A power supply scheme generation method, device and equipment for industry expansion installation considering new energy access and a computer storage medium
By separating the actual total growth and spatial migration of new energy vehicle charging demand, and combining AC power flow calculation and electrical constraint margin analysis, a safe access system scheme is generated and continuously transmitted to the power receiving and billing scheme. This solves the problem of spatiotemporal fluctuations and spatial migration of new energy vehicle charging demand, and improves the integrity and consistency of the power supply scheme.
Patent Information
- Application Number
- CN202611536468.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-20
AI Technical Summary
Existing power supply solutions for business expansion applications fail to effectively consider the spatiotemporal fluctuations and spatial migration characteristics of new energy vehicle charging demand, resulting in localized reverse power and high node voltage, and making it difficult to achieve coordinated adjustment of parameters such as power supply voltage level and power supply capacity.
By acquiring target customers' electricity application information and new energy configurations, and combining multi-source spatiotemporal data to predict regional background charging demand, the system separates the actual total growth and spatial migration components, performs AC power flow calculations, quantifies changes in electrical constraint margins, generates a safe access system scheme, and continuously transmits it to the power receiving system and metering and billing scheme to ensure the consistency of all parameters.
Effectively identify changes in electrical constraints caused by spatial shifts in charging demand, reflect the impact of reverse power from new energy sources, improve the matching degree between access location and actual power distribution operation status, reduce scheme deviation, and ensure the integrity and consistency of power supply scheme.
Smart Images

Figure CN123144233A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of new energy vehicle charging technology, specifically to a method, apparatus, equipment, and computer storage medium for generating a power supply scheme for business expansion applications that takes into account new energy access. Background Technology
[0002] With the continuous growth of new energy vehicle ownership and various charging facilities, new energy vehicle charging load has become an important component of the new load on the power distribution network. At the same time, the continuous integration of new energy resources such as distributed photovoltaic, distributed wind power, and user-side energy storage has made the power flow of the power distribution network exhibit significant time-varying and bidirectional characteristics. Existing power supply schemes for business expansion applications typically determine the power source and access line based on factors such as the customer's requested capacity, electricity address, line load rate, remaining capacity of the power supply transformer, and power supply distance.
[0003] However, the charging demand of new energy vehicles is affected by factors such as vehicle origin-destination (OD), traffic flow, parking duration, regional functions, weather, and user behavior, exhibiting obvious spatiotemporal fluctuations and spatial migration characteristics; the access of new energy vehicles may also lead to local reverse power and high voltage at nodes.
[0004] Future changes in regional charging load may stem from both actual total growth and spatial migration of existing charging demand between different areas. Even if the total charging demand in the power supply area does not increase due to migration, the migration of charging demand from areas with large electrical margins to areas closer to thermal stability or voltage boundaries may still alter the safety margins of lines, power supply transformers, and node voltages. Conversely, migration to areas with high renewable energy output may absorb renewable energy power, alleviating reverse power flow or high voltage. Therefore, predicting future regional load alone is insufficient to reflect the changes in electrical constraints caused by differences in electrical location before and after spatial migration.
[0005] Furthermore, a complete power supply solution for business expansion typically includes an overview of the customer's electricity application, a system access plan, a power receiving system plan, and a metering and billing plan. If existing solutions only specify the access point, power supply, and lines, without further transferring parameters such as power supply voltage level, power supply capacity, number of circuits, and property boundaries to the power receiving and metering systems, it becomes difficult to achieve coordinated adjustments to the configurations of the power receiving transformer, main wiring, incoming lines and protection systems, reactive power compensation, emergency power supply, substation, metering points, metering devices, information collection, billing, and loss handling.
[0006] Therefore, it is necessary to establish a power supply solution generation technology that can take into account the growth and spatial migration of charging demand, the bidirectional power impact of new energy sources, and realize the associated generation and verification of customer applications, access systems, power receiving systems and metering and billing schemes.
[0007] The information disclosed in the background section is only intended to enhance the understanding of the background of this disclosure, and therefore may include information that does not constitute prior art known to those skilled in the art. Summary of the Invention
[0008] The purpose of this application is to provide a method, apparatus, equipment, and computer storage medium for generating power supply schemes for business expansion applications that take into account the access of new energy sources, so as to solve the problems in the background art mentioned above.
[0009] To achieve the above objectives, this application provides the following technical solution: a method for generating a power supply scheme for business expansion applications considering new energy access, comprising:
[0010] Obtain electricity application information, load information, and new energy and energy storage configuration information of target customers to construct an overview of customer electricity applications, thereby forming a unified data foundation for the target customers' new installed load, new energy output, and energy storage operation characteristics;
[0011] Acquire multi-source spatiotemporal data of the target power supply area to predict the regional background charging demand that does not include the new load applied for by the target customer, so as to distinguish the new load applied for by the target customer from the regional background charging demand and reduce the impact of the new load of the target customer being repeatedly included in the background load on the subsequent power supply analysis.
[0012] The actual total growth component and spatial migration component of regional background charging demand are separated, and the background source load of each region is mapped to the distribution node to obtain the background active and reactive source load status of the distribution node. Thus, the changes in charging demand at the regional scale are transformed into changes in node source load with actual electrical location attributes.
[0013] AC power flow calculations are performed based on the background active and reactive power load status of distribution nodes to obtain the electrical operating status of lines, power supply side transformers and distribution nodes in the distribution network under the regional background power load conditions.
[0014] The impact of electrical constraint margin on different distribution nodes is obtained by obtaining the node power disturbance, the electrical constraint difference component of the corresponding electrical location before and after spatial migration is calculated, and the power supply side access conditions of candidate distribution nodes are obtained, so as to quantify the change in safety margin when the same background charging demand occurs in different electrical locations.
[0015] By utilizing the customer's electricity application overview, electrical constraint differential components, and power supply side access conditions, candidate access system schemes are generated, thereby incorporating the customer's actual electricity demand, the electrical impact of spatial migration of charging demand, and the actual power supply capacity of the distribution side into the candidate scheme generation process.
[0016] The target customer load and new energy and energy storage configurations are superimposed onto the candidate networks corresponding to each candidate access system scheme to verify the AC power flow and power supply reliability, and screen the safe access system schemes, so as to redetermine the power distribution operation safety and load power supply capacity based on the network status after the actual access of the target customers.
[0017] For each security access system solution, a matching power receiving system solution and metering and billing solution are configured. The consistency of the customer's electricity application overview, security access system solution, power receiving system solution and metering and billing solution is verified, and the target business expansion application power supply solution is output. In this way, the power supply side analysis results are continuously transmitted to the customer's power receiving and metering and billing configuration process, which effectively improves the consistency and completeness of various technical parameters in the target business expansion application power supply solution.
[0018] Preferably, the regional background charging demand consists of a real total growth component and a spatial migration component. The real total growth component is obtained by allocating the change in the overall background charging demand of the target power supply area according to the regional growth allocation coefficient. The spatial migration component is obtained based on the migration probability of charging demand between regions and the available charging demand. Furthermore, the inflow power and outflow power of all regions remain constant.
[0019] This separates the total change in charging demand in the target power supply area from the change in the location of charging demand, avoiding the direct treatment of the increase or decrease in regional load caused by spatial migration as new charging demand, and providing an independent data basis for subsequent analysis of the electrical impact of charging demand migration.
[0020] Preferably, the electrical constraint margin impact includes the line thermal stability safety margin, the power supply side transformer capacity safety margin, and the node voltage safety margin; a combined active and reactive disturbance corresponding to the charging power factor is applied to the distribution node, and the unit charging power margin consumption coefficient is obtained based on the ratio of the change in safety margin before and after the disturbance to the disturbance active power, and the regional equivalent unit margin consumption coefficient is obtained by using the allocation coefficient of the spatial area and the distribution node.
[0021] By converting node power variations into margin variations of different electrical operating constraints, a quantitative correlation can be formed between spatial regions and distribution electrical constraints, providing basic parameters for differential calculation of electrical constraints generated by spatial migration.
[0022] Preferably, the electrical constraint difference components of the corresponding electrical locations before and after spatial migration are calculated based on the difference between the background equivalent charging demand migration power and the regional equivalent unit margin consumption coefficient of the migration area and the migration area. For the background equivalent charging demand migration power that exceeds the applicable range of a single disturbance, it is divided into multiple migration increments. After each migration increment is completed, the background active and reactive power source load status of the distribution node and the regional equivalent unit margin consumption coefficient are updated, and the electrical constraint difference components corresponding to each migration increment are accumulated.
[0023] This method can reflect the increase or decrease in constraint margin caused by the change in electrical location after the charging demand is transferred from one region to another. At the same time, it reduces the impact of nonlinear changes in AC power flow on the differential results under large-scale migration by segmented updates.
[0024] Preferably, the candidate access system schemes correspond to different candidate distribution nodes and power supply paths. Under the condition that the regional background charging demand does not include the target customer's new installed load, the target customer's load, new energy output and energy storage charging and discharging power are loaded to the corresponding candidate distribution nodes to reconstruct the candidate network. The AC power flow and the maximum expected short-circuit current are recalculated for each candidate network to obtain the power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current and property boundary location of the safe access system scheme.
[0025] This allows for the formation of actual candidate network states after a target customer's access at different access locations, avoiding the direct use of background network calculation results before the target customer's access to evaluate the power supply status after access, and improving the correspondence between the secure access system scheme and the actual access conditions.
