A cost warning method, device and medium for an offshore wind power transmission project

By breaking down offshore wind power transmission projects into multiple cost component units, analyzing environmental factors and market risks, and dynamically adjusting cost benchmarks and early warning levels, the problem of cost estimation deviating from reality in traditional methods has been solved, achieving more scientific cost management.

CN123140664APending Publication Date: 2026-11-20STATE GRID FUJIAN POWER ELECTRIC CO ECONOMIC RESEARCH INSTITUTE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611452464.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-18
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

Traditional cost forecasting methods are unable to dynamically reflect real-time changes in environmental factors and fluctuations in market material prices, leading to deviations in the cost estimates of offshore wind power transmission projects from reality and affecting the scientific nature of project decision-making.

Method used

The offshore wind power transmission project is broken down into multiple cost component units. The impact of environmental factors and market risks on each component unit is analyzed, and the impact coefficient and cost disturbance coefficient are constructed. Combined with the engineering quantity correction rate and market risk index, the cost benchmark and early warning level are dynamically adjusted.

Benefits of technology

It improves the scientific rigor and environmental adaptability of cost forecasting, reduces estimation bias, and enhances the reliability of project decisions.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The present application relates to a kind of offshore wind power transmission project cost early warning method, equipment and medium, belong to engineering management technical field, comprising the following steps: offshore wind power transmission project is split into multiple cost components unit and extracts engineering cost characteristics, obtain cost benchmark according to this;Analysis environmental factor on the influence coefficient of each unit;Build market risk index and each unit cost disturbance coefficient;From influence coefficient, determine engineering quantity correction rate and engineering correction coefficient;Combined with engineering correction coefficient, cost disturbance coefficient and cost benchmark, calculate cost deviation rate;According to cost deviation rate, market risk index and engineering quantity correction rate, determine cost early warning grade.The present application extracts features according to unit, based on historical sample similarity fusion data, determines benchmark engineering quantity, unit price and measure fee, fully considers unit difference, makes cost benchmark close to actual, avoids uniform standard deviation, provides reliable reference for cost deviation analysis, improves the scientific nature of cost estimation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to a cost early warning method, equipment, and medium for offshore wind power transmission projects, belonging to the field of engineering management technology. Background Technology

[0002] In recent years, as the global energy structure has accelerated its transformation towards cleaner and lower-carbon energy, offshore wind power, as an important component of renewable energy, has entered a stage of large-scale and industrialized development. my country's installed capacity of offshore wind power has continued to grow, and transmission projects, as a crucial link connecting offshore wind farms to onshore power grids, account for a significant proportion of the total investment in offshore wind power projects.

[0003] Offshore wind power transmission projects face significant uncertainty and complexity in cost management due to their unique construction environment, substantial constraints from marine hydrological and meteorological conditions, and frequent fluctuations in material and equipment prices. Traditional cost forecasting and control methods often rely on static historical quotas or simple experience corrections, which fail to dynamically reflect the nonlinear disturbances of real-time environmental factors on project quantities or effectively quantify the impact of market material price fluctuations on costs. This results in estimates deviating from reality and delayed cost risk warnings, severely restricting the scientific nature of project decision-making. Summary of the Invention

[0004] To address the problems existing in the prior art, this invention proposes a cost early warning method, equipment, and medium for offshore wind power transmission projects.

[0005] The technical solution of the present invention is as follows: On the one hand, this invention provides a method for cost early warning of offshore wind power transmission projects, including the following steps: The offshore wind power transmission project is divided into at least two cost component units, and the project cost characteristics of each cost component unit are obtained. The cost benchmark for offshore wind power transmission projects is obtained based on the engineering cost characteristics of each cost component unit. The impact of environmental factors on various cost components of offshore wind power transmission projects was analyzed, and the impact coefficients of environmental factors on each cost component were obtained. Construct a market risk index and cost disturbance coefficient for each cost component unit of offshore wind power transmission projects; Based on the aforementioned influence coefficients, the engineering quantity correction rate and the engineering correction coefficient for each cost component unit of the offshore wind power transmission project are determined. The cost deviation rate of offshore wind power transmission projects is determined based on engineering correction coefficients, cost disturbance coefficients, and cost benchmarks. The cost early warning level of offshore wind power transmission projects is determined based on the cost deviation rate, market risk index, and engineering quantity correction rate.

