Double-z-axis device and ultra-high-speed bulk patching machine
By integrating dual Z-axis equipment into the placement machine and utilizing a staggered overlay design and a visual recognition module, the efficiency bottleneck of the single Z-axis was solved, achieving a highly efficient placement process.
Patent Information
- Application Number
- CN202611465798.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-20
- Publication Date
- 2026-11-20
AI Technical Summary
The efficiency of existing single Z-axis placement machines has reached a bottleneck, making it difficult to meet the demands of high-speed production.
The device employs a dual Z-axis design, integrating two independently controllable Z-axis modules within a limited space. It also incorporates sliders and lead screw nut seats with varying thicknesses to achieve staggered overlapping. Combined with a dual Mark point visual recognition module and through-beam optical fiber, this enhances positioning and detection efficiency.
Without increasing the lateral dimensions of the equipment, it significantly improves placement efficiency, shortens positioning time, and ensures production reliability and efficiency.
Smart Images

Figure CN123145884A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of automation equipment technology, and in particular to a dual Z-axis device and an ultra-high-speed bulk material placement machine. Background Technology
[0002] Pick and place machines are key pieces of equipment in the electronics manufacturing industry, and their efficiency directly affects the production line's capacity. Existing pick and place machines typically use a single Z-axis structure for material handling and placement operations.
[0003] However, with the development of technology, the single Z-axis structure and its related machine layout design have reached a bottleneck in terms of efficiency improvement, and its working chip placement efficiency is difficult to improve further, which cannot meet the growing demand for high-speed production. Summary of the Invention
[0004] The technical problem to be solved by the present invention is to provide a dual Z-axis device and an ultra-high-speed bulk material placement machine including the device, so as to solve the problem that the working efficiency of the single Z-axis placement machine in the prior art is difficult to improve.
[0005] The present invention adopts the following technical solution: A dual Z-axis device includes a front Z-axis module and a rear Z-axis module, wherein the front Z-axis module and the rear Z-axis module are respectively provided with a patch suction nozzle; The front Z-axis module includes a front suction nozzle assembly, a second mounting plate, a second slider, a second lead screw, and a second lead screw nut seat; wherein, the front suction nozzle assembly is fixed to the second mounting plate, the second mounting plate is fixed to the second slider and the second lead screw nut seat, and the second lead screw nut seat is fixed to the nut of the second lead screw; The rear Z-axis module includes a rear suction nozzle assembly, a first mounting plate, a first slider, a first lead screw, and a first lead screw nut seat; wherein, the rear suction nozzle assembly is fixed to the first mounting plate, the first mounting plate is fixed to the first slider and the first lead screw nut seat, and the first lead screw nut seat is fixed to the nut of the first lead screw; The second slider and the first slider are slidably coupled to the same guide rail; The second slider and the first slider have different thicknesses in the front-to-back direction, and the second lead screw nut seat and the first lead screw nut seat also have different thicknesses in the front-to-back direction, thus together placing the second mounting plate in front of the first mounting plate.
[0006] Furthermore, the second motor is connected to one end of the second lead screw via a second coupling to drive the second lead screw to rotate, causing the second lead screw nut seat to move up and down along the second lead screw; The first motor is connected to one end of the first lead screw via a first coupling to drive the first lead screw to rotate, causing the first lead screw nut seat to move up and down along the first lead screw.
[0007] Furthermore, one end of the second spring is fixedly installed, and the other end is connected to the second mounting plate; One end of the first spring is fixedly installed, and the other end is connected to the first mounting plate.
[0008] Furthermore, the second mounting plate is fixed to the second slider by the second pad.
[0009] Furthermore, it also includes a dual-Mark point visual recognition module, which includes a left camera, a right camera, a left light source, and a right light source, used to capture the Mark points on the PCB board to achieve the positioning of the PCB board.
