A method for whole life cycle operation and maintenance management and overhaul task scheduling of zinc oxide lightning arrester

By using full lifecycle maintenance records and maintenance task scheduling methods, the problem of data isolation in the maintenance of zinc oxide surge arresters has been solved. This enables reasonable sequencing and resource optimization of equipment status assessment and maintenance tasks, forming a closed-loop management system and improving maintenance efficiency and accuracy.

CN123140932APending Publication Date: 2026-11-20D G SOLUTIONS ELECTRIC XIAMEN
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611604386.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-16
Publication Date
2026-11-20

AI Technical Summary

Technical Problem

During the operation and maintenance of zinc oxide surge arresters, the existing technology lacks a unified data association, which leads to unreasonable sorting of maintenance tasks. This can easily result in delayed maintenance of high-risk equipment, premature maintenance of low-risk equipment, task conflicts, and redundant resource allocation. Furthermore, the maintenance results are not promptly fed back into the full life cycle archive, making it difficult to form a closed-loop management system.

Method used

Through the operation and maintenance management platform, a full life cycle operation and maintenance file for zinc oxide surge arresters is established, integrating basic equipment information, online status assessment results, historical records, etc., to determine the maintenance requirement level and maintenance task type, optimize maintenance resource allocation, generate maintenance work orders, and feed the execution results back to the file, forming a closed-loop management.

Benefits of technology

This system enables unified management of multiple zinc oxide surge arresters, reduces conflicts between maintenance tasks and resources, improves the reliability of condition assessments, establishes a closed-loop management system from condition assessment to maintenance feedback, and optimizes the sequencing of maintenance tasks and the utilization of resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123140932A_ABST
    Figure CN123140932A_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of power equipment operation and maintenance management, in particular to a zinc oxide lightning arrester full life cycle operation and maintenance management and maintenance task scheduling method, comprising: obtaining the equipment basic information, online state evaluation results, historical inspection records, historical maintenance records, impact action records and operation life of each zinc oxide lightning arrester, and establishing a full life cycle operation file according to the unique identification of the equipment; determining the maintenance requirement level, allowable maintenance period and maintenance task type of each zinc oxide lightning arrester, and establishing a maintenance task set; obtaining maintenance resource information such as planned power outage window, maintenance team, spare parts inventory and expected maintenance duration; establishing a candidate maintenance scheme and determining the task priority value according to the equipment operation risk, task urgency, task overdue degree, resource occupation situation and equipment importance; realizing unified management, resource scheduling and closed-loop maintenance of multiple lightning arrester maintenance tasks.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power equipment operation and maintenance management technology, specifically a method for the whole life cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters. Background Technology

[0002] Currently, during the operation and maintenance of zinc oxide surge arresters, online monitoring data, periodic inspection records, historical maintenance records, impact action records, and basic equipment information are usually stored separately. There is a lack of unified correlation between the status assessment results and the generation of maintenance tasks, power outage plans, maintenance teams, and spare parts configuration.

[0003] When multiple surge arresters in the same area or substation require maintenance at the same time, the existing method usually involves maintenance personnel manually determining the maintenance sequence and time based on the results of a single test and a fixed maintenance cycle. This makes it difficult to consider the equipment's full life cycle status, task urgency, planned power outage window, and maintenance resource occupancy at the same time, which can easily lead to problems such as delayed maintenance of high-risk equipment, premature maintenance of low-risk equipment, task conflicts, and redundant allocation of maintenance resources.

[0004] In addition, the measured results, defect handling results and resource consumption information after maintenance are usually not written back to the full life cycle maintenance file in a timely manner, which results in the continued use of the original parameters for subsequent maintenance cycles and task priorities, making it difficult to form a closed-loop maintenance management between status assessment, task formation, maintenance execution and result feedback. Summary of the Invention

[0005] The purpose of this invention is to provide a method for the full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters. This purpose can be achieved through the following technical solutions: This invention provides a method for the full lifecycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters, executed by an operation and maintenance management platform, including: Obtain basic equipment information, online status assessment results, historical inspection records, historical maintenance records, impulse action records, and years of operation for each zinc oxide surge arrester, and establish corresponding full life cycle operation and maintenance files according to the unique equipment identifier; Based on the online status assessment results, historical inspection records, historical maintenance records, impact action records, years of operation, and time interval since the last maintenance, determine the maintenance requirement level, allowable maintenance period, and maintenance task type for each zinc oxide surge arrester, and establish a set of tasks to be maintained based on the maintenance requirement level and allowable maintenance period. Obtain maintenance resource information, which includes at least several of the following: planned power outage window, maintenance team, team's operational capacity, spare parts inventory, and estimated maintenance duration. For each maintenance task in the set of tasks to be maintained, at least one candidate maintenance plan is established based on the maintenance requirement level, allowable maintenance period, planned power outage window and maintenance resource information. The task priority value of each candidate maintenance plan is determined based on equipment operation risk, task urgency, task overdue degree, resource occupation and equipment importance. The execution order and target execution time of maintenance tasks are determined according to the task priority value and maintenance resource constraints, and corresponding maintenance work orders are generated. The maintenance work order includes at least the target surge arrester, maintenance task type, execution period, required maintenance resources, and maintenance acceptance items. Receive the maintenance execution results and acceptance results corresponding to the maintenance work order, write the maintenance execution results, acceptance results and actual resource usage into the corresponding full life cycle operation and maintenance file, and adjust the next maintenance cycle and maintenance requirement level of the corresponding zinc oxide surge arrester according to the updated full life cycle operation and maintenance file.

[0006] Preferably, the full lifecycle operation and maintenance file is associated with the device number, device model, rated voltage level, installation location, commissioning time, operating years, historical inspection records, historical maintenance records, historical fault and defect records, number of impact actions and corresponding action levels, results of previous online status assessments, last maintenance time and next maintenance cycle according to the unique device identifier. The basic equipment information is retrieved from the equipment ledger database. The historical inspection records and historical maintenance records are retrieved from the inspection management system and maintenance management system, respectively. The online status assessment results are generated and written into the full life cycle operation and maintenance file according to the preset evaluation cycle. The maintenance execution results and acceptance results are written into the full life cycle operation and maintenance file after the corresponding maintenance work order is accepted.

[0007] Preferably, the maintenance requirement level, allowable maintenance period, and maintenance task type for each zinc oxide surge arrester are determined, including: The equipment status evaluation indicators and indicator trends in the online status assessment results are compared with the corresponding thresholds. Combined with historical fault and defect records, years of operation, and time interval since the last maintenance, the maintenance requirement level is determined as Level 1 of emergency, high, medium, and low according to the preset level rules. When the online status assessment result meets the preset immediate on-site verification conditions, the maintenance requirement level is determined to be emergency, and the allowable maintenance period is determined to be the first period; when the equipment status evaluation index is lower than the warning threshold and the rate of deterioration of the index trend exceeds the preset rate, the maintenance requirement level is determined to be high, and the allowable maintenance period is determined to be the second period; when the index trend exceeds the corresponding threshold but does not meet the high-level conditions, the maintenance requirement level is determined to be medium, and the allowable maintenance period is determined to be the third period; in other cases, the maintenance requirement level is determined to be low; the first period is shorter than the second period, and the second period is shorter than the third period; Based on the trigger indicators of the maintenance demand level, the maintenance task type is determined as on-site inspection, power outage maintenance, preventive maintenance, or surface treatment.

