A BIM-based hydropower engineering construction period early warning method, device and medium
By establishing multi-level schedule baseline data and WBS decomposition units in hydropower projects, and combining resource input and network plan time difference analysis, hierarchical early warning information is generated and displayed on the BIM model. This solves the problem that traditional hydropower project construction schedule management cannot identify critical path delays and resource shortages, and achieves the improvement of dual-dimensional early warning and visualization.
Patent Information
- Application Number
- CN202611635622.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-22
- Publication Date
- 2026-11-20
AI Technical Summary
Traditional hydropower project construction progress management lacks a two-dimensional early warning system that combines network time difference and resource input, making it impossible to identify potential schedule risks caused by critical path delays and resource shortages. Furthermore, the visualization display cannot be adapted to the characteristics of different hydraulic structures.
By establishing multi-level schedule baseline data, binding WBS decomposition units and configuring baseline quantities, resource input parameters and network planning time parameters, collecting actual construction data for hierarchical aggregation, performing schedule deviation analysis in the dimensions of resource input and network planning time difference, generating hierarchical early warning information, and visually displaying it on the BIM model.
It achieves hierarchical early warning based on both resources and schedule, improving the comprehensiveness and accuracy of schedule risk identification, adapting to the visualization of different hydraulic structures, and providing intuitive risk location support.
Smart Images

Figure CN123140675A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of hydropower engineering construction progress management technology, and in particular to a BIM-based hydropower engineering schedule early warning method, equipment and medium. Background Technology
[0002] Hydropower projects, especially pumped storage power stations, long water diversion tunnels, and dam projects, are characterized by complex geological conditions, intersecting spatial structures, multiple construction work surfaces, long construction periods, and numerous participating units, making schedule management extremely difficult.
[0003] Traditional progress management relies on Gantt charts and network plans, and on regular manual reporting for progress comparison, which has problems such as data lag and biased analysis. Currently, BIM (Building Information Modeling) is usually associated with the construction schedule to form a 4D construction simulation for pre-construction scheme rehearsal and visual briefing, but the following defects still exist: (1) Single early warning logic: It only compares the planned and actual start and end times, without combining the network plan time difference analysis to analyze the impact of delays on the critical path and the total project duration, and cannot distinguish between "local delays that do not affect the total project duration" and "major delays that will cause project delays". (2) Lack of resource advance early warning: It only focuses on the project duration result and cannot identify potential project duration risks caused by insufficient investment of personnel and equipment resources in advance. (3) Fixed visualization form, which cannot adapt to the construction characteristics of different hydraulic structures. Linear tunnel excavation and layered dam filling are suitable for time-series growth display; multi-face parallel projects such as reservoir expansion excavation and inlet / outlet concrete are more suitable for status marking display, and the existing technology cannot distinguish between the two scenarios.
[0004] Therefore, there is an urgent need for a hydropower project schedule early warning solution that can combine network time difference and resource input for dual-dimensional early warning and adapt to different hydraulic structure BIM visualization modes, in order to solve the above-mentioned problems of existing technologies. Summary of the Invention
[0005] The purpose of this application is to provide a BIM-based method, equipment, and medium for early warning of hydropower project schedules, which can be adapted to the visualization of different hydraulic structures and realize a two-dimensional hierarchical early warning of resources and schedules during the construction process of hydropower projects.
[0006] To achieve the above objectives, this application provides the following solution: Firstly, this application provides a BIM-based method for early warning of the construction period of hydropower projects, the method comprising the following steps: Establish multi-level schedule baseline data for hydropower projects; the multi-level schedule baseline data is bound to WBS decomposition units, and each WBS decomposition unit is configured with baseline project quantities, baseline resource input parameters, and network planning time parameters.
[0007] Collect actual construction data of the WBS decomposition unit corresponding to the hydropower project construction site.
[0008] Based on the relationships between the WBS decomposition units, the actual construction data is hierarchically aggregated to obtain a dynamic progress dataset.
[0009] Based on the dynamic progress dataset and the multi-level progress benchmark data, progress deviation analysis is performed from the dimensions of resource input and network planning time difference to generate hierarchical early warning information.
[0010] Establish a mapping relationship between the WBS decomposition units and BIM model components. Based on the hierarchical early warning information and the mapping relationship, visualize the construction progress on the BIM model and locate the BIM model components corresponding to the early warning.
[0011] Optionally, the network planning time parameters include: total float time and free float time.
[0012] The schedule deviation analysis of the network plan time lag dimension includes: calculating the construction lag days of the WBS decomposition unit, comparing the lag days with the free float time and the total float time respectively, judging the impact of the deviation on the critical path and the total project duration, and outputting the schedule warning level.
[0013] Optionally, the number of lag days is calculated based on the amount of work completed; the construction period warning levels include: Low-level warning: If the number of lag days is less than or equal to the free float time, the critical path will not be changed and the overall project duration will not be affected.
[0014] Intermediate warning: The number of lag days is greater than the free float time but less than or equal to the total float time. The total float time is exhausted, and there is a risk of critical route shift.
[0015] Advanced warning: The number of lag days is greater than the total float time, affecting the total project duration.
