A risk analysis method and system for construction engineering construction

By acquiring construction and personnel data in real time, generating risk control areas and broadcasting evacuation instructions, the problem of supervisors being unable to fully monitor personnel within the impact range of hoisting was solved, thus achieving timely and comprehensive safety control of construction projects.

CN123140671APending Publication Date: 2026-11-20FUJIAN METALLURGICAL IND DESIGN INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611628298.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-21
Publication Date
2026-11-20

Smart Images

  • Figure CN123140671A_ABST
    Figure CN123140671A_ABST
Patent Text Reader

Abstract

The application relates to the technical field of construction management, and discloses a risk analysis method and system for building engineering construction, which comprises the following steps: acquiring construction data of a target object in real time, analyzing the construction data, determining ground projection points, calculating a real-time track point set formed by the multiple ground projection points, and generating a risk control area representing a construction risk influence range. According to the scheme, the supervision personnel are not restricted by ground observation positions and fields of vision, can comprehensively master the distribution and danger degrees of all construction personnel in a hoisting influence range, preferentially broadcast in an extremely angular interval with high interval evacuation urgency, make the pertinence and audibility of the evacuation instruction stronger, reduce the personnel retention and casualty risks when the hoist fails, and improve the timeliness of the safety control of building engineering construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of construction management technology, and specifically to a risk analysis method and system for building construction. Background Technology

[0002] Currently, in the construction process, the lifting of heavy objects is a risky stage. Therefore, safety management usually focuses on monitoring the operating parameters of the crane and having supervisors manage personnel on the ground to identify and assess the safety risks in the lifting operation.

[0003] However, the above control plan still has the following defects: the supervisors are limited by the ground observation position and field of vision, and cannot investigate and locate all personnel within the scope of the hoisting impact. As a result, once the crane malfunctions, it is difficult to grasp the distribution of personnel in the danger zone in a timely manner and organize effective evacuation, thus affecting the safety control of construction. Summary of the Invention

[0004] To address the shortcomings of existing technologies, this invention provides a risk analysis method and system for building construction, thus solving the aforementioned problems.

[0005] The above-mentioned technical objective of the present invention is achieved through the following technical solution: A risk analysis method for building construction includes: Step S1: Acquire construction data of the target object in real time, analyze the construction data, determine the ground projection points, and calculate the real-time trajectory point set formed by multiple ground projection points to generate a risk control area representing the scope of construction risk. Step S2: Real-time acquisition of personnel data for all construction workers; based on the personnel data, analysis of the risk boundary radius; determination of whether the construction worker is within the risk control area; and calculation of the risk impact degree representing the degree of danger of the construction worker after dividing the polar angle interval. Step S3: Real-time acquisition of the fault trigger signal of the target object. When the target object is in a fault state, analyze the number and location of personnel in the personnel data, and calculate the risk impact in combination to obtain a broadcast evacuation instruction for evacuating construction personnel. Step S4: During the execution of the broadcast evacuation instructions, continuously monitor the construction personnel in the risk control area and adjust the broadcast evacuation instructions accordingly until safety control is completed.

[0006] Furthermore, the construction data is analyzed to determine the ground projection points, including: The vertical projection of the fixed center point of the target object's boom rotating around its fixed center point in the horizontal plane onto the ground is taken as the center of rotation. A polar coordinate system is established with the center of rotation as the pole. The horizontal projection radius of the hook is the boom length multiplied by the cosine of the amplitude angle. The horizontal projection abscissa is the hook horizontal projection radius multiplied by the cosine of the rotation angle, and the ordinate is the hook horizontal projection radius multiplied by the sine of the rotation angle. For each sampling time, the ordered pair of abscissa and ordinate is the ground projection point.

[0007] Furthermore, the real-time trajectory point set formed by multiple ground projection points is calculated to generate a risk control area representing the scope of construction risk, including: For each ground projection point obtained at each sampling time, all projection points from the start of construction to the current time are arranged in chronological order to form a real-time trajectory point set; Sort the real-time trajectory points in ascending order of rotation angle, and calculate the polar radius and polar angle for two adjacent points after sorting, with the rotation center as the pole. If the angle step size is determined by the minimum value of the polar angle differences between adjacent points in the real-time trajectory point set that is greater than 0, then linear interpolation is performed within the polar angle range between these two adjacent points using the polar radius, with the interpolation step size being the angle step size, to obtain continuous boundary points. The maximum polar radius in each polar direction is taken as the risk boundary radius in that direction. All boundary points are sequentially connected to the center of rotation to form a polygon. This polygon is the risk control area representing the scope of construction risk.

