A method for processing inclined steel pipe and a mounting method for cast-in-place beam construction

By adopting spiral steel pipe stiffening plate connection and welding precast anchor plates to the pier reinforcement, combined with precise hoisting, the problems of insufficient shear resistance and unstable connection in the processing and installation of inclined steel pipes were solved, thus ensuring the safety and quality of cast-in-place beam construction.

CN123149706APending Publication Date: 2026-11-24CHINA RAILWAY GUANGZHOU ENG GRP CO LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202511955713.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-12-23
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Traditional methods of processing inclined steel pipes have insufficient shear resistance at the joints, making them prone to cracking. They also fail to take into account anchoring requirements, resulting in low positioning accuracy of pre-embedded components during installation, insufficient rigidity of the vertical steel pipe connection system, and uneven overall stress, which affects the safety and quality of cast-in-place beam construction.

Method used

The φ630×10mm spiral steel pipe is connected by circumferential butt weld stiffening plates. The prefabricated anchor plates are matched and welded with the pier reinforcement. Combined with the precise lifting and welding by an 80t truck crane, a stable frame is formed to ensure a reliable connection between the inclined steel pipe and the pier.

Benefits of technology

It improves the shear resistance of the inclined steel pipe extension, ensures accurate installation, forms a stable structure, is compatible with Bailey beam and inclined steel pipe combined support, enhances load transfer stability, reduces deformation, and ensures construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123149706A_ABST
    Figure CN123149706A_ABST
Patent Text Reader

Abstract

This invention discloses a method for processing inclined steel pipes and an installation method for cast-in-place beam construction, including step one: selecting a base material: selecting a spiral steel pipe with a specification of φ630×10mm as the base material for the inclined steel pipe; step two: extension treatment: extending the spiral steel pipe by welding with a circumferential butt weld, grinding the excess part after full welding, and evenly arranging stiffening plates at the joint, wherein the material of the stiffening plates is the same as that of the spiral steel pipe; this invention belongs to the field of building construction, specifically referring to a method for processing inclined steel pipes and an installation method for cast-in-place beam construction; this invention uses spiral steel pipes and pre-set anchor plates during processing to ensure the extension strength and pier connection, and can accurately position and construct a stable structure during installation, adapting to the Bailey beam and inclined steel pipe combined support, which can transfer loads, improve stability, reduce deformation, and effectively ensure construction safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of building construction technology, specifically referring to a method for processing inclined steel pipes and an installation method for cast-in-place beam construction. Background Technology

[0002] In the field of cast-in-place bridge construction, the Bailey bridge combined with inclined steel pipe support system has become a commonly used support solution due to its strong adaptability. However, this type of support system has stringent requirements for the processing accuracy, connection strength, and installation stability of the core component, the inclined steel pipe. Traditional processes have many shortcomings and cannot meet the construction requirements. From the perspective of inclined steel pipe processing, traditional methods of splicing ordinary steel pipes often rely solely on simple circumferential welds without specifically reinforcing the joint structure. Due to the load of the cast-in-place beams in the Jiya Waterway Bridge section, the joints are prone to cracking due to insufficient shear resistance. Furthermore, the subsequent anchoring requirements with the pier were not considered during processing, necessitating additional welding of anchoring components later. This not only prolongs the construction period but also easily leads to stress concentration in the steel pipe due to secondary welding, creating potential safety hazards.

[0003] In the installation phase, traditional methods lack systematic planning in the initial preparation. During the construction of the foundation and pier, insufficient control over the positioning accuracy of embedded components, and deviations in the positions of anchor bolts and anchoring bars, directly lead to subsequent misalignment of the column base installation, thus affecting the connection accuracy of vertical and inclined steel pipes. After the vertical steel pipes are installed, traditional connection systems often use small steel sections, resulting in insufficient overall rigidity and difficulty in forming a stable initial frame, creating potential problems for the subsequent installation of inclined steel pipes. During the hoisting and fixing of inclined steel pipes, traditional methods lack precise angle control. The connection between the inclined steel pipes and the pier body and column base, as well as the subsequent installation of the connection system, lack coordination in traditional methods, easily leading to uneven overall stress and excessive deformation of the support structure. This makes it difficult to meet the requirements for load distribution and deformation control in cast-in-place beam construction, seriously threatening construction safety and project quality. Summary of the Invention