[0006] Preferably, the cost benchmark for offshore wind power transmission projects is obtained based on the engineering cost characteristics of each cost component unit. The specific steps are as follows: Based on the aforementioned engineering cost characteristics, calculate the similarity weight coefficient between each cost component unit of the offshore wind power transmission project and each cost component unit of the historical samples; Based on the similarity weighting coefficient, the engineering quantity, unit price, and measure fee of each historical sample are integrated to obtain the benchmark engineering quantity, benchmark unit price, and benchmark measure fee of each cost component unit of the offshore wind power transmission project. The cost benchmark for offshore wind power transmission projects is obtained based on the benchmark engineering quantity, benchmark unit price, and benchmark invoice cost.

[0007] Preferably, the analysis of the impact of environmental factors on various cost components of offshore wind power transmission projects involves the following steps: Environmental factors are normalized to represent the intensity of environmental disturbance. The influence coefficients of environmental factors on each cost component unit are constructed based on the water depth, distance from the shore, and intensity of environmental disturbance.

[0008] Preferably, the market risk index and cost disturbance coefficient of each cost component unit for offshore wind power transmission projects are constructed, and the specific steps are as follows: Obtain the relative price volatility of various materials; The cost disturbance coefficients of each cost component unit of the offshore wind power transmission project are determined based on the relative price volatility. The average cost disturbance coefficient is used as the market risk index for offshore wind power transmission projects.

[0009] Preferably, the engineering quantity correction rate and the engineering correction coefficient of each cost component unit of the offshore wind power transmission project are determined based on the influence coefficient. The specific steps are as follows: Based on the aforementioned influence coefficient and the baseline engineering quantity of each cost component unit, the engineering correction coefficient of each cost component unit is obtained; The quantity correction rate for offshore wind power transmission projects is determined based on the engineering correction coefficients and benchmark unit prices of each cost component unit.

[0010] Preferably, the cost deviation rate of offshore wind power transmission projects is determined based on engineering correction factors, cost disturbance factors, and cost benchmarks. The specific steps are as follows: The comprehensive unit price is determined based on the aforementioned cost disturbance coefficient and benchmark unit price; The coupling coordination cost of offshore wind power transmission projects is obtained based on engineering correction factors. The comprehensive cost of offshore wind power transmission projects is obtained based on the comprehensive unit price and coupling coordination costs. The cost deviation rate of offshore wind power transmission projects is determined based on cost benchmarks and comprehensive costs.

[0011] Preferably, the cost early warning level of the offshore wind power transmission project is determined based on the cost deviation rate, market risk index, and engineering quantity correction rate. The specific steps are as follows: The posterior probability distribution of cost risk level is obtained based on market risk index and engineering quantity correction rate. The cost warning level of offshore wind power transmission projects is obtained based on the posterior probability distribution and cost deviation rate.

[0012] In another aspect, the present invention also provides an electronic device having a computer program stored thereon, wherein when the computer program is executed by a processor, it implements the cost early warning method for offshore wind power transmission projects as described in any embodiment of the present invention.

[0013] In another aspect, the present invention also provides a computer-readable storage medium for storing one or more programs, which, when executed by one or more processors, cause the one or more processors to implement the cost early warning method for offshore wind power transmission projects as described in any embodiment of the present invention.

[0014] The present invention has the following beneficial effects: 1. This invention breaks down offshore wind power transmission projects into multiple cost component units, extracts the cost characteristics of each unit, and performs data fusion based on similarity analysis with historical samples to determine the benchmark quantity, benchmark unit price, and benchmark provision costs for each unit. This approach fully considers the differences in engineering characteristics among different component units, ensuring that the cost benchmark closely reflects the actual conditions of the project, avoiding deviations caused by uniform standards, providing a more reliable basis for subsequent cost deviation analysis, and improving the scientific nature of cost calculation.

