Cable laying operation intelligent path planning system and method, electronic device and storage medium
By using an intelligent path planning system for cable laying operations and leveraging BIM models and data conversion technology, the conflict between cable laying and track laying operations in rail transit construction has been resolved, improving construction safety and schedule controllability.
Patent Information
- Application Number
- CN202611149112.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-31
- Publication Date
- 2026-11-20
AI Technical Summary
In current rail transit construction, there is a lack of coordination between cable laying and track laying operations, which leads to a high possibility of operational conflicts and affects construction safety and progress.
An intelligent path planning system for cable laying operations is adopted. Through BIM model building, data conversion, efficiency acquisition, rule setting, and path planning modules, the operation progress can be monitored and adjusted in real time to avoid conflicts.
It enables real-time progress tracking and conflict avoidance for different tasks, improving construction safety and the reliability of the project's steady progress.
Smart Images

Figure CN123140374A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of work path planning technology, and relates to a work path planning system, and more particularly to an intelligent path planning system, method, electronic device and storage medium for cable laying operations. Background Technology
[0002] In rail transit construction projects, track laying and cable installation are required after the tunnel boring machine (TBM) is completed. Current management methods are rather rudimentary; track laying and cable installation companies typically only agree on a general work schedule for a specific area, with one company completing its work before the other begins. This existing approach prevents one company from directly monitoring the other's progress and creates the possibility of work conflicts, impacting operational safety.
[0003] In view of this, there is an urgent need to design a new cable laying operation path planning system in order to overcome at least some of the above-mentioned defects in existing cable laying operations. Summary of the Invention
[0004] This invention provides an intelligent path planning system, method, electronic device, and storage medium for cable laying operations. It can track the progress of different construction operations in real time, avoid conflicts between different operations, improve the safety of project construction, and ensure the steady progress of the project.
[0005] To solve the above-mentioned technical problems, according to one aspect of the present invention, the following technical solution is adopted: A smart path planning system for cable laying operations, the smart path planning system for cable laying operations includes: The BIM model building module is used to build a BIM model of the construction tunnel. The BIM model includes the coordinates of each key point of the construction tunnel in a preset coordinate system. The cable laying operation data conversion module is used to acquire cable laying operation data and convert the cable laying operation data into a first vector related to the location in the BIM model; The short rail laying operation data conversion module is used to acquire short rail laying operation data and convert the short rail laying operation data into a second vector related to the location in the BIM model; The cable laying operation efficiency acquisition module is used to acquire the first efficiency data of cable laying operation per unit time; the first efficiency data includes the first manual operation efficiency data and the first machine operation efficiency data. The short rail laying operation efficiency acquisition module is used to acquire the second efficiency data of the short rail laying operation per unit time; the second efficiency data includes the second manual operation efficiency data and the second machine operation efficiency data. The laying rule setting module is used to set the laying rule data between cable laying operations and short rail laying operations; The path planning module is used to plan the path for cable laying operations and short rail laying operations based on cable laying operation data, short rail laying operation data, first efficiency data, second efficiency data, laying rule data, and operation objectives. The path planning module allocates first manual operation efficiency data, first machine operation efficiency data, second manual operation efficiency data, and second machine operation efficiency data according to the operation objectives.
[0006] As one embodiment of the present invention, the intelligent path planning system for cable laying operations further includes: A mathematical model construction module for laying operations is used to construct a mathematical model for laying operations; the mathematical model for laying operations performs path planning for cable laying operations and short rail laying operations based on the operation objectives, cable laying operation data, short rail laying operation data, first efficiency data, and second efficiency data. A cable laying operation simulation module is used to acquire cable laying operation data, which includes at least one cable laying operation segment. Based on the acquired cable laying operation data, the module simulates the first progress segment vector of each cable laying operation segment in the BIM model constructed by the BIM model building module. The first progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point. When presenting the progress, the module generates a corresponding operation simulation animation display based on the first progress segment vector of each cable laying operation segment, and can present the corresponding cable laying completion animation at a set time node according to the time axis. A short rail laying operation simulation module is used to acquire short rail laying operation data, which includes at least one short rail laying operation segment. Based on the acquired short rail laying operation data, the module simulates the second progress segment vector of each short rail laying operation segment in the BIM model constructed by the BIM model building module. The second progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point. When presenting the progress, the module generates a corresponding operation simulation animation display based on the second progress segment vector of each short rail laying operation segment, and can present the corresponding short rail laying completion animation at a set time node according to the time axis. The collision detection module is used to detect whether there is a collision risk between two operations based on the first progress segment vector constructed by the cable laying operation simulation module and the second progress segment vector constructed by the short rail laying operation simulation module. The specific judgment method includes: extracting the operation segments in each construction unit time in the first progress segment vector, extracting the operation segments in each construction unit time in the second progress segment vector, and judging whether there is partial coordinate overlap between the two operation progress segments in a certain construction unit time. If so, it is judged that there is a collision risk, that is, there is a construction operation intersection point, and an alarm signal is sent. The path planning module includes an intelligent operation adjustment module, which is used to intelligently adjust the cable laying operation and / or short rail laying operation after the collision detection module detects the existence of a construction operation intersection point, thereby avoiding the occurrence of construction operation intersection points.
