A power distribution network fault location system and method based on multi-source transient information

By screening and classifying anchor points, traveling wave matching and deviation processing, and combining distributed generation phase-locked loop verification, the problems of time synchronization error and insufficient fusion of multi-source information in distribution network fault location are solved, and high-precision and stable fault location is achieved.

CN123136267APending Publication Date: 2026-11-20NANYANG POWER SUPPLY COMPANY OF STATE GRID HENAN ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611080784.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-20
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

In existing power distribution network fault location technologies, inaccurate location results are caused by terminal time synchronization errors and insufficient fusion of multi-source transient information. There is a lack of effective verification methods, making it difficult to accurately locate fault sections, especially under conditions of clock drift and complex electromagnetic environments.

Method used

By selecting effective anchor points, confidence levels are established based on waveform stability and harmonic interference levels. By combining traveling wave matching and deviation processing, a partitioned deviation feature matrix is ​​constructed. Distributed power supply phase-locked loop verification is introduced to establish a self-optimizing timing reference and dynamically correct timing errors.

Benefits of technology

It significantly improves the accuracy and stability of fault location, suppresses the influence of data distortion at individual measurement points, ensures the reliability and credibility of the location results, and can detect and correct hidden timing deviations caused by model mismatch or parameter drift.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123136267A_ABST
    Figure CN123136267A_ABST
Patent Text Reader

Abstract

The application discloses a power distribution network fault positioning system and method based on multi-source transient information, and relates to the technical field of fault positioning.The method comprises the following steps: acquiring a power frequency zero point, screening effective anchor points according to terminal topology levels and historical clock drift statistical values, grading based on waveform stability and harmonic interference degree, and outputting a confidence level label anchor point set; matching wave head anchor points, downgrading matching and reversely adjusting levels when the deviation exceeds the historical deviation statistical range; generating characteristic values from the matching deviation, combining anchor point confidence levels, wave head signal-to-noise ratios and measuring point topology positions, and constructing a partition deviation characteristic matrix; verifying in a time difference allowable interval according to line physical parameters, compressing and correcting the deviation when the deviation exceeds the allowable interval, updating the matching determination threshold, and marking abnormal measuring points; adjusting the drift parameter to regenerate the anchor point set when the branch abnormal proportion exceeds the critical value; stably outputting the corrected time scale of the compliance or abnormal set; extracting a DG phase-locked loop power frequency phase angle time scale for one-way verification, and triggering an additional verification cycle when the limit is exceeded.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of fault location technology, specifically a distribution network fault location system and method based on multi-source transient information. Background Technology

[0002] In the field of distribution network fault location, two- or multi-terminal ranging methods based on traveling wave and power frequency transient information have become the mainstream technical approach. The core premise of this method is that high-precision time synchronization must be achieved between distributed monitoring terminals to ensure accurate comparability of the timescales at wavefront or zero-crossing points. Currently, time synchronization of distribution network terminals mainly relies on external time synchronization systems. However, the operating environment of distribution networks is complex, with a large number of terminals distributed over a wide area. External time synchronization signals are easily blocked, interfered with, or experience device-level clock drift, leading to relative deviations between the timescales of each terminal that are difficult to measure directly. When the timescales of some terminals shift as a whole due to clock drift, traditional methods often lack effective means to identify and correct such systematic timing errors, frequently resulting in misjudgment or failure to locate the fault section. Due to variations in electromagnetic environments and signal attenuation levels among different terminals, the waveform quality of their acquired zero-crossing points and traveling wavefronts varies considerably. Existing methods, when fusing this multi-source transient information, typically assign equal or fixed levels of confidence to data from each measurement point, failing to dynamically reflect the actual reliability of each information source under fault conditions. Furthermore, existing methods generally lack independent third-party verification mechanisms separate from the main positioning system. The reliability of the positioning results depends on the self-consistency of the internal algorithm; when model mismatch or parameter drift occurs within the system, there is a lack of external objective evidence to verify and correct the output results. Summary of the Invention

[0003] The purpose of this invention is to provide a distribution network fault location system and method based on multi-source transient information to solve the problems raised in the prior art.

[0004] To achieve the above objectives, the present invention provides the following technical solution: a method for fault location in a distribution network based on multi-source transient information, the method comprising: S100: Obtain the zero-crossing time of the power frequency voltage and current of each monitoring terminal, filter effective anchor points according to the terminal topology level and historical clock drift statistics, classify the effective anchor points based on waveform stability and harmonic interference, and output the effective original anchor point time series set with confidence level label. S200. Match the high-frequency traveling wave head time with the effective anchor point. If the matching deviation exceeds the statistical range of the historical deviation of the measurement point, downgrade the anchor point level and perform a second matching. Adjust the anchor point confidence level in reverse according to the matching result. S300. Generate deviation feature values ​​based on the matching deviation of each measurement point, and construct a partitioned deviation feature matrix by combining the confidence level of the anchor point, the signal-to-noise ratio of the wavefront and the topological position of the measurement point. S400: Set the allowable time difference interval for measurement points based on the physical parameters of the line, and iteratively verify the deviation matrix; perform constraint compression correction on deviations that exceed the allowable time difference interval, and update the matching judgment threshold based on the correction amount; mark measurement points that cannot be corrected by constraint compression as abnormal measurement points; when the proportion of abnormal measurement points in the same topology branch exceeds the proportion threshold, adjust the drift parameters and regenerate the anchor point set; when all deviations fall into the allowable time difference interval or the abnormal measurement point set stabilizes after multiple rounds, stop the loop and output the corrected time scale of each measurement point. S500: Extract the power frequency phase angle time scale of the distributed power grid connection point phase-locked loop output, perform one-way matching verification on the corrected time scale, if all comparison deviations fall within the time difference tolerance range, the verification passes and the corrected timing data is output; if any comparison deviation exceeds the limit, an additional verification cycle is triggered. S600. Based on the verified corrected timing data, obtain the arrival time of the initial traveling wave front of the fault after correction for each monitoring terminal, combine it with the physical parameters of the line, complete the fault location calculation, and output the fault location result.

[0005] According to the above scheme, step S100 includes: S110. Extract the voltage zero-crossing time and current zero-crossing time of each monitoring terminal in multiple power frequency cycles before and after the fault occurrence time, and generate the initial zero-crossing time sequence set of each monitoring terminal. S120. The initial zero-crossing time of each monitoring terminal is compared with the historical clock drift statistics of the corresponding terminal. Zero-crossing points with deviations exceeding the historical drift fluctuation range are eliminated. The remaining zero-crossing points are sorted according to the terminal topology level. The arrival time difference of the same zero-crossing point between adjacent level terminals is calculated. The power frequency phase delay of the same zero-crossing point propagating along the line to adjacent level terminals is used as the synchronization judgment benchmark. Zero-crossing points with time differences exceeding the allowable deviation range corresponding to the benchmark are eliminated, and valid original anchor points are generated. S130. For each valid original anchor point, determine the degree of symmetry of the waveform within one-quarter of the power frequency cycle before and after the zero crossing point, and generate a waveform stability label; determine the proportion of high-frequency harmonic components of the voltage and current waveforms within one-eighth of the power frequency cycle before and after the zero crossing point, and generate a harmonic interference degree label. S140. Based on the combination of waveform stability label and harmonic interference level label, divide each effective original anchor point into high confidence level, medium confidence level and low confidence level, and output the effective original anchor point time series set with initial confidence level label.

