A substation site selection method and device and a quantum computer
By constructing decision variables and constraints, the problem is transformed into a quadratic unconstrained binary optimization problem. Using quantum computing algorithms, the problem of finding local optimal solutions in traditional substation site selection methods is solved, achieving global optimal site selection and scientific accuracy in power grid planning.
Patent Information
- Application Number
- CN202510988311.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-07-17
- Publication Date
- 2026-11-20
AI Technical Summary
Traditional substation site selection methods often fall into multiple local optima when considering factors such as geographical location, power supply reliability, and cost, resulting in non-globally optimal site selection results.
The decision variables and constraints are constructed, and the problem is transformed into a quadratic unconstrained binary optimization problem by combining the objective cost function and the penalty term. The global optimal solution is obtained by using quantum computing algorithms such as quantum approximation optimization algorithms.
This avoids local optima caused by multiple factors, improves the scientificity and accuracy of substation site selection and power grid planning, reduces human interference, and adapts to dynamic changes in power demand.
Smart Images

Figure CN123140446A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of quantum computer technology, and in particular to a substation site selection method, apparatus, and quantum computer. Background Technology
[0002] With the rapid development of the social economy and the acceleration of urbanization, the demand for electricity continues to grow, placing higher demands on the power supply capacity and service quality of the power grid. Against this backdrop, the upgrading and renovation of old substations and the site selection and construction of new substations have become key tasks to improve the performance of the power grid and meet the ever-increasing demand for electricity. Since the construction of substations involves huge investments and complex technical decisions, how to scientifically and efficiently select the location of substations has become an important issue in power grid planning and design.
[0003] Traditional substation site selection methods often rely on experience-based judgment and simple techno-economic comparisons. When considering factors such as geographical location, power supply reliability, and cost, the site selection and capacity determination problem often has multiple locally optimal solutions, which may result in a suboptimal site selection. Therefore, how to comprehensively consider multiple influencing factors and quickly determine the globally optimal substation site selection scheme is a technical problem that urgently needs to be solved. Summary of the Invention
[0004] This invention provides a substation site selection method and apparatus to solve the problem that in the prior art, when considering factors such as geographical location, power supply reliability and cost, the site selection and capacity determination problem often has multiple local optimal solutions, which may lead to the site selection result not being optimal.
[0005] This specification provides an embodiment of a substation site selection method, including:
[0006] Construct decision variables and constraints on the decision variables; wherein, the decision variables include location variables and allocation variables; the location variables represent the establishment of a target substation at the target location, and the allocation variables represent the service provided by the target substation to the target users;
[0007] Acquire transportation cost data from the target location to the target user, substation cost data required to build the target substation at the target location, and construct a target cost function based on the location variables, allocation variables, transportation cost data, and substation cost data;
[0008] By combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection result.
[0009] Optionally, the constraints include a substation service association constraint, which indicates that the substation can only serve users after it has been built.
[0010] The process involves combining the objective cost function with a penalty term obtained by introducing a first penalty coefficient to the constraints associated with the substation construction service. This process constructs and solves a quadratic unconstrained binary optimization problem characterizing the substation site selection, yielding the substation site selection results, including:
[0011] By combining the objective cost function and the first penalty term obtained by introducing a first penalty coefficient to the associated constraints of the substation construction service, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection and sizing results.
[0012] Optionally, the constraints may also include user allocation constraints, which state that each user must be assigned to a substation at a specific location.
[0013] The process involves constructing and solving a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, resulting in the substation site selection outcome, including:
[0014] By combining the objective cost function and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, a quadratic unconstrained binary optimization problem characterizing the substation location is constructed and solved to obtain the substation location result.
[0015] Alternatively, by combining the objective cost function, the first penalty term, and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, a quadratic unconstrained binary optimization problem characterizing the substation location can be constructed and solved to obtain the substation location result.
[0016] Optionally, the constraints include capacity load constraints, which indicate that the total power demand of the users served by the substation does not exceed the maximum power capacity of the substation.
[0017] The process involves constructing and solving a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, resulting in the substation site selection outcome, including:
[0018] By combining the objective cost function, the first penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation location is constructed and solved to obtain the substation location result.
[0019] Alternatively, by combining the objective cost function, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection result;
[0020] Alternatively, by combining the objective cost function, the first penalty term, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation location can be constructed and solved to obtain the substation location result.
