Shielded TBM surrounding rock shield contact extrusion prediction method
By filling the space between the shield and the surrounding rock with equivalent solid units and using a progressive transition modulus recovery method, the inaccuracy of the shield-type TBM surrounding rock shield contact compression prediction in the prior art has been solved, achieving more accurate assessment of frictional resistance and jamming risk, and supporting safe construction of deep-buried soft rock tunnels.
Patent Information
- Application Number
- CN202611644825.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-23
- Publication Date
- 2026-11-20
AI Technical Summary
Existing technologies struggle to accurately reconstruct the dynamic interaction between the surrounding rock and the shield during the contact compression process of shield-type TBMs, particularly in terms of the reasonable dispersion of thin-walled shields, dynamic triggering of excavation gaps, and segment load transfer, leading to inaccurate predictions of machine jamming.
A three-dimensional finite difference model is adopted. By filling the excavation gap between the shield and the surrounding rock with equivalent solid elements whose deformation modulus is lower than that of the surrounding rock as a transition medium for transferring stress and displacement, combined with single-step dynamic cyclic excavation and the progressive transition modulus recovery method of equivalent solid elements, the normal displacement is monitored and the modulus is updated to establish contact compression between the shield and the surrounding rock, and the contact stress distribution and frictional resistance are output.
It enables continuous characterization of the contact stress between the shield and the surrounding rock, reduces abrupt changes in contact pressure, improves the accuracy of frictional resistance and jamming prediction, can reproduce the real process of surrounding rock deformation, and supports the safe construction of deep-buried soft rock tunnels.
Smart Images

Figure CN123139698A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel and underground engineering construction technology, specifically to a method for predicting contact compression of the surrounding rock shield of a shield-type TBM. Background Technology
[0002] The gestation process of a shield-type TBM jamming disaster essentially involves the surrounding rock deforming beyond the pre-reserved excavation gap of the cutterhead, leading to full contact and compression between the surrounding rock and the shield. The interfacial frictional resistance continuously increases with the deformation of the surrounding rock, taking into account aging deformation, eventually exceeding the rated thrust of the equipment. Therefore, accurately recreating the dynamic process of contact compression between the surrounding rock and the shield before actual contact is a prerequisite for jamming mechanism analysis and risk prediction. Existing technologies for predicting the interaction between the TBM surrounding rock and the shield mainly focus on the following directions.
[0003] One approach is the one-time tunneling method, which involves excavating the tunnel excavation area in a single step in the numerical model, applying support, and then solving for the surrounding rock deformation. This method is often used for the rapid assessment of the surrounding rock stability of conventional tunnels. However, this approach has limitations in reproducing the real process of the TBM gradually excavating and the surrounding rock gradually unloading and deforming as it progresses. It also has limited ability to characterize the spatial effects at the tunnel face and the convergence gradient of the surrounding rock along the axial direction, which in turn affects the accurate description of the contact state at each section of the shield.
[0004] Another approach treats the shield as a conventional solid element and sets up a conventional contact surface between the shield and the surrounding rock for interaction calculation. Since the TBM shield is extremely thin relative to the excavation diameter and the segment thickness, it is easy to cause mesh distortion and calculation instability when treated with conventional solid elements. If the excavation gap area is directly hollowed out, the transmission of stress and displacement in this area will be limited, affecting the accuracy of the characterization of the contact timing.
[0005] Another approach is a simplified simulation that does not include dynamic gap closure transition and ignores segment load transfer. It approximates the rock-shield action with preset fixed contact conditions, or only the shield supports the rock. This approach has limited ability to reproduce the dynamic triggering mechanism that "the rock deformation reaches the excavation gap and then changes from non-contact to contact compression", which affects the accuracy of contact pressure estimation. Moreover, when the load transfer from the shield tail segment to the shield is not taken into account, the resulting rock compression force on the shield is too large.
[0006] It is evident that existing technologies still need improvement in aspects such as the dynamics of gradual excavation, the reasonable dispersion of thin-walled shields, the dynamic triggering of contact compression from no contact in the excavation gap, and the transfer of segment loads. In particular, the establishment of contact is often treated as a binary event of geometric penetration or a single displacement threshold, and the contact stiffness changes abruptly at the triggering moment, which in turn affects the shield contact stress and even the accuracy of the calculated frictional resistance and jamming criteria. Summary of the Invention
[0007] This invention proposes a prediction method for contact compression of the surrounding rock shield in shield-type TBMs. It addresses the technical problems of distorted prediction results caused by deficiencies in existing shield-type TBM contact compression prediction methods, such as the inability to reconstruct the dynamic process of the surrounding rock from non-contact to contact compression, reasonable discretization of thin-walled shields, dynamic triggering of excavation gaps, and segment load transfer.
