Urban green space ecological environment monitoring project management method and system
By constructing a point-based task resource status matrix and instantiating environmental event tracking objects, and combining meteorological forecast parameters to dynamically predict the duration of water receding, the problem of management lag caused by short-term environmental changes in urban green space ecological environment monitoring projects has been solved, enabling refined management and timely decision-making, and improving the quality of project execution and management level.
Patent Information
- Application Number
- CN202611649747.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-23
- Publication Date
- 2026-11-20
AI Technical Summary
Existing urban green space ecological environment monitoring project management lacks dynamic tracking of the duration and recovery status of environmental events when dealing with short-term environmental changes. This can easily lead to treating short-term water accumulation as a continuous impact, or causing delays in management actions due to waiting for confirmation. Consequently, the task status may be incorrectly marked as requiring adjustment or further delay, thus affecting the closed loop of monitoring project progress deviation perception and resource scheduling feedback correction.
By acquiring the spatial environmental constraint parameters and task plan baseline parameters of the monitoring points, a task resource status matrix of the points is constructed, and a baseline for triggering plan adjustments is set. Environmental event tracking objects are instantiated, and the duration of water receding and recovery time are dynamically predicted in combination with meteorological forecast parameters. Based on the confidence index, the evolution branch of the obstructed state of the monitoring points is judged, and environmental monitoring project management instructions are generated.
It enables refined management and timely decision-making regarding the obstruction of monitoring points, improves the efficiency and accuracy of project management, avoids unnecessary task adjustments and resource waste, and enhances the overall execution quality and management level of urban green space ecological environment monitoring projects.
Smart Images

Figure CN123140891A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of environmental monitoring technology, and in particular to a management method and system for urban green space ecological environment monitoring projects. Background Technology
[0002] In the management of urban green space ecological environment monitoring projects, in order to achieve multi-source integration of monitoring data, resource scheduling of monitoring equipment, and dynamic tracking of project execution progress, the conventional approach is to arrange on-site personnel and monitoring equipment to collect data from each monitoring point periodically according to a predetermined monitoring task plan baseline, and manage the project based on the task progress status reported on-site. When environmental changes cause the task to be hindered, the management will decide whether to wait, postpone, or adjust the plan based on the reported abnormal status, in order to maintain the authenticity of the progress status and allocate resources reasonably.
[0003] However, urban green spaces are often in open or semi-open environments, and some low-lying monitoring points are highly susceptible to short-term water accumulation and other environmental changes after rainfall. In this scenario, the time alignment between determining the duration of environmental changes and triggering planned adjustments often becomes a critical link affecting the management loop. When short-term water accumulation renders a monitoring point temporarily inaccessible, on-site personnel typically report that the location is environmentally restricted, resulting in the task not being completed on time. While the water may recede quickly, on-site recovery information often requires manual review or feedback, leading to a time lag in recovery confirmation.
[0004] Upon receiving initial disruption information, project management needs to decide whether to adjust the plan when the duration of the environmental disruption is unclear. If management waits for confirmation of recovery, the task status will remain in a disrupted or delayed state for an extended period, even though execution may already be possible on-site. If management directly triggers a task rescheduling or personnel dispatch order, the waterlogging may have already subsided by the time the order is issued and arrives on-site. Existing conventional management methods often lack dynamic tracking of the duration and recovery status of environmental events when dealing with such short-term environmental changes, easily treating short-term waterlogging as a continuous impact, or causing delays in management actions due to waiting for confirmation. In scenarios where urban green space monitoring points are temporarily inaccessible due to short-term waterlogging, when there is a lack of time alignment between the duration of the environmental event, the assessment of recoverability, and the triggering of plan adjustments, the task status may be incorrectly marked as requiring adjustment or continuing to be delayed because the recovery confirmation is later or earlier than the plan adjustment action. This, in turn, affects the perception of progress deviations in monitoring projects and the closed loop of resource scheduling feedback and correction. Summary of the Invention
[0005] This application provides a management method and system for urban green space ecological environment monitoring projects, aiming to solve the problem that existing management methods in urban green space ecological environment monitoring projects lack dynamic tracking of the duration and recovery status of environmental events when dealing with short-term environmental changes. This can easily lead to short-term water accumulation being treated as a continuous impact, or delays in management actions due to waiting for confirmation, resulting in the task status being incorrectly marked as needing adjustment or further delay, thereby affecting the closed loop of monitoring project progress deviation perception and resource scheduling feedback correction.
[0006] Firstly, to address the aforementioned technical problems, this invention provides a management method for urban green space ecological environment monitoring projects. This method includes: acquiring spatial environmental constraint parameters and task plan baseline parameters for monitoring points; constructing a point-based task resource status matrix containing the correlation between the spatial environmental constraint parameters and the task plan baseline parameters; and setting a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary; responding to obstructed reporting information corresponding to the monitoring point; instantiating an environmental event tracking object based on the obstructed reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point-based task resource status matrix; and changing the status of the monitoring point in the point-based task resource status matrix to an obstructed and pending evaluation state. The tracking object records the obstruction start time, on-site water accumulation observation parameters, and the identification code of the monitoring point corresponding to the obstruction reporting information; obtains the meteorological forecast parameters of the area where the monitoring point is located; determines the expected dissipation time parameter and expected recovery time parameter of the monitoring point based on the meteorological forecast parameters, the on-site water accumulation observation parameters, and the spatial environmental constraint parameters; compares the expected recovery time parameter with the task plan baseline parameters to determine the recovery probability confidence index corresponding to the monitoring point; determines the obstruction state evolution branch corresponding to the monitoring point based on the expected recovery time parameter, the recovery probability confidence index, and the plan adjustment trigger baseline; and generates environmental monitoring project management instructions based on the obstruction state evolution branch.
[0007] Secondly, this application provides an urban green space ecological environment monitoring project management system, which includes: a first acquisition unit, used to acquire spatial environmental constraint parameters and task plan baseline parameters of monitoring points, construct a point task resource status matrix containing the correlation between spatial environmental constraint parameters and task plan baseline parameters, and set a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary; a first processing unit, used to respond to obstructed reporting information corresponding to the monitoring point, instantiate an environmental event tracking object according to the obstructed reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix, and change the status of the monitoring point in the point task resource status matrix to an obstructed pending evaluation state, wherein the environmental event tracking object is recorded. The system includes: a first unit for recording the obstruction start time, on-site water accumulation observation parameters, and the identification code of the monitoring point corresponding to the obstruction reporting information; a second acquisition unit for acquiring meteorological forecast parameters for the area where the monitoring point is located, determining the expected dissipation time parameter and expected recovery time parameter of the monitoring point based on the meteorological forecast parameters, the on-site water accumulation observation parameters, and the spatial environmental constraint parameters, and comparing the expected recovery time parameter with the task plan baseline parameters to determine the recovery probability confidence index corresponding to the monitoring point; and a second processing unit for determining the obstruction state evolution branch corresponding to the monitoring point based on the expected recovery time parameter, the recovery probability confidence index, and the plan adjustment trigger baseline, and generating environmental monitoring project management instructions based on the obstruction state evolution branch.
