A power system source and network collaborative evolution scenario construction method and system
By constructing a scenario for the coordinated evolution of power system sources and grids, the load and new energy access are updated in stages. Combined with synchronous machine load rate and network topology correction, the problem of insufficient description of synchronous machine retirement and new energy penetration path in traditional methods is solved, and the continuous evolution of power structure and frequency characteristic analysis support are realized.
Patent Information
- Application Number
- CN202611218671.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-12
- Publication Date
- 2026-11-20
AI Technical Summary
Existing methods for constructing power system evolution scenarios fail to fully consider the decommissioning process of traditional synchronous machines and the penetration path of grid-connected renewable energy sources. They are also unable to accurately analyze the impact of different power source structure evolutions on the dynamic frequency characteristics of the system, especially lacking a phased description when the proportion of grid-connected renewable energy sources changes.
A method for constructing a power system source-grid collaborative evolution scenario is adopted. By obtaining the initial model and evolution parameters, the load and new energy access are updated in stages. Combined with the synchronous machine load rate and network topology correction, a multi-stage source-grid collaborative evolution scenario is generated, which describes in detail the synchronous machine decommissioning and new energy penetration path.
It realizes the continuous evolution process under load growth and new energy access, truly reflects the decay of synchronous machine support capacity, generates power structure evolution scenarios under various new energy penetration paths, and provides a basis for system dynamic frequency characteristic analysis.
Smart Images

Figure CN123144201A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power system evolution scenario construction technology, and in particular to a method and system for constructing a power system source-grid collaborative evolution scenario. Background Technology
[0002] The statements in this section are merely background information related to the present invention and do not necessarily constitute prior art.
[0003] As the installed capacity of new energy power generation continues to increase, the online capacity and operating output of traditional synchronous power sources are declining, and some units may be decommissioned due to prolonged low-load operation. Simultaneously, the proportion of grid-connected new energy is gradually increasing, and its impact on system frequency support, inertia response, and power regulation capabilities is becoming increasingly significant. Therefore, the dynamic characteristics of the new power system depend not only on the penetration rate of new energy at a certain stage, but also closely on the synchronous machine decommissioning process, the ratio of incremental new energy from grid-connected and grid-connected sources, source-load distribution, and changes in network topology.
[0004] Existing methods for constructing power system evolution scenarios mostly focus on changes in installed power generation capacity or the penetration rate of new energy sources. They typically generate different operating conditions by using preset proportions, manually given scenarios, or static section replacements. While these methods can reflect the impact of increased new energy share on system operating characteristics to some extent, they do not adequately consider the output reduction, continuous low-load operation, and decommissioning process of traditional synchronous generators during new energy substitution. Consequently, they fail to depict the actual process of the gradual decline in the support capacity of synchronous power sources as the evolutionary stage progresses.
[0005] Furthermore, existing methods often treat new energy sources as a uniform equivalent power source, or only distinguish between new energy sources and traditional power sources, without fully differentiating the differences between grid-connected and grid-built new energy sources in terms of frequency support mechanisms and dynamic response characteristics. Especially in scenarios where the proportion of grid-built new energy sources changes with different stages, without a staged description of the penetration path of grid-built new energy sources, it is difficult to accurately analyze the impact of different power structure evolution paths on the dynamic frequency characteristics of the system. Summary of the Invention
[0006] To address the aforementioned issues, this invention proposes a method and system for constructing power system source-grid coordinated evolution scenarios. Taking into account the retirement of synchronous machines and the penetration path of grid-connected new energy sources, it recursively generates power structure, output distribution, synchronous machine online status, grid-connected / following-grid new energy capacity ratio, and network topology status at different evolution stages, providing basic scenario support for dynamic frequency characteristic evolution analysis and source-grid coordinated planning of new power systems.
[0007] In some implementations, the following technical solutions are adopted: A method for constructing a power system source-grid coordinated evolution scenario includes: Obtain the initial model and evolution parameters of the power system; the evolution parameters include at least the load growth rate and the proportion function of grid-connected new energy sources among newly added new energy sources; Based on the load growth rate, in the... In the first evolutionary stage, the active power load of each load node is updated according to a unified growth pattern, and the calculation is performed. The node load increment in each evolution stage relative to the initial stage; Determine the first based on the load increment. The cumulative installed capacity of new energy and the typical active power output of new energy in each evolution stage are then evenly distributed to each new energy access node to obtain the source-load distribution state after the new energy access. Based on the total system load and the total output of new energy sources, the output allocation results of the online synchronous machines are calculated recursively; based on the load rate of each synchronous machine, it is determined whether the decommissioning conditions are triggered, and the synchronous machines that have triggered decommissioning are removed in the next evolution stage; Based on the updated node active power injection, determine whether the branch is a critical power flow bottleneck channel. If so, perform parallel expansion equivalent correction on the branch to obtain the network topology correction result, which serves as the input for the next evolution stage. Based on the grid-type new energy proportion function, the newly added new energy installed capacity is split to obtain the cumulative installed capacity of grid-type new energy and the cumulative installed capacity of grid-connected new energy. After all evolutionary stages have been iteratively calculated, a multi-stage source-network collaborative evolution scenario set has been formed.