[0008] Furthermore, based on personnel data, the risk boundary radius is analyzed to determine whether the construction worker is within the risk control area, including: For each construction worker, convert the x-coordinate and y-coordinate of their position into the worker's polar radius and polar angle; for each boundary point of the risk control area, convert the x-coordinate and y-coordinate into the boundary polar radius and polar angle. Within the risk control area, locate the adjacent boundary points on both sides of the boundary polar angle and the personnel polar angle: sort all boundary points in ascending order of boundary polar angle and form a closed sequence with the beginning and end connected; First, normalize the polar angle of the personnel to the range of 0-2π: if the polar angle of the personnel is less than 0, add 2π; if the polar angle of the personnel is equal to 2π, set it to 0. Then, determine whether the normalized polar angle of the personnel is equal to a certain boundary polar angle. If they are equal, directly use the boundary polar radius of the boundary point as the risk boundary radius in the direction of the personnel polar angle. Otherwise, using the normalized personnel polar angle as an index, find the boundary point in the closed sequence that corresponds to the maximum boundary polar angle where the boundary polar angle is less than the personnel polar angle, and the boundary point that corresponds to the minimum boundary polar angle where the boundary polar angle is greater than the personnel polar angle. If there is no boundary point with a polar angle greater than the personnel's polar angle, then take the first boundary point with the smallest polar angle, add 2π to its polar angle and use it as the adjacent boundary point with a polar angle greater than the personnel's polar angle. Use these two boundary points as the adjacent boundary points on both sides of the personnel's polar angle, and perform linear interpolation between the personnel's polar angle and the polar angles on both sides to obtain the risk boundary radius in the direction of the personnel's polar angle. If the radius of the personnel's polarity is less than or equal to the radius of the risk boundary, then the construction personnel are determined to be within the risk control area. For construction workers within the risk control area, the radial intrusion depth is obtained by subtracting the worker's extreme diameter from the risk boundary radius in the polar angle direction. The radial intrusion ratio is obtained by dividing the radial intrusion depth by the risk boundary radius in the polar angle direction of the worker. The radial velocity of a person is obtained by subtracting the radial radius of the same person from the radial radius of the person at the previous sampling time from the radial radius of the person at the current sampling time, and then dividing by the sampling period. The sampling period is the time interval between two consecutive acquisitions of construction data of the target object.

[0009] Furthermore, after dividing the polar angle intervals, calculations are performed to obtain the risk impact degree representing the level of danger to construction workers, including: The risk boundary change rate is obtained by subtracting the risk boundary radius of the same person in the polar direction at the current sampling time from the risk boundary radius of the same person in the polar direction at the previous sampling time, and then dividing by the sampling period. The net escape velocity is calculated based on the radial velocity of personnel and the boundary change velocity, and the speed hazard factor is determined based on the net escape velocity: when the net escape velocity ≤ 0, the speed hazard factor is equal to 1; when the net escape velocity > 0, the speed hazard factor is calculated. The risk control area is divided into polar angle intervals with the same number of boundary points according to the polar angles of the boundary points: Let the number of boundary points be N, and after sorting, they are called the first boundary polar angle, the second boundary polar angle, and so on up to the Nth boundary polar angle. For any construction worker within the risk control area, if the worker's polar angle is less than the first boundary polar angle, first add twice pi to the worker's polar angle, then find a polar angle interval that satisfies the condition that the worker's polar angle is greater than or equal to the starting point of any polar angle interval and the worker's polar angle is less than the ending point of that polar angle interval. If this condition is met, the worker is assigned to that polar angle interval. If the worker's polar angle is equal to the starting point of the Nth polar angle interval, then the worker is assigned to that polar angle interval. If the worker's polar angle is equal to the ending point of the last polar angle interval, and the ending point is equal to the first boundary polar angle plus twice pi, then the worker is assigned to the last polar angle interval. The number of construction workers within the risk control area in each polar angle interval is counted. If the total number of construction workers in the current risk control area is 0, the risk impact is 0. Otherwise, the number of construction workers in the polar angle interval where the construction worker is located is divided by the total number of construction workers in the current risk control area to obtain the personnel number factor. The personnel number factor, radial intrusion ratio and velocity hazard factor are calculated to obtain the risk impact representing the degree of danger of the construction workers.

[0010] Furthermore, when the target object is in a fault state, the number and location of personnel in the personnel data are analyzed, and combined with the risk impact, calculations are performed to obtain broadcast evacuation instructions for evacuating construction personnel, including: For each defined polar angle interval, the number of construction workers within that polar angle interval is counted, and the risk impact of all construction workers within that polar angle interval is added together to obtain the cumulative risk value of the interval. The average intrusion ratio of the interval is calculated based on the radial intrusion ratio of all construction personnel within the polar angle interval and the number of construction personnel within the polar angle interval. Based on the cumulative risk value and the average intrusion ratio of the interval, the urgency of evacuating all construction personnel within the polar angle interval is analyzed to obtain the urgency of interval evacuation.

[0011] Furthermore, when the target object is in a fault state, the number and location of personnel in the personnel data are analyzed, and combined with the risk impact, calculations are performed to obtain broadcast evacuation instructions for evacuating construction personnel, including: Sort all polar angle intervals with evacuation urgency > 0 according to their corresponding evacuation urgency from largest to smallest, and the candidate volume level of the r-th polar angle interval is N-r+1. The number of broadcast repetitions = the number of construction workers whose net escape velocity within the interval is ≤0 + 1; Generate broadcast evacuation instructions that include candidate volume levels and the number of broadcast repetitions.

