A control method for improving hanging basket construction precision

By constructing control formulas and using real-time monitoring technology, the problem of low accuracy in hanging basket construction was solved, achieving efficient, safe, and precise control of cantilever casting construction, thus meeting the construction needs of modern long-span bridges.

CN123137115APending Publication Date: 2026-11-20CCCC THIRD HARBOR ENGINEERING CO LTD
View PDF -1 Cites 0 Cited by

Patent Information

Application Number
CN202611476606.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-22
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Existing hanging basket construction control methods have low precision and lack real-time attitude monitoring and dynamic correction mechanisms, resulting in large deviations in the cantilever casting construction line, posing safety hazards and high costs.

Method used

By constructing control formulas and monitoring key parameters of the hanging basket in real time, accurate control of the entire process of hanging basket preloading, movement, formwork erection and pouring is achieved, including graded loading preloading, real-time posture calibration, dynamic pouring and linkage control, to ensure construction accuracy and safety.

Benefits of technology

It achieves millimeter-level precision control in hanging basket construction, reducing construction costs and safety hazards, improving construction efficiency and safety, and reducing rework and rectification workload.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123137115A_ABST
    Figure CN123137115A_ABST
Patent Text Reader

Abstract

The application provides a control method for improving the construction precision of a hanging basket, and belongs to the technical field of precision control, which comprises the following steps: step 1, performing pre-compression deformation calculation and control on the hanging basket for the hanging basket construction; step 2, after the pre-compression deformation calculation and control on the hanging basket for the hanging basket construction, performing control on the walking posture of the hanging basket; step 3, after the control on the walking posture of the hanging basket, performing setting and control on the formwork erection elevation; step 4, after the setting and control on the formwork erection elevation, performing dynamic control on the concrete pouring process; and step 5, after the dynamic control on the concrete pouring process, performing maintenance and subsequent segment linkage control. By accurately quantifying the key parameters of each link of the hanging basket construction, the corresponding control formula is constructed, the accurate control of the whole process of the hanging basket pre-compression, walking and pouring is realized, the linear precision and structural safety of the bridge cantilever pouring are ensured, the construction cost is reduced, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of precision control technology, specifically relating to a control method for improving the construction precision of hanging baskets. Background Technology

[0002] In the cantilever construction of long-span bridges, the formwork, as a key construction equipment, directly determines the bridge structure's alignment quality, stress safety, and closure accuracy through its construction precision. It is a crucial control link in cantilever construction. Currently, formwork construction control mainly relies on traditional experience-based adjustments and segmented monitoring methods, which have many technical shortcomings and cannot meet the millimeter-level construction precision requirements of modern long-span bridges.

[0003] Specifically, existing technologies for calculating the prestressing deformation of hanging baskets often rely on empirical estimations or simplified formulas, failing to fully consider real-time loads, temperature changes, and material properties during construction. This results in significant deviations in the prestressing deformation data, which in turn affects the accuracy of setting the formwork elevation. During the movement of the hanging basket, the lack of real-time attitude monitoring and dynamic correction mechanisms makes it prone to problems such as basket offset and tilting, which not only affects construction efficiency but may also pose safety hazards. Uneven load distribution and temperature gradient changes during the concrete pouring stage can easily lead to unexpected deformation of the hanging basket, and traditional control methods cannot achieve real-time monitoring and synchronous adjustment of deformation, which can easily cause deviations in the beam alignment, making subsequent rectification difficult and costly.

[0004] Furthermore, the impact of creep shrinkage and temperature deformation of the already poured beam segments on subsequent formwork construction has not been accurately quantified, further exacerbating deviations in the construction alignment. Therefore, developing a precise, efficient, and stable control method to improve the accuracy of formwork construction has become an urgent need to address current defects in formwork construction. Summary of the Invention

[0005] The purpose of this invention is to overcome the technical defects of low precision and insufficient dynamic adjustment in existing hanging basket construction control, and to provide a control method to improve the precision of hanging basket construction. By accurately quantifying the key parameters of each stage of hanging basket construction and constructing corresponding control formulas, accurate control of the entire process of hanging basket preloading, movement and pouring is achieved, ensuring the alignment accuracy and structural safety of bridge cantilever pouring, reducing construction costs and improving construction efficiency.

