A modular cruise ship construction project scheduling optimization method

By constructing a multi-stage fuzzy multi-objective resource-constrained project scheduling model and a strategy group evolution algorithm, a feasible scheduling scheme suitable for modular cruise ship construction is generated, which solves the problems of high cost and complex scheduling in modular cruise ship construction, and achieves shortened construction period and cost control.

CN123140533APending Publication Date: 2026-11-20HARBIN ENGINEERING UNIVERSITY SANYA NANHAI INNOVATION & DEVELOPMENT BASE +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611367877.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-04
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Existing methods for scheduling modular cruise ship construction projects cannot effectively address the issues of high production costs, transportation costs, low manufacturing rates, and high scheduling complexity. Furthermore, existing methods are not applicable to the specific scenarios of modular cruise ship construction.

Method used

A multi-stage fuzzy, multi-objective, resource-constrained project scheduling model is constructed. Combined with the policy group evolution algorithm, feasible scheduling schemes are generated using priority rule policy groups. The solution is updated and the final scheduling scheme is generated through non-dominated sorting and congestion distance evaluation.

Benefits of technology

This has improved the scheduling flexibility, shortened the construction period, and controlled costs of modular cruise ship construction projects, thus meeting the actual needs of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123140533A_ABST
    Figure CN123140533A_ABST
Patent Text Reader

Abstract

The application discloses a kind of modularization cruise ship construction project scheduling optimization methods, belong to cruise ship construction technical field, including: constructing the multi-stage coupling modularization cruise ship construction project scheduling optimization mathematical model, constructs double-layer vector, obtains candidate scheduling scheme by inputting double-layer vector into the multi-stage coupling modularization cruise ship construction project scheduling optimization mathematical model, while calculating the objective function value of each candidate scheduling scheme, with the objective function value of each candidate scheduling scheme as basis, using non-dominated sorting and crowded distance estimation scheme advantage and disadvantage, update external set and save non-dominated solution, obtain feasible scheduling scheme, with feasible scheduling scheme as parent basis, using the evolution strategy of selection, crossover and mutation to obtain offspring scheme, repeat execution, when meeting algorithm termination condition, obtain final scheduling scheme.The application improves the scheduling flexibility in cruise ship construction, shortens the project completion period and has important significance for project cost control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention applies to the field of cruise ship construction technology and relates to a modular cruise ship construction project scheduling method that couples multiple stages and flexibly applies various scheduling strategies. Background Technology

[0002] Cruise ship construction differs from conventional shipbuilding, being subject to strict delivery dates and extensive construction activities. Modular shipbuilding technology, a core technology in modern cruise ship manufacturing, significantly improves efficiency and controllability by breaking down complex ship structures into standardized prefabricated functional modules. Compared to traditional construction methods, modular shipbuilding allows for the parallel advancement of production, transportation, and assembly, shortening assembly time and reducing uncontrollable factors in on-site construction. However, modular cruise ship construction projects also present numerous challenges. High production costs, high transportation costs, low manufacturing rates, and additional resource requirements increase the total project cost. Furthermore, the strong coupling between modular production and assembly leads to an exponential increase in scheduling complexity, requiring coordination of supply chain logistics, hoisting resources, site constraints, and other multiple constraints. Planning and scheduling modular cruise ship construction projects according to quality, time, and resource requirements and constraints can shorten project duration, reduce costs, and improve product quality, directly determining whether project objectives can be achieved on time and effectively. Therefore, researching scheduling optimization methods for modular cruise ship construction projects is of great significance for improving scheduling flexibility, shortening project completion time, and controlling project costs in cruise ship construction.

[0003] Existing technical literature 1, “A project scheduling problem with spatial resource constraints and a corresponding guided local search algorithm”, Hu et al., Journal of the Operational Research Society, 2019, 70(8), 1349–1361, considers the characteristics of the segmented assembly process in shipyards and proposes a project scheduling problem with spatial resource constraints (2D-RCPSP). It also proposes a complex guided local search algorithm (GLS) to solve the problem. However, this method focuses on the constraints of the two-dimensional characteristics of spatial resources and does not consider the uncertainties in the cruise ship construction process. It is not suitable for the scheduling of modular cruise ship construction projects. Reference 2, "Multi-objective multi-mode resource-constrained project scheduling with fuzzy activity durations in prefabricated building construction," Yuan et al., Computers & Industrial Engineering, 2021, 158, 107316, uses triangular fuzzy numbers to describe the fuzziness of activity durations in resource-constrained project scheduling problems. It establishes a multi-objective fuzzy RCPSP model and designs a hybrid co-evolutionary algorithm (HCOEA) for solving it. However, this method is designed for prefabricated building (PB) construction projects, and its model constraints cannot be applied to the field of cruise ship construction. Therefore, further research is needed on scheduling optimization methods that can be directly applied to modular cruise ship construction projects. Summary of the Invention