[0012] Furthermore, during the execution of broadcast evacuation instructions, construction personnel within the risk control area are continuously monitored, and the broadcast evacuation instructions are adjusted accordingly until safety control is achieved, including: During the execution of the broadcast evacuation order, the construction personnel in the risk control area are continuously monitored. For the polar angle intervals where there are still construction personnel, M is set as the number of polar angle intervals with construction personnel in the risk control area in the current sampling period. The M polar angle intervals with construction personnel are reordered from largest to smallest according to the evacuation urgency of the interval in the current sampling period. The sorting position is denoted as k, where k ranges from 1 to M. The candidate volume level of the kth polar angle interval with personnel is N minus k + 1, where N is the total number of polar angle intervals divided in the risk control area. Obtain the actual volume level of the previous broadcast cycle for the polar angle interval. If the number of construction workers in the risk control area within the current sampling cycle of the polar angle interval is greater than the number of construction workers in the risk control area within the polar angle interval of the previous broadcast cycle, and the number of construction workers with a net escape velocity ≤ 0 within the current sampling cycle of the polar angle interval is greater than the number of construction workers with a net escape velocity ≤ 0 within the polar angle interval of the previous broadcast cycle, then the final volume level of the broadcast evacuation instruction is selected as the largest of the candidate volume level and the actual volume level of the previous broadcast cycle plus 1, and it does not exceed N. Otherwise, the final volume level selection for the broadcast evacuation instruction will be the largest of the candidate volume level and the actual volume level of the previous broadcast cycle.

[0013] Furthermore, during the execution of broadcast evacuation instructions, continuous monitoring of construction personnel within the risk control area is conducted, and the broadcast evacuation instructions are adjusted adaptively until safety control is achieved. This also includes: For each polar angle interval with construction workers, the broadcast repetition count is updated to the number of construction workers with a net escape velocity ≤ 0 in the current sampling period of that polar angle interval plus 1, and a new broadcast evacuation instruction with the final volume level and broadcast repetition count is generated and executed. Once the total number of construction workers in the risk control area is zero, stop issuing broadcast evacuation instructions and complete safety control.

[0014] Furthermore, a risk analysis system for building construction, applied to the above-mentioned analysis method, includes: The regional analysis unit is used to acquire construction data of the target object in real time, analyze the construction data, determine the ground projection points, and calculate the real-time trajectory point set formed by multiple ground projection points to generate a risk control area representing the scope of construction risk. The risk impact unit is used to acquire personnel data of all construction workers in real time. Based on the personnel data, the risk boundary radius is analyzed to determine whether the construction worker is within the risk control area. After dividing the polar angle interval, the risk impact degree representing the degree of danger of the construction worker is calculated. The broadcast evacuation unit is used to acquire the fault trigger signal of the target object in real time. When the target object is in a fault state, it analyzes the number and location of personnel in the personnel data and calculates the risk impact to obtain a broadcast evacuation instruction for evacuating construction personnel. The safety control unit is used to continuously monitor construction personnel within the risk control area during the execution of broadcast evacuation instructions, and to adaptively adjust the broadcast evacuation instructions until safety control is completed.

[0015] In summary, the present invention has the following main beneficial effects: By acquiring real-time construction data of the target object and determining ground projection points, a risk control zone representing the scope of construction risk is generated. Then, based on personnel data analysis of construction workers, the risk boundary radius is determined to assess whether workers are within the risk control zone. After dividing the zone into polar angle intervals, a risk impact degree representing the level of danger to construction workers is obtained. When the target object is in a faulty state, a broadcast evacuation instruction is generated by combining the number of personnel, their location, and the risk impact degree. During execution, construction workers within the risk control zone are continuously monitored, and the final volume level and broadcast repetition count are dynamically adjusted until the number of construction workers within the risk control zone is zero. This solution allows supervisors to be unrestricted by ground observation positions and field of vision, enabling them to fully grasp the distribution and danger level of all construction workers within the hoisting impact range. Priority is given to broadcasting to polar angle intervals with high evacuation urgency, making the evacuation instructions more targeted and audible, reducing the risk of personnel being stranded and injured during crane malfunctions, and improving the timeliness and comprehensiveness of safety management in construction projects. Attached Figure Description

[0016] Figure 1 This is a flowchart illustrating the risk analysis method for building construction of the present invention.

[0017] Figure 2 This is a diagram illustrating the steps for determining the ground projection point according to the present invention.

[0018] Figure 3 This is a diagram illustrating the analysis steps for the risk management area of ​​this invention. Detailed Implementation

[0019] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0020] refer to Figure 1 , Figure 2 and Figure 3 A risk analysis method for building construction projects, comprising: Step S1: Real-time acquisition of construction data of the target object, analysis of the construction data, determination of ground projection points, calculation of the real-time trajectory point set formed by multiple ground projection points, and generation of a risk control area representing the scope of construction risk. The target object is the crane. Construction data includes: luffing angle, slewing angle, lifting height, and boom length, etc. Among them, the luffing angle is the angle between the boom axis and the horizontal plane, the slewing angle is the angle between the projection of the boom axis on the horizontal plane and the crane reference direction, the lifting height is the vertical distance from the lower surface of the hook to the ground plane, and the boom length is the length from the boom root hinge point to the boom end. Step S2: Real-time acquisition of personnel data for all construction workers; based on the personnel data, analysis of the risk boundary radius; determination of whether the construction worker is within the risk control area; and calculation of the risk impact degree representing the degree of danger of the construction worker after dividing the polar angle interval. Personnel data includes: number of personnel and personnel location, etc. Step S3: Real-time acquisition of the fault trigger signal of the target object. When the target object is in a fault state, analyze the number and location of personnel in the personnel data, and calculate the risk impact in combination to obtain a broadcast evacuation instruction for evacuating construction personnel. Step S4: During the execution of the broadcast evacuation instructions, continuously monitor the construction personnel in the risk control area and adjust the broadcast evacuation instructions accordingly until safety control is completed.