[0026] Preferably, the power receiving system scheme limits the configuration of the main power receiving wiring and power receiving transformer based on the power supply voltage level, power supply capacity and number of power supply circuits of the safe access system scheme, limits the rated current of the power receiving circuit based on the maximum continuous operating current, limits the corresponding breaking capacity based on the maximum expected short circuit current, and configures the emergency power supply capacity according to the customer's security load and available energy storage.
[0027] By continuing to use the key electrical parameters formed by the secure access system scheme as the configuration basis for the power receiving system scheme, the parameter transfer relationship between the power supply side capacity and the customer's power receiving capacity can be established, and the customer load demand under normal operation and specified power supply conditions can be effectively guaranteed.
[0028] Preferably, the metering and billing scheme establishes a mapping relationship between independent billing power supply circuits and metering points, and configures line loss and transformer loss handling methods according to the location relationship between the property boundary and the metering point; when there is reverse active power at the metering point, forward active energy and reverse active energy are obtained respectively, and the power supply capacity, power receiving capacity, power supply circuit, operating current, short circuit current, property boundary, reactive power compensation and emergency power supply are used as correlation consistency verification parameters.
[0029] This enables the system to adapt to the bidirectional power exchange operation that occurs after new energy sources are connected, and establishes a correspondence between the key parameters of the access side, the power receiving side, and the metering side, effectively reducing the problem of parameter inconsistency caused by different schemes generating parameters separately.
[0030] This application also provides a power supply scheme generation device for business expansion applications that takes into account the access of new energy sources, including a customer information processing unit, a background demand prediction unit, a source-load mapping unit, a power flow calculation unit, an electrical impact processing unit, a candidate scheme generation unit, a safety scheme screening unit, and a scheme output unit.
[0031] The customer information processing unit is used to obtain the target customer's electricity application information, load information, and new energy and energy storage configuration information, and to construct an overview of the customer's electricity application.
[0032] The background demand forecasting unit is used to acquire multi-source spatiotemporal data of the target power supply area and forecast the background charging demand in areas that do not include new load applications from target customers.
[0033] The source-load mapping unit is used to separate the actual total growth component and spatial migration component of the regional background charging demand, and to map the background source load of each region to the distribution node to obtain the background active and reactive source load status of the distribution node.
[0034] The power flow calculation unit is used to perform AC power flow calculations based on the background active and reactive load states of the distribution nodes.
[0035] The electrical influence processing unit is used to obtain the electrical constraint margin influence of different power distribution nodes through node power disturbance, calculate the electrical constraint difference components of the corresponding electrical positions before and after spatial migration, and obtain the power supply side access conditions of candidate power distribution nodes.
[0036] The candidate solution generation unit is used to generate candidate access system solutions by utilizing the customer's electricity application overview, electrical constraint differential components, and power supply side access conditions.
[0037] The security scheme screening unit is used to overlay the target customer load and new energy and energy storage configurations onto the candidate networks corresponding to each candidate access system scheme to verify the AC power flow and power supply reliability, and to screen the security access system scheme.
[0038] The solution output unit is used to configure matching power receiving system solutions and metering and billing schemes for the secure access system solution. It performs consistency verification on the customer's electricity application overview, secure access system solution, power receiving system solution, and metering and billing scheme, and outputs the target business expansion application power supply solution. Through data connection between various processing units, the electrical impact of spatial changes in regional charging demand can be integrated into the access solution selection and subsequent power receiving and metering and billing configuration process.
[0039] This application also provides a power supply scheme generation device for business expansion application considering new energy access, including a processor and a memory. The memory stores a computer program. When the computer program is executed by the processor, it obtains the target customer's electricity application information, load information and new energy and energy storage configuration information to construct a customer's electricity application overview.
[0040] Acquire multi-source spatiotemporal data of the target power supply area and predict the background charging demand in areas that do not include new load applications from target customers;
[0041] Separate the actual total growth component and spatial migration component of the background charging demand in the region, and map the background source load of each region to the distribution node to obtain the background active and reactive source load status of the distribution node.
[0042] AC power flow calculations are performed based on the background active and reactive load states of distribution nodes. The influence of electrical constraint margins on different distribution nodes is obtained through node power disturbances. The electrical constraint difference components of the corresponding electrical locations before and after spatial migration are calculated, and the power supply side access conditions of candidate distribution nodes are obtained.
[0043] Candidate access system solutions are generated by utilizing customer electricity application overview, electrical constraint differential components, and power supply side access conditions;
[0044] The target customer load and the configuration of new energy and energy storage are superimposed onto the candidate networks corresponding to each candidate access system scheme to verify the AC power flow and power supply reliability, and to select a safe access system scheme.
[0045] Configure a matching power receiving system scheme and metering and billing scheme for the security access system scheme, and output the target business expansion application power supply scheme after verifying the correlation consistency.
[0046] By executing the above continuous processing by the processor, the access of new energy sources, the spatial migration of charging demand, and the electrical constraints of the distribution network can be incorporated into the power supply scheme generation process for business expansion applications.
[0047] This application also provides a computer storage medium, in which a computer program is stored. When the computer program is executed by a processor, it implements the above-mentioned method for generating a power supply scheme for business expansion applications that takes into account the access of new energy sources.
[0048] By continuously processing customer application data, multi-source spatiotemporal data, power distribution node source-load status, and candidate network operation data through computer programs, the power supply scheme for target business expansion applications can be calculated and generated, while maintaining consistency in processing logic among the methods, devices, equipment, and computer storage media corresponding to the technical solutions.
[0049] The technical effects and advantages provided by this application in the above technical solution are as follows:
[0050] This application separates the actual total growth of new energy vehicle charging demand from its spatial migration, and maps regional background loads to actual distribution nodes. By quantifying the differences in the impact of different electrical locations before and after charging demand migration on line loads, power supply transformer capacity, and node voltage safety margins through AC power flow and node power disturbances, it effectively identifies changes in electrical constraints caused by the spatial transfer of charging demand. Simultaneously, incorporating the reverse power of new energy sources into the analysis process reflects the mitigation effect of charging demand migration into new energy output areas on reverse power flow and voltage exceedance risks, improving the matching degree between candidate access locations and actual distribution operation states.
[0051] This application continuously transmits the customer's electricity application overview, electrical constraint differentials, and power supply access conditions to candidate access system schemes. It also loads the target customer's load, as well as new energy and energy storage configurations, into the corresponding candidate networks for AC power flow and power supply reliability verification. This effectively reduces scheme deviations caused by the repeated inclusion of new target customer loads in the background load calculation and the continued use of original operating results after network changes. After obtaining a secure access system scheme, it further transmits parameters such as power supply voltage level, power supply capacity, number of power supply circuits, operating current, short-circuit current, and property boundary to the power receiving system scheme and metering and billing scheme. Through correlation consistency verification, it ensures continuous correspondence of parameters at each stage, improving the completeness and technical consistency of the power supply scheme for business expansion applications. Attached Figure Description
[0052] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in this application. For those skilled in the art, other drawings can be obtained based on these drawings.
[0053] Figure 1 A flowchart outlining the overall process for generating power supply solutions for business expansion applications that take into account the integration of new energy sources.
[0054] Figure 2 This is a schematic diagram illustrating the process of generating power supply schemes for business expansion applications based on power supply scheme generation equipment.
[0055] Figure 3 A program processing logic diagram for generating a power supply scheme for business expansion applications that takes into account the access of new energy sources, for the execution of computer programs. Detailed Implementation
[0056] Exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, these exemplary embodiments can be implemented in many forms and should not be construed as limited to the examples set forth herein; rather, they are provided so that the description of this disclosure will be more complete and fully convey the concept of the exemplary embodiments to those skilled in the art.
[0057] like Figure 1 As shown, this application provides a method for generating a power supply scheme for business expansion applications that considers the access of new energy sources, including the following steps:
[0058] Obtain electricity application information, load information, and new energy and energy storage configuration information of target customers, construct an overview of customer electricity application, and obtain multi-source spatiotemporal data of the target power supply area to predict the background charging demand in areas that do not include the target customer's new installed load.
[0059] The actual total growth component and spatial migration component of the background charging demand in the separated area are separated, and the background source load of each area is mapped to the distribution node to obtain the background active and reactive source load status of the distribution node.
[0060] AC power flow calculations are performed based on the background active and reactive load states of distribution nodes. The influence of electrical constraint margins on different distribution nodes is obtained through node power disturbances. The electrical constraint difference components of the corresponding electrical locations before and after spatial migration are calculated, and the power supply side access conditions of candidate distribution nodes are obtained.
[0061] Candidate access system schemes are generated by using customer electricity application overview, electrical constraint differential components and power supply side access conditions. The target customer load and new energy and energy storage configurations are superimposed on the candidate networks corresponding to each candidate access system scheme to verify AC power flow and power supply reliability, and screen safe access system schemes.
[0062] For each secure access system solution, a matching power receiving system solution and metering and billing solution are configured. The consistency of the customer's electricity application overview, secure access system solution, power receiving system solution and metering and billing solution is verified, and the target business expansion application power supply solution is output.
[0063] In practice, the following steps are taken to obtain the target customer's electricity application information, load information, and new energy and energy storage configuration information: Electricity application information should include at least the customer's identifier, electricity address, industry category, applied electricity capacity, approved electricity capacity, electricity category, load nature, load level, customer importance level, and security load requirements; Load information should include at least the active load, reactive load, and power factor at different operating time segments within the planning phase; New energy and energy storage configuration information should include at least the rated active power of the new energy source, the rated apparent capacity of the inverter, the rated charge and discharge power of the energy storage, the rated energy of the energy storage, the energy storage charging efficiency, the energy storage discharging efficiency, and the initial energy storage capacity.