[0008] To address the aforementioned technical problems, this invention provides a method for predicting contact compression of a shield-type TBM surrounding rock shield, comprising the following steps: Step S1: Based on the burial depth of the tunnel section to be predicted, the mechanical parameters and time-dependent deformation parameters of the surrounding rock, as well as the shield length and shield radius of the TBM, a three-dimensional finite difference model is constructed. Solid elements are used to simulate the surrounding rock and tunnel segments, and structural elements are used to simulate the shield. An equivalent solid element with a deformation modulus lower than that of the surrounding rock is filled in the excavation gap between the shield and the surrounding rock as a transition medium for transmitting stress and displacement. Step S2: Apply vertical ground stress to the three-dimensional finite difference model according to the burial depth. And complete the initial geostress equilibrium, where The density of the overlying rock strata. For burial depth; Step S3: Perform dynamic cyclic excavation in a single-step advance manner. In each excavation step, apply equivalent excavation face support pressure to the face to simulate cutterhead thrust and redistribute it as the face advances. At the same time, remove the equivalent excavation face support pressure at the previous face position, drive the shield to move forward one advance along the axis, install segments at the shield tail, and grout backfill the annular gap between the segments and the surrounding rock. Convert the actual time required for a single excavation advance into creep time steps according to the construction speed, and advance the corresponding creep time steps in each excavation step to take into account the time deformation of the surrounding rock. In each excavation step, monitor the normal displacement of the surrounding rock adjacent to the equivalent solid unit. Update the deformation modulus of the equivalent solid unit according to the relationship between the normal displacement and the excavation gap, so that it recovers from the deformation modulus of the transition medium to the deformation modulus of the surrounding rock to establish contact compression between the shield and the surrounding rock, and output the contact stress distribution on the shield surface. Step S4: Integrate the contact stress distribution along the shield surface to obtain the frictional resistance of the surrounding rock to the shield, and predict the jamming state of the tunnel section to be predicted based on the relationship between the thrust required to overcome the frictional resistance, the thrust required for normal continuous tunneling of the TBM, and the rated thrust of the TBM; wherein, when the sum of the thrust required to overcome the frictional resistance and the thrust required for normal continuous tunneling of the TBM is greater than the rated thrust of the TBM, it is predicted as jamming, otherwise it is predicted as no jamming.
[0009] Preferably, the recovery of the deformation modulus of the equivalent solid element in step S3 adopts a gradual transition: within each excavation step, the transition factor β is determined according to the following formula and the deformation modulus of the equivalent solid element is updated accordingly: ; ; In the formula, The monitored normal displacement, For the initial transition displacement, To widen the gap, As a transition index, The coefficient representing the influence of aging deformation rate. For the aging deformation rate, The updated equivalent solid element deformation modulus, The deformation modulus of the transition medium. The deformation modulus of the surrounding rock; when the monitored normal displacement is not greater than the transition initiation displacement, the transition factor is... Take 0.
[0010] Preferably, the transition factor The range of values is The transition initiation displacement The transition index is taken as 10% to 30% of the enlargement gap. The value is 1 to 3.
[0011] Preferably, the calculation of the transition factor is corrected within each excavation step based on the shield contact stress: using the aging-constraint sensitivity coefficient as... Convergence tolerance is The maximum number of iterations is First, the shield contact stress of the previous iteration. With vertical ground stress Calculate the corrected aging deformation rate using the following formula : ; Again replace Update the deformation modulus of the equivalent solid element as follows: ; Repeat the calculation until the difference between the deformation moduli of the equivalent solid elements in two consecutive calculations is less than 1. or reach Next; in the formula, For time-constraint sensitivity coefficient, For shield contact stress, This refers to vertical ground stress.
[0012] Preferably, the time-constraint sensitivity coefficient The value range is [0,1), and the convergence tolerance is... The maximum number of iterations is taken as 0.1% to 1% of the deformation modulus of the surrounding rock. The value is between 3 and 6.
[0013] Preferably, the recovery of the deformation modulus of the equivalent solid element in step S3 adopts a step switching: within each excavation step, when the monitored normal displacement is greater than or equal to the widening gap, the deformation modulus of the equivalent solid element is changed from the deformation modulus of the transition medium. Deformation modulus of the surrounding rock To activate contact extrusion, otherwise maintain the deformation modulus of the transition medium. .
[0014] Preferably, the deformation modulus of the transition medium is 1% to 10% of the deformation modulus of the surrounding rock.
[0015] Preferably, the frictional resistance of the surrounding rock to the shield in step S4 is... The integral along the shield surface is obtained using the following formula: ; In the formula, For the shield radius, The coefficient of friction between the shield and the surrounding rock. For shield axis coordinates Shield contact stress at the location, For shield length, For the weight of the shield itself.
[0016] Preferably, the shield is simulated by lining structural units closely attached to the inner surface of the excavation gap, and the cohesion at the interface between the shield and the surrounding rock is set to zero to allow the surrounding rock and the shield to separate normally and slide tangentially at the interface; the segments are simulated by solid units and advanced one ring at a time to take into account the load transfer of the segments to the shield.
