Blast furnace matching tank method and device, electronic equipment and storage medium
By establishing a molten iron task scoring model and a ladle car cost model, and dynamically allocating ladle car resources, the problems of human error and system mismatch in molten iron scheduling in steel plants have been solved, achieving efficient and reasonable molten iron scheduling and ensuring the stability and efficiency of production.
Patent Information
- Application Number
- CN202611323145.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-28
- Publication Date
- 2026-11-20
AI Technical Summary
The existing methods for molten iron dispatching in steel plants rely on manual operation, which carries the risk of untimely dispatching and human error. Furthermore, the existing dispatching system cannot meet the molten iron dispatching needs of most steel plants across all scenarios.
Establish a molten iron task scoring model and a ladle car cost model. By calculating the score and matching cost of each molten iron task, ladle car resources are dynamically allocated to achieve efficient and reasonable molten iron scheduling.
To reduce human error, improve response speed, meet the dynamic needs of blast furnace production, ensure a reasonable match between molten iron temperature and time constraints, reduce the probability of low-temperature delivery and delays of molten iron, and improve production stability and efficiency.
Smart Images

Figure CN123140508A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of metallurgical control technology, and in particular to a blast furnace batching method, apparatus, electronic equipment, and storage medium. Background Technology
[0002] In the steel production process, molten iron dispatch is a key link connecting blast furnace ironmaking and steel plant processes. It is necessary not only to always have a sufficient number of ladle cars located under the blast furnace taphole to receive molten iron and ensure production safety, but also to dispatch the ladle cars that have finished receiving iron to the steel plant in a timely manner to avoid excessive drop in molten iron temperature, which would affect subsequent molten iron processing.
[0003] The current method of molten iron dispatching in steel plants still relies heavily on communication and coordination between dispatchers and locomotive drivers. Dispatchers need to make comprehensive judgments based on information such as blast furnace tapping, steel plant demand, and the real-time status of ladle cars to formulate ladle allocation plans. However, this method is prone to problems such as untimely dispatching and the risk of human error. With the development of internet technology, some steel plants use dispatching systems to issue and execute dispatching tasks based on system recommendations. However, currently, such dispatching systems can only be adapted to specific scenarios in certain steel plants and cannot meet the full-scenario molten iron dispatching needs of most steel plants. Summary of the Invention
[0004] This invention provides a blast furnace batching method, apparatus, electronic equipment, and storage medium to solve the technical problems of potential errors in manual scheduling and the mismatch between existing scheduling systems and actual conditions.
[0005] On one hand, the present invention provides a blast furnace ladle feeding method, the method comprising: A hot metal task scoring model is established based on the temperature of the molten iron and the time from the taphole to the target plant area. The score for each molten iron task is obtained based on the task scoring model, and then the task priority is determined. Establish a cost model for tank cars, monitor the status of each tapping hole under the blast furnace and the information of each tank car, obtain the iron demand task of the target plant area, and obtain the matching cost of each tank car based on the cost model; Based on task priority and matching cost, the locations of ladle cars and tapping points are matched one-to-one with the corresponding tasks to complete the ladle matching for the target blast furnace.
[0006] In one embodiment of the present invention, the step of obtaining a score for each molten iron task based on a task scoring model and then confirming the task priority specifically includes: calculating the score of the molten iron task according to the following formula. , , in, and It is a constant. This is the highest temperature of molten iron inside the blast furnace. This refers to the current temperature of the molten iron inside the blast furnace. The minimum required temperature for molten iron in the target plant area. The latest time for molten iron to be delivered to the target plant area. For the current time, This is the maximum allowable delay time.
[0007] In one embodiment of the present invention, when there are multiple molten iron tasks, This represents the maximum allowed delay time among multiple tasks.
[0008] In one embodiment of the present invention, the step of establishing a cost model for ladle cars, monitoring the status of each tapping hole under the blast furnace and the information of each ladle car, obtaining the iron demand task of the target plant area, and obtaining the matching cost for each ladle car based on the cost model specifically includes: obtaining the matching cost according to the following formula. , , in, , and It is a constant; Indicates the current tanker truck Distance from the taphole The distance; Indicates tanker truck The waiting time from the current time until a new task becomes available.