[0064] Set target customers in the planning stage Running time section The calculated active load is The overall power factor is Calculate the apparent load And calculate reactive load They are represented as follows:
[0065]
[0066]
[0067] During the planning phase, the target customer's maximum computed active load and maximum computed apparent load are respectively:
[0068]
[0069]
[0070] The approved electricity capacity of the target customer is denoted as And satisfy:
[0071]
[0072] Obtain operating status when there are security load requirements. The active power load that needs to be continuously guaranteed and corresponding comprehensive power factor The apparent load is represented as:
[0073]
[0074] By establishing a customer electricity application overview using the above parameters, subsequent access system schemes, power receiving system schemes, and metering and billing schemes can adopt a unified source of customer capacity, load level, and guaranteed load data.
[0075] At the same time, the target power supply area is divided into multiple spatial regions. The spatial region can be an administrative grid, a traffic analysis area, a charging service area, or a geographical unit with unified charging behavior characteristics. The system acquires historical data on new energy vehicle charging power, vehicle origin and destination points, road traffic flow, vehicle arrival time, vehicle departure time, parking duration, regional functional attributes, weekday and holiday attributes, temperature, rainfall, sunlight, wind speed, background base load, background distributed photovoltaic output, background distributed wind power output, and existing energy storage charging and discharging data for each spatial region. Simultaneously, it acquires data on distribution nodes, node nominal voltage, line impedance, line allowable current, rated capacity of transformers on the power supply side, and electrical connections between distribution nodes within the target power supply area.
[0076] Using a uniform time interval across different data sources Spatiotemporal alignment with a unified spatial region numbering is performed. For power data with a sampling frequency higher than the unified time scale, spatiotemporal alignment is performed at the time cross-section. Internally calculated average power:
[0077]
[0078] in, Time section The number of raw power sampling points is specified. For vehicle flow and arrival count, cumulative values over time are used; for continuous data such as temperature, illumination, and wind speed, average values over time are used; and for weekdays, holidays, and regional functional attributes, category codes are used. Vehicle origin-destination data are mapped to corresponding spatial regions and operating time segments according to vehicle departure area, arrival area, and arrival time.
[0079] The regional background charging demand does not include new installation loads from target customers or changes in source load resulting from the target customers' planned configuration of new energy sources and energy storage. The original forecast data already includes the target customers' future new installation loads, which are deducted from the corresponding operating time segment of the spatial region where the target customers are located.
[0080] For example, if the original predicted charging power for region A from 18:00 to 19:00 is 12MW, and the predicted charging power for the target customer's proposed new charging facilities during the same time period is 2MW, then the background charging power for the region entering the background source load processing is:
[0081]
[0082] The target customer's corresponding 2MW is only retained in the customer's electricity application overview and loaded into the corresponding candidate distribution node after the candidate access system scheme is established, thereby avoiding the target customer's new load being counted repeatedly.
[0083] Regional background charging demand forecasting includes forecasting the overall background charging demand of the target power supply area and forecasting the spatial distribution of the region. A baseline timeframe is established. The overall background charging power of the target power supply area is:
[0084]
[0085] An overall background charging demand forecasting function is established using the number of new energy vehicles, historical charging power, traffic flow, parking duration, regional functions, weekday and holiday attributes, and meteorological variables.
[0086]
[0087] in, This represents the scale variable of new energy vehicles. Represents traffic flow variables. Represents the parking duration variable. Represents meteorological variables, Represents date and region-related variables. Prediction function. Multiple regression, gradient boosting decision trees, recurrent neural networks, long short-term memory networks, or other methods that can output future charging power from historical multi-source spatiotemporal data can be used for prediction. The specific type of prediction function does not change the subsequent separation process between the actual total growth and spatial migration.
[0088] The target power supply area is in the planning stage Running time section The actual total growth is expressed as:
[0089]
[0090] The regional growth allocation coefficient is calculated based on changes in the scale of new energy vehicles, the utilization rate of charging facilities, the intensity of population activity, and changes in regional functions in each spatial region. And satisfy:
[0091]
[0092]
[0093] The components of the region's real total growth are represented as follows:
[0094]
[0095] In one alternative approach, the regional growth allocation coefficient is calculated based on the proportion of the projected increase in new energy vehicle charging volume in the region:
[0096]
[0097] in, Representing a spatial region The projected increase in charging capacity corresponds to a specific time segment. By first calculating the overall actual total growth of the target power supply area and then allocating it to each spatial region, it is possible to separate "changes in the total charging demand of the target power supply area" from "existing charging demand that only changes in its location" at the definition level.
[0098] Background charging demand migration caused by vehicle spatial movement is calculated independently. For spatial regions... Departure and in the space region Vehicles that have engaged in charging activities are included in the statistical planning phase. Time cross section Equivalent number of charging vehicles The probability of inter-regional charging demand migration is expressed as:
[0099]
[0100] satisfy:
[0101]
[0102] If spatial region The background charging power that can undergo spatial redistribution at the corresponding time segment is Then, from the spatial region Migration to space region The background equivalent charging demand transfer power is:
[0103]
[0104] And satisfy:
[0105]
[0106] In another implementation, the migration power is calculated directly based on the number of vehicles being migrated and the average charging capacity.
[0107]
[0108] in, For spatial regions Transfer to space region The average charging amount of the vehicle within the corresponding time segment.
[0109] For example, if the time span is 1 hour, and the charging demand of 100 vehicles is transferred from spatial region A to spatial region B, with each vehicle averaging 20 kWh of charging capacity during this time span, then the background equivalent charging demand migration power is:
[0110]
[0111] When vehicle-level origin-destination data is unavailable, a regional migration probability matrix can be constructed using road traffic flow matrices, parking vehicle inflow-outflow matrices, and historical regional charging power changes. Let the spatial region... Flowing into spatial regions The number of vehicles is ,area The probability of charging after parking is ,but:
[0112]
[0113] This method can continue to obtain background equivalent charging demand transfer power even when single-vehicle trajectory data is lacking.
[0114] After separating real total growth from spatial migration, spatial regions During the planning stage Time cross section The regional background charging demand is expressed as:
[0115]
[0116] And satisfy:
[0117]
[0118] All spatial migrations satisfy the law of conservation of migration power:
[0119]
[0120] therefore:
[0121]
[0122] The above relationship means that spatial migration only changes the spatial location of background charging demand, and does not change the total charging demand of the target power supply area determined by the actual total growth component.
[0123] Next, the regional background charging demand and other background source loads will be mapped to the distribution nodes. Define the spatial region. to distribution nodes The allocation coefficient is ,satisfy:
[0124]
[0125]
[0126] in, For spatial regions The corresponding set of power distribution nodes.
[0127] When historical charging power node statistics exist, the following method is used:
[0128]
[0129] in, For spatial regions Internal distribution nodes The historical average charging power handled. When complete historical power data is unavailable, the rated power of the charging facility corresponding to the node can be used for calculation.
[0130]
[0131] When a spatial region corresponds to only one distribution node, the allocation coefficient of that distribution node is 1, and the allocation coefficient of the other distribution nodes is 0.
[0132] Distribution nodes The active power of new energy vehicle charging is expressed as follows:
[0133]
[0134] If spatial region Background: The comprehensive power factor of new energy vehicle charging load is The corresponding charging reactive power is expressed as:
[0135]
[0136] Positive values represent power absorbed from the distribution network, and negative values represent power injected into the distribution network, all in a unified direction. Let the distribution nodes be... The background base load, background active power output of new energy sources, and existing energy storage charging and discharging power are respectively , , and The background active load state of the distribution node is then represented as:
[0137]
[0138] The corresponding background reactive power source state is represented as follows:
[0139]
[0140] For example, if the background charging active power in space region A is 4MW, and the allocation coefficients for distribution nodes N1 and N2 are 0.6 and 0.4 respectively, then the charging active power undertaken by the two distribution nodes is 2.4MW and 1.6MW respectively. When the overall power factor is 0.95:
[0141]
[0142] Therefore, the corresponding reactive power for charging is approximately:
[0143]
[0144] as well as:
[0145]
[0146] This transforms the regional background charging demand into the background active and reactive load states of distribution nodes with clearly defined electrical locations.
[0147] Subsequently, AC power flow calculations are performed based on the background active and reactive load states of the distribution nodes. For the distribution nodes... The active and reactive power flow equations are expressed as follows:
[0148]
[0149]
[0150] in, and They are nodes ,node voltage amplitude, and The phase angle, and These represent the real and imaginary parts of the corresponding elements in the node admittance matrix. The background active and reactive load states of the distribution node are converted into the net injected power of the node corresponding to the power flow equation according to the aforementioned power direction.
[0151] AC power flow can be solved using the Newton-Raphson method, the forward-backward substitution method, or other numerical methods applicable to distribution networks.
[0152] After solving for the AC power flow, the safety margins for line thermal stability, transformer capacity on the power supply side, upper limit of node voltage, and lower limit of node voltage are calculated respectively. (Line) The thermal stability safety margin is:
[0153]
[0154] in, For the line operating current, This is the allowable current for the line.
[0155] Power supply side transformer The capacity safety margin is:
[0156]
[0157] in, The apparent power of the transformer operating on the power supply side. This is the rated capacity.