[0016] Optionally, the progress deviation analysis of the resource input dimension includes: calculating the resource input rate of the WBS decomposition unit, and classifying the resource early warning level according to the relationship between the resource input rate and a preset threshold; the resource input rate is the ratio of the actual resource input amount to the baseline resource input amount.
[0017] Optionally, the visualization of the BIM model includes: a growth-style display mode and a state-based display mode.
[0018] The growth-based display mode includes: for hydraulic structures with a fixed time sequence, rendering and displaying the BIM model components corresponding to each WBS decomposition unit in sequence according to the construction time sequence and spatial progression order.
[0019] The status-based display mode includes: for hydraulic structures with multiple working faces under parallel construction, the overall geometric structure of the BIM model is fully preserved, and the construction status of each WBS decomposition unit is marked with different colors.
[0020] Optionally, the multi-level schedule baseline data includes: overall project schedule, annual schedule, monthly schedule, and weekly work plan; each level of schedule is linked through WBS coding, and the multi-level schedule baseline data is solidified after each level of schedule is approved online.
[0021] Optionally, the hierarchical aggregation rules for the actual construction data include: cumulative summation of the engineering quantity data along the hierarchy of the WBS decomposition unit; and taking the peak input amount of resource input data within the statistical period.
[0022] Optionally, the method further includes: generating an early warning ledger and pushing tiered early warning information; receiving on-site rectification feedback, updating the early warning status, and forming a closed-loop management process of early warning, rectification, and item clearance.
[0023] In a second aspect, this application provides a computer device, including: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the steps of the BIM-based hydropower project schedule early warning method described in the first aspect above.
[0024] Thirdly, this application provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the BIM-based hydropower project schedule early warning method described in the first aspect above.
[0025] According to the specific embodiments provided in this application, this application has the following technical effects: This application provides a BIM-based method, equipment, and medium for early warning of construction schedules in hydropower projects. First, it constructs multi-level schedule baseline data bound to Work Breakdown Structure (WBS) decomposition units. Each WBS decomposition unit is configured with baseline quantities, baseline resource input parameters, and network planning time parameters, providing a standardized multi-dimensional comparison benchmark for schedule comparison analysis and achieving unit-based binding management of schedule, resource, and network planning time parameter information. Second, it collects actual construction data from the corresponding WBS decomposition units at the construction site and aggregates the actual construction data hierarchically based on the relationships between WBS decomposition units to obtain a dynamic schedule dataset. This automatically completes the summary and processing of actual on-site data, achieving dynamic aggregation of actual construction progress, reducing the workload of manual summary processing, and improving work efficiency. Simultaneously, it conducts schedule deviation analysis from two dimensions: resource input and network planning time difference, generating tiered early warning information. This identifies risks at the resource input level and assesses the impact of schedule deviations in conjunction with network planning time differences, achieving tiered early warning from both resource and schedule dimensions, resulting in tiered warning results and improving the comprehensiveness and accuracy of schedule risk identification. Furthermore, by establishing a mapping relationship between WBS decomposition units and BIM model components, and combining hierarchical early warning information with this mapping relationship, the construction progress can be visualized on the BIM model, and the BIM model components corresponding to the early warning can be located. This establishes a data link between progress business data and the BIM model, enabling an intuitive display of construction progress and accurate location of the component parts where early warnings occur. It is also compatible with the visualization of different hydraulic structures, providing managers with intuitive risk location support. Attached Figure Description
[0026] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0027] Figure 1 An application environment diagram of a BIM-based hydropower project schedule early warning method provided in one embodiment of this application; Figure 2 A flowchart illustrating a BIM-based hydropower project schedule early warning method provided in one embodiment of this application; Figure 3 A complete flowchart illustrating each step of a BIM-based hydropower project schedule early warning method provided in an embodiment of this application; Figure 4 This is a visual illustration of a growth-style display mode provided in an embodiment of this application, wherein, Figure 4(a) in the diagram is a schematic diagram of the growth-based BIM progress display of a linear hydraulic structure. Figure 4 (b) is a schematic diagram of the growth-based BIM progress display for fill-type hydraulic structures; Figure 5 This is a visual illustration of a status-based display mode provided in an embodiment of this application, wherein, Figure 5 (a) in the diagram is a schematic diagram of the BIM model of the hydraulic structure before construction begins. Figure 5 (b) is a schematic diagram of the BIM model of the hydraulic structure in the completed construction state; Figure 6 This is a schematic diagram of the structure of a computer device provided in an embodiment of this application. Detailed Implementation
[0028] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0029] To make the above-mentioned objectives, features and advantages of this application more apparent and understandable, the application will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0030] The BIM-based hydropower project schedule early warning method provided in this application embodiment can be applied to, for example... Figure 1In the application environment shown, terminal 102 communicates with server 104 via a network. A data storage system can store the data that server 104 needs to process. The data storage system can be set up independently, integrated into server 104, or placed in the cloud or on another server. Terminal 102 can send the pending hydropower project construction-related data to server 104. After receiving the pending hydropower project construction-related data, server 104 establishes multi-level progress baseline data for the hydropower project. The multi-level progress baseline data is bound to WBS (Work Breakdown Structure) decomposition units, and each WBS decomposition unit is configured with baseline engineering quantities, baseline resource input parameters, and network planning time parameters. Actual construction data of the corresponding WBS decomposition units at the hydropower project construction site is collected. Based on the correlation between each WBS decomposition unit, the actual construction data is hierarchically aggregated to obtain a dynamic progress dataset. Based on the dynamic progress dataset and the multi-level progress baseline data, progress deviation analysis is performed from the resource input dimension and the network planning time difference dimension to generate hierarchical early warning information. A mapping relationship between the WBS decomposition units and BIM model components is established. According to the hierarchical early warning information and the mapping relationship, the construction progress is visualized on the BIM model and the BIM model components corresponding to the early warning are located. Server 104 can feed back the obtained hierarchical early warning information, construction progress visualization results, and early warning component location information to terminal 102. Furthermore, in some embodiments, the BIM-based hydropower project schedule early warning method can also be implemented independently by server 104 or terminal 102. For example, terminal 102 can directly perform hydropower project schedule early warning processing on the hydropower project construction-related data to be processed, or server 104 can obtain the hydropower project construction-related data to be processed from the data storage system and perform hydropower project schedule early warning processing on the hydropower project construction-related data to be processed.