[0004] To address the above issues and overcome the shortcomings of existing technologies, this invention provides a method for processing inclined steel pipes and an installation method for cast-in-place beam construction. This effectively solves the problems currently found in the market where steel pipe extension relies solely on simple circumferential welds, resulting in joints prone to cracking due to poor shear resistance. Furthermore, the lack of coordinated anchoring requirements leads to stress concentration during secondary welding, and the simple anchoring structure results in weak connections to the pier and poor load transfer. During installation, the low positioning accuracy of pre-embedded components easily causes subsequent installation deviations; the vertical steel pipe connection system lacks rigidity, leading to an unstable initial frame; the inclined steel pipe hoisting lacks precise angle control methods, resulting in large angle deviations; temporary fixing is simple; and the lack of coordination between various connection and installation stages leads to uneven overall stress and easy deformation. Moreover, the lack of an integrated process results in low efficiency, numerous hidden dangers, and difficulty in meeting construction requirements.

[0005] The technical solution adopted by the present invention is as follows: The present invention proposes a method for processing inclined steel pipes and an installation method for cast-in-place beam construction, including step one: selecting a base material: selecting a spiral steel pipe with a specification of φ630×10mm as the base material for the inclined steel pipe; Step 2: Extension treatment: The spiral steel pipe is extended by circumferential butt weld. After the weld is fully welded, the excess part is ground smooth. Stiffening plates are evenly arranged at the joint. The material of the stiffening plates is the same as that of the spiral steel pipe. Step 3: Anchor plate prefabrication: A connecting plate is installed at one end of the inclined steel pipe near the pier body. The connecting plate is matched and welded to the anchor plate. The anchor plate is made of Q345C steel plate. The anchor plate is provided with steel bar through holes. The steel bar through holes are adapted to the HRB400 steel bars pre-embedded in the pier body.

[0006] Furthermore, in step two, the number and spacing of the stiffening plates are determined according to the stress requirements at the joint of the spiral steel pipe.

[0007] Furthermore, in step three, the inclined steel pipe is fully welded to the connecting plate, the connecting plate is fully welded to the anchor plate, the weld thickness is not less than 4.8mm, the width is not less than 12.8mm, and the weld is visually inspected after welding is completed.

[0008] Furthermore, the steel pipe is provided with several sets of stiffening plates evenly arranged at the joint of the steel pipe, and a connecting plate is fully welded to one end of the steel pipe near the pier body. The connecting plate is fully welded to the anchor plate, and several sets of reinforcing bar through holes are provided on the anchor plate.

[0009] Further, step one: preliminary preparation: when constructing the foundation, pre-embed φ25mm precision threaded steel anchor bolts, which are used to fix the column base; When constructing the pier body, HRB400 anchoring steel bars are pre-embedded at the corresponding installation positions of the inclined steel pipes, and the spacing of the HRB400 anchoring steel bars is 30cm. Step 2: Vertical steel pipe installation. An 80t truck crane is used to lift the vertical steel pipe and weld it to the column base. The column base and the vertical steel pipe are pre-welded and then installed in place as a whole. The vertical steel pipe is connected to the pier wall-mounted embedded parts through a 2[32b type steel connection system to form an initial stable frame. Step 3: Installation of inclined steel pipe. Weld two lifting lugs to the top of the inclined steel pipe and use an 80t truck crane for hoisting. Use a φ20 steel wire rope to control the lifting angle of the inclined steel pipe during hoisting and adjust the angle of the inclined steel pipe to 19.7°. Step 4: Fixing method: Temporarily fix the bottom of the inclined steel pipe, then weld the pre-set anchor plate of the inclined steel pipe to the HRB400 steel bar pre-embedded in the pier body. The length of the welding is 10d when using single-sided welding and 5d when using double-sided welding. Temporarily connect the inclined steel pipe to the vertical steel pipe with 10# channel steel. Step 5: Final Fixing: Remove the temporary channel steel, weld the bottom of the inclined steel pipe to the column base, and then install the 2[20b type steel connecting system to form an integral load-bearing structure with the inclined steel pipe, vertical steel pipe and connecting system.