[0004] The purpose of this invention is to overcome the shortcomings of existing technologies and to propose a scheduling optimization method for modular cruise ship construction projects. This method constructs a multi-stage fuzzy, multi-objective, resource-constrained project scheduling model that conforms to the background of modular cruise ship construction. Simultaneously, a strategy group evolution algorithm is designed, utilizing a strategy group containing multiple priority rules to generate an overall feasible scheduling scheme. Non-dominated sorting and congestion distance calculations are performed, non-dominated solutions are stored, and evolution strategies of selection, crossover, and mutation are used to update the solutions. Finally, the solution set is obtained through iteration. The specific steps of the method are as follows: To achieve the above objectives, the present invention provides a modular cruise ship construction project scheduling optimization method, characterized in that the method includes the following steps: S1: Construct a multi-stage coupled modular cruise ship construction project scheduling optimization mathematical model, which includes an objective function and constraints; S2: Based on the scheduling priority rules, a priority rule strategy group is constructed. A two-layer vector is constructed by combining the priority rule strategy group. The two-layer vector is input into the multi-stage coupled modular cruise ship construction project scheduling optimization mathematical model to obtain candidate scheduling schemes. At the same time, the objective function value of each candidate scheduling scheme is calculated. S3: Based on the objective function value of each candidate scheduling scheme, the merits of the candidate scheduling schemes are evaluated by non-dominated sorting and congestion distance. The high-quality candidate scheduling schemes are put into the external file set, the external file set is updated and the non-dominated solution is saved to obtain the feasible scheduling scheme. S4: Using feasible scheduling schemes as the parent generation basis, the offspring schemes are obtained by using evolution strategies of selection, crossover and mutation; S5: Repeat steps S2 to S4. When the algorithm termination condition is met, the non-dominated solution in the outer set is obtained, which is the final scheduling scheme.

[0005] Preferably, in step S1, a multi-stage coupled modular mathematical model for cruise ship construction project scheduling optimization is constructed, and the specific process is as follows: First, construct the model objective function, which includes the following: The time objective optimization function is expressed as follows:

[0006] The cost target optimization function is expressed as follows:

[0007] in, This indicates minimizing the project's maximum expected completion time. Represents the maximization function. Represents the expectation operator. Indicates the stage number. Indicates the activity number. Indicates the time point number. Indicates activity In the stage The fuzzy end time, This represents minimizing the total expected cost of the project. Indicates unit cost, activity In the stage Operating costs Indicates activity In the stage Fuzzy operation time, Represents time-based decision variables. Indicates a time period; Secondly, the model constraints are constructed, specifically including the following: Resource uniqueness constraints on the timeline are represented as follows:

[0008] in, Indicates a time period; The uniqueness constraint for resource allocation is expressed as follows:

[0009] in, Representing resource decision variables, stage Activities In resources When the order is given to be carried out, =1; otherwise 0; Indicates the total number of resources; The activity time calculation constraint is as follows:

[0010] in, Indicates activity In the stage The fuzzy start time, Indicates activity In the stage Fuzzy operation time, Indicates the total number of stages. Indicates the total number of activities; The preceding activity sequence constraint is expressed as follows:

[0011] in, Indicates activity In the stage The fuzzy end time, Indicates the current activity The preceding activity number, Indicates activity In the stage The precursor activity set in; Cross-stage timing constraints are represented as follows:

[0012] in, Representation phase Chinese activities The fuzzy end time, Representation phase The fuzzy operation time of the first activity in the middle, Represents the decision variables for activities, in stages The first activity was held on time. When assigned to perform, =1; otherwise 0. Representation phase The set of preliminary stages; Resource capacity constraints are expressed as follows:

[0013] in, Indicates non-renewable resources. R represents the maximum available quantity of non-renewable resources, and R represents the total number of resource types.

[0014] Preferably, in step S2, the two-layer vector includes a priority rule sequence and an activity order sequence, specifically represented as follows:

[0015] in, The individual's identification number. , Indicates population size, Indicates the specified vector length. This represents the sequence of priority rules used to construct the project schedule. The general form is , Indicates the location The number of the priority rule used at that location. This indicates the sequence of activities following priority rules. The common form of expression is , Indicates the location The location follows the numbering. The number of activities according to the priority rule, and satisfying the following formula:

[0016] in, This indicates the total number of activities.