[0031] The terminal 102 can be, but is not limited to, various desktop computers, laptops, smartphones, tablets, and IoT devices. The server 104 can be implemented using a standalone server or a server cluster consisting of multiple servers, or it can be a cloud server.
[0032] In one exemplary embodiment, such as Figure 2 As shown, a BIM-based method for early warning of construction schedules in hydropower projects is provided. This method is executed by computer equipment, specifically by a terminal or server alone, or by both a terminal and a server. In this embodiment, the method is applied to... Figure 1 Taking server 104 as an example, the following steps are included: S1: Establish multi-level schedule baseline data for hydropower projects; the multi-level schedule baseline data is bound to WBS decomposition units, and each WBS decomposition unit is configured with baseline project quantities, baseline resource input parameters, and network planning time parameters.
[0033] S2: Collect the actual construction data of the WBS decomposition unit corresponding to the hydropower project construction site.
[0034] S3: Based on the association relationship of each WBS decomposition unit, the actual construction data is hierarchically aggregated to obtain a dynamic progress dataset.
[0035] S4: Based on the dynamic progress dataset and the multi-level progress benchmark data, perform progress deviation analysis from the perspectives of resource input and network plan time difference, and generate hierarchical early warning information.
[0036] S5: Establish the mapping relationship between the WBS decomposition unit and the BIM model component. Based on the hierarchical early warning information and the mapping relationship, visualize the construction progress on the BIM model and locate the BIM model component corresponding to the early warning.
[0037] Implementing steps S1 to S5 not only enables unitized binding management of schedule, resource, and network planning time parameter information, but also allows for schedule deviation analysis and generation of tiered early warning information from two dimensions: resource input and network planning time difference, achieving tiered early warning for both resources and schedule. Furthermore, it enables visualization of construction progress on the BIM model, locating the BIM model components corresponding to the early warning, intuitively displaying the construction progress, adapting to the visualization of different hydraulic structures, and providing managers with intuitive risk location support.
[0038] As an optional implementation, in step S1, the multi-level schedule baseline data includes: the overall project schedule, the annual schedule, the monthly schedule, and the weekly work plan; the schedule plans at each level are linked through WBS coding, and after the schedule plans at each level are approved online, the multi-level schedule baseline data is solidified.
[0039] In this context, a WBS decomposition unit refers to a work unit formed by breaking down engineering tasks according to the work breakdown structure of a hydropower project. Each WBS decomposition unit has a unique WBS code. Multi-level schedule baseline data is bound to the WBS decomposition unit, and baseline quantities, baseline resource input parameters, and network planning time parameters are configured under each WBS decomposition unit. Actual construction data collected on the construction site is also associated with the corresponding WBS decomposition unit. Subsequent data aggregation, schedule deviation analysis, and mapping with BIM model components all use the WBS decomposition unit as the data link.
[0040] As an optional implementation, before establishing the multi-level progress baseline data for the hydropower project in step S1, a project progress information process classification library is pre-established. This project progress information process classification library is a resource library used to store different construction processes and the corresponding control resource types, serving as a configuration template for plan preparation. During the preparation of the project schedule plan, each WBS decomposition unit connects to the project progress information process classification library according to its corresponding construction process, retrieves the control resource types corresponding to that process, and then enters the corresponding project's baseline engineering quantity, baseline resource input parameters, and network planning time parameters to form an original schedule plan awaiting approval. After the original schedule plan is approved and solidified online, the multi-level progress baseline data can be obtained. This embodiment of the application provides standardized process-resource templates for WBS decomposition units through the project progress information process classification library, reducing the workload of manual entry of resource types during the plan preparation process and ensuring the uniformity of resource control items for the same type of process; then, combined with the actual business parameters of the project, multi-level progress baseline data is formed, taking into account both template standardization and project personalization.