[0008] This application has at least the following beneficial effects: Through the above technical solution, this application effectively solves the problem in the existing technology of urban green space ecological environment monitoring project management that, when dealing with short-term environmental changes, there is a lack of dynamic tracking of the duration and recovery status of environmental events. This leads to the tendency to treat short-term water accumulation as a continuous impact, or to delay management actions due to waiting for confirmation, resulting in the task status being incorrectly marked as needing adjustment or further delay, thus affecting the closed loop of monitoring project progress deviation perception and resource scheduling feedback correction. This application, by introducing dynamic environmental event tracking, intelligent recovery time prediction, and confidence-based state evolution judgment, achieves refined management and timely decision-making for the obstructed state of monitoring points, significantly improving the efficiency and accuracy of project management, avoiding unnecessary task adjustments and resource waste, thereby improving the overall execution quality and management level of urban green space ecological environment monitoring projects. Attached Figure Description
[0009] Figure 1 This is a flowchart illustrating a management method for urban green space ecological environment monitoring projects provided in this application;
[0010] Figure 2This is a flowchart illustrating another urban green space ecological environment monitoring project management method provided in this application;
[0011] Figure 3 This is a schematic diagram of the structure of an urban green space ecological environment monitoring project management system provided in this application. Detailed Implementation
[0012] The technical solutions of this application will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are merely some embodiments of this application, and not all embodiments. The components of this application described and shown in the accompanying drawings can generally be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of this application provided in the accompanying drawings is not intended to limit the scope of the claimed application, but merely to illustrate selected embodiments of this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application.
[0013] It should be noted that similar reference numerals and letters in the following figures indicate similar items; therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures. Furthermore, in the description of this application, terms such as "first," "second," etc., are used only to distinguish descriptions and should not be construed as indicating or implying relative importance.
[0014] In the management of urban green space ecological environment monitoring projects, the traditional management method typically follows a predetermined baseline of monitoring task plans, arranging on-site personnel and monitoring equipment to collect data from various monitoring points on a periodic basis, and managing the project based on the task progress status reported on-site. However, when environmental changes cause task obstruction, such as some low-lying monitoring points being prone to short-term water accumulation after rainfall, the existing management method often lacks dynamic tracking of the duration and recovery status of environmental events. This can easily lead to treating short-term water accumulation as a continuous impact, or causing delays in management actions due to waiting for confirmation. Consequently, the task status may be incorrectly marked as requiring adjustment or further delay, thus affecting the perception of monitoring project progress deviations and the closed loop of resource scheduling feedback and correction.
[0015] In view of the above problems, this application provides a management method for urban green space ecological environment monitoring projects. By dynamically tracking the duration and recovery status of environmental events, it realizes intelligent assessment of monitoring task obstruction and timely generation of management instructions, thereby effectively solving the problems of lag and misjudgment in traditional management methods when dealing with short-term environmental changes, and improving the efficiency and accuracy of project management.
[0016] The following specific examples will provide a detailed introduction and explanation of the urban green space ecological environment monitoring project management method provided in this application.
[0017] Reference Figure 1 This application provides a method for managing urban green space ecological environment monitoring projects, which may include the following steps:
[0018] S101. Obtain the spatial environment constraint parameters and task plan baseline parameters of the monitoring points, construct a point task resource status matrix that includes the correlation between the spatial environment constraint parameters and the task plan baseline parameters, and set a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary.
[0019] S102. In response to the obstruction reporting information corresponding to the monitoring point, based on the obstruction reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix, instantiate an environmental event tracking object and change the status of the monitoring point in the point task resource status matrix to an obstruction pending evaluation state.
[0020] Among them, the environmental incident tracking records include the start time of the obstruction, the on-site water accumulation observation parameters, and the identification code of the monitoring point corresponding to the obstruction reporting information.
[0021] S103. Obtain meteorological forecast parameters for the area where the monitoring point is located. Based on the meteorological forecast parameters, on-site water accumulation observation parameters, and spatial environmental constraint parameters, determine the expected duration of water receding and the expected recovery time parameters for the monitoring point. Compare the expected recovery time parameters with the baseline parameters of the mission plan to determine the recovery probability confidence index corresponding to the monitoring point.
[0022] S104. Based on the expected recovery time parameters, recovery probability confidence index, and planned adjustment trigger baseline, determine the obstructed state evolution branch corresponding to the monitoring point, and generate environmental monitoring project management instructions according to the obstructed state evolution branch.
[0023] To better understand the method proposed in this application, some key terms involved will be explained first.
[0024] "Spatial environmental constraint parameters" refer to static or semi-static attributes related to the geographical environment of the monitoring point, such as topographic elevation, soil type, and vegetation cover. These parameters affect the formation, retention, and receding of water. "Task plan baseline parameters" refer to the initial task execution plan set for the monitoring point, including the task's start time, end time, and required resources. "Point Task Resource Status Matrix" is a data structure used to store and manage information such as spatial environmental constraint parameters, task plan baseline parameters, and task execution status for each monitoring point, and reflects the relationships between these parameters. "Plan Adjustment Trigger Baseline" is a time point set for each monitoring point, representing the latest time boundary for plan adjustments without affecting the overall project schedule. "Obstruction Reporting Information" refers to reports submitted by on-site personnel through the system regarding task obstruction at the monitoring point, typically including the cause of obstruction and on-site conditions. "Environmental Event Tracking Object" is a data entity used to record and track detailed information about specific environmental events (such as water accumulation), including the event's start time, on-site observation data, and associated monitoring point identification codes. "Blocked and Awaiting Evaluation Status" is an intermediate state for a monitoring point's task, indicating that the task is suspended due to obstruction and awaits further evaluation and decision-making from the system. "Weather Forecast Parameters" refer to weather forecast data about the monitoring point's location obtained from meteorological services, such as rainfall intensity and duration. "Expected Receding Duration Parameter" refers to the predicted time required for the accumulated water to completely recede from its current state, based on various environmental and meteorological conditions. "Expected Recovery Time Parameter" refers to the specific time point at which the monitoring point will return to a normal, executable state, calculated based on the expected receding duration parameter. "Recovery Probability Confidence Index" assesses the confidence level of whether the monitoring point can recover within the planned time, typically categorized as high, medium, or low. "Blocked State Evolution Branches" refer to different processing paths planned for the blocked state of the monitoring point based on the evaluation results, such as short-term waiting, critical uncertainty, or continuous obstruction. "Environmental Monitoring Project Management Instructions" are specific management operation instructions generated by the system based on the blocked state evolution branches, such as waiting instructions, high-frequency observation instructions, or rescheduling instructions.
[0025] The method proposed in this application first requires obtaining the spatial environmental constraint parameters and task plan baseline parameters of the monitoring points, constructing a task resource status matrix for each monitoring point, and setting a plan adjustment trigger baseline for each monitoring point. In practice, spatial environmental constraint parameters can be obtained in various ways. For example, topographic elevation information of the monitoring points can be obtained through Geographic Information System (GIS) data, soil type and permeability data can be obtained through field surveys or remote sensing image analysis, or the average frequency of water accumulation and natural receding time of the area can be obtained through historical data analysis. The task plan baseline parameters are usually generated by the project management system during the task planning phase, including the planned start time, planned end time of the task, and resource information such as the required on-site personnel and monitoring equipment. The construction of the task resource status matrix can be done using a relational database or a NoSQL database, using the monitoring point identifier as the primary key to associate and store the aforementioned spatial environmental constraint parameters, task plan baseline parameters, and task execution status fields. The setting of the plan adjustment trigger baseline can be based on the latest end time of the task plan, taking into account the travel time required for on-site personnel to transfer to the next planned monitoring point, and determined through a time subtraction operation. For example, if the latest end time of a monitoring point's task plan is 5 p.m., and it takes 30 minutes to move from that point to the next point, then the task adjustment trigger baseline can be set at 4:30 p.m.
[0026] When a blocked reporting information corresponding to a monitoring point is received, the system instantiates an environmental event tracking object based on this information and the spatial environmental constraint parameters associated with that monitoring point in the point's task resource state matrix. Simultaneously, the status of the monitoring point in the point's task resource state matrix is changed to a blocked and awaiting evaluation state. Blocked reporting information can be manually submitted by on-site personnel via a mobile application, or automatically detected and reported by sensors installed at the monitoring point. This information typically includes the start time of the blockage, on-site water accumulation observation parameters (such as estimated water accumulation area and current rainfall status observations), and the monitoring point's identification code. The instantiation of the environmental event tracking object can be a software object whose attributes include the start time of the blockage, on-site water accumulation observation parameters, the monitoring point's identification code, and the relative values of terrain elevation and permeability coefficient extracted from the point's task resource state matrix. This object also reserves fields for estimated recovery time, event duration flags, and a secondary confirmation countdown for subsequent dynamic updates and management. Changes in the status of monitoring points can be achieved by updating the task execution status field of the corresponding monitoring point record in the point task resource status matrix.