[0006] The present invention employs the following technical solution.

[0007] A control method for improving the construction accuracy of hanging baskets includes:

[0008] Step 1: Perform pre-stressing deformation calculation and control for the hanging basket construction;

[0009] Step 2: After performing the pre-stressing deformation calculation and control for the hanging basket construction, control the walking posture of the hanging basket.

[0010] Step 3: After controlling the walking posture of the hanging basket, set and control the elevation of the formwork.

[0011] Step 4: After setting and controlling the formwork elevation, perform dynamic control of the concrete pouring process;

[0012] Step 5: After implementing dynamic control of the concrete pouring process, execute the curing and subsequent segment linkage control.

[0013] Furthermore, step 1 specifically includes:

[0014] After the hanging basket is assembled, a graded loading prestressing method is adopted to simulate the actual construction load distribution, monitor the deformation data of key parts of the main truss, front crossbeam and bottom basket platform of the hanging basket in real time, and calculate the elastic deformation value and inelastic deformation value of the hanging basket.

[0015] The pre-compression qualification standard of the hanging basket is determined based on the elastic deformation value and inelastic deformation value of the hanging basket.

[0016] Furthermore, in step 1, the formula for calculating the elastic and inelastic deformation values ​​of the hanging basket is:

[0017] ;

[0018] In the formula, The elastic deformation value of the hanging basket refers to the recoverable deformation of the hanging basket when it is loaded to the design load. This is the total deformation of the hanging basket when it is loaded to the maximum preload, which is 120% of the design load. The inelastic deformation value of the hanging basket refers to the permanent deformation that cannot be recovered after the hanging basket is unloaded; It refers to the residual deformation of the hanging basket after pre-loading and unloading; It refers to the initial deformation amount before the preloading of the hanging basket.

[0019] Furthermore, in step 1, the pre-compression qualification standard for the hanging basket is:

[0020] When the inelastic deformation value is less than 0.5 mm and the convergence of elastic deformation is less than 0.2 mm / h within 2 consecutive hours, the preloading is qualified; otherwise, the preloading is repeated until the qualification standard is met.

[0021] Furthermore, step 2 specifically includes:

[0022] Before the hanging basket moves, the horizontality and flatness of the track are calibrated. A total station is used to monitor the horizontal offset and vertical tilt angle during the movement of the hanging basket in real time, and the amount of correction for the movement of the hanging basket is calculated.

[0023] When horizontal offset The absolute value is greater than 2mm or the vertical tilt angle is greater than 2mm. When the absolute value is greater than 0.05°, the synchronous correction device is activated to adjust the walking speed and posture of the hanging basket until the offset and tilt angle meet the design requirements, and then the walking continues.

[0024] Furthermore, in step 2, the formula for calculating the travel correction amount of the hanging basket is:

[0025] ;

[0026] In the formula, This represents the horizontal offset during the basket's movement. A positive value indicates a shift to the right. A negative value indicates a shift to the left; The measured horizontal position of the hanging basket during its movement; The horizontal position designed for the movement of the hanging basket; The vertical tilt angle deviation during basket movement. A positive value indicates that the front of the basket is tilted upwards. A negative value indicates that the front end of the basket is tilted downwards; The measured vertical tilt angle during the hanging basket's movement; The vertical tilt angle designed for the hanging basket to move.

[0027] Furthermore, step 3 specifically includes:

[0028] The formwork elevation is calculated by combining the pre-stressing deformation data of the hanging basket, the deformation data of the cast beam segment, and the real-time temperature data.

[0029] After the formwork is erected, an electronic level and an indium steel ruler are used to remeasure the elevation at the three pre-set sections (front, middle, and back) on the top surface of the formwork. If the measured elevation deviates from the calculated value by more than ±2mm, fine-tuning is performed until the accuracy requirements are met, and then the formwork is locked.

[0030] Furthermore, in step 3, the formula for calculating the elevation of the formwork is:

[0031] ;

[0032] In the formula, This refers to the elevation of the formwork for the hanging basket, i.e., the target elevation of the top surface of the formwork. Design elevation of the front end of the segment; This refers to the deformation of the cast-in-place beam segment due to creep or shrinkage. A positive value indicates that the poured beam segment is arched. A negative value indicates the deflection of the poured beam segment, which is obtained from previous measured data. The effect of temperature change on the beam elevation is calculated from 24-hour temperature gradient monitoring data. When the temperature rises... It is a positive value when the temperature decreases. It is a negative value.