[0008] Preferably, the task priority value of each candidate maintenance plan is determined, including: The equipment operation risk value is determined based on the online status assessment results; the task urgency value is determined based on the time difference between the allowable maintenance period and the current time; the task overdue value is determined based on the extent to which the planned execution time of the candidate maintenance plan exceeds the allowable maintenance period; and the equipment importance value is determined based on the voltage level and power supply range of the target surge arrester. The task priority value is obtained by multiplying the equipment operation risk value, task urgency value, task overdue value and equipment importance value by their respective positive weighting coefficients, summing them, and then deducting the resource usage deduction value corresponding to the resource usage situation. The candidate maintenance plans are arranged in descending order of task priority. When the task priority values ​​are the same, the candidate maintenance plan with the earlier allowable maintenance period is ranked first. When the allowable maintenance period is the same, the candidate maintenance plan with the higher equipment operation risk value is ranked first.

[0009] Preferably, the planned power outage window is obtained from the power outage planning management system, and the planned power outage window includes the scope of the power outage equipment, the start and end times of the window, and the window capacity; the maintenance team and team operation capacity are obtained from the team management database, and the team operation capacity includes the maintenance qualification level, the number of work areas that can be performed simultaneously, and the team's geographical location; the spare parts inventory is obtained from the spare parts management system, and the spare parts inventory includes the spare parts model, available quantity, and warehouse location; the estimated maintenance duration is retrieved from the standard working hour database according to the maintenance task type, or determined based on the actual working hours statistics of similar historical maintenance work orders. When the estimated maintenance time of the candidate maintenance plan does not exceed the available time of the corresponding planned power outage window, the work capacity of the executing team covers the corresponding maintenance task type, the available quantity of spare parts is not less than the required quantity, and the travel time from the team's geographical location to the target surge arrester does not exceed the preset value, the corresponding maintenance resources are determined to match the candidate maintenance plan.

[0010] Preferably, at least one candidate maintenance plan is established, including: for each maintenance task, each planned power outage window within the allowed maintenance period is combined with a maintenance team and spare parts that meet the matching conditions to form at least one candidate maintenance plan. The candidate maintenance plan includes the planned execution time, the execution team, the spare parts occupied, and the corresponding planned power outage window. Maintenance resources are locked for each maintenance task in descending order of priority. When multiple candidate maintenance plans compete for the same maintenance resource, resulting in a resource conflict, the candidate maintenance plan with the higher priority is retained, and the maintenance tasks with the lower priority are recombined using the remaining maintenance resources to form new candidate maintenance plans. If the remaining maintenance resources cannot meet the corresponding maintenance task within the allowed maintenance period, the corresponding maintenance task is marked as a resource-constrained task, and a resource expansion prompt is output. The resource conflicts include at least one of the following: the same work group being assigned to multiple maintenance tasks at the same time; the total duration of maintenance tasks assigned within the same planned power outage window exceeding the window capacity; and the number of spare parts allocated at the same time exceeding the available quantity.

[0011] Preferably, after generating the corresponding maintenance work order, the status of the maintenance work order is flowed in the order of pending dispatch, dispatched, in progress, pending acceptance, and accepted. Maintenance work orders that fail acceptance are returned to the in progress status and the reason for rejection is recorded. The maintenance execution results include actual execution time, actual working hours, defect handling results, and measured data of power outage maintenance. The acceptance results include the acceptance conclusions of each maintenance acceptance item. The actual resource usage is compared with the planned maintenance resources in the maintenance work order. When the deviation exceeds the preset range, the reason for the resource deviation is recorded in the full life cycle operation and maintenance file. The next maintenance cycle for the corresponding zinc oxide surge arrester is re-determined based on the updated full life cycle maintenance records, and the maintenance requirement level is re-determined. When the acceptance results indicate that the equipment status has not recovered to the preset level, the maintenance requirement level for the corresponding zinc oxide surge arrester is maintained or increased, and a new maintenance task is generated and added to the set of tasks to be maintained.

[0012] Preferably, the online status assessment results are formed in the following manner: It receives electronic monitoring data including leakage current, operating voltage, surge arrester surface temperature, ambient temperature, ambient humidity, and impulse action data; it correlates the data according to a unified timestamp, and selects healthy operating samples based on sampling validity, time alignment error, sensor self-test results, and operating environment. Based on healthy operating samples, establish operating benchmarks for temperature rise, resistive current, and response index, and determine temperature rise deviation, resistive current deviation, response index change, and impact damage.

[0013] Preferably, the online status assessment results also include health factors, the rate of decline of health factors, and the annualized growth rate of resistive current; The health factor is determined based on the temperature rise deviation, resistive current deviation, response index change and impact damage amount. The rate of decline of the health factor is determined based on the time change of the health factor within the evaluation window. The annualized growth rate of the resistive current is determined based on the resistive current trend sample after removing the candidate data of the impact action. Specifically, the operating voltage is subjected to phase extraction processing to obtain the phase of the leakage current sampling value relative to the fundamental wave of the operating voltage. Within one power frequency analysis cycle, the in-phase component and quadrature component are extracted based on the instantaneous sampling value of the leakage current and the corresponding phase, and the resistive current and capacitive current are determined respectively. When the total harmonic distortion rate of the operating voltage exceeds the preset value, Fourier transform or synchronous detection is used to extract the in-phase components of the fundamental wave, the third harmonic and the fifth harmonic relative to the corresponding voltage harmonics. Each in-phase component is multiplied by the corresponding non-negative harmonic weight and then summed to synthesize the resistive current.

[0014] Preferably, the evaluation method is selected according to the validity status of the electronic monitoring data: when all electronic monitoring data is valid, a complete evaluation is performed; when some electronic monitoring data is invalid, a downgrade evaluation is performed, and the evaluation credibility of the corresponding online status evaluation result is limited to a preset upper limit; when all electronic monitoring data is invalid, the reading of the mechanical action counter set on the surge arrester is obtained and a basic inspection prompt is output. After the power outage maintenance is completed, the measured data of the power outage maintenance is compared with the online status assessment results. When the deviation exceeds the preset threshold, the operating benchmarks of temperature rise, resistive current and response index are corrected, and the correction results are written into the full life cycle operation and maintenance file to determine the next maintenance cycle and maintenance requirement level.

[0015] Compared with the prior art, the present invention has the following beneficial effects: Achieve unified management and task pooling of maintenance needs for multiple zinc oxide surge arresters; enable task priority values ​​to simultaneously reflect equipment operation risk values, task urgency values, and resource constraints; reduce conflicts between maintenance tasks and power outage plans, work teams, and spare parts, and reduce redundant resource occupation; establish a closed-loop system covering the entire lifecycle from condition assessment, maintenance task formation, work order execution to acceptance feedback; and ensure that power outage maintenance measurement data is not only used to correct the electrical condition model, but also to adjust the next maintenance cycle and maintenance requirement level.

[0016] Furthermore, as a secondary technical effect, the online condition assessment process invoked by this invention can distinguish between valve plate deterioration, increased surface leakage, and short-term impact disturbances, thereby improving the accuracy of resistive current identification and the reliability of condition assessment, and providing reliable equipment condition input for determining maintenance requirement levels. Attached Figure Description

[0017] The accompanying drawings, which are included to provide a further understanding of the invention and form part of this application, illustrate exemplary embodiments of the invention and, together with their description, serve to explain the invention and do not constitute an undue limitation thereof. In the drawings: Figure 1 This paper presents a flowchart illustrating a method for the full lifecycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to this application. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to specific embodiments.

