A method for tracing causes and deducing paths of rush construction of water conservancy and hydropower projects
By quantitatively analyzing and calibrating the inverse dissipation of multi-dimensional engineering monitoring data, a precise expedited construction path plan was generated, which solved the problems of unclear causes and unidentified hidden losses in the expedited construction plan of water conservancy and hydropower projects, and improved the accuracy of predicting and implementing the expedited construction effect.
Patent Information
- Application Number
- CN202611368415.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-04
- Publication Date
- 2026-11-20
AI Technical Summary
Existing plans for expediting water conservancy and hydropower projects lack precise causal analysis, leading to inappropriate selection of measures and an inability to effectively identify and eliminate hidden losses from interventions, resulting in poor expediting outcomes.
By unifying and quantitatively analyzing multi-dimensional engineering monitoring data, and combining the discrimination values of four dimensions—progress control, resource supply, environmental constraints, and organizational implementation—an initial expedited construction path plan is generated. Then, through reverse dissipation calibration, the implicit losses of intervention are corrected layer by layer, and the final expedited construction path plan is output.
It achieves a precise correspondence between expedited work measures and their causes, identifies and corrects the hidden losses of expedited work interventions, generates more realistic expedited work path solutions, and improves the accuracy of predicting expedited work effects and the efficiency of implementation.
Smart Images

Figure CN123140706A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of construction management technology for water conservancy and hydropower projects, and in particular to a method for tracing the causes and proving the path of rushed construction in water conservancy and hydropower projects. Background Technology
[0002] Water conservancy and hydropower projects are characterized by large construction scale, long construction period, many participating entities, and complex environmental constraints. Construction progress control is always the core link of project management. During the implementation of the project, the actual progress often deviates from the planned progress due to the intertwined influence of multiple factors such as changes in meteorology and hydrology, abnormal geological conditions, fluctuations in resource supply, and adjustments to construction organization, thus creating a need for expedited construction. Faced with the need for expedited work, existing technologies typically follow a forward optimization approach. In the cause assessment phase, project managers retrieve the planned and actual progress curves from the progress management system, comparing the difference in workload at each time point. Based on the magnitude of the lag, they directly determine the strength of the expedited work effort. However, while factors such as fluctuations in resource supply, environmental constraints, and inefficient construction organization objectively exist in the project data, they are not included in the quantitative analysis. Managers cannot determine whether the schedule delay stems from insufficient resources, environmental interference, or organizational inefficiency. Therefore, the selection of expedited work measures lacks precise causal targeting, and the interventions applied fail to address the root cause of the problem. In the solution formulation phase, managers start by increasing personnel... Several measures are selected from conventional methods such as equipment investment, reducing the time of non-critical processes, and expanding the scope of cross-operations to form a rush-work plan and put it into practice. In this process, the industry assumes that the effect of rush-work intervention is linearly additive, that is, the more resources invested and the more processes compressed, the more significant the shortening of the construction period. The plan design only focuses on the cumulative effect of positive intervention, without considering the reverse losses generated by the intervention itself during the implementation process. Excessive concentration of resources leads to personnel fatigue and reduced efficiency and equipment failure. Excessive compression of processes leads to process connection conflicts and quality risks. Excessive cross-operation scope causes mutual interference between work surfaces. These hidden losses continuously offset the actual effect of rush-work intervention, but have never been included in the verification and correction of the plan.
[0003] The shortcomings of the above two aspects cause existing rush-work schemes to often become disconnected from the actual causes, and the side effects of the schemes themselves are not identified and eliminated, making it difficult to achieve the expected results in rush-work. There is an urgent need for a rush-work path deduction method that can achieve accurate source tracing of multi-dimensional causes and quantitatively correct the losses of rush-work intervention itself. To this end, we propose a method for source tracing and path deduction of rush-work causes in water conservancy and hydropower projects. Summary of the Invention
[0004] To address the aforementioned problems in existing technologies, the present invention aims to provide a method for tracing the causes and proposing pathways for accelerated construction in water conservancy and hydropower projects. This method achieves accurate tracing of the causes of accelerated construction through unified quantitative analysis of multi-dimensional engineering monitoring data, and quantifies and corrects the implicit losses of accelerated construction interventions layer by layer through reverse dissipation calibration, thereby generating a feasible accelerated construction pathway plan.
[0005] To solve the above problems, the technical solution adopted by the present invention is as follows: A method for tracing the causes and proving the path of rushed construction in water conservancy and hydropower projects, the steps of which are as follows: Collect multi-dimensional engineering monitoring data of the target water conservancy and hydropower project. The multi-dimensional engineering monitoring data covers the dimensions of progress control, resource supply, environmental constraints, and organization and implementation. Quantitative analysis was conducted on the engineering monitoring data of each dimension to obtain the corresponding judgment values for schedule deviation, resource allocation, environmental conditions, and construction organization. The comprehensive cause discrimination index is calculated by integrating four types of discrimination values. The corresponding expediting measures are matched by combining the contribution ratio of each dimension to the expediting demand. The initial expediting path plan is formed by logically assembling the construction procedures. The initial expedited work path plan is subjected to reverse dissipation calibration. During the calibration process, the degree of secondary deviation caused by the implementation of the plan is first calculated from the overall level. Then, the actual dissipation level of the expedited work intervention is deduced step by step and the overall deviation calculation result is corrected. When the dissipation of a single process is deduced, it is further refined to the work execution unit. The dissipation calculation result of a single process is corrected by combining the continuous operation loss of personnel and equipment. After the layer-by-layer correction, the final expedited work path plan is output. The comprehensive cause discrimination index is compared with the preset dual threshold decision range. Based on the comparison results, the level of expedited work demand is divided, the corresponding control response is triggered, and the final expedited work path plan is output.
[0006] Preferably, the collection and classification of multi-dimensional engineering monitoring data shall be carried out in the following manner: It connects to four types of data interfaces of the target project: progress management system, resource management system, environmental monitoring system, and construction management system, to collect all original project data; The data is categorized and collected based on the business characteristics it carries. Data that carries time nodes and project completion characteristics are categorized into the progress control dimension; data that carries personnel allocation, material supply, and equipment scheduling characteristics are categorized into the resource supply dimension; data that carries meteorological, hydrological, geological conditions, and policy control characteristics are categorized into the environmental constraints dimension; and data that carries process arrangement, team scheduling, and on-site management characteristics are categorized into the organization and implementation dimension.
[0007] Preferably, the schedule deviation judgment value is calculated based on the time-series data of the schedule control dimension: Extract the planned schedule time series, actual schedule time series, and the baseline schedule threshold for the corresponding work period from the schedule control dimension data; The difference in the amount of work at adjacent time nodes is calculated to generate a sequence of deviation change rates. Combined with the baseline progress threshold, the cumulative absolute value of the deviation and the duration of the deviation are statistically analyzed. After the deviation duration is compounded, it is mapped to a standardized numerical range of zero to one, and the progress deviation discrimination value is output.
[0008] Preferably, the resource allocation discriminant value is generated through a weighted fusion of multiple indicators: Extract the on-duty personnel, material inventory, equipment usage and corresponding timestamp sequences for each time node from the resource supply data. Calculate the resource allocation adjustment speed for each dimension by calculating the difference between adjacent nodes, and sum the total resource allocation adjustment range within the complete cycle. The resource allocation change trajectory curve is fitted and its fluctuation curvature is calculated. The three indicators of allocation adjustment speed, total adjustment amplitude and fluctuation curvature are weighted and integrated to obtain the resource allocation discriminant value.