[0017] Preferably, when step S4 predicts that the machine will jam, the excavation gap is increased or the construction speed is increased, and steps S1 to S4 are repeated until the machine is predicted to not jam. Then, the tunneling is organized according to the excavation gap and construction speed corresponding to the prediction that the machine will not jam.
[0018] The beneficial effects of the present invention include at least the following: 1) The equivalent solid element filled in the excavation gap of this invention not only allows the stress and displacement of the area to be transmitted, but also achieves the gradual recovery of the modulus by monitoring the normal displacement of the surrounding rock and interpolating the deformation modulus according to the transition factor, so that the contact between the shield and the surrounding rock is established as the surrounding rock converges; since the deformation modulus of the equivalent solid element is continuously updated with the normal displacement, the shield contact stress no longer jumps abruptly with the binary switching or geometric penetration at the triggering moment, thereby eliminating the abrupt change in contact pressure at the moment of contact establishment, so that the contact stress converges with the surrounding rock and is continuously characterized. The frictional resistance and jamming prediction results calculated by it are closer to the actual situation.
[0019] 2) This invention uses lining structure units to simulate the shield and sets the interface cohesion to zero, which avoids the mesh distortion and calculation instability caused by discretizing the shield with extremely thin solid units, and can reflect the normal separation and tangential sliding of the surrounding rock and the shield at the interface.
[0020] 3) The dynamic cyclic excavation of the single-step advance of this invention reproduces the process of gradual unloading and deformation of the surrounding rock as the TBM advances and the spatial effect of the tunnel face. The creep time step is linked to the construction speed, which can incorporate the time-dependent deformation into the calculation.
[0021] 4) The method of this invention can reproduce the asymmetric settlement and uplift of the arch crown and arch bottom, radial convergence around the tunnel, spatial effect of the tunnel face and plastic zone wrapping, etc. The obtained laws are consistent with the general trend of deformation of the surrounding rock of deep buried soft rock tunnels; and can support the single-factor sensitivity analysis of the main controlling factors such as burial depth, surrounding rock mechanical parameters, time-dependent deformation parameters, construction speed and excavation gap on shield friction, plastic zone and surrounding rock convergence, providing a basis for TBM jamming mechanism analysis and jamming risk prediction.
[0022] 5) Because the present invention corrects the deformation rate of the time-lapse deformation as the shield contact stress increases, the recovery of the deformation modulus of the equivalent solid unit no longer uses the free field deformation rate of the non-contact stage, and the shield contact stress of the trigger stage is no longer continuously increased by the time-lapse term. Thus, under the working conditions of deep buried high ground stress and strong creep soft rock, the overestimation of the shield contact stress and the frictional resistance obtained by integrating it along the shield surface and the prediction results of the jamming machine are suppressed, making the jamming risk assessment closer to reality. Attached Figure Description
[0023] Figure 1 This is a flowchart of the prediction method for contact compression of the shield-type TBM surrounding rock shield according to the present invention. Figure 2 This is a schematic diagram of the three-dimensional calculation model used in this invention; Figure 3 A schematic diagram showing the cutter head reaming tools and the formation of the reaming gap; Figure 4 This diagram illustrates the interaction between the surrounding rock, the excavation gap, the shield, and the tunnel lining segments. Figure 5 A schematic diagram showing the structural unit format used for the shield; Figure 6 A schematic diagram of each stage of dynamic cyclic excavation with single-step advance; Figure 7 This diagram shows the cross-section of the TBM excavation space and the relationship between shield contact stress, frictional resistance, and tunneling thrust. Figure 8 This is a schematic diagram illustrating the transition from no contact to contact and compression between the surrounding rock and the shield. Figure 9 This is a cloud map showing the vertical displacement of the surrounding rock under the baseline working condition. Figure 10 This is a contour map of the vertical displacement of the cross section under the reference working condition; Figure 11 The curve of longitudinal deformation (LDP) of the surrounding rock under the baseline working condition; Figure 12 This is a map showing the distribution of the plastic zone in the surrounding rock under the baseline working condition. Figure 13 A graph showing the variation of shield friction at different burial depths; Figure 14 The graph shows the variation of shield frictional resistance under different deformation moduli. Figure 15 A graph showing the variation of shield frictional resistance under different cohesion. Figure 16 A graph showing the variation of shield frictional resistance under different internal friction angles; Figure 17 The graph shows the variation of shield frictional resistance under different shear moduli G2. Figure 18 The graph shows the variation of shield frictional resistance under different viscosity coefficients η1; Figure 19 The graph shows the variation of shield frictional resistance under different viscosity coefficients η2; Figure 20 The graph shows the variation of shield frictional resistance at different construction speeds; Figure 21 This is a graph showing the variation of shield friction resistance under different excavation gaps. Detailed Implementation
[0024] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present invention.