[0007] As one embodiment of the present invention, the laying rules set by the laying rule setting module include: within a set area and within the same unit time, cable laying and short rail laying operations cannot be carried out simultaneously; cable laying using a machine can only be carried out after the short rail laying is completed within the corresponding area. The cable laying operation simulation module simulates the progress segments of the cable laying operation in the BIM model based on the input cable laying operation construction plan data and actual construction progress data.
[0008] The short rail laying operation simulation module simulates the progress segments of the short rail laying operation in the BIM model based on the input short rail laying operation construction plan data and actual construction progress data.
[0009] The intelligent path planning system for cable laying operations further includes an operation correction module, which is used to correct the cable laying operation data obtained by the cable laying operation simulation module and the short rail laying operation obtained by the short rail laying operation simulation module based on the actual completed operation data and / or the operation plan adjustment data; the operation correction module only corrects the corresponding first progress segment vector and / or second progress segment vector.
[0010] In one embodiment of the present invention, the intelligent job adjustment module includes: The key target acquisition unit is used to acquire the key targets of the operation and the priority order of each key target, so that the intelligent operation adjustment module can adjust the cable laying operation and / or short rail laying operation to meet the key target settings. The cable laying operation path allocation unit is used to allocate the cable laying operation path into several sub-operation paths and obtain the area coordinates corresponding to each sub-operation path. The work status update unit is used to update the status of cable laying work based on whether the work path track is available; the status includes track unusable status and track usable status, and updates the work efficiency of each work path under different statuses. The conflict zone operation adjustment unit is used to adjust the progress of cable laying operations and short rail laying operations; the adjustment method includes at least one of the following: (1) Adjust the time period for cable laying operations in conflict areas to avoid them being carried out in conflict areas or within the same construction time unit as short rail laying operations; (2) The conflict area is further divided into several sub-conflict areas, or / and the construction unit time is divided into several sub-construction unit times, so that the cable laying operation and the short rail laying operation are carried out in the sub-conflict areas and in the sub-construction unit time. (3) Adjust the time period for short rail laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas.
[0011] According to another aspect of the present invention, the following technical solution is adopted: a smart path planning method for cable laying operations, the smart path planning method for cable laying operations comprising: BIM model construction steps: The BIM model construction module constructs a BIM model of the construction tunnel, which includes the coordinates of each key point of the construction tunnel in a preset coordinate system; Cable laying operation data conversion steps: The cable laying operation data conversion module acquires the cable laying operation data and converts the cable laying operation data into a first vector related to the location in the BIM model; Short rail laying operation data conversion steps: The short rail laying operation data conversion module acquires the short rail laying operation data and converts the short rail laying operation data into a second vector related to the location in the BIM model; Cable laying operation efficiency acquisition steps: The cable laying operation efficiency acquisition module acquires the first efficiency data of cable laying operation per unit time; the first efficiency data includes the first manual operation efficiency data and the first machine operation efficiency data; Steps for obtaining efficiency data of short rail laying operation: The short rail laying operation efficiency acquisition module acquires the second efficiency data of short rail laying operation per unit time; the second efficiency data includes the second manual operation efficiency data and the second machine operation efficiency data; Laying rule setting steps: The laying rule setting module sets the laying rule data between cable laying operations and short rail laying operations; Path planning steps: The path planning module performs path planning for cable laying operations and short rail laying operations based on cable laying operation data, short rail laying operation data, first efficiency data, second efficiency data, laying rule data, and operation objectives; the path planning module allocates first manual operation efficiency data, first machine operation efficiency data, second manual operation efficiency data, and second machine operation efficiency data according to the operation objectives.