[0010] Furthermore, in step one, the pre-embedded anchor bolts need to be calibrated to ensure that their axis coincides with the axis of the column base mounting hole, with a deviation not exceeding 2mm.

[0011] Furthermore, in step two, when the 80t truck crane lifts the vertical steel pipe, the boom length is set to 40m and the working radius is controlled at 15m to ensure that the lifting capacity meets the requirements during the lifting process.

[0012] Furthermore, in step three, the lifting lug is made of steel with the same material as the inclined steel pipe, the lifting lug is fully welded, and a load-bearing test is conducted after the lifting lug is welded. Before using the φ20 steel wire rope, it is necessary to check for broken wires, wear, etc. Steel wire ropes that do not meet the requirements must not be used.

[0013] Furthermore, in step four, when welding the inclined steel pipe to the HRB400 steel bar embedded in the pier body, positioning welding must be performed first, and formal welding can only be carried out after the position is accurately adjusted. Windproof measures are adopted during the welding process to avoid porosity in the weld.

[0014] Furthermore, in step five, the connection between the connecting system and the inclined steel pipe and the vertical steel pipe is made by welding, and the weld requirements are consistent with the welding requirements of the inclined steel pipe and the anchor plate.

[0015] The beneficial effects of the present invention using the above structure are as follows: This solution proposes a method for processing inclined steel pipes and an installation method for cast-in-place beam construction. This method uses spiral steel pipes and pre-set anchor plates during processing to ensure the extension strength and pier connection. During installation, it can be accurately positioned and a stable structure can be built. It is compatible with Bailey beams and inclined steel pipe combined supports, which can transfer loads, improve stability, reduce deformation, and effectively ensure construction safety. Attached Figure Description

[0016] Figure 1 This is a flowchart illustrating the overall process of the inclined steel pipe processing method and its installation method for cast-in-place beam construction proposed in this invention. Figure 2This invention provides a detailed flowchart of steps one and two of a method for processing inclined steel pipes and an installation method for cast-in-place beam construction. Figure 3 This is a detailed flowchart of step three of the inclined steel pipe processing method and installation method for cast-in-place beam construction proposed in this invention. Figure 4 This is a schematic diagram of the steel pipe extension structure for the inclined steel pipe processing method and installation method for cast-in-place beam construction proposed in this invention. Figure 5 This invention provides a method for processing inclined steel pipes and an installation method for cast-in-place beams, and presents a general flowchart of the installation method for cast-in-place beams. Figure 6 This invention provides a method for processing inclined steel pipes and an installation method for cast-in-place beams, including detailed flowcharts of steps one to three of the installation method for cast-in-place beam construction. Figure 7 This invention provides a method for processing inclined steel pipes and an installation method for cast-in-place beams, including detailed flowcharts of steps four and five of the installation method for cast-in-place beams.

[0017] The accompanying drawings are provided to further illustrate the invention and form part of the specification. They are used together with the embodiments of the invention to explain the invention and do not constitute a limitation thereof. Detailed Implementation

[0018] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.

[0019] In the description of this invention, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this invention.

[0020] like Figures 1-4 As shown, the present invention proposes a method for processing inclined steel pipes and an installation method for cast-in-place beam construction, including step one: selecting a base material: selecting a spiral steel pipe with a specification of φ630×10mm as the base material for the inclined steel pipe; Step 2: Extension treatment: The spiral steel pipe is extended by circumferential butt weld. After the weld is fully welded, the excess part is ground smooth. Stiffening plates are evenly arranged at the joint. The material of the stiffening plates is the same as that of the spiral steel pipe. Step 3: Anchor plate prefabrication: A connecting plate is installed at one end of the inclined steel pipe near the pier body. The connecting plate is matched and welded to the anchor plate. The anchor plate is made of Q345C steel plate. The anchor plate is provided with steel bar through holes. The steel bar through holes are adapted to the HRB400 steel bars pre-embedded in the pier body.