[0021] In one embodiment, analyzing construction data to determine ground projection points includes: The vertical projection of the fixed center point of the target object's boom rotating around its fixed center point in the horizontal plane onto the ground is taken as the center of rotation. A polar coordinate system is established with the center of rotation as the pole, and the polar axis is the projection of the crane's reference direction onto the horizontal plane. Since the hook of the target object is suspended below the end of the boom by the hoisting wire rope, the horizontal projection of the hook coincides with the horizontal projection of the boom end. Therefore, the ground projection point is the vertical projection of the center of the lower surface of the hook onto the ground plane. The ground projection point is calculated as follows: the horizontal projection radius of the hook is the boom length multiplied by the cosine of the amplitude angle; the horizontal projection abscissa is the horizontal projection radius of the hook multiplied by the cosine of the rotation angle; and the vertical coordinate is the horizontal projection radius of the hook multiplied by the sine of the rotation angle. For each sampling time, the ordered pair of abscissa and vertical coordinate is the ground projection point.

[0022] In one embodiment, a real-time trajectory point set formed by multiple ground projection points is calculated to generate a risk control area representing the scope of construction risk, including: For each ground projection point obtained at each sampling time, all projection points from the start of construction to the current time are arranged in chronological order to form a real-time trajectory point set; Sort the real-time trajectory points in ascending order of rotation angle. If multiple points have the same rotation angle, retain the maximum value of the horizontal projection radius of the hook. For two adjacent points after sorting, calculate the polar radius and polar angle with the rotation center as the pole. If the difference between adjacent polar angles is greater than the minimum value of the difference between adjacent polar angles in the real-time trajectory point set that is greater than 0, then linear interpolation is performed within the polar angle range between these two adjacent points using the polar radius, with the interpolation step size being the angle step size, to obtain continuous boundary points. If the difference between adjacent polar angles is less than or equal to the angle step size, then the two adjacent points are directly used as boundary points. The angle step size is the minimum value of the polar angle difference between all adjacent points in the real-time trajectory point set that is greater than 0. If there is no polar angle difference between adjacent points that is greater than 0, that is, if the polar angle difference between all adjacent points is 0 or the number of points in the real-time trajectory point set is less than 2, then the polar angle range between these two adjacent points is not interpolated. The maximum polar radius in each polar direction is taken as the risk boundary radius in that direction. All boundary points are sequentially connected to the center of rotation to form a polygon. This polygon is the risk control area representing the scope of construction risk.

[0023] By determining ground projection points and generating risk control zones, the scope of construction risks affecting the target object in the horizontal plane can be intuitively mapped to the ground. This allows supervisors to grasp the distribution of personnel within the risk control zone without being limited by ground observation positions and field of vision. It is beneficial to promptly identify and locate personnel in dangerous areas, and to quickly organize effective evacuation when the target object malfunctions, reducing the risk of personnel being stranded. Continuous boundary points and polygonal risk control zones can improve the safety control capabilities of heavy object hoisting in construction projects.

[0024] In one embodiment, based on personnel data, the risk boundary radius is analyzed to determine whether the construction worker is within the risk control area, including: For each construction worker, convert the x-coordinate and y-coordinate of their position into the worker's polar radius and polar angle: the worker's polar radius is the square root of the sum of the squares of the x-coordinate and the squares of the y-coordinate, and the worker's polar angle is the arctangent of the four quadrants atan2(y-coordinate, x-coordinate) with the positive x-axis as the polar axis and the counterclockwise direction as positive. For each boundary point in the risk control area, its x and y coordinates are converted into the boundary polar radius and boundary polar angle: the boundary polar radius is the square root of the sum of the squares of the x and y coordinates of the boundary point, which represents the straight-line distance from the boundary point to the center of rotation; the boundary polar angle is the arctangent of the x and y coordinates of the boundary point in the four quadrants, atan2(y coordinate, x coordinate). Within the risk control area, locate the adjacent boundary points on both sides of the boundary polar angle and the personnel polar angle: sort all boundary points in ascending order of boundary polar angle and form a closed sequence with the beginning and end connected; First, normalize the polar angle of the personnel to the range of 0-2π: if the polar angle of the personnel is less than 0, add 2π; if the polar angle of the personnel is equal to 2π, set it to 0. Then, determine whether the normalized polar angle of the personnel is equal to a certain boundary polar angle. If they are equal, directly use the boundary polar radius of the boundary point as the risk boundary radius in the direction of the personnel polar angle. Otherwise, using the normalized personnel polar angle as an index, find the boundary point in the closed sequence that corresponds to the maximum boundary polar angle where the boundary polar angle is less than the personnel polar angle, and the boundary point that corresponds to the minimum boundary polar angle where the boundary polar angle is greater than the personnel polar angle. If there is no boundary point with a polar angle greater than the personnel polar angle, then take the first boundary point with the smallest polar angle, add 2π to its polar angle and use it as the adjacent boundary point with a polar angle greater than the personnel polar angle. Use these two boundary points as the adjacent boundary points on both sides of the personnel polar angle, and perform linear interpolation between the personnel polar angle and the polar angles on both sides: add the polar radius of one side of the boundary to the difference between the polar radii of the two sides of the boundary, multiply by the difference between the personnel polar angle and the polar angle of one side of the boundary, and then divide by the difference between the polar angles of the two sides of the boundary to obtain the risk boundary radius in the direction of the personnel polar angle. If the radius of the personnel's polarity is less than or equal to the radius of the risk boundary, then the construction personnel are determined to be within the risk control area. For construction workers within the risk control area, the radial intrusion depth is obtained by subtracting the worker's extreme diameter from the risk boundary radius in the polar angle direction. The radial intrusion ratio is obtained by dividing the radial intrusion depth by the risk boundary radius in the polar angle direction of the worker. The radial velocity of a person is obtained by subtracting the radial radius of the same person from the radial radius of the person at the previous sampling time from the radial radius of the person at the current sampling time, and then dividing by the sampling period. The sampling period is the time interval between two consecutive acquisitions of construction data of the target object.