[0027] Next, the system will acquire meteorological forecast parameters for the area where the monitoring point is located, and combine these with on-site water accumulation observation parameters and spatial environmental constraint parameters to determine the expected recession duration and expected recovery time parameters for the monitoring point. Then, the expected recovery time parameter will be compared with the baseline parameters of the task plan to determine the recovery probability confidence index corresponding to the monitoring point. Meteorological forecast parameters can be obtained by calling a third-party meteorological service interface to acquire real-time rainfall intensity and future short-term rainfall forecast data. The determination of the expected recession duration parameter needs to be dynamically adjusted based on the meteorological forecast parameters. For example, if the meteorological forecast indicates continuous rainfall and the real-time rainfall intensity is greater than the permeability coefficient corresponding to the permeability, a preset delay penalty value can be set as the expected recession duration parameter. If the meteorological forecast indicates that rainfall has stopped or is about to stop, a comprehensive correction coefficient needs to be calculated, taking into account factors such as the ratio of the estimated on-site water accumulation area to the historical average water accumulation area, and the reduction ratio of the soil's previous moisture content parameter to the permeability coefficient. This coefficient will then be used to correct the historical average natural recession duration, thereby obtaining a more accurate expected recession duration parameter. The expected recovery time parameter is calculated by summing the start time of the obstruction with the expected duration of regression. The confidence level of the recovery probability is determined by comparing the expected recovery time parameter with the latest end time of the task plan in the baseline parameters of the task plan. For example, if the expected recovery time parameter is earlier than the latest end time of the task plan and the time difference is greater than a preset first threshold, it can be judged as high confidence; if the time difference is between the preset first threshold and a preset second threshold, it is judged as medium confidence; if the expected recovery time parameter is later than the latest end time of the task plan, or the time difference is less than or equal to the preset second threshold, it is judged as low confidence.
[0028] Finally, based on the expected recovery time parameter, the recovery probability confidence index, and the planned adjustment trigger baseline, the system determines the obstructed state evolution branch corresponding to the monitoring point and generates corresponding environmental monitoring project management instructions based on this evolution branch. Determining the obstructed state evolution branch is a decision-making process. For example, if the expected recovery time parameter is later than or equal to the planned adjustment trigger baseline, or the recovery probability confidence index is a low confidence value, the monitoring point is determined to have entered the persistent obstructed evolution branch, indicating that the task has exceeded the task window tolerance limit. If it has not entered the persistent obstructed evolution branch, but the expected recovery time parameter is earlier than the planned adjustment trigger baseline and the time difference is less than or equal to the preset system buffer margin parameter, or the recovery probability confidence index is a medium confidence value, the monitoring point is determined to have entered the critical uncertainty evolution branch, indicating a risk of recovery fluctuations. In other cases, the monitoring point is determined to have entered the short-term waiting evolution branch, indicating that on-site waiting conditions are met. Based on the determined obstructed state evolution branch, the system generates different environmental monitoring project management instructions. For example, for the short-term waiting evolution branch, a short-term dwell-wait instruction can be generated, instructing on-site personnel to wait until the expected recovery time parameter. For the critically uncertain evolution branch, a high-frequency observation instruction can be generated, requiring on-site personnel to submit on-site status image data within a specified warning time threshold for further system evaluation. For the persistently blocked evolution branch, a rescheduling instruction may be generated, changing the task status of the monitoring point to a rescheduled state and releasing the occupancy lock on on-site personnel and monitoring equipment to allow for resource reallocation.
[0029] The urban green space ecological environment monitoring project management method proposed in this application constructs a comprehensive monitoring point status management framework by introducing spatial environmental constraint parameters, task plan baseline parameters, point task resource status matrix, and plan adjustment trigger baseline. When a monitoring point is obstructed due to environmental changes, the system can respond to obstruction reporting information, instantiate environmental event tracking objects, and promptly change the monitoring point status to an obstructed and awaiting assessment state. Subsequently, by acquiring meteorological forecast parameters and combining them with field observation data and spatial environmental constraint parameters, the system can accurately predict the expected receding time and expected recovery time of water accumulation, and assess the recovery probability confidence level. Based on these dynamic assessment results, the system can intelligently determine the obstruction state evolution branch of the monitoring point (short-term waiting, critical uncertainty, or continuous obstruction) and generate corresponding environmental monitoring project management instructions accordingly.
[0030] In some embodiments, reference is made to Figure 2This application further proposes the following steps for obtaining the spatial environmental constraint parameters and task plan baseline parameters of the monitoring points, constructing a point task resource status matrix containing the correlation between the spatial environmental constraint parameters and the task plan baseline parameters, and setting a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary:
[0031] S201. Extract the relative values of topographic elevation corresponding to the monitoring points, the permeability coefficient of the green space type, the average frequency of water accumulation in historical rainfall events, the average historical water accumulation range, and the average historical natural receding time to obtain spatial environmental constraint parameters.
[0032] S202. Extract the start time and latest end time of the task plan assigned to the monitoring points to obtain the task plan baseline parameters, and extract the bound on-site execution personnel number, monitoring equipment type and resource occupation cycle to obtain the on-site execution resource parameters.
[0033] S203. Construct a point task resource status matrix that uses the monitoring point identification code as an index and associates and stores spatial environmental constraint parameters, task plan baseline parameters, on-site execution resource parameters, and task execution status fields.
[0034] The task execution status field is configured as pending execution during initialization to record the status changes of monitoring point tasks when they are subsequently blocked and reported.
[0035] S204. Based on the latest end time of the task plan and the travel time required for on-site personnel to transfer to the next planned monitoring point, determine the plan adjustment trigger baseline corresponding to the monitoring point through a subtraction operation.
[0036] Specifically, spatial environmental constraint parameters refer to static or semi-static data related to the geographical environment and historical climate conditions of the monitoring site. For example, the relative value of topographic elevation can reflect the degree of depression of the site relative to the surrounding area, thus indicating its risk of water accumulation; the permeability coefficient of the green space type is directly related to the soil's infiltration capacity, affecting the rate of water receding; the average frequency of water accumulation, the average extent of water accumulation, and the average duration of natural receding during historical rainfall events provide typical response patterns of the site in the past when facing rainfall events, providing important basis for predicting future water accumulation. The extraction of these parameters aims to comprehensively characterize the environmental vulnerability of the monitoring site.
[0037] Among them, the task plan baseline parameters are the pre-defined time nodes and resource allocation information in project management. The task plan start time and the latest task plan end time define the execution window of the monitoring task and are the basis for measuring task progress and assessing the risk of delays. The on-site personnel number, monitoring equipment type, and resource occupancy period record in detail the specific human and material resources required to complete the task, as well as the length of time these resources are occupied, which is crucial for subsequent resource scheduling and conflict resolution.
[0038] In practical applications, the monitoring point task resource status matrix is constructed as a structured data storage format, with the monitoring point identifier code as its core index. This index allows for the associated storage of the extracted spatial environmental constraint parameters, task plan baseline parameters, and on-site execution resource parameters. Furthermore, the matrix includes a task execution status field, which is set to a pending execution state during task initialization. Its main purpose is to dynamically record the status changes of the monitoring point task during subsequent execution, especially when encountering and reporting obstacles, such as changing from pending execution to obstructed and awaiting evaluation. This centralized storage method ensures the traceability and consistency of all relevant information.
