Method, system and electronic device for automatic warning of lack of spare parts for nuclear power plant planned work orders
By automating the analysis of spare parts inventory in nuclear power plant work orders, generating shortage warnings and adjusting plans, the problem of equipment maintenance plan cancellations caused by spare parts shortages has been solved, improving management efficiency and accuracy.
Patent Information
- Application Number
- CN202611329130.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-28
- Publication Date
- 2026-11-20
AI Technical Summary
In nuclear power plants, the cancellation of equipment maintenance plans due to the shortage of spare parts for planned work orders affects operational stability and safety, and manual data analysis is complex, time-consuming and inefficient.
The system uses automated methods to acquire planned work order data, filter valid work orders, calculate available spare parts inventory, generate out-of-stock alert tasks, and distribute them to preparation terminals. Engineers then evaluate and adjust the plan.
It improved work efficiency, reduced manual intervention, ensured the accurate execution of equipment maintenance plans, avoided plan cancellations due to spare parts shortages, and enhanced management accuracy and efficiency.
Smart Images

Figure CN123140833A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the technical field of planned work order management in nuclear power plants, and more specifically, to a method, system, and electronic device for automatic early warning of spare parts shortages in planned work orders of nuclear power plants. Background Technology
[0002] After the routine and major overhaul equipment maintenance work orders of nuclear power plants are completed and the spare parts resources are checked and confirmed to meet the implementation conditions, they are submitted and included in the implementation plan. Work orders in this state are called planned work orders. Due to the limitations of system equipment operation, isolation, management and other conditions, some cannot be implemented immediately. During this period, the planned start time of on-site equipment inspection, equipment maintenance, experience feedback and troubleshooting, technical problems, modification and optimization and other work may be carried out in advance or new work with higher priority may be added and carried out. This may unexpectedly occupy the spare parts resources of the work orders that have been included in the plan to be implemented, resulting in insufficient spare parts inventory and the inability of the relevant maintenance plan to be implemented at the original time.
[0003] Currently, nuclear power plants mostly manually search for work orders that are expected to start soon, and then verify whether the spare parts resources required for each work order meet the start-up conditions. If not, they apply to the planning department to remove the work orders from the plan to the spare parts waiting status, and then submit them and include them in the plan after the spare parts are purchased and delivered. However, this method has the following problems: (1) The work orders in the plan are only found to be canceled before the start of the work due to the higher priority work orders jumping the queue, resulting in insufficient spare parts inventory. At this time, in order to obtain the equipment maintenance window and status, the operators may have already carried out system status preparation and system and equipment isolation operations. Temporarily canceling the work orders in the plan is a waste of relevant manpower and material resources, and may also have a certain adverse impact on the stability, reliability and safety of the system and equipment operation; (2) The maintenance plans for daily and overhaul unit equipment are relatively independent. The spare parts originally planned for daily work orders are likely to be occupied by overhaul work orders due to the concentrated testing and inspection of equipment during overhaul, resulting in some of the daily work not being carried out according to the planned time. (3) Daily plans typically schedule thousands of work orders to be executed within at least 12 weeks in advance. During this period, routine equipment inspections and tests are ongoing, continuously generating new work orders that are added to the plan. Higher priority work orders may require spare parts that are the same as those required by the work orders in the plan and are scheduled to be executed within the 12-week plan. Special activities such as feedback from internal and external nuclear power plants and equipment reliability improvement may add a large number of maintenance work orders to the 12-week plan, occupying the same spare parts resources required by the original work orders, resulting in the work orders in the plan not being executed according to the original schedule. (4) Manually sorting out thousands of work orders and tens of thousands of spare parts required at different times in a short period of time is extremely complex, time-consuming, and inefficient, as is the data analysis and processing of tens of thousands of data. Summary of the Invention
[0004] The technical problem to be solved by the present invention is to provide a method, system and electronic equipment for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, in view of the problems existing in the prior art.
