Method, device and equipment for synergistic water control of redrying and rehumidification, and storage medium

By constructing a feasible atomization domain and performing synergistic optimization control to minimize water addition deviation and optimize atomization quality, the coupling contradiction between water addition accuracy and atomization quality in the re-drying and re-moistening water addition control was resolved. Stable atomization and water addition accuracy were achieved under low load and head-to-tail switching conditions, thereby improving the stability and safety of the control system.

CN123147676APending Publication Date: 2026-11-24HONGTA TOBACCO (GROUP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611379530.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-07
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

In existing re-drying and re-moistening water control methods, the serial architecture that separates water demand calculation from atomization constraint verification leads to a prominent coupling contradiction between water addition accuracy and atomization quality under low load and head-to-tail switching conditions. In particular, the atomization quality deterioration and uneven local absorption problems are serious under low flow conditions.

Method used

By constructing feasible atomization domains for each zone, coupling the total water demand based on projection theory, and employing a collaborative optimization control method with the dual objectives of minimizing water addition deviation and optimizing atomization quality, online deviation correction is performed by combining virtual feedback values ​​of predicted future outlet moisture and temperature, thereby achieving collaborative optimization of water addition accuracy and atomization quality.

Benefits of technology

Under low load and head-to-tail switching conditions, the stability of atomization quality and the accuracy of water addition were improved, reducing water stains and smoke and uneven local absorption, thus ensuring the stability and safety of the control system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123147676A_ABST
    Figure CN123147676A_ABST
Patent Text Reader

Abstract

This application discloses a collaborative water addition control method, apparatus, equipment, and storage medium for reheating and rehydration, relating to the field of data processing technology. The method calculates the theoretical total water addition demand by collecting incoming material data and environmental data; it transforms atomization quality constraints into feasible regions by constructing atomization capability feature vectors for each zone, elevating atomization conditions from post-event verification to pre-event modeling; it redistributes water addition demands exceeding the feasible region to adjacent zones through coupled projection, preventing water addition demands in a certain zone from falling into atomization dead zones; it solves for water addition commands and atomization control commands within the feasible region through dual-objective collaborative optimization of minimizing water addition deviation and optimizing atomization quality, eliminating coupling contradictions in the serial architecture; it corrects control deviations in advance under large time delay conditions by predicting future outlet moisture and outlet temperature and using virtual feedback values; and it performs safety verification and degradation processing through operating condition labels and fault diagnosis results, ensuring control safety during head-to-tail switching and abnormal operating conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of data processing technology, and in particular to a method, apparatus, equipment and storage medium for coordinated water addition control during re-drying and rehydration. Background Technology

[0002] Re-drying and rehydration is a key process in tobacco processing. The moisture content and temperature are increased by applying atomized water to the tobacco leaves during the rehydration stage.

[0003] The rehumidification section is usually divided into four zones according to process responsibilities. Each zone undertakes different roles such as pre-humidification, main humidification, and terminal fine-tuning. Water is supplied to the nozzle islands distributed in each zone through a dual-plunger pump, supplemented by steam heat and humidity regulation and compressed air pressure stabilization to maintain atomization quality.

[0004] During production, the control system needs to calculate the theoretical total water demand based on data such as inlet material flow rate, inlet moisture content, and inlet temperature, and then allocate the water supply to each zone according to their respective process responsibilities. Because there is a material conveying delay of over one hundred seconds between the rehydration inlet and the outlet detection point, the outlet moisture content cannot be obtained in real time. Therefore, control actions need to be made in advance, considering the material segments that will reach the outlet in the future.

[0005] Existing methods for controlling water addition during re-drying and rehydration typically employ a serial processing architecture. This involves first calculating the theoretical total water demand and allocating it to each zone, then verifying the atomization quality of the parameters for each zone. When the water demand in a zone is low under low flow conditions and the number of nozzles activated is excessive, the pressure drop before the nozzles leads to increased droplet size, weakened droplet penetration, and uneven local absorption, resulting in water stains and smoke. Reducing the number of nozzles to maintain pressure presents problems such as inconsistent pressure settings and insufficient water addition accuracy.

[0006] This serial architecture, which separates the calculation of water supply requirements from the verification of atomization constraints, does not fundamentally resolve the coupling contradiction between water supply accuracy and atomization quality, which is particularly prominent under low load and head-to-tail switching conditions. Summary of the Invention

[0007] The main purpose of this application is to provide a method, device, equipment and storage medium for coordinated water addition control during reheating and rehydration, so as to solve the problem that the serial architecture of the prior art, which separates the calculation of water addition requirements from the verification of atomization constraints, does not fundamentally solve the coupling contradiction between water addition accuracy and atomization quality, which is particularly prominent under low load and head-to-tail switching conditions.

[0008] To achieve the above objectives, this application provides the following technical solution: A method for controlling synergistic water addition during re-drying and rehydration, the method comprising: Step S1: Collect incoming material data and environmental data for the re-drying and rehydration section; calculate dry basis mass flow rate based on incoming material flow rate, inlet moisture and inlet temperature; calculate the theoretical total water demand based on the target outlet moisture and dry basis mass flow rate. Step S2: Based on the combined relationship of the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure and droplet size, construct the atomization capability feature vector of each zone, transform the atomization quality constraints of each zone into atomization feasible regions, and output the boundary of the atomization feasible region of each zone. Step S3: Couple the theoretical total water demand according to the boundary of the atomization feasible domain of each zone. When the theoretical total water demand falls outside the atomization feasible domain of a certain zone, redistribute the excess water demand of that zone to the feasible domain of the adjacent zone, and output the coupled feasible water supply range of each zone. Step S4: Within the feasible water addition range of each zone, perform collaborative optimization with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and output water addition commands and atomization control commands for each zone. Step S5: Based on the water addition command and atomization control command of each zone, predict the future outlet moisture and outlet temperature, use the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable real outlet value, update the online deviation corrector with the delayed real detection value, and correct the water addition command and atomization control command of each zone based on the online deviation corrector. Step S6: Based on the operating condition label and fault diagnosis results, perform safety verification and downgrade processing on the corrected water addition instructions and atomization control instructions for each zone, output the final control instructions and issue them for execution.

[0009] Beneficial effects of steps S1 to S6: This method addresses the serial architecture problem of separating water demand calculation and atomization constraint verification in the control of water addition during re-drying and rehydration. By constructing a feasible atomization domain for each zone and coupling and projecting the theoretical total water addition demand into the feasible domain, it achieves coordinated optimization control of water addition accuracy and atomization quality. It can maintain stable atomization under low load and head-to-tail switching conditions, reducing water stains, smoke, and uneven local absorption.

[0010] Step S1 calculates the theoretical total water demand by collecting incoming material data and environmental data, providing an accurate benchmark for the total water demand in subsequent coordinated control. Step S2 transforms the atomization quality constraint into a feasible region by constructing atomization capability feature vectors for each zone, upgrading the atomization conditions from post-event verification to pre-event modeling. Step S3 redistributes the water demand exceeding the feasible region to adjacent zones through coupled projection, preventing the water demand of a certain zone from falling into the atomization dead zone. Step S4 uses dual-objective coordinated optimization of minimizing water demand deviation and optimizing atomization quality to simultaneously solve for water demand commands and atomization control commands within the feasible region, eliminating coupling contradictions in the serial architecture. Step S5 predicts future outlet moisture and outlet temperature and uses virtual feedback values ​​for deviation correction, pre-correcting control deviations under large time delay conditions. Step S6 performs safety verification and degradation processing through operating condition labels and fault diagnosis results, ensuring control safety during head-to-tail switching and abnormal operating conditions.

[0011] As a further improvement to this application, step S1 involves collecting incoming material data and environmental data for the re-drying and rehydration section, calculating the dry basis mass flow rate based on the incoming material flow rate, inlet moisture content, and inlet temperature, and calculating the theoretical total water demand based on the target outlet moisture content and dry basis mass flow rate, including: Step S1.1: Collect the incoming material flow rate, inlet moisture, inlet temperature, material layer thickness, and conveying speed of the re-drying and rehydration section to generate an incoming material data vector; Step S1.2: Collect ambient temperature and humidity, generate an environmental data vector, synchronize the incoming material data vector and the environmental data vector with a unified sampling period, and generate an incoming material status vector. Step S1.3: Calculate the dry basis mass flow rate based on the incoming material flow rate and inlet moisture content in the incoming material state vector; Step S1.4: Calculate the theoretical total water demand based on the target outlet moisture content and the dry basis mass flow rate.

[0012] Beneficial effects of steps S1.1 to S1.4: This series of steps addresses the issues of asynchronous and incomplete data collection between incoming material and environmental data during the re-drying and rehydration stage. By synchronizing the incoming material and environmental data according to a unified sampling period to generate an incoming material status vector, a time-aligned and dimensionally complete input benchmark is provided for calculating the theoretical total water demand.

[0013] Specifically, step S1.1 generates an incoming material data vector by collecting data on incoming material flow rate, inlet moisture, inlet temperature, material layer thickness, and conveying speed, covering full-dimensional information on the material state; step S1.2 synchronizes the incoming material data vector and the environmental data vector with a unified sampling period to eliminate calculation deviations introduced by timestamp misalignment; step S1.3 calculates the dry basis mass flow rate by extracting the incoming material flow rate and inlet moisture from the incoming material state vector, establishing the water addition requirement calculation on the material dry basis mass benchmark; step S1.4 calculates the theoretical total water addition requirement using the target outlet moisture and dry basis mass flow rate, providing an accurate total input for subsequent coupled projection.

[0014] As a further improvement to this application, step S2 involves constructing a feature vector of atomization capability for each zone based on the joint relationship between the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure, and droplet size. This transforms the atomization quality constraints of each zone into a feasible atomization domain, and outputs the boundaries of the feasible atomization domains for each zone, including: Step S2.1: Calculate the number of effective nozzles in each zone based on the pump frequency and the number of nozzle island combinations; Step S2.2: Calculate the single nozzle flow rate of each zone based on the effective number of nozzles and the zone pressure; Step S2.3: Estimate the droplet size of each zone based on the zone pressure and the number of effective nozzles; Step S2.4: Based on the theoretical total water demand, the flow rate of a single nozzle in each zone, and the droplet size in each zone, construct the atomization capability feature vector for each zone; Step S2.5: Based on the atomization capability feature vector of each region, the atomization quality constraint of each region is transformed into atomization feasible region, and the boundary of the atomization feasible region of each region is output.

[0015] Beneficial effects of steps S2.1 to S2.5: This series of steps addresses the problem of atomization deterioration under low flow conditions caused by post-verification of atomization quality constraints in the re-drying and re-moistening water addition control. By modeling the joint relationship between pump frequency, number of nozzle island combinations, zone pressure, and droplet size as the atomization feasible domain for each zone, the atomization conditions are elevated from post-verification to a pre-calcifiable capability boundary, providing an executable constraint space for subsequent coupled projection.

[0016] Specifically, step S2.1 calculates the effective number of nozzles in each zone using pump frequency and the number of nozzle island combinations, quantifying the currently available nozzle resources in each zone; step S2.2 calculates the single nozzle flow rate in each zone using the effective number of nozzles and zone pressure, establishing a mapping relationship between the number of nozzles and flow rate; step S2.3 estimates the droplet size in each zone using zone pressure and effective number of nozzles, incorporating atomization quality indicators into a calculable parameter system; step S2.4 constructs an atomization capability feature vector by integrating the theoretical total water supply demand, the single nozzle flow rate in each zone, and the droplet size in each zone, unifying water supply demand and atomization capability into the same feature space; and step S2.5 transforms atomization quality constraints into a feasible atomization domain and outputs the feasible domain boundary, providing explicit executable constraint boundaries for subsequent coupled projection.