[0006] According to the above scheme, step S200 includes: S210. Extract the initial traveling wave head time of the fault from the high-frequency data stream of each monitoring terminal; S220. Match the current traveling wave front time of the measurement point with the nearest high-confidence anchor point in the effective original anchor point time series set that is before the traveling wave front time and is close to it. Calculate the time interval between the traveling wave front time and the matched anchor point as the matching deviation. S230. Compare the matching deviation with the historical matching deviation statistics accumulated by the measuring point under normal operating conditions; if the matching deviation does not exceed the historical matching deviation statistics range, the matching is determined to be successful. S240. If the matching deviation exceeds the historical matching deviation statistical range, abandon the current high confidence level anchor point and perform a second matching on the time axis to a lower confidence level anchor point that is farther away from the time of the traveling wave head. S250. If the second match is successful, the confidence level of the matched anchor point is lowered by one level; if the second match is still unsuccessful, a mapping failure flag is output; when the first match is successful, the current confidence level of the corresponding anchor point remains unchanged; when the second match is successful, the confidence level of the anchor point used is lowered; and the confidence level of the valid anchor point is adjusted in reverse according to the matching result.

[0007] According to the above scheme, step S300 includes: S310. According to the feeder topology branch affiliation label, the matching deviation of each measuring point is assigned to the deviation dataset of the corresponding branch. S320. Calculate the interquartile range for the matching deviation of all measurement points within the same branch, remove the deviation data points that exceed the outlier determination interval determined based on the interquartile range, and calculate the median value of the remaining matching deviation after removing outliers, which is used as the branch representative deviation feature of the branch. S330. Generate a deviation confidence weight for each measuring point. The deviation confidence weight is jointly determined by the confidence level of the anchor point currently used by the measuring point, the signal-to-noise ratio level at the moment of capturing the traveling wave front of the measuring point, and the proximity of the measuring point to the predicted fault source section in the feeder topology. S340. Construct a partitioned unified deviation feature matrix by combining the matching deviation values ​​of each measuring point, the branch representative deviation characteristics, the deviation confidence weight, and the measuring point identification and topological branch attribution information.

[0008] According to the above scheme, step S400 includes: S410. Calculate the theoretical propagation delay of each adjacent measuring point pair based on the physical parameters of the line between adjacent monitoring points, and set the corresponding time difference tolerance interval based on the theoretical propagation delay of each adjacent measuring point pair. S420. Substitute the corrected time scale of each measuring point in the partition deviation feature matrix into each adjacent measuring point pair for verification, and calculate the deviation between the measured time difference and the theoretical propagation delay; perform constraint compression correction on the deviation that exceeds the corresponding time difference allowable interval, so that the corrected time difference falls within the time difference allowable interval, and record the correction offset and the degree of deviation; according to the degree of deviation, divide the measuring points into measuring points that pass the constraint compression correction and abnormal measuring points that cannot pass the constraint compression correction. S430. Based on the correction offset of each measuring point, update the matching judgment threshold of the corresponding measuring point; S440. When more than half of the measurement points in the same topology branch are marked as abnormal measurement points in two consecutive loops, it is determined that there is an overall temporal offset of the anchor points of the branch. The drift weight parameters of all terminals of the branch are increased, and the effective original anchor point set is re-extracted. S450. Determine whether the loop termination condition is met in each round. The termination condition is that the corrected time difference of all adjacent measurement points falls into the corresponding time difference allowable range, or the abnormal measurement point set no longer increases or decreases in multiple consecutive loops. Stop the loop when any termination condition is met, and output the current corrected deviation feature matrix.

[0009] According to the above scheme, step S500 includes: S510. Extract the phase angle change trajectory of the power frequency voltage output from the phase-locked loop at the grid connection point of the distributed power source, read the zero-crossing time stamps in multiple power frequency cycles before and after the fault occurrence time, and form a DG-side time stamp reference sequence independent of the terminal sampling data. S520. Perform a one-way matching comparison between the corrected time scales of each measuring point and the time scale reference sequence on the DG side. Determine the reference time scale corresponding to the corrected time scale of each measuring point according to the principle of the nearest neighbor of the time axis, and calculate the comparison deviation. S530. If the comparison deviation of all measuring points falls within the allowable time difference range of the corresponding measuring points, the verification is deemed to be successful, and the corrected time synchronization timing data is output. S540. If the measurement point comparison deviation exceeds the corresponding time difference tolerance range, an additional verification loop is triggered. This loop is a supplementary topology verification loop. During execution, the matching deviation value of the measurement point that exceeds the tolerance range is replaced with the corresponding comparison deviation. A constraint compression correction is performed based on the updated partition deviation feature matrix. After the supplementary loop is completed, a single comparison verification is performed. The DG side timescale reference sequence is only used for verification and judgment and does not participate in the correction calculation of the deviation value.

[0010] A distribution network fault location system based on multi-source transient information, the system includes: an anchor point classification module, a traveling wave matching module, a deviation processing module, a DG verification module, and a timing output module; The anchor point classification module is used to obtain the zero-crossing time of the power frequency voltage and current of each monitoring terminal, filter the effective anchor points according to the terminal topology level and historical clock drift statistics, classify the effective anchor points based on waveform stability and harmonic interference, and output the effective original anchor point time series set with confidence level label. The traveling wave matching module is used to match the high-frequency traveling wave head time with the effective anchor point. If the matching deviation exceeds the statistical range of the historical deviation of the measurement point, the anchor point level is downgraded and a second matching is performed. The anchor point confidence level is adjusted in reverse according to the matching result. The deviation processing module is used to remove outliers by feeder branch based on the matching deviation of each measuring point, calculate the representative deviation characteristics of the branch, and construct a partitioned deviation feature matrix by combining the anchor point confidence level, wavefront signal-to-noise ratio, and measuring point topology location to assign confidence weights. It also sets the allowable time difference interval based on the line physical parameters and iteratively verifies the deviation matrix. Deviations exceeding the allowable interval are constrained and compressed for correction, and the matching judgment threshold is updated based on the correction amount. When the proportion of abnormal measuring points within the same topology branch exceeds the critical proportion value, the drift parameters are adjusted and anchor point regeneration is triggered. When the termination condition is met, the corrected timestamps of each measuring point are output. The DG verification module is used to extract the power frequency phase angle time scale of the phase-locked loop output of the distributed power source grid connection point as an independent reference sequence and perform one-way verification on the corrected time scale. When the verification fails, the deviation characteristic value of the out-of-tolerance measurement point is replaced with the comparison deviation, and the deviation processing module is driven to perform supplementary constraint compression correction. The independent reference sequence is only used for verification and does not participate in the correction calculation. The timing output module is used to output corrected time-synchronized timing data after verification, serving as a unified timing reference for fault traveling wave location.