[0005] The technical solution adopted by this invention to solve its technical problem is: to construct a method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, comprising the following steps: Step S10: Obtain the data information of the planned work order and the spare parts data reserved in the work order; Step S20: Based on the data information and the reserved spare parts data, perform work order screening to obtain valid work orders; Step S30: Calculate the available inventory of spare parts based on the spare parts information reserved in the valid work order; the spare parts information reserved in the valid work order includes: spare parts material number, work order required quantity, required date, and the inventory quantity corresponding to the spare parts material number in the database, and the quantity of orders delivered but not accepted; Step S40: Automatically verify the planned work order based on the available inventory of the spare parts, and determine whether it meets the verification rules. If it does, automatically generate a spare parts shortage warning pending task for the planned work order. Step S50: Display the spare parts shortage warning pending tasks in a single row according to the planned work order dimension; Step S60: Automatically distribute the spare parts shortage warning task to the corresponding preparation terminal.
[0006] In the nuclear power plant planned work order spare parts shortage early warning method of the present invention, after step S60, the method further includes: Step S70: Receive the evaluation conclusion returned by the preparation terminal, and generate an evaluation ledger based on the evaluation conclusion.
[0007] In the method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to the present invention, the method further includes: If the assessment concludes that spare parts do not need to be returned, the original plan of the work order will remain unchanged; if the assessment concludes that spare parts need to be returned, the corresponding work order will be returned to the spare parts status.
[0008] In the nuclear power plant planned work order spare parts shortage early warning method of the present invention, the method further includes: Repeat steps S10 to S70 daily according to the set conditions.
[0009] In the automatic early warning method for spare parts shortage in planned work orders of nuclear power plants according to the present invention, step S30 includes: Obtain the spare parts information reserved in the valid work order; the spare parts information reserved in the valid work order includes: spare parts material number, work order required quantity, required date, and the inventory quantity corresponding to the spare parts material number in the database, and the quantity of orders delivered but not accepted; The available inventory of spare parts is calculated based on the work order requirements, required dates, inventory quantities, and unaccepted order quantities reserved in the valid work orders.
[0010] In the method for automatic early warning of spare parts shortage in nuclear power plant planned work orders according to the present invention, the inventory quantity satisfies the following conditions: the work order number is within the set plan data, and the work order status is valid. The quantity of orders that have not been delivered and accepted meets the following condition: the order number and line number are in the procurement node of the entire procurement process data as either "delivery not yet received" or "delivery pending acceptance".
[0011] In the method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to the present invention, the method further includes: On the spare parts shortage warning pending task display interface, the reserved spare parts information in the corresponding planned work order is displayed according to the viewing command; the reserved spare parts information includes: spare parts material code, spare parts description, inventory quantity, required quantity and required date data.
[0012] In the method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to the present invention, the method further includes: The terminal is prepared to receive the spare parts shortage warning task and display the spare parts shortage warning task. Receive the evaluation conclusion of the preparation engineer on the pending tasks for the spare parts shortage warning; The evaluation results are saved and automatically transmitted to the daily planning system.
[0013] This invention also provides a system for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, comprising: The data acquisition unit is used to acquire data information from planned work orders and spare parts data reserved in the work orders; The work order filtering unit is used to filter work orders based on the data information and the reserved spare parts data to obtain valid work orders; The available inventory calculation unit is used to calculate the available inventory of spare parts based on the spare parts information reserved in the valid work order; the spare parts information reserved in the valid work order includes: spare parts material number, work order required quantity, required date, and the inventory quantity of spare parts in the database, and the quantity of orders delivered but not yet accepted; The stockout warning judgment unit is used to automatically verify the planned work order based on the available inventory of the spare parts, and determine whether it meets the verification rules. If it does, it automatically generates a spare parts stockout warning pending task for the planned work order. The to-do display unit is used to display the spare parts shortage warning to-do tasks in a single row according to the planned work order dimension. The task push unit is used to automatically distribute the spare parts shortage warning task to the corresponding preparation terminal.