[0025] The overall process of the method is as follows: Figure 1As shown, after establishing the three-dimensional model, the ground stress is applied according to the burial depth and initially balanced. Then, dynamic cyclic excavation with single-step advance is carried out. In each excavation step, FISH monitors the normal displacement of the surrounding rock adjacent to the equivalent solid element and updates the modulus of the equivalent solid element according to the transition factor. Subsequently, the segment installation and grouting backfill are completed, and the creep time step is advanced according to the construction speed. The cycle continues until the excavation is completed, the shield contact stress is extracted, the frictional resistance is calculated by integration, and the jamming status is predicted according to the jamming criteria.
[0026] Step S1: Based on the burial depth of the tunnel section to be predicted, the mechanical parameters and time-dependent deformation parameters of the surrounding rock, as well as the shield length, shield radius, rated thrust and construction speed of the TBM, a three-dimensional finite difference model is constructed. Solid elements are used to simulate the surrounding rock and tunnel segments, and structural elements are used to simulate the shield. An equivalent solid element with a deformation modulus lower than that of the surrounding rock is filled in the excavation gap between the shield and the surrounding rock as a transition medium for transmitting stress and displacement. Step S2: Apply vertical geostress to the three-dimensional finite difference model according to the burial depth. And complete the initial geostress equilibrium, where The density of the overlying rock strata. For burial depth; Step S3: Perform dynamic cyclic excavation in a single-step advance manner. In each excavation step, apply equivalent excavation face support pressure to the face to simulate cutterhead thrust and redistribute it as the face advances. At the same time, remove the equivalent excavation face support pressure at the previous face position, drive the shield to move forward one advance along the axis, install segments at the shield tail, and grout backfill the annular gap between the segments and the surrounding rock. Convert the actual time required for a single excavation advance into creep time steps according to the construction speed, and advance the corresponding creep time steps in each excavation step to take into account the time deformation of the surrounding rock. Monitor the normal displacement of the equivalent solid unit adjacent to the surrounding rock in each excavation step. Update the deformation modulus of the equivalent solid unit according to the relationship between the normal displacement and the excavation gap, so that it recovers from the deformation modulus of the transition medium to the deformation modulus of the surrounding rock to establish contact compression between the shield and the surrounding rock, and output the contact stress distribution on the shield surface. Step S4: Integrate the contact stress distribution along the shield surface to obtain the frictional resistance of the surrounding rock to the shield, and predict the jamming state of the tunnel section to be predicted based on the relationship between the thrust required to overcome the frictional resistance, the thrust required for normal continuous tunneling of the TBM, and the rated thrust of the TBM; wherein, when the sum of the thrust required to overcome the frictional resistance and the thrust required for normal continuous tunneling of the TBM is greater than the rated thrust of the TBM, it is predicted as jamming, otherwise it is predicted as no jamming.
[0027] Specifically, in the three-dimensional finite difference model, solid elements are used to simulate the surrounding rock and tunnel segments, and structural elements are used to simulate the shield. A layer of equivalent solid elements with a deformation modulus lower than that of the surrounding rock is filled in the excavation gap between the shield and the surrounding rock, serving as a transition medium for transferring stress and displacement. Vertical in-situ stress is applied to the model according to the burial depth. ,in For the unit weight of the overlying rock strata, To achieve the required burial depth and initial ground stress equilibrium, dynamic cyclic excavation was then carried out using a single-step advance method. Each excavation step included: solving for mechanical equilibrium based on the stress and deformation state of the previous excavation step; applying equivalent excavation face support pressure at the face to simulate cutterhead thrust and redistributing it as the face advanced; simultaneously removing the equivalent excavation face support pressure at the previous face position; driving the shield forward one advance along the axis; installing segments at the shield tail and grouting and backfilling the annular gap between the segments and the surrounding rock; and converting the actual time required for a single excavation advance into creep time steps according to the construction speed, advancing the corresponding creep time steps within each excavation step to account for the time-dependent deformation of the surrounding rock. The shield is simulated by lining structural units closely attached to the inner surface of the excavation gap, and the cohesion of the interface between the shield and the surrounding rock is set to zero to allow the surrounding rock and the shield to separate normally and slide tangentially at the interface; the segments are simulated by solid units and advanced one ring at a time to take into account the load transfer of the segments to the shield.
[0028] The three-dimensional calculation model used in this invention is as follows: Figure 2 As shown; the process of the cutterhead excavation tool cutting the surrounding rock to form an excavation gap is as follows: Figure 3 As shown; the interaction relationships between the surrounding rock, the excavation gap, the shield, and the tunnel lining segments are as follows: Figure 4 As shown; the shield is displayed in the form of structural units, as shown below. Figure 5 As shown; the single-step dynamic cyclic excavation process sequentially goes through four stages: mechanical equilibrium solution, application of cutterhead thrust, shield entry into the tunnel, and segment installation and grouting backfilling. Figure 6 As shown; TBM excavation space profile and shield contact stress Shield friction With tunneling thrust The relationship between them is as follows Figure 7 As shown.