[0019] Reference Figure 1 A method for full lifecycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters, executed by an operation and maintenance management platform, includes: acquiring basic equipment information, online status assessment results, historical inspection records, historical maintenance records, impulse action records, and operating years of each zinc oxide surge arrester, and establishing a corresponding full lifecycle operation and maintenance file according to the equipment's unique identifier; determining the maintenance requirement level, allowable maintenance period, and maintenance task type of each zinc oxide surge arrester based on the online status assessment results, historical inspection records, historical maintenance records, impulse action records, operating years, and the time interval since the last maintenance, and establishing a set of tasks to be maintained based on the maintenance requirement level and allowable maintenance period; acquiring maintenance resource information, which includes at least several of the following: planned power outage window, maintenance team, team's operational capacity, spare parts inventory, and estimated maintenance duration; and scheduling maintenance tasks according to the set of tasks to be maintained. For each maintenance task in the task set, at least one candidate maintenance plan is established based on the maintenance requirement level, allowable maintenance period, planned power outage window, and maintenance resource information. The priority of each candidate maintenance plan is determined based on equipment operation risk value, task urgency value, task overdue degree value, resource occupancy status, and equipment importance value. The execution order and planned execution time of the maintenance tasks are determined according to the task priority and maintenance resource constraints, and a corresponding maintenance work order is generated. The maintenance work order includes at least the target surge arrester, maintenance task type, execution period, required maintenance resources, and maintenance acceptance items. The maintenance execution results and acceptance results corresponding to the maintenance work order are received, and the maintenance execution results, acceptance results, and actual resource usage are written into the corresponding full lifecycle maintenance file. The next maintenance cycle and maintenance requirement level of the corresponding zinc oxide surge arrester are adjusted based on the updated full lifecycle maintenance file.

[0020] The operation and maintenance management platform includes a data acquisition controller, edge processing nodes, communication units, a server, a database, and operation and maintenance terminals. The data acquisition controller, located on-site, receives sampled values ​​from various monitoring sensors and writes them with a unified timestamp and sensor self-test results. Edge processing nodes perform time correlation of data, effective sample screening, and intermediate calculations for online status assessment. The server generates online status assessment results, determines maintenance requirement levels, manages sets of tasks awaiting repair, generates candidate repair plans, calculates task priority values, matches repair resources, generates repair work orders, and maintains the entire lifecycle of operation and maintenance records. The database stores the entire lifecycle of operation and maintenance records, repair resource information, repair work orders, and repair task records. The operation and maintenance terminals display repair tasks, repair work orders, and early warning information to operation and maintenance personnel and receive repair execution results and acceptance results entered by the personnel. Each zinc oxide surge arrester corresponds to a full life cycle operation and maintenance file. The data records are linked through the unique equipment identifier and time identifier, so that the current status, historical deterioration process and maintenance and handling of any surge arrester can be traced in the same file. This enables the closed-loop operation of status assessment, task formation, resource scheduling, work order execution and result feedback on the same platform.

[0021] The full lifecycle maintenance file is associated with and stores the device number, device model, rated voltage level, installation location, commissioning time, operating years, historical inspection records, historical maintenance records, historical fault and defect records, number of impact actions and corresponding action levels, previous online status assessment results, last maintenance time and next maintenance cycle according to the device's unique identifier. The basic device information is retrieved from the device ledger database, the historical inspection records and historical maintenance records are retrieved from the inspection management system and maintenance management system, respectively, the online status assessment results are generated according to the preset evaluation cycle and written into the full lifecycle maintenance file, and the maintenance execution results and acceptance results are written into the full lifecycle maintenance file after the corresponding maintenance work order is accepted.

[0022] The archive includes at least the equipment number, equipment model, rated voltage level, installation location, substation or line, commissioning time, service life, historical inspection records, historical maintenance records, historical fault and defect records, number of impact actions and corresponding action levels, results of each online status assessment, last maintenance time, next maintenance cycle, and work order numbers for each maintenance task. Basic equipment information is retrieved from the equipment ledger database using the equipment's unique identifier; historical inspection and maintenance records are retrieved from the inspection management system and maintenance management system, respectively, using the equipment's unique identifier; online status assessment results are generated by the server according to a preset evaluation cycle and written into the archive; maintenance execution results, acceptance results, and actual resource usage are written into the archive after the corresponding maintenance work order is accepted. Through this associated storage and retrieval method, equipment data scattered across different systems is unified into a single archive, providing a complete data foundation for determining maintenance requirement levels and scheduling maintenance tasks.

[0023] Determining the maintenance requirement level, allowable maintenance period, and maintenance task type for each zinc oxide surge arrester includes: comparing the equipment condition evaluation indicators and indicator trends in the online condition assessment results with corresponding thresholds, and combining historical fault and defect records, operating years, and the time interval since the last maintenance, determining the maintenance requirement level as Level 1 among emergency, high, medium, and low levels according to preset level rules; when the online condition assessment results meet preset immediate on-site verification conditions, the maintenance requirement level is determined to be emergency, and the allowable maintenance period is determined to be the first period; when the equipment condition... When the status evaluation index is below the warning threshold and the rate of deterioration of the index trend exceeds the preset rate, the maintenance demand level is determined to be high level, and the allowable maintenance period is determined to be the second period; when the index trend exceeds the corresponding threshold but does not meet the high level condition, the maintenance demand level is determined to be medium level, and the allowable maintenance period is determined to be the third period; in other cases, the maintenance demand level is determined to be low level; the first period is shorter than the second period, and the second period is shorter than the third period; the maintenance task type is determined to be on-site inspection, power outage maintenance, preventive maintenance, or surface treatment according to the trigger index of the maintenance demand level.

[0024] The method for determining the maintenance requirement level, allowable maintenance period, and maintenance task type. In this embodiment, the equipment status evaluation index includes health factors, and the index trends include the rate of decline of health factors and the annualized growth rate of resistive current. When the online status assessment result meets the preset immediate on-site verification conditions, the maintenance requirement level is determined to be the emergency level, and the allowable maintenance period is the first period, which is 3 days in this embodiment. The immediate on-site verification conditions include: the temperature rise deviation exceeding the temperature rise alarm threshold for three consecutive preset evaluation cycles; the single-cycle decline of health factors exceeding the preset range; the detection data exceeding the sensor range; the leakage current increase exceeding the preset value and the temperature rise deviation remaining unchanged for a consecutive preset number of preset evaluation cycles; sensor self-test failure and no backup data; the number of impact actions reaching the action number risk threshold or the impact damage amount reaching the impact damage risk threshold. When the equipment status evaluation index is below the warning threshold and the rate of deterioration of the index trend exceeds the preset rate, the maintenance requirement level is determined to be high, and the allowable maintenance period is the second period, which is 90 days in this embodiment. That is, when the health factor is below the warning threshold and the rate of decline of the health factor or the annualized growth rate of resistive current exceeds the corresponding preset rate. To reduce the probability of false alarms, it can be further required that the temperature rise deviation also exceeds the temperature rise alarm threshold before it is determined to be high. When the index trend exceeds the corresponding threshold but does not meet the conditions for high level, the maintenance requirement level is determined to be medium, and the allowable maintenance period is the third period, which is 180 days in this embodiment. That is, when the rate of decline of the health factor or the annualized growth rate of resistive current exceeds the corresponding preset rate but the health factor is not lower than the warning threshold. It can also be further required that the number of impact actions exceeds the preset proportion of the number of designed actions and the assessment credibility is not lower than the decision credibility threshold before it is determined to be medium.