[0017] As a further improvement to this application, in step S3, the theoretical total water demand is coupled and projected according to the boundaries of the feasible atomization domains of each region. When the theoretical total water demand falls outside the feasible atomization domain of a certain region, the excess water demand of that region is redistributed to the feasible domains of adjacent regions, and the coupled feasible water supply ranges of each region are output, including: Step S3.1: Allocate the theoretical total water demand to the initial water demand of each zone according to the basic process weights of the four zones; Step S3.2: Project the initial water demand of each zone according to the boundary of the atomization feasible domain of each zone, and determine whether the initial water demand of each zone falls within the atomization feasible domain of the corresponding zone. Step S3.3: When the initial water demand of a certain area falls outside the feasible atomization domain of the corresponding area, calculate the excess water demand of that area. Step S3.4: The excess water demand is redistributed to the feasible atomization domain of the adjacent area, the water demand after projection of each area is integrated, and the coupled feasible water supply range of each area is output.

[0018] Beneficial effects of steps S3.1 to S3.4: This series of steps addresses the issues in the control of water addition during re-drying and re-moistening where a fixed ratio allocation does not consider the differences in atomization capabilities between different zones, and the lack of an adjustment mechanism when the water addition demand in a certain zone falls into the atomization dead zone. By coupling the initial water addition demand to the boundary of the atomization feasible domain and redistributing the excess portion to adjacent zones, dynamic matching of water addition demand and atomization capability is achieved.

[0019] Specifically, step S3.1 establishes the initial allocation benchmark for water supply tasks in each zone by allocating the theoretical total water supply demand to the initial water supply demand of each zone according to the basic process weights of the four zones; step S3.2 identifies the mismatch between water supply demand and atomization capability by projecting the initial water supply demand of each zone onto the corresponding zone's atomization feasible domain and determining whether it falls within the feasible domain; step S3.3 quantifies the atomization capability gap in each zone by calculating the excess water supply demand that falls outside the feasible domain; and step S3.4 outputs the coupled feasible water supply range by redistributing the excess water supply demand to the feasible domains of adjacent zones and integrating the projected water supply demand of each zone, thereby eliminating the impact of atomization dead zones on water supply accuracy.

[0020] As a further improvement to this application, in step S4, within the feasible water addition range of each zone, collaborative optimization is performed with the dual objectives of minimizing water addition deviation and optimizing atomization quality, outputting water addition commands and atomization control commands for each zone, including: Step S4.1: Construct a water addition deviation objective function based on the feasible water addition range of each zone and the initial water addition requirement of each zone; Step S4.2: Construct an atomization quality objective function based on the droplet size deviation and zone pressure fluctuation corresponding to the boundary of the feasible atomization domain in each zone; Step S4.3: Perform weighted collaborative optimization on the objective function of water addition deviation and the objective function of atomization quality to obtain the optimal water addition flow rate and the optimal atomization parameters for each zone; Step S4.4: Generate water supply instructions for each zone based on the optimal water supply flow rate for each zone, and generate atomization control instructions for each zone based on the optimal atomization parameters for each zone.

[0021] Beneficial effects of steps S4.1 to S4.4: This series of steps addresses the problem that the sequential solution of water addition deviation and atomization quality in the re-drying and re-humidification water addition control leads to a coupling contradiction that cannot be simultaneously addressed. By constructing water addition deviation objective functions and atomization quality objective functions and performing weighted collaborative optimization, the water addition commands and atomization control commands of each zone can be solved simultaneously within the range of feasible water addition, eliminating the iteration loss of adding water first and then verifying in the serial architecture.

[0022] Specifically, step S4.1 constructs a water addition deviation objective function by coupling the feasible water addition range of each zone with the initial water addition demand of each zone, and quantifies the degree of deviation between the control output and the initial demand; step S4.2 constructs an atomization quality objective function by constructing the droplet size deviation and zone pressure fluctuation, and quantifies the atomization quality level corresponding to the control output; step S4.3 obtains the optimal water addition flow rate and the optimal atomization parameters of each zone by performing weighted collaborative optimization on the dual objective function, and realizes the synchronous optimization of water addition accuracy and atomization quality; step S4.4 generates water addition commands by generating the optimal water addition flow rate of each zone and atomization control commands by generating the optimal atomization parameters of each zone, and outputs directly executable dual objective collaborative control commands.

[0023] As a further improvement to this application, step S5, predicting future outlet moisture and outlet temperature based on water addition commands and atomization control commands for each zone, using the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable true outlet value, updating the online deviation corrector with the delayed-arriving true detection value, and correcting the water addition commands and atomization control commands for each zone based on the online deviation corrector, including: Step S5.1: Construct a control input sequence based on the water addition instructions and atomization control instructions for each zone; Step S5.2: Predict future outlet moisture content and future outlet temperature based on the control input sequence; Step S5.3: Using the predicted outlet moisture content as a virtual feedback value, calculate the prediction deviation between the virtual feedback value and the target outlet moisture content; Step S5.4: Update the online deviation corrector using the residual between the delayed actual detection value and the corresponding predicted value; Step S5.5: Based on the online deviation corrector and the predicted deviation, correct the water addition command and the atomization control command for each zone.

[0024] Beneficial effects of steps S5.1 to S5.5: This series of steps addresses the problem of delayed control deviation correction caused by the large time delay from the inlet to the outlet detection position in the re-drying and re-humidification section and the unavailability of the outlet moisture content in the current period. By constructing a control input sequence to predict future outlet indicators and using virtual feedback values ​​to replace the actual detection values ​​for online deviation correction, a forward-looking feedback control under large time delay conditions is achieved.

[0025] Specifically, step S5.1 constructs a control input sequence by using water addition commands and atomization control commands for each zone, integrating the dispersed control commands into a time-sequential predictive input; step S5.2 predicts future outlet moisture and future outlet temperature using the control input sequence, obtaining forward-looking estimates of outlet indicators in advance; step S5.3 quantifies the expected deviation of the current control strategy by calculating the predicted deviation between the virtual feedback value and the target outlet moisture; step S5.4 updates the online deviation corrector by using the residual between the delayed arrival of the actual detection value and the corresponding predicted value, eliminating the systematic deviation of the prediction model; and step S5.5 corrects the water addition commands and atomization control commands for each zone using the online deviation corrector and the predicted deviation, achieving closed-loop adaptive correction of the control strategy.

[0026] As a further improvement to this application, step S6 involves performing safety checks and downgrading on the revised water addition commands and atomization control commands for each zone based on the operating condition labels and fault diagnosis results, outputting the final control commands, and issuing them for execution, including: Step S6.1: Generate working condition labels based on material location and material occupation status. The working condition labels include four categories: material head, steady state, material tail, and empty material. Step S6.2: Generate fault diagnosis results based on the zone pressure residual and nozzle flow residual; Step S6.3: Perform a safety check on the corrected water filling instructions and atomization control instructions for each zone based on the operating condition label and the fault diagnosis results; Step S6.4: When the safety check fails, downgrade the water addition command and atomization control command for each zone that failed. Step S6.5: Integrate the water filling instructions and atomization control instructions of each zone that have passed the safety verification, as well as the water filling instructions and atomization control instructions of each zone after downgrading, and output the final control instructions and issue them for execution.

[0027] Beneficial effects of steps S6.1 to S6.5: This series of steps addresses the issues of lack of differentiated verification of control commands during the switching between the beginning and end of the re-drying and rehydration stages and under empty material conditions, as well as the lack of a degradation mechanism when equipment malfunctions, which leads to the risk of non-compliance. By using operating condition labels and fault diagnosis results, control commands are safely verified and downgraded to ensure control safety under abnormal operating conditions.

[0028] Specifically, step S6.1 generates four types of operating condition labels—material head, steady state, material tail, and empty material—based on material location and material occupation status, providing a benchmark for operating condition identification for differentiated control; step S6.2 generates fault diagnosis results based on zone pressure residuals and nozzle flow residuals, enabling automatic identification of equipment anomalies; step S6.3 performs safety checks on the corrected water addition commands and atomization control commands for each zone based on the operating condition labels and fault diagnosis results, intercepting control commands that do not meet safety conditions; step S6.4 downgrades commands that fail the check, maintaining basic control capabilities under abnormal operating conditions; and step S6.5 integrates the checked and downgraded commands to output the final control command and issue it for execution, ensuring the completeness and executability of the issued command.

[0029] To achieve the above objectives, this application also provides the following technical solutions: A coordinated water-addition control device for re-drying and rehydration, wherein the coordinated water-addition control device is applied to the coordinated water-addition control method described above, and the coordinated water-addition control device comprises: The theoretical total water demand calculation module is used to collect incoming material data and environmental data of the re-drying and rehydration section, calculate the dry basis mass flow rate based on incoming material flow rate, inlet moisture and inlet temperature, and calculate the theoretical total water demand based on the target outlet moisture and dry basis mass flow rate. The atomization feasible domain boundary acquisition module is used to construct the atomization capability feature vector of each zone based on the joint relationship of the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure and droplet size, transform the atomization quality constraints of each zone into atomization feasible domain, and output the atomization feasible domain boundary of each zone. The coupled feasible water supply range acquisition module is used to couple the theoretical total water supply demand according to the boundary of the atomization feasible domain of each zone. When the theoretical total water supply demand falls outside the atomization feasible domain of a certain zone, the water supply demand exceeding the boundary of that zone is redistributed to the feasible domain of the adjacent zone, and the coupled feasible water supply range of each zone is output. The collaborative instruction acquisition module is used to perform collaborative optimization within the feasible water addition range of each zone, with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and output water addition instructions and atomization control instructions for each zone. The collaborative instruction correction module is used to predict the future outlet moisture and outlet temperature based on the water addition instructions and atomization control instructions of each zone, and to use the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable real outlet value. The online deviation corrector is updated by the delayed real detection value, and the water addition instructions and atomization control instructions of each zone are corrected based on the online deviation corrector. The final control command issuance module is used to perform safety verification and downgrade processing on the corrected water addition commands and atomization control commands for each zone based on the operating condition labels and fault diagnosis results, and outputs the final control command for execution.

[0030] To achieve the above objectives, this application also provides the following technical solutions: An electronic device includes a processor and a memory coupled to the processor, the memory storing program instructions executable by the processor; when the processor executes the program instructions stored in the memory, it implements the above-described coordinated water addition control method for reheating and rehydration.

[0031] To achieve the above objectives, this application also provides the following technical solutions: A computer-readable storage medium storing program instructions, which, when executed by a processor, enable the implementation of the aforementioned coordinated water addition control method for reheating and rehydration. Attached Figure Description

[0032] Figure 1 This is a schematic flowchart illustrating the steps of an embodiment of the synergistic water addition control method for re-drying and rehydration according to this application; Figure 2 This is a schematic diagram of the functional modules of a collaborative water addition control device for re-drying and rehydration according to an embodiment of this application; Figure 3 This is a schematic diagram of the structure of an embodiment of the electronic device of this application; Figure 4 This is a schematic diagram of the structure of one embodiment of the storage medium of this application. Detailed Implementation

[0033] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of the embodiments. Based on the embodiments of this application, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of this application.