[0029] Within each excavation step, the normal displacement of the surrounding rock adjacent to the equivalent solid element is monitored. The material parameters of the equivalent solid element are updated based on the relationship between this normal displacement and the widening gap, restoring the deformation modulus of the equivalent solid element from the deformation modulus of the transition medium to the deformation modulus of the surrounding rock. This establishes contact compression between the shield and the surrounding rock, and outputs the contact stress distribution on the shield surface. Based on this, the frictional resistance of the surrounding rock against the shield is calculated by integrating along the shield surface, and the jamming state is predicted according to the jamming criteria. The contact stress distribution on the shield surface is denoted as the shield contact stress distributed along the shield surface, and its coordinates along the shield axis are... The value at point is denoted as The surrounding rock and the shield change from a state of no contact to a state of contact and compression, as shown in the example. Figure 8 As shown.
[0030] Frictional resistance of surrounding rock to the shield The integral along the shield surface is obtained using the following formula: ,in For shield radius, The coefficient of friction between the shield and the surrounding rock, For shield axis coordinates Shield contact stress at the location For shield length, Let the shield's own weight be the propulsive force required to overcome this frictional resistance. and The thrust required for normal continuous tunneling by a TBM is The rated thrust of the TBM is The stuck state is determined as follows: when If the system is stuck, it is considered frozen; otherwise, it is considered not frozen.
[0031] Example 1 This embodiment uses the soft rock section of a deep-buried, long-distance water diversion tunnel as an application scenario to illustrate the complete implementation process of progressive contact transition using a shield TBM. The computational domain is 90 meters along the vertical tunnel axis, the tunnel axis, and the vertical direction. The mesh is fined within approximately 40 meters around the tunnel perimeter and coarsened in the far region, using hexahedral elements. In this embodiment, there are approximately 140,000 elements and 138,000 nodes. The surrounding rock and tunnel segments are simulated using solid elements, while the shield is simulated using structural elements. A layer of equivalent solid elements with a deformation modulus lower than that of the surrounding rock is filled within the excavation gap. The deformation modulus of these solid elements can be selected within the range of one to ten percent of the surrounding rock deformation modulus; this embodiment exemplarily uses... The surrounding rock is constituted using a viscoelastic-plastic creep constitutive model that can describe time-dependent deformation. The baseline conditions are: burial depth 600 meters, deformation modulus 2.3 GPa, cohesion 0.45 MPa, internal friction angle 25 degrees, construction speed 12 m / day, excavation gap 5 cm, shield length 7 meters, shield-surrounding rock friction coefficient 0.3, and the thrust required for normal tunneling. Take 16MN, rated thrust Take 123.7MN.
[0032] Excavation was carried out in single-step advances, with each step being 1 meter long and a total of 90 steps. Within each excavation step, the stress and deformation state of the previous excavation step was first solved to achieve mechanical equilibrium. Then, equivalent excavation face support pressure was applied at the face to simulate the cutterhead thrust, and redistributed as the face advanced. Simultaneously, the support pressure at the previous face was removed, driving the shield forward by 1 meter. Subsequently, segments were installed at the shield tail and grout was injected into the annular gap for backfilling. At each section where the shield was located, the normal convergence displacement of the surrounding rock adjacent to the equivalent solid element was monitored in real time by the FISH program. Take the transition initial displacement 20% of the enlarged excavation gap, transition index Take 2, the influence coefficient of aging deformation rate Take 0.05d / mm and determine the transition factor using the following formula. And update the deformation modulus of the equivalent element of the cross section: , In the formula To widen the gap, For aging deformation rate, For the deformation modulus of the transition medium, For the deformation modulus of the surrounding rock, This is the updated deformation modulus of the equivalent solid element; where the aging deformation rate is the ratio of the normal displacement increment of the surrounding rock adjacent to the equivalent solid element of the cross section in the previous creep time step to the actual duration corresponding to that time step, expressed in mm / d, approximately 2 mm / d under the reference working condition. The dimension of the aging deformation rate influence coefficient is its reciprocal, expressed in d / mm. When hour Taking zero, the equivalent solid element maintains the low modulus of the transition medium, and the shield has not yet come into contact with the surrounding rock; [following this,] Increase The equivalent solid element modulus increases asymptotically from zero. Gradual recovery to The contact stiffness gradually builds up; when Time operation Taking a value of 1, the equivalent solid element modulus is restored to the surrounding rock modulus, and the shield is subjected to full contact compression with the surrounding rock. The value range of the transition factor is limited to... The technical motivation lies in the fact that the closure of the excavation gap is a hard upper limit constraint, and the recovery of the equivalent unit modulus is at most limited to the surrounding rock modulus; the introduction of The second independent variable is chosen because, under conditions of deep-buried soft rock, the same normal displacement corresponds to different stress release and contact trends at different creep rates. Judging solely by displacement is insufficient to characterize the influence of age-related deformation on the timing of contact establishment. As tunneling progresses, the surrounding rock converges more fully the further away from the tunnel face. The larger, The equivalent solid element modulus asymptotically approaches one from zero. Gradual recovery to The contact stress of the shield is then established smoothly rather than increasing abruptly in a single step. After excavation is completed, the shield surface is followed... Integrate to obtain the frictional resistance, and then... and The comparison outputs the card status.
