new load quota for use by the heating controller.

[0064] Preferably, in step S4, the real-time remaining capacity is applied to the three-phase equal current new load: the minimum value of the remaining current of each phase is compared with zero and the larger value is taken as the new current limit, which is then multiplied by the sum of the effective phase voltages of the three phases and converted into kilovolt-amperes; the new load limit also carries the remaining current of each phase and the effective cutoff time.

[0065] Specifically, the occupancy envelope of all branches is accumulated on each phase. The allowable current is then subtracted sequentially from the upper limit of the background current, the metering margin, and the accumulated value, resulting in a signed residual current. When this residual value is less than zero, its negative value is retained to determine the gap. The absolute value is not taken phase by phase first, nor is the negative phase gap offset by the positive allowance of another phase.

[0066] The minimum value of the three-phase residual current is compared and then the larger value is taken compared to zero to obtain the additional current allowance. If one phase is not allowed to add current, the additional current allowance for the three-phase equal current load is zero; if all three phases have positive allowances, the additional heating current is constrained by the restricted phase corresponding to the minimum value.

[0067] The background current RMS value and the branch current RMS values ​​are added together in this step according to the upper bound, based on the assumption that the waveform RMS values ​​satisfy the triangle inequality. This sum may be greater than the measured RMS value of the total incoming line, indicating a conservative approach rather than claiming that the RMS values ​​of different phase currents can be precisely arithmetically superimposed.

[0068] When the upper bound of S2 is applicable, and the actual current of a branch does not exceed its respective envelope, the effective value of the total current of any phase does not exceed the sum of the upper bound of the background and the envelope of the branch. The positive residual obtained by subtracting from the given measurement deviation using the metering margin can then be used as the conservative boundary for the new current.

[0069] The new capacity of a three-phase load with equal current is calculated by multiplying the new current rating by the sum of the effective phase voltages of the three phases, and then dividing by one thousand to obtain the kilovolt-ampere value. This conversion simultaneously outputs the current rating; the heating controller uses the current rating of each phase as a hard constraint, and cannot simply use the displayed capacity to extrapolate a larger current after a voltage change.

[0070] When active power needs to be displayed, the power factor applicable to the newly added load is read separately and converted separately, and its display field is labeled as kilowatts. This displayed value does not replace the current constraint, nor does it directly treat the transformer's rated kVA as available kilowatts. This embodiment issues a current limit value, without relying on an unknown power factor to complete capacity reservation.

[0071] The output record includes the measurement cycle number, allowable current for each phase, upper limit of background current, sum of envelopes for each phase, three-phase residual current, newly added current allowance, real-time residual capacity, data window end time, and effective cutoff time. The effective cutoff time is the data window end time plus the control response time domain length.

[0072] The supervisory control unit (SCHU) only submits a load increase request if the current time has not exceeded the valid cutoff time and the recorded quality is valid. The time-of-use electricity price or steam demand determines whether a request is made, but does not change the physical current rating generated by S4; when there is no heat demand, no load increase is performed, and the capacity calculation continues to be updated.

[0073] If the residual current of any phase is negative, the main unit outputs zero new capacity and the phase shortfall is calculated, and the heating controller sends a load reduction command. Before the load reduction is confirmed by measurement, S3 remains in its old position, so the requested load reduction amount will not be mistakenly redistributed in the next cycle.

[0074] S4 provides the newly added allowance and the sum of existing envelopes. When you need to view the total allowable allowance for the heating branch, it is displayed separately by subtracting the background upper limit and metering margin from the allowable current. Otherwise, the total allowable allowance for heating is directly added to the current branch target.

[0075] S5: Before issuing a new heating command, include it in the heating command record and update the branch occupancy envelope; based on the execution feedback and the corresponding measurement window, update the still valid heating commands so that the implemented load increase is carried by the actual current, and the load reduction is released after measurement confirmation, and the calculation is repeated.

[0076] Preferably, in step S5, the inclusion of new heating commands and the updating of branch occupancy envelopes are completed within the same critical region. Based on the updated phase occupancy verification of allowable current constraints, if the constraints are met, a record is submitted and a command is sent; if the constraints are not met, the new command is revoked. No new load commands are accepted for the same branch before the previous adjustment command is completed. In step S5, when the synchronous current waveform is missing, the measured data exceeds the effective cutoff time, or the command execution exceeds the delay limit of the control response time domain, the new load quota is set to zero, the occupancy corresponding to the still valid heating command is retained, and a stop heating command is sent. After obtaining the stop feedback and the effective measurement window after the stop, the upper bound of the background current and the branch occupancy envelope are re-established.