[0011] According to the above scheme, the anchor point grading module includes a zero-crossing screening unit and a quality grading unit; The zero-crossing screening unit is used to compare the initial zero-crossing point of each terminal with the historical clock drift statistics, eliminate abnormal points, and perform adjacent level verification based on the power frequency phase delay between topology levels to generate valid original anchor points. The quality rating unit is used to generate waveform stability labels based on the symmetry of the waveform before and after the zero crossing, generate harmonic interference level labels based on the proportion of high-frequency harmonic components, and comprehensively classify confidence levels.

[0012] According to the above scheme, the deviation processing module includes a matrix construction unit, a cyclic correction unit, and a drift adjustment unit; The matrix construction unit is used to collect and match deviations according to feeder branches. It removes outliers by using the interquartile range method and takes the median value as the representative deviation feature of the branch. At the same time, it generates a confidence weight for the deviation of each measuring point and constructs a partitioned deviation feature matrix. The loop correction unit is used to perform time difference verification and constraint compression correction, dynamically update the matching judgment threshold and mark abnormal measurement points, and determine the loop termination condition. The drift adjustment unit is used to monitor the proportion of abnormal measurement points in a branch. When the limit is exceeded, it determines that there is an overall temporal offset in the branch, increases the drift weight parameters of all terminals in the branch, and triggers anchor point regeneration.

[0013] According to the above scheme, the DG verification module includes a time stamp extraction unit and a one-way verification unit; The time stamp extraction unit is used to extract the zero-crossing time stamp of the power frequency phase angle from the phase-locked loop at the grid connection point of the distributed power source, forming a third-party reference sequence independent of the terminal sampling data; The one-way verification unit is used to perform one-way comparison. When the verification fails, the deviation characteristic value of the out-of-tolerance measurement point is replaced with the comparison deviation, triggering the deviation processing module to perform supplementary constraint compression correction.

[0014] Compared with the prior art, the beneficial effects of the present invention are: 1. The invention establishes a self-optimizing closed loop for timing reference by constructing hierarchical confidence anchor points through multi-dimensional screening of power frequency zero-crossing points and waveform quality classification, combined with secondary matching of traveling wave classification and reverse updating of anchor point confidence levels; it significantly suppresses timing synchronization errors, provides a high-precision unified timing reference for traveling wave fault location, and reduces fault location deviation; 2. This invention constructs a partitioned deviation feature matrix, removes outlier deviation data, and uses the branch median as the representative deviation feature. At the same time, it assigns a confidence weight to the deviation of each measuring point, which is jointly determined by the anchor confidence level, wavefront signal-to-noise ratio, and topological position. This enables the deviation correction and positioning solution to suppress the influence of severe distortion of individual measuring point data and improve the statistical stability of the final positioning result. 3. This invention introduces the power frequency phase angle timescale output by the phase-locked loop at the grid connection point of the distributed power source as a completely independent reference sequence, adding an external objective verification layer. This can detect and trigger the correction of hidden timing deviations caused by model mismatch or parameter drift, ensuring the reliability and credibility of the final output timescale sequence. Attached Figure Description

[0015] Figure 1 This is a flowchart illustrating the steps of a power distribution network fault location method based on multi-source transient information according to the present invention. Figure 2 This is a schematic diagram of the structure of a power distribution network fault location system based on multi-source transient information according to the present invention. Detailed Implementation

[0016] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0017] Example: Figures 1-2 As shown, the present invention provides a technical solution, a method for fault location in a distribution network based on multi-source transient information, the method comprising: S100: Obtain the zero-crossing time of the power frequency voltage and current of each monitoring terminal, filter effective anchor points according to the terminal topology level and historical clock drift statistics, classify the effective anchor points based on waveform stability and harmonic interference, and output the effective original anchor point time series set with confidence level label. S200. Match the high-frequency traveling wave head time with the effective anchor point. If the matching deviation exceeds the statistical range of the historical deviation of the measurement point, downgrade the anchor point level and perform a second matching. Adjust the anchor point confidence level in reverse according to the matching result. S300. Generate deviation feature values ​​based on the matching deviation of each measurement point, and construct a partitioned deviation feature matrix by combining the confidence level of the anchor point, the signal-to-noise ratio of the wavefront and the topological position of the measurement point. S400: Set the allowable time difference interval for measurement points based on the physical parameters of the line, and iteratively verify the deviation matrix; perform constraint compression correction on deviations that exceed the allowable time difference interval, and update the matching judgment threshold based on the correction amount; mark measurement points that cannot be corrected by constraint compression as abnormal measurement points; when the proportion of abnormal measurement points in the same topology branch exceeds the proportion threshold, adjust the drift parameters and regenerate the anchor point set; when all deviations fall into the allowable time difference interval or the abnormal measurement point set stabilizes after multiple rounds, stop the loop and output the corrected time scale of each measurement point. S500: Extract the power frequency phase angle time scale of the distributed power grid connection point phase-locked loop output, perform one-way matching verification on the corrected time scale, if all comparison deviations fall within the time difference tolerance range, the verification passes and the corrected timing data is output; if any comparison deviation exceeds the limit, an additional verification cycle is triggered. S600. Based on the verified corrected timing data, obtain the arrival time of the initial traveling wave front of the fault after correction for each monitoring terminal, combine it with the physical parameters of the line, complete the fault location calculation, and output the fault location result.

[0018] Specifically, step S100 includes: S110. Extract the voltage zero-crossing time and current zero-crossing time of each monitoring terminal in multiple power frequency cycles before and after the fault occurrence time, and generate the initial zero-crossing time sequence set of each monitoring terminal. S120. The initial zero-crossing time of each monitoring terminal is compared with the historical clock drift statistics of the corresponding terminal. Zero-crossing points with deviations exceeding the historical drift fluctuation range are eliminated. The remaining zero-crossing points are sorted according to the terminal topology level. The arrival time difference of the same zero-crossing point between adjacent level terminals is calculated. The power frequency phase delay of the same zero-crossing point propagating along the line to adjacent level terminals is used as the synchronization judgment benchmark. Zero-crossing points with time differences exceeding the allowable deviation range corresponding to the benchmark are eliminated, and valid original anchor points are generated. S130. For each valid original anchor point, determine the degree of symmetry of the waveform within one-quarter of the power frequency cycle before and after the zero crossing point, and generate a waveform stability label; determine the proportion of high-frequency harmonic components of the voltage and current waveforms within one-eighth of the power frequency cycle before and after the zero crossing point, and generate a harmonic interference degree label. S140. Based on the combination of waveform stability label and harmonic interference level label, divide each effective original anchor point into high confidence level, medium confidence level and low confidence level, and output the effective original anchor point time series set with initial confidence level label.