[0041] As an optional implementation, in step S2, when collecting the actual construction data of the WBS decomposition units corresponding to the hydropower project construction site, the WBS decomposition units are used as data objects, and the actual construction data corresponding to each WBS decomposition unit at the hydropower project construction site is collected one-to-one. The actual construction data refers to the real business data generated during on-site construction, corresponding to the actual completed work volume and actual resource input of each WBS decomposition unit. Data collection can be achieved through on-site reporting, importing from external system interfaces, etc. The collected actual construction data is bound one-to-one with each WBS decomposition unit, ensuring that the data source for subsequent deviation analysis remains consistent with the statistical object of the benchmark data. By collecting the actual construction data of the construction site corresponding one-to-one with each WBS decomposition unit, the actual on-site business data can be matched with the multi-level progress benchmark data based on the same WBS decomposition unit, ensuring that the benchmark object for subsequent progress deviation analysis is consistent with the actual statistical object, providing a reliable original on-site data foundation for subsequent hierarchical aggregation and two-dimensional progress deviation analysis.
[0042] As an optional implementation, in step S3, the hierarchical aggregation rules of the actual construction data include: cumulative summation of the engineering quantity data along the hierarchy of the WBS decomposition unit; and taking the peak input amount of resource input data within the statistical period.
[0043] As an optional implementation, in step S1, the network planning time parameters include: total float time and free float time. In step S4, the schedule deviation analysis of the network planning time difference dimension includes: calculating the construction lag days of the WBS decomposition unit, comparing the lag days with the free float time and the total float time respectively, determining the impact of the deviation on the critical path and the total project duration, and outputting the schedule warning level.
[0044] As an optional implementation, the delay days are calculated based on the amount of work completed. The project schedule warning levels include the following three levels: (1) Low-level warning: When the number of lag days is less than or equal to the number of free float days, it is determined that the critical path will not be changed and the total project duration will not be affected.
[0045] (2) Intermediate warning: If the number of lagging days is greater than the free float time and less than or equal to the total float time, it is determined that the total float time is exhausted and there is a risk of critical path transfer.
[0046] (3) Advanced warning: If the number of lag days is greater than the total float time, it is determined that it will affect the total project duration.
[0047] As an optional implementation, in step S4, the progress deviation analysis of the resource input dimension includes: calculating the resource input rate (e.g., the resource input rate in terms of personnel or the resource input rate in terms of equipment) of the WBS decomposition unit, and classifying the resource warning level according to the relationship between the resource input rate and the preset threshold; the resource input rate is the ratio of the actual resource input amount to the baseline resource input amount.
[0048] As an optional implementation, the resource early warning level includes the following three warning levels: (1) Low-level warning: If the resource input rate is greater than or equal to the second preset threshold (e.g., 75%) and less than the first preset threshold (e.g., 100%), it is determined that it may not affect the completion of the work corresponding to the current WBS decomposition unit.
[0049] (2) Intermediate warning: If the resource input rate is greater than or equal to the third preset threshold (e.g., 50%) and less than the second preset threshold (e.g., 75%), it is determined that it may affect the completion of the work corresponding to the current WBS decomposition unit.
[0050] (3) Advanced warning: If the resource input rate is less than the third preset threshold (e.g., 50%), it is determined that it will definitely affect the completion of the work corresponding to the current WBS decomposition unit, such as affecting the total project duration.
[0051] As an optional implementation, in step S4, the generated hierarchical early warning information includes at least the early warning dimension, early warning level, and associated WBS decomposition unit identifier, and may also include: lag days, resource input rate, resource gap, deviation cause prompts, and impact assessment information on the critical path or total project duration.
[0052] As an optional implementation, in step S5, the visualization of the BIM model includes: a growth-based display mode and a state-based display mode. The growth-based display mode includes: for hydraulic structures with a fixed time sequence, rendering and displaying the BIM model components corresponding to each WBS decomposition unit sequentially according to the construction time sequence and spatial progression order. The state-based display mode includes: for hydraulic structures with multiple working faces under parallel construction, fully preserving the overall geometry of the BIM model and using different colors to mark the construction status of each WBS decomposition unit.
[0053] The BIM model is a 3D building information model corresponding to the hydropower project. The BIM model is broken down into several BIM model components, each corresponding to a different physical construction location within the hydropower project. By establishing a mapping relationship between WBS decomposition units and BIM model components, progress data and hierarchical early warning information obtained from the WBS decomposition units are transmitted to the BIM model. The BIM model can dynamically present the construction progress using either a growth-based or state-based display mode, and can locate the BIM model component that triggered the early warning based on the hierarchical early warning information.
[0054] As an optional implementation, the method further includes: generating an early warning ledger and pushing tiered early warning information; receiving on-site rectification feedback, updating the early warning status, and forming a closed-loop management process for early warning, rectification, and project cancellation. Specifically, after locating the BIM model component corresponding to the early warning on the BIM model, the BIM model component can be highlighted to distinguish it from model components without early warning; in response to operation commands, the tiered early warning information corresponding to the BIM model component can be retrieved, including the early warning dimension, early warning level, associated WBS decomposition unit identifier, and optional lag days, resource input rate, impact assessment on critical path and total project duration, etc. The early warning component identifier and tiered early warning information are associated and stored in the early warning ledger, and the early warning information is pushed to designated management personnel; when on-site rectification feedback confirms that the risk has been eliminated, the early warning highlighting mark of the BIM model component is removed, the early warning ledger status is updated, and the early warning is cancelled (i.e., the early warning is lifted), thereby realizing closed-loop management of hydropower project schedule early warning.
