BIM-based intelligent reinforcement production scheduling and waste rate optimization method
By using a BIM-based intelligent rebar scheduling and scrap rate optimization method, rebar information is automatically extracted, a multi-constraint scheduling optimization model is constructed, and a hierarchical intelligent algorithm is used to generate the optimal scheduling scheme. Through real-time dynamic adjustment via the Internet of Things and closed-loop management of surplus materials, the problems of low rebar detailing accuracy, serious material waste, chaotic scheduling, and ineffective utilization of surplus materials in rebar processing are solved, thus realizing the automation and efficient utilization of rebar processing.
Patent Information
- Application Number
- CN202611276031.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-21
- Publication Date
- 2026-11-20
AI Technical Summary
The existing steel bar processing process suffers from problems such as low detailing accuracy, serious material waste, chaotic production scheduling, and ineffective utilization of surplus materials. Furthermore, the BIM model is not deeply integrated into the steel bar processing stage, resulting in information silos and poor algorithm adaptability.
Based on the BIM model, steel reinforcement information is automatically extracted, a multi-constraint material layout optimization model is constructed, a hierarchical intelligent algorithm is used to generate the optimal production plan, and the Internet of Things is used to dynamically adjust it in real time. Combined with the closed-loop management of surplus materials, a data closed-loop feedback mechanism is formed.
It has achieved automation and standardization of rebar detailing, reduced material waste, improved detailing efficiency and surplus material utilization, enhanced the flexibility and accuracy of production scheduling, and formed a self-learning optimization mechanism.
Smart Images

Figure CN123137236A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of steel bar processing technology, specifically to a BIM-based intelligent scheduling and waste rate optimization method for steel bars. Background Technology
[0002] Reinforced concrete structures are one of the most common building forms, and steel bars, as a key load-bearing material, typically account for 30% to 40% of the total cost of a structural project. The detailing, cutting, and production scheduling processes during steel bar processing directly determine material utilization and project costs. Currently, the industry's commonly used steel bar processing method is still dominated by manual experience: construction workers manually create detailing based on design drawings, then combine the lengths of the steel bars to form a cutting plan based on experience; production planning relies on manual scheduling, with processing arranged on-site according to the order sequence. This method has revealed many insurmountable shortcomings in long-term practice.
[0003] First, the accuracy of rebar detailing relies heavily on the individual experience of technicians. Differences in understanding drawings and standard specifications among different personnel can easily lead to errors in calculating cutting lengths, resulting in low detailing efficiency and difficulty in meeting the needs of large-scale, multi-variety projects. Second, the cutting process lacks a systematic optimization method. In most cases, simple cutting is performed only for individual components or a few lengths, failing to comprehensively consider the demand for various specifications of rebar, the inventory of various standard-length raw materials, and available surplus materials on site. This leads to serious waste of raw materials, with scrap rates generally reaching 10% to 15%, and a large amount of reusable short surplus materials are directly discarded. Third, in terms of production scheduling, due to the lack of quantitative analysis of equipment capacity, process bottlenecks, and order priorities, planning is often crude and lagging, unable to dynamically respond to on-site disturbances such as equipment failures and urgent orders. This results in both idle equipment and work-in-process inventory, leading to a low order delivery guarantee rate.
[0004] Furthermore, although Building Information Modeling (BIM) technology has been widely used in the design and construction phases, its deep integration in the rebar processing stage remains insufficient. The rich geometric and attribute information of rebar in the BIM model has not been effectively transferred to the material cutting optimization and production scheduling system, forming information silos. Although a few existing software programs can achieve basic rebar statistics or linear programming for material cutting, most are limited to single specifications, small scale, or idealized assumptions. They lack adaptability to complex scenarios in actual projects, such as multi-specification raw materials, waste material recycling, and process capacity constraints. Moreover, their algorithms are simplistic and struggle to maintain a balance between computational efficiency and optimization quality under different scale problems. Summary of the Invention
[0005] The purpose of this invention is to provide a BIM-based intelligent rebar scheduling and waste rate optimization method. This method uses the BIM model as the data source to establish a rebar cutting length calculation system; it adopts a hierarchical intelligent optimization algorithm to complete the optimal cutting and nesting; it achieves dynamic scheduling through real-time on-site data acquisition; it forms a closed-loop optimization by combining a rule library for reuse of surplus materials; and finally, it sends the optimal solution to automated equipment for execution, solving the technical problems of low detailing accuracy, serious waste of cutting materials, chaotic scheduling, and ineffective utilization of surplus materials in the existing rebar processing process.
[0006] This invention is achieved through the following technical solution:
[0007] The BIM-based intelligent scheduling and scrap rate optimization method for steel reinforcement includes the following steps:
[0008] Step 1: Based on the BIM model, automatically extract the information of the reinforcing bars and calculate the cutting length, and output a standardized rebar material list;
[0009] Step 2: Using the standardized steel bar material list output in Step 1 and the current steel bar raw material inventory data, construct a multi-constraint material layout optimization model with the objectives of maximizing utilization and minimizing surplus material;
[0010] Step 3: Based on the optimization model constructed in Step 2, the steel bar cutting and production scheduling scheme is automatically generated through a hierarchical combination intelligent algorithm;
[0011] Step 4: Collect on-site data in real time through the Internet of Things. When the actual progress deviates from the planned progress by more than a threshold, automatically reschedule production and update the production plan in Step 3.