[0025] All other situations are classified as low-level. The type of maintenance task is determined based on the trigger indicators of the maintenance requirement level. If the trigger indicator is an immediate on-site inspection, it is classified as on-site inspection; if the trigger indicator is a health factor and its rate of decline, it is classified as power outage maintenance; if the trigger indicator is the annualized growth rate of resistive current or the number of impact actions, it is classified as preventative maintenance; if the trigger indicator is enhanced surface leakage and the annualized growth rate of resistive current does not exceed a preset rate within a consecutive preset evaluation period, it is classified as surface treatment. When the maintenance requirement level is emergency, high, or medium, or when the trigger indicator is enhanced surface leakage, maintenance tasks are generated according to the above correspondence. If the above conditions are not met, no maintenance task is generated, and the corresponding surge arrester continues to be monitored. The time interval since the last maintenance is used to correct the allowable maintenance period. Under the same maintenance requirement level, the longer the time interval since the last maintenance, the shorter the allowable maintenance period is by a preset percentage based on the corresponding baseline period. In this embodiment, this preset percentage is 10%, and the shortened allowable maintenance period is not less than half of the corresponding baseline period. The server will merge the maintenance tasks generated according to the above correspondence into the set of tasks to be maintained. Each maintenance task in the set of tasks to be maintained will be managed uniformly with the unique equipment identifier, maintenance requirement level, allowable maintenance period and maintenance task type as task attributes. Thus, the set of tasks to be maintained will be established based on the maintenance requirement level and allowable maintenance period.

[0026] The task priority value of each candidate maintenance plan is determined, including: determining the equipment operation risk value based on the online status assessment results; determining the task urgency value based on the time difference between the allowable maintenance period and the current time; determining the task overdue value based on the extent to which the planned execution time of the candidate maintenance plan exceeds the allowable maintenance period; and determining the equipment importance value based on the voltage level and power supply range of the target surge arrester. The equipment operation risk value, task urgency value, task overdue value, and equipment importance value are multiplied by their corresponding positive weighting coefficients, summed, and then the resource occupation deduction value corresponding to resource occupation is subtracted to obtain the task priority value. The candidate maintenance plans are arranged in descending order of task priority value. When the task priority values ​​are the same, the candidate maintenance plan with the earlier allowable maintenance period is ranked first. When the allowable maintenance periods are the same, the candidate maintenance plan with the higher equipment operation risk value is ranked first.

[0027] The task priority value is equal to the sum of the sum of the equipment operation risk value, task urgency value, task overdue value, and equipment importance value multiplied by their respective positive weight coefficients, and then the product of the resource usage deduction value and the corresponding positive weight coefficient is subtracted. Each positive weight coefficient is calibrated according to the operation and maintenance strategy; in this embodiment, they are 0.40, 0.25, 0.20, 0.15, and 0.10 respectively. In other embodiments, the resource usage deduction value can be directly deducted from the summation result without multiplying by the corresponding positive weight coefficient. The equipment operation risk value is determined by mapping the health factor and its decline rate in the online status assessment results. This embodiment uses a piecewise linear mapping: the equipment operation risk value is 0 when the health factor is 1 and the health factor decline rate is 0; the equipment operation risk value is 0.5 when the health factor equals the warning threshold or the health factor decline rate equals the preset rate; and the equipment operation risk value is 1 when the health factor equals the alarm threshold or the health factor decline rate reaches the preset alarm rate. Values ​​between these states are determined by linear interpolation. Among them, the alarm threshold for health factors is lower than the early warning threshold for health factors, and the preset alarm rate is an alarm level rate threshold greater than the preset rate. The task urgency value is determined by the ratio of the time difference between the allowed maintenance period and the current time to the total allowed maintenance period; the smaller this ratio, the higher the task urgency value. Once the allowed maintenance period is reached, the task urgency value is set to 1. The task overdue value is determined by the ratio of the planned execution time exceeding the allowed maintenance period to the total allowed maintenance period; if it does not exceed the allowed maintenance period, it is set to 0.

[0028] The equipment importance value is determined based on the voltage level and power supply range of the target surge arrester; the higher the voltage level and the larger the power supply range, the greater the equipment importance value. The resource occupancy deduction value is determined based on the number of work areas occupied by the candidate maintenance plan, the quantity of spare parts, and the planned outage window capacity ratio. When ranking, each candidate maintenance plan is arranged in descending order of task priority. If task priority values ​​are the same, the plan with the earlier allowable maintenance period is ranked first. If allowable maintenance periods are also the same, the plan with the higher equipment operation risk value is ranked first, ensuring that high-risk and time-sensitive tasks receive priority access to resources.

[0029] The planned power outage window is obtained from the power outage planning management system. The planned power outage window includes the scope of the power outage equipment, the start and end times of the window, and the window capacity. The maintenance team and its operational capabilities are obtained from the team management database. The operational capabilities of the team include the maintenance qualification level, the number of work areas that can be executed simultaneously, and the geographical location of the team. The spare parts inventory is obtained from the spare parts management system. The spare parts inventory includes the spare parts model, the available quantity, and the warehouse where it is located. The estimated maintenance duration is retrieved from the standard working hour database according to the maintenance task type, or determined based on the actual working hours of similar historical maintenance work orders. When the estimated maintenance duration of the candidate maintenance plan does not exceed the available time of the corresponding planned power outage window, the operational capabilities of the executing team cover the corresponding maintenance task type, the available quantity of spare parts is not less than the required quantity, and the travel time from the team's geographical location to the target surge arrester does not exceed the preset value, the corresponding maintenance resource is determined to match the candidate maintenance plan.

[0030] The channels for obtaining maintenance resource information and the conditions for resource matching are as follows. In this embodiment, the planned power outage window is obtained from the power outage planning management system, including the scope of the power outage equipment, the start and end time of the window, and the window capacity; the maintenance team and the team's operational capacity are obtained from the team management database, and the team's operational capacity includes the maintenance qualification level, the number of work areas that can be performed simultaneously, and the team's geographical location; the spare parts inventory is obtained from the spare parts management system, including the spare parts model, available quantity, and warehouse location; The estimated maintenance duration is retrieved from the standard working hours database based on the maintenance task type. The standard working hours for each maintenance task type in the database are updated periodically based on the actual working hours of historical maintenance work orders, or can be determined directly based on the actual working hours of similar historical maintenance work orders. During the matching determination, the corresponding maintenance resources are determined to match the candidate maintenance plan only if the estimated maintenance duration of the candidate maintenance plan does not exceed the available time of the corresponding planned power outage window, the work capacity of the executing team covers the corresponding maintenance task type, the available quantity of required spare parts is not less than the required quantity, and the travel time from the team's geographical location to the target surge arrester does not exceed the preset value. Resource combinations that do not meet the matching conditions are not formed into candidate maintenance plans, thus eliminating infeasible resource combinations at the plan generation stage and avoiding unexecutable work orders in subsequent scheduling.

[0031] Establish at least one candidate maintenance plan, including: for each maintenance task, combining each planned power outage window within the allowed maintenance period with a maintenance team and spare parts that meet the matching conditions to form at least one candidate maintenance plan. The candidate maintenance plan includes the planned execution time, the executing team, the spare parts occupied, and the corresponding planned power outage window; locking maintenance resources for each maintenance task in descending order of task priority; when multiple candidate maintenance plans compete for the same maintenance resource, resulting in a resource conflict, retaining the candidate maintenance plan with the higher task priority, and recombining the maintenance tasks with the lower task priority using the remaining maintenance resources to form a new candidate maintenance plan; when the remaining maintenance resources cannot meet the corresponding maintenance task within the allowed maintenance period, marking the corresponding maintenance task as a resource-constrained task and outputting a resource expansion prompt; the resource conflict includes at least one of the following: the same team being assigned to multiple maintenance tasks in the same time period, the total duration of maintenance tasks assigned within the same planned power outage window exceeding the window capacity, and the number of the same spare parts allocated in the same time period exceeding the available quantity.