[0008] As a further option, the evolution parameters include: load growth rate. The ratio between new energy installed capacity and load growth Typical output coefficient of new energy Minimum stable output threshold of synchronous machine Threshold for the number of consecutive low-load phases Line load rate threshold Line expansion coefficient And the function of the proportion of grid-type new energy in newly added new energy sources. .
[0009] As a further option, the active power load of each load node is updated according to a unified growth pattern, and the calculation of the first... The node load increments in each evolution stage relative to the initial stage are as follows: According to the node Determine the nodes based on the active power load and load growth rate in the initial stage. In the Active load at each evolutionary stage; The active load of all nodes is accumulated to obtain the first... The total load of each evolution stage, the difference between the total load and the total load of the initial stage, is used as the load increment.
[0010] As a further solution, based on the total system load and the total output of new energy sources, the output allocation result of the online synchronous machine is calculated recursively, specifically as follows: The total output of the synchronous machine required by the system is determined based on the load level and the output of new energy sources. The result is obtained by recursively deriving the output from the operating state of the previous evolution stage. The output of each synchronizer in each evolutionary stage; If the total output of the required synchronous machines is less than the total output of the synchronous machines in the previous evolution stage, the reduction amount will first be allocated to the online synchronous machines in the new energy centralized access area according to the current output ratio; if the synchronous machines in this area have been reduced to the minimum operating constraints and still cannot bear the full reduction amount, the remaining reduction amount will continue to be allocated to the other online synchronous machines in the entire system according to the ratio.
[0011] As a further step, the decommissioning conditions are determined based on the load rate of each synchronizer, specifically as follows: According to the The ratio of the output of each online synchronous machine to the rated capacity of the corresponding synchronous machine in each evolution stage is used to calculate the load rate of each synchronous machine. If the load rate of the synchronizer is less than the preset minimum stable output threshold of the synchronizer Then it is determined that the synchronizer is in the first... Each evolutionary stage is operating at low load. If the number of consecutive low-load operation periods of the synchronizer reaches a preset threshold... If the condition is met, the synchronizer is determined to have triggered the retirement condition and will be removed from the set of online synchronizers in the next evolutionary stage.
[0012] As a further solution, based on the updated node active power injection, it is determined whether the branch is a critical power flow bottleneck channel, specifically as follows: The active power injection at the nodes is calculated based on the updated load, new energy output, and synchronous machine output, and the active power flow of the line is obtained using a DC power flow model. According to the branch road The branch load rate is determined by the ratio of the active power flow to the branch equivalent transmission limit; whereby the branch equivalent transmission limit is based on the allowable phase angle difference limit and the branch load rate. In the The ratio of the equivalent reactance at each evolution stage can be obtained; If the branch load rate is greater than or equal to the preset line load rate threshold Determine the branch For the first The key trend bottleneck channels in each evolutionary stage.
[0013] As a further solution, based on the aforementioned grid-connected renewable energy proportion function, the newly added renewable energy installed capacity is divided into the following: According to the The function of newly added new energy installed capacity and the proportion of grid-type new energy in newly added new energy at each evolution stage Determine the first The newly added grid-type and grid-connected new energy capacity in each evolutionary stage; No. -1 stage of evolution: network-type new energy capacity and the first stage The sum of the newly added grid-type new energy capacity in each evolutionary stage is used as the first... The cumulative installed capacity of grid-connected new energy vehicles in each evolutionary stage; No. -1 evolutionary stage of grid-connected new energy capacity and the first The sum of the newly added grid-connected new energy capacity in each evolutionary stage is used as the first... The cumulative installed capacity of grid-type new energy in each evolutionary stage.
[0014] As a further solution, the multi-stage source-network collaborative evolution scenario set includes: the set of online synchronous machines, the set of retired synchronous machines, the total installed capacity of synchronous machines, the total output of synchronous machines, the total installed capacity of new energy sources, the total output of new energy sources, the cumulative installed capacity of grid-type new energy sources, the cumulative installed capacity of grid-connected new energy sources, the proportion of grid-type / grid-connected new energy installed capacity, the proportion of output of various power sources, the line load rate, the set of expanded lines, and the corrected network topology.
[0015] In other embodiments, the following technical solutions are adopted: A system for constructing power system source-grid collaborative evolution scenarios includes: The data acquisition module is used to acquire the initial model and evolution parameters of the power system; the evolution parameters include at least the load growth rate and the proportion function of grid-type new energy in newly added new energy sources; The phased load growth module is used to, according to the load growth rate, in the first... In the first evolutionary stage, the active power load of each load node is updated according to a unified growth pattern, and the calculation is performed. The node load increment in each evolution stage relative to the initial stage; The new energy output allocation module is used to determine the first load increment based on the load increment. The cumulative installed capacity of new energy and the typical active power output of new energy in each evolution stage are then evenly distributed to each new energy access node to obtain the source-load distribution state after the new energy access. The synchronous machine output adjustment module is used to recursively calculate the output allocation result of the online synchronous machine based on the total system load and the total output of new energy sources; determine whether the decommissioning conditions are triggered based on the load rate of each synchronous machine, and remove the synchronous machine that has triggered decommissioning in the next evolution stage; The network topology correction module is used to determine whether a branch is a critical power flow bottleneck channel based on the updated node active power injection. If so, the branch is modified by parallel expansion to obtain the network topology correction result, which is used as the input for the next evolution stage. The new energy path decomposition module is used to decompose the newly added new energy installed capacity according to the grid-type new energy proportion function to obtain the cumulative installed capacity of grid-type new energy and the cumulative installed capacity of grid-connected new energy. The results output module is used to form a multi-stage source-network collaborative evolution scenario set after all evolution stages have been iterated and calculated.