[0021] Optionally, the third penalty term obtained by introducing a third penalty coefficient into the capacity load constraint includes:
[0022] By introducing slack variables, the inequalities corresponding to the capacity load constraints are transformed into equalities; wherein, the slack variables are greater than or equal to 0.
[0023] The equation is transformed into a third penalty term by introducing the third penalty coefficient.
[0024] Optionally, the step of solving the quadratic unconstrained binary optimization problem characterizing the substation site selection to obtain the substation site selection result includes:
[0025] The quadratic unconstrained binary optimization problem characterizing the substation site selection is solved using at least one of the following algorithms: quantum approximation optimization algorithm, simulated annealing algorithm, quantum annealing algorithm, and genetic algorithm, to obtain the substation site selection result.
[0026] This specification also provides a substation site selection device, comprising:
[0027] A variable construction module is used to construct decision variables and constraints on the decision variables; the decision variables include location variables and allocation variables; the location variables represent the establishment of a target substation at the target location, and the allocation variables represent that the target user is served by the target substation;
[0028] The function construction module is used to obtain transportation cost data from the target location to the target user, substation cost data required to build the target substation at the target location, and construct the target cost function based on the location variables, allocation variables, transportation cost data and substation cost data.
[0029] The problem-solving module is used to construct and solve a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, and to obtain the substation site selection result.
[0030] A quantum control system that utilizes a substation location method to execute quantum computing tasks, or includes a substation location device.
[0031] A quantum computer, including a quantum control system.
[0032] A readable storage medium having a computer program stored thereon, which, when executed by a processor, enables the substation site selection method described above.
[0033] Its beneficial effects are as follows: This application transforms the substation site selection problem into a quadratic unconstrained binary optimization problem suitable for quantum processing by combining the objective cost function constructed based on the site selection variables, allocation variables, transportation cost data and substation cost data, and the penalty term obtained by introducing a penalty coefficient on the constraints. By solving the quadratic unconstrained binary optimization problem, the global optimal solution under substation site selection is obtained, avoiding the solution from getting trapped in local optima due to factors such as geographical location, power supply reliability and cost, reducing the interference of human factors, and improving the scientificity and accuracy of substation site selection and power grid planning. Attached Figure Description
[0034] The accompanying drawings, which are included to provide a further understanding of this application and form part of this application, illustrate exemplary embodiments and are used to explain this application, but do not constitute an undue limitation of this application. In the drawings:
[0035] Figure 1 A flowchart of a substation site selection method provided in the embodiments of this specification;
[0036] Figure 2 A schematic diagram of a substation site selection device provided in the embodiments of this specification;
[0037] Figure 3 This is a schematic diagram of a computer-readable medium provided for embodiments of this specification. Detailed Implementation
[0038] The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and should not be construed as limiting the present invention.
[0039] It should be noted that, unless otherwise specifically stated, the relative arrangement, numerical expressions, and values of the components and steps described in these embodiments do not limit the scope of the invention.
[0040] The following description of at least one exemplary embodiment is merely illustrative and is in no way intended to limit the invention or its application or use.
[0041] Techniques, methods, and equipment known to those skilled in the art may not be discussed in detail, but where appropriate, such techniques, methods, and equipment should be considered part of the specification.
[0042] In all the examples shown and discussed herein, any specific values should be interpreted as merely exemplary and not as limitations. Therefore, other examples of exemplary embodiments may have different values.
[0043] It should be noted that similar labels and letters in the following figures indicate similar items; therefore, once an item is defined in one figure, it does not need to be discussed further in subsequent figures.
[0044] Reference Figure 1 A flowchart of a substation site selection method provided in the embodiments of this specification includes: S101: constructing decision variables and constraints on the decision variables; wherein, the decision variables include site selection variables and allocation variables; the site selection variables represent establishing a target substation at a target location, and the allocation variables represent that the target user is served by the target substation;
[0045] In one optional embodiment, multiple decision variables are defined based on the substation site selection scenario to achieve substation site selection planning. Therefore, this embodiment uses two decision variables to determine the substation site selection, namely, the site selection variable y. i Assignment variable x ij The location variable represents the establishment of a substation at location i, and the allocation variable represents that user j is served by the substation at location i. Then, constraints are set on the decision variables. Since the location of the substation involves many factors such as geographical location, power supply reliability and cost, all the constraints set by the various factors involved are not listed here. Only a few constraints are shown as examples for easy understanding.