[0032] The generation method of candidate maintenance plans and the mechanism for resolving resource conflicts. In this embodiment, for each maintenance task in the set of tasks to be maintained, the server will allow each planned power outage window within the maintenance period to be combined with maintenance teams and spare parts that meet the matching conditions to form at least one candidate maintenance plan. The candidate maintenance plan records the planned execution time, the executing team, the spare parts used, and the corresponding planned power outage window; when on-site verification tasks do not require planned power outage windows, candidate maintenance plans are directly formed based on the team's reachability time.

[0033] The server locks maintenance resources for each maintenance task in descending order of task priority. When multiple candidate maintenance solutions compete for the same resource, causing a resource conflict, the candidate maintenance solution with the higher priority is retained. The remaining resources are used to recombine the lower priority tasks into new candidate maintenance solutions. If the recombination still cannot meet the requirements, the task is postponed to the next available planned power outage window. If the remaining maintenance resources cannot meet the requirements of the corresponding maintenance task within the allowed maintenance period, the corresponding maintenance task is marked as a resource-constrained task, and a resource expansion prompt is output to the maintenance terminal. The prompt includes the type of resource shortage, the number of shortages, and the suggested expansion method. Resource conflicts include at least one of the following: the same work team being assigned to multiple maintenance tasks at the same time; the total duration of maintenance tasks assigned within the same planned power outage window exceeding the window capacity; and the number of the same spare parts allocated at the same time exceeding the available quantity.

[0034] After generating the corresponding maintenance work order, the status of the maintenance work order is flowed in the order of pending dispatch, dispatched, in progress, pending acceptance, and accepted. Maintenance work orders that fail acceptance are rolled back to the in progress status and the reason for rejection is recorded. The maintenance execution result includes the actual execution time, actual working hours, defect handling results, and power outage maintenance measurement data. The acceptance result includes the acceptance conclusion of each maintenance acceptance item. The actual resource usage is compared with the planned maintenance resources in the maintenance work order. When the deviation exceeds the preset range, the reason for the resource deviation is recorded in the full life cycle operation and maintenance file. The next maintenance cycle of the corresponding zinc oxide surge arrester is re-determined based on the updated full life cycle operation and maintenance file, and the maintenance requirement level is re-determined. When the acceptance result reflects that the equipment status has not recovered to the preset level, the maintenance requirement level of the corresponding zinc oxide surge arrester is maintained or increased, and a new maintenance task is generated and added to the set of tasks to be maintained.

[0035] The maintenance work order status flow, acceptance write-back, and closed-loop update method are described. In this embodiment, the maintenance work order includes at least the work order number, the unique equipment identifier of the target surge arrester, the maintenance task type, the execution period, the planned execution time, the execution team, the list of required spare parts, the required tools and equipment, safety precautions, and maintenance acceptance items. The maintenance acceptance items are determined according to the maintenance task type. For power outage maintenance work orders, the acceptance items include DC 1 mA reference voltage measurement, leakage current measurement under 0.75 times DC 1 mA reference voltage conditions, visual inspection, and verification of mechanical action counter readings.

[0036] Work order status progresses in the following order: Pending Dispatch, Dispatched, Executing, Pending Acceptance, and Accepted. After the maintenance terminal confirms receipt, the work order is changed to "Dispatched." Once the maintenance personnel register the work on-site, it becomes "Executing." After completion and submission of the measured data for the acceptance items, it becomes "Pending Acceptance." Acceptance personnel confirm the acceptance conclusions item by item; if all items pass, it becomes "Accepted." If any acceptance item fails, the work order reverts to the "Executing" status, and the reason for rejection is recorded. After work order acceptance, the server writes the maintenance execution results and acceptance results into the corresponding surge arrester's full lifecycle maintenance file. Simultaneously, it compares the actual resource usage with the planned maintenance resources in the maintenance work order. If the deviation exceeds the preset range, the reason for the resource deviation is recorded in the file. The actual working hours are also written into the statistical sample of the standard working hour library to update the standard working hours for the corresponding maintenance task type. When the acceptance results indicate that the equipment status has not recovered to the preset level, the maintenance requirement level of the corresponding surge arrester is maintained or increased, and a new maintenance task is generated and added to the pending maintenance task set to participate in the next round of candidate maintenance plan generation and resource matching.

[0037] The online condition assessment results are generated as follows: receiving electronic monitoring data including leakage current, operating voltage, surge arrester surface temperature, ambient temperature, ambient humidity, and impact action data; associating data according to a unified timestamp, and screening healthy operating samples based on sampling validity, time alignment error, sensor self-test results, and operating environment; establishing operating benchmarks for temperature rise, resistive current, and response index based on the healthy operating samples, and determining temperature rise deviation, resistive current deviation, response index change, and impact damage.

[0038] The online status assessment results are generated as follows: In this embodiment, the leakage current acquisition unit is located at the grounding lead of the surge arrester and outputs the instantaneous sampled value, effective value, sampling timestamp, and current sensor self-test results of the leakage current; the operating voltage acquisition unit outputs the effective value of the operating voltage, the fundamental phase of the voltage, and the total harmonic distortion rate of the operating voltage through the voltage transformer or the station voltage measurement interface; the temperature acquisition unit outputs the surface temperature of the surge arrester and the ambient temperature; the humidity acquisition unit outputs the ambient humidity; and the impulse action counting unit outputs the action occurrence time, impulse action amplitude or action level, duration, and action count increment. When associating data according to a unified timestamp, a reference time for the analysis period is set, and the sampling time of various electronic monitoring data is determined respectively. The time alignment error is determined based on the time difference between the sampling time and the reference time for the analysis period. If the time alignment error does not exceed the preset maximum time alignment error, the corresponding sampled value is associated with the same analysis period; if it exceeds the maximum time alignment error, the original timestamp is retained but not used for the multi-physical quantity association calculation of the corresponding analysis period. Among them, the analysis cycle is the smallest time unit for correlation calculation of various electronic monitoring data. The preset evaluation cycle includes one or more consecutive analysis cycles. The server generates an online status assessment result every time a preset evaluation cycle is completed. The evaluation window includes multiple consecutive preset evaluation cycles, which are used to determine the rate of decline of health factors and the annualized growth rate of resistive current.

[0039] The selection criteria for healthy operation samples are: the effective sampling ratio of each necessary data item is not less than the corresponding preset ratio, the sensor self-test is qualified, the operating voltage is within the upper and lower limits of the rated operating voltage, and the corresponding analysis period is not in the preset impact action recovery window, surface leakage enhancement state, or abnormal pulse state. The surface leakage enhancement state is determined as follows: when the ambient humidity exceeds the preset humidity threshold, the effective value of the leakage current increases, and the temperature rise deviation does not exceed the temperature rise alarm threshold, the corresponding analysis period is determined to be in the surface leakage enhancement state. Operating benchmarks for temperature rise, resistive current, and response index are established based on the healthy operation samples. The temperature rise is obtained by subtracting the ambient temperature from the surge arrester surface temperature; the temperature rise operating benchmark, resistive current operating benchmark, and response index operating benchmark are respectively taken as the statistical average values ​​of the corresponding parameters in the healthy operation samples. The difference between the temperature rise of the current analysis period and the temperature rise operating benchmark is determined as the temperature rise deviation, and the difference between the resistive current of the current analysis period and the resistive current operating benchmark is determined as the resistive current deviation.