[0016] In other embodiments, the following technical solutions are adopted: A terminal device includes a processor and a memory, wherein the processor is used to implement instructions; and the memory is used to store multiple instructions, which are adapted to be loaded and executed by the processor to construct the above-described power system source-grid collaborative evolution scenario.
[0017] Compared with the prior art, the beneficial effects of the present invention are: This invention can continuously depict the entire process of the decline in output of traditional synchronous machines, the gradual assumption of new loads by new energy sources, and the phased changes in power supply structure under the combined effect of load growth and new energy access, forming a continuous and recursive source-grid coordinated evolution scenario. This overcomes the shortcomings of existing methods that use static section replacement and cannot reflect coupled evolution.
[0018] This invention, through a continuous low-load decommissioning criterion, can realistically reflect the preferential replacement effect of centralized renewable energy access on local traditional synchronous generators, and depict the actual process of the gradual decline of synchronous power supply support capacity as it evolves, rather than artificially setting the replacement ratio. Simultaneously, by using a phased description of the renewable energy proportion function in a grid-based system, it can generate power structure evolution scenarios under various penetration paths, such as fixed ratios, uniform transitions, and variable transitions, based on the same load growth and synchronous generator decommissioning. This provides a unified basis for comparing the impact of different development strategies on the dynamic frequency characteristics of the system.
[0019] Other features and advantages of the invention will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention. Attached Figure Description
[0020] Figure 1 This is a flowchart of the method for constructing a power system source-grid collaborative evolution scenario in an embodiment of the present invention; Figure 2 This is a topology diagram of the IEEE 39-node system in an embodiment of the present invention; Figure 3 This is a schematic diagram illustrating the changes in the output of the synchronous machine and new energy sources at different stages of load growth in an embodiment of the present invention; Figure 4 This refers to the installed capacity ratio of various power sources under the grid-type new energy incremental uniform-speed transition mode in this embodiment of the invention; Figure 5 These are the four grid-type new energy incremental proportion change patterns in the embodiments of the present invention. Figure 6 The load rate variation curves of lines 26-29 in this embodiment of the invention are shown. Detailed Implementation
[0021] It should be noted that the following detailed description is illustrative and intended to provide further explanation of the invention. Unless otherwise specified, all technical and scientific terms used in this invention have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains.
[0022] It should be noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the scope of exemplary embodiments according to the invention. As used herein, the singular form is intended to include the plural form as well, unless the context clearly indicates otherwise. Furthermore, it should be understood that when the terms "comprising" and / or "including" are used in this specification, they indicate the presence of features, steps, operations, devices, components, and / or combinations thereof.
[0023] Example 1 Existing scenario construction methods often generate operational scenarios by statically replacing cross-sections or pre-setting renewable energy penetration rates. This makes it difficult to describe the coupling relationship between load growth, new renewable energy access, synchronous generator output adjustments, and phased changes in the power structure within a unified recursive framework. Furthermore, they do not adequately consider the decommissioning process of traditional synchronous generators. Typically, synchronous generator capacity is adjusted only based on a manually set power replacement ratio, failing to consider the actual output level of the generators and continuous low-load operation to determine whether synchronous generators should be decommissioned. This makes it difficult to reflect the evolutionary characteristics of the gradual decline in the supporting capacity of synchronous power sources during renewable energy replacement.
[0024] Based on this, in one or more embodiments, a method for constructing a power system source-grid collaborative evolution scenario is disclosed, combining... Figure 1 Specifically, it includes the following process: S101: Obtain the initial model and evolution parameters of the power system.
[0025] In this embodiment, the initial network topology, branch reactance, node load, synchronous machine capacity, initial output of the synchronous machine, set of new energy access nodes, and number of evolution stages of the power system to be analyzed are obtained.
[0026] Assume the evolutionary stages are numbered as follows Let the set of load nodes be... The set of synchronizers is The set of new energy access nodes is .
[0027] Simultaneously, evolution parameters are set, including: load growth rate. The ratio between new energy installed capacity and load growth Typical output coefficient of new energy Minimum stable output threshold of synchronous machine Threshold for the number of consecutive low-load phases Line load rate threshold Line expansion coefficient And the function of the proportion of grid-type new energy in newly added new energy sources. .
[0028] in, The capacity proportion of grid-type new energy sources among the newly added new energy sources in the k-th evolution stage is used to characterize the range of its values: (1) It can be set to a fixed ratio mode, a uniform speed transition mode, a variable speed transition mode with a slow start and an accelerated finish, or a transition mode with a slow start, a fast middle, and a stable finish; the specific setting method can be selected according to actual needs.
[0029] As a concrete example, suppose there are a total K There are several evolutionary stages, numbered as follows: k =1,2,…, K ,but: (1) Fixed ratio mode: ; (2) Uniform transition mode: ; (3) In the variable-speed transition mode with slow initial speed and accelerated later speed: ; (4) A transition pattern characterized by slower initial stages, faster middle stages, and a more stable later stages: ; in, and These represent the percentage of GFM increment in the first and final stages, respectively. and All of these are set constants.