[0034] The terms "first," "second," and "third" in this application are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Therefore, a feature defined as "first," "second," or "third" may explicitly or implicitly include at least one of that feature. In the description of this application, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified. All directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of this application are only used to explain the relative positional relationships and movements between components in a specific orientation (e.g., as shown in the figures). If the specific orientation changes, the directional indications also change accordingly. Furthermore, the terms "comprising" and "having," and any variations thereof, are intended to cover non-exclusive having. For example, a process, method, system, product, or device having a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units not listed, or may optionally include other steps or units inherent to these processes, methods, products, or devices.

[0035] In this document, the term "embodiment" means that a particular feature, structure, or characteristic described in connection with an embodiment may be present in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a mutually exclusive, independent, or alternative embodiment. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.

[0036] It should be noted that, due to the limited types and number of symbols or letters that can represent specific meanings, for embodiments with many formulas or codes, there may be situations where symbols or letters cannot meet the usage requirements. Therefore, the interpretation of formula symbols in the steps or sub-steps of the embodiments is only valid for the current step or sub-step.

[0037] If the same symbol has different interpretations in different steps or sub-steps, the interpretation in the current step or sub-step shall prevail; if the same symbol appears in different steps or sub-steps, but no interpretation is given in subsequent steps or sub-steps after its first appearance, the interpretation in the first step or sub-step shall be used.

[0038] For example, "i=1,2,...,n" is a writing convention and a well-known meaning. If "i=1,2,...,n" has already appeared once in an embodiment and needs to be used again in formulas with different scenarios and meanings in the future, then the meaning of "i=1,2,...,n" should be interpreted according to the corresponding formulas. If "i=1,2,...,n" is not used for the first time and is changed to a symbol or letter with a non-well-known meaning, such as "p=1,2,...,q", to avoid repetition, it is more likely to cause confusion, ambiguity, and unclear problems.

[0039] like Figure 1 As shown, this embodiment provides an example of a synergistic water addition control method for re-drying and rehydration. In this embodiment, the synergistic water addition control method includes the following steps: Step S1: Collect incoming material data and environmental data for the re-drying and rehydration section. Calculate the dry basis mass flow rate based on the incoming material flow rate, inlet moisture content, and inlet temperature. Calculate the theoretical total water demand based on the target outlet moisture content and dry basis mass flow rate.

[0040] Furthermore, step S1 specifically includes the following steps: Step S1.1: Collect the incoming material flow rate, inlet moisture, inlet temperature, material layer thickness, and conveying speed of the re-drying and rehydration section to generate an incoming material data vector.

[0041] Preferably, the core of this step is to collect and vectorize the incoming material data. By deploying a weighing belt scale, near-infrared moisture meter, infrared thermometer, material layer thickness sensor and conveyor speed encoder at the entrance of the rehydration section, the state parameters of the material when it enters the rehydration section are collected simultaneously, providing material reference data for subsequent calculation of theoretical total water addition requirements.

[0042] For the incoming material flow rate, a weighing belt scale is used to collect the mass of material passing through the belt conveyor per unit time in real time, which is recorded as follows: The unit is kilograms per second (kg / s), and the recommended sampling interval is 1 second.

[0043] For the inlet moisture content, a near-infrared moisture meter was used to measure the surface moisture content of the material in a non-contact manner, denoted as . Expressed as a percentage by mass, the recommended range is [range to be specified]. The recommended sampling interval is 2 seconds.

[0044] For the inlet temperature, an infrared thermometer is used to measure the material surface temperature non-contactly, denoted as . The unit is Celsius (°C) C), the recommended range of values ​​is: The recommended sampling interval is 2 seconds.

[0045] For the material layer thickness, a material layer thickness sensor is used to measure the height of the material accumulation on the belt conveyor, denoted as . The unit is millimeters (mm), and the recommended range of values ​​is [range to be filled in]. The recommended sampling interval is 5 seconds.

[0046] For the conveying speed, an incremental encoder is used to measure the linear speed of the belt conveyor, denoted as . The unit is meters per second (m / s), and the recommended range of values ​​is [missing value]. The recommended sampling interval is 1 second.

[0047] Specifically, regarding the organization of the incoming material data vector, the aforementioned five-dimensional parameters are arranged in a fixed order, denoted as... It is updated once per sampling period.

[0048] Preferably, the sampling interval for incoming material flow rate is 1 second, the sampling interval for inlet moisture and inlet temperature is 2 seconds, the sampling interval for material layer thickness is 5 seconds, and the sampling interval for conveying speed is 1 second.

[0049] For example, at time YYYY-MM-DD-HH:MM:SS-001, a batch of tobacco leaves enters the rehydration stage, and the incoming flow rate is... kg / s, inlet moisture Inlet temperature C, Material layer thickness mm, conveying speed m / s, incoming material data vector The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-002.

[0050] Step S1.2: Collect ambient temperature and humidity data to generate an environmental data vector. Synchronize the incoming material data vector and the environmental data vector with a unified sampling period to generate an incoming material status vector.

[0051] Preferably, the core of this step is to complete environmental data acquisition and multi-source data synchronization. Environmental parameters are collected by temperature and humidity sensors deployed in the rehumidification workshop, and the incoming material data vector and environmental data vector are aligned with a unified sampling period to eliminate calculation deviations caused by timestamp misalignment.

[0052] For ambient temperature, the ambient air temperature in the rehumidification section is collected using a workshop temperature and humidity transmitter and denoted as . The unit is Celsius (°C) C), the recommended range of values ​​is: The recommended sampling interval is 10 seconds.

[0053] For ambient humidity, the same temperature and humidity transmitter was used to collect the relative humidity of the ambient air during the humidification period, denoted as . Expressed as a percentage, the recommended range of values ​​is [value range missing]. The recommended sampling interval is 10 seconds.

[0054] The organization of environmental data vectors is denoted as follows: .

[0055] Among them, for multi-source data synchronization, due to the incoming material data vector The sampling intervals for each dimension are inconsistent (from 1 second to 5 seconds), and the environmental data vector The sampling interval is 10 seconds, and all dimensions need to be unified to the same sampling period. It is recommended to take... seconds, for sampling intervals less than The dimension is taken from the last sampled value of each period, for sampling intervals greater than 1000. The dimensions are filled with the most recent sampled value.

[0056] Specifically, the organization of the incoming material status vector involves concatenating the synchronized incoming material data vector with the environmental data vector, denoted as... The dimension is 7.

[0057] Preferably, a uniform sampling period is used. The recommended sampling interval is 5 seconds, and the recommended sampling interval for ambient temperature and ambient humidity is 10 seconds.

[0058] For example, receiving the aforementioned incoming material data vector Ambient temperature within the same sampling period C, Ambient humidity Synchronous material state vector The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-003.

[0059] Step S1.3: Calculate the dry basis mass flow rate based on the incoming material flow rate and inlet moisture content in the incoming material state vector.

[0060] Preferably, the core of this step is to calculate the dry mass flow rate. By extracting the incoming flow rate and inlet moisture from the incoming material state vector, and removing the moisture mass from the material, the dry matter mass flow rate is obtained, providing a moisture-free material basis for calculating the theoretical total water demand.

[0061] Specifically, the calculation of dry basis mass flow rate is based on the incoming material state vector. Extracting incoming material flow and inlet moisture Dry basis mass flow rate The calculation formula is: .

[0062] in, This refers to the incoming material flow rate, expressed in kg / s. For the inlet moisture content, substitute it in decimal form (e.g., ...). Substitution ); This is the dry basis mass flow rate, expressed in kg / s.

[0063] Preferably, the inlet moisture When substituting into the calculation, the percentage must be converted to decimal form, i.e., divided by 100.

[0064] For example, receiving the above-mentioned incoming material status vector Incoming material flow kg / s, inlet moisture Dry basis mass flow rate kg / s, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-004.

[0065] Step S1.4: Calculate the theoretical total water demand based on the target outlet moisture content and dry basis mass flow rate.

[0066] Preferably, the core of this step is to calculate the theoretical total water demand. Based on the difference between the target outlet moisture and the inlet moisture, and combined with the dry basis mass flow rate, the amount of water to be added per unit time is calculated, providing a total baseline for the subsequent construction of the atomization feasible domain and coupling projection.

[0067] Specifically, the target outlet moisture content is set according to the process formula, and is denoted as . Expressed as a percentage by mass, the recommended range is [range to be specified]. Different brands of tobacco have different set values.

[0068] The calculation of the theoretical total water demand is based on the dry basis mass flow rate. , entrance moisture and target export moisture Theoretical total water demand The calculation formula is: .

[0069] in, The theoretical total water demand is expressed in kg / s. Dry basis mass flow rate; The target export moisture content is substituted into the decimal form; The inlet water content is substituted as a decimal.

[0070] Preferably, the target export moisture content When substituting into the calculation, the percentage must be converted to decimal form. The theoretical total water demand... A positive value indicates that water needs to be added, while a negative value indicates that dehydration is required (in the rehydration stage, only water is usually added, and a negative value is taken as 0).

[0071] For example, receiving the above-mentioned dry basis mass flow rate kg / s, inlet moisture Target export moisture Theoretical total water demand kg / s, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-005.

[0072] Beneficial effects of steps S1.1 to S1.4: This series of steps addresses the issues of asynchronous and incomplete data collection between incoming material and environmental data during the re-drying and rehydration stage. By synchronizing the incoming material and environmental data according to a unified sampling period to generate an incoming material status vector, a time-aligned and dimensionally complete input benchmark is provided for calculating the theoretical total water demand.

[0073] Specifically, step S1.1 generates an incoming material data vector by collecting data on incoming material flow rate, inlet moisture, inlet temperature, material layer thickness, and conveying speed, covering full-dimensional information on the material state; step S1.2 synchronizes the incoming material data vector and the environmental data vector with a unified sampling period to eliminate calculation deviations introduced by timestamp misalignment; step S1.3 calculates the dry basis mass flow rate by extracting the incoming material flow rate and inlet moisture from the incoming material state vector, establishing the water addition requirement calculation on the material dry basis mass benchmark; step S1.4 calculates the theoretical total water addition requirement using the target outlet moisture and dry basis mass flow rate, providing an accurate total input for subsequent coupled projection.

[0074] Step S2: Construct the atomization capability feature vector for each zone based on the combined relationship of theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure, and droplet size. Transform the atomization quality constraints of each zone into atomization feasible regions and output the boundary of the atomization feasible region for each zone.

[0075] Furthermore, step S2 specifically includes the following steps: Step S2.1: Calculate the number of effective nozzles in each zone based on the pump frequency and the number of nozzle island combinations.

[0076] Preferably, the core of this step is to calculate the number of effective nozzles in each zone. By obtaining the current operating frequency of the dual plunger pump and the operational status of the nozzle island combination in each zone, the actual number of effective nozzles that can participate in atomization in each zone is calculated, providing a nozzle resource base for subsequent calculations of single nozzle flow rate and droplet size.

[0077] Among them, the operating frequency of the dual-plunger pump is denoted as: The unit is Hertz (Hz), and the recommended range of values ​​is [range missing]. Hz, the two pumps can operate at the same frequency or operate at different frequencies.

[0078] Regarding the number of sprinkler island combinations, ten sets of sprinkler islands are deployed in the four zones of the backflow section, arranged in a 2:3:3:2 ratio across the four zones, with one set in zone one. Zone 2 is The three zones are The fourth district is Each nozzle island group contains several nozzles; the number of nozzle island groups currently in operation is denoted as [number missing]. ,in For partition numbering, .