[0012] As one embodiment of the present invention, the intelligent path planning method for cable laying operations further includes: The steps for constructing a mathematical model for cable laying operations are as follows: The mathematical model construction module constructs a mathematical model for cable laying operations; the mathematical model for cable laying operations performs path planning for cable laying operations and short rail laying operations based on the operation objectives, cable laying operation data, short rail laying operation data, first efficiency data, and second efficiency data. Cable laying operation simulation steps: The cable laying operation simulation module acquires cable laying operation data, which includes at least one cable laying operation segment; based on the acquired cable laying operation data, the module simulates the first progress segment vector of each cable laying operation segment in the BIM model constructed by the BIM model building module. The first progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point; when presenting the progress, the module generates a corresponding operation simulation animation display based on the first progress segment vector of each cable laying operation segment, and can present the corresponding cable laying completion animation at set time nodes according to the time axis; The simulation steps for short rail laying are as follows: The short rail laying operation simulation module acquires short rail laying operation data, which includes at least one short rail laying operation segment; based on the acquired short rail laying operation data, the module simulates the second progress segment vector of each short rail laying operation segment in the BIM model constructed by the BIM model building module. The second progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point; when presenting the progress, a corresponding operation simulation animation is generated based on the second progress segment vector of each short rail laying operation segment, and the corresponding short rail laying completion animation can be presented at set time nodes according to the time axis. Collision detection steps: The collision detection module detects whether there is a collision risk between the two operations based on the first progress segment vector constructed by the cable laying operation simulation module and the second progress segment vector constructed by the short rail laying operation simulation module. The specific judgment method includes: extracting the operation segments in each construction unit time in the first progress segment vector, extracting the operation segments in each construction unit time in the second progress segment vector, and judging whether there is a partial overlap of the coordinates of the two operation progress segments in a certain construction unit time. If so, it is judged that there is a collision risk, that is, there is an intersection point of construction operations, and an alarm signal is sent. Intelligent operation adjustment steps: After the collision detection module detects the existence of construction operation intersections, the intelligent operation adjustment module will intelligently adjust the cable laying operation and / or short rail laying operation to avoid construction operation intersections.
[0013] As one embodiment of the present invention, the cable laying operation simulation module simulates the progress segment of the cable laying operation in the BIM model based on the input cable laying operation construction plan data and actual construction progress data. The short rail laying operation simulation module simulates the progress segments of the short rail laying operation in the BIM model based on the input short rail laying operation construction plan data and actual construction progress data.
[0014] The intelligent path planning method for cable laying operations further includes: an operation correction module correcting the cable laying operation data obtained by the cable laying operation simulation module and the short rail laying operation obtained by the short rail laying operation simulation module based on the actual completed operation data and / or the operation plan adjustment data; the operation correction module only corrects the corresponding first progress segment vector and / or the second progress segment vector.
[0015] As one embodiment of the present invention, the intelligent operation adjustment step includes: The key target acquisition unit acquires each key target of the operation and obtains the priority order of each key target, so that the intelligent operation adjustment module adjusts the cable laying operation and / or short rail laying operation to meet the key target settings. The cable laying operation path allocation unit divides the cable laying operation path into several sub-operation paths and obtains the area coordinates corresponding to each sub-operation path. The operation status update unit updates the status of cable laying operation based on whether the operation path track is available; the status includes track unusable status and track usable status, and updates the work efficiency of each operation path under different statuses; The conflict zone operation adjustment unit adjusts the progress of cable laying and short rail laying operations; the adjustment methods include at least one of the following: (1) Adjust the time period for cable laying operations in conflict areas to avoid them being carried out in conflict areas or within the same construction time unit as short rail laying operations; (2) The conflict area is further divided into several sub-conflict areas, or / and the construction unit time is divided into several sub-construction unit times, so that the cable laying operation and the short rail laying operation are carried out in the sub-conflict areas and in the sub-construction unit time. (3) Adjust the time period for short rail laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas.
[0016] According to another aspect of the present invention, the following technical solution is adopted: an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the steps of the above method.
[0017] According to another aspect of the present invention, the following technical solution is adopted: a storage medium storing computer program instructions thereon, which, when executed by a processor, implement the steps of the above-described method.
[0018] The beneficial effects of the present invention are as follows: The intelligent path planning system, method, electronic device and storage medium for cable laying operations proposed in this invention can track the progress of different construction operations in real time, avoid conflicts between different operations, improve the safety of project construction and ensure the steady progress of the project. Attached Figure Description
[0019] Figure 1 This is a schematic diagram of the composition of an intelligent path planning system for cable laying operations in one embodiment of the present invention.
[0020] Figure 2 This is a flowchart of an intelligent path planning method for cable laying operations in one embodiment of the present invention.
[0021] Figure 3 This is a schematic diagram of the composition of an electronic device according to an embodiment of the present invention. Detailed Implementation
[0022] The preferred embodiments of the present invention will now be described in detail with reference to the accompanying drawings.
[0023] To further understand the present invention, preferred embodiments of the present invention are described below in conjunction with examples. However, it should be understood that these descriptions are only for further illustrating the features and advantages of the present invention, and not for limiting the scope of the claims of the present invention.
[0024] The description in this section pertains to only a few typical embodiments, and the present invention is not limited to the scope of the embodiments described. Substitution of identical or similar prior art methods with some technical features in the embodiments is also within the scope of the description and protection of this invention.
[0025] The steps described in the various embodiments in the specification are for illustrative purposes only, and the implementation of this application is not limited by the order of the steps.
[0026] The term "connection" in the specification includes both direct and indirect connections, such as connections made through active devices, passive devices, or electrical conduction media; it may also include connections made by other active or passive devices that are known to those skilled in the art and can achieve the same or similar functional purpose, such as connections made through circuits or components such as switches or follower circuits.