[0055] In an exemplary embodiment, to illustrate the technical solutions provided in the embodiments of this application in detail, the following are provided: Figure 3This paper presents a BIM-based method for early warning of construction schedules in hydropower projects. The method encompasses planned progress, execution progress, and visual progress. Planned progress includes milestone schedules, data additions or imports of overall, annual, monthly, and weekly plans for each section, and an online approval process. Once approved, these plans are assigned as tasks. Execution progress includes weekly, monthly, annual, and overall completion for each section, as well as milestone completion. It automatically collects actual on-site completion data, aggregates weekly completion data, and associates with assigned tasks to intelligently analyze the construction period and resource allocation. Visual progress refers to the dynamic display of the BIM model by linking data from planned and execution progress. WBS coding maps BIM model information to progress data, visually displaying the current execution progress and intuitively locating lagging components and related components. The method specifically includes the following steps: Step 1: Create a resource library.
[0056] In this embodiment of the application, a project progress information process classification library is established, such as: open excavation, tunnel excavation, concrete, and filling. Different processes are assigned to the types of resources to be controlled during the construction process. For example, tunnel excavation mainly controls the types of workers such as drillers and drivers, and the types of equipment such as hand drills and dump trucks. In the WBS coding, the process level is linked to the corresponding process in the project progress information process classification library.
[0057] Step 2: The planning and issuance stage includes the following steps: Step A1: Add or import the prepared schedule source file. The file types include milestone nodes, overall plan, annual plan and monthly plan. The schedule content includes construction content, start time, end time, planned duration, free float time and total float time.
[0058] Step A2: Complete the key information of the progress, including selecting the WBS code, filling in the planned quantity of the visual project, the planned quantity of the physical project, the types and quantities of personnel involved, and the models and quantities of equipment involved.
[0059] Step A3: Submit the online approval process. If approved, the task will be assigned as a planned task, and completion items will be automatically generated, using milestone nodes, overall plan, annual plan, and monthly plan data as benchmarks—that is, multi-level progress benchmark data for the hydropower project. If the approval fails, return to step A2 for modification.
[0060] Step A4: Filter the weekly work tasks from the monthly plan, including the amount of work and the number of personnel and equipment involved, and issue the weekly work tasks.
[0061] Step 3: Perform the data acquisition phase.
[0062] In this embodiment, the project department receives the work tasks for the week, fills in the construction completion status according to the construction content of different processes, including the completion amount of the image project, the completion amount of the physical project, the actual number of personnel of different types of work, and the actual number of equipment of different models, and generates weekly completion data.
[0063] Step 4: Automatic summary, including the following steps: Step B1: Weekly completion data is automatically updated to monthly completion data. The workload of the same process is automatically accumulated and summed based on the unique WBS code. For the same resource, the maximum weekly input is taken based on the unique WBS code.
[0064] Step B2: Monthly completed data is automatically updated to annual completed data, and the workload of the same process is automatically accumulated and summed based on the unique WBS code.
[0065] Step B3: Annual completed data is automatically updated to total completed data, and the workload of the same process is automatically accumulated and summed based on the unique WBS code.
[0066] For example, add a new data entry to the master plan submission document, and update the corresponding progress information, including: WBS codes for construction content, planned quantities for visual works, planned quantities for physical works, total float time, and free float time. Submit for approval, and upon approval, automatically generate a master completion data entry containing all planned data from the master plan.
[0067] Add a new data item for the annual plan submission document, and improve the progress information corresponding to the annual plan submission document data, including: WBS codes for construction content, planned quantities for visual works, and planned quantities for physical works. Submit for approval; upon approval, an annual completion data entry will be automatically generated, containing all planned data information from the annual plan.
[0068] Add a new monthly plan submission data item, and improve the progress information corresponding to the monthly plan submission data, including: WBS codes for construction content, planned quantities for visual works, planned quantities for physical works, planned quantities for key personnel, and planned quantities for key machinery and equipment. Submit for approval; upon approval, a monthly completion data entry will be automatically generated, containing all planned data information from the monthly plan.
[0069] In this embodiment of the application, work tasks within the planned period of the weekly plan are selected from the monthly plan, including the planned input of the main types of workers and the main mechanical equipment, and are issued as the work tasks for this period. After issuance, a data entry is automatically generated for the week, containing all the planned data information from the weekly plan.
[0070] In this embodiment of the application, the weekly completion data generated after the plan is issued includes the completion amount of the image project, the completion amount of the physical project, the actual amount of main workers involved, and the actual amount of main machinery and equipment involved, corresponding to the construction content.
[0071] Step 5: Early Warning. Generate tiered early warning information, including the following steps: Step C1: Compare the data approved in Step A3 as the baseline data. Automatically calculate the resource input rate based on the baseline resource input and the actual resource input in Step B1. The specific formula is: Resource Input Rate = Actual Resource Input / Baseline Resource Input. Trigger a resource alert based on the calculated resource input rate. If the resource input rate ≥ 1, the input is sufficient, and no resource alert is triggered. If the resource input rate < 1, the input is insufficient, and a resource alert is triggered. Resource alert levels are divided into three levels: low alert, medium alert, and high alert. The criteria for a low alert are: 75% ≤ personnel input or equipment input < 100%; the criteria for a medium alert are: 50% ≤ personnel input or equipment input < 75%; and the criteria for a high alert are: personnel input or equipment input < 50%.