[0010] Furthermore, the first mounting plate is provided with a first photoelectric sensor, which moves up and down with the first mounting plate and cooperates with the first photoelectric sensor and the second photoelectric sensor to achieve origin finding and overshoot protection. The second mounting plate is also provided with a second photoelectric sensor, a third photoelectric sensor, and a fourth photoelectric sensor. The second photoelectric sensor moves up and down with the second mounting plate and cooperates with the corresponding third and fourth photoelectric sensors to achieve origin finding and overshoot protection.
[0011] Furthermore, the positive and negative pressures of the patch nozzles of the front nozzle assembly and / or the rear nozzle assembly are controlled by solenoid valves, and are monitored in real time by pressure gauges.
[0012] Furthermore, it also includes a front-through fiber and a rear-through fiber, which are used to detect whether there is residual material on the corresponding patch nozzle; both the front-through fiber and the rear-through fiber include a transmitter and a receiver. When there is residual material on the corresponding patch nozzle, the light emitted by the transmitter is blocked, and the receiver cannot receive the light to determine that there is residual material.
[0013] An ultra-high-speed bulk material placement machine includes the aforementioned dual Z-axis device.
[0014] Compared with the prior art, the beneficial effects of the present invention are as follows: By setting up front and rear Z-axis modules, and designing the second slider and the first slider, as well as the second lead screw nut seat and the first lead screw nut seat, to have different thicknesses in the front-to-back direction, the two Z-axis modules can achieve staggered stacking in front-to-back space while sharing the same guide rail. This integrates two Z-axis that can work independently or collaboratively without significantly increasing the lateral size of the equipment. This allows the equipment to achieve efficient working modes such as simultaneous or alternating material picking and placement by dual nozzles, significantly improving placement efficiency compared to traditional single Z-axis structures. Furthermore, by configuring a dual Mark point vision recognition module, the time required for PCB board positioning can be shortened. By setting up through-beam optical fibers, the presence of excess material after placement can be quickly detected, ensuring production reliability. Attached Figure Description
[0015] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0016] Figure 1 This is an axial view of the patch dual Z-axis structure of the present invention.
[0017] Figure 2 This is a side view of the patch dual Z-axis structure of the present invention.
[0018] Figure 3 This is a first front view of the patch dual Z-axis structure of the present invention.
[0019] Figure 4 This is a second front view of the patch dual Z-axis structure of the present invention.
[0020] Figure 5 This is a front view of the patch dual Z-axis structure of the present invention, which hides the second mounting plate.
[0021] Figure 6 This is a front view of the patch dual Z-axis structure of the present invention, concealing the first and second mounting plates.
[0022] Figure 7 This is a top view of the layout of an ultra-high-speed bulk material patching machine according to the present invention.
[0023] Figure 8 This is a top view of the fly-sweep correction module of an ultra-high-speed bulk material patch machine according to the present invention.
[0024] Figure 9 This is a top view of the vibratory feeder module and main turntable of an ultra-high-speed bulk material patching machine according to the present invention.
[0025] Figure 10 This is a schematic diagram of the carrier loading of an ultra-high-speed bulk material patching machine according to the present invention.
[0026] Figure 11 This is a schematic diagram of a high-speed bulk material patching machine according to the present invention.
[0027] Wherein: 1-Front suction nozzle assembly; 2-Second mounting plate; 3-Second slider; 4-Second pad; 5-Second coupling; 6-Second fixed seat; 7-Second lead screw; 8-Second spring; 9-Rear suction nozzle assembly; 10-First mounting plate; 11-Second motor; 12-First slider; 13-First lead screw; 14-First fixed seat; 15-First coupling; 16-First motor; 17-First spring; 18-First photoelectric sensor; 19-First photoelectric sensor sheet; 20-Second photoelectric sensor; 21-Front through-beam optical fiber; 22-Rear through-beam fiber optic cable; 23-Left camera; 24-Left light source; 25-Right camera; 26-Right light source; 29-Second lead screw nut seat; 30-First lead screw nut seat; 31-Flying sweep calibration module; 31-1-Groove; 32-Inlet conveyor belt module; 33-Outlet conveyor belt module; 34-Vibrating plate module; 36-First correction mechanism; 37-Testing mechanism; 38-First material feeding imaging mechanism; 39-Polar rotation mechanism; 40-Second correction mechanism; 41-Second NG material feeding mechanism; 42-Carrier; 43-Main turntable. Detailed Implementation
[0028] The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present invention.