[0012] Step 5: Implement hierarchical closed-loop management based on the surplus material data collected on-site, and feed back the information on reusable surplus materials to the raw material inventory in Step 2;
[0013] Step 6: Send the optimization plan generated in Step 4 to the automated equipment for execution and form a data closed-loop feedback and continuous optimization.
[0014] In this solution, the geometric and non-geometric information of the reinforcing bars is automatically extracted based on the BIM model, and the cutting length is calculated, avoiding the calculation errors and information silos of traditional manual rebar detailing. Moreover, a multi-constraint material layout optimization model is constructed with the goal of maximizing utilization and minimizing waste material, which can quickly generate the optimal cutting scheme under different project scales. At the same time, the Internet of Things collects on-site data in real time and dynamically adjusts the production schedule, and implements hierarchical closed-loop management of waste material, prioritizing the reuse of reusable waste material, further reducing raw material consumption. Finally, the optimized scheme is distributed to the automated equipment in the form of CNC code, and the actual processing data is collected to feed back the iterative algorithm parameters, forming a self-learning optimization mechanism. This effectively solves the technical problems of low detailing accuracy, serious waste material cutting, chaotic production scheduling, and inability to recycle waste material in traditional reinforcing bar processing.
[0015] Furthermore, step 1 specifically includes the following steps:
[0016] Step 11: Generate a three-dimensional rebar model using rebar modeling and detailing software. Automatically obtain rebar grade, diameter, design length, component location, and anchorage lap splice parameters from the three-dimensional rebar model. This overcomes the shortcomings of traditional manual detailing, which relies on personal experience, is prone to errors, and is inefficient. At the same time, it avoids the loss and isolation of design information during the transmission process.
[0017] Step 12: The bending adjustment value and hook increase value are automatically calculated according to the preset specification library to form a unified standard cutting length. This solves the problem of inconsistent and arbitrary calculation of bending adjustment value and hook increase value by various units in the current construction, and ensures the standardization and consistency of cutting length.
[0018] Step 13: Output a standardized steel bar material list containing a simplified shape diagram, cutting length, number of bars, and usage location. This realizes the structured storage and visualization of steel bar information, which not only provides a clean and accurate data source for subsequent cutting optimization and production scheduling, but also greatly facilitates technical briefings and processing operations for on-site construction personnel.
[0019] In summary, this solution further upgrades the calculation of rebar detailing and cutting length from a manual, experience-based model to an automated and standardized model, effectively eliminating human calculation errors and improving detailing efficiency.
[0020] Furthermore, to address the issues of length deviation and material waste caused by inconsistent standards and arbitrary parameters in traditional steel bar cutting length calculations, step 12 specifically includes the following steps:
[0021] The bending adjustment value is calculated based on the obtained bending angle, bending diameter, and rebar diameter. The hook increase value is calculated based on the obtained rebar type, hook angle, and straight section length. This accurately converts the outer dimensions in the design drawings into the cutting length based on the center axis, avoiding the cumulative errors caused by traditional manual estimation or simply applying fixed values. Furthermore, the bending adjustment value and hook increase value are dynamically configured according to current national standards or custom engineering parameters, enabling this method to flexibly adapt to the requirements of different types of projects such as bridges and buildings, as well as different rebar grades, diameters, and seismic resistance levels. Standardized applications across regions and projects can be achieved without modifying the core algorithm.
[0022] Furthermore, the objective function of the multi-constraint material layout optimization model is to minimize the total raw material consumption or the total waste length, and its specific formula is as follows:
[0023] ;
[0024] Where Z represents the objective function value, the smaller the value, the better the solution. The total number of cutting methods. Let j be the number of times the j-th cutting method is used, and it is an integer. Let be the length of the excess material produced by the j-th cutting method. This represents the maximum length of the remaining material among all raw materials.
[0025] The constraints of the model include at least: demand quantity constraints. Raw material length constraints Raw material inventory quantity constraints ,in, Let be the number of steel bars of the ith cutting length in the ith cutting method. Let i be the required number of steel bars of the i-th cutting length. Let L be the cutting length for the i-th type, where L is the standard length of the raw material, or the effective length after deducting the preset cutting loss; when the cutting loss is negligible, L is the standard length of the raw material. Let be the inventory quantity of raw material of specification t.
[0026] In this solution, the objective function is modified by introducing the concept of "subtracting the maximum remaining material length". This approach improves upon the traditional one-dimensional material cutting problem by subtracting the minimum total surplus material or the minimum number of pieces. Instead, it adopts an optimization-oriented approach of "actively retaining one long surplus material while controlling the total surplus material." This effectively solves the problem of existing methods failing to distinguish between two scenarios with the same total surplus material: "multiple short surplus materials" and "one long surplus material and the rest of the remaining zero surplus materials." This allows the solution to intentionally generate a reusable long surplus material while meeting all requirements, thus increasing the secondary utilization value of surplus materials in actual engineering projects. Furthermore, the model sets constraints on the quantity of demand, the length of raw materials, and the inventory quantity of multi-specification raw materials. The latter, in particular, groups the cutting methods according to raw material specifications and limits the usage quantity of each, avoiding the mixing of inventory of different specifications of raw materials and more closely reflecting the real-world scenario of limited inventory on construction sites.