[0158] Distribution nodes The upper and lower voltage safety margins are as follows:
[0159]
[0160]
[0161] in, , and These are the upper limit of permissible voltage, the lower limit of permissible voltage, and the nominal voltage. These different types of constraints are collectively numbered as electrical operating constraints. The corresponding safety margin is uniformly denoted as .
[0162] To obtain the impact of the increased unit charging power at different distribution nodes on various electrical operating constraints, combined active and reactive power perturbations are applied to the candidate analysis nodes. Let the reference power be... The disturbance ratio is The disturbance active power is expressed as:
[0163]
[0164] in, It can be selected within the range of 0.1% to 5%.
[0165] In one embodiment, , ,but:
[0166]
[0167] The background charging load power factor is At that time, the corresponding reactive power disturbance is:
[0168]
[0169] Record the first time before the disturbance Safety margin of electrical operating constraints At the distribution node Increase and After re-executing the communication flow, a safety margin is obtained after the disturbance. Distribution nodes For the first The unit charging power margin consumption factor for the electrical operating constraints is:
[0170]
[0171] To control the difference error caused by the perturbation scale, further methods can be adopted. Repeat the calculation, and satisfy:
[0172]
[0173] in, This is the preset differential tolerance. If this condition is not met, the disturbance amount will continue to decrease until the preset differential tolerance is met or the preset minimum disturbance amount is reached.
[0174] Using the spatial region-distribution node allocation factor, the unit charging power margin consumption factor of the node is converted into the equivalent unit margin consumption factor of the spatial region:
[0175]
[0176] For spatial regions Migration to space region Background equivalent charging demand transfer power The electrical constraint difference components generated by the corresponding electrical positions before and after spatial migration are expressed as:
[0177]
[0178] when When, it indicates that the spatial migration consumes an additional amount of time compared to the state before the migration. Safety margin of electrical operating constraints; when When the time is specified, it indicates the safety margin corresponding to the release of spatial migration. Therefore, under the reverse power operation state of new energy sources, the migration of charging demand can reflect the mitigating effect on the reverse power or voltage upper limit constraint through the negative electrical constraint differential component.
[0179] For example, the equivalent unit margin consumption coefficient of line L1 corresponding to spatial region A is: The equivalent unit margin consumption coefficient for line L1 corresponding to spatial region B is: If 2MW of background charging demand is transferred from A to B, then:
[0180]
[0181] If the equivalent unit margin consumption coefficient of line L1 corresponding to region B is ,but:
[0182]
[0183] At this point, spatial migration releases a safety margin of 0.06 for line L1.
[0184] When the background equivalent charging demand migration power exceeds the preset single disturbance applicable range, the migration power is divided into multiple increments:
[0185]
[0186] After each migration increment is completed, the active and reactive loads corresponding to that increment are redistributed to the corresponding distribution nodes in the outgoing and incoming areas, and then AC power flow is executed and updated. and The cumulative electrical constraint differential is:
[0187]
[0188] By using segmented updates, it is possible to handle the changes in the unit margin effect caused by the nonlinearity of AC power flow after the migration power increases.
[0189] Further considering the uncertainty in predicting the migration of background charging demand, let the predicted migration power be... Migration bias is obtained based on historical prediction error quantiles or preset error proportions. The migration power value range is:
[0190]
[0191]
[0192] For example, the 95th percentile of the absolute percentage error in historical migration power prediction is 15%, which can be set as follows:
[0193]
[0194] The entire migration power range, the upper limit condition for migration power, and the migration conservation condition together constitute the set of background charging demand migration states. . No. The most unfavorable migration difference index corresponding to the electrical operating constraints is expressed as:
[0195]
[0196] The differential contributions for each migration direction are sorted by absolute contribution value, and the cumulative contribution ratio is calculated:
[0197]
[0198] When the cumulative contribution ratio reaches the preset threshold At that time, the front Each migration direction serves as the primary migration direction for the corresponding electrical operating constraints. Preset thresholds can be set according to the required analysis accuracy, such as 80%, 90%, or 95%.
[0199] After completing the differential identification of electrical constraints, the power supply access conditions for candidate distribution nodes are generated. Starting from the target customer's electricity consumption location, the available power supply path distance from each available distribution node to the target customer's location is calculated. Set the allowed search distance At the same time, obtain the set of allowable power supply voltage levels for the target customers. Background available power supply capacity corresponding to each power distribution node The set of candidate distribution nodes is represented as:
[0200]
[0201] The available power supply capacity is jointly limited by the allowable current of the associated lines of the candidate distribution node, the remaining capacity of the upstream power supply transformer, and the available power supply capacity under specified operating conditions. For three-phase power supply paths, the line capacity boundary can be calculated based on the allowable line current.
[0202]
[0203] in:
[0204]
[0205] The remaining capacity of the power supply side transformer is expressed as follows:
[0206]
[0207] The available power supply capacity for candidate distribution nodes is the capacity value with the smallest limiting capacity among the associated power supply paths.
[0208] Subsequently, candidate access system schemes were generated using the customer's electricity application overview, electrical constraint differential components, and power supply side access conditions. For candidate distribution nodes... Define the first considering spatial migration Estimated residual safety margin:
[0209]
[0210] in, This represents the basic safety margin in the background network corresponding to the candidate distribution nodes. This is the most unfavorable migration differential index associated with the power supply path of this candidate distribution node. It satisfies:
[0211]
[0212] Candidate distribution nodes are included in the scope of access scheme generation.
[0213] For multiple candidate distribution nodes that meet the criteria, migration impact indicators can also be calculated:
[0214]
[0215] in, Preset weights for different electrical operating constraints satisfy:
[0216]
[0217] A positive number is set to prevent the denominator from being zero. This index is used to describe the overall occupancy of electrical operation constraints associated with candidate distribution nodes due to spatial migration, but the final safe access system scheme is still obtained through the verification of AC power flow and power supply reliability of the candidate network.
[0218] Candidate access system schemes should at least include the power supply, candidate distribution nodes, power supply voltage level, power supply capacity, number of power supply circuits, power supply path, and property boundary location. The power supply path can be represented by the permitted power supply channels as shown in the diagram:
[0219]
[0220] in, For a set of connectable locations, This is the set of power supply paths between adjacent connectable locations. For path edges... Define the cost:
[0221]
[0222] in, For path length, For the implementation cost parameters of the corresponding path, For channel occupancy parameters, , and Preset weights are used. Candidate power supply paths from candidate distribution nodes to the target customer's power consumption location are obtained using Dijkstra's algorithm, A* algorithm, or other graph search methods.
[0223] Regarding the first There are 1 candidate access system schemes, and the set of power supplies is denoted as _____. Under normal operating conditions, the apparent power supply capacity that each power source can provide to the target customer meets the following requirements:
[0224]
[0225] For the set of operational states corresponding to customer importance levels:
[0226]
[0227] in, This indicates the normal operating status. Other operating statuses may include a power supply circuit being disconnected, an incoming line being disconnected, or a power supply disconnection status that needs to be considered according to the customer's load level requirements. Operating Status The following is a list of power sources that can still be put into operation: And satisfy:
[0228]
[0229] This allows the guaranteed load requirements in the customer's electricity application overview to be transmitted to the candidate access system solutions.
[0230] After the candidate access system scheme is generated, the communication flow results of the background network are not directly used as the operating results after the target customer accesses the system. Instead, a candidate network is established for each candidate access system scheme.
[0231] The background active and reactive power load status of the distribution node continues to serve as the background input for the candidate network, while the target customer load, new energy and energy storage configuration are only loaded onto the candidate distribution node specified by the corresponding candidate access system scheme.
[0232] set up Indicates distribution node For the first The target customer access node for each candidate access system scheme is set to 0, otherwise the value is 0. The active power status of the node after the target customer accesses is represented as follows:
[0233]
[0234] The corresponding reactive power state is represented as follows:
[0235]
[0236] Among them, the active and reactive power output of new energy sources and the charging and discharging power of energy storage for target customers are defined with the same power direction as the background source load.
[0237] The target customer's energy storage status is based on:
[0238]
[0239] Update and satisfy:
[0240]
[0241]
[0242]
[0243] When the target customer's new energy and energy storage have reactive power regulation capabilities, the corresponding reactive power is simultaneously added to the candidate network AC power flow.
[0244] For each candidate network, AC power flow and node power disturbance calculations are re-executed, and the unit charging power margin consumption factor and spatial migration electrical constraint differential component are updated for different distribution nodes after the target customer's access. For the planning phase... Running time section Background charging demand migration status Other background load states and running status , No. The candidate access system scheme corresponds to the first The safety margin of the electrical operating constraints is expressed as follows:
[0245]
[0246] The corresponding robust safety margin is expressed as:
[0247]
[0248] And satisfy:
[0249]
[0250] Other background load states This can be constructed using a forecast range based on background load, renewable energy output, and existing energy storage operating power. For example, the forecast active power of renewable energy is... The prediction bias is ,but:
[0251]
[0252] The background base load is established with upper and lower limits in the same way to obtain the set of other background source load states.
[0253] The candidate network also calculates the maximum expected short-circuit current. For the fault location... The equivalent impedances of the power supply, lines, and transformers are attributed to the fault location to obtain the equivalent impedance of the fault point. One method for calculating a three-phase short circuit is as follows:
[0254]
[0255] in, The nominal line voltage at the fault location is used. When there is a contribution from the fault current of renewable energy sources, the fault current of the renewable energy sources is included in the fault point current according to their grid connection location and fault current limit. The maximum value among all fault locations and operating states to be considered is taken as the maximum expected short-circuit current corresponding to the candidate grid connection scheme.