[0017] Preferably, in step S2, candidate scheduling schemes are obtained, and the objective function value of each candidate scheduling scheme is calculated. The specific process is as follows: By utilizing the constraints in the mathematical model of scheduling optimization for a multi-stage coupled modular cruise ship construction project, the two-layer vector is decoded, the start and end times of each activity are arranged sequentially, and candidate scheduling schemes that satisfy all constraints are generated. The execution time and resource allocation data of each activity are extracted, substituted into the objective function, and the expected maximum completion time and expected total cost of each candidate scheduling scheme are calculated to obtain the objective function value of each candidate scheduling scheme.

[0018] Preferably, in step S3, a feasible scheduling scheme is obtained, and the specific process is as follows: The evaluation is based on the objective function value of each candidate scheduling scheme. First, the candidate scheduling schemes are non-dominated and sorted, dividing the non-dominated solution sets into different levels, and eliminating inferior solutions that are completely dominated by other schemes. Then, congestion distance is calculated for schemes within the same level to measure the distribution density of each scheme, resulting in a solution ranking from best to worst, and within the same level, from largest to smallest congestion distance. Subsequently, based on the solution ranking, high-quality candidate scheduling schemes are selected and placed into an external archive set. Non-dominated solutions with even distribution and better overall performance are retained. Finally, non-dominated scheduling solutions that meet the actual engineering needs and have a reasonable distribution are selected from the external archive set to obtain feasible scheduling schemes.

[0019] Preferably, in step S4, a feasible scheduling scheme is used as the parent generation basis, and an evolution strategy of selection, crossover, and mutation is used to obtain the offspring scheme. The specific process is as follows: Using feasible scheduling schemes as the parent candidate base, the non-dominated tournament selection method is adopted to select the optimal feasible scheduling scheme individuals from the parent candidate base to form a league set. The feasible scheduling scheme individuals with the best non-dominated level and the largest congestion distance are selected as the parent. The first and second layers of the parent's two-layer vector are subjected to normal distribution differential crossover and exchange mutation, and repaired according to the total number of activities constraint to obtain the offspring scheme.

[0020] The beneficial effects of this invention are: (1) Extracting the scheduling characteristics of modular cruise ship construction projects in actual production, a multi-stage fuzzy multi-objective resource-constrained project scheduling problem model conforming to the modular cruise ship construction scenario is constructed. A unified mathematical description of the scheduling of multi-stage coupled modular cruise ship construction projects in actual production is realized; (2) A strategy group evolution algorithm is proposed, which combines the strategy of generating feasible solutions based on priority rule strategy groups with the evolution strategy of selection, crossover and mutation, thereby improving the scheduling flexibility. Multi-objective evaluation parameters of non-dominated sorting and congestion distance are set, and an external set is designed to realize the updating and storage of non-dominated solutions, so as to obtain the final required scheduling scheme and achieve the dual advantages of schedule and cost. Attached Figure Description

[0021] Figure 1 This is a flowchart of a modular cruise ship construction project scheduling optimization method according to the present invention.

[0022] Figure 2 This is a diagram illustrating the scheduling scheme of a modular cruise ship construction project scheduling optimization method according to the present invention. Detailed Implementation

[0023] The technical solutions of the present invention will be clearly and completely described below with reference to the embodiments and accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0024] like Figure 1 As shown, the present invention proposes a modular cruise ship construction project scheduling optimization method, which includes the following steps: S1: Construct a multi-stage coupled modular cruise ship construction project scheduling optimization mathematical model, which includes an objective function and constraints; The mathematical model for scheduling optimization in a multi-stage coupled modular cruise ship construction project consists of two parts: an objective function and constraints. First, construct the model objective function, which includes the following: The time objective optimization function is expressed as follows:

[0025] The cost target optimization function is expressed as follows:

[0026] in, This indicates minimizing the project's maximum expected completion time. Represents the maximization function. Represents the expectation operator. Indicates the stage number. Indicates the activity number. Indicates the time point number. Indicates activity In the stage The fuzzy end time, This represents minimizing the total expected cost of the project. Indicates unit cost, activity In the stage Operating costs Indicates activity In the stage Fuzzy operation time, Represents time-based decision variables. Indicates a time period; Secondly, the model constraints are constructed, specifically including the following: Resource uniqueness constraints on the timeline are represented as follows:

[0027] in, Indicates a time period; The uniqueness constraint for resource allocation is expressed as follows:

[0028] in, Represents resource decision variables, stage Activities In resources When the order is given to be carried out, =1; otherwise 0; Indicates the total number of resources; The activity time calculation constraint is expressed as follows:

[0029] in, Indicates activity In the stage The fuzzy start time, Indicates activity In the stage Fuzzy operation time, Indicates the total number of stages. Indicates the total number of activities; The preceding activity sequence constraint is expressed as follows:

[0030] in, Indicates activity In the stage The fuzzy end time, Indicates the current activity The preceding activity number, Indicates activity In the stage The precursor activity set in; Cross-stage timing constraints are represented as follows:

[0031] in, Representation phase Chinese activities The fuzzy end time, Representation phase The fuzzy operation time of the first activity in the middle, Represents the decision variables for activities, in stages The first activity was held on time. When assigned to perform, =1; otherwise 0. Representation phase The set of preliminary stages; Resource capacity constraints are expressed as follows:

[0032] in, Indicates non-renewable resources. R represents the maximum available quantity of non-renewable resources, and R represents the total number of resource types.

[0033] For the relevant fuzzy time parameters in the model, including activities In the stage Fuzzy end time ,Activity In the stage Fuzzy operation time and activities In the stage Fuzzy start time Using triangular fuzzy numbers for representation, in order to activate In the stage Fuzzy operation time For example, the representation method is as follows:

[0034] in, Represents about variables The membership function, the variable here Indicates the operation time. Each represents a stage Chinese activities The shortest, most likely, and longest operation time.

[0035] S2: Based on the scheduling priority rules, a priority rule strategy group is constructed. A two-layer vector is constructed by combining the priority rule strategy group. The two-layer vector is input into the multi-stage coupled modular cruise ship construction project scheduling optimization mathematical model to obtain candidate scheduling schemes. At the same time, the objective function value of each candidate scheduling scheme is calculated. 1. Constructing vectors : ① Construct a priority rule set This includes all the priority rules required for scheduling:

[0036] in, The number representing the priority rule is set in total. Each distinct priority rule constitutes a priority rule set. ; ②For individuals ,initialization If the sequence is empty, clear the tabu list. ; ③Regarding location From the set of rules Randomly select 1 item that is not on the taboo list Rules in insert Location Location:

[0037] Add it to the taboo list To ensure that subsequent positions do not repeatedly select the same rule, among which, , Indicates the specified vector length; ④ When The number of elements in the data reaches , representing an individual corresponding Generation complete.

[0038] Constructing vectors : ①Regarding location Randomly generate one integer. ,in , For custom upper limits, the value should not be too large. , To represent the specified vector length, the following formula must be satisfied:

[0039] in, This indicates the total number of activities.

[0040] ② Repeat the above steps to generate the initial... Then calculate the difference between the current total number of activities and the total number of activities. :

[0041] in, Indicates the total number of activities, if Then from Random selection Each of the elements is incremented by 1. Then from Random selection Each of the elements is subtracted by 1. If so, no adjustment is needed; ③ Repeat the above steps until... ,generate .

[0042] Next, repeat the above steps for each individual to finally generate the corresponding [database name] for each individual. and Additionally, the taboo table is reset after each individual is generated. and rule set .

[0043] according to The vectors are applied sequentially according to the priority rules, each rule... according to vector The process of allocating the number of activities and generating a scheduling plan needs to be carried out under the constraints of the model. Then, based on the objective function, the expected maximum completion time of the project and the total expected cost of the project are calculated.

[0044] S3: Based on the objective function value of each candidate scheduling scheme, the merits of the candidate scheduling schemes are evaluated by non-dominated sorting and congestion distance. The high-quality candidate scheduling schemes are put into the external file set, the external file set is updated and the non-dominated solution is saved to obtain the feasible scheduling scheme. The population solutions are classified according to their dominance relationship using non-dominated sorting. Then, the degree of dispersion of solutions of the same level is measured by calculating the crowding distance. The solutions are sorted from best to worst in terms of level, and from largest to smallest in terms of crowding distance in terms of level. The process of updating the outer collection is as follows: ① Initialize the outer collection Collect the non-dominated solutions in the current population. After sorting in the previous step, select the non-dominated solutions with a level of 1 and add them all to the outer set. ; ② Remove solutions from the set that are dominated by other solutions. All individuals are then subjected to a non-dominated sort, retaining only solutions of level 1. The number of solutions in this case is denoted as . ; ③Based on the maximum capacity of the outer set Determine if the current set exceeds the maximum capacity. This indicates that the capacity has not been exceeded. This indicates that the capacity is exceeded and filtering is required. The filtering strategy is to prioritize solutions with larger crowding distances among non-dominated solutions of the same level, and then select the top solutions after sorting. The solutions form a new set. .