[0040] The response index characterizes the sensitivity of the resistive component of the leakage current to fluctuations in operating voltage. In the healthy operating sample, periods of voltage fluctuation are selected, and the ratio of the relative change in resistive current to the relative change in operating voltage is calculated for each period. The statistical average of these ratios is used as the response index, and the difference between the response index of the current analysis period and the operating baseline is determined as the change in response index. The impact damage quantity is obtained by accumulating the impact amplitude, duration, and action level using a pre-calibrated impact damage model. The impact damage model is established based on the impact withstand test data of the surge arrester valve or the impact withstand characteristics provided by the manufacturer, using a lookup table with impact amplitude, duration, and action level as input and single impact damage increment as output. After each effective impact action occurs, the lookup table is consulted to obtain the corresponding single impact damage increment, which is then accumulated sequentially.

[0041] The online status assessment results also include health factors, the rate of decline of health factors, and the annualized growth rate of resistive current. Health factors are determined based on temperature rise deviation, resistive current deviation, response index change, and impact damage. The rate of decline of health factors is determined based on the time change of health factors within the evaluation window. The annualized growth rate of resistive current is determined based on the resistive current trend sample after removing candidate impact action data. Specifically, the operating voltage undergoes phase extraction processing to obtain the phase of the instantaneous leakage current sample value relative to the fundamental frequency of the operating voltage. Within one power frequency analysis cycle, in-phase and quadrature components are extracted based on the instantaneous leakage current sample value and the corresponding phase to determine the resistive and capacitive currents, respectively. When the total harmonic distortion rate of the operating voltage exceeds a preset value, Fourier transform or synchronous detection is used to extract the in-phase components of the fundamental, third, and fifth harmonics relative to the corresponding voltage harmonics. Each in-phase component is multiplied by its corresponding non-negative harmonic weight and then summed to synthesize the resistive current.

[0042] The methods for determining the health factor, the rate of decline of the health factor, and the annualized growth rate of resistive current, as well as the method for extracting resistive current, are described below. In this embodiment, the health factor is determined as follows: the temperature rise deviation, resistive current deviation, response index change, and impact damage are normalized to a value range of 0 to 1 based on their respective alarm thresholds. The four normalized components are multiplied by their corresponding positive weighting coefficients and then summed to obtain the overall degradation value. The sum of the four positive weighting coefficients is 1. In this embodiment, these coefficients are 0.30, 0.35, 0.15, and 0.20 respectively. The overall degradation value is then subtracted from 1 to obtain the health factor. The health factor ranges from 0 to 1; a lower health factor indicates a worse equipment condition. The rate of decline of the health factor is obtained by linearly fitting the health factor sequence within the evaluation window and taking the negative of the fitting slope.

[0043] The annualized growth rate of resistive current is obtained by linearly fitting the resistive current trend sample after removing the candidate data of impact actions, and then dividing the fitting slope by the resistive current operating benchmark after converting it to an annual value. The candidate data of impact actions are data that meet the abnormal pulse conditions and are accompanied by effective impact action signals within a continuous analysis period, and are not used for long-term trend calculation.

[0044] The method for extracting resistive current is as follows: Phase extraction processing is performed on the operating voltage to obtain the phase of the fundamental wave of the operating voltage. The phase of the fundamental wave of the operating voltage is used as a reference to determine the phase of the instantaneous sampled value of the leakage current relative to the fundamental wave of the operating voltage. Within one power frequency analysis cycle, in-phase and quadrature components are extracted based on the instantaneous sampled value of the leakage current and the corresponding phase, and resistive and capacitive currents are determined respectively. When the total harmonic distortion rate of the operating voltage exceeds the preset value, Fourier transform or synchronous detection is used to extract the in-phase components of the fundamental wave, the third harmonic, and the fifth harmonic relative to the corresponding voltage harmonics. Each in-phase component is multiplied by the corresponding non-negative harmonic weight and then summed to synthesize the resistive current. The harmonic weights are determined by fitting healthy operating samples and the weight sum is 1. During fitting, the resistive current determined by the in-phase component of the fundamental wave in the healthy operating samples is used as the fitting reference. Least squares are used to solve for each non-negative harmonic weight to minimize the deviation between the synthesized resistive current and the fitting reference, so that accurate resistive current can still be obtained when the harmonic content of the power grid is high.

[0045] The evaluation method is selected according to the validity status of the electronic monitoring data: a full evaluation is performed when all electronic monitoring data is valid; a downgraded evaluation is performed when some electronic monitoring data is invalid, and the evaluation credibility of the corresponding online status evaluation result is limited to a preset upper limit; when all electronic monitoring data is invalid, the reading of the mechanical action counter set on the surge arrester is obtained and a basic inspection prompt is output; after the power outage maintenance is completed, the measured data of the power outage maintenance is compared with the online status evaluation results. When the deviation exceeds the preset threshold, the operating benchmarks of temperature rise, resistive current and response index are corrected, and the correction results are written into the full life cycle operation and maintenance file to determine the next maintenance cycle and maintenance requirement level.

[0046] The evaluation method is selected based on the validity status of electronic monitoring data, and a mechanism for correcting the operating baseline after maintenance is established. In this embodiment, a complete evaluation is performed when all electronic monitoring data is valid; when at least one of the temperature or humidity data is invalid but the operating voltage and leakage current are valid, a downgrade evaluation is performed based on the resistive current extracted from the operating voltage phase and its correspondence with the operating voltage, and the upper limit of the evaluation confidence level is set to 0.75; when only the leakage current is valid, a leakage current trend evaluation is performed, which is compared with a fixed threshold retrieved from the threshold database based on the surge arrester model, rated voltage level, and manufacturing parameters, and the upper limit of the evaluation confidence level is set to 0.50; when all electronic monitoring data is invalid, the reading of the mechanical action counter set on the surge arrester is obtained and a basic inspection prompt is output.

[0047] When communication is interrupted, the data acquisition controller with a local clock and non-volatile memory continues to acquire, calculate and buffer timestamped data, and retransmits it according to the retransmission identifier after communication is restored. After a power outage maintenance is completed, the leakage current, visual inspection level, and mechanical action counter readings under DC 1 mA reference voltage, 0.75 times DC 1 mA reference voltage conditions are compared with the DC 1 mA reference voltage, resistive current operating benchmark, surface leakage enhancement state, and number of impact actions recorded in the full life cycle maintenance file for the previous power outage maintenance. When the relative deviation of the numerical parameters exceeds 15% or the visual inspection level is inconsistent, the operating benchmarks for temperature rise, resistive current, and response index are updated with weights according to the preset update rules. The weighted update is performed by multiplying the original operating benchmark by the first weight and the corresponding parameter measured during the power outage maintenance by the second weight, and then summing the results. The sum of the first weight and the second weight is 1. The second weight is determined based on the evaluation reliability of the corresponding online status evaluation result. The higher the evaluation reliability, the larger the value of the second weight. The correction result is written into the full life cycle maintenance file to determine the next maintenance cycle and maintenance requirement level, so that the online evaluation benchmark is continuously calibrated with the measured data.

[0048] The working principle of the overall technical solution of this invention is as follows: The on-site data acquisition controller continuously collects leakage current, operating voltage, arrester surface temperature, ambient temperature, ambient humidity, and impulse action data from each zinc oxide surge arrester, and writes them to a unified timestamp and sensor self-test results. The edge processing node associates various types of data to the same analysis cycle according to the unified timestamp, and selects healthy operating samples based on sampling validity, time alignment error, sensor self-test results, and operating environment. When communication is interrupted, the data acquisition controller continues to collect and cache data using a local clock and non-volatile memory, and retransmits the data after communication is restored to ensure the integrity of the data chain.