[0029] Before providing a further detailed description of the embodiments of this application, some of the nouns and terms involved in the embodiments of this application will be explained. The nouns and terms involved in the embodiments of this application are subject to the following interpretations.
[0030] (1) Dual Z-axis equipment: refers to an actuator used in automated equipment such as pick and place machines, which integrates two Z-axis modules that can move up and down independently in a limited space (e.g., sharing the same guide rail) to improve work efficiency.
[0031] (2) Front-back direction: In this application, it refers to the direction in which the two Z-axis modules are staggered on the same guide rail. This direction is perpendicular to the length direction of the guide rail. Figures 3 to 6 In this context, the front-back direction refers to the direction perpendicular to the paper.
[0032] (3) Dual Mark Point Visual Recognition Module: refers to a vision system used to accurately locate objects to be processed (such as PCB boards). It usually includes at least two cameras and matching light sources. It calculates the precise position and orientation of the object by photographing two or more reference points (Mark points) on the object, thereby shortening the positioning time.
[0033] (4) Through-beam optical fiber: This refers to a photoelectric sensor consisting of a transmitter and a receiver. The transmitter emits a light beam, which is received by the receiver. When an object (such as residual material) blocks the light path, the receiver cannot receive the light signal, thus determining the presence of the object.
[0034] Please see Figures 1 to 6 This application provides a dual Z-axis device to address the bottleneck in efficiency of existing single Z-axis pick-and-place machines, which is difficult to further improve. This application achieves a significant increase in efficiency while maintaining a compact structure by integrating two independently controllable Z-axis modules (front and rear) within a limited space and sharing a portion of the guiding mechanism. The device mainly includes a front Z-axis module and a rear Z-axis module, both of which are equipped with pick-and-place nozzles for picking up and placing electronic components (LED beads).
[0035] The front Z-axis module includes a front suction nozzle assembly 1, a second mounting plate 2, a second slider 3, a second lead screw 7, and a second lead screw nut seat 29. The rear Z-axis module also adopts a similar structure, including a rear suction nozzle assembly 9, a first mounting plate 10, a first slider 12, a first lead screw 13, and a first lead screw nut seat 30. This independent modular design provides a structural basis for independent motion control of the two Z-axis.
[0036] To allow the two Z-axis modules to coexist in a compact space, the second slider 3 of the front Z-axis module and the first slider 12 of the rear Z-axis module are slidably mounted on the same guide rail. This means that the two independent vertical motion modules share the same guiding system, saving space in the left-right direction and avoiding structural redundancy and increased costs associated with setting up two completely independent guide rail systems. Generally, there are two second sliders 3, two first sliders 12, and two guide rails. The first second slider 3 and the first first slider 12 are slidably mounted on the first guide rail on the left, and the second second slider 3 and the second first slider 12 are slidably mounted on the second guide rail on the right. This avoids the large space required by having two guide rails for the front Z-axis module and two more for the rear Z-axis module, resulting in a total of four guide rails arranged in the left-right direction.