[0027] Furthermore, to improve the engineering applicability and robustness of steel bar cutting, in step 3, the hierarchical combination intelligent algorithm includes:
[0028] Calculate the number of steel bar combinations (NR) and the total quantity (NT) for the cutting length. NR is calculated using the following formula:
[0029] , ;
[0030] The NT is calculated according to the following formula:
[0031] ;
[0032] wherein, fix is the floor function, L is the fixed length of the raw material, is the dimension of the steel bar of the j-th blanking length, is the maximum number of steel bars of the j-th blanking length that can be cut from each steel bar of fixed length, k is the number of types of steel bars of different blanking lengths, is the required number of steel bars of the i-th blanking length;
[0033] The steel bar blanking scale is divided into small scale, medium scale or large scale according to the numerical relationship between the NR and the NT, and different sub-algorithms are correspondingly called for solving, thereby avoiding the defects of low calculation efficiency or insufficient optimization quality that may occur when a single algorithm deals with problems of different scales.
[0034] Further, when the system determines that the problem is a small-scale problem, a linear programming combined with an AR local search algorithm is adopted, which can quickly enumerate limited cutting modes and obtain a theoretical optimal solution through the global optimization capability of linear programming, and then fine-tune non-integer solutions or remaining demands through AR local search, which ensures optimality while taking into account integer feasibility; when it is determined to be a medium-scale problem, an improved simulated annealing algorithm is used for global optimization, by setting a threshold for the number of times the local solution is not improved in the inner loop and the alternating action of AR local search, the iteration time is greatly reduced while avoiding falling into local optimum; when it is determined to be a large-scale problem, a hybrid sequential heuristic algorithm is adopted, by setting the number of levels and a residual material threshold, AISA is first used to search for high-utilization cutting modes and reuse them until a certain specification is exhausted, then the remaining demands are degraded to call LP-AR or AISA, which effectively avoids the problem of utilization rate decrease in the later stage of the sequential heuristic algorithm.
[0035] Further, in order to achieve the optimal balance between calculation efficiency and optimization quality, the above division rules are as follows:
[0036] When NR<Y, it is determined as a small-scale problem;
[0037] When NR≥Y and NT<P, it is determined as a medium-scale problem;
[0038] When NR≥Y and NT≥P, it is determined as a large-scale problem;
[0039] wherein, Y and P are preset thresholds, the value range of Y is 3000 to 8000, and the value range of P is 300 to 800.
[0040] Further, in order to solve the problems of the response capability to disturbances at the steel bar processing site and the overall production efficiency, the real-time collection of on-site data through the Internet of Things and dynamic adjustment of the production scheduling scheme include:
[0041] Real-time data collection of equipment operating status, process completion progress, and actual remaining material data; calculation of process load rate. :
[0042] ;
[0043] in, The total required man-hours for the process. Available capacity for the process;
[0044] When η≥70%, it is identified as a bottleneck process, and the output rhythm of the bottleneck process is used as the production scheduling drumbeat;
[0045] When the deviation between the actual progress and the planned progress Δ exceeds the preset threshold δ, production rescheduling is automatically triggered, updating the start and end times of the remaining tasks. This avoids order delays caused by traditional manual scheduling due to the inability to respond promptly to disturbances such as equipment failures, emergency orders, or material shortages.
[0046] Furthermore, the graded closed-loop management and priority reuse of surplus steel bars includes:
[0047] Based on the ratio of the surplus material length Lr to the raw material length L, λ = Lr / L, the surplus material is divided into at least three grades:
[0048] When λ≥λ1, it is included in the reusable surplus material warehouse;
[0049] When λ2≤λ<λ1, the orientation is used for non-principal load-bearing components;
[0050] When λ < λ2, it is treated as waste.
[0051] Wherein, λ1 takes values of 0.25 to 0.30, and λ2 takes values of 0.08 to 0.12;
[0052] When optimizing the material cutting for a new batch, the system matches leftover materials according to the following priority rules:
[0053] ;
[0054] in Let be the number of the i-th type of steel bars in the scrap cutting scheme. Its length.
[0055] This solution transforms short, discarded rebar scraps into recyclable resources by implementing a three-level quantitative classification based on the length ratio λ (reusable scrap warehouse, targeted use for non-main load-bearing components, and waste disposal) and a minimum difference matching rule when cutting new batches. This significantly reduces raw material waste and forms a closed-loop management mechanism.
[0056] Furthermore, step 6 specifically includes: transmitting the material cutting plan and production schedule to the steel bar processing equipment via IoT protocol in the form of CNC code or task sheet; automatically feeding back the actual number of steel bars processed, time consumed, and residual material output after the equipment completes processing; comparing the actual and planned data, identifying the source of deviation, and iteratively updating the algorithm parameters or thresholds.
[0057] In this solution, the optimized cutting plan and production schedule are directly transmitted to the rebar processing equipment via IoT protocol in the form of CNC code or task sheet. After the equipment completes processing, it automatically provides feedback on the actual number of bars processed, the time taken, and the amount of leftover material produced. This achieves an end-to-end data loop from the optimization algorithm to the equipment execution, eliminating the information gap between the cutting plan and the CNC equipment in traditional rebar processing. Based on this, the system automatically compares the actual data with the planned data, calculates the bar count deviation rate and the time taken deviation rate. When the deviation continuously exceeds the threshold, it automatically identifies the source of the deviation and iteratively updates the algorithm parameters or thresholds accordingly (such as correcting the processing time in the time library, adjusting the convergence factor of the optimization model, or the leftover material classification threshold). This gives the entire optimization system the ability to learn and evolve. At the same time, it avoids the decay of optimization effect caused by long-term use of initial parameters, realizing a continuous improvement cycle of "execution-feedback-optimization-re-execution".