[0039] Furthermore, the plan adjustment trigger baseline is a key time point used to characterize the latest plan adjustment time boundary. It is determined based on the latest end time of the planned task, taking into account the travel time required for on-site personnel to move from the current monitoring point to the next planned monitoring point. By subtracting the required travel time from the latest end time of the planned task, a lead time is obtained; this lead time is the plan adjustment trigger baseline. The purpose of setting this baseline is to provide project managers with an early warning window, ensuring sufficient time for plan adjustments if the task may not be completed on time, thus avoiding a chain reaction affecting subsequent tasks.
[0040] Through the aforementioned technical solutions, this application enables refined and intelligent initial data acquisition and system configuration in the management of urban green space ecological environment monitoring projects. Specifically, by extracting detailed spatial environmental constraint parameters, the system can more accurately assess the environmental vulnerability and water accumulation risk of monitoring sites, providing more reliable input for subsequent calculations of expected receding duration and recovery time. The explicit extraction of task plan baseline parameters and on-site execution resource parameters makes resource allocation and task scheduling more transparent and efficient. The construction of a site task resource status matrix centrally manages all key information, greatly improving data consistency and traceability, and providing a unified platform for dynamic monitoring and management. Most importantly, the setting of a plan adjustment trigger baseline allows the system to provide early warnings of potential plan delays, giving project managers valuable decision-making time and effectively reducing the overall delay risk caused by environmental factors, thus improving the predictability and responsiveness of project management.
[0041] In some embodiments described above in this application, a method is proposed that, in response to obstructed reporting information corresponding to a monitoring point, an environmental event tracking object is instantiated based on the obstructed reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix. The status of the monitoring point in the point task resource status matrix is then changed to an obstructed and pending evaluation state. Specifically, the above steps can be further refined into the following operations:
[0042] Upon receiving a report of obstruction from the field monitoring point, the system records the system time of the reception as the start time of the obstruction. Simultaneously, it extracts the estimated area of water accumulation and the current rainfall status observation values from the obstruction report to obtain the field water accumulation observation parameters. The obstruction report also carries the identification code of the monitoring point.
[0043] Subsequently, the obstruction initiation time, the on-site water accumulation observation parameters, the identification code, and the relative values of terrain elevation and permeability coefficient from the spatial environmental constraint parameters are encapsulated to create and instantiate the environmental event tracking object. This environmental event tracking object is designed to centrally manage all information related to a specific obstruction event.
[0044] The environmental event tracking object will include fields for estimated recovery time, event duration flags, and secondary confirmation countdown. These fields are designed to provide necessary data storage and management functions for subsequent event assessment, status tracking, and on-site verification.
[0045] Finally, in the location task resource status matrix, the system will use the identifier code as an index to find the corresponding record and change the task execution status field in the corresponding record from the initial pending status to the obstructed and awaiting evaluation status. This status change indicates that the task at this monitoring point is currently obstructed and requires further evaluation and processing.
[0046] Through the aforementioned technical solutions, this application can significantly improve the response efficiency and management precision of urban green space ecological environment monitoring projects when faced with sudden environmental obstructions. Specifically, accurately recording the onset time of obstruction and on-site water accumulation observation parameters provides reliable initial data for subsequent calculations of the estimated receding time and recovery time, thereby improving the accuracy of predictions. Instantiating environmental event tracking objects and reserving key tracking fields allows each obstruction event to be managed and tracked independently and comprehensively, effectively avoiding information dispersion and processing chaos, and ensuring traceability throughout the entire event lifecycle. Simultaneously, timely updating the task execution status of monitoring points to an obstruction-awaited-assessment status enables the project management system to reflect the on-site situation in real time and accurately, providing timely and accurate decision-making basis for subsequent risk assessment, task rescheduling, or resource allocation, thereby effectively reducing the risk of project delays and enhancing the resilience and adaptability of overall project management.
[0047] This application further proposes a step of obtaining meteorological forecast parameters for the area where the aforementioned monitoring points are located, and determining the expected recession duration and expected recovery time parameters for the monitoring points based on the meteorological forecast parameters, the on-site water accumulation observation parameters, and the spatial environmental constraint parameters. Specifically, this includes: calling a preset meteorological interface to obtain the real-time rainfall intensity and short-term rainfall forecast data for a preset period starting from the current time in the area where the monitoring points are located, as the meteorological forecast parameters; and determining a preset delay penalty value as the expected recession when the meteorological forecast parameters indicate continuous rainfall and the real-time rainfall intensity is greater than the permeability corresponding to the permeability coefficient. Duration parameter; when the meteorological forecast parameter indicates that rainfall has stopped or is about to stop, the soil pre-accelerated moisture content parameter of the area where the monitoring point is located is obtained. Based on the ratio of the estimated on-site water accumulation range to the historical average water accumulation range in the spatial environmental constraint parameters, and the reduction ratio of the soil pre-accelerated moisture content parameter to the permeability coefficient, a comprehensive correction coefficient is determined. The historical average natural recession duration in the spatial environmental constraint parameters is then corrected using the comprehensive correction coefficient to obtain the expected recession duration parameter. The expected recovery time parameter is obtained by summing the obstruction start time and the expected recession duration parameter.
[0048] Specifically, calling the preset meteorological interface refers to obtaining real-time meteorological data and short-term meteorological forecasts through a data communication channel established with an external meteorological service system. Real-time rainfall intensity refers to the rainfall amount in the monitored area at the current moment, while short-term rainfall forecast data refers to the predicted rainfall trend over the next few hours or day. These meteorological forecast parameters provide important environmental basis for judging the receding of waterlogged areas. The permeability coefficient, corresponding to the infiltration rate, can be understood as the maximum amount of water that a specific type of green space soil can infiltrate per unit time. When the real-time rainfall intensity exceeds this infiltration rate, it indicates that the rainfall is greater than the soil's absorption capacity, and waterlogging will continue or worsen. The preset delay penalty value is a pre-set time length used to conservatively estimate the additional time required for waterlogging to recede in cases of continuous rainfall and insufficient infiltration capacity. The soil pre-moisture content parameter refers to the soil moisture level in the monitored area before a rainfall event; its level directly affects the soil's subsequent infiltration capacity. The ratio of the estimated on-site waterlogging area to the historical average waterlogging area is used to quantify the difference between the current waterlogging severity and the historical average. The reduction ratio of soil pre-congestion moisture content to permeability coefficient means that the higher the soil moisture content, the lower the permeability coefficient, thus slowing down the rate of water receding. The comprehensive correction coefficient is a factor that combines the current waterlogging situation with changes in soil permeability; it is used to adjust the historical average natural receding time to better reflect the current situation. Time accumulation calculation involves simply adding the start time of the obstruction to the expected receding time parameter to obtain the predicted time point when the water has completely receded and the area is back to a workable state.
[0049] Through the aforementioned technical solution, this application can dynamically and accurately predict the duration and recovery time of water accumulation at monitoring points based on real-time meteorological conditions and changes in the on-site environment, avoiding errors caused by simple estimations or experience-based judgments. This significantly improves the accuracy and reliability of project planning, enabling subsequent project management instructions (such as short-term stays, high-frequency observations, or rescheduling) to be based on more robust data support. This effectively reduces project delays and resource waste caused by environmental emergencies, and enhances the overall management efficiency and response capabilities of urban green space ecological environment monitoring projects.
[0050] This application further proposes a step of comparing the expected recovery time parameter with the task plan baseline parameter to determine the recovery probability confidence index corresponding to the monitoring point. Specifically, it includes: extracting the latest end time of the task plan from the task plan baseline parameter; assigning a high confidence value to the recovery probability confidence index when the expected recovery time parameter is earlier than the latest end time of the task plan and the time difference between the two is greater than a preset first judgment threshold; assigning a medium confidence value to the recovery probability confidence index when the time difference between the expected recovery time parameter and the latest end time of the task plan is less than or equal to the preset first judgment threshold and greater than a preset second judgment threshold; and assigning a low confidence value to the recovery probability confidence index when the expected recovery time parameter is later than the latest end time of the task plan, or the time difference between the two is less than or equal to the preset second judgment threshold.