[0009] In one embodiment of the present invention, after matching the location of the ladle car and the tapping hole with the corresponding task according to the task priority and matching cost to complete the ladle matching of the target blast furnace, the method further includes: after the ladle car completes the task, comparing the arrival time of the ladle car with the task time, determining whether the arrival of the ladle car is on time, early, or late, then calculating the scheduling performance reward, and feeding it back to the cost model of the ladle car to optimize the cost model of the ladle car.
[0010] In one embodiment of the present invention, the state of the iron outlet includes open and closed, and a corresponding number of empty tank cars are matched for each iron outlet according to the state of the iron outlet.
[0011] In one embodiment of the present invention, the number of empty tank trucks and the number of loaded tank trucks at the site are collected, and a balance weight is obtained based on the number of empty tank trucks and the number of loaded tank trucks. If the balance weight is less than or equal to a preset value, the number of empty tank trucks under each iron tap is configured according to Mode 1; if it is greater than the preset value, the number of empty tank trucks under each iron tap is configured according to Mode 2. The number of empty tank trucks under the iron tap in the opening of Mode 2 is greater than the number of empty tank trucks under the iron tap in the opening of Mode 1.
[0012] On the other hand, the present invention also provides a blast furnace can-feeding device, which employs the blast furnace can-feeding method described above, and the device includes: The modeling module is used to establish a hot metal task scoring model and a ladle car cost model based on the hot metal temperature and the time from the taphole under the blast furnace to the target plant area. The monitoring module is used to monitor the status of each tapping hole under the blast furnace and the information of each ladle car; The first confirmation module is used to obtain a score for each molten iron task based on the task scoring model, and then confirm the task priority. The second determining module is used to obtain the matching cost for each tanker truck based on the cost model; The matching module is used to match the location of the ladle car and the tapping hole with the corresponding task based on the task priority and matching cost, so as to complete the ladle matching for the target blast furnace.
[0013] On the other hand, the present invention also provides an electronic device, including: a processor, a memory, and a communication bus; the communication bus is used to connect the processor and the memory; the processor is used to execute a computer program stored in the memory to implement the blast furnace batching method as described above.
[0014] On the other hand, the present invention also provides a computer-readable storage medium having a computer program stored thereon, the computer program being used to cause a computer to perform the blast furnace batching method as described above.
[0015] The beneficial effects of this invention are as follows: The blast furnace ladle matching method, apparatus, electronic equipment, and storage medium proposed in this invention establish a molten iron task scoring model and a ladle car cost model. First, the priority of each task requiring molten iron in the target plant area is calculated. Then, the matching cost for each ladle car is calculated, and the task with the lowest matching cost is selected to complete the highest priority task. The remaining tasks are then matched sequentially. In this way, by matching the ladle car with the lowest cost according to task priority, dynamic allocation and scheduling of empty ladle cars is achieved, making the ladle matching plan more rational and efficient, and able to promptly meet the dynamic changes in the actual production needs of the blast furnace. Attached Figure Description
[0016] The accompanying drawings, which are incorporated in and form part of this specification, illustrate embodiments consistent with this application and, together with the description, serve to explain the principles of this application. It is obvious that the drawings described below are merely some embodiments of this application, and those skilled in the art can obtain other drawings based on these drawings without any inventive effort.
[0017] In the attached diagram: Figure 1 This is a flowchart of a blast furnace pot filling method provided in an embodiment of the present invention; Figure 2 This is a flowchart illustrating the selection of a canning mode in one embodiment of the present invention. Detailed Implementation
[0018] The following specific examples illustrate the implementation of the present invention. Those skilled in the art can easily understand other advantages and effects of the present invention from the content disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments. Various details in this specification can also be modified or changed based on different viewpoints and applications without departing from the spirit of the present invention. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.
[0019] It should be noted that the illustrations provided in the following embodiments are only schematic representations of the basic concept of the present invention. The drawings only show the components related to the present invention and are not drawn according to the actual number, shape and size of the components in the actual implementation. In the actual implementation, the form, quantity and proportion of each component can be arbitrarily changed, and the layout of the components may also be more complex.
[0020] In the following description, numerous details are explored to provide a more thorough explanation of embodiments of the invention. However, it will be apparent to those skilled in the art that embodiments of the invention may be practiced without these specific details. In other embodiments, well-known structures and devices are shown in block diagram form rather than in detail to avoid obscuring embodiments of the invention.