[0027] This invention discloses an intelligent path planning system for cable laying operations. Figure 1 This is a schematic diagram of the intelligent path planning system for cable laying operations in one embodiment of the present invention; please refer to [link / reference]. Figure 1 The intelligent path planning system for cable laying operations includes: a BIM model construction module 1, a cable laying operation data conversion module 2, a short rail laying operation data conversion module 3, a cable laying operation efficiency acquisition module 4, a short rail laying operation efficiency acquisition module 5, a laying rule setting module 6, and a path planning module 7.
[0028] The BIM model building module 1 is used to build a BIM model of the construction tunnel, and the BIM model includes the coordinates of each key point of the construction tunnel in a preset coordinate system.
[0029] The cable laying operation data conversion module 2 is used to obtain cable laying operation data and convert the cable laying operation data into a first vector related to the location in the BIM model.
[0030] The short rail laying operation data conversion module 3 is used to obtain short rail laying operation data and convert the short rail laying operation data into a second vector related to the location in the BIM model.
[0031] The cable laying operation efficiency acquisition module 4 is used to acquire the first efficiency data of cable laying operation per unit time; the first efficiency data includes the first manual operation efficiency data and the first machine operation efficiency data.
[0032] The short rail laying operation efficiency acquisition module 5 is used to acquire the second efficiency data of the short rail laying operation per unit time; the second efficiency data includes the second manual operation efficiency data and the second machine operation efficiency data.
[0033] The laying rule setting module 6 is used to set the laying rule data between cable laying operations and short rail laying operations. For example, some sections require short rail laying operations to be carried out first, followed by cable laying operations; or, if cable laying operations are carried out first, the work efficiency is only 30% of that of short rail laying operations (because cable laying can rely on the laid short rails, and the efficiency can be increased by 2 times).
[0034] The path planning module 7 is used to plan paths for cable laying operations and short rail laying operations based on cable laying operation data, short rail laying operation data, first efficiency data, second efficiency data, laying rule data, and operation objectives. The path planning module allocates first manual operation efficiency data, first machine operation efficiency data, second manual operation efficiency data, and second machine operation efficiency data according to the operation objectives. The operation objectives can be time node data for completing the operation, operation quality data, or worker workload data; alternatively, the operation objectives can be a combination of multiple data sets.
[0035] In one embodiment of the present invention, the intelligent path planning system for cable laying operations further includes: a laying operation mathematical model construction module 9, a cable laying operation simulation module 10, a short rail laying operation simulation module 11, and a collision detection module 12.
[0036] The laying operation mathematical model construction module 9 is used to construct the laying operation mathematical model; the laying operation mathematical model performs path planning for the cable laying operation and the short rail laying operation based on the operation objective, cable laying operation data, short rail laying operation data, first efficiency data, and second efficiency data. The cable laying operation simulation module 10 is used to acquire cable laying operation data, which includes at least one cable laying operation segment. Based on the acquired cable laying operation data, the module simulates the first progress segment vector of each cable laying operation segment in the BIM model constructed by the BIM model construction module. The first progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and completion time point data corresponding to each key point. When presenting the progress, the module generates a corresponding operation simulation animation display based on the first progress segment vector of each cable laying operation segment, and can present the corresponding cable laying completion animation at a set time node according to the time axis. The short rail laying operation simulation module 11 is used to acquire short rail laying operation data, which includes at least one short rail laying operation segment. Based on the acquired short rail laying operation data, the module simulates the second progress segment vector of each short rail laying operation segment in the BIM model constructed by the BIM model construction module. The second progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and completion time point data corresponding to each key point. When presenting the progress, the module generates corresponding operation simulation animation display based on the second progress segment vector of each short rail laying operation segment, and can present the corresponding short rail laying completion animation at set time nodes according to the time axis.
[0037] The collision detection module 12 is used to detect whether there is a collision risk between two operations based on the first progress segment vector constructed by the cable laying operation simulation module and the second progress segment vector constructed by the short rail laying operation simulation module. The specific judgment method includes: extracting the operation segments in each construction unit time in the first progress segment vector, extracting the operation segments in each construction unit time in the second progress segment vector, and judging whether there is a partial coordinate overlap between the two operation progress segments in a certain construction unit time. If so, it is judged that there is a collision risk, that is, there is a construction operation intersection point, and an alarm signal is sent. The path planning module includes an intelligent operation adjustment module. The intelligent operation adjustment module is used to intelligently adjust the cable laying operation and / or the short rail laying operation after the collision detection module detects the existence of a construction operation intersection point, thereby avoiding the occurrence of construction operation intersection points.
[0038] In one embodiment of the present invention, the laying rules set by the laying rule setting module include: within a set area and within the same unit time, cable laying and short rail laying operations cannot be carried out simultaneously; cable laying using a machine can only be carried out after the short rail laying is completed within the corresponding area.