[0037] Furthermore, this embodiment achieves spatial misalignment of the two Z-axis modules in the front-to-back direction by utilizing the dimensional differences of the structural components. The second slider 3 and the first slider 12 have different thicknesses in the front-to-back direction, and the second lead screw nut seat 29 and the first lead screw nut seat 30 are also correspondingly set to have different thicknesses in the front-to-back direction. This allows the second mounting plate 2, which supports the front suction nozzle assembly 1, to be spatially positioned in front of the first mounting plate 10, which supports the rear suction nozzle assembly 9, thus forming a front-to-back arrangement of the two Z-axis modules and avoiding physical interference during vertical movement. This embodiment achieves the integration of dual Z-axis modules by utilizing the front-to-back depth without increasing the left-to-right width.
[0038] Furthermore, in a preferred embodiment, in order to drive the two Z-axis modules to achieve precise up-and-down movement, please refer to... Figure 4 and Figure 5 The front Z-axis module is equipped with a second motor 11, which is connected to one end of the second lead screw 7 via a second coupling 5. When the second motor 11 starts rotating, its rotational motion is transmitted to the second lead screw 7 through the second coupling 5, driving the second lead screw 7 to rotate. Since the second lead screw nut seat 29, which is threaded into the second lead screw 7, is constrained in the rotational direction, it will translate along the axial direction of the second lead screw 7, i.e., the up-down direction.
[0039] Similarly, the rear Z-axis module is also equipped with an independent drive system. The first motor 16 is connected to one end of the first lead screw 13 via a first coupling 15. When the first motor 16 rotates, it drives the first lead screw 13 to rotate via the first coupling 15, thereby driving the first lead screw nut seat 30, which in turn drives the first lead screw nut seat 30 to move up and down along the first lead screw 13. By configuring an independent motor and lead screw drive system for each of the front and rear Z-axis modules, complete decoupling of their movements is achieved. They can move simultaneously, alternately, or independently, providing maximum flexibility for implementing complex placement strategies and improving efficiency.
[0040] In another preferred embodiment, to balance the weight of the Z-axis module itself, reduce the load on the drive motor, and improve the dynamic response performance of the system, please refer to [link to relevant documentation]. Figure 4 and Figure 5 The front Z-axis module is equipped with a second spring 8, one end of which is fixedly mounted on the frame, and the other end is connected to a second mounting plate 2 that can move up and down. Similarly, the rear Z-axis module is also equipped with a first spring 17, one end of which is fixedly mounted, and the other end is connected to a movable first mounting plate 10.
[0041] These two springs are normally under tension, providing an upward lifting force to the corresponding Z-axis module. This lifting force can partially or completely offset the module's own weight, thus significantly reducing the torque required by the drive motor to vertically lift the module. On the one hand, a lower-power and lower-cost motor can be selected, reducing equipment manufacturing costs; on the other hand, it reduces the motor's load, allowing for faster response during acceleration and deceleration, reducing positioning time, and further improving placement efficiency. Simultaneously, in the event of a power outage or other unexpected situation, the spring's lifting action also prevents the Z-axis module from suddenly falling due to gravity, providing a certain degree of protection.
[0042] In one alternative embodiment, the second mounting plate 2 is fixed to the second slider 3 by a second pad 4. See also... Figure 4 and Figure 6 The second pad 4 serves as a connector. On the one hand, it can be used to adjust the distance between the second mounting plate 2 and the second slider 3. On the other hand, it works in conjunction with the thickness of the second lead screw nut seat 29 to ensure the accurate positioning of the front Z-axis module relative to the rear Z-axis module in the front-rear direction.
[0043] Furthermore, to shorten alignment time and improve overall system efficiency, this application also provides a dual-Mark point visual recognition module. Please refer to... Figure 7 The module includes a left camera 23 and a right camera 25, each equipped with a left light source 24 and a right light source 26. This dual-mark point visual recognition module is integrated into an XY motion gantry mechanism. When positioning a PCB board, unlike a single-camera system, it does not require moving a long distance to sequentially capture images of two distant mark points. In this embodiment, the gantry mechanism only needs to move a short distance for the left and right cameras to capture images of the two mark points on the PCB board. By using parallel or near-parallel shooting with dual cameras, the movement and focusing time between the two mark points is greatly shortened, thus significantly reducing the overall positioning time of the PCB board. In high-speed, high-volume production, the accumulated positioning time saved in each cycle will greatly improve the unit time productivity of the equipment. In addition, the independent left light source 24 and right light source 26 can be independently controlled in terms of switching and brightness according to the shooting needs of different cameras, ensuring clear mark point images under various lighting conditions, guaranteeing the accuracy and robustness of positioning.