[0072] Step C2: Compare the data approved in Step A3 as the baseline data. Automatically calculate the lag days based on the planned data and the actual data from Step B3. The lag days are calculated based on the actual project volume, using the formula: Lag Days = Planned Duration × (Completed Quantity / Planned Quantity) - Actual Duration. A schedule warning is triggered based on the lag days. If the lag days ≥ 0, the schedule is normal, and no warning is triggered. If the lag days < 0, the schedule is abnormal, and a warning is triggered. Schedule warnings are categorized into three levels: low, medium, and high. The criteria for a low-level warning are: lag days ≤ free float time; for a medium-level warning, free float time < lag days ≤ total float time; and for a high-level warning, lag days > total float time.
[0073] In this embodiment of the application, based on the uniqueness of the WBS code, the weekly completion data is automatically accumulated to the monthly completion data, the monthly completion data is automatically accumulated to the annual completion data after the monthly completion data is updated, and the annual completion data is automatically accumulated to the total completion data after the annual completion data is updated. After the completion data is updated, the number of days of lag is automatically calculated by comparing it with the planned data. The planned amount of resource input for each month is compared with the actual planned amount of resource input to provide resource warnings. The number of days of lag in the total completion data is compared with the free float time and the total float time to provide schedule warnings.
[0074] Total float, also known as total slack, refers to the maximum time that this work can be delayed without affecting the overall project duration. The calculation formula is as follows: TF = LS - ES = LF - EF; Wherein, TF represents total float time, LS represents latest start time, which is the latest time that the work must start without delaying the overall project schedule; ES represents earliest start time, which is the earliest time that the work can start; LF represents latest finish time, which is the latest time that the work must finish without delaying the overall project schedule; and EF represents earliest finish time, which is the earliest time that the work can finish.
[0075] Free float, also known as free time difference, represents the maximum time a task can be delayed without affecting the earliest start time of its successor tasks. The formula for calculating free float is: FF=minES JH -EF Now ; Where FF represents free float time; minES JH The minimum value representing the earliest start time of the immediately following work; EF Now Indicates the earliest completion time.
[0076] In this embodiment, the classification of project schedule warning levels depends on the comparison between the number of lag days and the total free float. The classification of resource warning levels depends on the comparison between the resource input rate and a preset threshold. Different colors can be used to represent different warning levels; for example, both project schedule warnings and resource warnings are classified into yellow (low-level warning), orange (medium-level warning), and red (high-level warning).
[0077] Table 1 shows the different levels of schedule warnings, the number of lag days, and the resulting changes. The yellow level (low-level warning) indicates that during project implementation, non-critical tasks experienced delays, resource adjustments, and minor tweaks to operational logic, but the critical path remained unchanged. The orange level (medium-level warning) indicates that factors such as process schedule deviations, resource shortages, and changes in construction plans have exhausted the total float of one or more original non-critical paths, creating a new secondary critical path, and the critical path may change. The red level (high-level warning) indicates that due to major design changes, large-scale resource shortages, force majeure, or severe delays in preceding processes, the original critical path of the project has been completely replaced, disappeared, or globally restructured. In this case, a new critical path will emerge, and the original critical path is no longer the only critical path.
[0078] Table 1. Different levels of project schedule warning, number of days of delay, and resulting changes.
[0079] The critical path refers to the path that connects all the longest-running activities from the start to the end of a project. If any link in the critical path is delayed, the completion time of the entire project will be postponed.
[0080] Table 2 shows the different resource warning levels, resource input rates, and the resulting changes. In the resource warning system, the yellow level (low warning) indicates insufficient resource input but high resource efficiency, which may not affect work completion; in this case, only resource warning needs to be monitored. The orange level (medium warning) indicates insufficient resource input with normal efficiency, which may affect work completion; in this case, a level warning reminder is issued. The red level (high warning) indicates insufficient resource input with normal or low efficiency, which will definitely affect work completion; in this case, increased resources are required.
[0081] Table 2. Resource warning levels, resource input rates, and resulting changes at different levels.
[0082] Step C3: The early warning data triggered by steps C1 and C2 automatically generates an early warning ledger and pushes it to the designated management personnel.
[0083] Step C4: After receiving the warning message, the designated administrator shall rectify and respond to the content and propose measures to lift the warning.
[0084] Step 6: BIM visualization, including the following steps: Step D1: Map the unique WBS code of the building process data source and the component attribute code of the BIM model to establish the mapping relationship between the two, and retrieve the value from step B3 to dynamically display the BIM model of the construction progress.
[0085] Step D2: The visualization display mode is divided into growth display mode and status display mode according to the characteristics of the building. In the growth display mode, the building process has a fixed construction sequence according to the construction plan. For example, in the excavation of a single tunnel, different colors are used to dynamically display the components of the constructed part from the tunnel entrance to the tunnel. In the status display mode, the building process has no specific construction sequence. Different colors are used to distinguish the construction status of not started, under construction or completed according to the completion ratio.
[0086] Step D3: Based on the WBS codes in the early warning log, intuitively locate the BIM model components corresponding to the building processes that are lagging behind in progress.