[0256]
[0257] Candidate access system schemes that meet the requirements of AC power flow, electrical operation constraint safety margin, and power supply reliability are included in the safe access system scheme set, and the power supply voltage level is retained. Power supply capacity Number of power supply circuits Maximum continuous operating current Maximum expected short-circuit current Active power at the power supply boundary, reactive power at the power supply boundary, and location of the property boundary. The above parameters continue to serve as inputs for the power receiving system scheme and the metering and billing scheme, thereby maintaining the continuous transmission of technical parameters from one end to the other.
[0258] For each secure access system solution, a matching power receiving system solution is configured based on the power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current, maximum expected short-circuit current, and customer power application details.
[0259] First, establish a set of candidate main power receiving connections that are compatible with the number of power supply circuits. The candidate main power receiving connections may include single busbar operation mode, single busbar segmented operation mode, dual power supply line operation mode, and other power receiving connection methods that meet the customer's power supply circuit conditions.
[0260] For candidate power receiving main wiring In running state The set of power receiving circuits that can be put into operation is denoted as The apparent capacity that each power receiving circuit can provide is And satisfy:
[0261]
[0262] This means that the number of power supply circuits and the customer's guaranteed load in the secure access system solution are both included in the configuration of the main power receiving wiring.
[0263] The rated capacity of the customer-side power receiving transformer is selected from the preset set of available capacities:
[0264]
[0265] Select from the options. For those containing... Candidate configurations for the receiving transformer, number The rated capacity of the receiving transformer is The allowable load factor is Normal operating conditions are met:
[0266]
[0267] Running status The collection of power receiving transformers that can still be put into operation is as follows The corresponding condition is satisfied:
[0268]
[0269] The number and capacity combinations of receiving transformers in the preset capacity set are enumerated, and the configuration that simultaneously meets the normal operation capacity requirements and the load protection requirements of each operating state is retained, thereby obtaining the power receiving capacity configuration that matches the safe access system scheme.
[0270] For a three-phase AC power receiving circuit, if the power receiving circuit The maximum apparent power it can handle is The nominal line voltage is The maximum operating current is expressed as:
[0271]
[0272] The rated current of the power receiving circuit meets the following requirements:
[0273]
[0274] in, This is the preset current margin coefficient. The corresponding short-circuit breaking capacity satisfies:
[0275]
[0276] This allows the maximum operating current and maximum expected short-circuit current output by the safe access system scheme to directly constrain the electrical parameters on the power receiving side.
[0277] For the receiving line, let the active power of the three-phase line be... reactive power is The equivalent resistance and reactance of the line are respectively and The nominal voltage is The percentage of line voltage drop can be expressed as:
[0278]
[0279] And satisfy:
[0280]
[0281] This allows the power supply voltage level, the power receiving load, and the line electrical parameters to jointly participate in the operating voltage control on the power receiving side.
[0282] The power protection parameters are configured based on the maximum operating current and short-circuit current. The minimum fault current is specified for the location of the fault within the protection range. and protection operating current setting value The protection sensitivity is expressed as:
[0283]
[0284] And it meets the preset minimum sensitivity requirement. When there is a hierarchical protection relationship, the action time meets the following:
[0285]
[0286] in, and These are the protection action times for the superior and subordinate levels, respectively. The preset time interval is used for coordination.
[0287] When a customer has a reactive power compensation requirement, a time section is set. The customer's active load is The power factor before compensation is The target power factor is The reactive power before compensation and the target reactive power are respectively:
[0288]
[0289]
[0290] For new energy inverters, the rated apparent capacity is The active power output at the time section is At that time, the upper limit of reactive power regulation that can be provided within the corresponding operating capacity range is:
[0291]
[0292] The rated apparent capacity of the energy storage converter is The active power at the time section is hour:
[0293]
[0294] After considering the reactive power regulation capabilities of new energy sources and energy storage, the independent reactive power compensation demand is expressed as:
[0295]
[0296] Independent reactive power compensation capacity should at least cover the planned operating time range. The maximum value.
[0297] When the target customer has a security load, set a time segment. The security load is The energy storage's security load capacity is The power that other available emergency power supply capabilities can handle is ,satisfy:
[0298]
[0299] Energy storage to undertake the prescribed emergency response time When the internal safety load is reached, the required reserve energy storage capacity is:
[0300]
[0301] Assume the available energy at the start of an emergency energy storage event is: The minimum retention energy is ,but:
[0302]
[0303] When the same energy storage system simultaneously undertakes peak shaving for normal operation, renewable energy consumption, and security load protection, it should further meet the following requirements within the time frame where emergency backup capabilities need to be maintained:
[0304]
[0305] This avoids the same portion of energy storage that has already been used for normal operation being included in the security load guarantee capacity again.
[0306] After the power receiving system scheme is generated, a metering and billing scheme is generated based on the power supply boundary, property boundary location, number of power supply circuits, power supply voltage level, and electricity usage category in the customer's electricity application overview, as specified in the secure access system scheme. Let the set of power supply circuits requiring independent billing be... The candidate measurement point set is Define the measurement mapping variables:
[0307]
[0308] in, Indicates power supply circuit From measurement point Responsible for settlement and metering. Each power supply circuit requiring independent settlement must meet the following requirements:
[0309]
[0310] This establishes a one-to-one correspondence between power supply circuits and billing metering points.
[0311] For measurement points Define the planning phase Time cross section Operating status The lower boundary active power is .Regulation:
[0312]
[0313] This indicates that the distribution network delivers active power to the target customer.
[0314]
[0315] This indicates that the target customer's new energy or energy storage is transmitting active power in the reverse direction to the distribution network.
[0316] One metering cycle The forward active energy and the reverse active energy are expressed as follows:
[0317]
[0318]
[0319] when:
[0320]
[0321] At the same time, the metering and billing scheme records both positive and negative active power, so that the reverse power status of new energy sources in the safe access system scheme continues to be transmitted to the metering and billing scheme.
[0322] For metering methods using current transformers and voltage transformers, the metering points The maximum continuous operating current is expressed as:
[0323]
[0324] The primary rated current of the current transformer meets the following requirements:
[0325]
[0326] The current transformer ratio is expressed as:
[0327]
[0328] The voltage transformer ratio is expressed as:
[0329]
[0330] Secondary side power metering value Converted to the first side, it is:
[0331]
[0332] When using direct measurement, the strain ratio is taken as 1.
[0333] When the property boundary location differs from the settlement metering point location, calculate the line losses and transformer losses that need to be attributed between the two. For three-phase lines, the time section... The line current is The equivalent resistance of each phase is The active power loss of the line is:
[0334]
[0335] The line power loss during the metering period is:
[0336]
[0337] For transformers that need to be included in the settlement boundary, the no-load active power loss is... Rated load loss is The actual apparent load at the time section is Rated capacity is The corresponding active power loss is expressed as:
[0338]
[0339] The transformer power loss during the metering period is:
[0340]
[0341] When there are two power directions, forward power supply and reverse power transmission, the forward settlement amount, reverse settlement amount and corresponding loss attribution direction are stored separately to avoid using a single power direction to handle bidirectional power exchange.
[0342] Electricity consumption information is collected using data identifiers that are uniquely associated with each metering point. The collection period is set to [number missing]. The continuous collection time is The theoretical number of data collection records is:
[0343]
[0344] Each metering point must record at least the metering point identifier, collection address, collection period, forward active energy, reverse active energy, and corresponding time identifier; if there is no reverse power operation state, reverse settlement of electricity can be disabled.
[0345] Billing processing uses the settled electricity volume for different billing time intervals within the metering cycle. Let the first... The positive electricity volume for each billing time period is The corresponding positive unit electricity price is Reverse charge is The corresponding reverse settlement unit price is The forward electricity fee and the reverse settlement amount are respectively:
[0346]
[0347]
[0348] The specific pricing range and unit price are read from the billing parameters applicable to the corresponding customer's electricity consumption category, therefore there is no limitation on the price value for a specific region or period.
[0349] After completing the power receiving system scheme and the metering and billing scheme, a consistency check is performed on the customer's electricity application overview, the secure access system scheme, the power receiving system scheme, and the metering and billing scheme. This process does not regenerate the four parts independently, but rather uses the aforementioned continuously transmitted parameters to determine whether the four parts meet the corresponding technical relationships item by item.
[0350] The customer capacity and power supply capacity must meet the following requirements:
[0351]
[0352] as well as:
[0353]
[0354] The customer's guaranteed load and operating power supply capacity must meet the following requirements:
[0355]
[0356] Power supply voltage level of secure access system solution Voltage level of the power receiving system scheme satisfy:
[0357]
[0358] Number of power supply circuits in a secure access system solution Number of independent power receiving lines in the power receiving system scheme When no aggregation relation exists, the following condition is met:
[0359]
[0360] When multiple power supply convergence relationships exist, establish a mapping variable from the power supply loop to the incoming power line. It also requires that each power supply circuit be mapped to at least one corresponding power receiving line to avoid missing power supply circuits in the power receiving system scheme.
[0361] The maximum continuous operating current output by the secure access system solution meets the following requirements: the rated current of the power receiving circuit and the primary rated current of the current transformer.
[0362]
[0363]
[0364] The maximum expected short-circuit current and the corresponding short-circuit breaking capacity of the receiving circuit must satisfy the following:
[0365]
[0366] When the property boundary location and the metering point location are the same, the metered electricity volume is directly used as the settlement boundary electricity volume; when the two locations are different, the metering and billing scheme must have a corresponding line loss or transformer loss handling relationship.