[0021] In the integrated iron and steel smelting process, molten iron produced in the blast furnace needs to be transported to the next process plant (such as the converter steelmaking plant and the iron casting machine workshop) in a timely and high-quality manner using dedicated transport tankers. During transportation, the molten iron naturally dissipates heat, and its temperature gradually decreases. If the molten iron arrives at a temperature that is too low, it will affect the smelting efficiency, energy consumption, and product quality of subsequent processes, and may even lead to equipment damage or production interruption. At the same time, the dispatching of molten iron must meet strict production rhythm requirements; delayed delivery will disrupt downstream production plans.
[0022] Please see Figure 1 The above is a flowchart illustrating a blast furnace batching method as an exemplary embodiment of this application. This blast furnace batching method can be executed by computer equipment, such as... Figure 1 As shown, in an exemplary embodiment, the blast furnace batching method includes at least steps S1 to S4, which are described in detail below: S1, Component molten iron task scoring model; Multi-dimensional key parameters related to molten iron transportation are collected, mainly including: the current actual tapping temperature of the molten iron, the transportation distance and estimated travel time from the blast furnace tapping point to the target plant (such as a steel plant, foundry, or blast furnace), the process requirement threshold for molten iron temperature at the target plant, and the rate of temperature drop of the molten iron during transit. Based on this, a comprehensive scoring function is established, which can quantify the urgency and importance of each molten iron transportation task.
[0023] For example, a task should receive a higher score when the molten iron temperature is close to the minimum acceptable temperature of the target plant area and the transportation time is long; conversely, a score should be relatively low if the molten iron temperature is high and the transportation path is short. Furthermore, weighting coefficients can be introduced to reflect the differences in sensitivity of different plants or production lines to molten iron quality, thereby improving the adaptability and accuracy of the scoring model.
[0024] Specifically, the data required to establish the molten iron task scoring model and the molten iron tasks required by the steel plant are collected. Establishing the molten iron task scoring model requires collecting the highest temperature of molten iron in the blast furnace. This refers to the theoretically highest temperature that the molten iron may reach or has a historical record during the tapping process. It is typically measured by thermocouples and is used to characterize the initial thermal energy potential of the molten iron; the current temperature of the molten iron inside the blast furnace. This refers to the current measured temperature of the molten iron at the tapping point or in the ladle, reflecting the current thermal state of the molten iron; the minimum required temperature of molten iron for the target plant area. The temperature is determined by the process specifications of downstream processes (such as converter steelmaking, iron casting machines, etc.). Temperatures below this level will affect smelting efficiency, product quality, and may even lead to production interruptions. The latest time for molten iron to reach the target plant area is also specified. Set according to the production plan window of the target factory area; current time Used to dynamically calculate the remaining available time for a task; maximum allowable delay time. This indicates the maximum tolerable delay time for the task. Exceeding this time limit will trigger a serious production anomaly. This parameter can be set according to the importance level of different production lines.
[0025] Based on the above parameters, the weighted comprehensive score formula is used to calculate the first... Priority rating of molten iron task : (Equation 1) Among them, the first item The second term represents the reciprocal of the safety margin for molten iron temperature. A larger value indicates that the current iron temperature is closer to the lower limit of the process, the higher the risk of temperature drop, and the more urgent the task. Indicates the urgency of the time window, when close When the timeout period is reached, this value approaches 0; if the timeout has occurred, it becomes a negative value (truncation can be set), reflecting the time pressure of the task. Weighting coefficient and The values are determined based on the relative importance of temperature and time factors in the scoring, and can be configured according to the actual operating strategy of the factory (e.g., increasing the value in winter or in scenarios with poor insulation). Improve under high-paced continuous production mode In some embodiments, and The sum of is 1.
[0026] In some embodiments, if there is only one molten iron task, then Subtract the current time from the task time. When there are multiple molten iron tasks, each task has a allowed late delivery time. This represents the maximum allowed delay time among multiple tasks.
[0027] S2. Obtain a score for each molten iron task based on the task scoring model, and then confirm the task priority.
[0028] Based on the scoring model established in S1, all pending molten iron transportation tasks are scored and sorted from highest to lowest score to form a task priority sequence. High-priority tasks represent those with a greater impact on production continuity, energy consumption control, or product quality, and require priority resource allocation. Simultaneously, the system can dynamically update task scores—for example, if a task's waiting time is prolonged, causing a continuous drop in molten iron temperature, its score is automatically increased, ensuring the scheduling strategy has real-time responsiveness.