[0033] Furthermore, step 4 specifically includes:

[0034] Concrete pouring adopts a symmetrical and balanced approach, strictly following the sequence of pouring the bottom slab first, then the web slab, and finally the top slab. The deformation of the formwork and the amount of concrete poured are monitored in real time during the pouring process, and the deformation warning value is calculated using the following formula:

[0035] ;

[0036] In the formula, This refers to the deformation warning value during the concrete pouring process of the hanging basket; This refers to the volume of concrete that has already been poured. The total concrete pouring volume designed for the hanging basket;

[0037] When the measured deformation reaches 80% of the set warning value, the pouring speed is slowed down and the monitoring frequency is increased; when the measured deformation exceeds the warning value, the pouring is suspended in real time to investigate problems such as uneven load and abnormal hanging basket, and the pouring is resumed after the problems are resolved.

[0038] Furthermore, step 5 specifically includes:

[0039] After the concrete pouring is completed, the curing stage begins. The curing temperature and beam deformation are monitored in real time. Before and after prestressing tensioning and at key curing nodes, the elevation and axis of the poured beam segments are systematically re-measured. The measured deformation data are substituted into the calculation formula for the formwork elevation to update the formwork elevation parameters of the next segment, thereby achieving linkage control of the construction of each segment and ensuring the smooth alignment of the entire bridge.

[0040] The beneficial effects of the present invention are as follows, compared with the prior art:

[0041] This invention improves the control precision of preloading deformation, formwork elevation, and formwork travel offset of the formwork, meeting the millimeter-level construction precision requirements of modern long-span bridges, significantly reducing beam alignment deviation, and ensuring closure accuracy. This invention covers all construction stages of the formwork, including preloading, travel, formwork erection, pouring, and curing. By real-time monitoring of key parameters, dynamic calculation of control values, and timely correction and adjustment, it effectively avoids safety hazards such as formwork tilting, offset, and excessive deformation, reducing the number of work stoppages and rectifications during construction, and lowering the probability of safety accidents. Simultaneously, the deformation early warning mechanism during concrete pouring can predict deformation risks in advance, avoiding formwork instability and beam cracks caused by uneven loads, thus ensuring construction safety. This invention ensures the integrity of the entire structure. It links the deformation data and curing temperature data of the cast-in-place beam segment with the calculation of the formwork elevation of the next segment, realizing the linkage control of each construction segment. This effectively offsets the impact of creep shrinkage and temperature deformation of the cast-in-place beam segment on subsequent construction, ensuring the smoothness of the cantilever alignment of the entire bridge, reducing the amount of cutting and rectification work during the closure stage, and lowering construction costs. Through precise control, it reduces the amount of rework and rectification work during the construction process, shortens the construction time of hanging basket preloading, walking and formwork erection, and reduces material waste and labor costs. In addition, the linkage control mechanism reduces the construction difficulty of the closure stage, avoids secondary construction due to insufficient closure accuracy, further reduces construction costs, and improves construction efficiency. Attached Figure Description

[0042] Figure 1 This is a flowchart of the control method for improving the construction accuracy of hanging baskets in this invention. Detailed Implementation

[0043] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions of this invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of this invention. The embodiments described in this application are merely some embodiments of this invention, and not all embodiments. Based on the spirit of this invention, other embodiments obtained by those skilled in the art without creative effort are all within the protection scope of this invention.

[0044] like Figure 1 As shown, this invention proposes a control method to improve the construction accuracy of hanging baskets, comprising the following steps:

[0045] Step 1: Perform pre-stressing deformation calculation and control for the hanging basket construction;

[0046] In a preferred but non-limiting embodiment of the present invention, step 1 specifically includes:

[0047] After the hanging basket is assembled, a graded loading prestressing method is adopted to simulate the actual construction load distribution, monitor the deformation data of key parts of the main truss, front crossbeam and bottom basket platform of the hanging basket in real time, and calculate the elastic deformation value and inelastic deformation value of the hanging basket.