[0051] Specifically, the latest end time of the task plan refers to the latest time point in the task plan assigned to the monitoring point that the task must be completed, representing the hard time constraint of the task plan. The preset first and second judgment thresholds are time differences pre-set by the system to divide the recovery probability into different confidence intervals. For example, the preset first judgment threshold can be set to 2 hours, and the preset second judgment threshold can be set to 30 minutes. A high confidence value indicates that the monitoring point has a very high probability of recovering before the latest end time of the task plan, with sufficient buffer time; a medium confidence value indicates that the monitoring point has a certain probability of recovering before the latest end time of the task plan, but time is tight, and there is a certain risk of fluctuation; a low confidence value indicates that the recovery time of the monitoring point is likely to be later than the latest end time of the task plan, or even if it recovers within the plan, there is almost no buffer time, and the recovery risk is extremely high.
[0052] Through the aforementioned technical solution, this application provides a more refined and risk-aware decision-making basis for urban green space ecological environment monitoring project management. By comparing the expected recovery time parameter with the latest planned task completion time at multiple levels and introducing high, medium, and low confidence indices, the system no longer simply provides a recovery time point, but rather a quantitative assessment of the recovery probability. This allows managers to more accurately determine the risk level of completing the task on schedule, and thus, when the task is hindered, to take more appropriate and timely response strategies based on different confidence levels, such as choosing short-term waiting, high-frequency observation, or immediate rescheduling. This significantly improves the flexibility and risk response capability of project management, avoiding decision-making errors and resource waste caused by inaccurate predictions of a single time point.
[0053] This application further proposes a method to determine the obstructed state evolution branch corresponding to a monitoring point based on the expected recovery time parameter, the recovery probability confidence index, and the planned adjustment trigger baseline. Specifically, this includes: when the expected recovery time parameter is later than or equal to the planned adjustment trigger baseline, or the recovery probability confidence index is a low confidence value, determining that the monitoring point enters a persistent obstructed evolution branch that represents exceeding the task window tolerance limit; if the expected recovery time parameter is earlier than the planned adjustment trigger baseline and the time difference between the two is less than or equal to a preset system buffer margin parameter, or the recovery probability confidence index is a medium confidence value, determining that the monitoring point enters a critically uncertain evolution branch that represents the risk of recovery fluctuations; if the monitoring point enters neither the persistent obstructed evolution branch nor the critically uncertain evolution branch, determining that the monitoring point enters a short-term waiting evolution branch that represents on-site waiting conditions; and using the determined evolution branch as the obstructed state evolution branch corresponding to the monitoring point.
[0054] Specifically, the "obstructed state evolution branches" refer to the different processing paths categorized based on the severity and recovery probability of the obstructed monitoring point. The "persistent obstruction evolution branch" indicates that the estimated recovery time of the monitoring point exceeds the tolerance limit of the current task plan, or the probability of recovery is extremely low, indicating that the task at that point needs significant adjustment or rescheduling. The "critical uncertainty evolution branch" indicates that although the estimated recovery time of the monitoring point is before the planned adjustment trigger baseline, the time difference from the baseline is small, or the recovery probability confidence index is at a moderate level, indicating that there is some uncertainty in the recovery of the point, requiring close monitoring and further evaluation. The "short-term waiting evolution branch" indicates that the estimated recovery time of the monitoring point is much earlier than the planned adjustment trigger baseline, and the recovery probability confidence index is high, indicating that the point is expected to recover in a short time, and on-site personnel can wait briefly. The preset system buffer margin parameter can be understood as the time margin reserved by the system to cope with emergencies or minor delays, its purpose being to avoid prematurely triggering complex task rescheduling processes due to small time deviations.
[0055] The aforementioned technical solution enables refined management and intelligent decision-making regarding the status of obstructed monitoring points in urban green space ecological environment monitoring projects. This solution not only effectively avoids resource waste and inefficiency caused by blind waiting or premature rescheduling, but also significantly improves project management flexibility and the ability to respond to emergencies. By clearly distinguishing between three evolutionary branches—persistent obstruction, critical uncertainty, and short-term waiting—the system can provide the most suitable management strategy for each situation, thereby optimizing the workflow of on-site personnel, reducing the risk of project delays, and ultimately improving the overall efficiency of the monitoring project and the timeliness of data collection.
[0056] This application further proposes a scheme for generating environmental monitoring project management instructions based on the aforementioned obstructed state evolution branch, specifically including: when the obstructed state evolution branch is the short-term waiting evolution branch, generating a short-term dwell waiting instruction containing the expected recovery time parameter and the suggested waiting duration, and sending it to the mobile terminal of the associated on-site personnel; changing the status of the corresponding monitoring point in the point task resource status matrix to the controlled waiting status, and starting the countdown timer corresponding to the secondary confirmation countdown field in the environmental event tracking object, and sending an on-site status verification request signal when the countdown is triggered; When the obstructed state evolution branch is the critical uncertain evolution branch, a high-frequency observation command is generated, instructing on-site personnel to submit on-site status image data within a specified warning time threshold before reaching the planned adjustment trigger baseline; a preset image recognition algorithm is used to extract water receding features from the on-site status image data; when a feature quantity representing water receding is extracted, the planned adjustment trigger baseline is extended and the monitoring point is transferred to the short-term waiting evolution branch; when no feature quantity representing water receding is extracted, the monitoring point is forcibly transferred to the continuously obstructed evolution branch.
[0057] Specifically, when the system determines that a monitoring point has entered a short-term waiting evolution branch, it means that the expected recovery time parameter is relatively early and the recovery probability confidence index is high, indicating that the site meets the conditions for short-term waiting. At this time, the system will generate a short-term stay-wait instruction, which explicitly includes the expected recovery time parameter and the suggested waiting duration, and will be sent to the mobile terminals of the associated on-site personnel. This aims to guide on-site personnel to wait in place, avoiding unnecessary evacuation and rescheduling, thereby saving travel time and resources. At the same time, the status of the monitoring point in the point task resource status matrix will be updated to a controlled waiting state to reflect its current project management status. To ensure the effectiveness of the waiting and to obtain the latest on-site situation in a timely manner, a countdown timer corresponding to the secondary confirmation countdown field will be started in the environmental event tracking object. When this countdown timer is triggered, the system will automatically send an on-site status verification request signal, prompting on-site personnel to conduct a secondary confirmation of the water receding situation to ensure the accuracy of the information.
[0058] When a monitoring point enters the critical uncertainty evolution branch, it indicates that the expected recovery time parameter is close to the planned adjustment trigger baseline, or the recovery probability confidence index is moderate, posing a risk of recovery fluctuation. In this case, the system generates a high-frequency observation instruction, directing on-site personnel to submit on-site status image data within a specified warning time threshold before reaching the planned adjustment trigger baseline. The purpose of this instruction is to obtain real-time visual information before key decision-making points, assisting the system in making more accurate judgments. In practical applications, a preset image recognition algorithm is used to extract water receding features from the on-site status image data. For example, this algorithm can analyze the water area, depth changes, and water surface reflection characteristics in the image to determine whether the water is receding. If the algorithm successfully extracts features characterizing water receding, it indicates that the on-site situation has improved, and the system will correspondingly extend the planned adjustment trigger baseline and transfer the monitoring point to the short-term waiting evolution branch, giving it more recovery time. Conversely, if no characteristic quantity representing the receding of water accumulation is extracted, it indicates that the water accumulation situation has not improved or continues to worsen. The system will force the monitoring point to be transferred to the continuously obstructed evolution branch in order to initiate a higher-level task rescheduling or rescheduling process.