[0009] Preferably, the environmental condition discrimination value is calculated by combining the spatial coverage and temporal duration characteristics of the disturbance: Multiple environmental interference areas within the construction scope are identified from the environmental constraint dimension data. The scope of construction procedures covered by each area is statistically analyzed and the proportion of its affected area to the total construction area is calculated. A sequence of regional directional changes is generated by combining the duration of the interference. Based on the fluctuation degree of the regional directional change sequence, the environmental condition discrimination value is output by weighting two indicators: the proportion of affected area and the duration of interference.
[0010] Preferably, the calculation of the construction organization discriminant value incorporates the characteristics of process form and matching degree: Extract boundary node information and process category information of each construction process from the data of the organization and implementation dimension, calculate the proportion of process connection time to total process time, and calculate the height of the construction organization center of gravity control node by combining the coordinates of the critical path node; The process matching similarity is obtained by comparing with the preset standard process library. The three indicators of connection time ratio, control node height and matching similarity are weighted and integrated to obtain the construction organization discrimination value.
[0011] Preferably, the calculation of the comprehensive cause discrimination index and the generation of the initial rush work path plan are performed in the following manner: Based on the numerical ranges of the schedule deviation judgment value, resource allocation judgment value, environmental condition judgment value, and construction organization judgment value, corresponding weight coefficients are matched respectively. Obtain the working condition compensation coefficient for the current construction stage of the project; The four types of discrimination values are multiplied by their corresponding weight coefficients and summed, then multiplied by the working condition compensation coefficient to obtain the comprehensive cause discrimination index. Calculate the proportion of the four types of discriminant values in the comprehensive causal discriminant index to determine the contribution proportion of each dimension of the cause; Based on the contribution ratio, the corresponding expediting measure units are matched from the preset expediting measure library, and then assembled according to the sequential logic of the construction process to generate an initial expediting path plan.
[0012] Preferably, the calculation of secondary bias at the global level in reverse dissipation calibration is performed in the following manner: The initial expedited construction plan was broken down by time nodes and converted into a virtual construction progress sequence consistent with the dimensions of multi-dimensional engineering monitoring data. Extract resource overlay features, process compression features, and cross-operation features from the virtual construction progress sequence, and generate virtual resource configuration parameters, virtual construction organization parameters, and virtual progress deviation parameters respectively. Using the same quantitative rules as the causal tracing stage, virtual parameters were used to replace measured data to calculate the secondary schedule deviation judgment value, secondary resource allocation judgment value, and secondary construction organization judgment value, respectively. The weighted summation of the three types of secondary discrimination values yields the overall secondary deviation verification value.
[0013] Preferably, in the process of calculating the overall secondary deviation verification value, the dissipation level of the rush intervention is decomposed and deduced step by step in the following manner: The virtual construction progress sequence is divided into multiple independent expedited construction units according to the logical boundaries of the construction process; For each expedited work unit, the expedited intervention intensity parameter and the time compression range parameter within that unit are extracted. Using the ideal time compression amount under no dissipation state as a benchmark, the proportion of the expedited intervention effect attenuating with the implementation process is deduced in reverse using the calculation logic of the deviation change rate sequence, and the single-process intervention dissipation coefficient is obtained. The intervention dissipation coefficients of all process rush units are collected into an intervention dissipation coefficient set according to the process sequence. This set is then substituted into the calculation process of the overall secondary deviation verification value. The values are multiplied by the corresponding dimensions of the three types of secondary discriminant values to complete the initial correction of the three types of secondary discriminant values.
[0014] Preferably, in the derivation of the dissipation coefficient of a single process intervention, the fatigue attenuation calibration and iterative correction down to the work execution unit are performed in the following manner: Based on the division of work teams and equipment sets, a single process expediting unit is broken down into multiple work execution units; For each work execution unit, extract the parameters of continuous working time of personnel, continuous working time of equipment, and work intensity within the unit. Using the benchmark work efficiency under standard work intensity as a reference, the calculation logic of deviation time composite operation is used to reverse map the efficiency decay ratio within the unit work time to obtain the fatigue decay coefficient of a single work unit. The fatigue attenuation coefficients of all work execution units are collected into a fatigue attenuation coefficient set according to their respective processes. This set is then substituted into the calculation process of the single process intervention dissipation coefficient, and the intervention dissipation coefficient of the corresponding process is corrected unit by unit. The intervention dissipation coefficient, after being corrected at the work execution unit level, is substituted into the overall deviation calculation process to complete the second correction of the overall secondary deviation verification value. If the corrected overall secondary deviation verification value is lower than the preset secondary deviation threshold, the current initial rushing path plan is determined as the final rushing path plan. If it is higher than the preset secondary deviation threshold, the resource input intensity, process compression range, and cross-operation range of the initial rushing path plan are adjusted according to the contribution ratio of the three types of secondary discrimination values after correction, and the reverse dissipation calibration process is re-executed until the threshold requirements are met.
[0015] Compared with the prior art, the beneficial effects of the present invention are as follows: The system integrates data interfaces from four systems: progress management, resource management, environmental monitoring, and construction management. It collects all raw project data and categorizes it into four dimensions—progress control, resource supply, environmental constraints, and organizational implementation—based on the business characteristics of the data. Quantitative analysis is performed on the data for each dimension to obtain four types of discriminant values. These four discriminant values are then combined to calculate a comprehensive causal discrimination index and determine the contribution percentage of each dimension. Through this process, the determination of the causes of expedited work no longer relies solely on the lag in the progress curve but can pinpoint the root cause of the problem from four dimensions. This ensures a precise correspondence between the selected expedited work measures and the actual causes, allowing interventions to target the root of the problem. Secondly, the initial expedited work path plan is broken down and converted into a virtual construction progress sequence according to time nodes. The system extracts three types of features: resource overlay, process compression, and cross-operation, and generates virtual parameters. Using the same quantitative rules as the cause tracing stage, it calculates three types of discrimination values: secondary schedule deviation, secondary resource allocation, and secondary construction organization, thereby obtaining the overall secondary deviation verification value. Based on this, the intervention dissipation coefficient is decomposed and deduced for each process, and the overall deviation calculation is corrected. When deducing for a single process, it is further refined to the work execution unit mapping fatigue attenuation coefficient and the process dissipation calculation is corrected. After layer-by-layer correction and iteration, the final expedited construction path scheme is output. Through this process, the implicit losses of the expedited construction intervention itself are incorporated into the scheme verification stage. The scheme completes the identification and correction of its own side effects before output, and the output expedited construction path scheme is more in line with the actual project. The overall deviation calculation is gradually broken down to the process unit and the operation execution unit. The inner calculation results are fed back up layer by layer, and the specific links where dissipation occurs can be located, so that the scheme adjustment has a clear direction. The reverse calculation at each level follows the quantitative rules of the cause tracing stage, and the forward analysis and reverse calibration share the same set of measurement standards, so that the quantitative caliber of the whole process remains consistent. Attached Figure Description
[0016] Figure 1 This is an overall structural diagram of the present invention; Figure 2 This is a flowchart of the multi-dimensional quantization analysis of four types of discriminant values in this invention. Detailed Implementation
[0017] The present invention will be further described below with reference to specific embodiments.