[0045] S4: Using feasible scheduling schemes as the parent generation basis, the offspring schemes are obtained by using evolution strategies of selection, crossover and mutation; S5: Repeat steps S2 to S4. When the algorithm termination condition is met, the non-dominated solution in the outer set is obtained, which is the final scheduling scheme.

[0046] A dataset was constructed based on the actual scheduling environment of a cruise ship construction project, and the algorithm of this invention was applied to solve it. The algorithm parameters are as follows: Population size Crossover probability Probability of mutation Maximum number of iterations ; The selection process uses a "random tournament" method, as detailed below: ① Random selection from the parent population Individual solutions form the "League Group" "in, For the scale of a tournament; ②Regular assembly Sort the solutions in the set using non-dominated sorting and select the set. The solution with the highest dominance level enters the offspring population. If there are multiple individuals of the same dominance level, the individual with the largest crowding distance is selected. ③ Repeat the above steps until the offspring population size is [missing information]. .

[0047] The offspring are generated using a scaling factor-based crossover operation, as detailed below: ① First, generate the scaling factor. and follows a normal distribution. value range ; ②For vectors and Perform cross-processing:

[0048] in, and Representing two different parent generations, Indicates the newly generated offspring; ③ Convert the real numbers in the vector to integers:

[0049] in, This indicates the total number of priority rules. Indicates the total number of activities; ④ Repair Vector Converting real numbers in a vector to integers may violate the formula. Therefore, based on Perform the calculation, if Random selection Add 1 to each element; if Random selection Each of the elements is subtracted by 1. If so, no adjustment is needed.

[0050] The mutation operation is performed using the exchange mutation operator. First, the mutated object is randomly selected, and then... and Two positions in a vector and By swapping the genes at these two positions, a new vector is obtained, where... Next, check the vector. If the constraint is not within the range, then repair is performed, and then the process jumps to step S2 for iteration.

[0051] like Figure 2 As shown, the execution order of tasks for different cabins can be obtained, and it can be seen that the scheduling schemes all meet the total resource constraints. The non-dominated solution in the external set, i.e., the final scheduling scheme, has a time of 1 unit (32, 68, 75) and a cost of 121940.

[0052] Although preferred embodiments of this application have been described, those skilled in the art, once they learn the basic inventive concept, can make other changes and modifications to these embodiments. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments as well as all changes and modifications falling within the scope of this application. Obviously, those skilled in the art can make various modifications and variations to this application without departing from the spirit and scope of this application. Therefore, if these modifications and variations of this application fall within the scope of the claims of this application and their equivalents, this application also intends to include these modifications and variations.

Claims

1. A method for optimizing the scheduling of modular cruise ship construction projects, characterized in that, include: S1: Construct a multi-stage coupled modular cruise ship construction project scheduling optimization mathematical model, which includes an objective function and constraints; S2: Based on the scheduling priority rules, a priority rule strategy group is constructed. A two-layer vector is constructed by combining the priority rule strategy group. The two-layer vector is input into the multi-stage coupled modular cruise ship construction project scheduling optimization mathematical model to obtain candidate scheduling schemes. At the same time, the objective function value of each candidate scheduling scheme is calculated. S3: Based on the objective function value of each candidate scheduling scheme, the merits of the candidate scheduling schemes are evaluated by non-dominated sorting and congestion distance. The high-quality candidate scheduling schemes are put into the external file set, the external file set is updated and the non-dominated solution is saved to obtain the feasible scheduling scheme. S4: Using feasible scheduling schemes as the parent generation basis, the offspring schemes are obtained by using evolution strategies of selection, crossover and mutation; S5: Repeat steps S2 to S4. When the algorithm termination condition is met, the non-dominated solution in the outer set is obtained, which is the final scheduling scheme.