[0079] The calculation of the effective number of nozzles is based on the pump frequency. Determine the rated flow rate of a single pump The relationship between the rated flow rate of a single pump and the pump frequency is as follows: ,in This is the pump displacement coefficient, expressed in liters per revolution (L / r). The total flow rate of the two pumps is... Number of effective sprinklers in each zone Based on the number of nozzle island groups in operation in this area Number of nozzles in each nozzle island Sure: .

[0080] Preferably, the pump displacement coefficient It is recommended to determine the number of nozzles in each nozzle island based on the pump model's calibration parameters. Recommended to indivual.

[0081] For example, at time YYYY-MM-DD-HH:MM:SS-006, the operating frequency of the dual-plunger pump is... Hz, Zone 1 nozzle island put into operation There are 2 groups in total, and the number of nozzles in each group's nozzle island is... Number of effective sprinklers in Zone 1 One; Zone 2 put into operation There are 3 groups in total, with a total of [number] effective nozzles. One; three zones put into operation There are 3 groups in total, with a total of [number] effective nozzles. One; four districts put into operation There is 1 group in total, with a total of [number] effective nozzles. There is one, and the corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-007.

[0082] Step S2.2: Calculate the flow rate of a single nozzle in each zone based on the number of effective nozzles and the zone pressure.

[0083] Preferably, the core of this step is to calculate the flow rate of a single sprinkler head in each zone. By using the relationship between the number of effective sprinklers and the total water supply of the zone, the actual flow rate of a single sprinkler head is calculated, providing flow rate input for droplet size estimation.

[0084] For the zone pressure, the water supply pipeline pressure of each zone is denoted as: The unit is megapascals (MPa), and the recommended range of values ​​is [range missing]. MPa, collected in real time by pressure sensors in each zone.

[0085] Specifically, for calculating the flow rate of a single sprinkler head, the water supply flow rate for each zone is allocated proportionally according to the total pump flow rate, denoted as... Single nozzle flow rate The calculation formula is: .

[0086] in, For partitioning The water supply flow rate is expressed in liters per minute (L / min). For partitioning The number of effective nozzles; For partitioning The flow rate per nozzle is expressed in liters per minute (L / min).

[0087] Among them, the allocation of water supply flow by zone, the water supply flow by zone The total pump flow rate is allocated based on the proportion of the effective nozzles in this zone to the total effective nozzles in all four zones: .

[0088] Preferably, zone pressure The recommended range of values ​​is: MPa, high-pressure atomization conditions recommended are MPa.

[0089] For example, accepting the above-mentioned number of effective nozzles , , , Total number of effective nozzles Total pump flow L / min, water supply flow rate in one district L / min, flow rate per nozzle L / min, zone pressure MPa, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-008.

[0090] Step S2.3: Estimate the droplet size of each zone based on the zone pressure and the number of effective nozzles.

[0091] Preferably, the core of this step is to estimate the droplet size of each zone, establish a droplet size estimation model by using the relationship between zone pressure and single nozzle flow rate, and incorporate atomization quality indicators into a calculable parameter system.

[0092] For droplet size estimation, a droplet size estimation model based on pressure-flow experience is used, with the droplet size being the Sauter mean diameter. The estimation formula is: .

[0093] in, For partitioning The average diameter of the fog droplets, in micrometers (µm). m); This refers to the flow rate per nozzle. For partition pressure; , , The calibration coefficient for the nozzle model is obtained by fitting test data from the nozzle manufacturer.

[0094] Preferably, the average diameter of the Sotter is... The recommended range of values ​​is: m, the recommended threshold for acceptable atomization quality is... m, coefficient , , It is recommended to calibrate according to the nozzle model.

[0095] For example, receiving the above-mentioned single nozzle flow rate L / min and zone pressure MPa, nozzle calibration coefficient , , Droplet size in Zone 1 m corresponds to the timestamp record YYYY-MM-DD-HH:MM:SS-009.

[0096] Step S2.4: Construct the atomization capability feature vector for each zone based on the theoretical total water demand, the flow rate of a single nozzle in each zone, and the droplet size in each zone.

[0097] Preferably, the core of this step is to construct the atomization capability feature vector of each zone, unifying the three types of parameters—theoretical total water demand, single nozzle flow rate, and droplet size—into the same feature space, providing multi-dimensional input for the conversion of the atomization feasible domain.

[0098] Among them, the construction of the atomization capability feature vector will incorporate the theoretical total water addition requirement. Single nozzle flow rate in each zone Droplet size in each region By partition combination, the first The atomization capability feature vector of the region is denoted as: .

[0099] in, This represents the theoretical total water demand. For partitioning Single nozzle flow rate; For partitioning The droplet size; For partitioning The number of effective nozzles; For partitioning The partitioning pressure is such that the feature vector dimension is 5.

[0100] Preferably, the atomization capability feature vector has a dimension of 5, and the parameters of each dimension must be taken within the same sampling period.

[0101] For example, based on the above parameters, the theoretical total water demand is... kg / s, flow rate of a single nozzle in Zone 1 L / min, droplet size m, number of effective nozzles Partition pressure MPa, eigenvector of atomization capability in Zone 1 The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-010.

[0102] Step S2.5: Based on the atomization capability feature vector of each region, the atomization quality constraint of each region is transformed into atomization feasible region, and the boundary of the atomization feasible region of each region is output.

[0103] Preferably, the core of this step is to construct and output the feasible domain of atomization. By transforming the atomization quality constraints into the executable range of water flow rate and zone pressure in each zone, the atomization conditions are upgraded from post-verification to pre-calcifiable capability boundaries.

[0104] Among them, the constraints on atomization quality include three constraints: First, droplet size constraint. ,in The upper limit of the acceptable particle size for atomization quality; second, zoned pressure constraints. ,in and For partitioning Pressure upper and lower limits; third, single nozzle flow constraints. ,in and These are the upper and lower limits of the flow rate for a single nozzle.

[0105] Specifically, in constructing the feasible atomization region, the above three constraints are transformed into partitions. Water flow rate With partition pressure Two-dimensional feasible region : .

[0106] in, For partitioning Water flow rate; The droplet size is a function of the water flow rate and the zone pressure; For partitioning The feasible domain for atomization.

[0107] Among them, for the boundary of the atomization feasible region, the feasible region will be The boundary is denoted as Including the upper limit of water supply flow rate Lower limit of water flow rate Upper limit of pressure Lower limit of pressure The output is the boundary vector of the feasible atomization region for each region. .

[0108] Preferably, the upper limit of the qualified particle size for atomization quality is... The recommended value is 80. m, lower limit of single nozzle flow rate The recommended speed is 0.05 L / min, with an upper limit of [missing information]. The recommended flow rate is 0.5 L / min.

[0109] For example, the atomization capability feature vector of the above-mentioned region. Zone 1 pressure constraint MPa MPa, upper limit of particle size m, single nozzle flow constraint L / min, L / min, calculate the boundary of the feasible atomization region in zone one. That is, the water flow rate range of Zone 1 is 0.6 to 3.6 L / min, the zone pressure range is 5 to 10 MPa, and the corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-011.

[0110] Beneficial effects of steps S2.1 to S2.5: This series of steps addresses the problem of atomization deterioration under low flow conditions caused by post-verification of atomization quality constraints in the re-drying and re-moistening water addition control. By modeling the joint relationship between pump frequency, number of nozzle island combinations, zone pressure, and droplet size as the atomization feasible domain for each zone, the atomization conditions are elevated from post-verification to a pre-calcifiable capability boundary, providing an executable constraint space for subsequent coupled projection.

[0111] Specifically, step S2.1 calculates the effective number of nozzles in each zone using pump frequency and the number of nozzle island combinations, quantifying the currently available nozzle resources in each zone; step S2.2 calculates the single nozzle flow rate in each zone using the effective number of nozzles and zone pressure, establishing a mapping relationship between the number of nozzles and flow rate; step S2.3 estimates the droplet size in each zone using zone pressure and effective number of nozzles, incorporating atomization quality indicators into a calculable parameter system; step S2.4 constructs an atomization capability feature vector by integrating the theoretical total water supply demand, the single nozzle flow rate in each zone, and the droplet size in each zone, unifying water supply demand and atomization capability into the same feature space; and step S2.5 transforms atomization quality constraints into a feasible atomization domain and outputs the feasible domain boundary, providing explicit executable constraint boundaries for subsequent coupled projection.

[0112] Step S3: Couple the theoretical total water demand according to the boundary of the atomization feasible domain of each zone. When the theoretical total water demand falls outside the atomization feasible domain of a certain zone, redistribute the excess water demand of that zone to the feasible domain of the adjacent zone, and output the coupled feasible water supply range of each zone.

[0113] Furthermore, step S3 specifically includes the following steps: Step S3.1: Allocate the theoretical total water demand to the initial water demand of each zone according to the basic process weights of the four zones.

[0114] Preferably, the core of this step is to complete the initial allocation of the theoretical total water demand, set the basic process weights according to the process responsibilities of the four zones, allocate the theoretical total water demand to each zone according to the weights, and establish the initial allocation benchmark for the water supply tasks of each zone.

[0115] Among them, the basic process weights for the four zones are divided into the pre-humidification zone, the main humidification zone 1, the main humidification zone 2, and the terminal fine-tuning zone according to their process responsibilities, and the corresponding basic process weights are denoted as follows: ,satisfy The pre-humidification zone is responsible for raising the material temperature to promote moisture absorption, while the main humidification zones one and two handle the main water addition. The final fine-tuning zone makes precise adjustments to the final moisture content.

[0116] Among them, the calculation of the initial water supply demand for each district, and the theoretical total water supply demand. The initial water demand for each zone is allocated according to the weight of the basic processes. The calculation formula is: .

[0117] in, This represents the theoretical total water demand. For partitioning Basic process weight; For partitioning The initial water requirement is expressed in kg / s.

[0118] Preferably, the recommended weights for the basic processes in the four zones are as follows: The specific weight can be adjusted according to the brand's process formula.

[0119] For example, to meet the total theoretical water demand mentioned above. kg / s, weight of basic processes in four zones Initial water supply demand in each district kg / s, kg / s, kg / s, kg / s, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-012.

[0120] Step S3.2: Project the initial water demand of each zone according to the boundary of the atomization feasible domain of each zone, and determine whether the initial water demand of each zone falls within the atomization feasible domain of the corresponding zone.

[0121] Preferably, the core of this step is to complete the feasible domain projection and boundary judgment of the initial water addition requirement, compare the initial water addition requirement of each area with the boundary of the corresponding atomization feasible domain, and identify the mismatch area between water addition requirement and atomization capacity.

[0122] For feasible region projection, partitioning is performed. Initial water requirements After conversion to flow rate units, the boundary of the feasible atomization region is... Comparison of water flow rate ranges.

[0123] Among them, for the boundary judgment, if If the initial water demand in the area is lower than the lower bound of the feasible region, it is considered under-allocation; if If the initial water demand in the area exceeds the upper bound of the feasible region, it is considered over-allocation; if If the initial water demand for the area falls within the feasible region, it is considered feasible. The formula for determining boundary violations is: .

[0124] Preferably, when projecting the feasible region, the initial water demand should be standardized to a flow rate unit (L / min) and compared with the feasible region boundary. The unit conversion factor is recommended to be 1 kg / s. 60 L / min.

[0125] For example, the feasible domain boundary that accepts the initial water supply needs of the above-mentioned zones and the output of S2.5, Zone 1 kg / s 1.43 L / min, feasible region L / min, 1.43 falls into Within, it is determined to be feasible; Zone 4 kg / s 1.43 L / min, feasible region in four zones L / min (assuming fewer nozzles and lower pressure in zone four), 1.43 falls into Within this area, it is deemed feasible; assuming zone two... kg / s 3.35 L / min, feasible region in zone two L / min, 3.35>3.0, is determined to be over-allocation, and the corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-013.