[0019] Specifically, in this embodiment, the voltage zero-crossing and current zero-crossing times of each monitoring terminal are extracted for three power frequency cycles before and after the fault occurrence. The power frequency signal is 50Hz, and the duration of a single power frequency cycle is 20ms, corresponding to a collection duration of 60ms before and after the fault occurrence, generating an initial zero-crossing time sequence set for each monitoring terminal. The initial zero-crossing times of each terminal are compared with the historical clock drift statistics of the corresponding terminal. The historical clock drift fluctuation range is determined based on three times the standard deviation of the clock deviation data recorded by the terminal over the past seven consecutive days. For example, if the historical clock drift fluctuation range of a terminal is ±0.8ms, zero-crossing times with deviations exceeding this range are removed. The retained zero-crossing times are sorted according to the terminal topology hierarchy, and the arrival time difference of the same zero-crossing point between adjacent level terminals is calculated. The propagation speed of the power frequency zero-crossing point along the line is taken as a typical value for overhead lines, approximately 2.98 × 10⁻⁶. 8If the line length between adjacent level terminals is 6km, the corresponding theoretical power frequency phase delay is approximately 20μs, which is used as the synchronization judgment benchmark. The allowable deviation range is set to ±5μs based on the line length measurement error and the slight changes in power frequency wave velocity through statistical analysis. Zero-crossing points with time differences exceeding this allowable deviation range are eliminated, and finally, effective original anchor points are generated. Waveform data of one-quarter of the power frequency cycle before and after the zero-crossing point are taken, and the difference ratio between the positive half-cycle waveform area and the negative half-cycle waveform area in this period is calculated. The threshold of the difference ratio is determined based on the statistical results of a large number of field fault waveform recordings: the difference ratio of normal zero-crossing waveform symmetry is usually less than 5%, slight distortion is between 5% and 15%, and severe distortion exceeds 15%. Accordingly, a difference ratio of less than 5% is marked as... High stability is defined as 5%-15% as medium stability and greater than 15% as low stability. Waveform data from one-eighth of the power frequency cycle before and after the zero-crossing point are taken, and the ratio of the amplitude of the third and higher high-frequency harmonics to the fundamental frequency amplitude is calculated. The ratio threshold is set based on the power system harmonic limit standard and statistical analysis of zero-crossing detection error from a large amount of field waveform data. A ratio less than 3% is marked as weak interference, 3%-10% as medium interference, and greater than 10% as strong interference. Based on the two types of labels, high stability plus weak interference corresponds to a high confidence level, high stability plus medium interference, and medium stability plus weak interference correspond to a medium confidence level, and other combinations correspond to a low confidence level. The output is a set of valid original anchor point time series with initial confidence level labels. This is only an example and is not a limitation.

[0020] Specifically, step S200 includes: S210. Extract the initial traveling wave head time of the fault from the high-frequency data stream of each monitoring terminal; S220. Match the current traveling wave front time of the measurement point with the nearest high-confidence anchor point in the effective original anchor point time series set that is before the traveling wave front time and is close to it. Calculate the time interval between the traveling wave front time and the matched anchor point as the matching deviation. S230. Compare the matching deviation with the historical matching deviation statistics accumulated by the measuring point under normal operating conditions; if the matching deviation does not exceed the historical matching deviation statistics range, the matching is determined to be successful. S240. If the matching deviation exceeds the historical matching deviation statistical range, abandon the current high confidence level anchor point and perform a second matching on the time axis to a lower confidence level anchor point that is farther away from the time of the traveling wave head. S250. If the second match is successful, the confidence level of the matched anchor point is lowered by one level; if the second match is still unsuccessful, a mapping failure flag is output; when the first match is successful, the current confidence level of the corresponding anchor point remains unchanged; when the second match is successful, the confidence level of the anchor point used is lowered; and the confidence level of the valid anchor point is adjusted in reverse according to the matching result.

[0021] Specifically, in step S210, the initial traveling wave front time of the fault is extracted from the high-frequency data stream of each monitoring terminal. In this embodiment, the wavelet modulus maxima method is used for extraction. The high-frequency transient current signal is decomposed into multiple scales using wavelet decomposition to obtain wavelet coefficients at each scale. The modulus maxima points of the wavelet coefficients at each decomposition scale are calculated. The moment when the first abrupt change of the modulus maxima occurs is selected as the arrival time of the initial traveling wave front of the fault. The nearest high-confidence anchor point on the time axis before the current measuring point's traveling wave front time is selected, and the time interval between the traveling wave front time and the matching anchor point time is calculated as the matching deviation. The matching deviation formula is: Δt = t w -t a Where Δt is the single-point matching deviation; t w t represents the arrival time of the traveling wavefront. a To match the anchor point's timing, the matching deviation is compared with the historical matching deviation statistical range accumulated under normal operating conditions of the measurement point. The historical matching deviation statistical range is determined based on the statistical distribution of the matching deviation between the traveling wave front and the corresponding anchor point in multiple past fault or disturbance events of the measurement point, taking the mean ± 3 times the standard deviation. For example, the historical deviation statistical range of a certain measurement point is ±1200μs. If the matching deviation does not exceed this range, the first match is considered successful. If the matching deviation exceeds the historical deviation statistical range, the current high-confidence anchor point is abandoned, and the nearest lower-confidence anchor point is selected along the earlier direction of the time axis for a second match. The anchor point confidence level is adjusted in reverse according to the matching result. When the first match is successful, the current confidence level of the corresponding anchor point remains unchanged. When the second match is successful, the confidence level of the anchor point used in this match is lowered by one level. If the second match is still unsuccessful, a mapping failure flag is output. All level adjustment results are synchronously updated to the valid original anchor point time series set. This is only an example and is not a limitation.

[0022] Specifically, step S300 includes: S310. According to the feeder topology branch affiliation label, the matching deviation of each measuring point is assigned to the deviation dataset of the corresponding branch. S320. Calculate the interquartile range for the matching deviation of all measurement points within the same branch, remove the deviation data points that exceed the outlier determination interval determined based on the interquartile range, and calculate the median value of the remaining matching deviation after removing outliers, which is used as the branch representative deviation feature of the branch. S330. Generate a deviation confidence weight for each measuring point. The deviation confidence weight is jointly determined by the confidence level of the anchor point currently used by the measuring point, the signal-to-noise ratio level at the moment of capturing the traveling wave front of the measuring point, and the proximity of the measuring point to the predicted fault source section in the feeder topology. S340. Construct a partitioned unified deviation feature matrix by combining the matching deviation values ​​of each measuring point, the branch representative deviation characteristics, the deviation confidence weight, and the measuring point identification and topological branch attribution information.