[0087] In this embodiment, the BIM model takes values from the total completed data and dynamically displays the completion status using either a growth-based display mode or a state-based display mode, based on the building characteristics, as detailed below: Growth-based display mode: Based on the WBS decomposition structure, the BIM model is divided into multiple construction units. According to the predetermined construction sequence and spatial progression, each construction unit gradually appears or disappears. For example, it can simulate the dynamic growth process of excavation from the tunnel entrance to the tunnel body, or the dynamic growth process of dam filling from the dam foundation to the dam top.
[0088] Status-based display mode: The BIM model is divided into multiple construction units according to the WBS decomposition structure. The overall BIM model is displayed throughout the process. Three different colors are used to mark the three progress stages of each construction unit: not started, under construction, and completed, so as to intuitively present the construction progress of each component.
[0089] Figure 4 This is a visual illustration of the growth-based display mode, in which... Figure 4 (a) in the diagram is a growth-based BIM progress display of linear hydraulic structures (such as tunnels and corridors), showing the excavation progress of the ventilation and safety tunnel and the pilot tunnel in the crown arch. Figure 4 (b) in the diagram is a schematic diagram of the growth-type BIM progress display for embankment-type hydraulic structures (such as dams and slopes). The BIM model is divided into multiple construction units according to the WBS decomposition structure. Each construction unit is gradually revealed in sequence according to the predetermined construction timeline and spatial progression, simulating the dynamic growth process of the project from scratch.
[0090] Figure 5 This is a visual representation of the state-based display mode, in which... Figure 5 (a) in the diagram is a schematic diagram of the BIM model of the hydraulic structure before construction begins. Figure 5 (b) is a schematic diagram of the BIM model of the hydraulic structure in the completed construction state. Different colors are used to mark the progress status of each construction unit, such as not started and completed, to intuitively present the construction progress of each component.
[0091] Currently, traditional early warning methods require comparing all items using fixed thresholds and lag days. For example, a 10-day lag corresponds to a yellow warning, a 20-day lag to an orange warning, and a 30-day lag to a red warning. However, in this application's embodiment, different items have different comparison thresholds, which are related to whether they are critical path operations or their immediate predecessors or successors. These thresholds are automatically calculated from the schedule file, not manually set. For example, the excavation of the first floor of a factory building has a free float time and total float time of 0, with a lag of 5 days. According to traditional early warning rules, this would be a yellow warning; according to the early warning rules of this application's embodiment, it would be a red warning. For example, the concrete pouring of a diversion tunnel has a free float time of 10 days, a total float time of 40 days, and a lag of 35 days. Traditional early warning rules would be a red warning; however, the early warning rules of this application's embodiment would be an orange warning.
[0092] This application provides a BIM-based method, equipment, and medium for early warning of hydropower project schedules, which has the following technical advantages: (1) Achieve multi-level, full-cycle closed-loop management of planning and execution: Support the addition, import, approval and issuance of multi-level progress baseline data from milestones, overall plans to annual plans, monthly plans and weekly plans, forming a complete progress management chain; Through weekly completion data updates and automatic accumulation of monthly completion, annual completion and total completion data, realize dynamic tracking and automatic updates of execution progress.
[0093] (2) Intelligent Analysis and Early Warning: Automatically compares planned quantities with actual completed quantities and intelligently calculates lag days. Provides resource early warning: Compares the baseline resource input (personnel types, machinery and equipment, etc.) with the actual resource input, and triggers an early warning when resources are insufficient. Provides schedule early warning: Compares the lag days of the progress information of a single construction item in the total completion with the free float time and total float time of the construction item, and intelligently judges the degree of impact on the critical path.
[0094] (3) BIM Model Visualization Decision Support Based on WBS Coding: By accurately mapping BIM model information with progress data through WBS coding, information silos are broken down. Two modes, growth-based display mode and status-based display mode, are used to visualize the construction progress, dynamically and intuitively showing the completion status of the project. It can also accurately locate components with delayed progress and related components, providing managers with clear and intuitive decision-making basis, overcoming the shortcomings of traditional visualization and decision support.
[0095] (4) Improve the timeliness and accuracy of early warnings: By automatically collecting actual on-site completion data and linking it with weekly, monthly, annual, and overall plan data, timely early warnings are achieved, solving the problem of lag caused by post-event summarization in traditional methods. The calculation of the number of days of lag in the construction period early warning is combined with the characteristics of the building, and the calculation is based on the quantity of visual works, which improves the accuracy of the calculation results. The early warning results are specific to the number of days of lag, resource gaps, and specific components, which improves the precision and practicality of the early warning results.
[0096] In one exemplary embodiment, a computer device is provided, which may be a server or a terminal, and its internal structure diagram may be as follows. Figure 6As shown, the computer device includes a processor, memory, input / output (I / O) interfaces, and a communication interface. The processor, memory, and I / O interfaces are connected via a system bus, and the communication interface is also connected to the system bus via the I / O interfaces. The processor provides computational and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system, computer programs, and a database. The internal memory provides the environment for the operating system and computer programs in the non-volatile storage media to run. The database stores construction-related data for hydropower projects. The I / O interfaces are used for information exchange between the processor and external devices. The communication interface is used for communication with external terminals via a network connection. When the computer program is executed by the processor, it implements a BIM-based hydropower project schedule early warning method.