[0014] The present invention also provides an electronic device, including a memory and a processor, wherein the memory stores a computer program, and the processor executes the steps of the method for automatic early warning of spare parts shortage in nuclear power plant planned work orders as described above by calling the computer program stored in the memory.
[0015] The method, system, and electronic equipment for automatic early warning of spare parts shortages in planned work orders of nuclear power plants, implementing the present invention, have the following beneficial effects: The method includes: acquiring data information of planned work orders and reserved spare parts data; screening work orders; calculating the available inventory of spare parts based on the reserved spare parts data; automatically verifying and generating spare parts shortage early warning tasks for planned work orders based on the available inventory; displaying the spare parts shortage early warning tasks in a single row according to the planned work order dimension; and automatically distributing the spare parts shortage early warning tasks to the corresponding preparation terminals. The present invention automatically analyzes and calculates the available inventory of spare parts for planned work orders already included in the plan, thereby automatically determining whether the demand is met and automatically generating a work order shortage early warning ledger. This effectively solves the problem of original planned work orders being canceled due to pre-emptive work orders. Simultaneously, it automates the complex and inefficient data analysis and processing previously performed manually using big data software, greatly improving work efficiency and quality. Attached Figure Description
[0016] The present invention will be further described below with reference to the accompanying drawings and embodiments. In the accompanying drawings: Figure 1 This is a flowchart illustrating the automatic early warning method for spare parts shortage in planned work orders of nuclear power plants provided by the present invention. Figure 2 This is a display interface diagram of the evaluation ledger provided by the present invention; Figure 3 This is a logic block diagram of the automatic early warning system for spare parts shortage in nuclear power plant planned work orders provided by the present invention. Detailed Implementation
[0017] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0018] To address the problems of traditional solutions, this invention provides an automatic early warning method for spare parts shortages in planned work orders of nuclear power plants. This method automatically retrieves planned work orders, calculates whether the spare parts requirements of the work orders can be met after deducting the requirements of previous planned work orders, automatically generates risk warning items, and transmits the assessment results online to the planning stage after evaluation.
[0019] refer to Figure 1 In a preferred embodiment, the method for automatic early warning of spare parts shortage in planned work orders of the nuclear power plant includes the following steps: Step S10: Obtain the data information of the planned work order and the reserved spare parts data.
[0020] Specifically, data information from planned work orders is obtained from the 12-week production plan of the nuclear power plant (configurable in the configuration center: TN data items, flexible and adjustable), including but not limited to: work order number, function location, work order description, work order type, system conditions, version, etc. Simultaneously, spare parts data reserved in the planned work orders is obtained from the SAP system (Enterprise Management Solutions software system), including work order status, main work center, material code, material description reservation number, reservation line item number, reservation / purchase request, required quantity, required date, inventory quantity, regular order quantity, reserved quantity, reorder point, delivery quantity, MRP elements, etc. All this data is uniformly entered into the big data management platform.
[0021] Step S20: Based on the work order data and reserved spare parts data, filter the work orders to obtain valid work orders.
[0022] Specifically, all planned work orders obtained from the plan are filtered based on their data information and reserved spare parts data. The filtering process is as follows: Completed and non-execution planned work orders are excluded; that is, work orders with statuses containing "CSR" (Completed), "CPL" (Closed), "PC" (Equivalent), or "REJ" (Non-execution) are excluded; work orders with system statuses containing "CLSD" (Closed) or "TECO" (Technical Closed) are excluded; and finally, work orders with empty "Deleted Item" fields corresponding to reserved spare parts material codes are excluded from the remaining planned work orders, resulting in valid work orders. These valid work orders are the effective planned work orders.
[0023] Step S30: Calculate the available inventory of spare parts based on the spare parts information reserved in the valid work orders.
[0024] The spare parts information reserved in a valid work order includes: spare parts material number, work order required quantity, required date, spare parts inventory quantity in the database, and quantity of orders delivered but not yet accepted.