[0126] Step S3.3: When the initial water demand of a certain area falls outside the feasible atomization domain of the corresponding area, calculate the excess water demand of that area.

[0127] Preferably, the core of this step is to calculate the excess water demand, quantify the atomization capacity gap of the out-of-bounds zones, and provide the amount of water to be allocated for subsequent redistribution.

[0128] Specifically, for the calculation of water demand exceeding the limit, when the zone... When it is determined to be over-allocation, the excess water demand will be [received / reimbursed]. The calculation formula is: .

[0129] in, For partitioning The excess water demand; For partitioning Initial water requirements; For partitioning The upper limit of the feasible domain for water flow.

[0130] Among them, when partition When an allocation is determined to be under-allocated, the excess portion does not need to be reallocated in that area, but the amount of under-allocation is recorded. This is provided for reference in subsequent collaborative optimization.

[0131] Preferably, the excess water demand A positive value indicates an over-allocation, which must be redistributed to adjacent areas.

[0132] For example, if the above two zones are determined to be over-allocated, the initial water supply demand will be... kg / s 3.35 L / min, upper bound of the feasible region L / min, exceeding the water filling requirement L / min 0.0058 kg / s, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-014.

[0133] Step S3.4: The excess water demand is redistributed to the feasible atomization domain of adjacent zones, the water demand after projection of each zone is integrated, and the coupled feasible water supply range of each zone is output.

[0134] Preferably, the core of this step is to redistribute and couple the output of the excess water volume to the feasible water addition range, transferring the excess water volume of the out-of-bounds zone to the adjacent zone with atomization capacity margin, thereby eliminating the impact of the atomization dead zone on the water addition accuracy.

[0135] For the redistribution of excess water, priority is given to the partition with the largest feasible region margin among adjacent partitions. The feasible region margin of an adjacent partition is defined as the upper bound of its feasible region minus the current initial water supply requirement. .

[0136] in, For partitioning The feasible region margin. If the over-allocation region is region two, and the adjacent regions are regions one and three, calculate the margin separately. and The excess portion will be allocated preferentially to adjacent areas with larger reserves. If the reserves in adjacent areas are insufficient to accommodate the entire excess portion, it will be allocated to multiple adjacent areas proportionally to the reserves.

[0137] Among them, for the output of the coupling feasible water supply range, the water supply demand of each zone after redistribution is denoted as: Integrate into a coupled feasible water addition range vector Each component satisfies .

[0138] Preferably, the excess portion is redistributed to the adjacent area with the largest remaining feasible area. If the remaining area of ​​the adjacent area is insufficient, it is redistributed according to the proportion of the remaining area.

[0139] For example, taking over the portion exceeding the above two zones. L / min, adjacent zone one-zone margin L / min, three-zone margin (Zone 3 is also over-allocated), Zone 1 has sufficient capacity, so the excess 0.35 L / min will be allocated entirely to Zone 1. After allocation... L / min, L / min (take the upper limit) L / min (assuming the upper limit is also taken for the three zones). L / min, feasible water addition range for coupling L / min, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-015.

[0140] Beneficial effects of steps S3.1 to S3.4: This series of steps addresses the issues in the control of water addition during re-drying and re-moistening where a fixed ratio allocation does not consider the differences in atomization capabilities between different zones, and the lack of an adjustment mechanism when the water addition demand in a certain zone falls into the atomization dead zone. By coupling the initial water addition demand to the boundary of the atomization feasible domain and redistributing the excess portion to adjacent zones, dynamic matching of water addition demand and atomization capability is achieved.

[0141] Specifically, step S3.1 establishes the initial allocation benchmark for water supply tasks in each zone by allocating the theoretical total water supply demand to the initial water supply demand of each zone according to the basic process weights of the four zones; step S3.2 identifies the mismatch between water supply demand and atomization capability by projecting the initial water supply demand of each zone onto the corresponding zone's atomization feasible domain and determining whether it falls within the feasible domain; step S3.3 quantifies the atomization capability gap in each zone by calculating the excess water supply demand that falls outside the feasible domain; and step S3.4 outputs the coupled feasible water supply range by redistributing the excess water supply demand to the feasible domains of adjacent zones and integrating the projected water supply demand of each zone, thereby eliminating the impact of atomization dead zones on water supply accuracy.

[0142] Step S4: Within the feasible water addition range of each zone, perform collaborative optimization with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and output water addition commands and atomization control commands for each zone.

[0143] Furthermore, step S4 specifically includes the following steps: Step S4.1: Construct a water addition deviation objective function based on the feasible water addition range of each zone and the initial water addition requirement of each zone.

[0144] Preferably, the core of this step is to construct the objective function of water addition deviation. By quantifying the degree of deviation between the actual water addition flow rate and the initial water addition demand in each area, it provides an objective item for the water addition accuracy dimension for dual-objective collaborative optimization.

[0145] Among them, the objective function for water addition deviation is the actual water addition flow rate within the feasible water addition range of each zone. With initial water demand The objective function is constructed from the sum of squared deviations. : .

[0146] in, For partitioning The water flow rate to be optimized is expressed in L / min. For partitioning Initial water requirements; The smaller the value, the closer the actual water flow rate is to the initial demand.

[0147] Among them, for the optimization variable constraints, the water flow rate of each zone The coupling feasible water supply range constraint must be met. ,in and The coupling feasible water addition range from the output of step S3.4.

[0148] Preferably, the objective function for water addition deviation adopts the form of the sum of squared deviations, and the optimized variable is the water addition flow rate in the four zones. .

[0149] For example, the above-mentioned feasible water supply range for coupling. L / min, initial water demand L / min, when taking At that time, the objective function of water addition deviation The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-016.

[0150] Step S4.2: Construct the atomization quality objective function based on the droplet size deviation and zone pressure fluctuation corresponding to the boundary of the feasible atomization domain in each zone.

[0151] Preferably, the core of this step is to construct the atomization quality objective function. By quantifying droplet size deviation and zone pressure fluctuation, it provides target terms for the atomization quality dimension for dual-objective collaborative optimization.

[0152] Among them, for droplet size deviation, zoning The droplet size deviation is defined as the droplet size under the current operating conditions. With respect to the upper limit of qualified particle size for atomization quality Relative deviation: .

[0153] in, For partitioning Current droplet size; This represents the upper limit of the acceptable particle size for atomized quality. When the particle size is qualified, The particle size exceeded the standard.

[0154] Among them, for partition pressure fluctuations, partition Pressure fluctuation is defined as the current pressure With target pressure Deviation: .

[0155] in, For partitioning For the target pressure, it is recommended to take the median value of the feasible pressure range. .

[0156] Specifically, the objective function for atomization quality is constructed by combining droplet size deviation and zone pressure fluctuation. : .

[0157] in, This is the particle size deviation weighting coefficient; This is the pressure fluctuation weighting coefficient; This indicates that penalties are only applied to items with particle size exceeding the standard, while the penalty for items with acceptable particle size is 0. This represents the objective function value for atomization quality; a smaller value indicates better atomization quality.

[0158] Preferably, particle size deviation weight The recommended value is 1.0, with a pressure fluctuation weight. The recommended value is 0.5, and the target pressure should be the midpoint of the feasible pressure range.

[0159] For example, based on the above parameters, the current particle size in zone one m, m, Particle size is within acceptable limits, penalty is 0; Current pressure in Zone 1 MPa, target pressure MPa The pressure remained stable. The current particle size in Zone 2... m (low flow rate condition) Qualified; Pressure MPa MPa MPa, atomization quality objective function The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-017.

[0160] Step S4.3: Perform weighted collaborative optimization on the objective function of water addition deviation and the objective function of atomization quality to obtain the optimal water addition flow rate and the optimal atomization parameters for each zone.

[0161] Preferably, the core of this step is to complete the dual-objective weighted collaborative optimization solution. By weighting and combining the water addition deviation objective function and the atomization quality objective function into a single objective optimization problem, the optimal water addition flow rate and optimal atomization parameters of each zone are solved simultaneously within the coupled feasible water addition range, so as to achieve synchronous optimization of water addition accuracy and atomization quality.

[0162] Among them, for the weighted collaborative objective function, the water addition deviation objective function is... With atomization quality objective function Weighted combination as a collaborative objective function : .

[0163] in, This is the weighting coefficient for water addition deviation; The atomization quality weighting coefficient satisfies ; The value of the collaborative objective function.

[0164] Among the optimization variables are the water flow rates in each zone. and atomization parameters of each zone There are a total of 8 optimization variables.

[0165] For the optimization solution method, the Sequential Quadratic Programming (SQP) method is used under the coupled feasible water addition range constraint, and the optimization variables are iteratively updated until... Convergence is determined by the change in the objective function between two consecutive iterations. ,in This is the convergence threshold.

[0166] Preferably, the water addition deviation weight The recommended value is 0.6, for atomization quality weight. The recommended value is 0.4, which is the convergence threshold. Recommended The maximum number of SQP iterations is recommended to be 100.

[0167] For example, following the above and ,Pick , Initial collaborative objective function After SQP iterative solution converged, the optimal water supply flow rate for each zone was obtained. L / min, optimal atomization parameters for each zone (zone pressure) MPa, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-018.

[0168] Step S4.4: Generate water supply instructions for each zone based on the optimal water supply flow rate for each zone, and generate atomization control instructions for each zone based on the optimal atomization parameters for each zone.

[0169] Preferably, the core of this step is to generate control commands, converting the optimal water flow rate and optimal atomization parameters obtained from the optimization solution into directly executable control commands, which are then output to the subsequent prediction correction and safety verification stages.

[0170] Among these, the generation of water supply instructions for each zone will determine the optimal water supply flow rate. This is converted into pump frequency commands and valve opening commands for each zone. Pump frequency command Based on the total water flow rate and pump displacement coefficient Reverse calculation: .

[0171] in, For partitioning The optimal water flow rate, expressed in L / min; This represents the pump displacement coefficient; the 2 in the denominator indicates a dual-pump system, and 60 is the unit conversion factor. The valve opening degree for each zone is determined based on the ratio of the optimal water supply flow rate to the single sprinkler head flow rate for that zone.

[0172] Among them, the generation of atomization control commands for each zone will use the optimal atomization parameters (zone pressure). This is converted into commands for the opening of pressure regulating valves in each zone and commands for the activation of the nozzle island. The opening of the pressure regulating valves is based on the target pressure. With current pressure The deviation is determined by proportional control; the number of effective sprinklers required for the optimal water flow rate of the area is determined by the combination of sprinkler islands.

[0173] Preferably, the pump frequency command calculation must consider the simultaneous operation of two pumps, and the valve opening command range for each zone is as follows: .

[0174] For example, to receive the above-mentioned optimal water supply flow rate L / min, total water supply flow rate L / min, pump displacement coefficient L / r, pump frequency command Hz – This value is too low, indicating that the pump displacement coefficient or conversion relationship needs to be adjusted. (Assuming...) L / r (miniature plunger pump) Hz, water supply commands for each zone include pump frequency commands. Hz and valve opening in each zone Optimal atomization parameters MPa, atomization control commands for each zone include pressure regulating valve opening. Combined with the operation of the nozzle island The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-019.