[0030] This embodiment can automatically generate power structure evolution scenarios under various grid-based new energy penetration paths by introducing different grid-based new energy proportion functions in the initial stage, without having to repeat the entire process.
[0031] S102: Based on the load growth rate, in the... In the first evolutionary stage, the active power load of each load node is updated according to a unified growth pattern, and the calculation is performed. The node load increment in each evolution stage relative to the load increment in the initial stage.
[0032] In this embodiment, in the first In each evolutionary stage, the active power load of each load node is updated according to a unified growth pattern: (2) in, For nodes Active load in the initial stage, For nodes In the Active load during a given period.
[0033] Then the first The total load of the system at this stage is: (3) The load increment relative to the initial stage is: (4) in, This represents the total system load in the initial phase.
[0034] This embodiment updates the load of each node in stages through a unified growth method, ensuring that the load data of each evolution stage is strictly derived from the previous stage, thus avoiding the discontinuity between stages caused by manually given scenarios or static cross-section replacement in existing methods.
[0035] S103: Determine the first based on load increment. The cumulative installed capacity of new energy sources and the typical active power output of new energy sources are calculated for each evolution stage. The installed capacity and typical active power output are then evenly distributed to each new energy access node to obtain the source-load distribution state after the new energy sources are connected.
[0036] In this embodiment, based on the ratio coefficient between new energy installed capacity and load growth... And the determination of system load increment The cumulative installed capacity of new energy in each phase is as follows: (5) in, This refers to the initial installed capacity of new energy sources; when no new energy sources are connected in the initial stage, .
[0037] No. Typical contributions of new energy sources in this phase include: (6) Let the set of new energy access nodes be defined. The CCP If there are multiple nodes, the installed capacity and output of new energy sources will be allocated to each new energy access node, specifically as follows: (7) (8) in, Indicates the first The first evolutionary stage The installed capacity of each node, Indicates the first The first evolutionary stage Typical active power output of a node.
[0038] This yields the source-load distribution status after the new energy sources are connected at each stage.
[0039] This embodiment uses a scaling factor. By directly linking the cumulative installed capacity of new energy sources with the increase in load, we can ensure that the scale of new energy installed capacity at each stage is coordinated and matched with the system load demand, thus avoiding the source-load mismatch problem caused by the pre-setting of a fixed penetration rate in existing methods.
[0040] S104: Based on the total system load and the total output of new energy sources, recursively calculate the output allocation results of the online synchronous machines; based on the load rate of each synchronous machine, determine whether the retirement conditions are triggered, and remove the synchronous machines that have triggered retirement in the next evolution stage.
[0041] In this embodiment, in the first Each evolutionary stage, based on the total system load level and new energy contribution Determine the total output of the synchronizer required by the system. Specifically: (9) Let the first The set of online synchronizers for each evolutionary stage is as follows: The output adjustment of the synchronous machine is based on the actual output of the online synchronous machine in the previous stage, i.e., the [missing information]. The output of each synchronizer in the stage is from the first The stage operation status is obtained recursively. This ensures a smooth transition in the output of the synchronous machine between adjacent stages, avoiding output jumps between stages caused by static section replacement, and making the evolution process closer to the actual operating law.
[0042] When the total output of the required synchronous generators is less than the total reference output of the online synchronous generators in the previous stage, it indicates that the newly added output of new energy sources needs to replace part of the synchronous generator output. At this time, the output is reduced according to the principle of "local priority replacement and global coordinated reduction", which truly reflects the priority replacement effect of centralized access of new energy sources on local synchronous generators, is consistent with the actual power system operation and dispatch logic, and overcomes the shortcomings of the existing method of simply replacing by proportion.
[0043] The reduction principle is as follows: First, the reduction amount is allocated to the online synchronous generators in the centralized new energy access area according to the current output ratio; if the synchronous generators in this area have already dropped to the minimum stable output threshold of the synchronous generators. If the remaining reduction cannot be borne by all the reductions, the remaining reductions will continue to be shared proportionally by the other online synchronizers in the entire system.
[0044] Among them, the centralized renewable energy access area is defined by pre-dividing the power system into regions based on the distribution of renewable energy resources, renewable energy base planning, policy development goals, and renewable energy access nodes, and the area where the renewable energy access nodes are located is designated as the centralized renewable energy access area; the current output ratio refers to the [number]th [unit] in the centralized renewable energy access area. i The proportion of the active power output of the online synchronous machine in the previous evolution stage to the total active power output of all online synchronous machines in the region.
[0045] When the total required output of the synchronous machines exceeds the sum of the reference outputs of the online synchronous machines in the previous stage, it indicates that the load increase necessitates an increase in the output of the synchronous machines. In this case, the increase is distributed proportionally according to the remaining available capacity of the online synchronous machines to ensure the system maintains active power balance.
[0046] Based on the above explanation, the specific recursive process is as follows: From equation (9), we obtain the first... k The total output of the synchronizer required for each evolutionary stage of the system is: .