[0058] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0059] 1. This invention automatically generates a 3D steel bar model through a parametric modeling plugin developed in Revit, and automatically calculates the bending adjustment value and hook increase value according to a preset specification library. This achieves standardized extraction of steel bar information and accurate calculation of cutting length, avoiding errors and information silos caused by experience differences and atlas misunderstandings in traditional manual detailing, and realizing the standardization and automation of cutting length calculation.
[0060] 2. This invention uses two quantitative indicators, NR (number of steel bar combinations by cutting length) and NT (total quantity), to automatically classify problems into small-scale, medium-scale, and large-scale, and then matches them with hybrid algorithms, improved simulated annealing algorithms, and hybrid sequential heuristic algorithms respectively, overcoming the shortcomings of low computational efficiency or poor optimization quality of single algorithms under different scales.
[0061] 3. This invention transmits the optimized material cutting scheme and production schedule directly to the steel bar processing equipment via IoT protocol in the form of CNC code. After the equipment completes the process, it automatically feeds back the actual number of steel bars processed, the time consumed, and the remaining material data. The system compares the deviation between the plan and the actual situation, identifies the source of the deviation, and iteratively updates the algorithm parameters or thresholds. This self-learning mechanism enables the accuracy of subsequent batch production scheduling to continue to improve, avoiding the decay of optimization effects during long-term operation.
[0062] 4. Starting from the BIM model, this invention forms a complete intelligent steel bar production and waste rate optimization chain through information extraction, multi-constraint optimization, hierarchical intelligent algorithm solution, IoT dynamic scheduling, closed-loop reuse of surplus materials, and equipment execution and feedback. Moreover, the bending adjustment value and hook increase value can be dynamically configured according to different national standards or custom parameters of the project, so that it can flexibly adapt to various engineering scenarios such as building construction, bridges, and tunnels. Attached Figure Description
[0063] The accompanying drawings, which are included to provide a further understanding of embodiments of the invention and form part of this application, do not constitute a limitation thereof. In the drawings:
[0064] Figure 1 This is a flowchart of the present invention;
[0065] Figure 2 This is a flowchart of the BIM information extraction and material cutting length calculation process of the present invention. Detailed Implementation
[0066] To make the objectives, technical solutions, and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the embodiments and accompanying drawings. The illustrative embodiments and descriptions of the present invention are only used to explain the present invention and are not intended to limit the present invention.
[0067] Example 1
[0068] This embodiment 1 provides a BIM-based intelligent rebar scheduling and scrap rate optimization method using a bridge engineering rebar cutting and production optimization case study. Figure 1 As shown, it includes the following steps:
[0069] Step 1: Automatically extract rebar information and calculate cutting length based on the BIM model;
[0070] First, a BIM model of the bridge's superstructure and substructure was created in Revit software. The model's detail level reached LOD400, including the geometric dimensions, concrete strength grade, and reinforcement information of components such as pile foundations, abutments, piers, and box girders. This invention utilizes a Revit secondary development plugin (such as...) Figure 2 The parametric modeling module shown in the figure automatically generates a three-dimensional rebar model. Other rebar modeling and detailing software with similar functions can also be used to generate a three-dimensional rebar model. This embodiment does not impose any specific limitations.
[0071] Specifically, by clicking the "Reinforcement Information Extraction" button in the Revit interface, the plugin uses FilteredElementCollector to filter all structural components, then iterates through the reinforcement elements in each component to obtain the reinforcement grade (e.g., HPB300, HRB400), diameter (e.g., 6mm, 10mm, 18mm), design length (outer dimensions in the design drawings), component location (e.g., "a precast web of a side box"), and anchorage lap parameters (e.g., seismic anchorage length coefficient, lap length coefficient). The plugin stores these parameters in a temporary data table.
[0072] Subsequently, the bending adjustment value and hook increase value are automatically calculated according to the preset specification library. In this embodiment, based on the "Technical Specification for Construction of Highway Bridges and Culverts" (JTG / T3650—2020), for a 180° hook at the end of an HPB300 rebar, the bending radius D = 2.5d and the straight section length L = 3d are taken. The formula M180° = π(2.5d + d) × 180 / 360 + 3d − (2.5d / 2 + d) = 6.25d Calculate the hook increase; for a 90° hook of HRB400 rebar, take D=5d, straight section L=10d, increase M90°=11.21d; for the bending adjustment value, substitute the bending angles of 45°, 60°, and 90° into the formula W=(D+2d)tan(α / 2)−π(D+d)α / 360, where the bending radius of bridge rebar is D=20d, and calculate W45°=0.866d, W60°=1.706d, W90°=5.507d. The preset specification library supports user-defined parameters, for example, in the project settings interface (…). Figure 2 (Not shown in the text but part of the plugin) allows modification of bending radius coefficient, straight section length, etc., with dynamic configuration of adjustment values. The plugin subtracts the bending adjustment value from the outer dimensions of the design drawing and adds the hook increment value to obtain the precise cutting length of each rebar.
[0073] Finally, a standardized steel reinforcement bill of materials is output in Excel format, containing a simplified shape diagram of each steel bar (automatically generated from Revit elements), cutting length, required number of bars, and application location (e.g., "one side box precast web - longitudinal reinforcement"). The bill of materials is automatically uploaded to the system database as input for subsequent optimization.