[0015] 2. This invention analyzes the impact of environmental factors on various cost components and constructs an environmental impact coefficient. It combines engineering characteristics such as water depth and distance from the shore with the intensity of environmental disturbance to systematically assess the differentiated impact of different environmental conditions on each component. This enables cost management to respond promptly to environmental changes, dynamically reflect the disturbance of real-time changes in environmental factors on the project quantity, and enhance the environmental adaptability of cost forecasting. Detailed Implementation

[0016] The technical solutions in the embodiments of the present invention will be clearly and completely described below. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0017] It should be understood that the step numbers used in the text are for ease of description only and are not intended to limit the order in which the steps are performed.

[0018] It should be understood that the terminology used in this specification is for the purpose of describing particular embodiments only and is not intended to limit the invention. As used in this specification and the appended claims, the singular forms “a,” “an,” and “the” are intended to include the plural forms unless the context clearly indicates otherwise.

[0019] The terms “comprising” and “including” indicate the presence of the described feature, whole, step, operation, element and / or component, but do not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or collections thereof.

[0020] The term “and / or” refers to any combination of one or more of the associated listed items, as well as all possible combinations, and includes these combinations.

[0021] Example 1: This embodiment provides a method for cost early warning of offshore wind power transmission projects, including the following steps: S1. Break down the offshore wind power transmission project into... The cost component unit is divided into several cost components, and the engineering cost characteristics of each cost component unit are obtained.

[0022] In at least one embodiment, the cost component unit includes a submarine cable line unit, a terrestrial cable line unit, an overhead line unit, a tower foundation unit, a submarine cable protection unit, a landing section protection unit, a booster station unit, a converter station unit, and a communication and monitoring unit.

[0023] In at least one embodiment, the engineering cost characteristics are expressed in vector form, including water depth, distance from shore, seabed type (e.g., "1" represents "sand" and "2" represents "silt"), rated voltage level, transmission capacity, number of transmission loops, and landing point conditions (e.g., "1" represents "sand beach" and "2" represents "rocky coast").

[0024] In at least one embodiment, the engineering cost characteristics are standardized to eliminate the influence between different dimensions.

[0025] S2. Obtain the cost benchmark for offshore wind power transmission projects based on the engineering cost characteristics of each cost component unit. The specific steps are as follows: S201. Based on the aforementioned engineering cost characteristics, calculate the similarity weight coefficient between each cost component unit of the offshore wind power transmission project and each cost component unit of the historical samples, expressed by the formula: ; In the formula, This indicates the first offshore wind power transmission project. The cost component unit and the first The first historical sample The similarity weight coefficient of each cost component unit. Indicates the first The first historical sample The engineering cost characteristics of each cost component unit This indicates the first offshore wind power transmission project. The engineering cost characteristics of each cost component unit Indicates the first The similarity decay bandwidth parameter for each cost component unit is used to control the degree of influence of differences in engineering cost characteristics on the rate of decrease in similarity weights. Indicates the first The number of historical samples for each cost component unit Indicates the first The first historical sample The engineering cost characteristics of each cost component unit This indicates the calculation of Euclidean distance; S202. Based on the similarity weighting coefficient, the quantities, unit prices, and inconvenience costs of each historical sample are merged to obtain the benchmark quantities, benchmark unit prices, and benchmark inconvenience costs for each cost component unit of the offshore wind power transmission project, expressed by the formula: ; ; ; In the formula, This indicates the first offshore wind power transmission project. The baseline quantity of work for each cost component unit Indicates the first The first historical sample The quantity of work for each cost component unit. This indicates the first offshore wind power transmission project. The benchmark unit price of each cost component unit. Indicates the first The first historical sample The unit price of each cost component unit. This indicates the first offshore wind power transmission project. The benchmark cost of each construction component unit. Indicates the first The first historical sample The cost of each component unit includes, for example: dispatching fee for large submarine cable laying vessel, and on-site fee for piling vessel / crane vessel. S203. The cost benchmark for offshore wind power transmission projects is obtained based on benchmark quantities, benchmark unit prices, and benchmark indirect costs, expressed by the following formula: ; In the formula, This indicates the cost benchmark for offshore wind power transmission projects.