[0047] If the actual output of the online synchronizer in the previous stage is used as the reference output for this stage, then the total reference output is: ; The total output adjustment of the synchronous machine in this stage is: ; when This indicates a need to reduce the output of the synchronous generators. The reduction is initially allocated to the online synchronous generators within the centralized renewable energy access area according to their actual output ratio from the previous stage. For the synchronous generators... iThe apportionment ratio is as follows: ; The corresponding recursive force is: ; in, For the collection of online synchronization machines in the centralized access area of new energy sources, Indicates the previous stage synchronization machine i The actual output.
[0048] If there is still an unallocated reduction after some synchronous machines have reached their minimum operating output, the remaining reduction will be distributed among the other online synchronous machines in the entire system according to their current output ratio.
[0049] when When this indicates a need to increase the output of the synchronizer, the increase is distributed proportionally to the remaining available capacity of each online synchronizer. (Synchronizer) i The sharing ratio is: ; in, Indicates a synchronous machine i Maximum output.
[0050] The corresponding recursive force is: ; when At that time, the output of each synchronizer remains constant: ; For in the first k Synchronizers that are decommissioned at the end of Phase 1, in the... k The stage removes it from the set of online synchronizers, sets its output to zero, and it no longer participates in output allocation.
[0051] Through the above recursive adjustments, we obtain the... Output of each online synchronizer in each stage .
[0052] For the Stage Online Synchronizer Calculate its load factor: (10) in, Synchronizer Rated capacity.
[0053] When formula (11) is satisfied: (11) Determine the synchronization machine In the The system is currently operating at low load.
[0054] Further statistics on synchronization machines The number of stages in which the machine continuously operates under low load. (If the synchronous machine...) The number of consecutive low-load phases reached the threshold If the condition is met, the synchronizer is determined to have triggered the retirement condition and will be removed from the set of online synchronizers in the next evolutionary stage. (12) in, For the first The set of synchronizers that are phased to retire. For the first +1 stage online synchronization machine set.
[0055] This yields the number of online synchronizers, online capacity, decommissioned unit numbers, and cumulative decommissioned capacity at each stage.
[0056] This embodiment objectively reflects the process of a synchronous machine naturally retiring due to long-term low-load operation by using a dual criterion of load rate threshold and number of consecutive low-load stages. It overcomes the technical defects of existing methods that rely solely on manually setting replacement ratios to adjust the capacity of the synchronous machine and cannot reflect the gradual decline in support capacity.
[0057] S105: Based on the updated node active power injection, determine whether the branch is a critical power flow bottleneck channel. If so, perform parallel expansion equivalent correction on the branch to obtain the network topology correction result, which serves as the input for the next evolution stage.
[0058] In this embodiment, in the first In this phase, the active power injection at the nodes is calculated based on the updated load, new energy output, and synchronous machine output, and the line power flow is obtained using a DC power flow model.
[0059] For branch roads Its contributing tidal current is represented as: (13) in, , The first Phase Node ,node voltage phase angle, branch road In the The equivalent reactance of the stage.
[0060] According to the upper limit of the allowable phase angle difference Define the upper limit of equivalent transmission for tributaries: (14) Branch load rate: (15) When the branch load factor satisfies formula (16): (16) The branch was determined to be the first The key bottleneck channel of the phase is identified, and the branch is expanded in parallel with equivalent correction.
[0061] The corrected branch reactance is: (17) in, This represents the line expansion factor. For branches that have not reached the load factor threshold, the parameters remain unchanged. The corrected network topology serves as the input for the next stage of power flow calculation, realizing the cumulative evolution of the network-side state.
[0062] In existing source-network evolution scenario construction, power supply-side evolution and network-side topology changes are usually handled separately. This makes it difficult to make phased corrections to the network topology or line transmission capacity based on the line power flow bottlenecks formed after the centralized access of new energy sources. Consequently, the generated scenarios fail to reflect the power flow shifts and network enhancement requirements caused by changes in source-load distribution. This embodiment calculates line power flow in conjunction with the current source-load distribution at each evolution stage and dynamically corrects the network topology based on the calculation results. This ensures that the network side and the source side always maintain coordinated evolution, fundamentally solving the technical defects of source-network separation processing.
[0063] S106: Based on the grid-type new energy proportion function, the newly added new energy installed capacity is split to obtain the cumulative installed capacity of grid-type new energy and the cumulative installed capacity of grid-connected new energy.
[0064] In this embodiment, the newly added new energy installed capacity in the k-th evolution stage is set as: (18) Then the newly added grid-type new energy capacity in the kth evolution stage is: (19) The newly added grid-connected renewable energy capacity is: (20) Further obtain the first The cumulative installed capacity of grid-connected new energy vehicles in this phase is: (twenty one) No. The cumulative installed capacity of grid-connected new energy vehicles in this phase is: (twenty two) By further decomposing the total installed capacity of new energy into grid-connected new energy and grid-linked new energy in the above manner, the power structure evolution results under different grid-connected new energy penetration paths can be obtained.
[0065] Existing methods typically treat new energy sources as a uniform equivalent power source, failing to distinguish the fundamental differences between grid-connected and grid-following new energy sources in terms of frequency support mechanisms and dynamic response characteristics. They also lack a description of the penetration path of the changing proportion of grid-connected new energy sources in each evolutionary stage, making it difficult to support power structure evolution analysis under different grid-connected new energy development models. This embodiment fundamentally solves this deficiency by introducing a grid-connected new energy proportion function β(k), accurately dividing the newly added new energy installed capacity into grid-connected and grid-following types at each evolutionary stage. By setting different forms of the β(k) function (e.g., fixed ratio mode, uniform transition mode, variable speed transition mode, and S-shaped transition mode), multiple power structure evolution scenarios under different grid-connected new energy penetration paths can be generated based on the same load growth, total new energy access volume, and synchronous machine retirement. Multiple differentiated scenarios can be obtained without repeatedly executing the entire evolution process, significantly improving scenario generation efficiency.