[0021] In practical application, based on the load-bearing capacity requirements of the support system for cast-in-place beam construction, φ630×10mm spiral steel pipes are selected as the base material. This specification of steel pipe can meet the load requirement of approximately 4.2t for a single inclined steel pipe, avoiding deformation or collapse due to insufficient base material strength. The spiral steel pipes are spliced ​​using circumferential butt welding followed by grinding to avoid stress concentration at the weld. Evenly distributed stiffening plates of the same material enhance the shear resistance of the butt joint by dispersing shear force, ensuring overall stability of the steel pipe support system and extending its service life. A connecting plate is installed near the pier end of the inclined steel pipe, fully welded to a Q345C steel plate anchor plate. The anchor plate has pre-drilled holes for the embedded HRB400 steel bars in the pier, ensuring a reliable connection between the inclined steel pipe and the pier. The load is transferred via the embedded steel bars, ensuring coordinated load-bearing between the support system and the pier, preventing displacement of the inclined steel pipe during construction, and guaranteeing the safety of cast-in-place beam construction.

[0022] In step two, the number and spacing of the stiffening plates are determined according to the stress requirements at the joint of the spiral steel pipe.

[0023] In practical applications, based on the stress distribution pattern at the joint of the spiral steel pipe, the shear force at the joint varies under different stress conditions. The number and spacing of stiffening plates need to be determined in conjunction with specific stress calculations to avoid excessive reinforcement leading to material waste or insufficient reinforcement leading to structural weakness. This ensures that the stiffening plates can accurately disperse the shear force, further improving the structural stability of the steel pipe joint and adapting to complex load changes during cast-in-place beam construction.

[0024] In step three, the inclined steel pipe is fully welded to the connecting plate, and the connecting plate is fully welded to the anchor plate. The weld thickness is not less than 4.8 mm and the width is not less than 12.8 mm. After the welding is completed, the weld is visually inspected.

[0025] In practical application, the connecting plate, inclined steel pipe, and anchor plate are all fully welded, with a specified weld thickness of not less than 4.8mm and a width of not less than 12.8mm. Full welding increases the welding contact area, ensuring the load-bearing capacity of the welded parts. Post-weld visual inspection allows for the timely detection of defects such as cracks, slag inclusions, and porosity, preventing these defects from affecting weld strength. Full welding and compliant weld dimensions ensure reliable connection between the connecting plate, inclined steel pipe, and anchor plate, effectively transferring loads and preventing breakage due to insufficient strength. Visual inspection of the welds can eliminate potential welding defects in advance, ensuring the overall structural strength of the inclined steel pipe and laying a foundation for safe subsequent installation and construction.

[0026] This includes steel pipes, with several sets of stiffening plates evenly arranged at the joints of the steel pipes. A connecting plate is fully welded to one end of the steel pipe near the pier body. The connecting plate is fully welded to the anchor plate. Several sets of reinforcing bar perforations are provided on the anchor plate.

[0027] In practical use, the stiffening plate at the joint of the steel pipes ensures that the joint maintains sufficient shear resistance during installation and use, preventing damage to the joint due to installation stress. The fully welded structure of the connecting plate and anchor plate near the pier provides a stable interface for the connection between the inclined steel pipe and the pre-embedded reinforcing bars in the pier. The perforated anchor plate, matching the pre-embedded reinforcing bars, ensures a rigid connection between the inclined steel pipe and the pier. The connection and perforation between the connecting plate and anchor plate allow the inclined steel pipe to quickly and accurately connect with the pre-embedded reinforcing bars in the pier, improving installation efficiency while ensuring a firm connection and preventing loosening of the inclined steel pipe during construction.