[0074] Step 2: Construct a multi-constraint material layout optimization model with the objectives of maximizing utilization and minimizing waste material;
[0075] The system reads the standardized material list from the database to obtain the set of lengths of all steel bars to be cut. and required number of elements Simultaneously, it reads the current inventory information of steel rebar raw materials: This embodiment provides two standard lengths of raw materials, 9 meters and 12 meters, with inventory quantities of respectively. =500 roots =800 pieces. The system automatically establishes a multi-constraint material layout optimization model, with the objective function as follows:
[0076] ;
[0077] Where Z represents the objective function value, the smaller the value, the better the solution; m is the total number of cutting methods; and the decision variable is... Let j be the number of times the j-th cutting method is used, and it is an integer. Let be the length of the excess material produced by the j-th cutting method. The maximum length of the remaining material among all raw materials; the constraints of this model include at least:
[0078] Demand quantity constraints ,in, Let be the number of steel bars of the ith cutting length in the ith cutting method. Let be the required number of steel bars of the i-th cutting length, ensuring that the total number of steel bars cut for each cutting length equals the required quantity;
[0079] Raw material length constraints ,in, Let L be the cut length for the i-th type, where L is the standard length of the raw material (9m or 12m), or the effective length after deducting the preset cutting loss; when the cutting loss is negligible, L is the standard length of the raw material.
[0080] Raw material inventory quantity constraints , That is, the number of raw materials consumed for 9m and 12m are respectively limited to not exceeding the inventory.
[0081] Step 3: Automatically generate rebar cutting and production scheduling plans using a hierarchical combination intelligent algorithm;
[0082] The system first calculates the number of rebar combinations (NR) and the total quantity (NT) for each cutting length. In this example, there are 46 different cutting lengths of rebar (k=46), with a raw material length of L=12m (NR is calculated using 12m as an example; the same applies to 9m). For each cutting length... Calculate the maximum number of steel bars of the j-th cutting length that can be cut from each standard length steel bar. ,but The calculated NR is approximately 8230. Total quantity , is the required number of rebars of the i-th blanking length. In this embodiment, the total required number of all types of rebars is 1876. The preset threshold Y=5000, P=500. Since NR=8230≥Y and NT=1876≥P, the system determines that it is a large-scale blanking problem. In other embodiments, if NR<Y, it is determined as a small-scale problem, and if NR≥Y and NT<P, it is determined as a medium-scale problem.
[0083] The system automatically invokes the hybrid SHP sequential heuristic algorithm for solving. Algorithm parameter settings: number of levels F=500, initial temperature T0=10×N (N=1876), cooling coefficient α=0.98, number of non-improvements of local optimal solution NUM=20, number of outer loops=10. The algorithm first generates an initial solution sequence, adopts a decimal real number coding method, and randomly shuffles and merges the raw material rebar sequence and the blanking length rebar sequence. Iterative optimization is performed through the AR local search algorithm (Adapt Replacement): for each raw material, calculate the current remaining material , find the maximum rebar with a length less than among the uncut rebars , and swap their positions, so as to improve the utilization rate of a single raw material. Every time a blanking method that meets the remaining material threshold YL (YL=0.2m in this embodiment) is found, this method is repeatedly used until the demand for rebars of a certain blanking length is zero. After multi-layer iterations, the types and quantities of remaining unblanked rebars decrease, NR and NT are recalculated, the problem is downgraded to a small-scale problem, and the LP-AR algorithm (linear programming combined with AR local search) is invoked to complete fine nesting, and output the optimal nesting scheme. The scheme includes using 501 pieces of 12m raw material, 0 pieces of 9m raw material (due to sufficient inventory), and the remaining material length of the last raw material is 1.28m (≥0.25×12m), which is convenient for reuse. At the same time, a production scheduling scheme is generated: according to the rebar type and use position corresponding to each blanking method, the cutting operation sequence is generated according to the flow sequence of the formwork table.
[0084] Step 4: Collect on-site data in real time through the Internet of Things and dynamically adjust the production scheduling scheme;
[0085] In this embodiment, in the rebar processing workshop, each numerical control device (such as a rebar bending center, a shearing production line) collects the equipment operating status (running / standby / fault), the completion progress of the current process (number of completed pieces / planned number of pieces), and the length of remaining material generated by cutting. The collected data is uploaded to the IoT cloud platform via the MQTT protocol, and the cloud platform pushes it to the production scheduling module in real time. The system calculates the load rate of each process , where is the total required working hours of the process is the available capacity of the process; when η≥70%, it is identified as a bottleneck process, and the output beat of the bottleneck process is taken as the production scheduling drumbeat.
[0086] In this embodiment, the total required time for the grinding process is... =320 hours, available capacity =380 hours, η=84.2%≥70%, the system automatically identifies this process as the bottleneck process, and uses the output rhythm of the bottleneck process (15 steel bars per hour) as the production rhythm of the entire production line. A time buffer (feeding materials 2 hours in advance) and an inventory buffer (keeping 20 work-in-process) are set before the bottleneck process. The upstream process pulls production (rope) according to the bottleneck demand, and the downstream process pushes production.
[0087] During production, if a temporary equipment failure occurs (such as a 40-minute downtime of the bending machine), the IoT platform detects that the equipment status changes from "running" to "faulty," and the actual progress lags behind the planned progress by Δ=1.2 hours, exceeding the preset threshold δ=1 hour. The system will automatically trigger a rescheduling: based on the current work-in-process status (the quantity of completed rebars and the distribution of work-in-process), recalculate the start and end times of the remaining tasks, update the production scheduling Gantt chart, and distribute it to the operators.