[0018] This application provides a method for tracing the causes and proposing pathways for accelerated construction in water conservancy and hydropower projects. It achieves accurate tracing of the causes of accelerated construction through unified quantitative analysis of multi-dimensional engineering monitoring data, and quantifies and corrects the implicit losses of accelerated construction intervention layer by layer through reverse dissipation calibration, generating an accelerated construction pathway plan that is practically feasible.
[0019] The present invention will be further described below with reference to specific embodiments. The embodiments described herein are only for explaining the present invention and are not intended to limit the scope of protection of the present invention. Taking the main concrete pouring stage of a water conservancy project as an example, due to the combined effects of the early flood season and local seepage of the upstream cofferdam, the progress of the main concrete pouring is significantly delayed compared to the plan. The goal of catching up is to control the delayed construction period within the controllable range stipulated in the contract. The method is mainly divided into five stages: the first stage completes the collection and classification of multi-dimensional engineering monitoring data; the second stage completes the multi-dimensional quantitative analysis of four types of discrimination values; the third stage completes the comprehensive analysis. The process involves calculating causal identification indicators and making dual-threshold decisions for expedited work levels. The fourth stage generates the initial expedited work path plan and performs reverse dissipation calibration. The fifth stage outputs the final expedited work path plan. Among these, reverse dissipation calibration is the core, quantifying and reversing the efficiency decay caused by factors such as personnel fatigue, equipment wear and tear, and process conflicts in the expedited work intervention. It adopts a three-layer nested architecture from the outside to the inside, which includes overall secondary deviation verification, process-level intervention dissipation deduction, and work unit-level fatigue decay mapping. The inner layer results are fed back upwards layer by layer to correct the outer layer calculations, and the reverse calculations at each level reuse the same source quantification rules from the causal tracing stage.
[0020] The first phase, encompassing multiple dimensions, specifically covers four aspects: progress control, resource supply, environmental constraints, and organizational implementation. These four dimensions comprehensively depict the construction status of water conservancy and hydropower projects from four perspectives: progress results, resource input, external conditions, and organizational methods. The progress control dimension reflects the status of progress deviations; the resource supply dimension reflects the sufficiency of human, material, and equipment input; the environmental constraints dimension reflects the degree of interference from uncontrollable external conditions; and the organizational implementation dimension reflects the rationality of on-site management and work process arrangement. The data collection process is achieved through the Enterprise Service Bus, which connects to four types of data interfaces deployed in the project: progress management system, resource management system, environmental monitoring system, and construction management system. The Enterprise Service Bus acts as middleware to achieve data format conversion and protocol adaptation between different systems, avoiding direct interoperability issues caused by differences in database types, interface protocols, and data field definitions. The data retrieval cycle is set to automatically collect all original project data from the previous day at midnight every day. The midnight time slot is chosen because the data for the day has been entered into each business system and the system load is low at this time, so the retrieval process will not affect the normal operation of the business systems. The progress management system stores the network diagrams of each sub-project and the planned and actual cumulative completed work volume of each statistical node. The network diagrams are stored in the form of double-symbol network diagrams, storing the logical relationships and time parameters between each process. The resource management system stores the attendance and on-duty quantity of personnel for each type of work, the batches of various materials entering the site and the on-site inventory, the number of sets of various construction equipment put into use and the operating hours. Personnel attendance is automatically collected through the access control system and on-site time clocks, and equipment operating hours are automatically collected through remote monitoring terminals installed on the equipment. The environmental monitoring system stores temperature, precipitation and wind speed data collected by automatic weather stations, river water level and flow data collected by hydrological stations, surrounding rock grade and fault distribution data provided by geological survey departments, and construction period control requirements issued by ecological and environmental departments. Meteorological and hydrological data are automatically collected every hour, and geological data is relatively static data that is entered before construction and updated when geological conditions change. The construction management system stores the process logical relationships of the construction network plan, the shift schedules of each team, process handover and acceptance records, and on-site coordination meeting minutes. The process logical relationships are kept synchronized with the network diagram in the progress management system. After data collection is completed, the business characteristics carried by each data point are considered. The system automatically categorizes and aggregates data. Categorization rules are implemented using a pre-defined feature keyword library and a data field mapping table. The feature keyword library is established along four dimensions, and the data field mapping table maps the original field names from each system to unified standard field names. After mapping, categorization is completed based on the dimension to which the standard fields belong. Data containing time node fields and project completion fields are categorized under the progress control dimension; data containing personnel allocation, material supply, and equipment scheduling fields are categorized under the resource supply dimension; data containing meteorological and hydrological, geological conditions, and policy control fields are categorized under the environmental constraints dimension; and data containing process arrangement, team scheduling, and site management fields are categorized under the organization and implementation dimension. Through categorization and aggregation, the original data from the four heterogeneous business systems are uniformly organized into four categories of engineering monitoring data. Each data entry carries a timestamp and spatial location tag. The timestamp is accurate to the day, and the spatial location tag includes three levels: sub-project number, construction location number, and warehouse number, providing a structured data foundation for subsequent quantitative analysis. If a certain type of system has not yet been deployed or its data interface is not yet connected, data for the corresponding dimension can be supplemented through manual entry and batch import of tables, while maintaining the categorization rules.
[0021] In the second stage, the data of the four dimensions are processed independently. A quantification method adapted to the business characteristics of each dimension is adopted to convert the original heterogeneous business data into a unified and comparable numerical discriminant value. The four discriminant values correspond one-to-one with the four dimensions and are unified into values in the range of 0 to 1. The larger the value, the more serious the contribution of that dimension to the progress lag. The design of the unified range allows the discriminant values of the four dimensions to be directly compared and weighted.
[0022] The schedule deviation judgment value is calculated based on the time series data of the schedule control dimension. The planned schedule time series, the actual schedule time series, and the benchmark schedule threshold for the corresponding construction period are extracted from the schedule control dimension data. The planned schedule time series is composed of the planned cumulative pouring volume of each statistical node arranged in chronological order with daily intervals. The actual schedule time series is also composed of the actual cumulative pouring volume arranged with daily intervals. The two series have the same length and the time nodes correspond one-to-one. The benchmark schedule threshold is determined based on the total construction period of the project contract and the approved construction organization design schedule plan. A certain percentage of the planned progress is taken as the benchmark. That is, when the actual progress is lower than the planned progress by this percentage, it is considered to enter the deviation state. The reason why the planned progress is not directly used as the benchmark is that there are normal progress fluctuations in the construction of water conservancy and hydropower projects. Allowing a certain range of deviation is within a reasonable range and there is no need to start rush work. Subsequently, the difference in the amount of work at adjacent time nodes is calculated to generate a deviation change rate sequence. First, the cumulative pouring volume on the same date in the two sequences is subtracted to obtain the daily progress deviation value. Then, the difference between the progress deviation value of the current day and the previous day is subtracted and divided by the time interval to obtain the daily deviation change rate. Arranged in chronological order, the deviation change rate sequence is formed. In the sequence, positive values indicate that the deviation is expanding, negative values indicate that the deviation is converging, and zero values indicate that the deviation is stable. Combined with the benchmark progress threshold, the cumulative absolute value of the deviation and the duration of the deviation are statistically analyzed. The cumulative absolute value of the deviation is the sum of the absolute values of the progress deviation values corresponding to all dates in the statistical period where the actual progress is lower than the benchmark threshold, reflecting the overall severity of the deviation. The duration of the deviation is the number of days when the actual progress is continuously lower than the benchmark threshold, reflecting the continuous impact of the deviation. After the deviation duration composite operation, it is mapped to a standardized numerical range of 0 to 1. The composite operation combines the cumulative absolute value of the deviation with the duration of the deviation in a weighted manner. The cumulative absolute value of the deviation has a higher weight because the severity of the deviation has a greater impact on the rush decision than the duration of the deviation. The mapping adopts piecewise linear normalization, and the final output is a progress deviation discrimination value. In this embodiment, the actual progress deviates significantly from the plan and the deviation continues to expand after the arrival of the flood season. The duration of the deviation is relatively long, and the output progress deviation discrimination value is about 0.72. The deviation change rate sequence calculation logic and the deviation duration composite operation logic defined here will be reused separately in the reverse dissipation calibration stage. The deviation change rate sequence logic is used for the reverse deduction of the process-level intervention dissipation coefficient, and the deviation duration composite operation logic is used for the reverse mapping of the work unit-level fatigue attenuation coefficient. This homogeneous reuse design ensures the uniformity of the quantitative standards for forward analysis and reverse calibration.