[0046] If the constraints include a substation service association constraint, the substation service association constraint indicates that the substation can only serve users after construction, denoted as x. ij ≤y i ; and / or, the constraints also include user-assigned constraints, denoted as Where n is the substation construction location number, and the user allocation constraint means that each user must be assigned to a substation at a specific location. This method establishes the decision variables and constraints, providing data support for transforming the linear programming problem with binary variables into a quadratic unconstrained binary optimization problem.
[0047] S102: Obtain transportation cost data from the target location to the target user, substation cost data required to build the target substation at the target location, and construct a target cost function based on the location variables, allocation variables, transportation cost data and substation cost data;
[0048] For ease of explanation, this embodiment assumes 3 selectable substation locations and 2 users requiring service, with i = 1, 2, 3, j = 1, 2. In this case, we obtain the transportation cost data T for power transmission to the two users when the substation is built at different locations, and the substation cost data F required when the substation is built at different locations. Let's assume the transportation cost data T... ij =[[10,20],[20,30],[30,40]],T ij Let F represent the transportation cost from location i to user j. Given the substation cost data F = [10, 20, 30] required for different locations, then construct a target cost function based on the location variables, allocation variables, transportation cost data, and substation cost data. Here, S represents the minimum cost value. Determining the target cost function in this way facilitates the subsequent determination of the optimal substation location.
[0049] S103: By combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection result.
[0050] To transform the linear programming problem with binary variables into a quadratic unconstrained binary optimization problem, taking the example of 3 possible substation locations and 2 users to be served, we need to convert the constraints into penalty terms, i.e., the substation service association constraint x. ij ≤y i This inequality transforms into the first penalty term, which imposes a user allocation constraint. The second penalty term is transformed into the third penalty term. When the only constraint is the station construction service-related constraint, the first penalty term, obtained by combining the objective cost function and the first penalty coefficient introduced into the station construction service-related constraint, is used to construct and solve a quadratic unconstrained binary optimization problem representing the substation site selection situation, thus obtaining the substation site selection result. Specifically, the quadratic unconstrained binary optimization problem of the substation site selection situation is expressed as follows:
[0051] When the only constraint is user allocation, a quadratic unconstrained binary optimization problem characterizing the substation location is constructed and solved by combining the objective cost function and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, thus obtaining the substation location result. Specifically, the quadratic unconstrained binary optimization problem for substation location is expressed as follows:
[0052] When the constraints include station construction service association constraints and user allocation constraints, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved by combining the objective cost function, the first penalty term, and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraints, to obtain the substation site selection result; specifically, the quadratic unconstrained binary optimization problem of substation site selection can be expressed as:
[0053] By solving the above-mentioned quadratic unconstrained binary optimization problem, the optimal substation location results under different constraints can be obtained. By combining the objective cost function constructed based on the location variables, allocation variables, transportation cost data, and substation cost data, and the penalty term obtained by introducing penalty coefficients to the constraints, the substation location problem is transformed into a quadratic unconstrained binary optimization problem suitable for quantum processing. Solving the quadratic unconstrained binary optimization problem yields the global optimal solution for substation location, avoiding the solution from getting trapped in local optima due to factors such as geographical location, power supply reliability, and cost. This reduces the interference of human factors and improves the scientificity and accuracy of substation location and power grid planning.
[0054] Optionally, the constraints include capacity load constraints, which indicate that the total power demand of the users served by the substation does not exceed the maximum power capacity of the substation. Taking an example where there are 3 available substation locations and 2 users to be served, the capacity load constraint is expressed as follows: Among them, D j C represents the electricity demand of user j. ij Let i be the maximum power supply that the substation can provide to user j at location i.
[0055] By combining the objective cost function, the first penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation location is constructed and solved to obtain the substation location result; specifically, the quadratic unconstrained binary optimization problem of the substation location is expressed as:
[0056] Alternatively, by combining the objective cost function, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation location can be constructed and solved to obtain the substation location result; specifically, the quadratic unconstrained binary optimization problem of the substation location is expressed as:
[0057] Alternatively, by combining the objective cost function, the first penalty term, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation site selection can be constructed and solved to obtain the substation site selection result; specifically, the quadratic unconstrained binary optimization problem of the substation site selection is expressed as:
[0058] Taking into account the factors affecting the maximum carrying capacity of substations, a global optimal solution for substation site selection is obtained by solving a quadratic unconstrained binary optimization problem. This reduces construction costs and avoids substation damage caused by excessive capacity load after construction, thereby improving the scientificity and accuracy of substation site selection and power grid planning.