[0026] S3. Obtain environmental factors and analyze their impact on various cost components of offshore wind power transmission projects. Obtain the influence coefficients of environmental factors on each cost component. The specific steps are as follows: S301. The environmental factors are normalized and used as the intensity of environmental disturbance, expressed by the formula: ; In the formula, Indicates in The first period Environmental disturbance intensity Indicates in The first period Environmental factors, Indicates the first The maximum value of environmental factors, Indicates the first The minimum value of a class of environmental factors; In at least one embodiment, environmental factors refer to quantitative marine environmental parameters that have a significant impact on offshore construction activities and project costs, which can be directly obtained through on-site monitoring equipment or released through regional marine forecasting systems, including significant wave height, surface current velocity, bottom current velocity, average wind speed, tide level, and water temperature. S302. Construct the influence coefficients of environmental factors on each cost component unit based on the intensity of environmental disturbance, expressed by the formula: ; In the formula, Indicates in Time period Environmental factors affecting offshore wind power transmission projects The influence coefficient of each cost component unit This indicates the first offshore wind power transmission project. The water depth of each cost component unit Represents the reference water depth constant. This indicates the first offshore wind power transmission project. The offshore distance of each cost component unit Represents the reference offshore distance constant. Indicates the reference time constant. Indicates the first The time accumulation index of environmental factors.

[0027] In at least one embodiment, the environmental risk index of the offshore wind power transmission project can also be obtained through the influence coefficient, expressed by the formula: ; In the formula, This indicates the environmental risk index of offshore wind power transmission projects. Indicates the quantity of environmental factors. Indicates the first Importance weighting coefficients for environmental factors.

[0028] The environmental risk index is presented in a dimensionless form, providing a direct understanding of the overall environmental situation of the current construction area. Its calculations fully consider the differences in the impact of various environmental factors on the project, as well as the weight of each component's workload, reflecting the environmental pressure level at the overall project level rather than a localized situation.

[0029] S4. Construct a market risk index for offshore wind power transmission projects. The specific steps are as follows: S401. Obtain the relative price volatility of various materials, expressed by the formula: ; In the formula, Indicates in Time period The relative price volatility of similar materials Indicates in Time period The price of similar materials, No. Price benchmark for similar materials; S402. Based on the aforementioned relative price volatility, determine the cost disturbance coefficient of each cost component unit of the offshore wind power transmission project, expressed by the formula: ; In the formula, Indicates in The first phase of the offshore wind power transmission project Cost disturbance coefficient of each component unit Indicates the quantity of material categories. Indicates the first In the cost component unit, the first Weighting coefficients for similar materials; S403. The average cost disturbance coefficient is taken as the market risk index for offshore wind power transmission projects, expressed by the formula: ; In the formula, Indicates in Market risk index for offshore wind power transmission projects during a given period.

[0030] S5. Determine the engineering quantity correction rate for offshore wind power transmission projects based on the aforementioned influence coefficients. The specific steps are as follows: S501. Based on the aforementioned influence coefficient and the baseline quantity of each cost component unit, obtain the engineering correction coefficient for each cost component unit, expressed by the formula: ; In the formula, Indicates in The first phase of the offshore wind power transmission project Engineering correction factor for each cost component unit Indicates the first The cost component unit for the first Sensitivity coefficient of engineering quantity for environmental factors Indicates the first The cost component unit for the first Engineering quantity response index for environmental factors; S502. The quantity correction rate for offshore wind power transmission projects is determined based on the engineering correction coefficient and benchmark unit price of each cost component unit, expressed by the formula: ; In the formula, Indicates in Correction rate for the amount of work involved in offshore wind power transmission projects during the specified period.

[0031] S6. Determine the cost deviation rate of offshore wind power transmission projects based on engineering correction coefficients, cost disturbance coefficients, and cost benchmarks. The specific steps are as follows: S601. Determine the comprehensive unit price based on the aforementioned cost disturbance coefficient and benchmark unit price, expressed by the formula: ; In the formula, Indicates in The first phase of the offshore wind power transmission project The comprehensive unit price of each cost component unit, Indicates the first Price transmission coefficient of each cost component unit; S602. The coupling coordination cost of offshore wind power transmission projects is obtained based on engineering correction factors, expressed by the formula: ; In the formula, Indicates in Coupling and coordination costs for offshore wind power transmission projects during specific time periods. Indicates the first The cost component unit and the first Paired coupling coefficients when multiple cost component units undergo simultaneous quantity adjustments; S603. The comprehensive cost of offshore wind power transmission projects is obtained based on the comprehensive unit price and coupling coordination costs, expressed by the formula: ; In the formula, Indicates in The overall cost of offshore wind power transmission projects during a given period; S604. The cost deviation rate of offshore wind power transmission projects is determined based on the cost benchmark and comprehensive cost, expressed by the formula: ; In the formula, Indicates in Cost deviation rate of offshore wind power transmission projects during a given period.