[0023] The resource allocation discriminant value is generated through a weighted fusion of multiple indicators. It extracts personnel on-duty status, material inventory, equipment deployment quantity, and corresponding timestamp sequences for each time point from the resource supply dimension data. The allocation adjustment speed for each dimension is obtained through difference calculations between adjacent nodes. For example, for the personnel dimension, the difference between the number of on-duty personnel on the current day and the previous day is divided by the time interval to obtain the personnel allocation adjustment speed. The same applies to the material and equipment dimensions. The larger the absolute value of the allocation adjustment speed, the more frequent the resource adjustments in that dimension. The total magnitude of resource allocation adjustments within the complete period is then summed. This is done by summing the absolute values of resource quantity changes for all adjacent days within the statistical period. The absolute value is used because both increases and decreases are considered allocation adjustments. All of these reflect the instability of resource supply. Frequent increases and decreases can lead to idle personnel and equipment, increasing construction costs. A resource allocation change trajectory curve is fitted and its fluctuation curvature is calculated. Cubic spline curves are fitted to the daily data of the three dimensions with date as the horizontal axis and resource quantity as the vertical axis. The average curvature of each curve within the statistical period is calculated; a larger curvature indicates more drastic fluctuations in resource allocation. The three indicators—adjustment speed, total adjustment magnitude, and fluctuation curvature—are normalized to the 0-1 range and then weighted and merged. Fluctuation curvature has the highest weight because long-term fluctuation trends reflect resource allocation stability better than daily adjustment speed. The average value of the three sub-dimensions—personnel, materials, and equipment—is used to obtain the resource allocation discriminant value.
[0024] Environmental condition discrimination values are calculated by combining the spatial coverage and temporal duration characteristics of the disturbance. Multiple environmental disturbance areas within the construction area are identified from the environmental constraint dimension data. Identification is achieved by overlaying environmental monitoring data with the spatial coordinates of the construction area. The entire construction area corresponding to days with rainfall reaching the rainstorm level is marked as a rainstorm disturbance area; the riverbed construction area corresponding to days with river levels exceeding the warning level is marked as a flood disturbance area; and areas where foundation pit seepage exceeds the design drainage capacity are marked as seepage disturbance areas. The scope of construction procedures covered by each area is statistically analyzed, and the proportion of its affected area to the total construction area is calculated. The affected area is obtained by overlaying the polygons of the disturbance area and the polygons of the construction area using a geographic information system. A sequence of regional directional changes is generated based on the duration of the disturbance, with the duration of the disturbance representing the duration of each environmental disturbance area. The number of days from the formation to the dissipation of the domain is used to arrange the changes in the proportion of the affected area of each region over time according to the spatial direction of the upstream and downstream of the river channel, thus forming a regional directional change sequence. Based on the fluctuation degree of the regional directional change sequence, the two indicators of the proportion of the affected area and the duration of the disturbance are weighted and calculated. The fluctuation degree is obtained by calculating the standard deviation of the sequence. The duration of the disturbance has the same weight as the proportion of the affected area and is higher than the fluctuation degree because these two factors directly determine the actual impact of environmental disturbance on construction. The environmental condition discrimination value is output. It should be noted that the environmental constraint dimension is an external uncontrollable factor. The implementation of the rush construction plan will not change the large-scale meteorological, hydrological and geological conditions. Therefore, the secondary environmental condition discrimination value is not calculated in the reverse dissipation calibration stage. The measures in the environmental dimension are essentially to avoid or mitigate environmental disturbance rather than eliminate it.
[0025] The construction organization discrimination value incorporates the calculation of process form and matching degree features. Boundary node information and process category information for each construction process are extracted from the organization and implementation dimension data. Boundary node information includes the time coordinates of the start and end nodes of each process (i.e., opening and closing times) and the spatial coordinates (i.e., the planar position and elevation of the construction site). Process category information includes the process name, the sub-project to which it belongs, and the process type. The extraction of boundary nodes is achieved by parsing the node data of the construction network plan and the site operation records of the construction management system. The proportion of process connection time to the total process time is calculated. Process connection time is the time between adjacent processes due to handover and acceptance, etc. The total waiting time caused by work area handover, resource allocation, etc. The higher this proportion, the more serious the waiting waste between processes and the lower the organizational efficiency. The height of the construction organization center of gravity control node is calculated by combining the coordinates of the critical path nodes. The critical path is determined by calculating the time parameters of the construction network plan, that is, the path with the longest total duration that determines the total project duration. The height of the center of gravity control node is obtained by weighting the time coordinates of each node of the critical path with the duration of the corresponding process of each node as the weight. It reflects the position of the construction organization control center of gravity on the time axis. Projects with a center of gravity that is too far back often need to invest more resources in the later stage to catch up on the schedule. The process matching similarity is obtained by comparing with a preset standard process library. The standard process library stores the typical duration, resource allocation quotas and logical relationships of standard construction processes for various water conservancy and hydropower projects. The data comes from the compilation of construction data and industry quotas of multiple completed projects. The duration, resource allocation and logical relationship of the actual construction process are compared with the corresponding process in the standard process library item by item. After calculating the deviation rate of each dimension, the similarity is obtained by comprehensive calculation. The lower the similarity, the more the actual construction organization deviates from the standard and the more serious the organizational problems are. The three indicators of connection time ratio, control node height and matching similarity are normalized and weighted and integrated. The connection time ratio has the highest weight because it directly reflects the on-site organization efficiency, and the construction organization discrimination value is obtained.
[0026] In the third stage, corresponding weight coefficients are matched according to the numerical range of each of the four discriminant values. A segmented matching method is used to divide the range of 0 to 1 into three segments: low, medium, and high, each corresponding to a different weight. The larger the discriminant value, the more severe the cause of that dimension, and the higher the weight. The segmented matching design, rather than fixed weights, allows the weights to be dynamically adjusted with the discriminant values, avoiding the underestimation of the contribution of a dimension with a high discriminant value but a fixed weight. The working condition compensation coefficient for the current construction stage is obtained. This coefficient is determined according to the construction stage to correct for the differences in progress sensitivity and rushing difficulty at different stages. The foundation excavation stage is greatly affected by the uncertainty of geological conditions and has a higher rushing difficulty, so the compensation coefficient is larger. The main body pouring stage has relatively mature procedures and moderate rushing difficulty. The finishing stage has fewer procedures and is relatively easy to rush, so the compensation coefficient is smaller. The four discriminant values are multiplied by their corresponding weight coefficients, summed, and then multiplied by the working condition compensation coefficient to obtain the comprehensive cause discrimination index. The proportion of each of the four discriminant values in the comprehensive cause discrimination index is calculated to determine the contribution ratio of each dimension's cause. The calculation of the contribution ratio provides a direct basis for subsequent measure matching.