[0059] Optionally, the third penalty term obtained by introducing a third penalty coefficient into the capacity load constraint includes: introducing a slack variable to transform the inequality corresponding to the capacity load constraint into an equation; wherein the slack variable is greater than or equal to 0; and introducing the third field penalty coefficient to transform the equation into a third penalty term.
[0060] In one alternative embodiment, since the capacity load constraint corresponds to an inequality, directly participating in the optimization may limit the range of feasible solutions. In order to transform it into an unconstrained problem, non-negative relaxation variables need to be introduced to transform it into an equation. Then, a third field penalty coefficient is introduced to transform the equation into a third penalty term. By adding a third penalty term to the quadratic unconstrained binary optimization problem characterizing the substation location, it is ensured that the substation will not be overloaded, thus avoiding damage to the substation caused by overload.
[0061] Optionally, the step of solving the quadratic unconstrained binary optimization problem characterizing the substation location to obtain the substation location result includes: using at least one of the following algorithms—quantum approximation optimization algorithm, simulated annealing algorithm, quantum annealing algorithm, and genetic algorithm—to solve the quadratic unconstrained binary optimization problem characterizing the substation location to obtain the substation location result.
[0062] In one optional embodiment, the quadratic unconstrained binary optimization problem characterizing substation site selection is solved using a quantum approximation optimization algorithm as an example. Specifically, for decision variables, such as the site selection variable y... i Assignment variable x ijThe process involves encoding decision variables into binary form, followed by polynomial expansion of the quadratic unconstrained binary optimization problem to obtain linear and quadratic terms. A QUBO Q-matrix is then constructed based on these terms, mapped to a problem Hamiltonian. The problem Hamiltonian and a pre-defined hybrid Hamiltonian are applied alternately, and classical optimization algorithms are used to optimize the parameters in both. The minimum energy value is obtained by measuring quantum states. This minimum energy value is then decoded to yield the substation location result. The substation location result requires reverse verification of the constraints. If the constraints are not met, the quadratic unconstrained binary optimization problem is regenerated by adjusting the penalty coefficient, and a QUBO Q-matrix is constructed for solving until the globally optimal solution for the substation location is obtained. The quantum approximation optimization algorithm leverages the parallel computing characteristics of quantum computing to accelerate the solution process in multi-variable scenarios, enabling the finding of a relatively optimal layout in a shorter time. Because electricity demand is dynamic in time and space, especially with significant fluctuations in regional electricity consumption during peak and off-peak periods, traditional optimization methods struggle to respond quickly to these changes. QAOA can combine the parallelism of quantum computing to quickly update model parameters, adapt to fluctuating power load demands, and flexibly adjust location and capacity decisions, thereby improving the adaptability and resilience of the power grid.
[0063] In one alternative embodiment, various decision variables and constraints of influencing factors can be added according to the specific circumstances of substation site selection, which will not be elaborated here. This enables the substation site selection under complex influencing factors to be achieved using the method described in this application, thereby reducing costs while meeting user needs.
[0064] Reference Figure 2 This specification also provides a substation site selection device, comprising:
[0065] The variable construction module 201 is used to construct decision variables and constraints on the decision variables; the decision variables include location variables and allocation variables; the location variables represent the establishment of a target substation at the target location, and the allocation variables represent that the target user is served by the target substation;
[0066] The function construction module 202 is used to obtain transportation cost data from the target location to the target user, substation cost data required to build the target substation at the target location, and construct the target cost function based on the location variables, allocation variables, transportation cost data and substation cost data;
[0067] The problem-solving module 203 is used to construct and solve a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, and to obtain the substation site selection result.
[0068] Optionally, the constraints include a substation service association constraint, which indicates that the substation can only serve users after it has been built.
[0069] The problem-solving module includes:
[0070] The problem-solving unit is used to construct and solve a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the first penalty term obtained by introducing a first penalty coefficient on the constraints associated with the substation construction service, and to obtain the substation site selection and sizing result.