[0023] Specifically, based on the feeder topology branch affiliation label, the matching deviations of all measuring points are assigned to the deviation dataset of the corresponding branch. For example, a feeder may have 3 topology branches, each branch corresponding to 4 monitoring points. The deviations of each measuring point are grouped and stored according to the branch label. The branch deviation data is processed using the interquartile range method. The matching deviations of n measuring points within the same branch are arranged in ascending order of value to obtain an ordered sequence x1, x2, ..., xn. The lower quartile Q1 is calculated, which is the value corresponding to the 25th quartile position in the ordered sequence. The upper quartile Q3 is calculated, which is the value corresponding to the 7th quartile position in the ordered sequence. The value corresponding to the 5th percentile position; calculate the interquartile range (IQR) using the formula: IQR = Q3 - Q1; where IQR is the interquartile range; Q3 is the upper quartile; Q1 is the lower quartile; determine the outlier detection interval as [Q1 - 1.5 × IQR, Q3 + 1.5 × IQR], and remove outlier data points that exceed this interval; calculate the median value M of the remaining matching bias after removing outliers, and use this median value as the branch representative bias feature of this branch; generate a bias confidence weight for each measurement point, the weight being jointly determined by three factors; each coefficient is obtained through... The error contribution analysis of historical fault samples determined that, based on a large number of recorded waveforms with known actual fault locations, the influence ratio of three factors on the final timing synchronization error was quantified: anchor confidence level, wavefront signal-to-noise ratio (SNR), and topological proximity. After normalization, the coefficient values ​​for each level were obtained: anchor confidence level coefficient w1: 1.0 for high confidence level, 0.7 for medium confidence level, and 0.4 for low confidence level; wavefront SNR coefficient w2: 1.0 for wavefront SNR greater than 20dB, 0.6 for 10dB-20dB, and 0 for less than 10dB. 0.3; Topological proximity coefficient w3: 1.0 for the measurement point located within the estimated fault source segment, 0.7 for the measurement point located in an adjacent segment, and 0.4 for the measurement point located between two or more segments; The final deviation confidence weight calculation formula is: W=w1×w2×w3; where W is the single measurement point deviation confidence weight; Taking the measurement point as the row unit, the matching deviation value of each measurement point, the branch representative deviation feature of the branch to which it belongs, the deviation confidence weight, the measurement point identifier, and the topological branch attribution information are integrated by column to form a partitioned unified deviation feature matrix. This is only an example and is not a limitation.

[0024] Specifically, step S400 includes: S410. Calculate the theoretical propagation delay of each adjacent measuring point pair based on the physical parameters of the line between adjacent monitoring points, and set the corresponding time difference tolerance interval based on the theoretical propagation delay of each adjacent measuring point pair. S420. Substitute the corrected time scale of each measuring point in the partition deviation feature matrix into each adjacent measuring point pair for verification, and calculate the deviation between the measured time difference and the theoretical propagation delay; perform constraint compression correction on the deviation that exceeds the corresponding time difference allowable interval, so that the corrected time difference falls within the time difference allowable interval, and record the correction offset and the degree of deviation; according to the degree of deviation, divide the measuring points into measuring points that pass the constraint compression correction and abnormal measuring points that cannot pass the constraint compression correction. S430. Based on the correction offset of each measuring point, update the matching judgment threshold of the corresponding measuring point; S440. When more than half of the measurement points in the same topology branch are marked as abnormal measurement points in two consecutive loops, it is determined that there is an overall temporal offset of the anchor points of the branch. The drift weight parameters of all terminals of the branch are increased, and the effective original anchor point set is re-extracted. S450. Determine whether the loop termination condition is met in each round. The termination condition is that the corrected time difference of all adjacent measurement points falls into the corresponding time difference allowable range, or the abnormal measurement point set no longer increases or decreases in multiple consecutive loops. Stop the loop when any termination condition is met, and output the current corrected deviation feature matrix.

[0025] Specifically, the theoretical propagation delay of the traveling wave for adjacent measuring point pairs is calculated using the formula: τ = L / v; where τ is the theoretical propagation delay of the traveling wave for adjacent measuring point pairs; L is the line length between adjacent measuring points; and v is the propagation speed of the traveling wave, which is determined based on the actual line type and parameter manual. For example, for overhead lines, the propagation speed is 2.98 × 10⁻⁶. 8 m / s, cable lines take 1.8×10 8 m / s; take 5% of the theoretical time delay as the allowable deviation Δτ. This percentage is determined based on the error propagation analysis of the line length measurement error and wave velocity uncertainty, and the corresponding allowable time difference interval is [τ-Δτ, τ+Δτ]; substitute the corrected time scale of each measuring point in the partition deviation characteristic matrix into the adjacent measuring point pair for verification. Before verification, use the branch representative deviation characteristics of each branch to perform overall translation calibration of the corrected time scale of all measuring points in the branch to eliminate branch-level system deviation; calculate the measured time difference t. m Then calculate the deviation e=t between the measured time difference and the theoretical propagation time delay. m -τ; If the deviation exceeds the corresponding time difference tolerance range, perform constraint compression correction; the corrected time difference formula is: t m =τ + k×e; where t m 't' represents the corrected measured time difference; τ represents the theoretical propagation delay; k represents the compression coefficient, which is optimized through simulation experiments to ensure convergence without causing excessive jumps. In this embodiment, the value is 0.3; e represents the measured deviation; if the time difference t after one compression correction... mIf the time difference still does not fall within the allowable range, the time difference corrected in the previous round is used as the new measured time difference. The formula is then repeatedly applied for iterative compression until the time difference falls within the allowable range or the number of iterations reaches a preset upper limit, which is set to 5 times in this embodiment. If the time difference still cannot fall within the allowable range after reaching the upper limit, the measurement point is marked as an abnormal measurement point. Each correction records the correction offset Δe=t. m '-t m The degree of deviation is considered; based on the degree of deviation and the anomaly marking results, the measurement points are classified into types, i.e., those that finally fall into the allowable range after constraint compression correction are corrected measurement points, and those that cannot fall into the range are abnormal measurement points; based on the correction offset of each measurement point, the matching judgment threshold of the corresponding measurement point is updated. The updated threshold formula is: T'=T+α×Δe; where T' is the updated matching judgment threshold; T is the original matching judgment threshold; α is the threshold update coefficient, which is set to 0.2 according to the slow change characteristics of clock drift, using the smoothing filtering idea to avoid drastic fluctuations in the threshold; Δe is the correction offset; when more than half of the measurement points in the same topology branch are marked as abnormal measurement points in two consecutive loops, it is determined that there is an overall timing offset of the anchor point of the branch, and the drift weight of all terminals of the branch is increased. The parameter is used as an amplification factor for the historical clock drift tolerance range. The initial value of the drift weight parameter is 1.0, and the step size is increased by 0.3. This step size is determined experimentally based on the relationship between the severity of the overall drift in the historical branch and the required relaxation of the screening conditions. For example, increasing the initial value from 1.0 to 1.3 corresponds to a 30% increase in the screening tolerance. After that, the effective original anchor point set is re-extracted. The loop termination condition is determined round by round. The loop terminates when the corrected time difference of all adjacent measurement point pairs falls into the corresponding time difference tolerance range, or when the abnormal measurement point set no longer increases or decreases in multiple consecutive loops. The number of consecutive rounds is verified based on a large number of simulations and actual fault data. Generally, 3 rounds are sufficient to reach a stable state. After the loop terminates, the current corrected deviation feature matrix is ​​output. This is only an example and is not a limitation.