[0077] Specifically, the measurement host places the shared state of capacity calculation and command submission under a single critical zone protection. The load increase request includes the branch number, target three-phase current, and the cycle number of the current quota record; after entering the critical zone, the latest background upper limit, envelope, and effective cutoff time are reread, and the old quota carried in the request is not directly approved.

[0078] First, a temporary command upper bound is formed for the request and substituted into the envelope of that branch. Other branches maintain the current envelope. Then, the residual current is recalculated phase by phase according to S4. If all three phases are not negative, the validity period is valid, and there are no uncompleted adjustments in that branch, a new command record and a new envelope are submitted. Then, the critical section is released and sent to the actuator.

[0079] If the request does not meet the phase-by-phase constraint, the temporary record is removed, the existing valid instruction is maintained, and the insufficient quota is returned to the requester. The requester can only resubmit under a subsequent valid quota and cannot bypass the review by sending an instruction first and then recording the quota.

[0080] For requests arriving at different branches almost simultaneously, they are processed in the order they enter the critical section. The remaining balance after processing the first request is used for the review of the next request. New load requests are rejected if the previous instruction of the same branch has not been completed, so as to avoid multiple targets being superimposed out of order in the executor.

[0081] Even if transmission fails or communication confirmation is lost, the new record is still considered valid because it is impossible to rule out that the executor has received the message based solely on the sender's error report. The host queries the execution status using the same sequence number, and does not release its holding or resend the same load with a different sequence number until the query is complete.

[0082] The executor deduplicates instructions by sequence number and prevents older sequence numbers from overwriting newer executed targets. After the host restarts, it first prevents new loads from being added, reads the executor targets and status, and then re-collects the complete historical window; no valid new quotas are output until the recorded and actual statuses match.

[0083] Missing measurement data, asynchronous sampling, exceeding the valid deadline, or excessive execution delay will all render the quota quality invalid, reset the newly added quota to zero, retain the remaining valid quota, and issue a stop heating command. The stop command does not carry out normal load increase quota allocation and is confirmed based on stop feedback and measurement results.

[0084] The controller is configured with a communication failure to stop heating function, which cancels heating enable after its own communication watchdog timer expires. Field overcurrent protection, temperature protection, and liquid level protection are independently retained; when the main unit receives these protection actions, it enters a stop confirmation state, and the command state at the moment of protection triggering cannot be directly interpreted as the current having disappeared.

[0085] Once the stop feedback arrives and the valid measurement window after the stop meets the confirmation conditions, delete the command that was replaced by the stop command, and retain the stop target record. Re-accumulate the complete background history, recalculate the upper bounds and envelopes of each phase, and restore the rated output after configuration, voltage, and data quality checks.

[0086] Figure 3Any execution timeout will trigger a stop confirmation; zero new quota will be maintained until the stop is completed or the historical window is rebuilt. Normal calculations are executed once per update cycle, and each processing session ends after output or failure return, without waiting for indefinite convergence of iterative solutions.

[0087] The host computer stores the current background buffer, smoothing value, and instruction records for each branch, while the actuator only stores its own target, sequence number, and actual execution status. The sampling channel transmits current data, and the actuator transmits status feedback. These two types of information are correlated with the acquisition time and execution time, completing a cycle from measurement, calculation, scheduling to feedback update.

[0088] Example 2 This embodiment provides a complete operational calculation for three heating devices sharing a plant transformer. All current values ​​refer to the primary values ​​on the low-voltage side. It is assumed that the allowable current for each of the three phases is 1000 amperes, the metering margin is 20 amperes per phase, the effective voltage of each phase is 230 volts, the historical window includes the five most recent consecutive effective update cycles, the smoothing weight is 0.5, and the number of load reduction confirmation windows is three.

[0089] Assuming the data age is 0.2 seconds, the update cycle is 1 second, and the maximum delay from communication to execution completion is 0.8 seconds, the control response time domain length is 2 seconds. Each instruction adopts an execution deviation limit of 2 amps; the initial set current of the three branches is 98 amps, therefore the upper limit of each instruction is 100 amps, and the actual current of the three phases does not exceed 100 amps.