[0027] After the comprehensive cause discrimination index is calculated, a dual-threshold decision response is implemented. The comprehensive cause discrimination index is compared with a preset dual-threshold decision range. The dual-threshold design, rather than a single-threshold design, is to avoid decision oscillation. When the comprehensive cause discrimination index fluctuates slightly around the threshold, it will not frequently switch the expedited work level. The width of the interval between the upper and lower limits can be adjusted according to the actual project situation. In this embodiment, if the comprehensive cause discrimination index exceeds the upper threshold, it is determined to be a high-level expedited work demand, triggering a level-one control response, including activating the project-level expedited work command center, increasing resource allocation authority, and holding daily progress coordination meetings. The implementation of the expedited work plan includes daily tracking and adjustments. Once the expedited work level is determined, an initial expedited work path plan is generated within that level framework, and reverse dissipation calibration is performed. Level 1 control response provides resource allocation authority and organizational support for plan generation and calibration. If the indicator is between the upper and lower limits, it is determined to be a medium-level expedited work requirement, triggering a Level 2 control response. The project department coordinates the implementation of the expedited work, holds weekly progress analysis meetings, and conducts weekly tracking and adjustments to the expedited work plan. If the indicator is below the lower threshold, it is determined that there is no expedited work requirement, and the original construction schedule is maintained without triggering an expedited work control response.
[0028] In the fourth stage, firstly, based on the contribution ratio, corresponding expediting measures units are matched from a pre-set expediting measures library. The expediting measures library is categorized and stored according to four dimensions. Each unit includes attributes such as measure name, applicable dimension, measure content, expected time reduction, resource requirements, and applicable conditions. The progress control dimension includes adjusting schedule priorities, reducing time differences for non-critical processes, and increasing work shifts. The resource supply dimension includes increasing personnel input, increasing equipment sets, pre-stocking critical materials, and optimizing material supply rhythm. The environmental constraints dimension includes building rainproof and heat-insulating facilities, adjusting work hours to avoid severe weather, optimizing construction sequence to avoid geologically complex areas, and strengthening the foundation. The implementation dimensions of measures include optimizing the process flow, increasing cross-operation areas, strengthening on-site coordination mechanisms, and adjusting work shifts. When matching measures, priority is given to the measure units with the highest contribution while also considering other dimensions. In this embodiment, six measures are selected: strengthening foundation pit drainage, building rain shelters, increasing night shifts, increasing the number of concrete mixer trucks, stockpiling cement and steel bars in advance, and optimizing the process flow. The implementation order and scope of each measure are arranged according to the sequential and spatial logic of the construction process to ensure that there are no conflicts between the measures and that they can work together effectively. This generates an initial expedited construction path plan, which is expected to bring the delayed construction period back to a controllable range.
[0029] After the initial expedited work path plan is generated, reverse dissipation calibration is performed. Reverse refers to the opposite of forward expedited work. Forward expedited work focuses on how much time can be compressed by the amount of intervention applied, while reverse calibration focuses on how much loss and how much effect the intervention itself will cause. Dissipation refers to the efficiency decay caused by factors such as personnel fatigue, equipment wear and tear, process conflicts, and cross-interference during the implementation of expedited work intervention. Calibration refers to modifying the initial plan after quantifying dissipation so that the expected effect of the plan is more in line with reality. Existing expedited work decision-making methods generally assume that the effect of expedited work intervention is linearly additive, that is, doubling the resources will compress the time by double. This assumption ignores the efficiency loss caused by the expedited work intervention itself, which often leads to the actual expedited work effect being lower than expected. Reverse dissipation calibration is proposed to address this defect. Its innovation lies in treating the expedited work intervention itself as the analysis object rather than just as a means, and modifying the plan by quantifying the side effects of the intervention. The calibration process comprises three nested levels, executed from the outside in. The first level is the overall secondary deviation verification, which calculates the degree of secondary deviation generated by the implementation of the scheme at the overall level. The second level is the process-level intervention dissipation deduction, nested within the first level, which decomposes and deduces the actual dissipation level of the rush intervention for each process and corrects the overall deviation calculation results. The third level is the work unit-level fatigue attenuation mapping, nested within the second level. When performing single-process dissipation deduction, it further refines the calculation results to the work execution unit, combining the continuous operation losses of personnel and equipment to correct the single-process dissipation calculation results. After layer-by-layer correction, the final rush path scheme is output. The three-layer nested design allows the calibration accuracy to be gradually refined from the overall level to the process level and then to the work unit level. The inner-layer correction results are fed back upwards layer by layer, forming a correction transmission chain from fine to coarse. In addition, the reverse calculation of each level reuses the same source quantification rules in the cause tracing stage. That is, the calculation logic of the secondary discriminant value is completely consistent with the calculation logic of the four types of forward discriminant values. This same source reuse design ensures the uniformity of the quantification standards for forward analysis and reverse calibration, avoiding the distortion of calibration results due to inconsistent quantification calibers.
[0030] The first layer is for overall secondary deviation verification. The initial expedited construction plan is broken down by time nodes, mapping the implementation time, resource input, and work sequence of each measure unit to a daily basis. This is converted into a virtual construction progress sequence consistent with the dimensions of multi-dimensional engineering monitoring data. This sequence is a simulation prediction of the project progress after the plan's implementation, rather than actual monitoring data. It includes daily virtual pouring volume, virtual on-duty personnel, virtual equipment usage, and virtual work sequence arrangements. The construction of the virtual sequence is based on the expected effect parameters of each measure unit, such as increasing night shifts expected to increase daily pouring volume, increasing mixer trucks expected to improve material transportation capacity by a certain percentage, and building rain shelters expected to increase the number of days available for work in rainy weather. These expected effect parameters are derived from the historical effect statistics of each measure unit in the expedited construction measures library. The environmental dimension parameters remain consistent with the measured values in the virtual sequence without modification, because environmental constraints are external uncontrollable factors, and the expedited construction plan does not change the environment itself. The resource superposition characteristics, process compression characteristics, and cross-operation characteristics in the virtual construction progress sequence are extracted to generate virtual resource configuration parameters, virtual construction organization parameters, and virtual progress deviation parameters, respectively. The resource superposition characteristics are obtained by calculating the increase ratio of daily resource input relative to the original plan. The process compression characteristics are obtained by calculating the compression range of the duration of each process relative to the original plan. The cross-operation characteristics are obtained by statistically analyzing the number of processes carried out simultaneously each day and the degree of spatial overlap. Using quantitative rules consistent with those in the causal tracing stage, virtual parameters were used to replace measured data to calculate secondary schedule deviation discriminant values, secondary resource allocation discriminant values, and secondary construction organization discriminant values. The secondary schedule deviation discriminant value reused the deviation change rate sequence and deviation duration composite calculation logic defined in the schedule deviation discriminant value, replacing the actual pouring volume sequence with a virtual pouring volume sequence and calculating using the same steps. The secondary resource allocation discriminant value reused the three weighted logics of configuration adjustment speed, total adjustment amplitude, and fluctuation curvature defined in the resource allocation discriminant value, replacing measured data with virtual personnel and equipment data and calculating using the same steps. The secondary construction organization discriminant value reused the three weighted logics of connection time ratio, control node height, and matching similarity defined in the construction organization discriminant value, replacing actual process arrangement with virtual process arrangement and calculating using the same steps. By reusing the same source quantitative rules, the quantitative standards for forward analysis and reverse calibration were ensured to be consistent. The secondary discriminant values and the forward discriminant values have the same dimensions and value range, allowing for direct comparison and calculation. The overall secondary deviation verification value is obtained by weighting the three types of secondary discriminant values equally. The equal weighting is because the three types of secondary deviations have a similar impact on the overall scheme. If the project is particularly sensitive to a certain type of deviation, a weighted average can also be used. In this embodiment, the rush-work scheme involves increased personnel input, increased equipment use, compression of key processes, and increased cross-operation surfaces. The secondary schedule deviation discriminant value is about 0.40, the secondary resource allocation discriminant value is about 0.55, the secondary construction organization discriminant value is about 0.48, and the overall secondary deviation verification value is about 0.48. This value is the initial verification value without considering the dissipation of processes and work units. It will be corrected layer by layer by the second and third layers.