[0028] like Figures 5-7 As shown, in step one: preliminary preparation: when constructing the foundation, pre-embed φ25mm precision threaded steel anchor bolts, which are used to fix the column base; When constructing the pier body, HRB400 anchoring steel bars are pre-embedded at the corresponding installation positions of the inclined steel pipes, and the spacing of the HRB400 anchoring steel bars is 30cm. Step 2: Vertical steel pipe installation. An 80t truck crane is used to lift the vertical steel pipe and weld it to the column base. The column base and the vertical steel pipe are pre-welded and then installed in place as a whole. The vertical steel pipe is connected to the pier wall-mounted embedded parts through a 2[32b type steel connection system to form an initial stable frame. Step 3: Installation of inclined steel pipe. Weld two lifting lugs to the top of the inclined steel pipe and use an 80t truck crane for hoisting. Use a φ20 steel wire rope to control the lifting angle of the inclined steel pipe during hoisting and adjust the angle of the inclined steel pipe to 19.7°. Step 4: Fixing method: Temporarily fix the bottom of the inclined steel pipe, then weld the pre-set anchor plate of the inclined steel pipe to the HRB400 steel bar pre-embedded in the pier body. The length of the welding is 10d when using single-sided welding and 5d when using double-sided welding. Temporarily connect the inclined steel pipe to the vertical steel pipe with 10# channel steel. Step 5: Final Fixing: Remove the temporary channel steel, weld the bottom of the inclined steel pipe to the column base, and then install the 2[20b type steel connecting system to form an integral load-bearing structure with the inclined steel pipe, vertical steel pipe and connecting system.

[0029] In practical use, anchor bolts are pre-embedded to fix the column base. The high strength of the precision-rolled threaded steel ensures the stability of the column base, providing reliable support for the vertical steel pipe. Anchor bars are pre-embedded at 30cm intervals to ensure uniform distribution of anchor points and improve the stability of the connection between the inclined steel pipe and the pier. The vertical steel pipe is lifted by an 80t truck crane. Combined with welding to the column base and connection of the 2[32b type steel connection system to the pre-embedded parts attached to the pier wall, an initial stable frame is formed. Multi-directional constraints ensure the vertical stability of the steel pipe. Lifting lugs are welded to the top of the inclined steel pipe and lifted by an 80t truck crane. Combined with φ20 steel wire rope, the lifting angle is controlled at 19.7°. This is determined based on the weight of the inclined steel pipe and the lifting capacity of the 80t truck crane (8.2t) with a boom length of 40m and a working radius of 15m, ensuring lifting safety and thus accurately controlling the installation angle. After the bottom of the inclined steel pipe is temporarily fixed, it is welded to the pre-embedded reinforcing bars according to specifications. A temporary 10# channel steel is used to connect the vertical steel pipe, temporarily fixing the position of the inclined steel pipe and facilitating angle adjustment. Subsequently, the temporary channel steel is removed, and the bottom is welded to the column base. A 2[20b type steel connection system is installed to form an integrated load-bearing structure. By perfecting the connection nodes, the overall support structure is ensured to bear the load collaboratively. The preliminary pre-embedded work provides a stable foundation for subsequent installation, preventing displacement of the column base and loosening of the inclined steel pipe connections. Precise hoisting and standardized welding of the inclined steel pipe, as well as the installation of the inclined steel pipe and connection system, ensure that the inclined steel pipe, vertical steel pipe, and pier body form a stable whole, effectively bearing the construction load of the cast-in-place beam, preventing deformation or collapse of the support structure, and guaranteeing the construction quality and safety of the cast-in-place beam.

[0030] In step one, the pre-embedded anchor bolts need to be calibrated to ensure that their axis coincides with the axis of the column base mounting hole, with a deviation not exceeding 2mm.

[0031] In practical use, the pre-embedded anchor bolts are calibrated to ensure their axis coincides with the axis of the column base mounting holes, with a deviation not exceeding 2mm. This ensures accurate installation of the column base and prevents it from tilting due to bolt misalignment, which could affect the verticality of the vertical steel pipe installation. Precise bolt positioning ensures stable installation of the column base, providing vertical and stable support for the vertical steel pipe, preventing additional stress on the pipe due to base tilt, reducing the risk of bending or breakage, and ensuring the installation accuracy of the entire support system afterwards.

[0032] In step two, when the 80t truck crane lifts the vertical steel pipe, the boom length is set to 40m and the working radius is controlled at 15m to ensure that the lifting capacity meets the requirements during the lifting process.