[0044] In a preferred embodiment, please refer to Figure 5Taking the rear Z-axis module as an example, a first photoelectric sensor 19 is fixedly mounted on the first mounting plate 10. The first photoelectric sensor 19 moves up and down with the first mounting plate 10. A first photoelectric sensor 18 and a second photoelectric sensor 20 are correspondingly mounted at fixed positions on the frame; these are typically U-shaped through-beam sensors. When the first photoelectric sensor 19 moves to a specific position and inserts into the sensing slot of one of the sensors, it blocks the light path, thereby triggering a signal. One of the sensors, such as the first photoelectric sensor 18, can be defined as the origin sensor. When the device starts, the first motor 16 drives the module to move slowly until the first photoelectric sensor 19 triggers the first photoelectric sensor 18, and the controller records this position as the origin of the Z-axis. The other sensor, such as the second photoelectric sensor 20, can be set as a limit sensor for the upper or lower travel limit. When the module's movement exceeds the preset safety range and triggers the sensor, the controller immediately stops the motor to prevent mechanical collisions caused by program errors or unexpected situations, thus achieving overshoot protection. Similarly, the second mounting plate 2 is also provided with a corresponding second photoelectric sensor and third and fourth photoelectric sensors to achieve the same function.
[0045] In another preferred embodiment, the internal positive or negative pressure of the pick-up nozzles of the front nozzle assembly 1 and / or the rear nozzle assembly 9 is precisely controlled by independent solenoid valves. During material handling, the solenoid valve switches to the negative pressure path, creating a vacuum inside the nozzle, thereby adsorbing the components (LED beads) onto the nozzle end. During placement, the solenoid valve switches to the positive pressure path or closes the negative pressure and breaks the vacuum, eliminating suction and smoothly placing the components on the PCB board.
[0046] To further improve process reliability, pressure gauges are also installed to monitor the pressure inside each placement nozzle in real time. By reading the pressure gauge data, the system can determine whether material has been successfully picked up. After successful material pickup, the negative pressure value will reach a stable range, or after placement, whether the pressure has completely returned to atmospheric pressure. This allows for more accurate monitoring of the pickup and placement status, timely detection of abnormalities such as material pickup failure and leakage, thereby ensuring the stability and yield of the entire placement process.
[0047] Furthermore, to address the issue of mounted materials (LED beads) potentially adhering to the nozzle and failing to be successfully released, please refer to [link to relevant documentation]. Figure 2This embodiment also includes a front through-beam fiber 21 and a rear through-beam fiber 22, used to detect whether there is residual material on the front and rear nozzle assemblies, respectively. Each set of through-beam fibers, such as the front through-beam fiber 21, includes a transmitter and a receiver. Its working principle is as follows: the transmitter continuously emits a beam of normally invisible infrared light towards the receiver. Under normal circumstances, i.e., when there is no residual material on the nozzle, the optical path is unobstructed, and the receiver can stably receive the light signal. However, if, after a mounting process, a component such as an LED bead fails to detach and remains stuck on the nozzle, the residual component (LED bead) will block the optical path. At this time, the receiver will not receive the light signal, and the system will determine that there is residual material and can immediately alarm and stop the machine or execute a preset abnormal handling procedure. The rear through-beam fiber 22 detects the rear nozzle assembly in the same way.