[0031] The second layer is the process-level intervention dissipation extrapolation. The virtual construction progress sequence is divided into multiple independent process expediting units according to the logical boundaries of the construction process. These logical boundaries are the start and end nodes of each process in the construction network plan. During the decomposition, it is ensured that the expediting units do not overlap in time and are spatially distinguishable. In this embodiment, the main concrete pouring stage is divided into seven process expediting units: rebar tying, formwork installation, concrete pouring, curing, embedded part installation, surface preparation, and vibration operation. Although vibration operation belongs to the concrete pouring process in terms of construction organization, its equipment input and operational intensity characteristics are independent and its impact on dissipation is significant; therefore, it is separately decomposed into a process expediting unit to improve extrapolation accuracy. For each process expediting unit, expediting intervention intensity parameters and schedule compression parameters are extracted. The expediting intervention intensity is determined by the increase in resource input for that process and... The proportion of increased work shifts is comprehensively measured, and the duration reduction is the amount by which the duration of the process is shortened relative to the original plan under the expedited work plan. Taking the ideal duration reduction under the dissipation-free state as the benchmark, the ideal duration reduction is the amount of reduction that the process should achieve when the expedited intervention effect is completely linearly superimposed and there is no efficiency loss. It can be theoretically calculated based on the intensity of the expedited intervention and the original duration of the process. Following the calculation logic of the deviation change rate sequence defined by the schedule deviation discrimination value, the proportion of the expedited intervention effect attenuating with the implementation process is deduced in reverse. The rate of change of the difference between the ideal duration reduction and the actual simulated duration reduction extracted from the virtual sequence is used as the basis for deduction. An increase in the difference with time indicates that the attenuation is intensifying, and a decrease in the difference with time indicates that the attenuation is converging. The dissipation coefficient of the single process intervention is obtained, with a value range of 0 to 1. The larger the value, the more severe the dissipation. The intervention dissipation coefficients of all expedited work units are aggregated into an intervention dissipation coefficient set according to the work sequence. Each expedited work unit is then categorized according to its main influence dimension. The categorization is based on the relative proportions of resource input changes, work sequence changes, and schedule compression changes within the expedited work unit. The main influence dimension is determined by the highest proportion. The resource input change with the highest proportion is categorized under the resource dimension; in this embodiment, concrete pouring, rebar tying, and vibration operations are categorized under the resource dimension. The work sequence change with the highest proportion is categorized under the organization dimension; formwork installation and embedded part installation are categorized under the organization dimension. The schedule compression change with the highest proportion is categorized under the schedule dimension; warehouse preparation and curing are categorized under the schedule dimension. Each dimension is calculated separately. The arithmetic mean of the dissipation coefficients of all process interventions within the degree is used to obtain the average dissipation coefficients of the resource dimension, organization dimension, and schedule dimension. The average dissipation coefficients of each dimension are substituted into the calculation process of the first-level overall secondary deviation verification value. The corrected secondary discriminant value is equal to the original secondary discriminant value multiplied by 1 plus the corresponding dimension's average dissipation coefficient. The three types of corrected secondary discriminant values are weighted and averaged to obtain the first corrected overall secondary deviation verification value, which is higher than before the correction. This indicates that the dissipation at the process level has further aggravated the secondary deviation. The physical meaning of the correction is that the efficiency loss generated by the rush intervention in each process will offset part of the expected effect, making the actual secondary deviation greater than the calculated value when dissipation is not considered.
[0032] The third layer is the fatigue attenuation mapping at the work unit level. Based on the boundaries between work teams and equipment sets, a single work process expediting unit is broken down into multiple work execution units. The work execution unit is the smallest execution unit in the construction organization, corresponding to a work team or a piece of equipment and its work content. During decomposition, it is ensured that the work content of each work execution unit is clear and the responsible entity is unique. In this embodiment, it is decomposed into more than ten work execution units, covering the work teams and main equipment sets of each process. For each work execution unit, parameters of continuous working time for personnel, continuous operating time for equipment, and work intensity are extracted. Work duration is calculated using shift schedules and attendance records. Work intensity is measured by the ratio of output per unit time to standard output. In this embodiment, night shifts exceed the standard working hours by several hours, and the unit time intensity of nighttime pouring is higher than that of daytime, with continuous equipment operation exceeding the standard duration. The benchmark work efficiency under standard work intensity is used as a reference. Benchmark work efficiency is the unit time output of the work unit under normal work intensity (i.e., standard working hours and conventional pouring intensity), which can be determined through historical construction data or industry quotas during non-rush periods. The deviation duration defined by the schedule deviation discrimination value is used. The calculation logic of the combined operation is reverse-mapped to the efficiency decay ratio within a unit of work time. It combines continuous work time with work intensity, with continuous work time having a higher weight because fatigue is mainly caused by the accumulation of long-term continuous work. The decay ratio is inferred by combining the difference between the benchmark work efficiency and the simulated actual work efficiency to obtain the fatigue decay coefficient of each work execution unit. In this embodiment, the night shift has a higher fatigue decay coefficient because the actual efficiency decays significantly compared to the benchmark due to the long continuous work time and high work intensity. The day shift has a smaller decay range and a lower fatigue decay coefficient. The more the equipment runs continuously beyond the standard time, the more severe the decay. The fatigue decay coefficients of all work execution units are collected into a fatigue decay coefficient set according to their respective processes. The fatigue decay coefficients of all work execution units in the same process are weighted and averaged according to the proportion of work volume to obtain the comprehensive fatigue decay coefficient of the process. This is substituted into the calculation process of the second-level single-process intervention dissipation coefficient. The corrected intervention dissipation coefficient is equal to the original intervention dissipation coefficient plus 1 minus the original intervention dissipation coefficient and then multiplied by the comprehensive fatigue decay coefficient. The corrected coefficient must be greater than the original value but not exceed 1. The physical meaning is that the fatigue decay at the work unit level is further superimposed with incremental dissipation on the basis of the original process dissipation.