[0033] In practical use, when the 80t truck crane is used to lift vertical steel pipes, the boom length is set to 40m and the working radius to 15m. This is based on the fact that the crane's lifting capacity of 8.2t is greater than the weight of the vertical steel pipe. This ensures that the crane can stably bear the load during the lifting process, avoids lifting accidents caused by insufficient lifting capacity, and improves lifting efficiency. It also ensures that the vertical steel pipe is successfully installed in place, laying the foundation for the subsequent assembly of the support frame.

[0034] In step three, the lifting lug is made of steel with the same material as the inclined steel pipe, the lifting lug is fully welded, and a load-bearing test is conducted after the lifting lug is welded. Before using the φ20 steel wire rope, it is necessary to check for broken wires, wear, etc. Steel wire ropes that do not meet the requirements must not be used.

[0035] In practical use, the lifting lugs are made of the same steel as the inclined steel pipe and are fully welded to ensure the compatibility of the materials and the connection strength between the lifting lugs and the inclined steel pipe, preventing the lifting lugs from falling off due to material differences or weak welding. After welding, a load-bearing test is conducted on the lifting lugs to verify whether their load-bearing capacity meets the standards. Before use, the φ20 steel wire rope is inspected for broken wires and wear to eliminate defects in the wire rope itself, preventing wire rope breakage during lifting, meeting the safety requirements for lifting accessories, ensuring stable lifting of the inclined steel pipe during the lifting process, and preventing the risk of falling.

[0036] In step four, when welding the inclined steel pipe to the HRB400 steel bar embedded in the pier body, positioning welding must be performed first, and formal welding can only be carried out after the position is accurately adjusted. Windproof measures are adopted during the welding process to avoid porosity in the weld.

[0037] In practical application, the inclined steel pipe is first positioned and welded to the pre-embedded reinforcing bars to initially fix its position, facilitating subsequent angle adjustments and preventing irreparable angle deviations after formal welding. Formal welding proceeds only after accurate position adjustment, ensuring the inclined steel pipe's position conforms to design standards. Wind protection measures are employed during welding to prevent wind from affecting the stability of the welding arc, avoiding defects such as porosity and slag inclusions in the weld, ensuring weld quality, and guaranteeing accurate installation angles of the inclined steel pipe that meet the support's load-bearing design requirements. These wind protection measures also ensure weld quality, preventing insufficient connection strength due to weld defects, preventing breakage of the welded portion of the inclined steel pipe under stress, and further enhancing the support's stability.

[0038] In step five, the connection between the connecting system and the inclined steel pipe and the vertical steel pipe is made by welding, and the weld requirements are consistent with the welding requirements of the inclined steel pipe and the anchor plate.

[0039] In practical use, the welding requirements between the connecting system and the inclined steel pipes and vertical steel pipes are consistent with the welding requirements between the inclined steel pipes and the anchor plates. This ensures uniform strength at the connection points between the connecting system and the steel pipes, preventing uneven stress on the overall support due to insufficient strength in some areas. It also ensures a firm connection between the connecting system and the steel pipes, enabling the inclined steel pipes, vertical steel pipes, and connecting system to form a complete and stable load-bearing system. This system can evenly transfer the construction load of the cast-in-place beam, preventing local stress concentration that could damage the support and ensuring the safety and reliability of the entire support system during construction.

[0040] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such process, method, article, or apparatus.

[0041] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

[0042] The present invention and its embodiments have been described above. This description is not restrictive, and the accompanying drawings are only one embodiment of the present invention; the actual structure is not limited thereto. In conclusion, if those skilled in the art are inspired by this description and design similar structures and embodiments without departing from the spirit of the invention, such designs should fall within the protection scope of the present invention.

Claims

1. A method for processing inclined steel pipes, characterized in that: Step 1: Selecting the base material: Select a spiral steel pipe with a specification of φ630×10mm as the base material for the inclined steel pipe; Step 2: Extension treatment: The spiral steel pipe is extended by circumferential butt weld. After the weld is fully welded, the excess part is ground smooth. Stiffening plates are evenly arranged at the joint. The material of the stiffening plates is the same as that of the spiral steel pipe. Step 3: Anchor plate prefabrication: A connecting plate is installed at one end of the inclined steel pipe near the pier body. The connecting plate is matched and welded to the anchor plate. The anchor plate is made of Q345C steel plate. The anchor plate is provided with steel bar through holes. The steel bar through holes are adapted to the HRB400 steel bars pre-embedded in the pier body.