[0025] In this embodiment of the invention, step S30 includes: obtaining the spare parts material number, work order required quantity, required date, and the spare parts inventory quantity and order delivery unaccepted quantity of the valid work order; and calculating the available inventory of spare parts required for each planned work order according to the inventory quantity, spare parts required quantity, required date, and order delivery unaccepted quantity in chronological order of required date.
[0026] Specifically, the inventory quantity must meet the following conditions: the work order number is within the set plan data and the work order status is valid; the quantity of orders delivered but not yet accepted must meet the following conditions: the order number and line number are in the status of "delivery not yet received" or "delivery pending acceptance" at the procurement node of the entire procurement process data.
[0027] Specifically, after filtering out all valid work orders in step S20, the available inventory of spare parts required for each valid planned work order is calculated based on the reserved work order demand quantity, demand date, inventory quantity, and unaccepted order delivery quantity. The calculation method for available inventory is as follows: Available quantity = Inventory quantity + Order delivery quantity not yet accepted - Work order demand quantity; The available quantity is the available inventory.
[0028] In practical applications, available inventory is calculated for each work order based on the MRP element data (i.e., stock quantity, order demand quantity, and order delivery unaccepted quantity) extracted from MD04 in the SAP system, arranged from the nearest to the oldest date for the reserved spare parts. Among the MRP element data used in the available inventory calculation, the OrdRes element type must simultaneously meet the following requirements: 1) The work order number is within the 12-week plan (configurable in the configuration center: TN data item, flexible and adjustable); 2) The work order status includes "SCHD" (planned) or "WIP" (in progress), and excludes "PC" or "REJ", and the [system status] does not include "CLSD" and "TECO"; Data in the ShpgNt element type that is included in the calculation must meet the following condition: [Order Number + Line Number] in the procurement node status of the procurement process data on the big data management platform is [Shipping Not Received] or [Received but Awaiting Acceptance]. Spare parts whose availability is questionable are not included in the calculation.
[0029] Step S40: Automatically verify the planned work order based on the available spare parts inventory and determine whether it meets the verification rules. If it does, automatically generate a spare parts shortage warning pending task for the planned work order. Specifically, the available spare parts inventory is automatically verified according to the demand date (i.e., the planned implementation date) of the spare parts in the planned work order, and each item is checked to see if it meets the verification rules. If it does, an automatic spare parts shortage warning pending task for the planned work order is generated. The verification rule is: [Available Quantity] < 0.
[0030] Specifically, after calculating the available spare parts inventory for each planned work order from the nearest to the furthest in time in step S30, the spare parts with different codes reserved for each planned work order are traversed according to the calculated available inventory. If there is a case where [available quantity] < 0, the corresponding spare parts shortage warning pending task is automatically generated.
[0031] Step S50: Display the spare parts shortage warning tasks in a single row according to the planned work order dimension.
[0032] In this embodiment of the invention, the method further includes: displaying the reserved spare parts information of the corresponding planned work order on the spare parts shortage warning pending task display interface according to the viewing instruction; the reserved spare parts information includes: spare parts material code, spare parts description, inventory data, required quantity and required date data.
[0033] Specifically, on the spare parts shortage warning task display interface, the spare parts shortage warning tasks are displayed in a single row according to the planned work order dimension. The spare parts shortage item of the planned work order is triggered by the "view" control, and the system responds to the view command to display the reserved spare parts information of the corresponding planned work order, such as spare parts material code, spare parts description, inventory data, required quantity, required date, delivery data, etc., so that the assessment personnel can quickly locate the items with shortage risk among the multiple spare parts required for a planned work order, and further verify whether the inventory and received spare parts meet the recent planned needs.
[0034] Step S60: Automatically distribute spare parts shortage warning tasks to the corresponding preparation terminals.