[0025] In one embodiment, after dividing the polar angle interval, a risk impact degree representing the degree of danger to construction workers is obtained through calculation, including: The risk boundary change rate is obtained by subtracting the risk boundary radius of the same person in the polar direction at the current sampling time from the risk boundary radius of the same person in the polar direction at the previous sampling time, and then dividing by the sampling period. Subtract the boundary change rate from the radial velocity of the personnel to obtain the net escape velocity, and determine the velocity hazard factor based on the net escape velocity: when the net escape velocity ≤ 0, the velocity hazard factor is equal to 1; when the net escape velocity > 0, calculate the velocity hazard factor: divide the radial intrusion depth by the net escape velocity to obtain the escape time, and divide the escape time by the sum of the sampling period and the escape time to obtain the velocity hazard factor. The risk control area is divided into polar angle intervals equal to the number of boundary points according to the polar angles of the boundary points: Let the number of boundary points be N, and after sorting, they are called the first boundary polar angle, the second boundary polar angle, and so on until the Nth boundary polar angle. Since the risk control area is formed by connecting these boundary points and the center of rotation in sequence to form a closed polygon, the angle between the Nth boundary polar angle and the first boundary polar angle plus twice pi is regarded as the first and last edges being connected, thus dividing the area into N polar angle intervals. The first polar angle interval extends from the first boundary polar angle to the second boundary polar angle, the second polar angle interval extends from the second boundary polar angle to the third boundary polar angle, and so on. Each polar angle interval corresponds to a boundary point and adjacent intervals are connected end to end. All polar angle intervals seamlessly cover the first boundary polar angle to the first boundary polar angle + 2 times pi, without overlap or omission. For any construction worker within the risk control area, if the worker's polar angle is less than the first boundary polar angle, first add twice pi to the worker's polar angle, then find a polar angle interval that satisfies the condition that the worker's polar angle is greater than or equal to the starting point of any polar angle interval and the worker's polar angle is less than the ending point of that polar angle interval. If this condition is met, the worker is assigned to that polar angle interval. If the worker's polar angle is equal to the starting point of the Nth polar angle interval, then the worker is assigned to that polar angle interval. If the worker's polar angle is equal to the ending point of the last polar angle interval, and the ending point is equal to the first boundary polar angle plus twice pi, then the worker is assigned to the last polar angle interval. The number of construction workers within the risk control area in each polar angle interval is counted. If the total number of construction workers in the current risk control area is 0, the risk impact is 0. Otherwise, the number of construction workers in the polar angle interval where the construction worker is located is divided by the total number of construction workers in the current risk control area to obtain the personnel quantity factor. If the total number of construction workers is 0, the risk impact is 0. The personnel quantity factor is multiplied by the radial intrusion ratio and then by the speed hazard factor to obtain the risk impact degree representing the degree of danger of the construction worker. The larger the risk impact degree, the higher the degree of danger of the construction worker.

[0026] By determining the risk boundary radius through personnel data, it is possible to accurately determine whether construction personnel are within the risk control area and obtain radial intrusion depth, radial intrusion ratio, personnel radial velocity, boundary change rate, net escape velocity, velocity hazard factor, and risk impact degree. The risk impact degree can reflect the degree of danger of each construction worker. As a result, supervisors are not limited by ground observation position and field of vision, and can fully grasp the distribution and location of personnel in the danger zone, promptly investigate and locate them, and organize evacuation, reducing the risk of personnel being stranded and injured when cranes malfunction, and enhancing the safety control capability of heavy lifting construction.

[0027] In one embodiment, when the target object is in a fault state, the number and location of personnel in the personnel data are analyzed, and a calculation is performed in conjunction with the risk impact level to obtain a broadcast evacuation instruction for evacuating construction personnel, including: For each defined polar angle interval, the number of construction workers within that polar angle interval is counted, and the risk impact of all construction workers within that polar angle interval is added together to obtain the cumulative risk value of the interval. The radial intrusion ratio of all construction personnel within the polar angle interval is summed and then divided by the number of construction personnel within that polar angle interval to obtain the interval average intrusion ratio. If the number of construction personnel within that polar angle interval is 0, the interval average intrusion ratio is set to 0. Based on the cumulative risk value of the interval and the average intrusion ratio of the interval, the urgency of evacuating all construction personnel in the polar angle interval is analyzed to obtain the evacuation urgency of the interval. Specifically, the cumulative risk value of the interval is multiplied by the average intrusion ratio of the interval to obtain the evacuation urgency of the interval. If there are no construction personnel in the polar angle interval, the evacuation urgency of the interval is 0. In one embodiment, when the target object is in a fault state, the number and location of personnel in the personnel data are analyzed, and a calculation is performed in conjunction with the risk impact level to obtain a broadcast evacuation instruction for evacuating construction personnel, including: Sort all polar angle intervals with evacuation urgency > 0 according to their corresponding evacuation urgency from largest to smallest, and the candidate volume level of the r-th polar angle interval is N-r+1. The number of broadcast repetitions = the number of construction workers whose net escape velocity within the interval is ≤0 + 1; Generate broadcast evacuation instructions that include candidate volume levels and broadcast repetition counts. If the total number of construction workers in the risk control area is 0, stop generating broadcast evacuation instructions.