[0029] For example, at 14:00, there are two tasks involving molten iron. Task A is to take one ladle of molten iron from blast furnace #3 (current temperature 1380℃) and deliver it to steelmaking #2 before 14:30. Task B is to take one ladle of molten iron from blast furnace #1 (temperature 1450℃) and deliver it to steelmaking #1 before 14:20.
[0030] in, and If the allowed late delivery time for Task A is 30 minutes and the allowed late delivery time for Task B is 20 minutes, then... minute, , ; Substituting the above explanation into Equation 1, we obtain the score for the calculation task.
[0031] =0.6*0.6+0.4*1=0.76;
[0032] ≈0.6*0.25+0.4*0.667≈0.417; therefore, > If task A has a higher priority than task B, then when allocating tank trucks, task A will be allocated tank trucks first.
[0033] S3. Construct a tanker truck cost model and calculate matching costs; After prioritizing molten iron tasks, the core task of the system is to optimally match limited ladle car resources with the molten iron tasks to be executed. The cost model aims to quantitatively evaluate the allocation (ladle car) Go to a specific iron outlet The cost or expense of making a decision to perform the corresponding task. This matching cost should comprehensively reflect losses in multiple dimensions, including transportation efficiency, time fit, and preservation of molten iron quality.
[0034] Each tapping point is assigned a geographic coordinate code, and its current status is as follows: tapping in progress, preparing to tapping (estimated start time), tapping completed, or under maintenance.
[0035] Each tanker truck has a unique number and its real-time satellite positioning coordinates. The system collects information on the tanker truck's status, such as whether it is empty, under heavy load, receiving iron, unloading iron, or waiting for instructions.
[0036] Establish a cost model for ladle cars, monitor the status of each tapping hole under the blast furnace and the information of each ladle car, obtain the iron demand task of the target plant area, and obtain the matching cost of each ladle car based on the cost model.
[0037] The cost model for ladle cars monitors the real-time operating status of each tapping point in the blast furnace (e.g., whether tapping is underway, estimated end time, molten iron composition, etc.), the location and status (empty / full, under maintenance, insulation performance), load capacity, and historical operating data of all available ladle cars. Simultaneously, it calculates the matching cost for each ladle car performing each task, based on the target plant's molten iron demand (including required quantity, composition requirements, and receiving window time). The matching cost considers multiple factors, such as the dispatch distance from the ladle car's current location to the tapping point, the compatibility of the ladle's preheating status with the molten iron temperature, ladle car turnover efficiency, whether inter-regional transport is required, and potential waiting or delay risks. By minimizing the total matching cost, overall logistics efficiency is improved.
[0038] Specifically, collect data from the current tanker truck. And tank trucks The waiting time from the current time until a new task becomes available. Then, the matching cost for each tanker truck performing each task is calculated using the following weighted comprehensive scoring formula. : (Equation 2) in, and It is a constant. Current position For iron tapping Location, To cover empty driving distance costs, assign tank trucks. From current location Drive to position k of the iron outlet The direct costs incurred. Specifically... It can be not only the straight-line distance in geography, but also the distance of feasible route planning based on the railway or road network in the factory area.
[0039] For example, tank car L1 is 200 meters from blast furnace #3 and 300 meters from blast furnace #1; it will be available after 5 minutes; tank car L2 is 1200 meters from blast furnace #3 and 300 meters from blast furnace #1, and will be available immediately; tank car L3 is 800 meters from blast furnace #3 and 700 meters from blast furnace #1, and will be available immediately. In this embodiment, Take 0.01, Take 10, specifically and It can be obtained by fitting multiple sets of data.
[0040] Then, the matching cost for tanker truck L1 to perform task A is calculated according to (Equation 2). = =52; The matching cost for tanker truck L2 to perform task A is calculated according to (Equation 2). = =12; The matching cost for tanker truck L3 to perform task A is calculated according to (Equation 2). = =8; Tanker truck L3 has the lowest matching cost, therefore tanker truck L3 is selected to perform task A.
[0041] To reduce computational load, after task A is matched, the matching cost for task B is calculated. Since tanker truck L3 has already been matched for task A, it is excluded when matching tankers for task B. The matching costs for tankers L1 and L2 to execute task B are calculated separately. The matching cost for tanker truck L1 is... = =53. The matching cost for tanker truck L2 to execute task B is = =7; Less than Therefore, tanker truck L2 was selected to perform task B.