[0039] The cable laying operation simulation module simulates the progress stages of the cable laying operation in the BIM model based on the input cable laying operation construction plan data and actual construction progress data. The short rail laying operation simulation module simulates the progress stages of the short rail laying operation in the BIM model based on the input short rail laying operation construction plan data and actual construction progress data.
[0040] The intelligent path planning system for cable laying operations further includes an operation correction module, which is used to correct the cable laying operation data obtained by the cable laying operation simulation module and the short rail laying operation obtained by the short rail laying operation simulation module based on the actual completed operation data and / or the operation plan adjustment data; the operation correction module only corrects the corresponding first progress segment vector and / or second progress segment vector.
[0041] In one embodiment of the present invention, the intelligent operation adjustment module includes: a key target acquisition unit, a cable laying operation path allocation unit, an operation status update unit, and a conflict area operation adjustment unit.
[0042] The key target acquisition unit is used to acquire each key target of the operation and to acquire the priority order of each key target, so that the intelligent operation adjustment module can adjust the cable laying operation and / or short rail laying operation to meet the key target settings.
[0043] The cable laying operation path allocation unit is used to allocate the cable laying operation path into several sub-operation paths and obtain the area coordinates corresponding to each sub-operation path.
[0044] The operation status update unit is used to update the status of cable laying operation based on whether the operation path track is available; the status includes track unusable status and track usable status, and updates the work efficiency of each operation path under different statuses.
[0045] The conflict zone operation adjustment unit is used to adjust the progress of cable laying operations and short rail laying operations; the adjustment method includes at least one of the following: (1) Adjust the time period for cable laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas; the adjustment method for the time period is to carry out the work in other areas first, and then carry out the cable laying operation in the corresponding area after the corresponding short rail laying is completed.
[0046] (2) The conflict area is further divided into several sub-conflict areas, or / and the construction unit time is divided into several sub-construction unit times, so that the cable laying operation and the short rail laying operation are carried out in the sub-conflict areas and in the sub-construction unit time. (3) Adjust the time period for short rail laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas.
[0047] This invention further discloses an intelligent path planning method for cable laying operations. Figure 2 This is a flowchart of an intelligent path planning method for cable laying operations according to an embodiment of the present invention; please refer to [link / reference]. Figure 2 The intelligent path planning method for cable laying operations includes:
Step S1
Step S2
Step S3
Step S4
Step S5
Step S6
Step S7
[0048] In one embodiment of the present invention, the intelligent path planning method for cable laying operations further includes: The steps for constructing a mathematical model for cable laying operations are as follows: The mathematical model construction module constructs a mathematical model for cable laying operations; the mathematical model for cable laying operations performs path planning for cable laying operations and short rail laying operations based on the operation objectives, cable laying operation data, short rail laying operation data, first efficiency data, and second efficiency data. Cable laying operation simulation steps: The cable laying operation simulation module acquires cable laying operation data, which includes at least one cable laying operation segment; based on the acquired cable laying operation data, the module simulates the first progress segment vector of each cable laying operation segment in the BIM model constructed by the BIM model building module. The first progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point; when presenting the progress, the module generates a corresponding operation simulation animation display based on the first progress segment vector of each cable laying operation segment, and can present the corresponding cable laying completion animation at set time nodes according to the time axis; The simulation steps for short rail laying are as follows: The short rail laying operation simulation module acquires short rail laying operation data, which includes at least one short rail laying operation segment; based on the acquired short rail laying operation data, the module simulates the second progress segment vector of each short rail laying operation segment in the BIM model constructed by the BIM model building module. The second progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point; when presenting the progress, a corresponding operation simulation animation is generated based on the second progress segment vector of each short rail laying operation segment, and the corresponding short rail laying completion animation can be presented at set time nodes according to the time axis. Collision detection steps: The collision detection module detects whether there is a collision risk between the two operations based on the first progress segment vector constructed by the cable laying operation simulation module and the second progress segment vector constructed by the short rail laying operation simulation module. The specific judgment method includes: extracting the operation segments in each construction unit time in the first progress segment vector, extracting the operation segments in each construction unit time in the second progress segment vector, and judging whether there is a partial overlap of the coordinates of the two operation progress segments in a certain construction unit time. If so, it is judged that there is a collision risk, that is, there is an intersection point of construction operations, and an alarm signal is sent. Intelligent operation adjustment steps: After the collision detection module detects the existence of construction operation intersections, the intelligent operation adjustment module will intelligently adjust the cable laying operation and / or short rail laying operation to avoid construction operation intersections.
[0049] In one embodiment of the present invention, the cable laying operation simulation module simulates the progress segment of the cable laying operation in the BIM model based on the input cable laying operation construction plan data and actual construction progress data. The short rail laying operation simulation module simulates the progress segments of the short rail laying operation in the BIM model based on the input short rail laying operation construction plan data and actual construction progress data.