[0059] Through the aforementioned technical solution, this application can generate more refined and dynamic project management instructions based on the evolutionary branches of the obstruction status at monitoring points. Specifically, for short-term obstruction situations with expected rapid recovery, generating short-term dwell-wait instructions supplemented by a secondary confirmation mechanism effectively avoids unnecessary task rescheduling, reducing resource waste and project interruptions. For critical obstruction situations with uncertain recovery, high-frequency observation instructions and image recognition algorithms are introduced to achieve real-time and objective assessment of the on-site situation. This allows the system to dynamically adjust the plan and trigger baseline based on actual decay characteristics and flexibly transfer tasks to more suitable evolutionary branches, thereby significantly improving the response speed and decision-making accuracy of project management. This hierarchical and dynamic instruction generation mechanism effectively reduces plan deviations caused by environmental events and improves the overall execution efficiency and adaptability of urban green space ecological environment monitoring projects.
[0060] This application further proposes the following steps for generating environmental monitoring project management instructions based on the aforementioned obstructed state evolution branch: when the obstructed state evolution branch is the continuously obstructed evolution branch, the status of the monitoring point is changed to a rescheduled state, and the occupancy lock status of the monitoring point on the corresponding on-site personnel and monitoring equipment is released; the current spatial location coordinates and remaining available working time parameters of the on-site personnel after the occupancy lock status is released are obtained, and the target candidate monitoring points that meet the shortest path condition and are in the pending execution state are traversed and searched in the point task resource status matrix; the estimated travel time for the on-site personnel to transfer to the target candidate monitoring point is calculated, and when the task plan window of the target candidate monitoring point matches the remaining available working time parameter, a point-change execution instruction pointing to the target candidate monitoring point is generated as the task rescheduling instruction; the original monitoring point corresponding to the continuously obstructed evolution branch is moved into the unassigned task pool, and a suggested rescheduled execution time parameter is automatically generated based on the rainless weather forecast window within a predetermined period.
[0061] Specifically, when a monitoring point is determined to have entered a continuously obstructed evolution branch, it indicates that the point has exceeded the tolerance limit of the task window and cannot be restored within the originally planned time. In this case, the system will update the task execution status of the monitoring point in the point task resource status matrix to a rescheduled state, clearly indicating that it will no longer be executed as originally planned. At the same time, to avoid resource waste, the system will immediately release the occupancy lock status of the monitoring point on the associated on-site personnel and monitoring equipment, allowing these resources to be reallocated.
[0062] After the lockout is lifted, the system obtains the real-time spatial coordinates of the on-site personnel and their remaining available working hours for the current workday or a specified period. These parameters are crucial for subsequent task rescheduling and resource optimization. The system then searches the point-task resource status matrix, starting from the on-site personnel's current location, for all monitoring points in a pending execution state. During the search, points whose spatial distance meets the shortest path condition are prioritized to maximize the efficiency of the on-site personnel.
[0063] In practical applications, for each candidate monitoring point that meets the criteria, the system calculates the estimated travel time required for on-site personnel to move from their current location to that candidate point. Next, the system compares the candidate point's task schedule window (i.e., its scheduled start time and latest scheduled end time) with the remaining available working time of the on-site personnel. If the task at the candidate point can be completed within the remaining available working time of the on-site personnel, and its task schedule window matches the remaining available working time parameter, the system generates a relocation instruction pointing to that target candidate monitoring point. This instruction, as a task rescheduling instruction, is issued to the on-site personnel, guiding them to the new monitoring point to perform their tasks.
[0064] In addition, monitoring sites that were previously unable to execute tasks due to persistent obstruction will have their tasks moved to an unassigned task pool. The system will continuously monitor weather forecast data, especially the rainless weather forecast window within the predetermined period, and automatically generate a suggested rescheduled execution time parameter. This parameter will be used to replan and reschedule tasks for the obstructed site to ensure monitoring is carried out under suitable weather conditions.
[0065] Through the aforementioned technical solution, this application provides an efficient, flexible, and intelligent response strategy for extreme situations of continuous obstruction in urban green space ecological environment monitoring project management. This solution significantly enhances project management resilience, preventing overall project stagnation or resource waste due to localized environmental events. Specifically, by promptly unlocking resources and intelligently matching alternative tasks, it effectively reduces the idle time of on-site personnel and monitoring equipment, improving resource utilization efficiency. Simultaneously, by including obstructed tasks in an unassigned task pool and automatically generating rescheduling suggestions, it provides project managers with clear directions for subsequent handling, helping to smooth the project schedule curve and reduce schedule deviations caused by unforeseen events. This proactive risk management and task rescheduling mechanism enables the project to maintain high operational efficiency and project continuity even in the face of force majeure, thereby ensuring the smooth progress of urban green space ecological environment monitoring.
[0066] This application further proposes a method for continuously monitoring the project execution status, evaluating progress, and verifying data consistency after generating environmental monitoring project management instructions, so as to ensure the comprehensiveness, real-time nature, and data accuracy of project management.
[0067] Specifically, after generating environmental monitoring project management instructions based on the obstructed state evolution branch, the method further includes: when the state of the corresponding monitoring point in the point task resource state matrix changes from a controlled waiting state to a completed state, recording the additional time consumption parameter caused by waiting, calculating the squeeze bias amount on the time window of subsequent related tasks using the additional time consumption parameter, and outputting a travel time compression warning signal for subsequent tasks when the squeeze bias amount is greater than a preset tolerance threshold; when the state of the corresponding monitoring point in the point task resource state matrix changes to a rescheduled state, shifting the expected completion date of the target monitoring project using the suggested rescheduled execution time parameter, and calculating the overall progress deviation parameter between the expected completion date and the initial baseline date; when the overall progress deviation parameter is greater than the contract tolerance threshold parameter, generating a progress delay risk report for the related environmental event tracking object; calling the global state consistency verification service to perform a consistency comparison on the data in the point task resource state matrix and the environmental event tracking object, and releasing and resetting tasks in a dangling state that are neither waiting nor rescheduled, as well as deadlocked resources that have no task assignment but have not been released.
[0068] Specifically, "when the status of the corresponding monitoring point in the task resource status matrix changes from a controlled waiting state to a completed state" means that after a monitoring point enters a controlled waiting state due to a short-term waiting evolution branch, the on-site personnel complete the monitoring task and update the task status to completed after the expected recovery time parameter is reached or the water accumulation recedes. At this time, the system automatically records the additional time consumed due to waiting from the start of the obstruction to the task completion time. This additional time consumption parameter can be understood as the difference between the actual task completion time and the originally planned task completion time, and its purpose is to quantify the actual impact of waiting on the project progress. Furthermore, using this additional time consumption parameter, the system calculates the compression bias on the time window of subsequent related tasks. The compression bias refers to the compression or shift in the time window of subsequent closely related tasks (e.g., the next monitoring point task handled by the same on-site personnel) caused by the additional time consumption of the current task, which may lead to the planned start or end time of the task being brought forward or delayed. When the squeeze offset exceeds the preset tolerance threshold, it indicates that the delay caused by waiting has had a significant impact on subsequent tasks. At this point, the system will output a travel time compression warning signal for subsequent tasks, reminding on-site personnel or the scheduling system to consider compressing travel time or adjusting the arrangement of subsequent tasks to avoid cascading delays. The preset tolerance threshold can be configured based on project management experience or actual business needs, for example, set to 15 minutes or 30 minutes.