[0032] S7. Determine the cost early warning level of the offshore wind power transmission project based on the cost deviation rate, market risk index, and engineering quantity correction rate. The specific steps are as follows: S701. The posterior probability distribution of cost risk level is obtained based on the market risk index and the engineering quantity correction rate, expressed by the formula: ; In the formula, Indicates the level of cost risk. This indicates that the quantity correction rate is... Market risk index is Under the condition that the cost risk level is The posterior probability distribution, This indicates that the cost risk level is Under the condition that the quantity correction rate is The conditional probability is obtained by querying the pre-constructed Bayesian network conditional probability table. This indicates that the cost risk level is Under the condition that the market risk index is The conditional probability, Indicates the cost risk level as The prior probability distribution, This indicates that the cost risk level is Under the condition that the quantity correction rate is The conditional probability, This indicates that the cost risk level is Under the condition that the market risk index is The conditional probability, Indicates the cost risk level as The prior probability distribution; S702. Based on the aforementioned posterior probability distribution and cost deviation rate, obtain the cost early warning level for offshore wind power transmission projects, expressed by the formula: ; In the formula, Indicates in Cost warning level for offshore wind power transmission projects during specific time periods This indicates the threshold for cost volatility. This represents the function that takes the value of the independent variable that makes the function reach its maximum value.

[0033] In at least one embodiment, the probability of cost exceeding the limit for offshore wind power transmission projects can also be obtained through the posterior probability distribution, expressed by the formula: ; In the formula, Indicates in Probability of cost exceeding limits for offshore wind power transmission projects during a given period. This indicates that the quantity correction rate is... Market risk index is Under the condition that the cost risk level is The posterior probability distribution, Indicates the level of cost risk The corresponding probability of exceeding the limit.

[0034] The cost overrun probability quantifies the overall probability estimate of a project cost exceeding the investment control limit based on currently observed engineering and market evidence.

[0035] Example 2: This embodiment provides an electronic device that stores a computer program. When the computer program is executed by a processor, it implements a cost early warning method for offshore wind power transmission projects as described in any embodiment of the present invention.

[0036] Example 3: This embodiment provides a computer-readable storage medium for storing one or more programs, which, when executed by one or more processors, cause the one or more processors to implement the cost early warning method for offshore wind power transmission projects as described in any embodiment of the present invention.

[0037] In this application embodiment, "at least one" refers to one or more, and "more than one" refers to two or more. "And / or" describes the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can represent the existence of A alone, A and B simultaneously, or B alone. A and B can be singular or plural. The character " / " generally indicates that the preceding and following related objects are in an "or" relationship. "At least one of the following" and similar expressions refer to any combination of these items, including any combination of singular or plural items. For example, at least one of a, b, and c can represent: a, b, c, a and b, a and c, b and c, or a and b and c, where a, b, and c can be single or multiple.

[0038] Those skilled in the art will recognize that the units and algorithm steps described in the embodiments disclosed herein can be implemented using electronic hardware, computer software, or a combination of electronic hardware and software. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementation should not be considered beyond the scope of this application.

[0039] Those skilled in the art will understand that, for the sake of convenience and brevity, the specific working processes of the systems, devices, and units described above can be referred to the corresponding processes in the foregoing method embodiments, and will not be repeated here.

[0040] In the several embodiments provided in this application, any function, if implemented as a software functional unit and sold or used as an independent product, can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, or a part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of this application. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks.

[0041] The above description is merely an embodiment of the present invention and does not limit the patent scope of the present invention. Any equivalent structural or procedural transformations made based on the content of the present invention specification, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of the present invention.