[0175] Beneficial effects of steps S4.1 to S4.4: This series of steps addresses the problem that the sequential solution of water addition deviation and atomization quality in the re-drying and re-humidification water addition control leads to a coupling contradiction that cannot be simultaneously addressed. By constructing water addition deviation objective functions and atomization quality objective functions and performing weighted collaborative optimization, the water addition commands and atomization control commands of each zone can be solved simultaneously within the range of feasible water addition, eliminating the iteration loss of adding water first and then verifying in the serial architecture.

[0176] Specifically, step S4.1 constructs a water addition deviation objective function by coupling the feasible water addition range of each zone with the initial water addition demand of each zone, and quantifies the degree of deviation between the control output and the initial demand; step S4.2 constructs an atomization quality objective function by constructing the droplet size deviation and zone pressure fluctuation, and quantifies the atomization quality level corresponding to the control output; step S4.3 obtains the optimal water addition flow rate and the optimal atomization parameters of each zone by performing weighted collaborative optimization on the dual objective function, and realizes the synchronous optimization of water addition accuracy and atomization quality; step S4.4 generates water addition commands by generating the optimal water addition flow rate of each zone and atomization control commands by generating the optimal atomization parameters of each zone, and outputs directly executable dual objective collaborative control commands.

[0177] Step S5: Based on the water addition command and atomization control command of each zone, predict the future outlet moisture and outlet temperature, use the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable real outlet value, update the online deviation corrector with the delayed real detection value, and correct the water addition command and atomization control command of each zone based on the online deviation corrector.

[0178] Furthermore, step S5 specifically includes the following steps: Step S5.1: Construct a control input sequence based on the water addition instructions and atomization control instructions for each zone.

[0179] Preferably, the core of this step is to construct the control input sequence, which integrates the scattered water addition commands and atomization control commands of each zone into a time-series predictive input sequence, providing structured input for predicting future export indicators.

[0180] Specifically, in constructing the control input sequence, each control cycle... Water flow rate in each district and atomization parameters of each zone The control input vectors for this cycle are arranged in partition order. The dimension is 8.

[0181] For time-series sequences, the past is taken. The control input vectors of each control cycle constitute the control input sequence. ,in Index for the current control cycle, This represents the length of the time window.

[0182] Preferably, the time window length The recommended number of control cycles is 32, with each cycle lasting 5 seconds, corresponding to a time window coverage of 160 seconds.

[0183] For example, the water supply flow rate of each zone receiving the output from S4.4. L / min and pressure in each zone MPa, current control cycle control input vector ,Pick , control input sequence It contains the control input vectors for the past 32 cycles, with the corresponding timestamp record being YYYY-MM-DD-HH:MM:SS-020.

[0184] Step S5.2: Predict future outlet moisture and future outlet temperature based on the control input sequence.

[0185] Preferably, the core of this step is to predict future export indicators. By controlling the time delay relationship between the input sequence and the export indicators, forward estimates of the export moisture content and export temperature are obtained in advance, providing a predictive benchmark for deviation correction.

[0186] For the prediction model, a time-series prediction model based on a Long Short-Term Memory (LSTM) network is adopted, with the input being the control input sequence. Output for the future Export moisture forecast after seconds and export temperature forecast ,in This represents the number of control cycles corresponding to the material handling delay. The LSTM network structure includes an input layer, hidden layers, and an output layer. The hidden layer contains... There are LSTM units, and the input layer dimension is [missing information]. The output layer has a dimension of 2.

[0187] Specifically, the predicted values ​​for outlet moisture and outlet temperature in the prediction formula are: .

[0188] in, For LSTM network parameters; To predict the number of delay cycles, , For material conveying delay, To control the cycle, This is for rounding up.

[0189] Preferably, the number of hidden layer units in the LSTM The recommended value is 64, and the predicted latency is... The recommended time is 160 seconds, control period. The recommended time is 5 seconds. One cycle.

[0190] For example, following the above control input sequence The LSTM model predicts the outlet moisture content after 160 seconds. outlet temperature C, Predicting the moisture content at the export point The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-021.

[0191] Step S5.3: Using the predicted outlet moisture content as the virtual feedback value, calculate the prediction deviation between the virtual feedback value and the target outlet moisture content.

[0192] Preferably, the core of this step is to calculate the prediction deviation. By comparing the predicted outlet moisture content with the target outlet moisture content, the expected deviation of the current control strategy is quantified, providing deviation input for subsequent online deviation correction.

[0193] Specifically, the virtual feedback value will predict the moisture content at the outlet. As virtual feedback value This replaces the currently unavailable true export moisture content.

[0194] In calculating the prediction deviation, the virtual feedback value and the target export moisture content are... The deviation is denoted as : .

[0195] in, The prediction deviation is indicated by a positive value, which means the predicted export moisture content is higher than the target, and a negative value, which means it is lower than the target. The unit is percentage.

[0196] Preferably, the prediction bias When the value is positive, the amount of water added should be reduced; when the value is negative, the amount of water added should be increased.

[0197] For example, the above-mentioned predicted export moisture content Target export moisture Prediction bias This indicates that the predicted export moisture content is 0.2 percentage points lower than the target, and the amount of water added needs to be increased appropriately. The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-022.

[0198] Step S5.4: Update the online deviation corrector by the residual between the delayed actual detection value and the corresponding predicted value.

[0199] Preferably, the core of this step is to update the online bias corrector, and to correct the corrector parameters by adjusting the residual between the delayed real detection value and the corresponding predicted value, thereby eliminating the systematic bias of the prediction model.

[0200] Among them, for the delayed arrival of the actual detection value, due to the material conveying delay... At present The actual export moisture content that can be obtained Corresponding to Predicted value at time .

[0201] Among them, the calculation of residuals involves the difference between the actual detected value and the predicted value. for: .

[0202] in, For a moment The prediction residuals reflect the systematic bias of the LSTM model.

[0203] Specifically, for updating the online deviation corrector, the corrector parameters are updated using an exponentially weighted moving average (EWMA). : .

[0204] in, EWMA smoothing coefficient; For a moment Deviation correction value, initial value .

[0205] Preferably, the EWMA smoothing coefficient The recommended value is 0.1, for deviation correction. Used to correct subsequent predicted values .

[0206] For example, accepting the above predicted values The actual measured value after 160 seconds Arrival, corresponding time prediction value residual Previous cycle correction value After the update The corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-023.

[0207] Step S5.5, based on the online deviation corrector and the predicted deviation, correct the water addition command and the atomization control command of each zone.

[0208] Preferably, the core of this step is to complete the closed-loop correction of the control command. By using an online deviation corrector and predictive deviation, the water addition command and atomization control command of each zone are adaptively adjusted to achieve forward-looking feedback control under large time delay conditions.

[0209] Among them, for the corrected predicted value, the deviation correction value is... The corrected predicted value is obtained by superimposing it onto the current predicted value: .

[0210] in, To predict the outlet moisture content after correction.

[0211] Among them, the calculation of the corrected prediction bias, the corrected prediction bias for: .

[0212] in, This represents the corrected prediction bias.

[0213] Among them, the correction of water supply instructions for each district is based on the corrected prediction deviation. and the influence coefficient of each district Adjust the water flow rate in each area: .

[0214] in, For the corrected partition Water flow rate; To correct the previous partition Optimal water flow rate; For partitioning The influence coefficient represents the weight of the water supply flow rate in the area on the outlet moisture content, satisfying the following conditions: ; This represents the current dry-basis mass flow rate.

[0215] Specifically, the modification of atomization control commands for each zone involves adjusting the zone pressure proportionally based on the modified water flow rate to maintain atomization quality within a feasible range. .

[0216] in, For the corrected partition pressure; To correct the previous partition Optimal pressure; This is the pressure-flow coupling coefficient.

[0217] Preferably, the zoning influence coefficient Recommended Consistent with the basic process weights; pressure-flow coupling coefficient The recommended value is 0.5 MPa / (L / min).

[0218] For example, accepting the above correction value Current forecast value Corrected predicted value Corrected prediction bias Dry basis mass flow rate kg / s, zoning influence coefficient Zone 1 correction amount kg / s L / min, after correction L / min, pressure correction MPa, water addition instructions after correction for each zone L / min, atomization control commands after correction for each zone MPa, corresponding to the timestamp record YYYY-MM-DD-HH:MM:SS-024.

[0219] Beneficial effects of steps S5.1 to S5.5: This series of steps addresses the problem of delayed control deviation correction caused by the large time delay from the inlet to the outlet detection position in the re-drying and re-humidification section and the unavailability of the outlet moisture content in the current period. By constructing a control input sequence to predict future outlet indicators and using virtual feedback values ​​to replace the actual detection values ​​for online deviation correction, a forward-looking feedback control under large time delay conditions is achieved.

[0220] Specifically, step S5.1 constructs a control input sequence by using water addition commands and atomization control commands for each zone, integrating the dispersed control commands into a time-sequential predictive input; step S5.2 predicts future outlet moisture and future outlet temperature using the control input sequence, obtaining forward-looking estimates of outlet indicators in advance; step S5.3 quantifies the expected deviation of the current control strategy by calculating the predicted deviation between the virtual feedback value and the target outlet moisture; step S5.4 updates the online deviation corrector by using the residual between the delayed arrival of the actual detection value and the corresponding predicted value, eliminating the systematic deviation of the prediction model; and step S5.5 corrects the water addition commands and atomization control commands for each zone using the online deviation corrector and the predicted deviation, achieving closed-loop adaptive correction of the control strategy.

[0221] Step S6: Based on the operating condition label and fault diagnosis results, perform safety verification and downgrade processing on the corrected water addition instructions and atomization control instructions for each zone, output the final control instructions and issue them for execution.

[0222] Furthermore, step S6 specifically includes the following steps: Step S6.1: Generate working condition labels based on material location and material occupation status. The working condition labels include four categories: material head, steady state, material tail, and empty material.

[0223] Preferably, the core of this step is to generate operating condition labels, which identify the current operating condition by the distribution of materials in the rehydration section and the material occupancy status of each zone, providing operating condition context for subsequent safety verification.

[0224] Specifically, regarding the material location, the conveying speed collected in S1.1 is used. Calculate the head position of the material based on the timestamp of the material entering the rehydration section. and the tail position of the material The total length of the backflow section is denoted as The lengths of the four zones are respectively ,satisfy .

[0225] Among them, for the material occupation state, zoning Material occupation status Defined as whether the area is covered by materials: if and If there are no materials in that area, Otherwise, there are materials in that area. .

[0226] The rules for generating working condition labels are based on the combination of material occupancy status in the four zones to determine the working condition: When the material head has just entered the rehydration section and some sections are not yet covered by material, it is determined to be the material head condition, and the condition label indicates this condition. When the material completely covers all four zones of the rehydration section, it is determined to be a steady-state operating condition, and the operating condition label will be displayed. When the tail of the material is about to leave the rehydration section and some sections are no longer covered by material, it is determined to be the tail condition, and the condition label will be displayed. When there is no material in the rehydration section, it is determined to be an empty material condition, and the condition label will be updated accordingly. .

[0227] Preferably, the working condition label update frequency is consistent with the control cycle, and it is recommended to update it once every 5 seconds.

[0228] For example, at time YYYY-MM-DD-HH:MM:SS-025, the position of the material head. material tail position All four zones are covered by materials, indicating a material-occupied state. Operating condition label At time YYYY-MM-DD-HH:MM:SS-026, the tail position of the material Material status in Zone 4 Operating condition label .

[0229] Step S6.2: Generate fault diagnosis results based on the zone pressure residual and nozzle flow residual.

[0230] Preferably, the core of this step is to generate fault diagnosis results, and to detect equipment malfunctions by using the residual pressure of the zones and the residual flow of the nozzles, thus providing a basis for the health status of the equipment for safety verification.