[0048] In a preferred but non-limiting embodiment of the present invention, in step 1, the formula for calculating the elastic deformation value and inelastic deformation value of the hanging basket is:

[0049] ;

[0050] In the formula, The elastic deformation value of the hanging basket refers to the recoverable deformation of the hanging basket when it is loaded to the design load. This is the total deformation of the hanging basket when it is loaded to the maximum preload, which is 120% of the design load. The inelastic deformation value of the hanging basket refers to the permanent deformation that cannot be recovered after the hanging basket is unloaded; It refers to the residual deformation of the hanging basket after pre-loading and unloading; It refers to the initial deformation amount before the preloading of the hanging basket.

[0051] It should be noted that the real-time monitoring of deformation data of key parts of the main truss, front crossbeam and bottom platform of the hanging basket is achieved by using a total station to monitor the deformation data of key parts of the main truss, front crossbeam and bottom platform of the hanging basket in real time.

[0052] For example, The methods for obtaining it include:

[0053] First, after the hanging basket is assembled and before preloading, use a total station to monitor key components such as the main truss, front crossbeam, and bottom platform of the hanging basket, and record the initial deformation, which is the amount of deformation in the formula. ;

[0054] Then, staged preloading is used (usually in 3 stages: 60%, 100%, and 120% of the design load). After loading to the maximum preload (120% * design load) and allowing it to stabilize, the total deformation at this point is recorded. ;

[0055] After preloading is completed, unloading is carried out. Once unloading is complete and the deformation of the hanging basket has stabilized, the residual deformation of key parts is monitored again. ;

[0056] Finally, use public... The calculation yields the inelastic deformation value of the hanging basket, which is the permanent deformation that cannot be recovered after the hanging basket is unloaded.

[0057] The pre-compression qualification standard of the hanging basket is determined based on the elastic deformation value and inelastic deformation value of the hanging basket.

[0058] In a preferred but non-limiting embodiment of the present invention, in step 1, the pre-compression qualification standard for the hanging basket is:

[0059] When the inelastic deformation value is less than 0.5 mm and the convergence of elastic deformation is less than 0.2 mm / h within 2 consecutive hours, the preloading is qualified; otherwise, the preloading is repeated until the qualification standard is met.

[0060] It should be noted that the elastic deformation convergence is the change in elastic deformation per unit time after the formwork is preloaded to the maximum load (120% * design load) and allowed to settle and stabilize. It primarily reflects the stability of the formwork's elastic deformation. The elastic deformation convergence needs to be continuously monitored after the formwork is preloaded to the maximum load (120% * design load) and allowed to settle. The specific steps are as follows: After loading to the maximum load, let it stand until the deformation is initially stable. Then, every hour, use a total station to monitor the deformation data of key parts of the hanging basket. Monitor continuously for 2 hours and calculate the deformation difference between two adjacent monitoring times. This difference is the hourly convergence amount. Take the maximum convergence amount within these 2 hours to determine whether it meets the requirement of ≤0.2mm / h. If the convergence amount of elastic deformation is too large, it means that the hanging basket is still deforming and has not reached a stable state. At this time, stop preloading. In subsequent construction, the hanging basket may continue to produce unexpected deformation, affecting the accuracy of the formwork. Only when the convergence amount meets the requirements can it be said that the elastic deformation of the hanging basket has stabilized and the preloading effect has met the standard. In subsequent construction, the deformation of the hanging basket can be controlled to avoid quality or safety problems caused by unstable deformation.

[0061] Step 2: After performing the pre-stressing deformation calculation and control for the hanging basket construction, control the walking posture of the hanging basket.

[0062] In a preferred but non-limiting embodiment of the present invention, step 2 specifically includes:

[0063] Before the hanging basket moves, the horizontality and flatness of the track are calibrated. A total station is used to monitor the horizontal offset and vertical tilt angle during the movement of the hanging basket in real time, and the amount of correction for the movement of the hanging basket is calculated.