[0071] Optionally, the constraints may also include user allocation constraints, which state that each user must be assigned to a substation at a specific location.
[0072] The problem-solving unit also constructs and solves a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, and obtains the substation site selection result.
[0073] Alternatively, the problem-solving unit can construct and solve a quadratic unconstrained binary optimization problem characterizing the substation location by combining the objective cost function, the first penalty term, and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, thereby obtaining the substation location result.
[0074] Optionally, the constraints include capacity load constraints, which indicate that the total power demand of the users served by the substation does not exceed the maximum power capacity of the substation.
[0075] The problem-solving unit also constructs and solves a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function, the first penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, and obtains the substation site selection result.
[0076] Alternatively, the problem-solving unit can construct and solve a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, thereby obtaining the substation site selection result.
[0077] Alternatively, the problem-solving unit can construct and solve a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function, the first penalty term, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, thereby obtaining the substation site selection result.
[0078] Optionally, the problem-solving unit further includes:
[0079] The slack variable is introduced into the sub-unit to transform the inequalities corresponding to the capacity load constraint into equalities; wherein the slack variable is greater than or equal to 0.
[0080] The penalty coefficient is introduced into a sub-unit to introduce the third field penalty coefficient and transform the equation into a third penalty term.
[0081] Optionally, the problem-solving module further includes using at least one of the following algorithms—quantum approximation optimization algorithm, simulated annealing algorithm, quantum annealing algorithm, and genetic algorithm—to solve the quadratic unconstrained binary optimization problem characterizing the substation site selection, thereby obtaining the substation site selection result.
[0082] Regarding the apparatus in the above embodiments, the process of performing each step has been described in detail in the embodiments of the method, and will not be elaborated here.
[0083] A quantum control system that utilizes a substation location method to execute quantum computing tasks, or includes a substation location device.
[0084] A quantum computer, including a quantum control system.
[0085] A readable storage medium having a computer program stored thereon, which, when executed by a processor, enables the substation site selection method described above.
[0086] Reference Figure 3 This is a schematic diagram of a computer-readable medium provided for embodiments of this specification.
[0087] accomplish Figure 1 The computer instructions of the method shown can be stored on one or more computer-readable media. A computer-readable medium can be a readable signal medium or a readable storage medium. A readable storage medium can be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor device, or any combination thereof. More specific examples (a non-exhaustive list) of readable storage media include: an electrical connection having one or more wires, a portable disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), optical fiber, portable compact disk read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof.
[0088] The computer-readable storage medium may include data signals propagated in baseband or as part of a carrier wave, carrying readable program code. Such propagated data signals may take various forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination thereof. The readable storage medium may also be any readable medium other than a readable storage medium, capable of transmitting, propagating, or transmitting a program for use by or in connection with an instruction execution device, apparatus, or apparatus. The program code contained on the readable storage medium may be transmitted using any suitable medium, including but not limited to wireless, wired, optical fiber, RF, etc., or any suitable combination thereof.
[0089] Program code for performing the operations of this invention can be written in any combination of one or more programming languages, including object-oriented programming languages such as Java and C++, and conventional procedural programming languages such as C or similar languages. The program code can execute entirely on the user's computing device, partially on the user's device, as a standalone software package, partially on the user's computing device and partially on a remote computing device, or entirely on a remote computing device or server. In cases involving remote computing devices, the remote computing device can be connected to the user's computing device via any type of network, including a local area network (LAN) or a wide area network (WAN), or it can be connected to an external computing device (e.g., via the Internet using an Internet service provider).
[0090] In summary, this invention can be implemented in hardware, or as software modules running on one or more processors, or a combination thereof. Those skilled in the art will understand that in practice, general-purpose data processing devices such as microprocessors or digital signal processors (DSPs) can be used to implement some or all of the functions of some or all of the components according to the embodiments of the invention. The invention can also be implemented as a device or apparatus program (e.g., a computer program and computer program product) for performing part or all of the methods described herein. Such programs implementing the invention can be stored on a computer-readable medium or can take the form of one or more signals. Such signals can be downloaded from an Internet website, provided on a carrier signal, or provided in any other form.
[0091] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of the present invention. It should be understood that the present invention is not inherently related to any specific computer, virtual device, or electronic device, and various general-purpose devices can also implement the present invention. The above descriptions are merely specific embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
[0092] The various embodiments in this specification are described in a progressive manner. The same or similar parts between the various embodiments can be referred to each other. Each embodiment focuses on describing the differences from other embodiments.