[0033] Building upon the aforementioned gradual transition, this embodiment further incorporates a correction for the triggering timing based on shield contact stress within each excavation step. The aging-constraint sensitivity coefficient is used. The convergence tolerance is 0.5. Take one-thousandth of the deformation modulus of the surrounding rock, and the maximum number of iterations. Take four times; at each section where the shield is located, first take the shield contact stress from the previous sub-iteration (first take the previous excavation step). With vertical ground stress Calculate the corrected aging deformation rate using the following formula : , and then Substitute into the transition factor formula to calculate the transition factor, and then... Update the deformation modulus of the equivalent solid element of the cross section, and resolve the contact to obtain the new shield contact stress; repeat the above calculation until the difference between the deformation moduli of two adjacent equivalent solid elements is less than 1. or reach Next. In the formula For time-constraint sensitivity coefficient, For shield contact stress, For vertical ground stress, Take the lower limit of zero Not less than zero. As tunneling progresses and contact stress gradually builds up, the aging deformation rate is adjusted. Consequently, the recovery of the deformation modulus of the equivalent solid element slows down compared to the uncorrected state, and the establishment of the shield contact stress during the triggering stage is more gradual. Compared to the forward transition rule driven solely by the free-field aging deformation rate, the above process, which determines the corrected aging deformation rate based on the shield contact stress and iterates to convergence within a single excavation cycle, improves the fidelity of the contact stress estimation during the triggering stage under strong creep conditions. As an example, under the above baseline conditions, if the correction of the aging deformation rate by the shield contact stress is not considered, the peak shield contact stress at the middle section of the shield during the contact triggering step is approximately 1.6 MPa, and the frictional resistance obtained by integrating it along the shield surface is approximately 78 MN. After incorporating this correction and iterating to convergence, the peak shield contact stress at the same section during the contact triggering step drops to approximately 1.1 MPa, and the frictional resistance drops to approximately 64 MN. The overshoot of the shield contact stress during the triggering stage is reduced by approximately 30%, and the jamming risk determined accordingly is closer to reality.
[0034] Example 2 This embodiment adopts a degenerate form of progressive transition rule. The model settings and baseline conditions are the same as in Embodiment 1. The only difference is the modulus update rule for the equivalent solid element: the normal displacement of the surrounding rock adjacent to the equivalent solid element is monitored in each excavation step. ,when Immediately change the deformation modulus of the equivalent solid element from the transition medium value. Set as surrounding rock value Activate contact extrusion; otherwise, maintain the transition medium value. .
[0035] The predicted results under the baseline working conditions are as follows: the maximum settlement of the arch crown is approximately 6.79 cm, and the maximum heave of the arch base is approximately 5.07 cm. The settlement of the arch crown is significantly greater than the heave of the arch base. The overall deformation decreases rapidly with increasing distance from the tunnel entrance. The radial deformation of the cross-section is approximately axisymmetric, with an influence range of about three to five times the tunnel diameter. The radial displacement at the tunnel wall reaches its peak. The longitudinal deformation curve shows that advanced displacement has occurred in front of the tunnel face. The radial deformation at the tunnel face is minimal. The fastest convergence occurs in the range of 0 to 10 meters from the tunnel face, and the deformation tends to stabilize after about 40 meters. The cumulative settlement of the arch crown is about 10 cm. The plastic zone is mainly characterized by shear failure, with sporadic tensile failure in some areas. A complete plastic encapsulation zone is formed around the tunnel. The above patterns are consistent with the general trend of deformation and plastic zone development in the surrounding rock of deeply buried soft rock tunnels.
[0036] The vertical displacement cloud diagram, cross-sectional vertical displacement cloud diagram, longitudinal deformation curve, and distribution of the plastic zone of the surrounding rock under the reference working condition are shown below. Figure 9 , Figure 10 , Figure 11 and Figure 12 As shown.
[0037] Example 3 This embodiment illustrates the analytical capability of this method for predicting the main control factors when used in shield risk assessment. Based on Embodiment 2, this embodiment uses the controlled variable method for single-factor sensitivity analysis, with other parameters fixed as the baseline condition. The calculation section is taken at the center of the tunnel axis. The influence of seven factors—burial depth, deformation modulus, cohesion, internal friction angle, time-dependent deformation parameters, construction speed, and excavation gap—on the radial convergence of the surrounding rock, the plastic zone, and the shield's frictional resistance is examined.