[0042] S4. Based on task priority and matching cost, match the location of the ladle car and tapping hole with the corresponding task to complete the ladle matching for the target blast furnace.
[0043] The task priority list generated by S2 and the matching cost matrix for each tank car-task combination generated by S3 aim to achieve global optimization while satisfying all process constraints (such as molten iron composition, temperature, and time). This minimizes matching costs while ensuring high-priority tasks receive priority.
[0044] This invention, through the aforementioned ladle distribution method, can reduce human error and improve response speed. The model operates based on real-time data (temperature, location, status), enabling rapid adaptation to sudden changes in the production site (such as blast furnace tapping delays, ladle car malfunctions, and path blockages) and achieving dynamic rescheduling. By combining a scoring model and a cost model, it comprehensively considers multiple constraints such as temperature, time, distance, and resources, pursuing the optimal overall efficiency of the entire molten iron logistics system, rather than local optima. By prioritizing high-risk tasks, the probability of low-temperature delivery and severe delays in molten iron is effectively reduced, ensuring the stability and continuity of mainline production. Accurate temperature drop prediction and path optimization reduce unnecessary molten iron temperature drops, thereby reducing the reheating energy consumption in the steelmaking process and directly saving production costs.
[0045] This invention, through the construction of a two-layer decision-making architecture consisting of a molten iron task scoring model and a ladle car cost model, realizes the transformation of blast furnace ladle allocation from experience-driven to data and model-driven, providing core technical support for steel enterprises to build an efficient, reliable, and energy-saving molten iron supply chain.
[0046] In some embodiments, the locations of the tank cars and tapping points are matched one-to-one with the corresponding tasks based on task priority and matching cost. After completing the tank matching for the target blast furnace, the method further includes: comparing the arrival time of the tank cars with the task time, determining whether the arrival of the tank cars is on time, early, or late, then calculating the scheduling performance reward, and feeding it back to the cost model of the tank cars to optimize the cost model of the tank cars.
[0047] Specifically, the scheduling performance bonus is calculated using the following formula:
[0048] in, The incentive score for arriving on time, The incentive score for arriving early Penalty points for arriving late; Specifically, It is a constant; ,
[0049] Indicates the latest time specified. Indicates the actual arrival time. and It is a constant.
[0050] For example, if tanker truck L3 delivers task A at 14:25 (5 minutes early), it will receive a reward. Tanker truck L2 delivered mission B at 14:18 (2 minutes early) and received a reward. .
[0051] In some embodiments, the tapping spout can be in an open or closed state, and a corresponding number of empty ladle cars are matched to each tapping spout for each state. An open state indicates that molten iron is being tapped from the tap, and the ladle cars are receiving the iron below the tap. A closed state indicates that the tap is closed, and the closed state can be one of three states: before opening, blocked, or at rest.
[0052] Generally, each blast furnace is equipped with two tapholes, and each taphole has two iron receiving lines. When the taphole is open, that is, when iron is being tapped from the taphole under the current blast furnace, the number of empty ladle cars under the taphole can be appropriately increased to ensure the safety of iron tapping from the blast furnace.
[0053] For example, if a blast furnace taphole dispenses 4-5 ladles of molten iron at a time, and the first taphole dispenses 3 ladles of molten iron, it can be assumed that the second taphole under the same blast furnace is about to open. This taphole is in the pre-opening state. When the system determines that the current taphole is about to open, it determines the number of ladle cars under the taphole based on the real-time position of the ladle cars. If there are insufficient ladle cars, it will provide the required number of empty ladle cars.
[0054] When the taphole is blocked, several safety ladles are usually placed in place to prevent a disruption to production if the taphole unexpectedly opens and molten iron is not dispensed. When the taphole is in a dormant state, it indicates that the taphole needs cleaning or maintenance and may not open for molten iron for an extended period.
[0055] This invention, based on a dynamic ladle allocation strategy according to the taphole status, transforms the safety management of the high-temperature, high-risk, and continuous process of blast furnace tapping from reliance on manual experience to automatic control. It ensures that under any condition, there are always just the right number of ladle cars available below the taphole, avoiding both excessive use of empty ladle cars leading to waste and safety or production accidents caused by a reduction in empty ladle cars, thus achieving a balance between safety and efficiency.