[0050] The intelligent path planning method for cable laying operations further includes: an operation correction module correcting the cable laying operation data obtained by the cable laying operation simulation module and the short rail laying operation obtained by the short rail laying operation simulation module based on the actual completed operation data and / or the operation plan adjustment data; the operation correction module only corrects the corresponding first progress segment vector and / or the second progress segment vector.
[0051] In one embodiment of the present invention, the intelligent job adjustment step includes: The key target acquisition unit acquires each key target of the operation and obtains the priority order of each key target, so that the intelligent operation adjustment module adjusts the cable laying operation and / or short rail laying operation to meet the key target settings. The cable laying operation path allocation unit divides the cable laying operation path into several sub-operation paths and obtains the area coordinates corresponding to each sub-operation path. The operation status update unit updates the status of cable laying operation based on whether the operation path track is available; the status includes track unusable status and track usable status, and updates the work efficiency of each operation path under different statuses; The conflict zone operation adjustment unit adjusts the progress of cable laying and short rail laying operations; the adjustment methods include at least one of the following: (1) Adjust the time period for cable laying operations in conflict areas to avoid them being carried out in conflict areas or within the same construction time unit as short rail laying operations; (2) The conflict area is further divided into several sub-conflict areas, or / and the construction unit time is divided into several sub-construction unit times, so that the cable laying operation and the short rail laying operation are carried out in the sub-conflict areas and in the sub-construction unit time. (3) Adjust the time period for short rail laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas.
[0052] In summary, the intelligent path planning system, method, electronic device, and storage medium for cable laying operations proposed in this invention can track the progress of different construction operations in real time, avoid conflicts between different operations, improve the safety of project construction, and ensure the steady progress of the project.
[0053] It should be noted that this application can be implemented in software and / or a combination of software and hardware; for example, it can be implemented using an application-specific integrated circuit (ASIC), a general-purpose computer, or any other similar hardware device. In some embodiments, the software program of this application can be executed by a processor to implement the steps or functions described above. Similarly, the software program of this application (including related data structures) can be stored in a computer-readable recording medium; for example, RAM memory, magnetic or optical drives, floppy disks, and similar devices. In addition, some steps or functions of this application can be implemented in hardware; for example, as circuitry that cooperates with a processor to perform the various steps or functions.
[0054] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0055] The description and application of the present invention herein are illustrative and not intended to limit the scope of the invention to the embodiments described above. Effects or advantages involved in the embodiments may not be apparent due to various factors, and the description of effects or advantages is not intended to limit the embodiments. Variations and modifications of the embodiments disclosed herein are possible, and various substitutions and equivalents of the components in the embodiments are well known to those skilled in the art. It should be apparent to those skilled in the art that the invention can be implemented in other forms, structures, arrangements, proportions, and with other components, materials, and parts without departing from the spirit or essential characteristics of the invention. Other variations and modifications can be made to the embodiments disclosed herein without departing from the scope and spirit of the invention.
Claims
1. A smart path planning system for cable laying operations, characterized in that, The intelligent path planning system for cable laying operations includes: The BIM model building module is used to build a BIM model of the construction tunnel. The BIM model includes the coordinates of each key point of the construction tunnel in a preset coordinate system. The cable laying operation data conversion module is used to acquire cable laying operation data and convert the cable laying operation data into a first vector related to location in the BIM model; The short rail laying operation data conversion module is used to acquire short rail laying operation data and convert the short rail laying operation data into a second vector related to the location in the BIM model; The cable laying operation efficiency acquisition module is used to acquire the first efficiency data of cable laying operation per unit time; the first efficiency data includes the first manual operation efficiency data and the first machine operation efficiency data. The short rail laying operation efficiency acquisition module is used to acquire the second efficiency data of the short rail laying operation per unit time; the second efficiency data includes the second manual operation efficiency data and the second machine operation efficiency data. The laying rule setting module is used to set the laying rule data between cable laying operations and short rail laying operations; The path planning module is used to plan the path for cable laying operations and short rail laying operations based on cable laying operation data, short rail laying operation data, first efficiency data, second efficiency data, laying rule data, and operation objectives. The path planning module allocates first manual operation efficiency data, first machine operation efficiency data, second manual operation efficiency data, and second machine operation efficiency data according to the operation objectives.