[0231] Among them, for partition pressure residual, partition Pressure residual Defined as the measured pressure in this area With command pressure Deviation: .

[0232] in, For partitioning Actual measured value from pressure sensor; This is the target pressure to be issued to the pressure regulating valve in this area.

[0233] Among them, for nozzle flow residual, zoning nozzle flow residual Defined as the estimated actual single-nozzle flow rate of this area. With instruction nozzle flow rate Deviation: .

[0234] in, Estimated based on the area's water supply flow and the number of effective sprinklers; To optimize the nozzle flow rate obtained from the solution.

[0235] Specifically, for generating fault diagnosis results, the fault type is determined by comparing the absolute value of the residual with a threshold: when At that time, the pressure in this area was determined to be abnormal, and a fault code was generated. ;when If the system determines that the sprinkler head in that area is clogged or leaking, a fault code will be generated. When neither type of residual exceeds the threshold, the area is considered normal, and a fault code is generated. .

[0236] Preferably, the pressure residual threshold The recommended value is 0.5 MPa, and the nozzle flow residual threshold is... The recommended flow rate is 0.05 L / min.

[0237] For example, at time YYYY-MM-DD-HH:MM:SS-027, the measured pressure in zone one... MPa, command pressure MPa, pressure residual MPa Pressure is normal; measured single-nozzle flow rate in Zone 2 L / min, commanded single nozzle flow rate L / min, nozzle flow residual L / min, The second zone nozzle was determined to be faulty; fault code was displayed. Fault diagnosis results .

[0238] Step S6.3: Perform a safety check on the revised water filling instructions and atomization control instructions for each zone based on the operating condition labels and fault diagnosis results.

[0239] Preferably, the core of this step is to complete the safety verification, determine whether the corrected control instructions meet the safety constraints based on the operating condition labels and fault diagnosis results, and identify the partition instructions that need to be downgraded.

[0240] Among them, for the safety constraints corresponding to the working condition labels, the control commands under different working conditions must meet different safety conditions: under the material head working condition, water addition commands are only issued to the zones that are covered by material, and the commands for the uncovered zones are set to zero; under the steady-state working condition, all zone commands must be within the range of feasible water addition; under the material tail working condition, the water addition flow rate of the zones without material is gradually reduced to zero; under the empty material working condition, all zone water addition commands and atomization control commands are set to zero, and only the pump is kept running at the lowest frequency.

[0241] Specifically, regarding the safety constraints corresponding to the fault diagnosis results, the water filling command for the faulty zone must be limited to a safe range: for zones with abnormal pressure, the pressure command for that zone must be limited to the lower bound of the feasible region. For abnormal sprinkler head zones, the water flow rate to that zone will be reduced proportionally to the decrease in the number of effective sprinkler heads. If the number of effective sprinkler heads is lower than the threshold, the water supply command for that zone will be set to zero.

[0242] In the safety verification process, each zone is checked to see if the corrected control commands meet the operating condition safety constraints and fault safety constraints. If all constraints are met, the zone passes the verification; otherwise, the zone fails the verification and is marked as pending downgrading.

[0243] Preferably, in the material head condition, the instruction for the uncovered area is set to zero; in the material tail condition, the flow rate in the area without material is gradually reduced; in the empty material condition, all flow rates are set to zero; in the pressure abnormal area, the pressure instruction is limited to the lower limit of the feasible domain; and in the nozzle abnormal area, the flow rate is reduced proportionally or set to zero.

[0244] For example, accepting the above-mentioned working condition labels and fault diagnosis results Water supply instructions for each district have been revised. L / min, Zone 2 sprinkler head malfunction, effective sprinkler head count in Zone 2 decreased from 18 to 12 (6 sprinkler heads clogged), reduction ratio. Upper limit of safe water supply flow in Zone 2 L / min, current command The security check for Zone 2 failed and is marked as pending downgrading; the security checks for Zones 1, 3, and 4 passed, and the corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-028.

[0245] Step S6.4: When the safety check fails, downgrade the water addition command and atomization control command for each zone that failed.

[0246] Preferably, the core of this step is to complete the degradation process, and execute the corresponding degradation strategy according to the fault type for partition instructions that fail the safety verification, so as to ensure the safe operation of the equipment under abnormal conditions.

[0247] Specifically, for the downgraded treatment of abnormal sprinkler zones, the water flow rate of the zone is limited to the safe upper limit according to the reduction ratio of the effective sprinkler number, and the excess water demand of the zone is redistributed to the adjacent normal zones according to the S3.4 coupling projection mechanism.

[0248] Specifically, the degradation process for pressure anomaly zones involves reducing the pressure command for that zone to the lower bound of the feasible region. At the same time, the water flow rate in the area will be reduced proportionally to the pressure decrease.

[0249] Specifically, for the downgraded processing of the empty material operation, all four-zone water addition commands and atomization control commands are reset to zero, and the pump frequency is reduced to the lowest standby frequency. .

[0250] Preferably, the lowest standby frequency The recommended frequency is 20 Hz. For areas with abnormal nozzles, the water demand exceeding the limit should be redistributed according to the available capacity of adjacent zones.

[0251] For example, if the safety check for Zone 2 fails, the water flow rate in Zone 2 will be limited from 2.96 L / min to 1.974 L / min, and any excess will be penalized. L / min, redistributed to adjacent zones 1 and 3, with a reserve in zone 1. L / min, three-zone margin L / min, any excess will be prioritized for allocation to Zone 1 (0.946 L / min) and Zone 3 (0.04 L / min). After downgrading, the water supply command for Zone 2 is 1.974 L / min, and the water supply command for Zone 1 is... L / min, three-zone water filling command L / min, the pressure command in Zone 2 is maintained at 6.5 MPa, and the corresponding timestamp is YYYY-MM-DD-HH:MM:SS-029.

[0252] Step S6.5: Integrate the water filling instructions and atomization control instructions of each zone that have passed the safety verification, as well as the water filling instructions and atomization control instructions of each zone after downgrading, and output the final control instructions and issue them for execution.

[0253] Preferably, the core of this step is to integrate and issue the final control commands, merging the verified partition commands and the downgraded partition commands into a complete control command set, which is then output to the actuator.

[0254] Specifically, the integration of final control commands involves merging the partition commands that have passed safety verification with the partition commands that have undergone degradation processing, according to the partition number, to form the final control command vector. .

[0255] Specifically, the final control command for each partition is either the verified pass command or the downgraded command: the verified partition uses the corrected command, and the downgraded partition uses the downgraded command. The final control command also includes a pump frequency command. Combined with the instructions for the commissioning of the nozzle island.

[0256] In terms of issuing control commands, the final control commands are sent to the programmable logic controller (PLC) via industrial Ethernet, and the PLC controls the pump frequency converter, pressure regulating valve, and nozzle island solenoid valve to execute them.

[0257] Preferably, the final control command issuance cycle is consistent with the control cycle, and it is recommended to be 5 seconds. The issuance protocol is EtherNet / IP.

[0258] For example, following the aforementioned downgrade process, Zone 1 verifies and retrieves the corrected instructions. L / min (including redistribution). MPa; After the second zone was downgraded L / min, MPa; Three-zone verification passed, including reallocation L / min, MPa; Fourth zone verification passed L / min, MPa, pump frequency command Based on the total water flow rate L / min calculation, final control command The command is sent to the PLC for execution, and the corresponding timestamp record is YYYY-MM-DD-HH:MM:SS-030.

[0259] Beneficial effects of steps S6.1 to S6.5: This series of steps addresses the issue of insufficient safety constraints on control commands during the switching between the head and tail of the re-drying and re-moistening section, as well as equipment failure conditions, which could lead to risks of dry head and wet tail and equipment damage. By using condition tag identification and fault diagnosis, the control commands are subjected to safety verification and downgrade processing to ensure safe operation of the equipment and continuous water supply under abnormal conditions.

[0260] Specifically, step S6.1 generates four types of operating condition labels—material head, steady state, material tail, and empty material—based on material location and material status to identify the current operating condition; step S6.2 generates fault diagnosis results based on zone pressure residual and nozzle flow residual to detect abnormal equipment operation; step S6.3 performs safety verification on the corrected control commands based on the operating condition labels and fault diagnosis results to identify zone commands that need to be downgraded; step S6.4 limits the zone commands that fail verification to a safe range and redistributes the excess to adjacent normal zones through downgrading, ensuring water supply continuity under abnormal operating conditions; step S6.5 integrates the verified commands and downgraded commands to output the final control command and issues it for execution, achieving a safe closed-loop execution of the control strategy.

[0261] In summary, the overall beneficial effects of steps S1 to S6 in this embodiment are as follows: This method addresses the serial architecture problem of separating water demand calculation and atomization constraint verification in the control of water addition during re-drying and rehydration. By constructing a feasible atomization domain for each zone and coupling and projecting the theoretical total water addition demand into the feasible domain, it achieves coordinated optimization control of water addition accuracy and atomization quality. It can maintain stable atomization under low load and head-to-tail switching conditions, reducing water stains, smoke, and uneven local absorption.

[0262] Step S1 calculates the theoretical total water demand by collecting incoming material data and environmental data, providing an accurate benchmark for the total water demand in subsequent coordinated control. Step S2 transforms the atomization quality constraint into a feasible region by constructing atomization capability feature vectors for each zone, upgrading the atomization conditions from post-event verification to pre-event modeling. Step S3 redistributes the water demand exceeding the feasible region to adjacent zones through coupled projection, preventing the water demand of a certain zone from falling into the atomization dead zone. Step S4 uses dual-objective coordinated optimization of minimizing water demand deviation and optimizing atomization quality to simultaneously solve for water demand commands and atomization control commands within the feasible region, eliminating coupling contradictions in the serial architecture. Step S5 predicts future outlet moisture and outlet temperature and uses virtual feedback values ​​for deviation correction, pre-correcting control deviations under large time delay conditions. Step S6 performs safety verification and degradation processing through operating condition labels and fault diagnosis results, ensuring control safety during head-to-tail switching and abnormal operating conditions.

[0263] like Figure 2 As shown, this embodiment provides a coordinated water addition control device for re-drying and rehydration. In this embodiment, the coordinated water addition control device is applied to the coordinated water addition control method as described in the above embodiment.

[0264] Specifically, the collaborative water supply control device includes a theoretical total water supply demand calculation module 1, an atomization feasible domain boundary acquisition module 2, a coupling feasible water supply range acquisition module 3, a collaborative instruction acquisition module 4, a collaborative instruction correction module 5, and a final control instruction issuance module 6, which are connected electrically or through communication in sequence.

[0265] The theoretical total water demand calculation module 1 collects incoming material data and environmental data for the re-drying and rehydration section, calculates the dry basis mass flow rate based on incoming material flow rate, inlet moisture, and inlet temperature, and calculates the theoretical total water demand based on the target outlet moisture and dry basis mass flow rate. The atomization feasible domain boundary acquisition module 2 constructs atomization capability feature vectors for each zone based on the joint relationship between the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure, and droplet size, transforms the atomization quality constraints of each zone into atomization feasible domains, and outputs the boundaries of each zone's atomization feasible domain. The coupled feasible water supply range acquisition module 3 couples and projects the theoretical total water demand according to the boundaries of each zone's atomization feasible domain. When the theoretical total water demand falls outside the atomization feasible domain of a certain zone, the excess water demand of that zone is redistributed to the feasible domains of adjacent zones, and the boundaries of each zone's feasible water supply range are output. The feasible water addition range for each zone is defined as follows: The collaborative instruction acquisition module 4 performs collaborative optimization within the feasible water addition range for each zone, with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and outputs water addition instructions and atomization control instructions for each zone; the collaborative instruction correction module 5 predicts future outlet moisture and outlet temperature based on the water addition instructions and atomization control instructions for each zone, uses the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable real outlet value, updates the online deviation corrector with the delayed real detection value, and corrects the water addition instructions and atomization control instructions for each zone based on the online deviation corrector; the final control instruction issuance module 6 performs safety verification and downgrading processing on the corrected water addition instructions and atomization control instructions for each zone according to the operating condition label and fault diagnosis results, outputs the final control instruction, and issues it for execution.