2. The method for processing inclined steel pipes according to claim 1, characterized in that: In step two, the number and spacing of the stiffening plates are determined according to the stress requirements at the joint of the spiral steel pipe.

3. The method for processing inclined steel pipes according to claim 1, characterized in that: In step three, the inclined steel pipe is fully welded to the connecting plate, and the connecting plate is fully welded to the anchor plate. The weld thickness is not less than 4.8 mm and the width is not less than 12.8 mm. After the welding is completed, the weld is visually inspected.

4. A slanted steel tube processing structure obtained by any one of the processing methods described in claims 1-3, characterized in that: The steel pipe includes several sets of stiffening plates evenly arranged at the joint of the steel pipe. A connecting plate is fully welded to one end of the steel pipe near the pier body. The connecting plate is fully welded to the anchor plate. Several sets of reinforcing bar through holes are provided on the anchor plate.

5. The installation method for cast-in-place beam construction according to claim 3, characterized in that: Step 1: Preliminary preparation: When constructing the foundation, pre-embed φ25mm precision threaded steel anchor bolts, which are used to fix the column base; When constructing the pier body, HRB400 anchoring steel bars are pre-embedded at the corresponding installation positions of the inclined steel pipes, and the spacing of the HRB400 anchoring steel bars is 30cm. Step 2: Vertical steel pipe installation. An 80t truck crane is used to lift the vertical steel pipe and weld it to the column base. The column base and the vertical steel pipe are pre-welded and then installed in place as a whole. The vertical steel pipe is connected to the pier wall-mounted embedded parts through a 2[32b type steel connection system to form an initial stable frame. Step 3: Installation of inclined steel pipe. Weld two lifting lugs to the top of the inclined steel pipe and use an 80t truck crane for hoisting. Use a φ20 steel wire rope to control the lifting angle of the inclined steel pipe during hoisting and adjust the angle of the inclined steel pipe to 19.7°. Step 4: Fixing method: Temporarily fix the bottom of the inclined steel pipe, then weld the pre-set anchor plate of the inclined steel pipe to the HRB400 steel bar pre-embedded in the pier body. The length of the welding is 10d when using single-sided welding and 5d when using double-sided welding. Temporarily connect the inclined steel pipe to the vertical steel pipe with 10# channel steel. Step 5: Final Fixing: Remove the temporary channel steel, weld the bottom of the inclined steel pipe to the column base, and then install the 2[20b type steel connecting system to form an integral load-bearing structure with the inclined steel pipe, vertical steel pipe and connecting system.

6. The installation method for cast-in-place beam construction according to claim 4, characterized in that: In step one, the pre-embedded anchor bolts need to be calibrated to ensure that their axis coincides with the axis of the column base mounting hole, with a deviation of no more than 2mm.

7. The installation method for cast-in-place beam construction according to claim 5, characterized in that: In step two, when the 80t truck crane lifts the vertical steel pipe, the boom length is set to 40m and the working radius is controlled at 15m to ensure that the lifting capacity meets the requirements during the lifting process.

8. The installation method for cast-in-place beam construction according to claim 6, characterized in that: In step three, the lifting lug is made of the same steel as the inclined steel pipe, the lifting lug is fully welded, and a load-bearing test is conducted after the lifting lug is welded. Before using the φ20 steel wire rope, it is necessary to check for broken wires, wear, etc. Steel wire ropes that do not meet the requirements must not be used.

9. The installation method for cast-in-place beam construction according to claim 7, characterized in that: In step four, when welding the inclined steel pipe to the HRB400 steel bar embedded in the pier body, positioning welding must be performed first. After the position is accurately adjusted, formal welding can be carried out. Wind protection measures are adopted during the welding process to avoid porosity in the weld.

10. The installation method for cast-in-place beam construction according to claim 8, characterized in that: In step five, the connection between the connecting system and the inclined steel pipe and the vertical steel pipe is made by welding, and the weld requirements are the same as those for the welding of the inclined steel pipe and the anchor plate.