[0033] After the intervention dissipation coefficients are corrected at the work execution unit level, they are re-collected into an updated set of intervention dissipation coefficients. The updated average dissipation coefficients for each dimension are then calculated again and substituted into the first-level overall deviation calculation process to complete the second correction of the overall secondary deviation verification value. The correction transmission path is: work unit-level fatigue attenuation coefficient corrects process-level intervention dissipation coefficients (inner layer corrects middle layer), and the corrected intervention dissipation coefficients then correct the overall secondary deviation verification value (middle layer corrects outer layer). In this embodiment, after work unit-level correction, the average dissipation coefficients for each dimension increase, and the overall secondary deviation verification value after the second correction is approximately 0.60. It is then determined whether the corrected overall secondary deviation verification value is lower than a preset secondary deviation threshold. The threshold is set based on the project's requirements for the stability of the expedited work plan; a lower threshold indicates higher stability requirements and smaller allowable secondary deviations. In this embodiment, the verification value is higher than the threshold and therefore does not meet the requirements. Based on the contribution ratio of the three types of secondary discrimination values after correction, the resource input intensity, process compression range, and cross-operation range of the initial expedited work path plan are adjusted accordingly. The secondary resource allocation discriminant value has the highest contribution, so the intensity of nighttime personnel input was reduced and some nighttime operations were adjusted to daytime off-peak operations. The secondary construction organization discriminant value has the second highest contribution, so the compression of key processes was appropriately reduced and the scope of cross-operations was narrowed. After the adjustment, the complete calibration process from the first-level overall secondary deviation verification to the third-level work unit fatigue attenuation mapping was re-executed. In the second round of calibration, the number of night shifts was reduced, the continuous working time of personnel was reduced, the compression of key processes was reduced, and the cross-operation surface was reduced. After re-deduction, the overall secondary deviation verification value decreased, but it was still higher than the threshold. In the third round of calibration, the compression of key processes and the scope of cross-operations were further adjusted, and the intensity of concrete pouring intervention was reduced. After re-deduction, the overall secondary deviation verification value dropped below the threshold. The current plan was determined as the final rush-up path plan. The expected amount of time recovery in this plan is slightly less than that in the initial plan, but the feasibility and stability of the plan are significantly improved, and the delayed time is controlled within the target range, achieving the rush-up target. In addition to the verification value being lower than the threshold, the iteration termination condition can also set the maximum number of iterations to avoid infinite loops. The three-layer nested calibration architecture can be used in combination to form a complete calibration process, or a single layer or two layers can be used alone according to the actual needs of the project. For projects with clear process divisions but insufficient work unit data, only the overall verification and process deduction layers can be executed. For small projects or scenarios with low urgency requirements, only the overall verification layer can be executed. This flexible combination allows the method to adapt to projects of different scales and data conditions.
[0034] After calibration, the fifth stage begins, where the final expedited construction path plan is output. The plan is delivered to the project team for implementation, and the output includes a Gantt chart-style schedule, resource allocation table, implementation measure list, and risk warning list to ensure that the project team can directly organize and implement the plan. The first-level control response mechanism is activated simultaneously, and the engineering-level expedited construction command center tracks the implementation of the plan daily and decides whether to initiate dynamic rolling calibration based on the actual progress deviation.
[0035] Based on the above, after each expedited construction plan is implemented, actual construction data is collected. The actual intervention dissipation coefficient of each process and the actual fatigue attenuation coefficient of each work unit are calculated. These are compared with the corresponding coefficients derived during the calibration process, and the deviation amount and direction are recorded. The deviation data of multiple projects are classified and stored according to dimensions such as project type, construction stage, and process category to construct a historical database of dissipation deviations. During the calibration process of subsequent projects, historical deviation data with similar characteristics to the current project are matched from the database to correct the derived coefficients. A weighted average method based on similar cases is used to select historical cases with high feature similarity rankings, and the predicted deviation is superimposed on the derived coefficients using similarity as the weight. As historical data accumulates, a calibration and implementation process is formed. The closed-loop iterative mechanism of feedback and optimization enables the calibration accuracy to continuously improve with engineering experience. It can also be extended to parallel simulation of multiple schemes and Pareto optimal selection scheme. When generating the initial rush path scheme, multiple combination strategies are used to generate multiple schemes in parallel, with resource supply measures as the main focus, organization and implementation measures as the main focus, balanced combination of all dimensions, and environmental constraint measures as the main focus. Inverse dissipation calibration is performed on each scheme to obtain the corresponding final scheme and verification value. At the same time, the expected time reduction, total resource input, cost increase, quality risk level and other evaluation indicators of each scheme are calculated. The set of non-inferior schemes is screened through Pareto optimality analysis, and then the decision-maker selects the final scheme according to the actual engineering preferences, overcoming the defect that a single scheme may fall into local optima. It can also be extended to a dynamic rolling calibration scheme for the expedited construction plan. During the implementation of the final expedited construction path plan, multi-dimensional engineering monitoring data is re-collected at daily intervals. Quantitative analysis and comprehensive cause judgment are performed to update indicators and contribution ratios. At the same time, actual progress data and resource consumption data since the implementation of the plan are collected to calculate the actual secondary deviations and intervention dissipation. The accuracy is evaluated by comparing with the calibration prediction values. If the change of the comprehensive cause judgment index exceeds a certain proportion or the actual deviation exceeds the allowable range of the predicted deviation, the initial plan generation and reverse dissipation calibration are re-executed to generate an updated plan to replace the original plan. This allows the expedited construction path plan to be continuously optimized with changes in working conditions, avoiding the gradual failure of static plans in complex construction environments.
[0036] Regarding the setting of various parameters and thresholds in the method, the weighting coefficients should follow the principle that the more severe the cause, the higher the weight. The interval division can be adjusted according to the sensitivity of the project to each dimension. For environmentally sensitive projects, the weighting interval of the environmental condition discrimination value can be appropriately increased, and for resource-intensive projects, the weighting interval of the resource allocation discrimination value can be appropriately increased. The condition compensation coefficient should be combined with the progress sensitivity of the construction stage. The value should be larger in the foundation excavation stage, the median value in the main body pouring stage, and the smaller value in the finishing stage. The secondary deviation threshold should be combined with the quality and safety requirements and progress control requirements of the project. The lower value should be used for projects with extremely high quality and safety requirements, and the higher value can be appropriately increased for projects with extremely high progress pressure. The calculation interval of the deviation change rate sequence can be adjusted according to the project scale. Large projects use daily intervals, and small and medium-sized projects can use weekly intervals. The resource allocation change trajectory curve can be fitted with cubic spline or polynomial fitting. The fitting order should not be too high to avoid overfitting. The above parameter setting principles are only recommended guidelines. Those skilled in the art can adjust them according to the actual situation of the project.
[0037] Finally, it should be noted that the above embodiments are merely examples for clearly illustrating the present invention and are not intended to limit the implementation. Those skilled in the art will recognize that other variations or modifications can be made based on the above description. It is neither necessary nor possible to exhaustively list all possible implementations. However, obvious variations or modifications derived therefrom are still within the scope of protection of this invention.