[0266] like Figure 3 As shown, the electronic device 7 includes a processor 71 and a memory 72 coupled to the processor 71.

[0267] The memory 72 stores program instructions for implementing the synergistic water addition control method for reheating and rehydration in any of the above embodiments.

[0268] The processor 71 is used to execute program instructions stored in the memory 72 to perform coordinated water addition control for reheating and rehydration.

[0269] The processor 71 can also be referred to as a CPU (Central Processing Unit). The processor 71 may be an integrated circuit chip with signal processing capabilities. The processor 71 can also be a general-purpose processor, a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, or discrete hardware components. A general-purpose processor can be a microprocessor or any conventional processor.

[0270] Furthermore, Figure 4This is a schematic diagram of the structure of a storage medium according to an embodiment of this application. See also: Figure 4 The storage medium 8 in this embodiment stores program instructions 81 capable of implementing all the above methods. These program instructions 81 can be stored in the storage medium as a software product, including several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) or processor to execute all or part of the steps of the methods in each embodiment of this application. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks, or terminal devices such as computers, servers, mobile phones, and tablets.

[0271] In the several embodiments provided in this application, it should be understood that the disclosed systems, methods, and approaches can be implemented in other ways. For example, the system embodiments described above are merely illustrative. For instance, the coordinated water filling control for reheating and rehydration of units is only one logical function. In actual implementation, there may be other coordinated water filling control methods for reheating and rehydration. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some interfaces; the indirect coupling or communication connection between systems or units may be electrical, mechanical, signal, or other forms.

[0272] Furthermore, the functional units in the various embodiments of this application can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated units described above can be implemented in hardware or as software functional units. The above are merely embodiments of this application and do not limit the patent scope of this application. Any equivalent structural or procedural transformations made based on the content of this application's specification and drawings, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of this application.

Claims

1. A method for controlling the synergistic water addition during re-drying and rehydration, characterized in that, The coordinated water supply control method includes: Step S1: Collect incoming material data and environmental data for the re-drying and rehydration section; calculate dry basis mass flow rate based on incoming material flow rate, inlet moisture and inlet temperature; calculate the theoretical total water demand based on the target outlet moisture and dry basis mass flow rate. Step S2: Based on the combined relationship of the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure and droplet size, construct the atomization capability feature vector of each zone, transform the atomization quality constraints of each zone into atomization feasible regions, and output the boundary of the atomization feasible region of each zone. Step S3: Couple the theoretical total water demand according to the boundary of the atomization feasible domain of each zone. When the theoretical total water demand falls outside the atomization feasible domain of a certain zone, redistribute the excess water demand of that zone to the feasible domain of the adjacent zone, and output the coupled feasible water supply range of each zone. Step S4: Within the feasible water addition range of each zone, perform collaborative optimization with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and output water addition commands and atomization control commands for each zone. Step S5: Based on the water addition command and atomization control command of each zone, predict the future outlet moisture and outlet temperature, use the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable real outlet value, update the online deviation corrector with the delayed real detection value, and correct the water addition command and atomization control command of each zone based on the online deviation corrector. Step S6: Based on the operating condition label and fault diagnosis results, perform safety verification and downgrade processing on the corrected water addition instructions and atomization control instructions for each zone, output the final control instructions and issue them for execution.

2. The synergistic water addition control method according to claim 1, characterized in that, Step S1: Collect incoming material data and environmental data for the re-drying and rehydration section. Calculate the dry basis mass flow rate based on the incoming material flow rate, inlet moisture content, and inlet temperature. Calculate the theoretical total water requirement based on the target outlet moisture content and dry basis mass flow rate, including: Step S1.1: Collect the incoming material flow rate, inlet moisture, inlet temperature, material layer thickness, and conveying speed of the re-drying and rehydration section to generate an incoming material data vector; Step S1.2: Collect ambient temperature and humidity, generate an environmental data vector, synchronize the incoming material data vector and the environmental data vector with a unified sampling period, and generate an incoming material status vector. Step S1.3: Calculate the dry basis mass flow rate based on the incoming material flow rate and inlet moisture content in the incoming material state vector; Step S1.4: Calculate the theoretical total water demand based on the target outlet moisture content and the dry basis mass flow rate.

3. The synergistic water addition control method according to claim 1, characterized in that, Step S2: Based on the combined relationship between the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure, and droplet size, construct the atomization capability feature vector for each zone. Transform the atomization quality constraints of each zone into a feasible atomization region, and output the boundary of the feasible atomization region for each zone, including: Step S2.1: Calculate the number of effective nozzles in each zone based on the pump frequency and the number of nozzle island combinations; Step S2.2: Calculate the single nozzle flow rate of each zone based on the effective number of nozzles and the zone pressure; Step S2.3: Estimate the droplet size of each zone based on the zone pressure and the number of effective nozzles; Step S2.4: Based on the theoretical total water demand, the flow rate of a single nozzle in each zone, and the droplet size in each zone, construct the atomization capability feature vector for each zone; Step S2.5: Based on the atomization capability feature vector of each region, the atomization quality constraint of each region is transformed into atomization feasible region, and the boundary of the atomization feasible region of each region is output.

4. The synergistic water addition control method according to claim 1, characterized in that, Step S3: Couple the theoretical total water demand according to the boundaries of the feasible atomization domains of each zone. When the theoretical total water demand falls outside the feasible atomization domain of a certain zone, redistribute the excess water demand of that zone to the feasible domains of adjacent zones, and output the coupled feasible water supply ranges of each zone, including: Step S3.1: Allocate the theoretical total water demand to the initial water demand of each zone according to the basic process weights of the four zones; Step S3.2: Project the initial water demand of each zone according to the boundary of the atomization feasible domain of each zone, and determine whether the initial water demand of each zone falls within the atomization feasible domain of the corresponding zone. Step S3.3: When the initial water demand of a certain area falls outside the feasible atomization domain of the corresponding area, calculate the excess water demand of that area. Step S3.4: The excess water demand is redistributed to the feasible atomization domain of the adjacent area, the water demand after projection of each area is integrated, and the coupled feasible water supply range of each area is output.

5. The synergistic water addition control method according to claim 1, characterized in that, Step S4: Within the feasible water addition range of each zone, perform collaborative optimization with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and output water addition commands and atomization control commands for each zone, including: Step S4.1: Construct a water addition deviation objective function based on the feasible water addition range of each zone and the initial water addition requirement of each zone; Step S4.2: Construct an atomization quality objective function based on the droplet size deviation and zone pressure fluctuation corresponding to the boundary of the feasible atomization domain in each zone; Step S4.3: Perform weighted collaborative optimization on the objective function of water addition deviation and the objective function of atomization quality to obtain the optimal water addition flow rate and the optimal atomization parameters for each zone; Step S4.4: Generate water supply instructions for each zone based on the optimal water supply flow rate for each zone, and generate atomization control instructions for each zone based on the optimal atomization parameters for each zone.

6. The synergistic water addition control method according to claim 1, characterized in that, Step S5: Based on the water addition commands and atomization control commands for each zone, predict the future outlet moisture content and outlet temperature. Use the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable true outlet value. Update the online deviation corrector using the delayed true detection value. Correct the water addition commands and atomization control commands for each zone based on the online deviation corrector, including: Step S5.1: Construct a control input sequence based on the water addition instructions and atomization control instructions for each zone; Step S5.2: Predict future outlet moisture content and future outlet temperature based on the control input sequence; Step S5.3: Using the predicted outlet moisture content as a virtual feedback value, calculate the prediction deviation between the virtual feedback value and the target outlet moisture content; Step S5.4: Update the online deviation corrector using the residual between the delayed actual detection value and the corresponding predicted value; Step S5.5: Based on the online deviation corrector and the predicted deviation, correct the water addition command and the atomization control command for each zone.

7. The synergistic water addition control method according to claim 1, characterized in that, Step S6: Based on the operating condition labels and fault diagnosis results, perform safety verification and downgrade processing on the corrected water addition commands and atomization control commands for each zone, output the final control commands and issue them for execution, including: Step S6.1: Generate working condition labels based on material location and material occupation status. The working condition labels include four categories: material head, steady state, material tail, and empty material. Step S6.2: Generate fault diagnosis results based on the zone pressure residual and nozzle flow residual; Step S6.3: Perform a safety check on the corrected water filling instructions and atomization control instructions for each zone based on the operating condition label and the fault diagnosis results; Step S6.4: When the safety check fails, downgrade the water addition command and atomization control command for each zone that failed. Step S6.5: Integrate the water filling instructions and atomization control instructions of each zone that have passed the safety verification, as well as the water filling instructions and atomization control instructions of each zone after downgrading, and output the final control instructions and issue them for execution.

8. A coordinated water addition control device for re-drying and rehydration, wherein the coordinated water addition control device is applied to the coordinated water addition control method as described in any one of claims 1 to 7, characterized in that, The coordinated water supply control device includes: The theoretical total water demand calculation module is used to collect incoming material data and environmental data of the re-drying and rehydration section, calculate the dry basis mass flow rate based on incoming material flow rate, inlet moisture and inlet temperature, and calculate the theoretical total water demand based on the target outlet moisture and dry basis mass flow rate. The atomization feasible domain boundary acquisition module is used to construct the atomization capability feature vector of each zone based on the joint relationship of the theoretical total water demand, pump frequency, number of nozzle island combinations, zone pressure and droplet size, transform the atomization quality constraints of each zone into atomization feasible domain, and output the atomization feasible domain boundary of each zone. The coupled feasible water supply range acquisition module is used to couple the theoretical total water supply demand according to the boundary of the atomization feasible domain of each zone. When the theoretical total water supply demand falls outside the atomization feasible domain of a certain zone, the water supply demand exceeding the boundary of that zone is redistributed to the feasible domain of the adjacent zone, and the coupled feasible water supply range of each zone is output. The collaborative instruction acquisition module is used to perform collaborative optimization within the feasible water addition range of each zone, with the dual objectives of minimizing water addition deviation and optimizing atomization quality, and output water addition instructions and atomization control instructions for each zone. The collaborative instruction correction module is used to predict the future outlet moisture and outlet temperature based on the water addition instructions and atomization control instructions of each zone, and to use the predicted outlet moisture content as a virtual feedback value to replace the currently unavailable real outlet value. The online deviation corrector is updated by the delayed real detection value, and the water addition instructions and atomization control instructions of each zone are corrected based on the online deviation corrector. The final control command issuance module is used to perform safety verification and downgrade processing on the corrected water addition commands and atomization control commands for each zone based on the operating condition labels and fault diagnosis results, and outputs the final control command for execution.

9. An electronic device, characterized in that, The method includes a processor and a memory coupled to the processor, the memory storing program instructions executable by the processor; when the processor executes the program instructions stored in the memory, it implements the coordinated water addition control method as described in any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores program instructions that, when executed by a processor, enable the coordinated water addition control method as described in any one of claims 1 to 7.