2. The intelligent path planning system for cable laying operations according to claim 1, characterized in that: The intelligent path planning system for cable laying operations further includes: A mathematical model construction module for laying operations is used to construct a mathematical model for laying operations; the mathematical model for laying operations performs path planning for cable laying operations and short rail laying operations based on the operation objectives, cable laying operation data, short rail laying operation data, first efficiency data, and second efficiency data. A cable laying operation simulation module is used to acquire cable laying operation data, which includes at least one cable laying operation segment. Based on the acquired cable laying operation data, the module simulates the first progress segment vector of each cable laying operation segment in the BIM model constructed by the BIM model building module. The first progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point. When presenting the progress, the module generates a corresponding operation simulation animation display based on the first progress segment vector of each cable laying operation segment, and can present the corresponding cable laying completion animation at a set time node according to the time axis. A short rail laying operation simulation module is used to acquire short rail laying operation data, which includes at least one short rail laying operation segment. Based on the acquired short rail laying operation data, the module simulates the second progress segment vector of each short rail laying operation segment in the BIM model constructed by the BIM model building module. The second progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point. When presenting the progress, the module generates a corresponding operation simulation animation display based on the second progress segment vector of each short rail laying operation segment, and can present the corresponding short rail laying completion animation at a set time node according to the time axis. The collision detection module is used to detect whether there is a collision risk between two operations based on the first progress segment vector constructed by the cable laying operation simulation module and the second progress segment vector constructed by the short rail laying operation simulation module. The specific judgment method includes: extracting the operation segments in each construction unit time in the first progress segment vector, extracting the operation segments in each construction unit time in the second progress segment vector, and judging whether there is partial coordinate overlap between the two operation progress segments in a certain construction unit time. If so, it is judged that there is a collision risk, that is, there is a construction operation intersection point, and an alarm signal is sent. The path planning module includes an intelligent operation adjustment module, which is used to intelligently adjust the cable laying operation and / or short rail laying operation after the collision detection module detects the existence of a construction operation intersection point, thereby avoiding the occurrence of construction operation intersection points.
3. The intelligent path planning system for cable laying operations according to claim 1, characterized in that: The laying rules set by the laying rule setting module include: within a set area and within the same unit of time, cable laying and short rail laying operations cannot be carried out simultaneously; cable laying using machines can only be carried out after the short rail laying is completed in the corresponding area. The cable laying operation simulation module simulates the progress segments of the cable laying operation in the BIM model based on the input cable laying operation construction plan data and actual construction progress data. The short rail laying operation simulation module simulates the progress segments of the short rail laying operation in the BIM model based on the input short rail laying operation construction plan data and actual construction progress data. The intelligent path planning system for cable laying operations further includes an operation correction module, which is used to correct the cable laying operation data obtained by the cable laying operation simulation module and the short rail laying operation obtained by the short rail laying operation simulation module based on the actual completed operation data and / or the operation plan adjustment data; the operation correction module only corrects the corresponding first progress segment vector and / or second progress segment vector.
4. The intelligent path planning system for cable laying operations according to claim 1, characterized in that: The intelligent operation adjustment module includes: The key target acquisition unit is used to acquire the key targets of the operation and the priority order of each key target, so that the intelligent operation adjustment module can adjust the cable laying operation and / or short rail laying operation to meet the key target settings. The cable laying operation path allocation unit is used to allocate the cable laying operation path into several sub-operation paths and obtain the area coordinates corresponding to each sub-operation path. The work status update unit is used to update the status of cable laying work based on whether the work path track is available; the status includes track unusable status and track usable status, and updates the work efficiency of each work path under different statuses. The conflict zone operation adjustment unit is used to adjust the progress of cable laying operations and short rail laying operations; the adjustment method includes at least one of the following: (1) Adjust the time period for cable laying operations in conflict areas to avoid them being carried out in conflict areas or within the same construction time unit as short rail laying operations; (2) The conflict area is further divided into several sub-conflict areas, or / and the construction unit time is divided into several sub-construction unit times, so that the cable laying operation and the short rail laying operation are carried out in the sub-conflict areas and in the sub-construction unit time. (3) Adjust the time period for short rail laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas.
5. A method for intelligent path planning in cable laying operations, characterized in that, The intelligent path planning method for cable laying operations includes: BIM model construction steps: The BIM model construction module constructs a BIM model of the construction tunnel, which includes the coordinates of each key point of the construction tunnel in a preset coordinate system; Cable laying operation data conversion steps: The cable laying operation data conversion module acquires the cable laying operation data and converts the cable laying operation data into a first vector related to the location in the BIM model; Short rail laying operation data conversion steps: The short rail laying operation data conversion module acquires the short rail laying operation data and converts the short rail laying operation data into a second vector related to the location in the BIM model; Cable laying operation efficiency acquisition steps: The cable laying operation efficiency acquisition module acquires the first efficiency data of cable laying operation per unit time; the first efficiency data includes the first manual operation efficiency data and the first machine operation efficiency data; Steps for obtaining efficiency data of short rail laying operation: The short rail laying operation efficiency acquisition module acquires the second efficiency data of short rail laying operation per unit time; the second efficiency data includes the second manual operation efficiency data and the second machine operation efficiency data; Laying rule setting steps: The laying rule setting module sets the laying rule data between cable laying operations and short rail laying operations; Path planning steps: The path planning module performs path planning for cable laying operations and short rail laying operations based on cable laying operation data, short rail laying operation data, first efficiency data, second efficiency data, laying rule data, and operation objectives; the path planning module allocates first manual operation efficiency data, first machine operation efficiency data, second manual operation efficiency data, and second machine operation efficiency data according to the operation objectives.