[0056] In some embodiments, the number of empty tank trucks and the number of loaded tank trucks are collected at the site, and a balancing weight is obtained based on the number of empty tank trucks and the number of loaded tank trucks, where the balancing weight = number of empty tank trucks / (number of empty tank trucks + number of loaded tank trucks). Figure 2 As shown, a balancing weight is obtained based on the number of empty tank cars and the number of loaded tank cars. If the balancing weight is less than or equal to a preset value, the number of empty tank cars under each tap is configured according to Mode 1; if it is greater than the preset value, the number of empty tank cars under each tap is configured according to Mode 2. The number of empty tank cars under the tap in Mode 2 is greater than the number of empty tank cars under the tap in Mode 1. The preset value can be a preset threshold with a range, having a maximum and a minimum value.
[0057] Specifically, if the balance weight is less than the minimum value of the preset threshold, it indicates a severe shortage of available empty ladle cars on site, which will be unable to meet the demand for continuous molten iron tapping and poses a risk of production interruption. The system should immediately trigger an emergency command to replenish empty ladle cars, allocating them from the spare train or parking area to the designated location to ensure that there are ladles available for subsequent molten iron tapping. To ensure a sufficient number of empty ladle cars on site, the required number of empty ladle cars needs to be allocated according to Mode 1.
[0058] If the balance weight is greater than or equal to the minimum of the preset threshold and less than or equal to the maximum of the preset threshold, this indicates that the tank car resources are in a relatively balanced and controllable state. The system performs fine-grained configuration according to Mode 1. This mode typically calculates and allocates the most reasonable number of empty tank cars to each tapping station based on the expected iron output, iron output rhythm, and priority, with the goal of achieving balanced utilization of resources and smooth processes among the tapping stations.
[0059] For example, Mode 1 is: Blast Furnace #1 has two tapholes. and At the iron mouth When it is in the open state, the iron tap The configuration below is 2+1, that is, iron mouth. The first receiving line is equipped with two empty tank cars, and the second receiving line is equipped with one empty tank car. It is in the pre-opening state, at this time the iron tap The configuration below is 2+1, that is, iron mouth. The first receiving line is equipped with two empty tank cars, and the second receiving line is equipped with one empty tank car.
[0060] When blast furnace #2 is blocked, the configuration is 1+1, that is, each receiving line under each tap is equipped with one empty tank car.
[0061] When blast furnace #3 is at rest, the configuration is 1+1, meaning that the first iron receiving line under the taphole is equipped with one empty tank car, while the second iron receiving line is not equipped with an empty tank car.
[0062] If the balance weight is greater than the maximum value of the preset threshold, it means that there are enough empty tank cars on the field, and the number of empty tank cars corresponding to each iron port can be configured according to mode two.
[0063] For example, Mode 2 is: Blast Furnace #1 has two tapholes. and At the iron mouth When it is in the open state, the iron tap The configuration below is 3+2, that is, iron tap. The first receiving line was equipped with 3 empty tank cars, and the second receiving line was equipped with 2 empty tank cars. It is in the pre-opening state, at this time the iron tap The configuration below is 2+2, that is, iron tap. The first receiving line is equipped with two empty tank cars, and the second receiving line is equipped with two empty tank cars. When the taphole is not open, Mode 1 and Mode 2 are the same.
[0064] For example, a steel plant currently has two blast furnaces and one steelmaking furnace. Each blast furnace has two tapholes, and there are 20 molten iron ladles in operation. The main ladle distribution model for the open taphole is 2+2 (two ladles on each of the two lines below the taphole). Under normal circumstances, four heavy ladles are used for pouring iron in the steelmaking plant, and eight ladles are waiting to receive iron under the blast furnace. Once two ladles are full, they are transported to the steelmaking plant by locomotive. When the steelmaking plant is under maintenance or the blast furnace tapping speed is increased, the consumption of molten iron on the site is relatively slower, leading to a backlog of heavy ladles and a shortage of empty ladle cars. At this time, the system calculates that the proportion of heavy ladles on the site is too high, and the number of empty ladle cars available for blast furnace ladle distribution is too small. It automatically switches the blast furnace ladle distribution model to 2+1, that is, two ladles are distributed on one line below the open taphole, and only one ladle is distributed on the other line, reducing the number of ladle distribution under the open taphole and adapting to the situation of heavy ladle backlog on the site.