[0048] This application also provides an ultra-high-speed bulk material placement machine, which employs the dual Z-axis equipment described in any of the foregoing embodiments, thereby achieving extremely high working efficiency. Please refer to... Figures 7 to 11 By understanding the overall workflow of this ultra-high-speed bulk material patching machine, we can see the application value of dual Z-axis equipment.
[0049] First, in the feeding area, bulk electronic components (LED beads) are screened and oriented by the vibratory feeder module 34 and then transported to the picking station. A main turntable 43 with multiple suction nozzles rotates and lifts intermittently, picking up the oriented components from the front end of the vibratory feeder.
[0050] After picking up the components, the main turntable 43 rotates, sequentially sending the components to multiple processing stations. First, the first correction mechanism 36 performs preliminary and precise correction on the component's position on the nozzle. Then, it reaches the testing mechanism 37, where the electrical performance parameters of the components are tested, and their polarity is determined based on the test results. The tested components are then conveyed to the first discharge imaging mechanism 38, where unqualified (NG) components are discharged, while qualified (OK) components undergo bottom appearance image inspection.
[0051] Next, the components arrive at the polarity rotation mechanism 39, where all components are rotated to a uniform orientation based on the polarity information obtained from previous tests. Then, a second position correction is performed in the second correction mechanism 40. Subsequently, the second NG discharge mechanism 41 removes components that fail the appearance inspection. After layers of screening and correction, the qualified components are finally transported by the main turntable 43 to the carrier loading station.
[0052] At the carrier loading station, the suction nozzles on the main turntable 43 precisely place the components into the slots of the carrier 42 by breaking the vacuum. For example... Figure 10As shown, the carrier 42 is typically designed with double or multiple rows of slots to match an efficient loading and unloading process. Once a carrier 42 is full of components, it is conveyed to the unloading position in the placement area, waiting for the dual Z-axis equipment to pick them up.
[0053] At this time, as Figure 11 As shown, the dual Z-axis device, equipped with a front suction nozzle assembly 1 and a rear suction nozzle assembly 9, moves at high speed above the carrier 42 under the drive of the gantry mechanism XY drive module. The front and rear suction nozzle assemblies can remove two rows of components from the double-row slots of the carrier 42 at extremely short intervals.
[0054] After material is picked up, the dual Z-axis device moves above the fly-sweep calibration module 31. For example... Figure 8 As shown, the fly-sweep calibration module 31 has calibration components that can move closer or further apart from each other, forming precise toothed grooves 31-1 when closed. The front Z-axis module and the rear Z-axis module descend independently, feeding the components on the nozzle into the toothed grooves 31-1. Through mechanical clamping, the position of the components on the nozzle is finally calibrated. After calibration, the Z-axis rises and resets.
[0055] Next, the dual Z-axis device passes through a high-speed imaging mechanism (not shown in the figure) to take high-speed pictures of the components on the nozzle, in order to reconfirm the position, appearance, and presence of empty components. At the same time, the dual Mark point vision recognition module on the machine has completed the precise positioning of the PCB board.
[0056] Finally, the gantry mechanism moves the dual Z-axis equipment to the target position above the PCB board. Based on calculated coordinates, the front and rear Z-axis modules alternately or collaboratively perform downward pressing actions, precisely placing the components on their respective nozzles onto the corresponding pads on the PCB board. After completing one cycle, the dual Z-axis equipment immediately returns to the pick-up position for the next pick-up, while the already placed PCB board is sent out via the output conveyor module 33, and a new empty board enters the placement position via the input conveyor module 32. The entire process repeats continuously, achieving a placement speed far exceeding that of traditional single Z-axis equipment through the efficient collaborative work of the dual Z-axis.
[0057] The present invention has been further described above with reference to specific embodiments. The specific descriptions herein should not be construed as limiting the nature and scope of the present invention. Various modifications made by those skilled in the art to the above embodiments after reading this specification are all within the scope of protection of the present invention.