6. The intelligent path planning method for cable laying operations according to claim 5, characterized in that: The intelligent path planning method for cable laying operations further includes: The steps for constructing a mathematical model for cable laying operations are as follows: The mathematical model construction module constructs a mathematical model for cable laying operations; the mathematical model for cable laying operations performs path planning for cable laying operations and short rail laying operations based on the operation objectives, cable laying operation data, short rail laying operation data, first efficiency data, and second efficiency data. Cable laying operation simulation steps: The cable laying operation simulation module acquires cable laying operation data, which includes at least one cable laying operation segment; based on the acquired cable laying operation data, the module simulates the first progress segment vector of each cable laying operation segment in the BIM model constructed by the BIM model building module. The first progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point; when presenting the progress, the module generates a corresponding operation simulation animation display based on the first progress segment vector of each cable laying operation segment, and can present the corresponding cable laying completion animation at set time nodes according to the time axis; The simulation steps for short rail laying are as follows: The short rail laying operation simulation module acquires short rail laying operation data, which includes at least one short rail laying operation segment; based on the acquired short rail laying operation data, the module simulates the second progress segment vector of each short rail laying operation segment in the BIM model constructed by the BIM model building module. The second progress segment vector includes the operation direction data, operation time period data, coordinate data of each key point of the operation segment in the coordinate system, and the completion time point data corresponding to each key point; when presenting the progress, a corresponding operation simulation animation is generated based on the second progress segment vector of each short rail laying operation segment, and the corresponding short rail laying completion animation can be presented at set time nodes according to the time axis. Collision detection steps: The collision detection module detects whether there is a collision risk between the two operations based on the first progress segment vector constructed by the cable laying operation simulation module and the second progress segment vector constructed by the short rail laying operation simulation module. The specific judgment method includes: extracting the operation segments in each construction unit time in the first progress segment vector, extracting the operation segments in each construction unit time in the second progress segment vector, and judging whether there is a partial overlap of the coordinates of the two operation progress segments in a certain construction unit time. If so, it is judged that there is a collision risk, that is, there is an intersection point of construction operations, and an alarm signal is sent. Intelligent operation adjustment steps: After the collision detection module detects the existence of construction operation intersections, the intelligent operation adjustment module will intelligently adjust the cable laying operation and / or short rail laying operation to avoid construction operation intersections.
7. The intelligent path planning method for cable laying operations according to claim 5, characterized in that: The cable laying operation simulation module simulates the progress segments of the cable laying operation in the BIM model based on the input cable laying operation construction plan data and actual construction progress data. The short rail laying operation simulation module simulates the progress segments of the short rail laying operation in the BIM model based on the input short rail laying operation construction plan data and actual construction progress data. The intelligent path planning method for cable laying operations further includes: an operation correction module correcting the cable laying operation data obtained by the cable laying operation simulation module and the short rail laying operation obtained by the short rail laying operation simulation module based on the actual completed operation data and / or the operation plan adjustment data; the operation correction module only corrects the corresponding first progress segment vector and / or the second progress segment vector.
8. The intelligent path planning method for cable laying operations according to claim 5, characterized in that: The intelligent operation adjustment steps include: The key target acquisition unit acquires each key target of the operation and obtains the priority order of each key target, so that the intelligent operation adjustment module adjusts the cable laying operation and / or short rail laying operation to meet the key target settings. The cable laying operation path allocation unit divides the cable laying operation path into several sub-operation paths and obtains the area coordinates corresponding to each sub-operation path. The operation status update unit updates the status of cable laying operation based on whether the operation path track is available; the status includes track unusable status and track usable status, and updates the work efficiency of each operation path under different statuses; The conflict zone operation adjustment unit adjusts the progress of cable laying and short rail laying operations; the adjustment methods include at least one of the following: (1) Adjust the time period for cable laying operations in conflict areas to avoid them being carried out in conflict areas or within the same construction time unit as short rail laying operations; (2) The conflict area is further divided into several sub-conflict areas, or / and the construction unit time is divided into several sub-construction unit times, so that the cable laying operation and the short rail laying operation are carried out in the sub-conflict areas and in the sub-construction unit time. (3) Adjust the time period for short rail laying operations in conflict areas to avoid construction in the same construction time unit as short rail laying operations in conflict areas.
9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, When the processor executes the computer program, it implements the steps of the method according to any one of claims 5 to 8.
10. A storage medium storing computer program instructions thereon, characterized in that, When executed by a processor, the computer program instructions implement the steps of the method according to any one of claims 5 to 8.