[0038] When the burial depth increases from 600 meters to 1400 meters, the final stable radial convergence displacement of the surrounding rock increases from approximately 0.10 m to approximately 0.21 m, the volume of the plastic zone increases sharply from approximately 6400 cubic meters to approximately 24000 cubic meters, and the shield frictional resistance increases from approximately 63.9 MN to approximately 136.35 MN, showing a significant positive correlation with the burial depth. When the deformation modulus increases from 1.3 GPa to 3.3 GPa, the stable radial convergence displacement of the surrounding rock decreases from approximately 0.126 m to approximately 0.091 m, and the shield frictional resistance decreases from approximately 73.3 MN to approximately 57 MN, showing a negative correlation. The deformation modulus, since it does not directly participate in yield determination, has a negligible impact on the size of the plastic zone. When the cohesion increases from 0.05 MPa to 0.85 MPa, the volume of the plastic zone decreases nonlinearly with increasing cohesion, first steeply and then gradually, and the shield frictional resistance decreases from approximately 73.4 MN to approximately 59.1 MN. When the internal friction angle increases from 25 degrees to 41 degrees, its control effect on the plastic zone is even stronger than that of cohesion, and the volume of the plastic zone drops sharply, thus reducing the shield frictional resistance. Regarding the aging deformation parameters, when the shear modulus increases from 1.5 GPa to 9.5 GPa, the shield frictional resistance increases linearly from approximately 63.9 MN to approximately 72.4 MN. With the increase of the two viscosity coefficients, the shield frictional resistance shows a linear increase and a nonlinear increase with decreasing rate of increase, respectively. Overall, while the increase in aging deformation parameters macroscopically limits early creep displacement, it hinders the release of surrounding rock stress through aging deformation and the induction of plastic zone expansion. Under short-term creep conditions, its overall impact on shield frictional resistance is relatively weak. When the construction speed increases from 6 m / day to 30 m / day, the radial convergence displacement of the surrounding rock decreases with increasing speed, and the shield frictional resistance decreases linearly from approximately 65.1 MN to approximately 55.4 MN, showing a negative correlation. This indicates that increasing the tunneling speed is an effective construction measure for preventing and controlling the risk of the tunnel boring machine jamming in soft rock. When the excavation gap increased from 5cm to 25cm, the radial convergence displacement of the surrounding rock increased from about 0.10m to about 0.225m, while the shield frictional resistance decreased from about 63.8MN to about 37.1MN, a decrease of more than 41%. This is the most significant construction parameter for controlling the shield frictional resistance in this sensitivity analysis. Its mechanical essence is the deformation space release effect, that is, the larger gap provides sufficient free deformation space for the surrounding rock. The deformation of the surrounding rock in the near-field of the tunnel face through which the shield passes has not yet contacted the rigid shield shell and cannot form a continuous squeezing positive pressure. Therefore, the larger the gap, the lower the shield frictional resistance.
[0039] The above-mentioned burial depth, deformation modulus, cohesion, internal friction angle, and shear modulus viscosity coefficient viscosity coefficient The influence of construction speed and excavation gap on the shield friction is as follows: Figure 13 , Figure 14 , Figure 15 , Figure 16 , Figure 17 , Figure 18 , Figure 19 , Figure 20, Figure 21 As shown.
[0040] In summary, this method can quantitatively characterize the influence of various controlling factors on surrounding rock displacement, plastic zone, and shield friction. Reasonably increasing the excavation gap and improving the tunneling speed can achieve early release of surrounding rock stress and reduce shield friction during construction, providing a basis for the analysis of the jamming mechanism and prediction of jamming risk in shield-type TBM tunneling in deeply buried, high-stress soft rock strata. Furthermore, if jamming is predicted according to step S4, steps S1 to S4 can be repeated by increasing the excavation gap or improving the construction speed until jamming is predicted to be non-jamming. Tunneling should then be organized according to the excavation gap and construction speed corresponding to the predicted non-jamming situation to ensure construction safety.
[0041] The deformation modulus of the transition medium, i.e., the deformation modulus of the equivalent solid element in the non-contact stage, can be taken as one percent to ten percent of the deformation modulus of the surrounding rock. This range ensures that the equivalent medium is soft enough not to significantly hinder the deformation of the surrounding rock in the non-contact stage, while also ensuring that it can transmit stress and displacement without numerical instability.
[0042] The technical features of the above embodiments can be combined arbitrarily. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described; only preferred embodiments of the present invention are illustrated. The descriptions are relatively specific and detailed, but they should not be construed as limiting the scope of the present invention. As long as the combination of these technical features does not contradict each other, it should be considered within the scope of this specification.
[0043] It should be noted that those skilled in the art can make various modifications and improvements without departing from the inventive concept, and these all fall within the scope of protection of this invention. Therefore, the scope of protection of this invention should be determined by the appended claims.