[0064] In a preferred but non-limiting embodiment of the present invention, in step 2, the formula for calculating the travel correction amount of the hanging basket is:

[0065] ;

[0066] In the formula, This represents the horizontal offset during the basket's movement. A positive value indicates a shift to the right. A negative value indicates a shift to the left; The measured horizontal position of the hanging basket during its movement; The horizontal position designed for the movement of the hanging basket; The vertical tilt angle deviation during basket movement. A positive value indicates that the front of the basket is tilted upwards. A negative value indicates that the front end of the basket is tilted downwards; The measured vertical tilt angle during the hanging basket's movement; The vertical tilt angle designed for the hanging basket to move.

[0067] When horizontal offset The absolute value is greater than 2mm or the vertical tilt angle is greater than 2mm. When the absolute value is greater than 0.05°, the synchronous correction device is activated to adjust the walking speed and posture of the hanging basket until the offset and tilt angle meet the design requirements, and then the walking continues.

[0068] Step 3: After controlling the walking posture of the hanging basket, set and control the elevation of the formwork.

[0069] In a preferred but non-limiting embodiment of the present invention, step 3 specifically includes:

[0070] The formwork elevation is calculated by combining the pre-stressing deformation data of the hanging basket, the deformation data of the cast beam segment, and the real-time temperature data.

[0071] In a preferred but non-limiting embodiment of the present invention, the formula for calculating the elevation of the formwork in step 3 is:

[0072] ;

[0073] In the formula, This refers to the elevation of the formwork for the hanging basket, i.e., the target elevation of the top surface of the formwork. The design elevation of the segment's front end is provided by the bridge design drawings; This refers to the deformation of the cast-in-place beam segment due to creep or shrinkage. A positive value indicates that the poured beam segment is arched. A negative value indicates the deflection of the poured beam segment, which is obtained from previous measured data. The effect of temperature change on the beam elevation is calculated from 24-hour temperature gradient monitoring data. When the temperature rises... It is a positive value when the temperature decreases. It is a negative value.

[0074] It should be noted that the front end of a segment, in the cantilever casting construction using a formwork system, refers to the end of the beam segment currently under construction, closest to the cantilever end of the bridge and furthest from the already cast beam. This is also the critical working end for formwork erection and casting, essentially the very front end of the current construction segment. The segment under construction has one end connected to the already cast beam (this end is called the rear end of the segment), and the other end is suspended, extending further into the cantilever direction after casting is completed. This suspended end is the front end of the segment, and its elevation is calculated during formwork erection. It is the design elevation of this front end position, because the accuracy of the front end elevation directly affects the connection of subsequent segments and the overall bridge alignment.

[0075] An exemplary method for calculating from 24-hour temperature gradient monitoring data includes:

[0076] On the beam (or formwork of the hanging basket) of the current construction segment, arrange 3-5 temperature monitoring points vertically (such as the top, middle and bottom of the beam, with a spacing of 50-100cm) to ensure coverage of the entire cross section of the beam. At the same time, set up ambient temperature monitoring points on the construction site to record the ambient temperature 24 hours a day.

[0077] Every hour, record the real-time temperature of all monitoring points. Monitor continuously for 24 hours, and compile the average temperature value of each monitoring point within 24 hours, as well as the temperature difference value obtained by subtracting the design reference temperature (the construction reference temperature specified in the bridge design drawings, usually 20℃).

[0078] Using the basic formula of thermal expansion and contraction = linear expansion coefficient of the material × temperature difference, where the linear expansion coefficient of the material is the linear expansion coefficient of the steel of the hanging basket.

[0079] After the formwork is erected, an electronic level and an indium steel ruler are used to remeasure the elevation at three pre-set sections (front, middle and back) on the top surface of the formwork (each section has three points on the left, middle and upper right). If the measured elevation deviates from the calculated value by more than ±2mm, fine-tuning is performed to correct the deviation until the accuracy requirements are met, and then the formwork is locked.

[0080] For example, methods for fine-tuning and correcting deviations include:

[0081] Determine the specific location where the measured elevation deviates from the tolerance (e.g., the right side of a section on the top surface of the template), mark the point, and then re-measure it with an electronic level to confirm the deviation value and direction (whether it is too high or too low) to avoid misjudgment.

[0082] For the support jacks of the hanging basket corresponding to the out-of-tolerance points (2-4 jacks for each template, evenly distributed), perform fine-tuning operations. If the measured elevation is too high, slowly loosen the pressure relief valve of the corresponding jack to allow the template to slowly sink, with each sinking amount controlled at 0.2-0.3mm. If the measured elevation is too low, slowly tighten the pressure valve of the jack to allow the template to slowly rise, with each rise also controlled at 0.2-0.3mm to avoid excessive adjustment.