[0028] In one embodiment, during the execution of the broadcast evacuation instruction, the construction personnel within the risk control area are continuously monitored, and the broadcast evacuation instruction is adaptively adjusted until safety control is completed, including: During the execution of the broadcast evacuation instructions, the construction personnel in the risk control area are continuously monitored. For the polar angle intervals where there are still construction personnel, M is set as the number of polar angle intervals with construction personnel in the risk control area in the current sampling period. The M polar angle intervals with construction personnel are reordered from largest to smallest according to the urgency of the interval evacuation in the current sampling period, and the sorting position is denoted as k, where k ranges from 1 to M. The candidate volume level of the kth polar angle interval with personnel is N minus k + 1, where N is the total number of polar angle intervals divided in the risk control area. The larger the candidate volume level, the louder the broadcast sound. Obtain the actual volume level of the previous broadcast cycle for the polar angle interval. If the number of construction workers in the risk control area within the current sampling cycle of the polar angle interval is greater than the number of construction workers in the risk control area within the polar angle interval of the previous broadcast cycle, and the number of construction workers with a net escape velocity ≤ 0 within the current sampling cycle of the polar angle interval is greater than the number of construction workers with a net escape velocity ≤ 0 within the polar angle interval of the previous broadcast cycle, then the final volume level of the broadcast evacuation instruction is selected as the largest of the candidate volume level and the actual volume level of the previous broadcast cycle plus 1, and it does not exceed N. Otherwise, the final volume level selection for the broadcast evacuation instruction will be the largest of the candidate volume level and the actual volume level of the previous broadcast cycle.

[0029] In one embodiment, during the execution of the broadcast evacuation instruction, continuous monitoring of construction personnel within the risk control area is carried out, and the broadcast evacuation instruction is adaptively adjusted until safety control is completed. This also includes: For each polar angle interval with construction workers, the broadcast repetition count is updated to the number of construction workers with a net escape velocity ≤ 0 in the current sampling period of that polar angle interval plus 1, and a new broadcast evacuation instruction with the final volume level and broadcast repetition count is generated and executed. Once the total number of construction workers in the risk control area is zero, stop issuing broadcast evacuation instructions and complete safety control.

[0030] When the target object is in a faulty state, it can automatically generate broadcast evacuation instructions for construction workers based on the number and location of personnel in the personnel data, combined with the degree of risk impact. This overcomes the shortcomings of supervisors who are limited by their ground observation position and field of vision, making it difficult to locate and position all personnel within the impact range of hoisting. By dividing polar angle intervals and obtaining the cumulative risk value, average intrusion ratio, and evacuation urgency of the intervals, it can accurately identify the degree of personnel gathering and the degree of danger urgency in different directions within the risk control area. This allows broadcast evacuation instructions to prioritize coverage of high-risk directions, avoiding blind broadcasting and chaotic evacuation.

[0031] By ranking candidate volume levels according to the urgency of evacuation in different areas and determining the number of broadcast repetitions based on net escape velocity, the sound intensity and number of repetitions are matched with the level of danger on site and the ability of personnel to escape. This increases the probability that construction workers will hear the instructions and evacuate in time. During the execution of broadcast evacuation instructions, the system continuously monitors the construction workers in the risk control area and dynamically updates the final volume level and number of broadcast repetitions. For polar-angle sections where the number of personnel increases or the net escape velocity is insufficient, the broadcast is intensified until the number of construction workers in the risk control area is 0, thus achieving closed-loop safety control. This solution can promptly grasp the distribution of personnel in dangerous areas when the target object fails, organize effective evacuation, reduce the risk of personnel being stranded and casualties, and improve the timeliness of safety control for heavy object hoisting construction.

[0032] In one embodiment, a risk analysis system for building construction is applied to the above-described analysis method, including: The regional analysis unit is used to acquire construction data of the target object in real time, analyze the construction data, determine the ground projection points, and calculate the real-time trajectory point set formed by multiple ground projection points to generate a risk control area representing the scope of construction risk. The risk impact unit is used to acquire personnel data of all construction workers in real time. Based on the personnel data, the risk boundary radius is analyzed to determine whether the construction worker is within the risk control area. After dividing the polar angle interval, the risk impact degree representing the degree of danger of the construction worker is calculated. The broadcast evacuation unit is used to acquire the fault trigger signal of the target object in real time. When the target object is in a fault state, it analyzes the number and location of personnel in the personnel data and calculates the risk impact to obtain a broadcast evacuation instruction for evacuating construction personnel. The safety control unit is used to continuously monitor construction personnel within the risk control area during the execution of broadcast evacuation instructions, and to adaptively adjust the broadcast evacuation instructions until safety control is completed.

[0033] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A risk analysis method for building construction projects, characterized in that, include: Step S1: Acquire construction data of the target object in real time, analyze the construction data, determine the ground projection points, and calculate the real-time trajectory point set formed by multiple ground projection points to generate a risk control area representing the scope of construction risk. Step S2: Real-time acquisition of personnel data for all construction workers; based on the personnel data, analysis of the risk boundary radius; determination of whether the construction worker is within the risk control area; and calculation of the risk impact degree representing the degree of danger of the construction worker after dividing the polar angle interval. Step S3: Real-time acquisition of the fault trigger signal of the target object. When the target object is in a fault state, analyze the number and location of personnel in the personnel data, and calculate the risk impact in combination to obtain a broadcast evacuation instruction for evacuating construction personnel. Step S4: During the execution of the broadcast evacuation instructions, continuously monitor the construction personnel in the risk control area and adjust the broadcast evacuation instructions accordingly until safety control is completed.