Claims
1. A method for predicting contact compression of a shield-type TBM surrounding rock shield, characterized in that, Includes the following steps: Step S1: Based on the burial depth of the tunnel section to be predicted, the mechanical parameters and time-dependent deformation parameters of the surrounding rock, as well as the shield length and shield radius of the TBM, a three-dimensional finite difference model is constructed. Solid elements are used to simulate the surrounding rock and tunnel segments, and structural elements are used to simulate the shield. An equivalent solid element with a deformation modulus lower than that of the surrounding rock is filled in the excavation gap between the shield and the surrounding rock as a transition medium for transmitting stress and displacement. Step S2: Apply vertical ground stress to the three-dimensional finite difference model according to the burial depth. And complete the initial geostress equilibrium, where The density of the overlying rock strata. For burial depth; Step S3: Perform dynamic cyclic excavation in a single-step advance manner. In each excavation step, apply equivalent excavation face support pressure to the face to simulate cutterhead thrust and redistribute it as the face advances. At the same time, remove the equivalent excavation face support pressure at the previous face position, drive the shield to move forward one advance along the axis, install segments at the shield tail, and grout backfill the annular gap between the segments and the surrounding rock. Convert the actual time required for a single excavation advance into creep time steps according to the construction speed, and advance the corresponding creep time steps in each excavation step to take into account the time deformation of the surrounding rock. In each excavation step, monitor the normal displacement of the surrounding rock adjacent to the equivalent solid unit. Update the deformation modulus of the equivalent solid unit according to the relationship between the normal displacement and the excavation gap, so that it recovers from the deformation modulus of the transition medium to the deformation modulus of the surrounding rock to establish contact compression between the shield and the surrounding rock, and output the contact stress distribution on the shield surface. Step S4: Integrate the contact stress distribution along the shield surface to obtain the frictional resistance of the surrounding rock to the shield, and predict the jamming state of the tunnel section to be predicted based on the relationship between the thrust required to overcome the frictional resistance, the thrust required for normal continuous tunneling of the TBM, and the rated thrust of the TBM; wherein, when the sum of the thrust required to overcome the frictional resistance and the thrust required for normal continuous tunneling of the TBM is greater than the rated thrust of the TBM, it is predicted as jamming, otherwise it is predicted as no jamming.
2. The method according to claim 1, characterized in that, The restoration of the deformation modulus of the equivalent solid element in step S3 adopts a gradual transition: within each excavation step, the transition factor β is determined according to the following formula and the deformation modulus of the equivalent solid element is updated accordingly: ; ; In the formula, The monitored normal displacement, For the initial transition displacement, To widen the gap, As a transition index, The coefficient representing the influence of aging deformation rate. For the aging deformation rate, The updated equivalent solid element deformation modulus, The deformation modulus of the transition medium. The deformation modulus of the surrounding rock; when the monitored normal displacement is not greater than the transition initiation displacement, the transition factor is... Take 0.
3. The method according to claim 2, characterized in that, The transition factor The range of values is The transition initiation displacement The transition index is taken as 10% to 30% of the enlargement gap. The value is 1 to 3.
4. The method according to claim 2, characterized in that, Within each excavation step, the calculation of the transition factor is corrected based on the shield contact stress: using the aging-constraint sensitivity coefficient as... Convergence tolerance is The maximum number of iterations is First, the shield contact stress of the previous iteration. With vertical ground stress Calculate the corrected aging deformation rate using the following formula : ; Again replace Update the deformation modulus of the equivalent solid element as follows: ; Repeat the calculation until the difference between the deformation moduli of the equivalent solid elements in two consecutive calculations is less than 1. or reach Next; in the formula, For time-constraint sensitivity coefficient, For shield contact stress, This refers to vertical ground stress.
5. The method according to claim 4, characterized in that, The time-constraint sensitivity coefficient The value range is [0,1), and the convergence tolerance is... The maximum number of iterations is taken as 0.1% to 1% of the deformation modulus of the surrounding rock. The value is between 3 and 6.
6. The method according to claim 1, characterized in that, The recovery of the deformation modulus of the equivalent solid element in step S3 adopts a step switching: within each excavation step, when the monitored normal displacement is greater than or equal to the widening gap, the deformation modulus of the equivalent solid element is changed from the deformation modulus of the transition medium. Deformation modulus of the surrounding rock To activate contact extrusion, otherwise maintain the deformation modulus of the transition medium. .
7. The method according to claim 1, characterized in that, The deformation modulus of the transition medium is taken as 1% to 10% of the deformation modulus of the surrounding rock.
8. The method according to claim 1, characterized in that, The frictional resistance of the surrounding rock to the shield mentioned in step S4 The integral along the shield surface is obtained using the following formula: ; In the formula, For the shield radius, The coefficient of friction between the shield and the surrounding rock. For shield axis coordinates Shield contact stress at the location, For shield length, For the weight of the shield itself.
9. The method according to claim 1, characterized in that, The shield is simulated by lining structural units closely attached to the inner surface of the excavation gap, and the cohesion of the interface between the shield and the surrounding rock is set to zero to allow the surrounding rock and the shield to separate normally and slide tangentially at the interface. The tunnel segments are simulated using solid units and advanced ring by ring in order to account for the load transfer of the tunnel segments to the shield.
10. The method according to claim 1, characterized in that, When step S4 predicts that the machine will jam, increase the excavation gap or increase the construction speed and then repeat steps S1 to S4 until the machine is predicted to not jam. Then organize the tunneling according to the excavation gap and construction speed corresponding to the prediction that the machine will not jam.