[0069] Furthermore, "when the status of the corresponding monitoring point in the task resource status matrix is detected to have changed to a rescheduled state" means that when the monitoring point's task is rescheduled due to continuous obstruction of its evolutionary branch, the system will use the previously generated suggested rescheduled execution time parameter to shift the expected completion date of the target monitoring project. The expected completion date refers to the date on which the entire monitoring project is expected to be completed after considering the rescheduled date. By comparing it with the initial baseline date (i.e., the original completion date set when the project started), the overall schedule deviation parameter can be calculated, which directly reflects the delay or advancement of the overall project schedule. When the overall schedule deviation parameter is greater than the contract tolerance threshold parameter, it indicates that the project schedule delay has exceeded the scope allowed by the contract or project charter. At this time, the system will automatically generate a schedule delay risk report for the associated environmental event tracking object. This report will record in detail the environmental event that caused the delay, the affected monitoring points, the expected delay duration, and the potential contract risks, and can be sent to the project manager or relevant stakeholders for timely countermeasures. The contract tolerance threshold parameter can be set according to the specific project contract terms, for example, set to 3 days or 5 days.
[0070] Through the aforementioned technical solutions, this application enables refined management and comprehensive risk control of the project execution process after generating environmental monitoring project management instructions. Specifically, by accurately recording the additional waiting time parameters and calculating the time window squeeze offset of subsequent tasks, project managers can obtain timely warnings of the impact of local delays on the overall schedule, thereby effectively avoiding chain reactions and ensuring the project progresses on time. Simultaneously, by dynamically evaluating the expected completion date of the rescheduled project and calculating the overall schedule deviation parameters, this application can identify and report significant schedule delay risks exceeding the contract's tolerance range in real time, providing project decision-makers with crucial risk warning information and facilitating timely remedial measures to reduce project risks. More importantly, the introduction of a global state consistency verification service ensures the accuracy and consistency of core data such as the point task resource state matrix and environmental event tracking objects, effectively avoiding system anomalies such as suspended tasks and deadlocked resources, significantly improving the stability of system operation and resource utilization efficiency, thereby comprehensively enhancing the scientific nature and reliability of urban green space ecological environment monitoring project management.
[0071] In some embodiments, reference is made to Figure 3This application proposes an urban green space ecological environment monitoring project management system, comprising: a first acquisition unit 301, used to acquire spatial environmental constraint parameters and task plan baseline parameters of monitoring points, construct a point task resource status matrix containing the correlation between spatial environmental constraint parameters and task plan baseline parameters, and set a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary; and a first processing unit 302, used to respond to obstructed reporting information corresponding to the monitoring point, instantiate an environmental event tracking object based on the obstructed reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix, and change the status of the monitoring point in the point task resource status matrix to an obstructed and pending evaluation state, and an environmental event tracking object. The tracking object records the obstruction start time, on-site water accumulation observation parameters, and the identification code of the monitoring point corresponding to the obstruction reporting information; the second acquisition unit 303 is used to acquire the meteorological forecast parameters of the area where the monitoring point is located, and determine the expected dissipation time parameter and expected recovery time parameter of the monitoring point based on the meteorological forecast parameters, on-site water accumulation observation parameters, and spatial environmental constraint parameters, and compare the expected recovery time parameter with the task plan baseline parameters to determine the recovery probability confidence index corresponding to the monitoring point; the second processing unit 304 is used to determine the obstruction state evolution branch corresponding to the monitoring point based on the expected recovery time parameter, recovery probability confidence index, and plan adjustment trigger baseline, and generate environmental monitoring project management instructions based on the obstruction state evolution branch.
[0072] The urban green space ecological environment monitoring project management system proposed in this application, through the configuration of a first acquisition unit, a first processing unit, a second acquisition unit, and a second processing unit, achieves intelligent and dynamic management of task obstruction caused by environmental changes in urban green space ecological environment monitoring projects. This system can automatically acquire and integrate multi-dimensional information from monitoring points, track and predict environmental events in real time, and intelligently generate corresponding management instructions based on the prediction results. Therefore, it effectively solves the problems of lag and misjudgment in traditional management methods when dealing with short-term environmental changes, significantly improving the efficiency, accuracy, and adaptability of project management, ensuring the smooth progress of monitoring tasks and the rational allocation of resources.
[0073] The above are merely embodiments of this application and are not intended to limit the scope of protection of this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the scope of protection of this application.
Claims
1. A management method for urban green space ecological environment monitoring projects, characterized in that, include: Acquire the spatial environment constraint parameters and task plan baseline parameters of the monitoring points, construct a point task resource status matrix containing the correlation between the spatial environment constraint parameters and the task plan baseline parameters, and set a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary; In response to the obstruction reporting information corresponding to the monitoring point, an environmental event tracking object is instantiated based on the obstruction reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix. The status of the monitoring point in the point task resource status matrix is changed to an obstruction pending evaluation state. The environmental event tracking object records the obstruction start time, on-site water accumulation observation parameters, and the identification code of the monitoring point corresponding to the obstruction reporting information. Obtain meteorological forecast parameters for the area where the monitoring point is located. Based on the meteorological forecast parameters, the on-site water accumulation observation parameters, and the spatial environment constraint parameters, determine the expected recession duration parameter and the expected recovery time parameter for the monitoring point. Compare the expected recovery time parameter with the task plan baseline parameters to determine the recovery probability confidence index corresponding to the monitoring point. Based on the expected recovery time parameter, the recovery probability confidence index, and the planned adjustment trigger baseline, the obstructed state evolution branch corresponding to the monitoring point is determined, and environmental monitoring project management instructions are generated according to the obstructed state evolution branch.
2. The method for managing urban green space ecological environment monitoring projects according to claim 1, characterized in that, The process involves acquiring spatial environmental constraint parameters and task plan baseline parameters for monitoring points, constructing a point-based task resource status matrix that includes the correlation between spatial environmental constraint parameters and task plan baseline parameters, and setting a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary, including: The spatial environment constraint parameters are obtained by extracting the relative values of topographic elevation corresponding to the monitoring points, the permeability coefficient of the green space type, the average frequency of water accumulation in historical rainfall events, the average historical water accumulation range, and the average historical natural receding time. Extract the start time and latest end time of the task plan assigned to the monitoring point to obtain the baseline parameters of the task plan, and extract the bound on-site execution personnel number, monitoring equipment type and resource occupation cycle to obtain the on-site execution resource parameters; Construct a point task resource status matrix that uses the monitoring point identification code as an index to associate and store the spatial environment constraint parameters, the task plan baseline parameters, the on-site execution resource parameters, and the task execution status field. The task execution status field is configured as pending execution during initialization to record the status change of the monitoring point task when it is subsequently blocked and reported. Based on the latest end time of the task plan and the travel time required for on-site personnel to transfer to the next planned monitoring point, the baseline for plan adjustment triggering the monitoring point is determined by subtraction.
3. The method for managing urban green space ecological environment monitoring projects according to claim 2, characterized in that, The response to the obstruction reporting information corresponding to the monitoring point involves instantiating an environmental event tracking object based on the obstruction reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix, and changing the status of the monitoring point in the point task resource status matrix to an obstruction pending evaluation state, including: Upon receiving the obstruction report information sent by the field terminal for the monitoring point, the system time of the receiving time is recorded as the obstruction start time, and the estimated value of the on-site water accumulation range and the current rainfall status observation value carried in the obstruction report information are extracted to obtain the on-site water accumulation observation parameters; the obstruction report information carries the identification code of the monitoring point. The environmental event tracking object is created and instantiated by encapsulating the obstruction start time, the on-site water accumulation observation parameters, the identification code, and the relative value of terrain elevation and permeability coefficient in the spatial environment constraint parameters. The environmental event tracking object reserves an estimated recovery time field, an event duration status flag field, and a secondary confirmation countdown field. In the location task resource status matrix, the corresponding record is searched using the identifier code as an index, and the task execution status field in the corresponding record is changed from the pending execution status to the blocked and awaiting evaluation status.