2. The risk analysis method for building construction according to claim 1, characterized in that, Analyze the construction data to determine the ground projection points, including: The vertical projection of the fixed center point of the target object's boom rotating around its fixed center point in the horizontal plane onto the ground is taken as the center of rotation. A polar coordinate system is established with the center of rotation as the pole. The horizontal projection radius of the hook is the boom length multiplied by the cosine of the amplitude angle. The horizontal projection abscissa is the hook horizontal projection radius multiplied by the cosine of the rotation angle, and the ordinate is the hook horizontal projection radius multiplied by the sine of the rotation angle. For each sampling time, the ordered pair of abscissa and ordinate is the ground projection point.

3. The risk analysis method for building construction according to claim 2, characterized in that, Calculate the real-time trajectory point set formed by multiple ground projection points to generate a risk control area representing the scope of construction risk, including: For each ground projection point obtained at each sampling time, all projection points from the start of construction to the current time are arranged in chronological order to form a real-time trajectory point set; Sort the real-time trajectory points in ascending order of rotation angle, and calculate the polar radius and polar angle for two adjacent points after sorting, with the rotation center as the pole. If the angle step size is determined by the minimum value of the polar angle differences between adjacent points in the real-time trajectory point set that is greater than 0, then linear interpolation is performed within the polar angle range between these two adjacent points using the polar radius, with the interpolation step size being the angle step size, to obtain continuous boundary points. The maximum polar radius in each polar direction is taken as the risk boundary radius in that direction. All boundary points are sequentially connected to the center of rotation to form a polygon. This polygon is the risk control area representing the scope of construction risk.

4. The risk analysis method for building construction according to claim 3, characterized in that, Based on personnel data, the risk boundary radius is analyzed to determine whether the construction worker is within the risk control area, including: For each construction worker, convert the x-coordinate and y-coordinate of their position into the worker's polar radius and polar angle; for each boundary point of the risk control area, convert the x-coordinate and y-coordinate into the boundary polar radius and polar angle. Within the risk control area, locate the adjacent boundary points on both sides of the boundary polar angle and the personnel polar angle: sort all boundary points in ascending order of boundary polar angle and form a closed sequence with the beginning and end connected; First, normalize the polar angle of the personnel to the range of 0-2π: if the polar angle of the personnel is less than 0, add 2π; if the polar angle of the personnel is equal to 2π, set it to 0. Then, determine whether the normalized polar angle of the personnel is equal to a certain boundary polar angle. If they are equal, directly use the boundary polar radius of the boundary point as the risk boundary radius in the direction of the personnel polar angle. Otherwise, using the normalized personnel polar angle as an index, find the boundary point in the closed sequence that corresponds to the maximum boundary polar angle where the boundary polar angle is less than the personnel polar angle, and the boundary point that corresponds to the minimum boundary polar angle where the boundary polar angle is greater than the personnel polar angle. If there is no boundary point with a polar angle greater than the personnel's polar angle, then take the first boundary point with the smallest polar angle, add 2π to its polar angle and use it as the adjacent boundary point with a polar angle greater than the personnel's polar angle. Use these two boundary points as the adjacent boundary points on both sides of the personnel's polar angle, and perform linear interpolation between the personnel's polar angle and the polar angles on both sides to obtain the risk boundary radius in the direction of the personnel's polar angle. If the radius of the personnel's extreme diameter is less than or equal to the radius of the risk boundary, then the construction personnel are determined to be within the risk control area. For construction workers within the risk control area, the radial intrusion depth is obtained by subtracting the worker's extreme diameter from the risk boundary radius in the polar angle direction. The radial intrusion ratio is obtained by dividing the radial intrusion depth by the risk boundary radius in the polar angle direction of the worker. The radial velocity of a person is obtained by subtracting the radial radius of the same person from the radial radius of the person at the previous sampling time from the radial radius of the person at the current sampling time, and then dividing by the sampling period. The sampling period is the time interval between two consecutive acquisitions of construction data of the target object.

5. The risk analysis method for building construction according to claim 4, characterized in that, After dividing the polar angle intervals, calculations are performed to obtain the risk impact degree representing the level of danger to construction workers, including: The risk boundary change rate is obtained by subtracting the risk boundary radius of the same person in the polar direction at the current sampling time from the risk boundary radius of the same person in the polar direction at the previous sampling time, and then dividing by the sampling period. The net escape velocity is calculated based on the radial velocity of personnel and the boundary change velocity, and the speed hazard factor is determined based on the net escape velocity: when the net escape velocity ≤ 0, the speed hazard factor is equal to 1; when the net escape velocity > 0, the speed hazard factor is calculated. The risk control area is divided into polar angle intervals with the same number of boundary points according to the polar angles of the boundary points: Let the number of boundary points be N, and after sorting, they are called the first boundary polar angle, the second boundary polar angle, and so on up to the Nth boundary polar angle. For any construction worker within the risk control area, if the worker's polar angle is less than the first boundary polar angle, first add twice pi to the worker's polar angle, then find a polar angle interval that satisfies the condition that the worker's polar angle is greater than or equal to the starting point of any polar angle interval and the worker's polar angle is less than the ending point of that polar angle interval. If this condition is met, the worker is assigned to that polar angle interval. If the worker's polar angle is equal to the starting point of the Nth polar angle interval, then the worker is assigned to that polar angle interval. If the worker's polar angle is equal to the ending point of the last polar angle interval, and the ending point is equal to the first boundary polar angle plus twice pi, then the worker is assigned to the last polar angle interval. The number of construction workers within the risk control area in each polar angle interval is counted. If the total number of construction workers in the current risk control area is 0, the risk impact is 0. Otherwise, the number of construction workers in the polar angle interval where the construction worker is located is divided by the total number of construction workers in the current risk control area to obtain the personnel number factor. The personnel number factor, radial intrusion ratio and velocity hazard factor are calculated to obtain the risk impact representing the degree of danger of the construction workers.