Claims
1. A dual Z-axis device, characterized in that, It includes a front Z-axis module and a rear Z-axis module, and the front Z-axis module and the rear Z-axis module are respectively provided with a patch suction nozzle; The front Z-axis module includes a front suction nozzle assembly (1), a second mounting plate (2), a second slider (3), a second lead screw (7), and a second lead screw nut seat (29); wherein, the front suction nozzle assembly (1) is fixed to the second mounting plate (2), the second mounting plate (2) is fixed to the second slider (3) and the second lead screw nut seat (29), and the second lead screw nut seat (29) is fixed to the nut of the second lead screw (7); The rear Z-axis module includes a rear suction nozzle assembly (9), a first mounting plate (10), a first slider (12), a first lead screw (13), and a first lead screw nut seat (30); wherein, the rear suction nozzle assembly (9) is fixed to the first mounting plate (10), the first mounting plate (10) is fixed to the first slider (12) and the first lead screw nut seat (30), and the first lead screw nut seat (30) is fixed to the nut of the first lead screw (13); The second slider (3) and the first slider (12) are slidably coupled to the same guide rail; The second slider (3) and the first slider (12) have different thicknesses in the front-to-back direction, and the second lead screw nut seat (29) and the first lead screw nut seat (30) have different thicknesses in the front-to-back direction, so that the second mounting plate (2) is located in front of the first mounting plate (10).
2. The dual Z-axis device according to claim 1, characterized in that, The second motor (11) is connected to one end of the second lead screw (7) via the second coupling (5) to drive the second lead screw (7) to rotate, so that the second lead screw nut seat (29) moves up and down along the second lead screw (7); The first motor (16) is connected to one end of the first lead screw (13) via the first coupling (15) to drive the first lead screw (13) to rotate, so that the first lead screw nut seat (30) moves up and down along the first lead screw (13).
3. A dual Z-axis device according to claim 1, characterized in that, One end of the second spring (8) is fixedly installed, and the other end is connected to the second mounting plate (2); One end of the first spring (17) is fixedly installed, and the other end is connected to the first mounting plate (10).
4. A dual Z-axis device according to claim 1, characterized in that, The second mounting plate (2) is fixed to the second slider (3) by the second pad (4).
5. A dual Z-axis device according to claim 1, characterized in that, It also includes a dual Mark point visual recognition module, which includes a left camera (23), a right camera (25), a left light source (24), and a right light source (26), used to capture the Mark points on the PCB board to achieve the positioning of the PCB board.
6. A dual Z-axis device according to claim 1, characterized in that, The first mounting plate (10) is provided with a first photoelectric sensor (19). The first photoelectric sensor (19) moves up and down with the first mounting plate (10) and cooperates with the first photoelectric sensor (18) and the second photoelectric sensor (20) to achieve origin search and overshoot protection. The second mounting plate (2) is also provided with a second photoelectric sensor, a third photoelectric sensor, and a fourth photoelectric sensor. The second photoelectric sensor moves up and down with the second mounting plate (2) and cooperates with the corresponding third photoelectric sensor and fourth photoelectric sensor to achieve origin search and overshoot protection.
7. A dual Z-axis device according to claim 1, characterized in that, The positive and negative pressures of the patch nozzles of the front nozzle assembly (1) and / or the rear nozzle assembly (9) are controlled by solenoid valves, and are monitored in real time by pressure gauges.
8. A dual Z-axis device according to claim 1, characterized in that, It also includes a front through-beam fiber (21) and a rear through-beam fiber (22), which are used to detect whether there is residual material on the corresponding patch nozzle. The front through-beam fiber (21) and the rear through-beam fiber (22) both include a transmitter and a receiver. When there is residual material on the corresponding patch nozzle, the light emitted by the transmitter is blocked and the receiver cannot receive the light to determine that there is residual material.
9. A high-speed bulk material placement machine, characterized in that, Includes a dual Z-axis device as described in any one of claims 1-8.