[0035] In this embodiment of the invention, spare parts shortage warning tasks are automatically distributed to the preparation terminal of the preparation engineer corresponding to the work order. After receiving the spare parts shortage warning task, the preparation terminal displays the task and the preparation engineer manually reviews it. Specifically, the engineer checks the reserved spare parts information to further verify the inventory and confirm whether the work order already included in the plan needs to be returned to the plan until the spare parts are procured before resubmitting the plan. An evaluation conclusion is generated and saved, and the evaluation conclusion is automatically transmitted to the daily planning system.
[0036] Furthermore, after step S60, the following is also included: Step S70: Receive the evaluation conclusion returned by the preparation terminal, and generate an evaluation ledger based on the evaluation conclusion.
[0037] Specifically, the preparation engineer handles spare parts shortage alerts and pending tasks, confirms whether planned work orders need to be returned from the plan to await spare parts, and saves the evaluation conclusion. This evaluation conclusion is automatically returned from the preparation terminal to the daily planning system, and an evaluation log is generated in this system. For example... Figure 2 As shown.
[0038] Furthermore, in this embodiment of the invention, after the evaluation conclusion is automatically transmitted back to the daily planning system, it can be viewed by the planning engineer. If the evaluation conclusion is that spare parts do not need to be returned, the original plan of the work order remains unchanged; if the evaluation conclusion is that spare parts need to be returned, the corresponding work order is returned to the spare parts waiting status, and the procurement and delivery are tracked according to the spare parts demand management process before being re-included in the plan. The evaluation conclusion is automatically transmitted back to the planning system through this system, allowing the planning engineer to obtain the evaluation conclusion directly without switching software systems and adjust the plan accordingly.
[0039] Furthermore, the automatic early warning method for spare parts shortages in planned work orders of nuclear power plants according to the present invention also includes: repeating steps S10 to S70 daily according to set conditions. For example, daily, according to custom configured set conditions (such as set cycle, refresh time point, etc.), the data information of planned work orders and reserved spare parts data are automatically obtained, the available inventory of spare parts reserved for daily planned work orders within the planning cycle is automatically calculated, and it is determined whether the demand is met. At the same time, the shortage risk that is not met is automatically updated to the "to-do" list of the preparation engineer, thereby realizing automatic monitoring of newly added pre-queue spare parts demand and spare parts inventory changes. A shortage risk assessment task ledger is automatically generated daily, and the planned daily planned work order spare parts shortage early warning task is automatically distributed to the preparation engineer. At the same time, the daily planned work order spare parts shortage early warning assessment conclusion is automatically transmitted to the planning management system through an interface. The planning engineer can directly know the information in the planning management system, reducing cross-system queries and offline manual communication, and improving management efficiency.
[0040] This invention automatically analyzes and calculates whether the spare parts requirements of thousands of planned equipment work orders are met, and automatically generates a shortage warning ledger for planned work orders. This automates the previously complex and inefficient manual data analysis and processing using big data software, greatly improving work efficiency and quality. The system provides multi-dimensional query and export capabilities for warning task-related work orders and spare parts status by work order number, functional location, material code, preparation engineer, maintenance center, etc., which can be used for secondary data analysis. This automated big data software system avoids repetitive manual data analysis and processing, significantly improving the accuracy of daily planning management.
[0041] refer to Figure 3 The present invention also provides a system for automatic early warning of spare parts shortage in planned work orders of nuclear power plants.
[0042] like Figure 3 As shown, the automatic early warning system for spare parts shortages in planned work orders at this nuclear power plant includes: The data acquisition unit 301 is used to acquire data information of the planned work order and reserved spare parts data; The work order screening unit 302 is used to screen work orders based on data information and reserved spare parts data to obtain valid work orders; Available inventory calculation unit 303 is used to calculate the available inventory of spare parts based on the spare parts information reserved in the valid work order. The spare parts information reserved in the valid work order includes: spare part material number, work order required quantity, required date, and the inventory quantity corresponding to the spare part material number in the database, as well as the quantity of orders delivered but not yet accepted.