[0367] The bidirectional power of new energy sources and the metering direction satisfy the following condition: This condition exists at any planning stage, time segment, or operational state:
[0368]
[0369] At the same time, the corresponding metering point is configured with both forward and reverse active energy recording relationships.
[0370] Reactive power compensation and the power factor at the power supply boundary are correlated through the boundary active and reactive power. Let the boundary active and reactive power be respectively... and The magnitude of the boundary power factor is expressed as:
[0371]
[0372] After the independent reactive power compensation, reactive power regulation of new energy inverters and reactive power regulation of energy storage in the power receiving system scheme are added to the boundary power calculation, the boundary power factor meets the preset target value.
[0373] Both power constraints and energy constraints must be satisfied between security loads and emergency power supplies:
[0374]
[0375] as well as:
[0376]
[0377] This ensures that the target customer's security load requirements, normal energy storage operation status, and emergency response capabilities are all maintained at the same energy status metric.
[0378] When the association consistency check finds that a certain relationship is not satisfied, the corresponding solution generation process is returned based on the data source of the relationship that is not satisfied.
[0379] For example, if the power supply capacity cannot cover the customer's maximum apparent load, the candidate access system scheme generation process is returned to reselect the power supply, candidate distribution node, or power supply circuit; if the power receiving circuit capacity cannot cover the output capacity of the safe access system scheme, the main power receiving wiring and power receiving capacity are reconfigured; if the maximum expected short-circuit current exceeds the corresponding breaking capacity of the power receiving side, the corresponding power receiving parameters are reconfigured; if the property boundary and metering point location are inconsistent and there is a lack of loss handling relationship, the metering and billing scheme is reconfigured; if the remaining energy of energy storage cannot cover the emergency energy demand of the security load, the normal operating energy storage energy and emergency reserved energy are reallocated.
[0380] After making the necessary adjustments, the corresponding consistency check is re-executed until all four parts satisfy the full set of relationships.
[0381] To further illustrate the above data transmission process, a complete numerical example is provided. Let the target customer's approved electricity capacity be:
[0382]
[0383] The maximum calculated active load is:
[0384]
[0385] The overall power factor is:
[0386]
[0387] but:
[0388]
[0389] satisfy:
[0390]
[0391] Assuming the target power supply area includes spatial region A and spatial region B, and the background equivalent charging demand for migration from A to B at a certain time segment is 2MW, the equivalent unit margin consumption coefficients of A and B for line L1 are respectively:
[0392]
[0393]
[0394] Then the electrical constraint differential components of line L1 corresponding to the spatial migration are:
[0395]
[0396] If the background safety margin of the associated line L1 of candidate distribution node N1 is 0.30 and the minimum allowable safety margin is 0.10, then the estimated safety margin after considering this migration difference is:
[0397]
[0398] satisfy:
[0399]
[0400] Therefore, candidate distribution node N1 can enter the candidate access system scheme generation process.
[0401] Assuming that another candidate distribution node N2 also meets the minimum safety margin requirements under the same background migration conditions, candidate networks corresponding to N1 and N2 are established respectively. The target customer's 6MW active load and corresponding reactive load are loaded into the candidate networks corresponding to N1 and N2 respectively, without changing the regional background charging demand that has already been reduced by the target customer's load.
[0402] For the two candidate networks, AC power flow, spatial migration electrical constraint differential calculations, and power supply reliability calculations were re-executed, and the scheme that satisfies all electrical operation constraints and operational status guarantee load requirements was retained as the safe access system scheme.
[0403] Assuming the final secure access system uses 10kV power supply, with a normal operating power supply capacity of 8MVA, and the target customer uses two 4MVA receiving transformers, then the total rated power receiving capacity under normal operating conditions is:
[0404]
[0405] Capable of covering:
[0406]
[0407] If a single 4MVA receiving transformer corresponds to the rated current of the three-phase 10kV side, then:
[0408]
[0409] The rated current and metering current parameters of the corresponding power receiving circuit shall be configured in accordance with the principle that they shall not be less than the corresponding maximum operating current.
[0410] If the target customer's renewable energy source generates reverse power at a certain time section, making the active power at the metering point boundary:
[0411]
[0412] The metering and billing scheme records both forward and reverse active energy, and processes the line or transformer losses between the property boundary and the metering point according to the actual power direction.
[0413] The final output is the target business expansion power supply plan. The target business expansion power supply plan should include at least the customer's electricity application overview, the target access system plan, the power receiving system plan that matches the target access system plan, and the metering and billing plan.
[0414] Among them, the customer's electricity application overview transmits the maximum calculated load, approved power capacity, guaranteed load, and new energy and energy storage configuration; the regional background charging demand is separated from the actual total growth and spatial migration, and the spatial area is mapped to the distribution node to generate the background active and reactive power source load status of the distribution node; the spatial migration is converted into electrical constraint differential components through node power disturbance, and participates in the generation of candidate distribution nodes and candidate access system schemes; the target customer load, new energy and energy storage configuration are loaded into the corresponding candidate network after the candidate access system scheme is established, and the safe access system scheme is screened through AC power flow and power supply reliability verification; the power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current, maximum expected short circuit current and property boundary location output by the safe access system scheme are further used for the generation of power receiving system scheme and metering and billing scheme.
[0415] Finally, by verifying the consistency of customer capacity, power supply capacity, power receiving capacity, operating current, short-circuit current, property boundary, bidirectional power of new energy sources, reactive power compensation, and emergency power supply, a complete target business expansion power supply solution is output, in which the technical parameters of each part correspond to each other.
[0416] This embodiment provides a power supply scheme generation device for business expansion applications that considers renewable energy access. It generates a power supply scheme matching the target customer's application requirements and the source-load operation status of the target power supply area. The device includes a customer information processing unit, a background demand prediction unit, a source-load mapping unit, a power flow calculation unit, an electrical impact processing unit, a candidate scheme generation unit, a safety scheme screening unit, and a scheme output unit. Data is transferred between these processing units according to the power supply scheme generation process.
[0417] The customer information processing unit acquires electricity application information, load information, and renewable energy and energy storage configuration information submitted by the target customer. The electricity application information includes the electricity address, applied capacity, electricity category, load level, and security load information; the load information includes the target customer's maximum active load, power factor, and corresponding operating period; and the renewable energy and energy storage configuration information includes the renewable energy installed capacity, rated energy storage power, rated energy storage capacity, and reactive power regulation capability of the converter equipment.
[0418] The customer information processing unit correlates the above information to form a summary of the customer's electricity application and then transmits it to the candidate solution generation unit and the security solution screening unit.
[0419] The background demand forecasting unit acquires multi-source spatiotemporal data of the target power supply area. This data includes historical charging load data, vehicle origin and destination data, traffic flow data, vehicle arrival and departure times, parking duration, regional functional attributes, meteorological data, and existing renewable energy and energy storage operation data within the target power supply area. The background demand forecasting unit correlates the multi-source spatiotemporal data according to a unified time scale and forecasts the regional background charging demand of the target power supply area during the corresponding time period.
[0420] When forecasting background charging demand, the new installation load of target customers is excluded from the forecast objects; when the original forecast data already includes the charging demand corresponding to the target customers, the corresponding part of the target customers is deducted from the original forecast results to avoid the new installation load of target customers being repeatedly superimposed in the subsequent candidate network reconstruction process.
[0421] The source-load mapping unit receives the regional background charging demand and separates the actual total growth component and the spatial migration component from the regional background charging demand. The actual total growth component is used to characterize the change in the overall total charging demand of the target power supply area, while the spatial migration component is used to characterize the portion where the total charging demand does not increase accordingly but the charging behavior changes location between different areas.
[0422] For the spatial migration component, the inter-regional migration power is determined based on the migration probability of charging demand between regions and the available charging demand, while maintaining the conservation relationship between the migration power entering and leaving all regions.
[0423] After completing the demand separation at the regional scale, the source-load mapping unit converts the background source load of each region to the corresponding distribution node based on the allocation coefficient between the spatial region and the distribution node. The allocation coefficient can be determined based on the proportion of historical charging power in different distribution nodes, or based on the proportion of the rated capacity of the charging facilities corresponding to different distribution nodes. Combining the base load, background charging load, renewable energy output, and existing energy storage charging and discharging power, the background active source load state and background reactive source load state of each distribution node are formed and sent to the power flow calculation unit.
[0424] The power flow calculation unit performs AC power flow calculations on the background active and reactive power source load states of the distribution nodes based on the node connection relationships, line impedance, line allowable current carrying capacity, rated capacity of the power supply side transformer, and allowable voltage range of the nodes. It obtains the node voltage, line current, and power supply side transformer load state under background operating conditions, and forms the line thermal stability safety margin, the power supply side transformer capacity safety margin, and the node voltage safety margin accordingly.
[0425] Based on the AC power flow calculation results, the electrical impact processing unit applies power disturbances to different distribution nodes. These disturbances include active power disturbances and reactive power disturbances determined according to the charging power factor. After each disturbance, the AC power flow calculation is re-executed. Based on the relationship between the change in the corresponding electrical constraint safety margin before and after the disturbance and the active power of the disturbance, the unit charging power margin consumption factor for different distribution nodes is obtained.