Claims
1. A method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects, characterized in that, The steps for this temperature control method are as follows: Collect multi-dimensional engineering monitoring data of the target water conservancy and hydropower project. The multi-dimensional engineering monitoring data covers the dimensions of progress control, resource supply, environmental constraints, and organization and implementation. Quantitative analysis was conducted on the engineering monitoring data of each dimension to obtain the corresponding judgment values for schedule deviation, resource allocation, environmental conditions, and construction organization. The comprehensive cause discrimination index is calculated by integrating four types of discrimination values. The corresponding expediting measures are matched by combining the contribution ratio of each dimension to the expediting demand. The initial expediting path plan is formed by logically assembling the construction procedures. The initial expedited work path plan is subjected to reverse dissipation calibration. During the calibration process, the degree of secondary deviation caused by the implementation of the plan is first calculated from the overall level. Then, the actual dissipation level of the expedited work intervention is deduced step by step and the overall deviation calculation result is corrected. When the dissipation of a single process is deduced, it is further refined to the work execution unit. The dissipation calculation result of a single process is corrected by combining the continuous operation loss of personnel and equipment. After the layer-by-layer correction, the final expedited work path plan is output. The comprehensive cause discrimination index is compared with the preset dual threshold decision range. Based on the comparison results, the level of expedited work demand is divided, the corresponding control response is triggered, and the final expedited work path plan is output.
2. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, The collection and classification of multi-dimensional engineering monitoring data shall be carried out in the following manner: It connects to four types of data interfaces of the target project: progress management system, resource management system, environmental monitoring system, and construction management system, to collect all original project data; The data is categorized and collected based on the business characteristics it carries. Data that carries time nodes and project completion characteristics are categorized into the progress control dimension; data that carries personnel allocation, material supply, and equipment scheduling characteristics are categorized into the resource supply dimension; data that carries meteorological, hydrological, geological conditions, and policy control characteristics are categorized into the environmental constraints dimension; and data that carries process arrangement, team scheduling, and on-site management characteristics are categorized into the organization and implementation dimension.
3. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, The schedule deviation judgment value is calculated based on the time-series data from the schedule control dimension: Extract the planned schedule time series, actual schedule time series, and the baseline schedule threshold for the corresponding work period from the schedule control dimension data; The difference in the amount of work at adjacent time nodes is calculated to generate a sequence of deviation change rates. Combined with the baseline progress threshold, the cumulative absolute value of the deviation and the duration of the deviation are statistically analyzed. After the deviation duration is compounded, it is mapped to a standardized numerical range of zero to one, and the progress deviation discrimination value is output.
4. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, Resource allocation criteria are generated through a weighted fusion of multiple indicators: Extract the on-duty personnel, material inventory, equipment usage and corresponding timestamp sequences for each time node from the resource supply data. Calculate the resource allocation adjustment speed for each dimension by calculating the difference between adjacent nodes, and sum the total resource allocation adjustment range within the complete cycle. The resource allocation change trajectory curve is fitted and its fluctuation curvature is calculated. The three indicators of allocation adjustment speed, total adjustment amplitude and fluctuation curvature are weighted and integrated to obtain the resource allocation discriminant value.
5. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, The environmental condition discrimination value is calculated by combining the spatial coverage and temporal duration characteristics of the disturbance: Multiple environmental interference areas within the construction scope are identified from the environmental constraint dimension data. The scope of construction procedures covered by each area is statistically analyzed and the proportion of its affected area to the total construction area is calculated. A sequence of regional directional changes is generated by combining the duration of the interference. Based on the fluctuation degree of the regional directional change sequence, the environmental condition discrimination value is output by weighting two indicators: the proportion of affected area and the duration of interference.
6. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, The calculation of the construction organization discriminant value incorporates the characteristics of process form and matching degree: Extract boundary node information and process category information of each construction process from the data of the organization and implementation dimension, calculate the proportion of process connection time to total process time, and calculate the height of the construction organization center of gravity control node by combining the coordinates of the critical path node; The process matching similarity is obtained by comparing with the preset standard process library. The three indicators of connection time ratio, control node height and matching similarity are weighted and integrated to obtain the construction organization discrimination value.
7. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, The calculation of the comprehensive cause discrimination index and the generation of the initial rush-work path plan are performed as follows: Based on the numerical ranges of the schedule deviation judgment value, resource allocation judgment value, environmental condition judgment value, and construction organization judgment value, corresponding weight coefficients are matched respectively. Obtain the working condition compensation coefficient for the current construction stage of the project; The four types of discrimination values are multiplied by their corresponding weight coefficients and summed, then multiplied by the working condition compensation coefficient to obtain the comprehensive cause discrimination index. Calculate the proportion of the four types of discriminant values in the comprehensive causal discriminant index to determine the contribution proportion of each dimension of the cause; Based on the contribution ratio, the corresponding expediting measure units are matched from the preset expediting measure library, and then assembled according to the sequential logic of the construction process to generate an initial expediting path plan.
8. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 1, characterized in that, Secondary bias calculation at the global level in reverse dissipation calibration is performed as follows: The initial expedited construction plan was broken down by time nodes and converted into a virtual construction progress sequence consistent with the dimensions of multi-dimensional engineering monitoring data. Extract resource overlay features, process compression features, and cross-operation features from the virtual construction progress sequence, and generate virtual resource configuration parameters, virtual construction organization parameters, and virtual progress deviation parameters respectively. Using the same quantitative rules as the causal tracing stage, virtual parameters were used to replace measured data to calculate the secondary schedule deviation judgment value, secondary resource allocation judgment value, and secondary construction organization judgment value, respectively. The weighted summation of the three types of secondary discrimination values yields the overall secondary deviation verification value.
9. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 8, characterized in that, In the process of calculating the overall secondary deviation verification value, the dissipation level of rush intervention is analyzed and deduced step by step according to the following method: The virtual construction progress sequence is divided into multiple independent expedited construction units according to the logical boundaries of the construction process; For each expedited work unit, the expedited intervention intensity parameter and the time compression range parameter within that unit are extracted. Using the ideal time compression amount under no dissipation state as a benchmark, the proportion of the expedited intervention effect attenuating with the implementation process is deduced in reverse using the calculation logic of the deviation change rate sequence, and the single-process intervention dissipation coefficient is obtained. The intervention dissipation coefficients of all process rush units are collected into an intervention dissipation coefficient set according to the process sequence. This set is then substituted into the calculation process of the overall secondary deviation verification value. The values are multiplied by the corresponding dimensions of the three types of secondary discriminant values to complete the initial correction of the three types of secondary discriminant values.
10. The method for tracing the causes and deducing the path of rushed construction in water conservancy and hydropower projects according to claim 9, characterized in that, In the derivation of the dissipation coefficient of a single process intervention, the fatigue attenuation calibration and iterative correction down to the work execution unit are performed in the following manner: Based on the division of work teams and equipment sets, a single process expediting unit is broken down into multiple work execution units; For each work execution unit, extract the parameters of continuous working time of personnel, continuous working time of equipment, and work intensity within the unit. Using the benchmark work efficiency under standard work intensity as a reference, the calculation logic of deviation time composite operation is used to reverse map the efficiency decay ratio within the unit work time to obtain the fatigue decay coefficient of a single work unit. The fatigue attenuation coefficients of all work execution units are collected into a fatigue attenuation coefficient set according to their respective processes. This set is then substituted into the calculation process of the single process intervention dissipation coefficient, and the intervention dissipation coefficient of the corresponding process is corrected unit by unit. The intervention dissipation coefficient, after being corrected at the work execution unit level, is substituted into the overall deviation calculation process to complete the second correction of the overall secondary deviation verification value. If the corrected overall secondary deviation verification value is lower than the preset secondary deviation threshold, the current initial rushing path plan is determined as the final rushing path plan. If it is higher than the preset secondary deviation threshold, the resource input intensity, process compression range, and cross-operation range of the initial rushing path plan are adjusted according to the contribution ratio of the three types of secondary discrimination values after correction, and the reverse dissipation calibration process is re-executed until the threshold requirements are met.