[0043] The stockout warning judgment unit 304 is used to automatically verify the planned work order based on the available inventory of spare parts and determine whether it meets the verification rules. If it does, it automatically generates a spare parts stockout warning pending task for the planned work order. To-do display unit 305 is used to display spare parts shortage warning tasks in a single row according to the planned work order dimension. The task push unit 306 is used to automatically distribute spare parts shortage warning tasks to the corresponding preparation terminals.
[0044] Specifically, the coordination process between the various units in the automatic early warning system for spare parts shortages in nuclear power plant work orders can be referred to in the above-mentioned method for automatic early warning of spare parts shortages in nuclear power plant work orders, and will not be repeated here.
[0045] Furthermore, an electronic device of the present invention includes a memory and a processor; the memory is used to store a computer program; the processor is used to execute the computer program to implement the method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, as described in any of the above embodiments. Specifically, according to embodiments of the present invention, the processes described above with reference to the flowchart can be implemented as computer software programs. For example, embodiments of the present invention include a computer program product comprising a computer program carried on a computer-readable medium, the computer program containing program code for performing the methods shown in the flowchart. In such embodiments, when the computer program is downloaded, installed, and executed by an electronic device, it performs the functions defined in the methods of the embodiments of the present invention. The electronic device in the present invention can be a terminal such as a laptop, desktop computer, tablet computer, or smartphone, or it can be a server.
[0046] Furthermore, one type of storage medium of the present invention stores a computer program thereon, which, when executed by a processor, implements the method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, as described above. Specifically, it should be noted that the storage medium described above in the present invention can be a computer-readable signal medium or a computer-readable storage medium, or any combination thereof. A computer-readable storage medium can be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination thereof. More specific examples of a computer-readable storage medium may include, but are not limited to: an electrical connection having one or more wires, a portable computer disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), optical fiber, portable compact disk read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof. In the present invention, a computer-readable storage medium can be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, apparatus, or device. In this invention, a computer-readable signal medium may include a data signal propagated in baseband or as part of a carrier wave, carrying computer-readable program code. This propagated data signal may take various forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination thereof. The computer-readable signal medium may also be any computer-readable medium other than a computer-readable storage medium, capable of sending, propagating, or transmitting a program for use by or in conjunction with an instruction execution system, apparatus, or device. The program code contained on the computer-readable medium may be transmitted using any suitable medium, including but not limited to: wires, optical fibers, RF (radio frequency), etc., or any suitable combination thereof.
[0047] The aforementioned computer-readable medium may be included in the aforementioned electronic device; or it may exist independently and not assembled into the electronic device.
[0048] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on its differences from other embodiments. Similar or identical parts between embodiments can be referred to interchangeably. For the apparatus disclosed in the embodiments, since they correspond to the methods disclosed in the embodiments, the description is relatively simple; relevant parts can be referred to the method section.
[0049] Those skilled in the art will further recognize that the units and algorithm steps of the various examples described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of both. To clearly illustrate the interchangeability of hardware and software, the components and steps of the various examples have been generally described in terms of functionality in the foregoing description. Whether these functions are implemented in hardware or software depends on the specific application and design constraints of the technical solution. Those skilled in the art can use different methods to implement the described functions for each specific application, but such implementations should not be considered beyond the scope of this invention.
[0050] The steps of the methods or algorithms described in conjunction with the embodiments disclosed herein can be implemented directly by hardware, a software module executed by a processor, or a combination of both. The software module can be located in random access memory (RAM), main memory, read-only memory (ROM), electrically programmable ROM, electrically erasable programmable ROM, registers, hard disk, removable disk, CD-ROM, or any other form of storage medium known in the art.
[0051] The above embodiments are only for illustrating the technical concept and features of the present invention, and are intended to enable those skilled in the art to understand the content of the present invention and implement it accordingly. They do not limit the scope of protection of the present invention. All equivalent changes and modifications made within the scope of the claims of the present invention should fall within the scope of the claims of the present invention.