[0065] When the rate at which the steel plant consumes molten iron exceeds the rate at which the blast furnace taps iron, there will be a shortage of molten iron on the site, resulting in an excess of empty ladle cars. In this case, the system automatically calculates that the proportion of empty ladle cars on site is too high. Based on the pre-configured mode, it automatically switches the ladle allocation mode of the blast furnace to 3+2, that is, one line under the open taphole is allocated 3 ladle cars, and the other line is allocated 2 ladle cars, increasing the number of ladle cars allocated under the open taphole to adapt to the situation of excess empty ladle cars on the site.
[0066] On the other hand, the present invention also provides a blast furnace ladle matching device, the core of which is to upgrade the traditional ladle car scheduling mode that relies on manual experience into a data-driven automated and intelligent dynamic optimization process through closed-loop collaboration of four major links: data modeling, real-time monitoring, intelligent decision-making and precise matching, thereby significantly improving the efficiency and safety of molten iron transportation.
[0067] The blast furnace pot filling device adopts the above-mentioned blast furnace pot filling method, and the device includes: The modeling module is used to establish a hot metal task scoring model and a ladle car cost model based on the hot metal temperature and the time from the taphole at the bottom of the blast furnace to the target plant area.
[0068] The molten iron task scoring model comprehensively considers the temperature drop and fluidity of molten iron in the ladle, as well as the estimated time required for it to flow from the blast furnace taphole to the target plant. By quantitatively analyzing these two key process parameters, the model can calculate the urgency and technological value of each batch of molten iron tasks, providing a scientific basis for task prioritization.
[0069] The tank car matching cost model is used to evaluate the cost of assigning a specific tank car to a specific task. Its calculation factors typically include: the distance between the tank car's current location and the target taphole (empty run cost), the availability and health of the tank car itself (such as the degree of lining erosion), the current molten iron level (for heavy tank follow-up operations), and the degree of compliance with process requirements (such as the need to use a special tank car for a specific steel grade).
[0070] The monitoring module is used to monitor the status of each tapping hole under the blast furnace and the information of each ladle car.
[0071] The system acquires the real-time status of each tapping spout, including key information such as whether the spout is in the opening stage, before opening, blocked, or at rest. It also tracks the precise location, load status, and tank temperature of each tank car in real time.
[0072] The first confirmation module is used to obtain a score for each molten iron task based on the task scoring model, and then confirm the task priority. It receives the molten iron task scores from the modeling module, combines them with upstream production plans (such as the molten iron demand plan of the steelmaking unit), and uses a sorting algorithm (such as priority-based queue management) to dynamically confirm and output the processing priority sequence of all currently pending molten iron tasks. High-priority tasks typically refer to tasks where the molten iron temperature drops rapidly or where the docking process is urgently needed.
[0073] The second determining module is used to obtain the matching cost for each tank car based on the cost model. Based on the tank car matching cost model and the real-time tank car information provided by the monitoring module, the real-time matching cost for each available tank car serving each molten iron task to be assigned is calculated, forming a dynamic cost matrix.
[0074] The matching module is used to match the location of the ladle car and the tapping hole with the corresponding task based on the task priority and matching cost, so as to complete the ladle matching for the target blast furnace.
[0075] The matching module receives the task priority sequence from the first module and the tank car-task cost matrix from the second module, and uses an optimization algorithm to perform a globally optimal or near-optimal matching. Its ultimate goal is to schedule the tank car in the most suitable state to the correct tap at the right time to undertake the correct molten iron task, and generate detailed scheduling instructions (such as tank car travel route and placement time window) and issue them to the locomotive or unmanned transportation system for execution.
[0076] The blast furnace ladle distribution device provided by this invention overcomes the limitations of manual scheduling with its localized perspective, optimizing resource utilization from a plant-wide viewpoint. Through precise prediction and proactive allocation, it fundamentally reduces the risk of production accidents caused by empty ladles not being in place. It prioritizes the rapid loading and unloading of high-temperature molten iron into the ladle, reducing heat loss and saving energy. Scientific task allocation balances the load on ladle cars, extending ladle life, reducing waiting time, and improving the utilization rate of empty ladle cars.
[0077] On the other hand, the present invention also provides an electronic device, including: a processor, a memory, and a communication bus; the communication bus is used to connect the processor and the memory; the processor is used to execute a computer program stored in the memory to implement the blast furnace batching method as described above.