[0088] Step 5: Implement graded closed-loop management and prioritize reuse of leftover steel bars;
[0089] After cutting, the leftover material is automatically conveyed to the leftover material collection area. On-site operators use a handheld barcode scanner to scan the QR code on the leftover material (the QR code is printed and affixed by the IoT system in step 4), and simultaneously measure the actual length Lr of the leftover material and input it into the system. The system classifies the material according to the ratio λ = Lr / L between the length Lr of the leftover material and the standard length L (12m) of the raw material.
[0090] When λ≥λ1 (λ1 is 0.28), i.e. Lr≥3.36m, it is included in the reusable surplus material library. In this embodiment, a total of 78 reusable surplus materials are generated. The system generates a unique code for each material, records its length, diameter, rebar grade, and source component, and stores it in the surplus material table of the MySQL database.
[0091] When λ2≤λ<λ1 (λ2 is 0.10), that is, 1.2m≤Lr<3.36m, it is oriented for non-main load-bearing components (such as pads, positioning bars, and stirrups). In this embodiment, 42 short surplus materials are generated, and the system automatically marks their uses and temporarily stores them in a special material rack.
[0092] When λ < λ2, i.e., Lr < 1.2m, it is treated as waste and automatically removed by the waste recycling device.
[0093] When a new batch of orders arrives, the system prioritizes matching the surplus material inventory in the optimization model of step 2. The matching rule is:
[0094] This involves selecting the scrap material closest to the total length required by the current cutting plan for nesting. For example, a new order requires 5 steel bars of 2.8m length, with a total required length of 14m. The system first traverses the scrap material library to find a single scrap material with a length close to 14m (e.g., an 11.8m scrap material can be cut into 4 2.8m pieces, and another 2.8m scrap material can be used to make up the 5th piece). If a single scrap material cannot cover the entire requirement, the system automatically starts a combination matching of multiple scrap materials. For example, it selects an 8.6m scrap material (which can be cut into 3 2.8m pieces, leaving 0.2m of scrap) and a 5.8m scrap material (which can be cut into 2 2.8m pieces, leaving 0.2m of scrap), with a total length of 14.4m. After combining, it cuts into 5 2.8m steel bars (total requirement 14m), with a total scrap material of only 0.4m, achieving a comprehensive utilization rate of 97.2%. If no directly matching combination of surplus materials is available, the system prioritizes consuming the surplus materials in inventory, with the remaining portion replenished by new raw materials. In this embodiment, all surplus materials used originate from the reusable surplus material warehouse generated during the early stages of construction in this project. Their material costs have already been amortized in the earlier phases of the project; therefore, this batch's accounting only calculates the consumption of newly added raw materials. The surplus material yield rate is calculated as the percentage of the actual effective length produced relative to the usable length of the surplus material. If the surplus materials come from shared inventory from external projects, a surplus material discount cost item needs to be added to the cost accounting, but this does not affect the core optimization logic of this method.
[0095] Step 6: Distribute the optimization plan to the automated equipment for execution and form a data closed-loop feedback and continuous optimization;
[0096] The final optimized plan (including the cutting combination table and production schedule) is sent from the server to the edge intelligent gateway, which converts it into CNC code (such as G-code or custom instructions) that the PLC can recognize. The equipment automatically retrieves the code to execute cutting and bending. After each rebar is completed, the PLC reports the actual number of rebars processed, the time taken for the current process, and the actual length of remaining material. After receiving the feedback data, the system compares it with the planned data and calculates the rebar count deviation rate. ×100% and time-consuming deviation rate ×100%. When 3 consecutive batches show... >5% or When the deviation rate is greater than 10%, the system automatically identifies the source of the deviation (in this embodiment, the calculated value of the longitudinal reinforcement bending adjustment value does not match the actual rebound deviation). Based on this, the bending adjustment value parameter in the standard time library is updated, and the convergence factor of the optimization model is adjusted from 0.98 to 0.96 until the deviation rate drops to less than 2%.
[0097] Example 2
[0098] This embodiment takes the standard floor reinforcement engineering of a high-rise residential building as the application object, and provides a BIM-based intelligent reinforcement scheduling and waste rate optimization method, such as... Figure 1 and Figure 2 As shown, it includes the following steps:
[0099] Step 1: BIM information extraction and blanking length calculation;
[0100] Establish a BIM model of the standard floor structure of this residential building (including columns, beams, slabs, and walls) in Revit. Extract all rebar information through the Revit plug-in of the present invention (the same as that in Embodiment 1, the structure is as Figure 2 shown). Since the specifications for rebar hooks and bends in housing construction engineering are different from those in bridges, this embodiment dynamically configures the specification library as "Code for Construction of Concrete Structure Engineering" (GB50666-2011) in the engineering settings: For HRB400 grade ribbed rebars, the bend adjustment value is calculated according to D=4d; for 135° hooks of stirrups, when there is a seismic requirement, the straight section length takes max(10d, 75mm), and the hook added value is calculated according to the formula (the same as that in Embodiment 1). The plug-in automatically calculates the blanking length of each stirrup and longitudinal rebar, and outputs a standardized rebar material list.