[0426] Furthermore, the unit charging power margin consumption coefficient is processed by regional equivalence using the allocation coefficient between the spatial region and the distribution node. Combined with the background equivalent charging demand migration power, the electrical constraint difference components of the corresponding electrical locations before and after the charging demand is transferred from the outgoing region to the incoming region are calculated. For cases where the scale of spatial migration exceeds the applicable range of a single power disturbance, the corresponding migration power is divided into multiple migration increments. After each migration increment is completed, the background active and reactive power source load states are updated, and the AC power flow calculation is re-executed to accumulate the electrical constraint difference components corresponding to the spatial migration.
[0427] The electrical impact processing unit also obtains the power supply side access conditions of candidate distribution nodes. The power supply side access conditions include the power supply voltage level, power supply path, available power supply capacity of the line, available capacity of the power supply side transformer, and node voltage operating conditions corresponding to the candidate distribution node, thereby forming candidate access basic data that can be used together with the customer's electricity application overview.
[0428] The candidate solution generation unit receives a summary of the customer's electricity application, differential electrical constraints, and power supply access conditions. It then generates candidate access system solutions from among the candidate distribution nodes that meet the target customer's requested capacity and power supply voltage requirements. Different candidate access system solutions correspond to different candidate distribution nodes, power supply paths, power supply capacities, and power supply circuit configurations.
[0429] The security scheme screening unit does not directly use the power flow calculation results of the background network as the operating results after the target customer is connected. Instead, it reconstructs the candidate network for each candidate access system scheme. Specifically, the target customer load is superimposed on the candidate distribution nodes, and the output of new energy and the charging and discharging power of energy storage are added according to the target customer's new energy and energy storage configuration information, thereby forming the source-load state of the candidate network after the target customer is actually connected.
[0430] For the reconstructed candidate networks, the security scheme screening unit re-executes AC power flow calculations and verifies power supply reliability in conjunction with different power supply operating states. Simultaneously, it obtains the maximum continuous operating current and maximum expected short-circuit current of the corresponding candidate networks. Candidate access system schemes that meet the requirements of line thermal stability, power supply-side transformer capacity, node voltage, and the target customer's guaranteed load power supply are determined as secure access system schemes.
[0431] The solution output unit configures the power receiving system solution based on the power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current, maximum expected short-circuit current, and property boundary location in the secure access system solution. Specifically, the power supply voltage level limits the voltage level on the power receiving side; the power supply capacity and number of power supply circuits determine the main power receiving wiring and the configuration of the power receiving transformer; the maximum continuous operating current limits the rated current of the power receiving circuits; the maximum expected short-circuit current limits the corresponding breaking capacity; and emergency power supply capacity is configured in conjunction with the customer's security load and available energy storage.
[0432] During the configuration of the metering and billing scheme, the scheme output unit establishes the correspondence between the independent settlement power supply circuit and the metering point, and determines the handling methods for line loss and transformer loss based on the positional relationship between the property boundary and the metering point. When the output of new energy causes reverse active power at the metering point, the forward active energy and reverse active energy are metered separately.
[0433] After completing the above configuration, the solution output unit uses the customer's electricity application overview as the demand-side benchmark and performs a consistency check on the power supply capacity, power receiving capability, power supply circuits, operating current, short-circuit current, property boundaries, reactive power compensation, and emergency power supply relationships among the security access system solution, power receiving system solution, and metering and billing solution. When all relationships meet the corresponding configuration requirements, the target business expansion application power supply solution is output.
[0434] Therefore, this embodiment combines regional background charging demand prediction, spatial migration analysis of charging demand, quantification of electrical constraints of distribution nodes, candidate network reconstruction after actual access of target customers, and continuous connection of power receiving and metering configuration. This can avoid the repeated inclusion of newly applied loads of target customers into the background load, and at the same time incorporate the bidirectional power changes after the access of new energy and energy storage into the power supply scheme generation process.
[0435] like Figure 2 As shown, this embodiment provides a power supply scheme generation device for business expansion applications that considers new energy access. This device can be used as the hardware carrier of the power supply scheme generation device in Embodiment 1. It includes a processor and a memory. The processor and the memory are communicatively connected. The memory stores a computer program that can be executed by the processor.
[0436] The processor can be used to perform data reading, data processing, AC power flow calculation, candidate network reconstruction, and scheme generation processing; the memory is used to store computer programs and can store customer electricity application overview, multi-source spatiotemporal data, distribution network topology data, regional background charging demand, background active and reactive power source and load status of distribution nodes, electrical constraint differential components, and the corresponding operating data of candidate access system schemes.
[0437] When a computer program is executed by a processor, the processor first reads the target customer's electricity application information, load information, and new energy and energy storage configuration information. It then performs correlation processing on the target customer's applied capacity, load characteristics, new energy output capacity, and energy storage charging and discharging capacity to form a summary of the customer's electricity application.
[0438] The processor further utilizes multi-source spatiotemporal data corresponding to the target power supply area to predict the regional background charging demand based on historical charging demand and its temporal variation characteristics, while excluding newly applied loads from target customers during data processing. Subsequently, the predicted regional background charging demand is decomposed into a real total growth component and a spatial migration component, and based on the correspondence between the region and distribution nodes, the background load, charging demand, renewable energy output, and existing energy storage charging and discharging power are converted into the background active and reactive power source load states of the distribution nodes.
[0439] Based on the aforementioned node source-load states, the processor reads the power distribution network topology, line parameters, and power supply-side transformer parameters stored in memory to perform AC power flow calculations, generating background operating results for each distribution node and power supply path. On this basis, the processor sequentially changes the active and reactive power injection quantities of the candidate distribution nodes and performs AC power flow calculations again on the perturbed node source-load states. The response relationship of different distribution nodes to changes in charging power is obtained from the changes in electrical constraint safety margins before and after the perturbation.
[0440] For scenarios where regional background charging demand migrates spatially, the processor calculates the electrical constraint difference component based on the response relationship between the incoming and outgoing locations. This component characterizes the changes in power distribution operation constraints caused by the change in electrical location of the same portion of charging demand. Subsequently, by combining the available line capacity of candidate power distribution nodes, the available capacity of power supply-side transformers, and node voltage conditions, candidate access system schemes corresponding to different power supply locations and paths are generated.
[0441] For each candidate access system scheme, the processor retrieves the target customer's load and renewable energy and energy storage configurations from the customer's electricity application overview, and superimposes the corresponding active and reactive power sources onto the candidate distribution nodes to form candidate network data after the target customer's access. Based on the reconstructed candidate network, the processor re-executes AC power flow calculation and power supply reliability verification, and obtains the corresponding operating current and expected short-circuit current of the candidate network. Based on this, candidate access system schemes that cannot meet power supply safety requirements or load power supply requirements are eliminated.
[0442] For the retained security access system scheme, the processor forms corresponding power receiving configuration parameters based on its power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current, maximum expected short circuit current, and property boundary location, and forms an emergency power supply configuration in combination with the target customer's security load and available energy storage.
[0443] When formulating a metering and billing scheme, the processor establishes a mapping between the independent billing power supply circuit and the corresponding metering point, and determines the power metering method based on the power direction of the metering point. When new energy sources form a reverse power exchange with the power supply side, the processor processes the forward active power and the reverse active power separately.
[0444] Finally, the processor calls the customer's electricity application overview and the existing security access system plan, power receiving system plan and metering and billing plan, performs correlation consistency verification on the technical parameters that have a transmission relationship between different plans, and generates the target business expansion application power supply plan after the corresponding relationship is met.
[0445] This embodiment uses a processor and memory to carry out the above-mentioned continuous data processing process, combining regional background demand changes with the actual power distribution network operation status, and reloading the target customer load, new energy and energy storage configuration after the candidate scheme is formed, thereby realizing continuous processing from background operation analysis to target customer access analysis and then to power supply scheme output.
[0446] like Figure 3 As shown, this embodiment provides a computer storage medium, specifically a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, it implements the aforementioned method for generating a power supply scheme for business expansion applications that considers the access of new energy sources.
[0447] The computer program may include program instructions for processing customer electricity application information, program instructions for processing multi-source spatiotemporal data of the target power supply area, program instructions for predicting and decomposing background charging demand, program instructions for mapping the source and load of the area and distribution nodes, program instructions for performing AC power flow calculations and node power disturbance analysis, and program instructions for generating candidate access system schemes and performing security screening.
[0448] When the processor reads and executes the above program instructions, it first converts the target customer's electricity application information, load information, and new energy and energy storage configuration information into a customer electricity application overview; then, based on the multi-source spatiotemporal data of the target power supply area, it forms the regional background charging demand that does not include the target customer's newly installed load, and processes the actual total growth and spatial migration of the regional background charging demand separately.
[0449] The computer program further controls the processor to map the background source loads of each region to the corresponding distribution nodes, and forms the background active and reactive source load states of the distribution nodes. Based on the source load states, the processor calls the AC power flow calculation program to obtain the background operation results of the distribution network, and then calls the node power disturbance program to change the power injection state of the corresponding distribution node, so as to obtain the electrical constraint margin response of different electrical locations to power changes.
[0450] For the spatial migration component, the computer program invokes electrical constraint differential processing instructions to correlate the electrical constraint margin effects corresponding to the migration-in and migration-out locations, and combines this with the migration power to form the electrical constraint differential component for the corresponding electrical locations before and after the spatial migration. This differential component, together with the power supply side access conditions of the candidate distribution nodes, participates in the generation of candidate access system schemes.
[0451] After candidate access system schemes are generated, the computer program control processor re-reads the target customer load and the configuration of new energy and energy storage from the customer electricity application overview, and superimposes them onto the candidate networks corresponding to each candidate access system scheme. The processor re-executes AC power flow calculations for the superimposed candidate networks and performs power supply reliability verification in conjunction with the power supply operation status to obtain a safe access system scheme.