Claims
1. A method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, characterized in that, Includes the following steps: step S10: Obtain the data information of the planned work order and the spare parts data reserved in the work order; Step S20: Based on the data information and the reserved spare parts data, perform work order screening to obtain valid work orders; Step S30: Calculate the available inventory of spare parts based on the spare parts information reserved in the valid work order; The spare parts information reserved in the valid work order includes: spare parts material number, work order required quantity, required date, and the inventory quantity corresponding to the spare parts material number in the database, as well as the quantity of orders delivered but not yet accepted. Step S40: Automatically verify the planned work order based on the available inventory of the spare parts, and determine whether it meets the verification rules. If it does, automatically generate a spare parts shortage warning pending task for the planned work order. Step S50: Display the spare parts shortage warning pending tasks in a single row according to the planned work order dimension; Step S60: Automatically distribute the spare parts shortage warning task to the corresponding preparation terminal.
2. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 1, characterized in that, Following step S60, the following is also included: Step S70: Receive the evaluation conclusion returned by the preparation terminal, and generate an evaluation ledger based on the evaluation conclusion.
3. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 2, characterized in that, The method further includes: If the assessment concludes that spare parts do not need to be returned, the original plan of the work order will remain unchanged; if the assessment concludes that spare parts need to be returned, the corresponding work order will be returned to the spare parts status.
4. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 1, characterized in that, The method further includes: Repeat steps S10 to S70 daily according to the set conditions.
5. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 1, characterized in that, Step S30 includes: Obtain the spare parts information reserved in the valid work order; the spare parts information reserved in the valid work order includes: the spare parts' material number, the quantity required by the work order, the requirement date, the inventory quantity of the spare parts in the database, and the quantity of orders delivered but not accepted; The available inventory of spare parts is calculated based on the work order requirements, required dates, inventory quantities, and unaccepted order quantities reserved in the valid work orders.
6. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 5, characterized in that, The required inventory quantity satisfies the following conditions: the work order number is within the set plan, and the work order status is valid. The quantity of orders that have not been delivered and accepted meets the following condition: the purchase application corresponding to the order number and line number is in the status of "delivery not yet arrived" or "delivery pending acceptance" at the procurement node of the entire procurement process data.
7. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 1, characterized in that, The method further includes: On the spare parts shortage warning pending task display interface, the spare parts information reserved in the corresponding planned work order is displayed according to the viewing command; the reserved spare parts information includes: spare parts material code, spare parts description, inventory data, required quantity and required date data.
8. The method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants according to claim 1, characterized in that, The method further includes: The terminal is prepared to receive the spare parts shortage warning task and display the spare parts shortage warning task. Receive the evaluation conclusion of the preparation engineer on the pending tasks for the spare parts shortage warning; The evaluation results are saved and automatically transmitted to the daily planning system.
9. A system for automatic early warning of spare parts shortage in planned work orders of nuclear power plants, characterized in that, include: The data acquisition unit is used to acquire data information from planned work orders and spare parts data reserved in the work orders; The work order filtering unit is used to filter work orders based on the data information and the reserved spare parts data to obtain valid work orders; Available inventory calculation unit, used to calculate the available inventory of spare parts based on the spare parts information reserved in the valid work order; The spare parts information reserved in the valid work order includes: spare parts material number, work order required quantity, required date, and the inventory quantity corresponding to the spare parts material number in the database, as well as the quantity of orders delivered but not yet accepted. The stockout warning judgment unit is used to automatically verify the planned work order based on the available inventory of the spare parts, and determine whether it meets the verification rules. If it does, it automatically generates a spare parts stockout warning pending task for the planned work order. The to-do display unit is used to display the spare parts shortage warning to-do tasks in a single row according to the planned work order dimension. The task push unit is used to automatically distribute the spare parts shortage warning task to the corresponding preparation terminal.
10. An electronic device, characterized in that, The device includes a memory and a processor, wherein the memory stores a computer program, and the processor executes the steps of the method for automatic early warning of spare parts shortage in planned work orders of nuclear power plants as described in any one of claims 1 to 8 by calling the computer program stored in the memory.