[0090] In the initial steady state, the background observation value for phase A is 500 amperes, for phase B it is 470 amperes, and for phase C it is 480 amperes. The five historical observation values ​​remain at their respective levels, with a positive rate of change of zero, and the smoothed value is equal to the observed value. Therefore, the upper bounds of the three-phase background currents are 500, 470, and 480 amperes respectively, and the total envelope of the three branches is 300 amperes per phase.

[0091] S4 outputs a residual current of 180 amps for phase A, 210 amps for phase B, and 200 amps for phase C, with a new current allowance of 180 amps. The sum of the effective phase voltages of the three phases is 690 volts, and the real-time residual capacity is 124.2 kVA; this value represents the new allowance beyond what is already registered.

[0092] At this point, the first heating device requests that the set current be increased from 98 amps to 148 amps, forming a new upper limit of 150 amps. S5 first changes the envelope of the first branch from 100 amps to 150 amps, and the sum of the three-phase envelopes becomes 350 amps. After verification, it still meets the allowable current constraint, then submits the record and issues the instruction.

[0093] During the period before the actuator has completed the load increase, even if the actual current of the first unit is still close to the original level, its envelope remains at 150 amps. At this time, the three-phase residual currents are 130, 160, and 150 amps, and the new quota is 130 amps, or 89.7 kVA. The 50 amps that were previously reserved by the first unit will no longer be allocated to the second unit.

[0094] After the actual current of the first unit rises to 148 amps, the total incoming current changes accordingly, but the original background current is still obtained after removing the synchronous waveform. The envelope of the first unit is taken as the larger value between 148 amps and 150 amps, which is still 150 amps; the sum of the envelopes of the three units is still 350 amps, so there will be no deduction due to the same load being registered first and then measured.

[0095] The first request then drops to 78 amps, corresponding to a new upper limit of 80 amps. If the load reduction is completed and feedback arrives but the three full confirmation windows have not yet been obtained, the old 150 amp upper limit remains, and the new current rating remains 130 amps, without being increased prematurely.

[0096] If, within each of the three complete power frequency windows following the feedback completion time, the current of the first unit in each phase does not exceed 80 amps, its old instruction is removed, and only the new target is retained. If the current update cycle still includes the window before load derating, the actual maximum current value still constrains the envelope; when all complete windows in subsequent update cycles are after load derating and do not exceed 80 amps, the envelope of the first unit is 80 amps, and the other two units are still 100 amps each, with the total envelope becoming 280 amps. The three-phase residual currents are 200, 230, and 220 amps, and the new rating is 200 amps, or 138 kVA.

[0097] Let the five most recent background observations for phase A be 492, 494, 496, 498, and 500 amperes in chronological order, with an interval of 1 second, and a maximum positive rate of change of 2 amperes per second. If the current smoothing value does not exceed 500 amperes, then the rise allowance for phase A is 4 amperes, and the upper limit of the background current is 504 amperes.

[0098] If all other conditions remain unchanged from the previous load reduction completion state, the remaining current of phase A is 196 amps, which is still less than the 230 amps of phase B and the 220 amps of phase C. Therefore, the new current rating is updated to 196 amps, the real-time remaining capacity is 135.24 kVA, and the corresponding capacity difference for background growth reserve is 2.76 kVA.

[0099] The above process separates controlled branch regulation from background growth. The increase or decrease of the load on the first heater only changes the branch envelope, and the continuous increase of the production load in phase A only changes the upper limit of the background and the rise reserve. The two are combined at the current constraints of each phase, rather than jointly driving the smoothing sequence of the total load.

[0100] If the measurement window of the third unit is missing, the host cannot use its previous current waveform to exclude the current total incoming waveform, and immediately outputs zero new quota and enters stop confirmation. At this time, the remaining valid commands of the three units are retained until stop execution feedback, continuous valid measurement windows, and a re-established background history are obtained.

[0101] If another request arrives carrying a quota record earlier than the load reduction completion time, the host will still be within the critical section to read the latest status and make a judgment, and will not directly send the 138 kVA according to the old record. If the effective deadline has passed, the load increase will be rejected, and the host will wait for the new cycle calculation result.

[0102] In this operation simulation, the heating controller receives the current rating of each phase and submits a request based on the heat demand. The calculation host completes the occupancy submission, the actuator completes the current adjustment, the synchronous acquisition unit returns the waveform, and finally the execution feedback and window confirmation close the adjustment process. Figure 1 The cycle Figure 2 Background and branch data and Figure 3 The occupancy status corresponds to each item in the above process.