6. The risk analysis method for building construction according to claim 5, characterized in that, When the target object is in a fault state, the number and location of personnel in the personnel data are analyzed, and combined with the risk impact, calculations are performed to obtain broadcast evacuation instructions for evacuating construction personnel, including: For each defined polar angle interval, the number of construction workers within that polar angle interval is counted, and the risk impact of all construction workers within that polar angle interval is added together to obtain the cumulative risk value of the interval. The average intrusion ratio of the interval is calculated based on the radial intrusion ratio of all construction personnel within the polar angle interval and the number of construction personnel within the polar angle interval. Based on the cumulative risk value and the average intrusion ratio of the interval, the urgency of evacuating all construction personnel within the polar angle interval is analyzed to obtain the urgency of interval evacuation.

7. The risk analysis method for building construction according to claim 6, characterized in that, When the target object is in a fault state, the number and location of personnel in the personnel data are analyzed, and combined with the risk impact, calculations are performed to obtain broadcast evacuation instructions for evacuating construction personnel, including: Sort all polar angle intervals with evacuation urgency > 0 according to their corresponding evacuation urgency from largest to smallest, and the candidate volume level of the r-th polar angle interval is N-r+1. The number of broadcast repetitions = the number of construction workers whose net escape velocity within the interval is ≤0 + 1; Generate broadcast evacuation instructions that include candidate volume levels and the number of broadcast repetitions.

8. The risk analysis method for building construction according to claim 7, characterized in that, During the execution of broadcast evacuation instructions, construction personnel within the risk control area are continuously monitored, and the broadcast evacuation instructions are adjusted accordingly until safety control is achieved, including: During the execution of the broadcast evacuation order, the construction personnel in the risk control area are continuously monitored. For the polar angle intervals where there are still construction personnel, M is set as the number of polar angle intervals with construction personnel in the risk control area in the current sampling period. The M polar angle intervals with construction personnel are reordered from largest to smallest according to the evacuation urgency of the interval in the current sampling period. The sorting position is denoted as k, where k ranges from 1 to M. The candidate volume level of the kth polar angle interval with personnel is N minus k + 1, where N is the total number of polar angle intervals divided in the risk control area. Obtain the actual volume level of the previous broadcast cycle for the polar angle interval. If the number of construction workers in the risk control area within the current sampling cycle of the polar angle interval is greater than the number of construction workers in the risk control area within the polar angle interval of the previous broadcast cycle, and the number of construction workers with a net escape velocity ≤ 0 within the current sampling cycle of the polar angle interval is greater than the number of construction workers with a net escape velocity ≤ 0 within the polar angle interval of the previous broadcast cycle, then the final volume level of the broadcast evacuation instruction is selected as the largest of the candidate volume level and the actual volume level of the previous broadcast cycle plus 1, and it does not exceed N. Otherwise, the final volume level selection for the broadcast evacuation instruction will be the largest of the candidate volume level and the actual volume level of the previous broadcast cycle.

9. The risk analysis method for building construction according to claim 8, characterized in that, During the execution of broadcast evacuation instructions, continuous monitoring of construction personnel within the risk control area is maintained, and the broadcast evacuation instructions are adjusted accordingly until safety control is achieved. This also includes: For each polar angle interval with construction workers, the broadcast repetition count is updated to the number of construction workers with a net escape velocity ≤ 0 in the current sampling period of that polar angle interval plus 1, and a new broadcast evacuation instruction with the final volume level and broadcast repetition count is generated and executed. Once the total number of construction workers in the risk control area is zero, stop issuing broadcast evacuation instructions and complete safety control.

10. A risk analysis system for building construction, applied in the analysis method as described in any one of claims 1-9, characterized in that, include: The regional analysis unit is used to acquire construction data of the target object in real time, analyze the construction data, determine the ground projection points, and calculate the real-time trajectory point set formed by multiple ground projection points to generate a risk control area representing the scope of construction risk. The risk impact unit is used to acquire personnel data of all construction workers in real time. Based on the personnel data, the risk boundary radius is analyzed to determine whether the construction worker is within the risk control area. After dividing the polar angle interval, the risk impact degree representing the degree of danger of the construction worker is calculated. The broadcast evacuation unit is used to acquire the fault trigger signal of the target object in real time. When the target object is in a fault state, it analyzes the number and location of personnel in the personnel data and calculates the risk impact to obtain a broadcast evacuation instruction for evacuating construction personnel. The safety control unit is used to continuously monitor construction personnel within the risk control area during the execution of broadcast evacuation instructions, and to adaptively adjust the broadcast evacuation instructions until safety control is completed.