[0026] Specifically, step S500 includes: S510. Extract the phase angle change trajectory of the power frequency voltage output from the phase-locked loop at the grid connection point of the distributed power source, read the zero-crossing time stamps in multiple power frequency cycles before and after the fault occurrence time, and form a DG-side time stamp reference sequence independent of the terminal sampling data. S520. Perform a one-way matching comparison between the corrected time scales of each measuring point and the time scale reference sequence on the DG side. Determine the reference time scale corresponding to the corrected time scale of each measuring point according to the principle of the nearest neighbor of the time axis, and calculate the comparison deviation. S530. If the comparison deviation of all measuring points falls within the allowable time difference range of the corresponding measuring points, the verification is deemed to be successful, and the corrected time synchronization timing data is output. S540. If the measurement point comparison deviation exceeds the corresponding time difference tolerance range, an additional verification loop is triggered. This loop is a supplementary topology verification loop. During execution, the matching deviation value of the measurement point that exceeds the tolerance range is replaced with the corresponding comparison deviation. A constraint compression correction is performed based on the updated partition deviation feature matrix. After the supplementary loop is completed, a single comparison verification is performed. The DG side timescale reference sequence is only used for verification and judgment and does not participate in the correction calculation of the deviation value.

[0027] Specifically, step S600 includes: Read the corrected time-series data of each monitoring terminal that has passed the DG side time-stamp verification, extract the arrival time of the initial traveling wave front of the fault corresponding to each monitoring terminal, and select the two effective monitoring points at both ends of the topology segment where the fault is located based on the constructed feeder topology branch relationship. The reliability weight of the deviation of each measuring point is taken from the constructed partitioned unified deviation feature matrix. In this embodiment, based on the principle of double-end traveling wave ranging, the fault distance is calculated by combining the physical parameters of the line and the traveling wave propagation speed. The ranging calculation formula is: x=[L+v×(t1-t2)] / 2; where x is the fault distance from the fault point to the measuring point at the beginning of the segment; L is the line length between the two measuring points at the ends of the current fault segment; v is the traveling wave propagation speed of the corresponding line, which is determined according to the line type. For overhead lines, v=2.98×10 8 m / s, for cable lines, take v = 1.8 × 10 m / s. 8 m / s; t1 and t2 are the arrival times of the traveling wave fronts after correction at the measuring points at both ends of the segment, respectively; a deviation confidence weight is introduced for each measuring point to optimize the ranging terminal pair. If there are multiple available measuring points at both ends of the faulty segment, the pair of adjacent terminals with the highest deviation confidence weight product is selected as the final ranging terminal pair to reduce the impact of low confidence measuring points on positioning accuracy; for example, if the faulty segment is determined to be located in branch F2, the weight product of adjacent terminal pairs T5-T6 in this segment is W5× W6 = 0.79 × 0.65 = 0.51, and the weighted product of terminal pairs T6-T7 is W6 × W7 = 0.65 × 0.82 = 0.53. Therefore, T6-T7 is selected as the ranging terminal pair. Using the corrected arrival time of the traveling wave front and the length of the line section of the selected ranging terminal pair, the fault distance is calculated again according to the double-ended traveling wave ranging formula. In this embodiment, taking the selected terminal pair T6-T7 as an example, the line length L = 700m, and the traveling wave velocity v = 2.98 × 10⁻⁶ m / s². 8m / s = 298m / μs, the corrected wavefront times t6 = 135.4μs, t7 = 136.8μs, then the distance from the fault point to T6 is x = [700 + 298 × (135.4 - 136.8)] / 2 = 141.4m; combining the distribution network topology and section mileage information, the corrected fault distance is mapped to the actual physical location of the line, and the final fault location result is output, thus completing the accurate location of the distribution network fault. This is only an example and is not a limitation.

[0028] This invention provides another technical solution: a distribution network fault location system based on multi-source transient information. The system includes: an anchor point classification module, a traveling wave matching module, a deviation processing module, a DG verification module, and a timing output module. The anchor point classification module is used to obtain the zero-crossing time of the power frequency voltage and current of each monitoring terminal, filter the effective anchor points according to the terminal topology level and historical clock drift statistics, classify the effective anchor points based on waveform stability and harmonic interference, and output the effective original anchor point time series set with confidence level label. The traveling wave matching module is used to match the high-frequency traveling wave head time with the effective anchor point. If the matching deviation exceeds the statistical range of the historical deviation of the measurement point, the anchor point level is downgraded and a second matching is performed. The anchor point confidence level is adjusted in reverse according to the matching result. The deviation processing module is used to remove outliers by feeder branch based on the matching deviation of each measuring point, calculate the representative deviation characteristics of the branch, and construct a partitioned deviation feature matrix by combining the anchor point confidence level, wavefront signal-to-noise ratio, and measuring point topology location to assign confidence weights. It also sets the allowable time difference interval based on the line physical parameters and iteratively verifies the deviation matrix. Deviations exceeding the allowable interval are constrained and compressed for correction, and the matching judgment threshold is updated based on the correction amount. When the proportion of abnormal measuring points within the same topology branch exceeds the critical proportion value, the drift parameters are adjusted and anchor point regeneration is triggered. When the termination condition is met, the corrected timestamps of each measuring point are output. The DG verification module is used to extract the power frequency phase angle time scale of the phase-locked loop output of the distributed power source grid connection point as an independent reference sequence and perform one-way verification on the corrected time scale. When the verification fails, the deviation characteristic value of the out-of-tolerance measurement point is replaced with the comparison deviation, and the deviation processing module is driven to perform supplementary constraint compression correction. The independent reference sequence is only used for verification and does not participate in the correction calculation. The timing output module is used to output corrected time-synchronized timing data after verification, serving as a unified timing reference for fault traveling wave location.

[0029] Specifically, the anchor point classification module includes a zero-crossing screening unit and a quality classification unit. The zero-crossing screening unit is used to compare the initial zero-crossing point of each terminal with the historical clock drift statistics, eliminate abnormal points, and perform adjacent level verification based on the power frequency phase delay between topology levels to generate valid original anchor points. The quality classification unit is used to generate waveform stability labels based on the symmetry of the waveform before and after the zero-crossing point, generate harmonic interference level labels based on the proportion of high-frequency harmonic components, and comprehensively classify confidence levels.