[0101] Step 2: Construction of multi-constraint nesting optimization model;
[0102] In this embodiment, the raw material inventory is 300 pieces of 9m fixed-length rebars and 200 pieces of 12m fixed-length rebars. There are 12 lengths of rebars to be blanked, and the total number of required pieces is only 156. The system automatically calculates , where the maximum is 4.2m, the minimum is 0.9m, NR≈1620; NT=156. The preset threshold values Y=3000, P=300, since NR=1620<Y, the system determines that it is a small-scale blanking problem. The objective function and constraint conditions are the same as those in Embodiment 1, but only small-scale solving needs to be considered.
[0103] Step 3: Hierarchical combined intelligent algorithm, that is, small-scale LP-AR solving;
[0104] The system calls the LP-AR algorithm. First, enumerate all feasible cutting methods (about 3200 kinds in this embodiment), and establish a linear programming model: the decision variable is the number of times each cutting method is used, and the objective function . Call the linprog function in the MATLAB optimization toolbox to solve the linear relaxation solution, round down after obtaining the non-integer solution, and obtain the initial nesting scheme A1. Calculate the number of remaining rebars that are not satisfied (16 pieces remain in this embodiment), then call the AR local search algorithm to optimize the remaining rebars, and generate scheme B1. Combine A1 and B1 to get the final scheme: 0 pieces of 9m rebars are used (because the overall utilization rate of 12m raw materials is higher), 65 pieces of 12m rebars are used, and the remaining material length of one raw material reaches 2.8m (λ=0.233, close to the lower limit of λ1), which can be stored in the warehouse as reusable remaining material.
[0105] Step 4: Dynamic scheduling and bottleneck elimination via the Internet of Things;
[0106] In this embodiment, the IoT system collects real-time data on the processing time of each workstation on the production line: infrared sensors detect the position of the mold table, current sensors monitor equipment start-up and shutdown, and industrial cameras identify the completion status of rebar tying. The system calculates the load rate of each process: the required working time for the longitudinal material laying process. =22 hours, available capacity =After 28 hours, η=78.6%≥70%, it is identified as a bottleneck. The system uses the rhythm of this process as the drumbeat, and sets up 10 buffer work-in-process molds in front of the bottleneck. The upstream straightening and shearing process pulls the material in accordance with the bottleneck.
[0107] Step 5: Graded management and priority reuse of surplus materials;
[0108] In this embodiment, the reusable surplus material library has accumulated 23 long surplus materials (Lr≥0.25×12m=3m) from previous batches, including one 5.8m surplus material, one 4.6m surplus material, and two 3.6m surplus materials. When optimizing the material cutting for new orders, the system prioritizes matching the surplus material library: using the formula... The system prioritizes matching single scrap materials. When a single scrap material cannot meet the demand, the system automatically expands to matching multiple scrap materials in combination, and completes the cutting with new raw materials. For example, a new order requires 8 2.8m steel bars (total required length 22.4m). The system retrieves two scrap materials from the scrap material library: 5.8m and 4.6m (total combined length 10.4m). It cuts out 2 and 1 2.8m steel bars respectively (3 in total), with scrap lengths of 0.2m and 1.8m respectively (the 1.8m is marked as a short scrap). The remaining 5 2.8m steel bars (required length 14m) are completed using two 12m raw materials: the first is cut into 2 pieces (4m used, 8m remaining in the library), and the second is cut into 3 pieces (8.4m used, 3.6m remaining in the library). Two 12m lengths of raw material were actually consumed, along with 10.4m of surplus material, resulting in a surplus material yield of 80.8%. After including the reuse of 3.6m of surplus material in subsequent batches, the overall surplus material reuse rate reached 72%. In this embodiment, the surplus material warehouse is a shared inventory within the project, and the cost of the surplus material has already been amortized in the previous phases of the project; therefore, only the newly added raw material consumption is accounted for.
[0109] Step 6: Equipment execution and data closed-loop feedback;
[0110] The optimization plan was sent to the CNC steel bar processing equipment via the Internet of Things. After the equipment executed the plan, it automatically reported the actual data. The system comparison found that the deviation of a certain batch of consumables reached 8%. After analysis, it was found that the straight section length of the stirrup hook was calculated to be 75mm, which did not match the actual requirement of 80mm on site. The system automatically updated the straight section parameter in the specification library to 80mm and recalculated the cutting length of subsequent orders until the deviation rate stabilized within 2%.
[0111] In summary, Examples 1 and 2 demonstrate the application effects of the present invention in large-scale bridge engineering and small-scale building construction projects, respectively. They fully reflect the technical advantages of the present invention in BIM information extraction, multi-constraint optimization, hierarchical combination algorithm, IoT dynamic scheduling, waste material closed-loop management, and self-learning feedback. The invention can significantly improve the utilization rate of steel bars, reduce the waste rate, and shorten the scheduling cycle, and has wide engineering applicability.
[0112] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of the present invention. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A BIM-based intelligent rebar scheduling and scrap rate optimization method, characterized in that, comprising the following steps: Step 1: Automatically extract rebar information and calculate the blanking length based on the BIM model, and output a standardized rebar material list; Step 2: Construct a multi-constraint nesting optimization model with the goals of maximizing utilization rate and minimizing remnant material based on the standardized rebar material list output in Step 1 and the current rebar raw material inventory data; Step 3: According to the optimization model constructed in Step 2, automatically complete the generation of rebar nesting and production scheduling schemes through a hierarchical combined intelligent algorithm; Step 4: Collect on-site data in real time through the Internet of Things, and automatically reschedule production to update the production scheduling scheme in Step 3 when the deviation between the actual progress and the planned progress exceeds a threshold; Step 5: Perform hierarchical closed-loop management according to the remnant material data collected on site, and feed the reusable remnant material information back to the raw material inventory in Step 2; Step 6: Issue the optimization scheme generated in Step 4 to automated equipment for execution, and form data closed-loop feedback and continuous optimization.
2. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 1, characterized in that, Said Step 1 specifically comprises the following steps: Step 11: Generate a three-dimensional rebar model through rebar modeling and detailing software, and automatically obtain the rebar grade, diameter, design length, component position, and anchorage and lap parameters from said three-dimensional rebar model; Step 12: Automatically calculate the bending adjustment value and hook increment value according to the preset specification library to form a unified standard blanking length; Step 13: Output a standardized rebar material list including shape sketch, blanking length, number of pieces, and use position.
3. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 2, characterized in that, Said Step 12 specifically comprises the following steps: Calculate the bending adjustment value according to the obtained rebar bending angle, bending diameter and rebar diameter; Calculate the hook increment value according to the obtained rebar type, hook angle and straight section length; Said bending adjustment value and hook increment value are dynamically configured according to the current national specifications or project custom parameters.
4. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 1, characterized in that, The objective function of said multi-constraint nesting optimization model is to minimize the total raw material consumption or minimize the total waste length, and the specific formula is: ; Where Z represents the objective function value, the smaller the value, the better the solution. The total number of cutting methods. Let j be the number of times the j-th cutting method is used, and it is an integer. Let be the length of the excess material produced by the j-th cutting method. This represents the maximum length of the remaining material among all raw materials. The constraints of the model include at least: demand quantity constraints. Raw material length constraints Raw material inventory quantity constraints ,in, Let be the number of steel bars of the ith cutting length in the ith cutting method. Let i be the required number of steel bars of the i-th cutting length. Let L be the cutting length for the i-th type, where L is the standard length of the raw material, or the effective length after deducting the preset cutting loss; when the cutting loss is negligible, L is the standard length of the raw material. Let t be the inventory quantity of the t-th specification of raw material.
5. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 1, characterized in that, In said Step 3, said hierarchical combined intelligent algorithm comprises: Calculating the number NR of rebar combination modes for blanking lengths and the total number NT, and said NR is calculated according to the following formula: , ; Said NT is calculated according to the following formula: ; Where fix is the floor function, and L is the standard length of the raw material. Let j be the dimensions of the steel bar with the j-th cutting length. Let k be the maximum number of steel bars of the j-th cutting length that can be cut from each standard length steel bar, and k be the number of types of steel bars of cutting length. The required number of steel bars of the i-th cutting length; Divide the rebar blanking scale into small scale, medium scale or large scale according to the numerical relationship between said NR and said NT, and call different sub-algorithms correspondingly for solution.
6. The BIM-based intelligent rebar production scheduling and waste rate optimization method according to Claim 5, characterized in that, Linear programming combined with local search is used for solving small-scale blanking; An improved simulated annealing algorithm is used for global optimization for medium-scale blanking; A hybrid sequential heuristic algorithm is used for optimization for large-scale blanking; The system automatically matches the algorithm according to the blanking scale and outputs the optimal nesting scheme.
7. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 5, characterized in that, Said division rules are: When NR<Y, it is determined as a small-scale problem; When NR≥Y and NT<P, it is determined as a medium-scale problem; When NR≥Y and NT≥P, it is determined as a large-scale problem; wherein Y and P are preset thresholds, the value range of Y is 3000 to 8000, and the value range of P is 300 to 800.
8. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 1, characterized in that, Said collecting on-site data in real time through the Internet of Things and dynamically adjusting the production scheduling scheme comprises: Real-time data collection of equipment operating status, process completion progress, and actual remaining material data; calculation of process load rate. : ; in, The total required man-hours for the process. Available capacity for the process; When η≥70%, it is identified as a bottleneck process, and the output rhythm of the bottleneck process is used as the production scheduling drumbeat; When the deviation Δ between the actual progress and the planned progress exceeds the preset threshold δ, a rescheduling is automatically triggered, updating the start and end times of the remaining tasks.
9. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 1, characterized in that, The graded closed-loop management and priority reuse of steel reinforcement scraps includes: Based on the ratio of the surplus material length Lr to the raw material length L, λ = Lr / L, the surplus material is divided into at least three grades: When λ≥λ1, it is included in the reusable surplus material warehouse; When λ2≤λ<λ1, the orientation is used for non-principal load-bearing components; When λ < λ2, it is treated as waste. Wherein, λ1 takes values of 0.25 to 0.30, and λ2 takes values of 0.08 to 0.12; When optimizing the material cutting for a new batch, the system matches leftover materials according to the following priority rules: ; in Let be the number of the i-th type of steel bars in the scrap cutting scheme. Its length.
10. The BIM-based intelligent steel reinforcement scheduling and scrap rate optimization method according to claim 1, characterized in that, Step 6 specifically includes: transmitting the material cutting plan and production schedule to the steel bar processing equipment via IoT protocol in the form of CNC code or task sheet; automatically feeding back the actual number of steel bars processed, time consumed, and residual material output after the equipment completes processing; comparing the actual and planned data, identifying the source of deviation, and iteratively updating the algorithm parameters or thresholds.