[0083] After each adjustment, immediately remeasure the elevation of the point using an electronic level, compare the measured value with the calculated value, determine whether the deviation has narrowed, and repeat the fine-tuning and remeasurement steps until the deviation between the measured elevation and the calculated value of the point is ≤ ±2mm.

[0084] After a single point is adjusted to be qualified, the three sections (three points on the left, middle and right of each section) of the top of the template are re-measured to ensure that all points meet the accuracy requirements and there are no omissions. After all are qualified, the jack locking device is tightened to fix the position of the template and complete the fine adjustment and correction.

[0085] Step 4: After setting and controlling the formwork elevation, perform dynamic control of the concrete pouring process;

[0086] In a preferred but non-limiting embodiment of the present invention, step 4 specifically includes:

[0087] Concrete pouring adopts a symmetrical and balanced approach, strictly following the sequence of pouring the bottom slab first, then the web slab, and finally the top slab. The deformation of the formwork and the amount of concrete poured are monitored in real time during the pouring process, and the deformation warning value is calculated using the following formula:

[0088] ;

[0089] In the formula, This refers to the deformation warning value during the concrete pouring process of the hanging basket; This refers to the volume of concrete that has already been poured. The total concrete pouring volume designed for the hanging basket;

[0090] When the measured deformation reaches 80% of the set warning value, the pouring speed is slowed down and the monitoring frequency is increased; when the measured deformation exceeds the warning value, the pouring is suspended in real time to investigate problems such as uneven load and abnormal hanging basket, and the pouring is resumed after the problems are resolved.

[0091] Exemplary methods for slowing down the pouring speed and increasing the monitoring frequency include:

[0092] The original pouring speed was 2 m³ / h, which was reduced to 1.2-1.5 m³ / h (usually reduced by 30%-40%, which does not affect the construction progress and can stabilize the load). It can be reduced to 1.5 m³ / h, which is determined by combining the on-site pouring efficiency and deformation control requirements.

[0093] By adjusting the output speed of the concrete pump or controlling the rhythm of the pouring personnel, for example, if the pump was originally delivering 2m³ of concrete per hour, the pump speed can be adjusted to reduce the hourly delivery to 1.5m³. At the same time, the concrete should be evenly distributed during pouring to avoid concentrated pouring in a certain area. After each layer (thickness ≤30cm), pause for 3-5 minutes before pouring the next layer to ensure that the load is applied slowly and evenly to the formwork.

[0094] After slowing down, check the actual pouring volume every 30 minutes to ensure that the pouring speed is stable at around 1.5 m³ / h, without sudden changes in speed, to avoid load fluctuations that could cause deformation of the formwork.

[0095] The key to increasing monitoring frequency is to increase the density of monitoring intervals, ensure full coverage of monitoring points, and promptly capture deformation changes. Specific steps include:

[0096] Originally, during the pouring process, the deformation of the hanging basket was usually monitored every 30 minutes; after the reinforcement, it was adjusted to be monitored every 10-15 minutes, and it can be selected to monitor every 10 minutes, because at this time it is close to the warning value, and more accurate capture of the deformation trend is needed.

[0097] The monitoring content remains unchanged, still focusing on the deformation of the hanging basket (with a focus on monitoring key parts of the main truss, front crossbeam, and bottom basket platform, consistent with the monitoring points during preloading and formwork erection), while simultaneously monitoring the concrete pouring volume to ensure that the deformation volume matches the pouring volume and to determine if there are any abnormalities.

[0098] After each monitoring, immediately record the measured deformation data, pouring volume, and monitoring time, and mark them on the construction record sheet; if it is found that the deformation growth rate is accelerating (for example, the difference in deformation between two consecutive monitoring exceeds 0.5mm), immediately report to the on-site technical supervisor, and promptly determine whether it is necessary to further slow down the pouring speed or suspend pouring to investigate the problem.

[0099] Step 5: After implementing dynamic control of the concrete pouring process, execute the curing and subsequent segment linkage control.