[0049] The server establishes operating benchmarks for temperature rise, resistive current, and response index based on healthy operating samples. Resistive current is obtained by extracting the phase of the operating voltage. When the total harmonic distortion rate of the operating voltage exceeds a preset value, a weighted synthesis of harmonic in-phase components is used to improve the accuracy of the resistive current. This determines the temperature rise deviation, resistive current deviation, response index change, and impact damage. A health factor is then weighted and calculated, along with the rate of decline of the health factor and the annualized growth rate of the resistive current. During this process, by eliminating candidate impact action data and identifying enhanced surface leakage, valve plate deterioration, enhanced surface leakage, and short-term impact disturbances are distinguished, avoiding misjudging surface leakage caused by humid environments as valve plate deterioration. Simultaneously, the system switches between complete assessment, degraded assessment, and basic inspection prompts based on the effective status of electronic monitoring data, limiting the assessment credibility to an upper limit commensurate with data quality to ensure the reliability of the equipment status upon which maintenance decisions are based.

[0050] The server compares the equipment status evaluation indicators and indicator trends in the above evaluation results with the corresponding thresholds according to the preset evaluation cycle. Combining historical fault and defect records, years of operation, and the time interval since the last maintenance, the server determines the maintenance requirement level of each surge arrester as Level 1 among emergency, high, medium, and low levels and assigns a corresponding allowable maintenance period. Then, based on the trigger indicators, the server generates the corresponding type of maintenance task and writes it into the set of tasks to be maintained, thereby realizing unified pooled management of maintenance requirements for multiple surge arresters. Subsequently, the server retrieves maintenance resource information from the power outage planning management system, team management database, spare parts management system, and standard working hour database. It combines planned power outage windows within the allowed maintenance period with maintenance teams and spare parts that meet the matching conditions to form candidate maintenance plans. The plans are then sorted in descending order according to the task priority value, which simultaneously reflects the equipment operation risk value, task urgency value, task overdue value, equipment importance value, and resource occupancy status. Maintenance resources are locked for each maintenance task in this order. When resource conflicts occur, the plan with the higher task priority value is retained. The remaining tasks are recombined using the remaining resources or postponed to the next available window. Tasks that still cannot be satisfied are marked as resource-constrained tasks and resource expansion prompts are output, so that the limited power outage windows, teams, and spare parts are prioritized for equipment with higher risks and more urgent deadlines. Once the schedule is determined, the server generates a maintenance work order that includes the target surge arrester, maintenance task type, execution period, required maintenance resources, and maintenance and acceptance items. The work order status flows in the order of pending dispatch, dispatched, in progress, pending acceptance, and accepted. Work orders that fail acceptance are returned to the in progress status and the reason for rejection is recorded.

[0051] After the work order is accepted, the maintenance execution results, acceptance results, and actual resource usage are written back to the full life cycle maintenance file. The actual measured data of power outage maintenance is compared with the online status assessment results for consistency. When the deviation exceeds the preset threshold, the operating benchmarks for temperature rise, resistive current, and response index are corrected. At the same time, the next maintenance cycle is restored to the benchmark maintenance cycle according to the defect elimination status. When the deviation exceeds the limit or the same defect occurs repeatedly, the preset ratio is shortened. When the equipment status is continuously better than the threshold, the preset ratio is extended but does not exceed the preset upper limit. The maintenance requirement level is re-determined. When the equipment status has not recovered to the preset level, the level is maintained or increased and a new maintenance task is generated and added to the set of tasks to be maintained. Taking a 110 kV substation and five surge arresters on adjacent outgoing lines as an example, within the same evaluation period, the first arrester is identified as a high-level power outage maintenance task, the second arrester is identified as an emergency-level on-site inspection task, the third and fifth arresters are identified as medium-level preventive maintenance tasks, and the fourth arrester is identified as a surface treatment task. Available resources include Team A, which can perform two work areas simultaneously and is relatively close in distance, Team B, which can only perform one work area and is relatively far in distance, and two planned power outage windows. After calculating the task priority values ​​of each task, the server locks resources in the order of second, first, fifth, third, and fourth tasks. The second task is to be inspected on-site by Team A on the second day. The first task occupies the first planned power outage window and is executed by Team A. The combined working hours of the fifth and third tasks do not exceed the capacity of the second planned power outage window, and Team A executes them simultaneously within that window. The fourth task is executed by Team B along with the second window. If the third task is upgraded to a higher priority due to a deterioration in its status and its recalculated task priority value is higher than that of the first task, the third task requests to occupy the first planned power outage window. Since the window capacity cannot accommodate two tasks simultaneously, a resource conflict occurs. The server retains the third task with the higher priority value and recombines the first task with the remaining resources to execute it in the second planned power outage window. If the second window still cannot meet the requirements and the allowed maintenance period for the first task is about to expire, the first task is marked as a resource-constrained task, and a prompt to request a temporary power outage window and additional resources from the maintenance team is output.

[0052] Thus, status assessment, task formation, resource scheduling, work order execution, and result feedback form a complete closed loop. The full life cycle operation and maintenance file is continuously updated with each assessment and maintenance. Subsequent maintenance cycles and maintenance requirement levels always reflect the true status of the equipment, realizing unified scheduling of operation and maintenance management and maintenance tasks for multiple zinc oxide surge arresters throughout their entire life cycle.

[0053] The above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to specific embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention.

Claims

1. A method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters, characterized in that, Performed by the operation and maintenance management platform, including: Obtain basic equipment information, online status assessment results, historical inspection records, historical maintenance records, impulse action records, and years of operation for each zinc oxide surge arrester, and establish corresponding full life cycle operation and maintenance files according to the unique equipment identifier; Based on the online status assessment results, historical inspection records, historical maintenance records, impact action records, years of operation, and time interval since the last maintenance, determine the maintenance requirement level, allowable maintenance period, and maintenance task type for each zinc oxide surge arrester, and establish a set of tasks to be maintained based on the maintenance requirement level and allowable maintenance period. Obtain maintenance resource information, which includes at least several of the following: planned power outage window, maintenance team, team's operational capacity, spare parts inventory, and estimated maintenance duration. For each maintenance task in the set of tasks to be maintained, at least one candidate maintenance plan is established based on the maintenance requirement level, allowable maintenance period, planned power outage window and maintenance resource information. The task priority value of each candidate maintenance plan is determined based on equipment operation risk, task urgency, task overdue degree, resource occupation and equipment importance. The execution order and target execution time of maintenance tasks are determined according to the task priority value and maintenance resource constraints, and corresponding maintenance work orders are generated. The maintenance work order includes at least the target surge arrester, maintenance task type, execution period, required maintenance resources, and maintenance acceptance items. Receive the maintenance execution results and acceptance results corresponding to the maintenance work order, write the maintenance execution results, acceptance results and actual resource usage into the corresponding full life cycle operation and maintenance file, and adjust the next maintenance cycle and maintenance requirement level of the corresponding zinc oxide surge arrester according to the updated full life cycle operation and maintenance file.

2. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1, characterized in that, The full lifecycle operation and maintenance file is associated with the unique identifier of the equipment and stores the equipment number, equipment model, rated voltage level, installation location, commissioning time, operating years, historical inspection records, historical maintenance records, historical fault and defect records, number of impact actions and corresponding action levels, results of each online status assessment, last maintenance time and next maintenance cycle. The basic equipment information is retrieved from the equipment ledger database. The historical inspection records and historical maintenance records are retrieved from the inspection management system and maintenance management system, respectively. The online status assessment results are generated and written into the full life cycle operation and maintenance file according to the preset evaluation cycle. The maintenance execution results and acceptance results are written into the full life cycle operation and maintenance file after the corresponding maintenance work order is accepted.

3. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1 or 2, characterized in that, Determine the maintenance requirement level, allowable maintenance period, and maintenance task type for each zinc oxide surge arrester, including: The equipment status evaluation indicators and indicator trends in the online status assessment results are compared with the corresponding thresholds. Combined with historical fault and defect records, years of operation, and time interval since the last maintenance, the maintenance requirement level is determined as Level 1 of emergency, high, medium, and low according to the preset level rules. When the online status assessment result meets the preset immediate on-site verification conditions, the maintenance requirement level is determined to be the emergency level, and the allowable maintenance period is determined to be the first period; when the equipment status evaluation index is lower than the warning threshold and the rate of deterioration of the index trend exceeds the preset rate, the maintenance requirement level is determined to be the high level, and the allowable maintenance period is determined to be the second period; when the index trend exceeds the corresponding threshold but does not meet the high level conditions, the maintenance requirement level is determined to be the medium level, and the allowable maintenance period is determined to be the third period; in other cases, the maintenance requirement level is determined to be the low level; the first period is shorter than the second period, and the second period is shorter than the third period; Based on the trigger indicators of the maintenance demand level, the maintenance task type is determined as on-site inspection, power outage maintenance, preventive maintenance, or surface treatment.

4. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1, characterized in that, Determine the task priority of each candidate maintenance plan, including: The equipment operation risk value is determined based on the online status assessment results; the task urgency value is determined based on the time difference between the allowable maintenance period and the current time; the task overdue value is determined based on the extent to which the planned execution time of the candidate maintenance plan exceeds the allowable maintenance period; and the equipment importance value is determined based on the voltage level and power supply range of the target surge arrester. The task priority value is obtained by multiplying the equipment operation risk value, task urgency value, task overdue value and equipment importance value by their respective positive weighting coefficients, summing them, and then deducting the resource usage deduction value corresponding to the resource usage situation. The candidate maintenance plans are arranged in descending order of task priority. When the task priority values ​​are the same, the candidate maintenance plan with the earlier allowable maintenance period is ranked first. When the allowable maintenance period is the same, the candidate maintenance plan with the higher equipment operation risk value is ranked first.

5. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1, characterized in that, The planned power outage window is obtained from the power outage planning management system, and the planned power outage window includes the scope of the power outage equipment, the start and end times of the window, and the window capacity; the maintenance team and team operation capacity are obtained from the team management database, and the team operation capacity includes the maintenance qualification level, the number of work areas that can be performed simultaneously, and the team's geographical location; the spare parts inventory is obtained from the spare parts management system, and the spare parts inventory includes the spare parts model, available quantity, and warehouse location; the estimated maintenance duration is retrieved from the standard working hour database according to the maintenance task type, or determined based on the actual working hours statistics of similar historical maintenance work orders. When the estimated maintenance time of the candidate maintenance plan does not exceed the available time of the corresponding planned power outage window, the work capacity of the executing team covers the corresponding maintenance task type, the available quantity of spare parts is not less than the required quantity, and the travel time from the team's geographical location to the target surge arrester does not exceed the preset value, the corresponding maintenance resources are determined to match the candidate maintenance plan.

6. A method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1 or 5, characterized in that, Establish at least one candidate maintenance plan, including: for each maintenance task, combine each planned power outage window within the allowed maintenance period with maintenance teams and spare parts that meet the matching conditions to form at least one candidate maintenance plan. The candidate maintenance plan includes the planned execution time, the execution team, the spare parts occupied, and the corresponding planned power outage window. Maintenance resources are locked for each maintenance task in descending order of priority. When multiple candidate maintenance plans compete for the same maintenance resource, resulting in a resource conflict, the candidate maintenance plan with the higher priority is retained, and the maintenance tasks with the lower priority are recombined using the remaining maintenance resources to form new candidate maintenance plans. If the remaining maintenance resources cannot meet the corresponding maintenance task within the allowed maintenance period, the corresponding maintenance task is marked as a resource-constrained task, and a resource expansion prompt is output. The resource conflicts include at least one of the following: the same work group being assigned to multiple maintenance tasks at the same time; the total duration of maintenance tasks assigned within the same planned power outage window exceeding the window capacity; and the number of spare parts allocated at the same time exceeding the available quantity.

7. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1, characterized in that, After generating the corresponding maintenance work order, the status of the maintenance work order is flowed in the order of pending dispatch, dispatched, in progress, pending acceptance, and accepted. Maintenance work orders that fail acceptance are returned to the in progress status and the reason for rejection is recorded. The maintenance execution results include actual execution time, actual working hours, defect handling results, and measured data of power outage maintenance. The acceptance results include the acceptance conclusions of each maintenance acceptance item. The actual resource usage is compared with the planned maintenance resources in the maintenance work order. When the deviation exceeds the preset range, the reason for the resource deviation is recorded in the full life cycle operation and maintenance file. The next maintenance cycle for the corresponding zinc oxide surge arrester will be re-determined based on the updated full life cycle maintenance records, and the maintenance requirement level will be re-determined. When the acceptance results indicate that the equipment status has not been restored to the preset level, the maintenance requirement level of the corresponding zinc oxide surge arrester is maintained or increased, and a new maintenance task is generated and added to the set of tasks to be maintained.

8. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 1, characterized in that, The online status assessment results are generated in the following manner: It receives electronic monitoring data including leakage current, operating voltage, surge arrester surface temperature, ambient temperature, ambient humidity, and impulse action data; it correlates the data according to a unified timestamp, and selects healthy operating samples based on sampling validity, time alignment error, sensor self-test results, and operating environment. Based on healthy operating samples, establish operating benchmarks for temperature rise, resistive current, and response index, and determine temperature rise deviation, resistive current deviation, response index change, and impact damage.

9. The method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 8, characterized in that, The online status assessment results also include health factors, the rate of decline of health factors, and the annualized growth rate of resistive current. The health factor is determined based on the temperature rise deviation, resistive current deviation, response index change and impact damage amount. The rate of decline of the health factor is determined based on the time change of the health factor within the evaluation window. The annualized growth rate of the resistive current is determined based on the resistive current trend sample after removing the candidate data of the impact action. Specifically, the operating voltage is subjected to phase extraction processing to obtain the phase of the leakage current sampling value relative to the fundamental wave of the operating voltage. Within one power frequency analysis cycle, the in-phase component and quadrature component are extracted based on the instantaneous sampling value of the leakage current and the corresponding phase, and the resistive current and capacitive current are determined respectively. When the total harmonic distortion rate of the operating voltage exceeds the preset value, Fourier transform or synchronous detection is used to extract the in-phase components of the fundamental wave, the third harmonic and the fifth harmonic relative to the corresponding voltage harmonics. Each in-phase component is multiplied by the corresponding non-negative harmonic weight and then summed to synthesize the resistive current.

10. A method for full life-cycle operation and maintenance management and maintenance task scheduling of zinc oxide surge arresters according to claim 8 or 9, characterized in that, The evaluation method is selected according to the validity status of the electronic monitoring data: a full evaluation is performed when all electronic monitoring data is valid; a downgrade evaluation is performed when some electronic monitoring data is invalid, and the evaluation credibility of the corresponding online status evaluation result is limited to a preset upper limit; when all electronic monitoring data is invalid, the reading of the mechanical action counter set on the surge arrester is obtained and a basic inspection prompt is output. After the power outage maintenance is completed, the measured data of the power outage maintenance is compared with the online status assessment results. When the deviation exceeds the preset threshold, the operating benchmarks of temperature rise, resistive current and response index are corrected, and the correction results are written into the full life cycle operation and maintenance file to determine the next maintenance cycle and maintenance requirement level.