[0103] Finally, it should be noted that the above content is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A method for dynamically calculating the real-time remaining capacity of a transformer, characterized in that, The method includes: S1: Obtain the synchronous current waveform, allowable current of each phase, and heating command record of the transformer's low-voltage main incoming line and each controllable heating branch; S2: Subtract the synchronous current waveform from each phase-by-phase sampling point to obtain the background current waveform after removing each controllable heating branch, and form the upper bound of the background current covering the control response time domain based on its effective value sequence. S3: Take the larger value between the actual effective value of the current and the upper limit of the current corresponding to the still effective heating command for each branch, and form the branch occupancy envelope that is counted only once. S4: Subtract the upper limit of the background current, the metering margin and the sum of the occupancy envelope of each branch from the allowable current for each phase to obtain the residual current. Compare the minimum value of the residual current of each phase with zero and take the larger value to form the real-time residual capacity. Output the new load quota for the heating controller. S5: Before issuing a new heating command, include it in the heating command record and update the branch occupancy envelope; Based on the execution feedback and the corresponding measurement window update of the still valid heating command, the implemented load increase is carried by the actual current, and the load reduction is released after measurement confirmation, and the calculation is repeated.

2. The method for dynamic calculation of real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S1, the synchronous current waveform is obtained by the acquisition channel with a shared sampling clock. Each channel has the same current direction, phase and transformer ratio, and a complete power frequency cycle with the same start and end time is used as the measurement window. In each update cycle, the maximum value of the effective current value of each measurement window is taken as the actual effective current value.

3. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S1, the allowable current is the minimum value among the rated current of the transformer low-voltage side, the current calculated based on the rated capacity and the upper limit of the allowable phase voltage, and the continuous operation limiting current. The continuous operation limiting current is preset based on the transformer derating conditions and the low-voltage main incoming current limit.

4. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S2, the formation of the upper bound of the background current includes: calculating the effective value of the background current waveform in each measurement window, and taking the maximum value of the same update cycle as the background current observation value. The background current observation value is exponentially smoothed, and the larger value between the current background current observation value and the smoothed value is taken, plus the rise reserve in the control response time domain.

5. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 4, characterized in that, In step S2, the rising reserve is obtained by multiplying the maximum positive rate of change of the background current observation within the historical window by the control response time domain length; The control response time domain length covers the age of the measurement data, the next update cycle, and the maximum delay from instruction communication to execution completion.

6. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S3, the branch occupancy envelope is formed according to phase; For the same branch, the upper limit of the current corresponding to the still valid heating command is taken as the maximum value, and compared with the actual effective value of the current of the branch, the larger value is taken. Multiple commands of the same branch are not accumulated. The upper limit of the current includes the command-set current and the execution deviation limit.

7. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 6, characterized in that, In step S3, when reducing the occupancy envelope of the branch, the upper limit of the command current before the reduction is retained until the execution completion feedback of the load reduction command is received, and the effective value of the branch current does not exceed the upper limit of the command current after the load reduction within a preset number of complete measurement windows after the feedback completion time, then the replaced command is removed.

8. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S4, the real-time remaining capacity is applied to the three-phase equal current new load: the minimum value of the remaining current of each phase is compared with zero and the larger value is taken as the new current limit, which is then multiplied by the sum of the effective phase voltages of the three phases and converted into kilovolt-amperes. The newly added load quota also carries the remaining current of each phase and the effective cutoff time.

9. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S5, the inclusion of the new heating command and the update of the branch occupancy envelope are completed in the same critical region. Based on the updated phase occupancy review allowable current constraints, if the constraints are met, the record is submitted and the command is sent; if the constraints are not met, the new command is revoked. No new load increase commands will be accepted for the same branch until the previous adjustment command is completed.

10. The method for dynamically calculating the real-time remaining capacity of a transformer according to claim 1, characterized in that, In step S5, when the synchronous current waveform is missing, the measurement data exceeds the effective cutoff time, or the command execution exceeds the delay limit of the control response time domain, the newly added load quota is set to zero, the occupancy corresponding to the still valid heating command is retained, and a stop heating command is sent. After obtaining the stop feedback and the effective measurement window after the stop, the upper limit of the background current and the branch occupancy envelope are re-established.