[0066] S107: All evolutionary stages have been iteratively calculated, forming a multi-stage source-network collaborative evolution scenario set.
[0067] Complete the first After the stage calculation, the evolution scenario data for that stage is output, including: the set of online synchronous machines, the set of retired synchronous machines, the total installed capacity of synchronous machines, the total output of synchronous machines, the total installed capacity of new energy, the total output of new energy, the cumulative installed capacity of grid-type new energy, the cumulative installed capacity of grid-connected new energy, the proportion of grid-type / grid-connected new energy installed capacity, the output proportion of various power sources, the line load rate, the set of expanded lines, and the corrected network topology.
[0068] Repeat the above steps until all evolutionary stages are completed. Ultimately, this will form a multi-stage source-network collaborative evolution scenario set that takes into account the retirement of synchronous machines, the penetration path of grid-type new energy sources, and the collaborative correction of network topology.
[0069] To illustrate the feasibility and engineering application value of the method in this embodiment, the following is combined with... Figure 2A case study analysis is conducted using the IEEE 39-node system. In this case study, the IEEE 39-node system is divided into three regions. Region 1 is designated as the centralized renewable energy access region, with nodes 25, 26, and 29 selected as renewable energy access points. Existing synchronous machines in Region 1 are prioritized for replacement by renewable energy sources. Based on this, a multi-stage source-network collaborative evolution scenario is generated by unifying load growth, centralized renewable energy access, continuous low-load retirement criteria for synchronous machines, and network topology correction based on DC power flow. Furthermore, the renewable energy structure is decomposed according to the renewable energy increment ratio change patterns of four network configurations, yielding the power structure evolution results under different renewable energy penetration paths.
[0070] In the IEEE 39-bus system example, the total system load increased from 6150.10 MW in Phase 0 to 8917.65 MW in Phase 9; the output of new energy sources increased from 0 MW to 4151.32 MW; and the total output of the synchronous machine decreased from 6150.10 MW to 4766.33 MW. Figure 3 As shown in the figure. The results indicate that this implementation method can continuously depict the process of declining output of traditional synchronous machines, gradual absorption of new loads by new energy sources, and phased changes in the power supply structure under the combined effects of load growth and new energy access.
[0071] The calculation results show that units 30, 37, and 38 were below the minimum stable output threshold for two consecutive stages, stages 7 and 8, and therefore decommissioning took effect in stage 9, as shown in Table 1. Specifically, unit 30 has a capacity of 300 MVA and a load factor of 0.179 in the final stage; unit 37 has a capacity of 600 MVA and a load factor of 0.193 in the final stage; and unit 38 has a capacity of 900 MVA and a load factor of 0.198 in the final stage. All three units are located in renewable energy access area 1, indicating that the method in this embodiment can demonstrate the priority replacement of local traditional synchronous generators by centralized renewable energy access.
[0072] Table 1. Retirement Status of Synchronous Generating Units
[0073] Figure 4 The curves showing the changing proportions of various power sources' installed capacity under the uniform-rate transition mode of incremental renewable energy in a grid-connected system are presented. Stage 8 shows a clear inflection point: in stage 8, the number of online synchronous generators is 10, and the online synchronous capacity is 6800MW; in stage 9, due to the retirement of 3 synchronous generators, the number of online synchronous generators decreases to 7, and the online synchronous capacity decreases to 5000MW. These results demonstrate that the method in this embodiment can not only generate the source-grid evolution state at each stage but also reveal the abrupt changes in system structure caused by the concentrated retirement of synchronous generators, providing a key scenario for subsequent dynamic frequency response analysis and frequency security verification.
[0074] After generating the basic power grid evolution scenario, this embodiment further considers four types of transition modes for the proportion of grid configurations in newly added renewable energy sources: a fixed ratio mode, a uniform transition mode, a variable-speed transition mode with slow initial phase and accelerated later phase, and a transition mode with slow initial phase, fast mid-term phase, and stable later phase. This allows for the formation of power structure evolution scenarios under different grid configurations for renewable energy development paths, based on the same load growth, renewable energy access, and synchronous machine retirement. Figure 5 As shown, this provides a unified basis for comparing the impact of different grid-type new energy penetration strategies on the dynamic frequency characteristics of the system.
[0075] Table 2 presents the details of the line expansion, combined with... Figure 6 Lines 26-29 reached load rates of 0.875 and 0.855 in stages 7 and 8 respectively, exceeding the set threshold. Therefore, they were identified as critical power flow bottleneck channels and triggered two equivalent expansion corrections.
[0076] Table 2. Line Expansion Status
[0077] The results show that as the installed capacity and output of new energy at node 29 gradually increase, this method can identify the pressure of new energy transmission in the region and reflect the coordinated evolution demand of the network side as the source side changes through the equivalent expansion of the line.