[0093] The above description is merely an embodiment of this application and is not intended to limit the scope of this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the scope of the claims of this application.
Claims
1. A method for selecting a substation site, characterized in that, include: Construct decision variables and constraints on the decision variables; wherein, the decision variables include location variables and allocation variables; The location variable represents the establishment of the target substation at the target location, and the allocation variable represents the service provided by the target substation to the target user; Acquire transportation cost data from the target location to the target user, substation cost data required to build the target substation at the target location, and construct a target cost function based on the location variables, allocation variables, transportation cost data, and substation cost data; By combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection result.
2. The method as described in claim 1, characterized in that, The constraints include a substation service association constraint, which states that the substation can only serve users after it has been built. The process involves combining the objective cost function with a penalty term obtained by introducing a first penalty coefficient to the constraints associated with the substation construction service. This process constructs and solves a quadratic unconstrained binary optimization problem characterizing the substation site selection, yielding the substation site selection results, including: By combining the objective cost function and the first penalty term obtained by introducing a first penalty coefficient to the associated constraints of the substation construction service, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection and sizing results.
3. The method as described in claim 2, characterized in that, The constraints also include user allocation constraints, which state that each user must be assigned to a substation at a specific location. The process involves constructing and solving a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, resulting in the substation site selection outcome, including: By combining the objective cost function and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, a quadratic unconstrained binary optimization problem characterizing the substation location is constructed and solved to obtain the substation location result. Alternatively, by combining the objective cost function, the first penalty term, and the second penalty term obtained by introducing a second penalty coefficient to the user allocation constraint, a quadratic unconstrained binary optimization problem characterizing the substation location can be constructed and solved to obtain the substation location result.
4. The method as described in claim 2 or 3, characterized in that, The constraints include capacity load constraints, which state that the total electricity demand of the users served by the substation does not exceed the substation's maximum power capacity. The process involves constructing and solving a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, resulting in the substation site selection outcome, including: By combining the objective cost function, the first penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation location is constructed and solved to obtain the substation location result. Alternatively, by combining the objective cost function, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation site selection is constructed and solved to obtain the substation site selection result; Alternatively, by combining the objective cost function, the first penalty term, the second penalty term, and the third penalty term obtained by introducing a third penalty coefficient to the capacity load constraint, a quadratic unconstrained binary optimization problem characterizing the substation location can be constructed and solved to obtain the substation location result.
5. The method as described in claim 4, characterized in that, The third penalty term obtained by introducing a third penalty coefficient into the capacity load constraint includes: By introducing slack variables, the inequalities corresponding to the capacity load constraints are transformed into equalities; wherein, the slack variables are greater than or equal to 0. The equation is transformed into a third penalty term by introducing the third penalty coefficient.
6. The method as described in claim 1, characterized in that, The solution of the quadratic unconstrained binary optimization problem characterizing the substation site selection results yields the following: The quadratic unconstrained binary optimization problem characterizing the substation site selection is solved using at least one of the following algorithms: quantum approximation optimization algorithm, simulated annealing algorithm, quantum annealing algorithm, and genetic algorithm, to obtain the substation site selection result.
7. A substation site selection device, characterized in that... ,include: The variable construction module is used to construct decision variables and constraints on the decision variables; The decision variables include location variables and allocation variables; The location variable represents the establishment of the target substation at the target location, and the allocation variable represents the service provided by the target substation to the target user. The function construction module is used to obtain transportation cost data from the target location to the target user, substation cost data required to build the target substation at the target location, and construct the target cost function based on the location variables, allocation variables, transportation cost data and substation cost data. The problem-solving module is used to construct and solve a quadratic unconstrained binary optimization problem characterizing the substation site selection by combining the objective cost function and the penalty term obtained by introducing a penalty coefficient to the constraints, and to obtain the substation site selection result.
8. A quantum control system, characterized in that, The substation location method as described in any one of claims 1 to 6 is used to perform quantum computing tasks, or includes the substation location device as described in claim 7.
9. A quantum computer, characterized in that, Including the quantum control system as described in claim 8.
10. A readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by a processor, it can implement the substation site selection method according to any one of claims 1 to 6.