2. The modular cruise ship construction project scheduling optimization method according to claim 1, characterized in that, In step S1, a multi-stage coupled modular mathematical model for cruise ship construction project scheduling optimization is constructed. The specific process is as follows: First, construct the model objective function, which includes the following: The time objective optimization function is expressed as follows: , The cost target optimization function is expressed as follows: , in, This indicates minimizing the project's maximum expected completion time. Represents the maximization function. Represents the expectation operator. Indicates the stage number. Indicates the activity number. Indicates the time point number. Indicates activity In the stage The fuzzy end time, This represents minimizing the total expected cost of the project. Indicates unit cost, activity In the stage Operating costs, Indicates activity In the stage Fuzzy operation time, Represents time-based decision variables. Indicates a time period; Secondly, the model constraints are constructed, specifically including the following: Resource uniqueness constraints on the timeline are represented as follows: , in, Indicates a time period; The uniqueness constraint for resource allocation is expressed as follows: , in, Representing resource decision variables, stage Activities In resources When the order is given to be carried out, Otherwise, it is 0; Indicates the total number of resources; The activity time calculation constraint is as follows: , in, Indicates activity In the stage The fuzzy start time, Indicates activity In the stage Fuzzy operation time, Indicates the total number of stages. Indicates the total number of activities; The preceding activity sequence constraint is expressed as follows: , in, Indicates activity In the stage The fuzzy end time, Indicates the current activity The preceding activity number, Indicates activity In the stage The precursor activity set in; Cross-stage timing constraints are represented as follows: , in, Representation phase Chinese activities The fuzzy end time, Representation phase The fuzzy operation time of the first activity in the middle, Represents the decision variables for activities, in stages The first activity was held on time. When assigned to perform, =1; otherwise 0. Representation phase The set of preliminary stages; Resource capacity constraints are expressed as follows: , in, Indicates non-renewable resources. R represents the maximum available quantity of non-renewable resources, and R represents the total number of resource types.

3. The modular cruise ship construction project scheduling optimization method according to claim 1, characterized in that, In step S2, the two-layer vector includes a priority rule sequence and an activity order sequence, specifically represented as follows: , , in, The individual's identification number. , Indicates population size, Indicates the specified vector length. This represents the sequence of priority rules used to construct the project schedule. The general form is , Indicates the location The number of the priority rule used at that location. This indicates the sequence of activities following priority rules. The common form of expression is , Indicates the location The location follows the numbering. The number of activities according to the priority rule, and satisfying the following formula: , in, This indicates the total number of activities.

4. The modular cruise ship construction project scheduling optimization method according to claim 1, characterized in that, In step S2, candidate scheduling schemes are obtained, and the objective function value of each candidate scheduling scheme is calculated. The specific process is as follows: By utilizing the constraints in the mathematical model of scheduling optimization for a multi-stage coupled modular cruise ship construction project, the two-layer vector is decoded, the start and end times of each activity are arranged sequentially, and candidate scheduling schemes that satisfy all constraints are generated. The execution time and resource allocation data of each activity are extracted, substituted into the objective function, and the expected maximum completion time and expected total cost of each candidate scheduling scheme are calculated to obtain the objective function value of each candidate scheduling scheme.

5. The modular cruise ship construction project scheduling optimization method according to claim 1, characterized in that, In step S3, a feasible scheduling scheme is obtained, and the specific process is as follows: The evaluation is based on the objective function value of each candidate scheduling scheme. First, the candidate scheduling schemes are non-dominated and sorted, dividing the non-dominated solution sets into different levels, and eliminating inferior solutions that are completely dominated by other schemes. Then, congestion distance is calculated for schemes within the same level to measure the distribution density of each scheme, resulting in a solution ranking from best to worst, and within the same level, from largest to smallest congestion distance. Subsequently, based on the solution ranking, high-quality candidate scheduling schemes are selected and placed into an external archive set. Non-dominated solutions with even distribution and better overall performance are retained. Finally, non-dominated scheduling solutions that meet the actual engineering needs and have a reasonable distribution are selected from the external archive set to obtain feasible scheduling schemes.

6. The modular cruise ship construction project scheduling optimization method according to claim 1, characterized in that, In step S4, a feasible scheduling scheme is used as the parent generation basis, and the offspring scheme is obtained by using the evolution strategy of selection, crossover, and mutation. The specific process is as follows: Using feasible scheduling schemes as the parent candidate base, the non-dominated tournament selection method is adopted to select the optimal feasible scheduling scheme individuals from the parent candidate base to form a league set. The feasible scheduling scheme individuals with the best non-dominated level and the largest congestion distance are selected as the parent. The first and second layers of the parent's two-layer vector are subjected to normal distribution differential crossover and exchange mutation, and repaired according to the total number of activities constraint to obtain the offspring scheme.