[0097] Figure 6 The structure shown is merely a block diagram of a portion of the structure related to the present application and does not constitute a limitation on the computer device to which the present application is applied. Specific computer devices may include more or fewer components than those shown in the figure, or combine certain components, or have different component arrangements.
[0098] In one exemplary embodiment, a computer-readable storage medium is provided storing a computer program that, when executed by a processor, implements the steps in the above-described method embodiments.
[0099] In one exemplary embodiment, a computer program product is provided, including a computer program that, when executed by a processor, implements the steps in the above-described method embodiments.
[0100] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, data stored, data displayed, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of related data must comply with relevant regulations and be authorized by the owner of the corresponding device.
[0101] Those skilled in the art will understand that all or part of the processes in the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium. When executed, the computer program can include the processes of the embodiments described above. Any references to memory, databases, or other media used in the embodiments provided in this application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM).
[0102] The databases involved in the embodiments provided in this application may include at least one type of relational database and non-relational database. Non-relational databases may include, but are not limited to, blockchain-based distributed databases. The processors involved in the embodiments provided in this application may be general-purpose processors, central processing units, graphics processing units, digital signal processors, programmable logic devices, quantum computing-based data processing logic devices, etc., and are not limited to these.
[0103] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0104] This document uses specific examples to illustrate the principles and implementation methods of this application. The descriptions of the above embodiments are only for the purpose of helping to understand the methods and core ideas of this application. Furthermore, those skilled in the art will recognize that, based on the ideas of this application, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this application.
Claims
1. A BIM-based method for early warning of construction period in hydropower projects, characterized in that, The method includes: Establish multi-level schedule baseline data for hydropower projects; the multi-level schedule baseline data is bound to WBS decomposition units, and each WBS decomposition unit is configured with baseline project quantities, baseline resource input parameters, and network planning time parameters; Collect actual construction data of the WBS decomposition unit corresponding to the hydropower project construction site; Based on the correlation between each WBS decomposition unit, the actual construction data is hierarchically aggregated to obtain a dynamic progress dataset. Based on the dynamic progress dataset and the multi-level progress baseline data, progress deviation analysis is performed from the dimensions of resource input and network plan time difference to generate hierarchical early warning information. Establish a mapping relationship between the WBS decomposition units and BIM model components. Based on the hierarchical early warning information and the mapping relationship, visualize the construction progress on the BIM model and locate the BIM model components corresponding to the early warning.
2. The BIM-based hydropower project schedule early warning method according to claim 1, characterized in that, The network planning time parameters include: total float time and free float time; The schedule deviation analysis of the network plan time lag dimension includes: calculating the construction lag days of the WBS decomposition unit, comparing the lag days with the free float time and the total float time respectively, judging the impact of the deviation on the critical path and the total project duration, and outputting the schedule warning level.
3. The BIM-based hydropower project schedule early warning method according to claim 2, characterized in that, The number of days of delay is calculated based on the amount of visual engineering work; The project schedule early warning levels include: Low-level warning: If the number of lag days is less than or equal to the free float time, the critical path will not be changed and the overall project duration will not be affected; Intermediate warning: The number of lag days is greater than the free float time and less than or equal to the total float time. The total float time is exhausted, and there is a risk of critical route shift. Advanced warning: The number of lag days is greater than the total float time, affecting the total project duration.
4. The BIM-based hydropower project schedule early warning method according to claim 1, characterized in that, The progress deviation analysis of the resource input dimension includes: calculating the resource input rate of the WBS decomposition unit, and classifying the resource early warning level according to the relationship between the resource input rate and the preset threshold; the resource input rate is the ratio of the actual resource input amount to the baseline resource input amount.
5. The BIM-based hydropower project schedule early warning method according to claim 1, characterized in that, The visualization of the BIM model includes: a growth-based display mode and a state-based display mode; The growth-style display mode includes: for hydraulic structures with a fixed time sequence, rendering and displaying the BIM model components corresponding to each WBS decomposition unit in sequence according to the construction time sequence and spatial advancement order; The status-based display mode includes: for hydraulic structures with multiple working faces under parallel construction, the overall geometric structure of the BIM model is fully preserved, and the construction status of each WBS decomposition unit is marked with different colors.
6. The BIM-based hydropower project schedule early warning method according to claim 1, characterized in that, The multi-level progress baseline data includes: overall project schedule, annual schedule, monthly schedule, and weekly work plan; each level of schedule is linked through WBS coding, and the multi-level progress baseline data is solidified after each level of schedule is approved online.
7. The BIM-based hydropower project schedule early warning method according to claim 1, characterized in that, The hierarchical aggregation rules for the actual construction data include: cumulative summation of engineering quantity data along the hierarchy of the WBS decomposition unit; and taking the peak input amount of resource input data within the statistical period.
8. The BIM-based hydropower project schedule early warning method according to claim 1, characterized in that, The method also includes: generating an early warning ledger and pushing tiered early warning information; receiving on-site rectification feedback, updating the early warning status, and forming a closed-loop management process of early warning, rectification and item clearance.
9. A computer device, comprising: A memory, a processor, and a computer program stored in the memory and capable of running on the processor, characterized in that the processor executes the computer program to implement the BIM-based hydropower project schedule early warning method according to any one of claims 1-8.
10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by the processor, it implements the BIM-based hydropower project schedule early warning method as described in any one of claims 1-8.