Claims

1. A method for cost early warning of offshore wind power transmission projects, characterized in that, Includes the following steps: The offshore wind power transmission project is divided into at least two cost component units, and the project cost characteristics of each cost component unit are obtained. The cost benchmark for offshore wind power transmission projects is obtained based on the engineering cost characteristics of each cost component unit. The impact of environmental factors on various cost components of offshore wind power transmission projects was analyzed, and the impact coefficients of environmental factors on each cost component were obtained. Construct a market risk index and cost disturbance coefficient for each cost component unit of offshore wind power transmission projects; Based on the aforementioned influence coefficients, the engineering quantity correction rate and the engineering correction coefficient for each cost component unit of the offshore wind power transmission project are determined. The cost deviation rate of offshore wind power transmission projects is determined based on engineering correction coefficients, cost disturbance coefficients, and cost benchmarks. The cost early warning level of offshore wind power transmission projects is determined based on the cost deviation rate, market risk index, and engineering quantity correction rate.

2. The cost early warning method for offshore wind power transmission projects according to claim 1, characterized in that, The cost benchmark for offshore wind power transmission projects is obtained based on the engineering cost characteristics of each cost component unit. The specific steps are as follows: Based on the aforementioned engineering cost characteristics, calculate the similarity weight coefficient between each cost component unit of the offshore wind power transmission project and each cost component unit of the historical samples; Based on the similarity weighting coefficient, the engineering quantity, unit price, and measure fee of each historical sample are integrated to obtain the benchmark engineering quantity, benchmark unit price, and benchmark measure fee of each cost component unit of the offshore wind power transmission project. The cost benchmark for offshore wind power transmission projects is obtained based on the benchmark engineering quantity, benchmark unit price, and benchmark invoice cost.

3. The cost early warning method for offshore wind power transmission projects according to claim 1, characterized in that, The specific steps for analyzing the impact of environmental factors on various cost components of offshore wind power transmission projects are as follows: Environmental factors are normalized to represent the intensity of environmental disturbance. The influence coefficients of environmental factors on each cost component unit are constructed based on the water depth, distance from the shore, and intensity of environmental disturbance.

4. The cost early warning method for offshore wind power transmission projects according to claim 1, characterized in that, The specific steps for constructing the market risk index and cost disturbance coefficients of various cost components for offshore wind power transmission projects are as follows: Obtain the relative price volatility of various materials; The cost disturbance coefficients of each cost component unit of the offshore wind power transmission project are determined based on the relative price volatility. The average cost disturbance coefficient is used as the market risk index for offshore wind power transmission projects.

5. The cost early warning method for offshore wind power transmission projects according to claim 3, characterized in that, Based on the aforementioned influence coefficients, the engineering quantity correction rate and the engineering correction coefficients for each cost component unit of the offshore wind power transmission project are determined. The specific steps are as follows: Based on the aforementioned influence coefficient and the baseline engineering quantity of each cost component unit, the engineering correction coefficient of each cost component unit is obtained; The quantity correction rate for offshore wind power transmission projects is determined based on the engineering correction coefficients and benchmark unit prices of each cost component unit.

6. The cost early warning method for offshore wind power transmission projects according to claim 2, characterized in that, The cost deviation rate of offshore wind power transmission projects is determined based on engineering correction factors, cost disturbance factors, and cost benchmarks. The specific steps are as follows: The comprehensive unit price is determined based on the aforementioned cost disturbance coefficient and benchmark unit price; The coupling coordination cost of offshore wind power transmission projects is obtained based on engineering correction factors. The comprehensive cost of offshore wind power transmission projects is obtained based on the comprehensive unit price and coupling coordination costs. The cost deviation rate of offshore wind power transmission projects is determined based on cost benchmarks and comprehensive costs.

7. The cost early warning method for offshore wind power transmission projects according to claim 1, characterized in that, The cost early warning level for offshore wind power transmission projects is determined based on the cost deviation rate, market risk index, and project quantity correction rate. The specific steps are as follows: The posterior probability distribution of cost risk level is obtained based on market risk index and engineering quantity correction rate. The cost warning level of offshore wind power transmission projects is obtained based on the posterior probability distribution and cost deviation rate.

8. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, When the processor executes the program, it implements the cost early warning method for offshore wind power transmission projects as described in any one of claims 1 to 7.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that, When executed by the processor, the program implements the cost early warning method for offshore wind power transmission projects as described in any one of claims 1 to 7.