[0452] For the secure access system scheme, the computer program further calls the power receiving configuration processing instructions to form a matching power receiving system scheme based on the power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current, maximum expected short-circuit current, and property boundary location; at the same time, it calls the metering and billing processing instructions to establish the mapping relationship between the power supply circuit and the metering point, and to form the corresponding electricity metering relationship for the positive and reverse power generated by the access of new energy sources.
[0453] The computer program also includes correlation consistency verification instructions, which are used to correlate relevant parameters between the customer's electricity application overview, the secure access system plan, the power receiving system plan, and the metering and billing plan. Under the condition that the power supply capacity corresponds to the power receiving capacity, the power supply circuit corresponds to the power receiving circuit, the operating current corresponds to the equipment rated capacity, the short circuit current corresponds to the breaking capacity, and the property boundary corresponds to the metering relationship, the program controls the processor to output the target business expansion application power supply plan.
[0454] The computer-readable storage medium can be used to continuously or non-continuously store the aforementioned computer program, and the processor executes the corresponding data processing logic by reading the program instructions therein. Therefore, this embodiment can realize, in a programmatic form, continuous processing between regional background charging demand prediction, spatial migration electrical impact calculation, candidate network reconstruction, secure access scheme screening, and power receiving and metering configuration, while maintaining a corresponding technical processing relationship with the aforementioned power supply scheme generation method and power supply scheme generation device.
[0455] The foregoing has only described certain exemplary embodiments of this application by way of illustration. Undoubtedly, those skilled in the art can modify the described embodiments in various ways without departing from the spirit and scope of this application. Therefore, the foregoing drawings and descriptions are illustrative in nature and should not be construed as limiting the scope of protection of the claims of this application.
Claims
1. A method for generating a power supply scheme for business expansion applications that considers the access of new energy sources, characterized in that, Includes the following steps: Obtain electricity application information, load information, and new energy and energy storage configuration information of target customers to construct an overview of customer electricity applications; Acquire multi-source spatiotemporal data of the target power supply area to predict the background charging demand in areas that do not include new load applications from target customers. The actual total growth component and spatial migration component of the background charging demand in the separated area are separated, and the background source load of each area is mapped to the distribution node to obtain the background active and reactive source load status of the distribution node. Perform AC power flow calculations based on the active and reactive load states of the distribution node background; The influence of electrical constraint margin on different distribution nodes is obtained by obtaining the node power disturbance, the electrical constraint difference component of the corresponding electrical position before and after spatial migration is calculated, and the power supply side access conditions of the candidate distribution nodes are obtained. Candidate access system solutions are generated by utilizing customer electricity application overview, electrical constraint differential components, and power supply side access conditions; The target customer load and the configuration of new energy and energy storage are superimposed onto the candidate networks corresponding to each candidate access system scheme to verify the AC power flow and power supply reliability, and to select a safe access system scheme. For each secure access system solution, a matching power receiving system solution and metering and billing solution are configured. The consistency of the customer's electricity application overview, secure access system solution, power receiving system solution and metering and billing solution is verified, and the target business expansion application power supply solution is output.
2. The method for generating a power supply scheme for business expansion applications considering new energy access, as described in claim 1, is characterized in that... Regional background charging demand consists of a component of actual total growth and a component of spatial migration, among which: The actual total growth component is obtained by allocating the overall background charging demand change in the target power supply area according to the regional growth allocation coefficient, while the spatial migration component is obtained based on the inter-regional charging demand migration probability and the available charging demand. Furthermore, the inflow and outflow power of all regions remain conserved.
3. The method for generating a power supply scheme for business expansion applications considering new energy access, as described in claim 1, is characterized in that... The impact of electrical constraint margins includes the line thermal stability safety margin, the power supply side transformer capacity safety margin, and the node voltage safety margin. A combined active and reactive disturbance corresponding to the charging power factor is applied to the distribution node. The unit charging power margin consumption coefficient is obtained based on the ratio of the change in safety margin before and after the disturbance to the active power of the disturbance. The regional equivalent unit margin consumption coefficient is obtained by using the allocation coefficient of the spatial area and the distribution node.
4. The method for generating a power supply scheme for business expansion applications considering new energy access, as described in claim 3, is characterized in that... The electrical constraint difference component of the corresponding electrical location before and after spatial migration is calculated based on the difference between the migration power of the background equivalent charging demand and the regional equivalent unit margin consumption coefficient of the migration area and the migration area. For the background equivalent charging demand migration power that exceeds the applicable range of a single disturbance, it is divided into multiple migration increments. After each migration increment is completed, the background active and reactive power source load status of the distribution node and the regional equivalent unit margin consumption coefficient are updated, and the electrical constraint difference component corresponding to each migration increment is accumulated.
5. The method for generating a power supply scheme for business expansion applications considering new energy access, as described in claim 1, is characterized in that... The candidate access system schemes correspond to different candidate distribution nodes and power supply paths. Under the condition that the regional background charging demand does not include the target customer's new installed load, the target customer load, new energy output and energy storage charging and discharging power are loaded to the corresponding candidate distribution nodes to reconstruct the candidate network. The AC power flow and the maximum expected short-circuit current are recalculated for each candidate network to obtain the power supply voltage level, power supply capacity, number of power supply circuits, maximum continuous operating current and property boundary location of the safe access system scheme.
6. The method for generating a power supply scheme for business expansion applications considering new energy access, as described in claim 5, is characterized in that... The power receiving system scheme limits the configuration of the main power receiving wiring and power receiving transformer based on the power supply voltage level, power supply capacity and number of power supply circuits of the safe access system scheme, limits the rated current of the power receiving circuit based on the maximum continuous operating current, limits the corresponding breaking capacity based on the maximum expected short circuit current, and configures emergency power supply capacity according to the customer's security load and available energy storage.
7. The method for generating a power supply scheme for business expansion applications considering new energy access, as described in claim 1, is characterized in that... The metering and billing scheme establishes a mapping relationship between independent billing power supply circuits and metering points, and configures line loss and transformer loss handling methods according to the relationship between the property boundary location and the location of the metering point; When there is reverse active power at the metering point, the forward active power and reverse active power are obtained respectively, and the power supply capacity, power receiving capacity, power supply circuit, operating current, short circuit current, property boundary, reactive power compensation and emergency power supply are used as correlation consistency verification parameters.
8. A power supply scheme generation device for business expansion applications considering new energy access, characterized in that, include: The customer information processing unit is used to obtain the target customer's electricity application information, load information, and new energy and energy storage configuration information, and to construct an overview of the customer's electricity application. The background demand forecasting unit is used to acquire multi-source spatiotemporal data of the target power supply area and forecast the background charging demand in areas that do not include the new load application of the target customer. The source-load mapping unit is used to separate the actual total growth component and spatial migration component of the regional background charging demand, and to map the background source load of each region to the distribution node to obtain the background active and reactive source load status of the distribution node. The power flow calculation unit is used to perform AC power flow calculations based on the background active and reactive load states of the distribution node. The electrical influence processing unit is used to obtain the electrical constraint margin influence of different distribution nodes through node power disturbance, calculate the electrical constraint difference components of the corresponding electrical positions before and after spatial migration, and obtain the power supply side access conditions of candidate distribution nodes. The candidate solution generation unit is used to generate candidate access system solutions by utilizing the customer's electricity application overview, electrical constraint differential components, and power supply side access conditions. The security scheme screening unit is used to overlay the target customer load and the configuration of new energy and energy storage onto the candidate networks corresponding to each candidate access system scheme to verify the AC power flow and power supply reliability, and to screen the security access system scheme. The solution output unit is used to configure a matching power receiving system solution and metering and billing solution for the security access system solution. It performs consistency verification on the customer's electricity application overview, security access system solution, power receiving system solution and metering and billing solution, and outputs the target business expansion application power supply solution.
9. A power supply scheme generation device for business expansion applications considering new energy access, characterized in that, It includes a processor and memory. The memory stores computer programs, and when the computer program is executed by the processor, it performs the following processing: Obtain electricity application information, load information, and new energy and energy storage configuration information of target customers to construct an overview of customer electricity applications; Acquire multi-source spatiotemporal data of the target power supply area and predict the background charging demand in areas that do not include new load applications from target customers; Separate the actual total growth component and spatial migration component of the background charging demand in the region, and map the background source load of each region to the distribution node to obtain the background active and reactive source load status of the distribution node. AC power flow calculations are performed based on the background active and reactive load states of distribution nodes. The influence of electrical constraint margins on different distribution nodes is obtained through node power disturbances. The electrical constraint difference components of the corresponding electrical locations before and after spatial migration are calculated, and the power supply side access conditions of candidate distribution nodes are obtained. Candidate access system solutions are generated by utilizing customer electricity application overview, electrical constraint differential components, and power supply side access conditions; The target customer load and the configuration of new energy and energy storage are superimposed onto the candidate networks corresponding to each candidate access system scheme to verify the AC power flow and power supply reliability, and to select a safe access system scheme. Configure a matching power receiving system scheme and metering and billing scheme for the security access system scheme, and output the target business expansion application power supply scheme after verifying the correlation consistency.
10. A computer storage medium, characterized in that, A computer-readable storage medium stores a computer program, which, when executed by a processor, implements a method for generating a power supply scheme for business expansion applications that considers the access of new energy sources, as described in any one of claims 1-7.