[0100] In a preferred but non-limiting embodiment of the present invention, step 5 specifically includes:

[0101] After the concrete is poured, the curing stage begins. The curing temperature and beam deformation are monitored in real time. Before and after prestressing tensioning and at key curing nodes (such as 1 day, 3 days or 7 days), the elevation and axis of the poured beam segments are systematically re-measured. The measured deformation data are substituted into the calculation formula for the formwork elevation to update the formwork elevation parameters of the next segment, so as to realize the linkage control of the construction of each segment and ensure the smoothness of the entire bridge alignment.

[0102] The beneficial effects of the present invention are as follows, compared with the prior art:

[0103] This invention improves the control precision of preloading deformation, formwork elevation, and formwork travel offset of the formwork, meeting the millimeter-level construction precision requirements of modern long-span bridges, significantly reducing beam alignment deviation, and ensuring closure accuracy. This invention covers all construction stages of the formwork, including preloading, travel, formwork erection, pouring, and curing. By real-time monitoring of key parameters, dynamic calculation of control values, and timely correction and adjustment, it effectively avoids safety hazards such as formwork tilting, offset, and excessive deformation, reducing the number of work stoppages and rectifications during construction, and lowering the probability of safety accidents. Simultaneously, the deformation early warning mechanism during concrete pouring can predict deformation risks in advance, avoiding formwork instability and beam cracks caused by uneven loads, thus ensuring construction safety. This invention ensures the integrity of the entire structure. It links the deformation data and curing temperature data of the cast-in-place beam segment with the calculation of the formwork elevation of the next segment, realizing the linkage control of each construction segment. This effectively offsets the impact of creep shrinkage and temperature deformation of the cast-in-place beam segment on subsequent construction, ensuring the smoothness of the cantilever alignment of the entire bridge, reducing the amount of cutting and rectification work during the closure stage, and lowering construction costs. Through precise control, it reduces the amount of rework and rectification work during the construction process, shortens the construction time of hanging basket preloading, walking and formwork erection, and reduces material waste and labor costs. In addition, the linkage control mechanism reduces the construction difficulty of the closure stage, avoids secondary construction due to insufficient closure accuracy, further reduces construction costs, and improves construction efficiency.

[0104] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that modifications or equivalent substitutions can still be made to the specific implementation of the present invention without departing from the spirit and scope of the present invention. Any modifications or equivalent substitutions should be covered within the scope of protection of the claims of the present invention.

Claims

1. A control method for improving the construction accuracy of hanging baskets, characterized in that, include: Step 1: Perform pre-stressing deformation calculation and control for the hanging basket construction; Step 2: After performing the pre-stressing deformation calculation and control for the hanging basket construction, control the walking posture of the hanging basket. Step 3: After controlling the walking posture of the hanging basket, set and control the elevation of the formwork. Step 4: After setting and controlling the formwork elevation, perform dynamic control of the concrete pouring process; Step 5: After implementing dynamic control of the concrete pouring process, execute the curing and subsequent segment linkage control.

2. The control method for improving the construction accuracy of hanging baskets according to claim 1, characterized in that, Step 1 specifically includes: After the hanging basket is assembled, a graded loading prestressing method is adopted to simulate the actual construction load distribution, monitor the deformation data of key parts of the main truss, front crossbeam and bottom basket platform of the hanging basket in real time, and calculate the elastic deformation value and inelastic deformation value of the hanging basket. The pre-compression qualification standard of the hanging basket is determined based on the elastic deformation value and inelastic deformation value of the hanging basket.

3. The control method for improving the construction accuracy of hanging baskets according to claim 2, characterized in that, In step 1, the formula for calculating the elastic and inelastic deformation values ​​of the hanging basket is: ; In the formula, The elastic deformation value of the hanging basket refers to the recoverable deformation of the hanging basket when it is loaded to the design load. This is the total deformation of the hanging basket when it is loaded to the maximum preload, which is 120% of the design load. The inelastic deformation value of the hanging basket refers to the permanent deformation that cannot be recovered after the hanging basket is unloaded; It refers to the residual deformation of the hanging basket after the pre-loading and unloading are completed; It refers to the initial deformation amount before the preloading of the hanging basket.