[0030] Specifically, the deviation processing module includes a matrix construction unit, a cyclic correction unit, and a drift adjustment unit. The matrix construction unit is used to collect and match deviations according to feeder branches, remove outliers using the interquartile range method, and take the median value as the representative deviation feature of the branch. At the same time, it generates a confidence weight for the deviation of each measurement point and constructs a partitioned deviation feature matrix. The cyclic correction unit is used to perform time difference verification and constraint compression correction, dynamically update the matching judgment threshold and mark abnormal measurement points, and determine the loop termination condition. The drift adjustment unit is used to monitor the proportion of abnormal measurement points in the branch. When the limit is exceeded, it determines that there is an overall time series offset in the branch, increases the drift weight parameters of all terminals in the branch, and triggers anchor point regeneration.

[0031] Specifically, the DG verification module includes a time stamp extraction unit and a one-way verification unit. The time stamp extraction unit is used to extract the zero-crossing time stamp of the power frequency phase angle from the phase-locked loop of the distributed power grid connection point to form a third-party reference sequence independent of the terminal sampling data. The one-way verification unit is used to perform one-way comparison, and when the verification fails, it replaces the deviation feature value of the out-of-tolerance measurement point with the comparison deviation, triggering the deviation processing module to perform supplementary constraint compression correction.

[0032] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from its spirit or essential characteristics. Therefore, the embodiments should be considered in all respects as exemplary and non-limiting, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of equivalents of the claims are intended to be included within the present invention. No reference numerals in the claims should be construed as limiting the scope of the claims.

Claims

1. A method for fault location in distribution networks based on multi-source transient information, characterized in that: The method includes: S100: Obtain the zero-crossing time of the power frequency voltage and current of each monitoring terminal, filter effective anchor points according to the terminal topology level and historical clock drift statistics, classify the effective anchor points based on waveform stability and harmonic interference, and output the effective original anchor point time series set with confidence level label. S200. Match the high-frequency traveling wave head time with the effective anchor point. If the matching deviation exceeds the statistical range of the historical deviation of the measurement point, downgrade the anchor point level and perform a second matching. Adjust the anchor point confidence level in reverse according to the matching result. S300. Generate deviation feature values ​​based on the matching deviation of each measuring point, and construct a partitioned deviation feature matrix by combining the confidence level of the anchor point, the signal-to-noise ratio of the wavefront and the topological position of the measuring point. S400: Set the allowable time difference interval for measurement points based on the physical parameters of the line, and iteratively verify the deviation matrix; perform constraint compression correction on deviations that exceed the allowable time difference interval, and update the matching judgment threshold based on the correction amount; mark measurement points that cannot be corrected by constraint compression as abnormal measurement points; when the proportion of abnormal measurement points in the same topology branch exceeds the proportion threshold, adjust the drift parameters and regenerate the anchor point set; when all deviations fall into the allowable time difference interval or the abnormal measurement point set stabilizes after multiple rounds, stop the loop and output the corrected time scale of each measurement point. S500: Extract the power frequency phase angle time scale of the distributed power grid connection point phase-locked loop output, perform one-way matching verification on the corrected time scale, if all comparison deviations fall within the time difference tolerance range, the verification passes and the corrected timing data is output; if any comparison deviation exceeds the limit, an additional verification cycle is triggered. S600. Based on the verified corrected timing data, obtain the arrival time of the initial traveling wave front of the fault after correction for each monitoring terminal, combine it with the physical parameters of the line, complete the fault location calculation, and output the fault location result.

2. The method for fault location in a distribution network based on multi-source transient information according to claim 1, characterized in that: Step S100 includes: S110. Extract the voltage zero-crossing time and current zero-crossing time of each monitoring terminal in multiple power frequency cycles before and after the fault occurrence time, and generate the initial zero-crossing time sequence set of each monitoring terminal. S120. The initial zero-crossing time of each monitoring terminal is compared with the historical clock drift statistics of the corresponding terminal. Zero-crossing points with deviations exceeding the historical drift fluctuation range are eliminated. The remaining zero-crossing points are sorted according to the terminal topology level. The arrival time difference of the same zero-crossing point between adjacent level terminals is calculated. The power frequency phase delay of the same zero-crossing point propagating along the line to adjacent level terminals is used as the synchronization judgment benchmark. Zero-crossing points with time differences exceeding the allowable deviation range corresponding to the benchmark are eliminated, and valid original anchor points are generated. S130. For each valid original anchor point, determine the degree of symmetry of the waveform within one-quarter of the power frequency cycle before and after the zero crossing point, and generate a waveform stability label; determine the proportion of high-frequency harmonic components of the voltage and current waveforms within one-eighth of the power frequency cycle before and after the zero crossing point, and generate a harmonic interference degree label. S140. Based on the combination of waveform stability label and harmonic interference level label, divide each effective original anchor point into high confidence level, medium confidence level and low confidence level, and output the effective original anchor point time series set with initial confidence level label.

3. The method for fault location in a distribution network based on multi-source transient information according to claim 1, characterized in that: Step S200 includes: S210. Extract the initial traveling wave head time of the fault from the high-frequency data stream of each monitoring terminal; S220. Match the current traveling wave front time of the measurement point with the nearest high-confidence anchor point in the effective original anchor point time series set that is before the traveling wave front time and is close to it. Calculate the time interval between the traveling wave front time and the matched anchor point as the matching deviation. S230. Compare the matching deviation with the historical matching deviation statistics accumulated by the measuring point under normal operating conditions; if the matching deviation does not exceed the historical matching deviation statistics range, the matching is determined to be successful. S240. If the matching deviation exceeds the historical matching deviation statistical range, abandon the current high confidence level anchor point and perform a second matching on the time axis to a lower confidence level anchor point that is farther away from the time of the traveling wave head. S250. If the second match is successful, the confidence level of the matched anchor point is lowered by one level; if the second match is still unsuccessful, a mapping failure flag is output; when the first match is successful, the current confidence level of the corresponding anchor point remains unchanged; when the second match is successful, the confidence level of the anchor point used is lowered; and the confidence level of the valid anchor point is adjusted in reverse according to the matching result.

4. The method for fault location in a distribution network based on multi-source transient information according to claim 1, characterized in that: Step S300 includes: S310. According to the feeder topology branch affiliation label, the matching deviation of each measuring point is assigned to the deviation dataset of the corresponding branch. S320. Calculate the interquartile range for the matching deviation of all measurement points within the same branch, remove the deviation data points that exceed the outlier determination interval determined based on the interquartile range, and calculate the median value of the remaining matching deviation after removing outliers, which is used as the branch representative deviation feature of the branch. S330. Generate a deviation confidence weight for each measuring point. The deviation confidence weight is jointly determined by the confidence level of the anchor point currently used by the measuring point, the signal-to-noise ratio level at the moment of capturing the traveling wave front of the measuring point, and the proximity of the measuring point to the estimated fault source section in the feeder topology. S340. Construct a partitioned unified deviation feature matrix by combining the matching deviation values ​​of each measuring point, the deviation characteristics represented by the branch, the deviation confidence weight, and the measuring point identifier and topological branch attribution information.