4. The method for managing urban green space ecological environment monitoring projects according to claim 3, characterized in that, The process of obtaining meteorological forecast parameters for the area where the monitoring point is located, and determining the expected duration of water receding and the expected recovery time parameters for the monitoring point based on the meteorological forecast parameters, the on-site water accumulation observation parameters, and the spatial environmental constraint parameters, includes: The system calls a preset meteorological interface to obtain real-time rainfall intensity and short-term rainfall forecast data for a preset period starting from the current moment in the area where the monitoring point is located, which are used as the meteorological forecast parameters. When the meteorological forecast parameters characterize continuous rainfall and the real-time rainfall intensity is greater than the permeability corresponding to the permeability coefficient, a preset delay penalty value is determined as the expected duration parameter; When the meteorological forecast parameters indicate that rainfall has stopped or is about to stop, the soil pre-term moisture content parameters of the area where the monitoring point is located are obtained. Based on the ratio of the estimated on-site water accumulation range to the historical average water accumulation range in the spatial environmental constraint parameters, and the reduction ratio of the soil pre-term moisture content parameters to the permeability coefficient, a comprehensive correction coefficient is determined. The historical average natural recession duration in the spatial environmental constraint parameters is then corrected using the comprehensive correction coefficient to obtain the expected recession duration parameter. The expected recovery time parameter is obtained by summing the time of the obstruction start time with the expected duration of the obstruction.
5. The urban green space ecological environment monitoring project management method according to claim 4, characterized in that, The step of comparing the expected recovery time parameter with the task plan baseline parameter to determine the recovery probability confidence index corresponding to the monitoring point includes: Extract the latest end time of the task plan from the baseline parameters of the task plan; When the expected recovery time parameter is earlier than the latest end time of the task plan, and the time difference between the two is greater than a preset first judgment threshold, the recovery probability confidence index is assigned a high confidence value. When the time difference between the expected recovery time parameter and the latest end time of the task plan is less than or equal to the preset first judgment threshold and greater than the preset second judgment threshold, the recovery probability confidence index is assigned a medium confidence value. When the expected recovery time parameter is later than the latest end time of the task plan, or the time difference between the two is less than or equal to the preset second judgment threshold, the recovery probability confidence index is assigned a low confidence value.
6. The method for managing urban green space ecological environment monitoring projects according to claim 1, characterized in that, The step of determining the obstructed state evolution branch corresponding to the monitoring point based on the expected recovery time parameter, the recovery probability confidence index, and the planned adjustment trigger baseline includes: When the expected recovery time parameter is later than or equal to the planned adjustment trigger baseline, or when the recovery probability confidence index is a low confidence value, the monitoring point is determined to have entered a continuously blocked evolution branch that represents the task window tolerance limit. If the expected recovery time parameter is earlier than the planned adjustment trigger baseline and the time difference between the two is less than or equal to the preset system buffer margin parameter, or the recovery probability confidence index is a medium confidence value, the monitoring point is determined to have entered the critical uncertain evolution branch that represents the risk of recovery fluctuations. If the monitoring point does not enter the continuously blocked evolution branch or the critically uncertain evolution branch, it is determined that the monitoring point has entered the short-term waiting evolution branch that represents the conditions for on-site waiting. The determined evolution branch is taken as the obstructed state evolution branch corresponding to the monitoring point.
7. The method for managing urban green space ecological environment monitoring projects according to claim 6, characterized in that, The step of generating environmental monitoring project management instructions based on the branch of the obstructed state evolution includes: When the blocked state evolution branch is the short-term waiting evolution branch, a short-term dwell waiting instruction containing the expected recovery time parameter and the suggested waiting duration is generated and sent to the mobile terminal of the associated on-site personnel. Change the status of the corresponding monitoring point in the point task resource status matrix to the controlled waiting state, and start the countdown timer corresponding to the secondary confirmation countdown field in the environmental event tracking object. Send a field status verification request signal when the countdown is triggered. When the obstructed state evolution branch is the critical uncertain evolution branch, a high-frequency observation command is generated, instructing the on-site personnel to submit on-site status image data within a specified early warning time threshold before reaching the planned adjustment trigger baseline; The preset image recognition algorithm is used to extract the water receding feature from the on-site state image data. When the feature quantity representing water receding is extracted, the planned adjustment trigger baseline is extended and the monitoring point is transferred to the short-term waiting evolution branch. When the feature quantity representing water receding is not extracted, the monitoring point is forcibly transferred to the continuously obstructed evolution branch.
8. The method for managing urban green space ecological environment monitoring projects according to claim 6, characterized in that, The step of generating environmental monitoring project management instructions based on the branch of the obstructed state evolution includes: When the obstructed state evolution branch is the continuous obstructed evolution branch, the state of the monitoring point is changed to the rescheduled state, and the occupation and locking state of the monitoring point for the corresponding on-site personnel and monitoring equipment is released. Obtain the current spatial location coordinates and remaining available working time parameters of the on-site personnel after the occupancy and locking status is released, and traverse the point task resource status matrix to search for target candidate monitoring points that meet the shortest path condition and are in the pending execution state. Calculate the estimated travel time for the on-site personnel to transfer to the target candidate monitoring point. When the task plan window of the target candidate monitoring point matches the remaining available working hours parameter, generate a point-change execution instruction pointing to the target candidate monitoring point as a task rescheduling instruction. The original monitoring points corresponding to the continuously obstructed evolution branch are moved into the unassigned task pool, and suggested rescheduled execution time parameters are automatically generated based on the rainless weather forecast window within the predetermined period.
9. A management method for urban green space ecological environment monitoring projects according to claim 1, characterized in that, After generating environmental monitoring project management instructions based on the hindered state evolution branch, the method further includes: When the status of the corresponding monitoring point in the point task resource status matrix changes from the controlled waiting state to the completed state, the additional time consumption parameter caused by waiting is recorded. The additional time consumption parameter is used to calculate the squeezing bias of the time window of subsequent related tasks. When the squeezing bias is greater than the preset tolerance threshold, a travel time compression warning signal for subsequent tasks is output. When the status of the corresponding monitoring point in the point task resource status matrix is detected to be changed to rescheduled, the expected completion date of the target monitoring project is shifted using the suggested rescheduled execution time parameter, and the overall progress deviation parameter between the expected completion date and the initial baseline date is calculated. When the overall schedule deviation parameter exceeds the contract tolerance threshold parameter, a schedule delay risk report for the associated environmental event tracking object is generated; The global state consistency verification service is invoked to perform a consistency comparison on the data in the point task resource state matrix and the environmental event tracking object, and to release and reset the dangling tasks that are neither waiting nor reordered, as well as the deadlocked resources that have no task assignments but have not been released.
10. A management system for urban green space ecological environment monitoring projects, characterized in that, include: The first acquisition unit is used to acquire the spatial environment constraint parameters and task plan baseline parameters of the monitoring points, construct a point task resource status matrix containing the correlation between the spatial environment constraint parameters and the task plan baseline parameters, and set a plan adjustment trigger baseline for each monitoring point to characterize the latest plan adjustment time boundary; The first processing unit is used to respond to the obstruction reporting information corresponding to the monitoring point, and based on the obstruction reporting information and the spatial environmental constraint parameters associated with the monitoring point in the point task resource status matrix, instantiate an environmental event tracking object, and change the status of the monitoring point in the point task resource status matrix to an obstruction pending evaluation state. The environmental event tracking object records the obstruction start time, on-site water accumulation observation parameters, and the identification code of the monitoring point corresponding to the obstruction reporting information. The second acquisition unit is used to acquire meteorological forecast parameters of the area where the monitoring point is located, and based on the meteorological forecast parameters, the on-site water accumulation observation parameters, and the spatial environment constraint parameters, determine the expected recession duration parameters and the expected recovery time parameters of the monitoring point, and compare the expected recovery time parameters with the task plan baseline parameters to determine the recovery probability confidence index corresponding to the monitoring point; The second processing unit is used to determine the obstructed state evolution branch corresponding to the monitoring point based on the expected recovery time parameter, the recovery probability confidence index and the planned adjustment trigger baseline, and generate environmental monitoring project management instructions according to the obstructed state evolution branch.