4. The control method for improving the construction accuracy of hanging baskets according to claim 3, characterized in that, In step 1, the pre-compression qualification standard for the hanging basket is: When the inelastic deformation value is less than 0.5 mm and the convergence of elastic deformation is less than 0.2 mm / h within 2 consecutive hours, the preloading is qualified; otherwise, the preloading is repeated until the qualification standard is met.

5. The control method for improving the construction accuracy of hanging baskets according to claim 4, characterized in that, Step 2 specifically includes: Before the hanging basket moves, the horizontality and flatness of the track are calibrated. A total station is used to monitor the horizontal offset and vertical tilt angle during the movement of the hanging basket in real time, and the amount of correction for the movement of the hanging basket is calculated. When horizontal offset The absolute value is greater than 2mm or the vertical tilt angle is greater than 2mm. When the absolute value is greater than 0.05°, the synchronous correction device is activated to adjust the walking speed and posture of the hanging basket until the offset and tilt angle meet the design requirements, and then the walking continues.

6. The control method for improving the construction accuracy of hanging baskets according to claim 5, characterized in that, In step 2, the formula for calculating the travel correction amount of the hanging basket is: ; In the formula, This represents the horizontal offset during the basket's movement. A positive value indicates a shift to the right. A negative value indicates a shift to the left; The measured horizontal position of the hanging basket during its movement; The horizontal position designed for the movement of the hanging basket; The vertical tilt angle deviation during basket movement. A positive value indicates that the front of the basket is tilted upwards. A negative value indicates that the front end of the basket is tilted downwards; The measured vertical tilt angle during the hanging basket's movement; The vertical tilt angle designed for the hanging basket to move.

7. The control method for improving the construction accuracy of hanging baskets according to claim 6, characterized in that, Step 3 specifically includes: The formwork elevation is calculated by combining the pre-stressing deformation data of the hanging basket, the deformation data of the cast beam segment, and the real-time temperature data. After the formwork is erected, an electronic level and an indium steel ruler are used to remeasure the elevation at the three pre-set sections (front, middle, and back) on the top surface of the formwork. If the measured elevation deviates from the calculated value by more than ±2mm, fine-tuning is performed until the accuracy requirements are met, and then the formwork is locked.

8. The control method for improving the construction accuracy of hanging baskets according to claim 7, characterized in that, In step 3, the formula for calculating the formwork elevation is: ; In the formula, This refers to the elevation of the formwork for the hanging basket, i.e., the target elevation of the top surface of the formwork. Design elevation of the front end of the segment; This refers to the deformation of the cast-in-place beam segment due to creep or shrinkage. A positive value indicates that the poured beam segment is arched. A negative value indicates the deflection of the poured beam segment, which is obtained from previous measured data. The effect of temperature change on the beam elevation is calculated from 24-hour temperature gradient monitoring data. When the temperature rises... It is a positive value when the temperature decreases. It is a negative value.

9. The control method for improving the construction accuracy of hanging baskets according to claim 8, characterized in that, Step 4 specifically includes: Concrete pouring adopts a symmetrical and balanced approach, strictly following the sequence of pouring the bottom slab first, then the web slab, and finally the top slab. The deformation of the formwork and the amount of concrete poured are monitored in real time during the pouring process, and the deformation warning value is calculated using the following formula: ; In the formula, This refers to the deformation warning value during the concrete pouring process of the hanging basket; This refers to the volume of concrete that has already been poured. The total concrete pouring volume designed for the hanging basket; When the measured deformation reaches 80% of the set warning value, the pouring speed is slowed down and the monitoring frequency is increased; when the measured deformation exceeds the warning value, the pouring is suspended in real time to investigate problems such as uneven load and abnormal hanging basket, and the pouring is resumed after the problems are resolved.

10. The control method for improving the construction accuracy of hanging baskets according to claim 9, characterized in that, Step 5 specifically includes: After the concrete pouring is completed, the curing stage begins. The curing temperature and beam deformation are monitored in real time. Before and after prestressing tensioning and at key curing nodes, the elevation and axis of the poured beam segments are systematically re-measured. The measured deformation data are substituted into the calculation formula for the formwork elevation to update the formwork elevation parameters of the next segment, thereby achieving linkage control of the construction of each segment and ensuring the smooth alignment of the entire bridge.