5. The method for fault location in a distribution network based on multi-source transient information according to claim 1, characterized in that: Step S400 includes: S410. Calculate the theoretical propagation delay of each adjacent measuring point pair based on the physical parameters of the line between adjacent monitoring points, and set the corresponding time difference tolerance interval based on the theoretical propagation delay of each adjacent measuring point pair. S420. Substitute the corrected time scale of each measuring point in the partition deviation feature matrix into each adjacent measuring point pair for verification, and calculate the deviation between the measured time difference and the theoretical propagation delay; perform constraint compression correction on the deviation that exceeds the corresponding time difference allowable interval, so that the corrected time difference falls within the time difference allowable interval, and record the correction offset and the degree of deviation; according to the degree of deviation, divide the measuring points into measuring points that pass the constraint compression correction and abnormal measuring points that cannot pass the constraint compression correction. S430. Based on the correction offset of each measuring point, update the matching judgment threshold of the corresponding measuring point; S440. When more than half of the measurement points in the same topology branch are marked as abnormal measurement points in two consecutive loops, it is determined that there is an overall temporal offset of the anchor points of the branch. The drift weight parameters of all terminals of the branch are increased, and the effective original anchor point set is re-extracted. S450. Determine whether the loop termination condition is met in each round. The termination condition is that the corrected time difference of all adjacent measuring points falls into the corresponding time difference allowable range, or the abnormal measuring point set no longer increases or decreases in multiple consecutive loops. Stop the loop when any termination condition is met, and output the current corrected deviation feature matrix.

6. The method for fault location in a distribution network based on multi-source transient information according to claim 1, characterized in that: Step S500 includes: S510. Extract the phase angle change trajectory of the power frequency voltage output from the phase-locked loop at the grid connection point of the distributed power source, read the zero-crossing time stamps in multiple power frequency cycles before and after the fault occurrence time, and form a DG-side time stamp reference sequence independent of the terminal sampling data. S520. Perform a one-way matching comparison between the corrected time scales of each measuring point and the time scale reference sequence on the DG side. Determine the reference time scale corresponding to the corrected time scale of each measuring point according to the principle of the nearest neighbor of the time axis, and calculate the comparison deviation. S530. If the comparison deviation of all measuring points falls within the allowable time difference range of the corresponding measuring points, the verification is deemed to be successful, and the corrected time synchronization timing data is output. S540. If the measurement point comparison deviation exceeds the corresponding time difference tolerance range, the additional verification loop is triggered. This loop is a supplementary topology verification loop. During execution, the matching deviation value of the measurement point that exceeds the tolerance range is replaced with the corresponding comparison deviation. A constraint compression correction is performed based on the updated partition deviation feature matrix. After the supplementary loop is completed, a single comparison verification is performed. The DG side timescale reference sequence is only used for verification and judgment and does not participate in the correction calculation of the deviation value.

7. A distribution network fault location system based on multi-source transient information, characterized in that: The system includes: an anchor point classification module, a traveling wave matching module, a deviation processing module, a DG verification module, and a timing output module; The anchor point classification module is used to obtain the zero-crossing time of the power frequency voltage and current of each monitoring terminal, filter effective anchor points according to the terminal topology level and historical clock drift statistics, classify the effective anchor points based on waveform stability and harmonic interference, and output a set of effective original anchor point time series with confidence level labels. The traveling wave matching module is used to match the high-frequency traveling wave head time with the effective anchor point. If the matching deviation exceeds the statistical range of the historical deviation of the measurement point, the anchor point level is downgraded and a second matching is performed. The anchor point confidence level is adjusted in reverse according to the matching result. The deviation processing module is used to remove outliers by feeder branch based on the matching deviation of each measuring point, calculate the representative deviation characteristics of the branch, and construct a partitioned deviation feature matrix by combining the anchor point confidence level, wavefront signal-to-noise ratio, and measuring point topology location to assign confidence weights; it also sets the time difference tolerance range according to the line physical parameters and iteratively verifies the deviation matrix; it performs constraint compression correction on deviations exceeding the tolerance range and updates the matching judgment threshold based on the correction amount; when the proportion of abnormal measuring points in the same topology branch exceeds the proportion threshold, it adjusts the drift parameters and triggers anchor point regeneration; and outputs the corrected time scale of each measuring point when the termination condition is met. The DG verification module is used to extract the power frequency phase angle time scale output by the phase-locked loop at the grid connection point of the distributed power source as an independent reference sequence, and to perform one-way verification on the corrected time scale; when the verification fails, the deviation characteristic value of the out-of-tolerance measurement point is replaced with the comparison deviation, and the deviation processing module is driven to perform supplementary constraint compression correction; the independent reference sequence is only used for verification and does not participate in the correction calculation. The timing output module is used to output corrected time-synchronized timing data after the verification is passed, as a unified timing reference for fault traveling wave location.

8. A distribution network fault location system based on multi-source transient information according to claim 7, characterized in that: The anchor point grading module includes a zero-crossing screening unit and a quality grading unit; The zero-crossing screening unit is used to compare the initial zero-crossing point of each terminal with the historical clock drift statistics, eliminate abnormal points, and perform adjacent level verification based on the power frequency phase delay between topology levels to generate valid original anchor points. The quality grading unit is used to generate waveform stability labels based on the symmetry of the waveform before and after the zero crossing, generate harmonic interference level labels based on the proportion of high-frequency harmonic components, and comprehensively classify confidence levels.

9. A distribution network fault location system based on multi-source transient information according to claim 7, characterized in that: The deviation processing module includes a matrix construction unit, a cyclic correction unit, and a drift adjustment unit; The matrix construction unit is used to collect and match deviations according to feeder branches, remove outliers by using the interquartile range method and take the median value as the branch representative deviation feature, and generate the confidence weight for the deviation of each measuring point to construct a partitioned deviation feature matrix. The loop correction unit is used to perform the time difference verification and constraint compression correction, dynamically update the matching judgment threshold and mark abnormal measurement points, and determine the loop termination condition. The drift adjustment unit is used to monitor the proportion of abnormal measurement points in the branch. When the limit is exceeded, it is determined that there is an overall temporal offset in the branch, and the drift weight parameters of all terminals in the branch are increased and the anchor point is regenerated.

10. A distribution network fault location system based on multi-source transient information according to claim 7, characterized in that: The DG verification module includes a time stamp extraction unit and a one-way verification unit; The time stamp extraction unit is used to extract the zero-crossing time stamp of the power frequency phase angle from the phase-locked loop of the distributed power grid connection point, forming a third-party reference sequence independent of the terminal sampling data; The one-way verification unit is used to perform the one-way comparison, and when the verification fails, it replaces the deviation feature value of the out-of-tolerance measurement point with the comparison deviation, triggering the deviation processing module to perform supplementary constraint compression correction.