[0078] On the other hand, the present invention also provides a computer-readable storage medium having a computer program stored thereon, the computer program being used to cause a computer to perform the blast furnace batching method as described above.
[0079] The above embodiments are merely illustrative of the principles and effects of the present invention and are not intended to limit the invention. Any person skilled in the art can modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by those skilled in the art without departing from the spirit and technical concept disclosed in the present invention should still be covered by the claims of the present invention.
Claims
1. A method for preparing blast furnace ladle filling, characterized in that, The method includes: A hot metal task scoring model is established based on the temperature of the molten iron and the time from the taphole to the target plant area. The score for each molten iron task is obtained based on the task scoring model, and then the task priority is determined. Establish a cost model for ladle cars, monitor the status of each tapping hole under the blast furnace and the information of each ladle car, obtain the molten iron task of the target plant area, and obtain the matching cost of each ladle car based on the cost model; Based on task priority and matching cost, the locations of ladle cars and tapping points are matched one-to-one with the corresponding tasks to complete the ladle matching for the target blast furnace.
2. The blast furnace ladle feeding method according to claim 1, characterized in that, The process of obtaining a score for each molten iron task based on the task scoring model and then determining the task priority includes: calculating the score of the molten iron task according to the following formula. , , in, and It is a constant. This is the highest temperature of molten iron inside the blast furnace. This refers to the current temperature of the molten iron inside the blast furnace. The minimum required temperature for molten iron in the target plant area. The latest time for molten iron to be delivered to the target plant area. For the current time, This is the maximum allowable delay time.
3. The blast furnace ladle preparation method according to claim 2, characterized in that, When there are multiple molten iron missions This represents the maximum allowed delay time among multiple tasks.
4. The blast furnace batching method according to claim 1, characterized in that, The process involves establishing a cost model for ladle cars, monitoring the status of each tapping hole under the blast furnace and the information of each ladle car, obtaining the target plant's molten iron demand, and calculating the matching cost for each ladle car based on the cost model. This includes obtaining the matching cost according to the following formula. , , in, , and It is a constant; Indicates the current tanker truck Distance from the taphole The distance; Indicates tanker truck The waiting time from the current time until a new task becomes available.
5. The blast furnace ladle feeding method according to claim 1, characterized in that: The process of matching the location of the ladle car and the tapping hole with the corresponding task based on task priority and matching cost to complete the ladle matching for the target blast furnace also includes: comparing the arrival time of the ladle car with the task time to determine whether the arrival of the ladle car is on time, early, or late; then calculating the scheduling performance reward and feeding it back to the cost model of the ladle car to optimize the cost model of the ladle car.
6. The blast furnace ladle preparation method according to claim 1, characterized in that, The state of the iron outlet includes open and closed, and a corresponding number of empty tank cars are matched for each iron outlet according to its state.
7. The blast furnace ladle feeding method according to claim 6, characterized in that: The number of empty tank trucks and loaded tank trucks at the collection site is collected, and a balancing weight is obtained based on the number of empty tank trucks and loaded tank trucks. If the balancing weight is less than or equal to a preset value, the number of empty tank trucks under each iron tap is configured according to Mode 1; if it is greater than the preset value, the number of empty tank trucks under each iron tap is configured according to Mode 2. The number of empty tank trucks under the iron tap in the opening of Mode 2 is greater than the number of empty tank trucks under the iron tap in the opening of Mode 1.
8. A blast furnace ladle feeding device, characterized in that, The blast furnace batching device adopts the blast furnace batching method according to any one of claims 1-7, and the device includes: The modeling module is used to establish a hot metal task scoring model and a ladle car cost model based on the hot metal temperature and the time from the taphole under the blast furnace to the target plant area. The monitoring module is used to monitor the status of each tapping hole under the blast furnace and the information of each ladle car; The first confirmation module is used to obtain a score for each molten iron task based on the task scoring model, and then confirm the task priority. The second determining module is used to obtain the matching cost for each tanker truck based on the cost model; The matching module is used to match the location of the ladle car and the tapping hole with the corresponding task based on the task priority and matching cost, so as to complete the ladle matching for the target blast furnace.
9. An electronic device, characterized in that, include: A processor, a memory, and a communication bus; the communication bus is used to connect the processor and the memory; The processor is used to execute the computer program stored in the memory to implement the blast furnace batching method as described in any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that, It stores a computer program that enables the computer to perform the blast furnace batching method as described in any one of claims 1 to 7.