[0078] It is worth noting that in the 9th stage, even with further growth in new energy sources, the load factor of lines 26-29 will decrease due to the decommissioning of the synchronous machine at node 38, which reduces the power transmission pressure.
[0079] In summary, the method in this embodiment can continuously depict the entire process of the decline in output of traditional synchronous machines, the gradual assumption of new loads by new energy sources, and the phased changes in power supply structure under the combined effect of load growth and new energy access. This overcomes the shortcomings of existing methods that use static section replacement and cannot reflect coupled evolution.
[0080] Example 2 In one or more embodiments, a power system source-grid collaborative evolution scenario construction system is disclosed, specifically including: The data acquisition module is used to acquire the initial model and evolution parameters of the power system; the evolution parameters include at least the load growth rate and the proportion function of grid-type new energy in newly added new energy sources; The phased load growth module is used to, according to the load growth rate, in the first... In the first evolutionary stage, the active power load of each load node is updated according to a unified growth pattern, and the calculation is performed. The node load increment in each evolution stage relative to the initial stage; The new energy output allocation module is used to determine the first load increment based on the load increment. The cumulative installed capacity of new energy and the typical active power output of new energy in each evolution stage are then evenly distributed to each new energy access node to obtain the source-load distribution state after the new energy access. The synchronous machine output adjustment module is used to recursively calculate the output allocation result of the online synchronous machine based on the total system load and the total output of new energy sources; determine whether the decommissioning conditions are triggered based on the load rate of each synchronous machine, and remove the synchronous machine that has triggered decommissioning in the next evolution stage; The network topology correction module is used to determine whether a branch is a critical power flow bottleneck channel based on the updated node active power injection. If so, the branch is modified by parallel expansion to obtain the network topology correction result, which is used as the input for the next evolution stage. The new energy path decomposition module is used to decompose the newly added new energy installed capacity according to the grid-type new energy proportion function to obtain the cumulative installed capacity of grid-type new energy and the cumulative installed capacity of grid-connected new energy. The results output module is used to form a multi-stage source-network collaborative evolution scenario set after all evolution stages have been iterated and calculated.
[0081] It should be noted that the specific implementation methods of the above modules are exactly the same as those in Example 1, and will not be described in detail again.
[0082] Example 3 In one or more embodiments, a terminal device is disclosed, which includes a processor and a memory. The processor is used to implement instructions; the memory is used to store multiple instructions, which are adapted to be loaded by the processor and executed as described in Embodiment 1, for constructing a power system source-grid collaborative evolution scenario.
[0083] It should be understood that in this embodiment, the processor can be a central processing unit (CPU), or it can be other general-purpose processors, digital signal processors (DSPs), application-specific integrated circuits (ASICs), field-programmable gate arrays (FPGAs), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor can be a microprocessor or any other conventional processor.
[0084] Memory may include read-only memory and random access memory, and provides instructions and data to the processor. A portion of the memory may also include non-volatile random access memory. For example, memory may also store information about the device type.
[0085] In the implementation process, each step of the above method can be completed by the integrated logic circuits in the processor hardware or by software instructions.
[0086] While the specific embodiments of the present invention have been described above in conjunction with the accompanying drawings, this is not intended to limit the scope of protection of the present invention. Those skilled in the art should understand that various modifications or variations that can be made by those skilled in the art without creative effort based on the technical solutions of the present invention are still within the scope of protection of the present invention.
Claims
1. A method for constructing a power system source-grid collaborative evolution scenario, characterized in that, include: Obtain the initial model and evolution parameters of the power system; the evolution parameters include at least the load growth rate and the proportion function of grid-connected new energy sources among newly added new energy sources; Based on the load growth rate, in the... In the first evolutionary stage, the active power load of each load node is updated according to a unified growth pattern, and the calculation is performed. The node load increment in each evolution stage relative to the initial stage; Determine the first based on the load increment. The cumulative installed capacity of new energy and the typical active power output of new energy in each evolution stage are then evenly distributed to each new energy access node to obtain the source-load distribution state after the new energy access. Based on the total system load and the total output of new energy sources, the output allocation result of the online synchronous machine is calculated recursively; Based on the load rate of each synchronizer, determine whether the retirement conditions have been triggered, and remove the synchronizers that have triggered retirement in the next evolution phase; Based on the updated node active power injection, determine whether the branch is a critical power flow bottleneck channel. If so, perform parallel expansion equivalent correction on the branch to obtain the network topology correction result, which serves as the input for the next evolution stage. Based on the grid-type new energy proportion function, the newly added new energy installed capacity is split to obtain the cumulative installed capacity of grid-type new energy and the cumulative installed capacity of grid-connected new energy. After all evolutionary stages have been iteratively calculated, a multi-stage source-network collaborative evolution scenario set has been formed.
2. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, The evolution parameters include: load growth rate. The ratio between new energy installed capacity and load growth Typical output coefficient of new energy Minimum stable output threshold of synchronous machine Threshold for the number of consecutive low-load phases Line load rate threshold Line expansion coefficient And the function of the proportion of grid-type new energy in newly added new energy sources. .
3. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, Update the active power load of each load node according to the unified growth method, and calculate the first... The node load increments in each evolution stage relative to the initial stage are as follows: According to the node Determine the nodes based on the active power load and load growth rate in the initial stage. In the Active load at each evolutionary stage; The active load of all nodes is accumulated to obtain the first... The total load of each evolution stage, the difference between the total load and the total load of the initial stage, is used as the load increment.
4. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, Based on the total system load and the total output of new energy sources, the output allocation result of the online synchronous machine is calculated recursively, as follows: The total output of the synchronous machine required by the system is determined based on the load level and the output of new energy sources. The result is obtained by recursively deriving the output from the operating state of the previous evolution stage. The output of each synchronizer in each evolutionary stage; If the total output of the required synchronous machines is less than the total output of the synchronous machines in the previous evolution stage, the reduction amount will first be allocated to the online synchronous machines in the new energy centralized access area according to the current output ratio; if the synchronous machines in this area have been reduced to the minimum operating constraints and still cannot bear the full reduction amount, the remaining reduction amount will continue to be allocated to the other online synchronous machines in the entire system according to the ratio.
5. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, Based on the load rate of each synchronizer, determine whether the retirement conditions are triggered, specifically as follows: According to the The ratio of the output of each online synchronous machine to the rated capacity of the corresponding synchronous machine in each evolution stage is used to calculate the load rate of each synchronous machine. If the load rate of the synchronizer is less than the preset minimum stable output threshold of the synchronizer Then it is determined that the synchronizer is in the first... Each evolutionary stage is operating at low load. If the number of consecutive low-load operation periods of the synchronizer reaches a preset threshold... If the condition is met, the synchronizer is determined to have triggered the retirement condition and will be removed from the set of online synchronizers in the next evolutionary stage.
6. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, Based on the updated node active power injection, determine whether the branch is a critical power flow bottleneck channel, specifically: The active power injection at the nodes is calculated based on the updated load, new energy output, and synchronous machine output, and the active power flow of the line is obtained using a DC power flow model. According to the branch road The branch load rate is determined by the ratio of the active power flow to the branch equivalent transmission limit; whereby the branch equivalent transmission limit is based on the allowable phase angle difference limit and the branch load rate. In the The ratio of the equivalent reactance at each evolution stage can be obtained; If the branch load rate is greater than or equal to the preset line load rate threshold Determine the branch For the first The key trend bottleneck channels in each evolutionary stage.
7. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, Based on the aforementioned grid-type renewable energy proportion function, the newly added renewable energy installed capacity is broken down as follows: According to the The function of newly added new energy installed capacity and the proportion of grid-type new energy in newly added new energy at each evolution stage Determine the first The newly added grid-type and grid-connected new energy capacity in each evolutionary stage; No. -1 stage of evolution: network-type new energy capacity and the first stage The sum of the newly added grid-type new energy capacity in each evolutionary stage is used as the first... The cumulative installed capacity of grid-connected new energy vehicles in each evolutionary stage; No. -1 evolutionary stage of grid-connected new energy capacity and the first The sum of the newly added grid-connected new energy capacity in each evolutionary stage is used as the first... The cumulative installed capacity of grid-type new energy in each evolutionary stage.
8. The method for constructing a power system source-grid collaborative evolution scenario as described in claim 1, characterized in that, The multi-stage source-network collaborative evolution scenario set includes: the set of online synchronous machines, the set of retired synchronous machines, the total installed capacity of synchronous machines, the total output of synchronous machines, the total installed capacity of new energy sources, the total output of new energy sources, the cumulative installed capacity of grid-type new energy sources, the cumulative installed capacity of grid-connected new energy sources, the installed capacity ratio of grid-type / grid-connected new energy sources, the output ratio of various power sources, the line load rate, the set of expanded lines, and the corrected network topology.
9. A system for constructing a power system source-grid collaborative evolution scenario, characterized in that, include: The data acquisition module is used to acquire the initial model and evolution parameters of the power system; the evolution parameters include at least the load growth rate and the proportion function of grid-type new energy in newly added new energy sources; The phased load growth module is used to, according to the load growth rate, in the first... In the first evolutionary stage, the active power load of each load node is updated according to a unified growth pattern, and the calculation is performed. The node load increment in each evolution stage relative to the initial stage; The new energy output allocation module is used to determine the first load increment based on the load increment. The cumulative installed capacity of new energy and the typical active power output of new energy in each evolution stage are then evenly distributed to each new energy access node to obtain the source-load distribution state after the new energy access. The synchronous machine output adjustment module is used to recursively calculate the output allocation result of the online synchronous machine based on the total system load and the total output of new energy sources; determine whether the decommissioning conditions are triggered based on the load rate of each synchronous machine, and remove the synchronous machine that has triggered decommissioning in the next evolution stage; The network topology correction module is used to determine whether a branch is a critical power flow bottleneck channel based on the updated node active power injection. If so, the branch is modified by parallel expansion to obtain the network topology correction result, which is used as the input for the next evolution stage. The new energy path decomposition module is used to decompose the newly added new energy installed capacity according to the grid-type new energy proportion function to obtain the cumulative installed capacity of grid-type new energy and the cumulative installed capacity of grid-connected new energy. The results output module is used to form a multi-stage source-network collaborative evolution scenario set after all evolution stages have been iterated and calculated.
10. A terminal device comprising a processor and a memory, the processor for implementing instructions; the memory for storing multiple instructions, characterized in that, The instructions are adapted to be loaded by a processor and executed as described in any one of claims 1-8, the method for constructing a power system source-grid collaborative evolution scenario.