360° rotation leveling type double-cabin cooperative operation construction method and system
By using a 360° rotating and leveling dual-crane collaborative operation method, the phase difference and attitude deviation problems during the collaborative rotation of dual cranes in the existing technology have been solved. This method achieves force balance and attitude accuracy control of the segmental beam during the rotation process, ensuring construction safety and positioning accuracy.
Patent Information
- Application Number
- CN202611069819.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-17
- Publication Date
- 2026-11-24
AI Technical Summary
The existing dual-crane operation system is prone to phase difference when rotating segment beams in coordination, resulting in uneven stress on the lifting points, causing the segment beams to tilt or twist in the air. The attitude accuracy during rotation is difficult to guarantee, and the impact of construction wind speed is not considered, posing safety hazards. Furthermore, it lacks a comprehensive evaluation of multi-degree-of-freedom positioning accuracy.
A 360° rotating and leveling dual-crane collaborative operation method is adopted. The main crane A and the main crane B lift the crane together, and the lifting force is dynamically distributed in real time to achieve force balance throughout the rotation. Adaptive speed correction and height compensation are performed during the rotation. Combined with the coupling relationship between the rotation angle and the elastic deformation of the lifting rope, the posture accuracy of the glued surface is ensured. The influence of wind speed is monitored in real time, and a comprehensive positioning accuracy evaluation standard is established.
This ensured that the normal deviation of the glued joint surface of the segmental beam was within the design allowable range during rotation, and that the rotation phase synchronization error of the main crane was less than 0.002 rad. It eliminated the dynamic imbalance of the lifting force, ensured rotation safety under high-altitude and high-wind conditions, and provided a quantitative basis for evaluating positioning accuracy.
Smart Images

Figure CN123151284A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of bridge construction technology, and more specifically, relates to a 360° rotating and leveling type double overhead crane collaborative operation construction method and system. Background Technology
[0002] Precast segmental beam cantilever construction is one of the mainstream construction methods for modern urban viaduct engineering. Segmental beams are produced in the prefabrication yard according to the matching pouring sequence. After being finished, they are transported to the beam lifting station, lifted by a gantry crane to the beam transport vehicle on the bridge deck, and then transported by the beam transport vehicle to the tail of the bridge erecting machine. Finally, the main crane of the bridge erecting machine completes the symmetrical cantilever assembly of each span.
[0003] In existing construction techniques, the transfer of segmental beams from the receiving position on the bridge deck transport vehicle to the girder assembly position typically requires the following actions: vertical lifting, longitudinal movement, lateral fine-tuning, and repositioning if there is a planar angular deviation. When the longitudinal axis of the segmental beam is not aligned with the axis of the main beam of the bridge erecting machine (such as in curved bridges, curved bridges, or situations where there is an angular difference between the feeding direction and the erection direction), a rotation operation must be performed on the segmental beam in the air to align its girder assembly surface with the end face of the matching beam.
[0004] However, the existing dual-crane operation system has the following shortcomings: First, the two cranes independently control their rotation mechanisms, lacking a rotation phase synchronization mechanism. When rotating the segmental beams in coordination, phase differences are easily generated, leading to uneven stress on the lifting points on both sides and causing the segmental beams to tilt or twist in the air. Second, the existing system has not established a coupling compensation model between the rotation angle and vertical leveling. When the center of gravity of the segmental beam is eccentric, the tension of the lifting steel ropes on both sides changes dynamically with the angle during rotation, causing additional spatial attitude deviation of the segmental beams during rotation, which cannot guarantee the attitude accuracy of the glued joint surface. Third, the existing rotation speed planning does not consider the real-time impact of construction wind speed on the rotation torque, resulting in safety hazards in rotation operations under high-altitude and windy conditions. Fourth, the existing operation process lacks a quantitative evaluation standard for multi-degree-of-freedom comprehensive positioning accuracy, relying solely on manual visual inspection or local measurement to determine the positioning status, resulting in poor accuracy consistency.
[0005] The aforementioned shortcomings have hindered the efficient, precise, and safe construction of large segmental beams (each weighing over 100 tons and with a width exceeding 20 meters). There is an urgent need for a new construction method with functions such as rotation-leveling coupling compensation, dual crane phase synchronous control, real-time wind load correction, and comprehensive positioning accuracy evaluation. Summary of the Invention
[0006] To solve the above technical problems, this invention proposes a 360° rotating leveling double overhead crane collaborative construction method, comprising: Step S1: The main crane A and the main crane B work together to lift the segment beam. When the segment beam is suspended, the lifting force of the main crane A and the main crane B is dynamically distributed in real time according to the rotation state and the eccentricity of the center of gravity of the segment beam, so that the lifting force on both sides remains balanced throughout the rotation. Step S2: The main crane A and the main crane B work together to drive the segment beam to rotate within a 360° range. During the rotation, the rotation speed command is adaptively corrected based on the amount of external environmental interference and the synchronization status of the rotation mechanisms of the main crane A and the main crane B. Step S3: During the rotation process, based on the coupling relationship between the rotation angle and the elastic deformation of the hoisting rope, height compensation is synchronously applied to the main crane A and the main crane B. Step S4: Verify the glued surfaces closely to confirm the matching relationship. After that, apply glue and bond the gluing. Apply temporary prestress, install the suspension rods and complete the tensioning. The main gantry crane A and the main gantry crane B unload and release the lifting gear simultaneously. Transfer the stress system of the segmental beam to the suspension rods to complete the segmental beam cantilever assembly and positioning.
[0007] Furthermore, before step S1, the following steps are also included: establishing a spatial reference coordinate system fixed to the bridge structure before construction, completing the zeroing calibration of the rotating mechanisms of the main crane A and the main crane B, and measuring the physical parameters of the segmental beams required for lifting force distribution calculation and rotation control. Furthermore, determining whether to initiate a fine-tuning procedure based on a single comprehensive positioning accuracy index includes: during fine-tuning, correcting the out-of-tolerance direction sequentially according to the weight of each degree of freedom until the comprehensive positioning accuracy index meets the requirements.
[0008] Furthermore, between steps S3 and S4, the following steps are also included: comprehensively measuring the positional deviation of the segmental beam in the four degrees of freedom of longitudinal, transverse, vertical and rotational angles, calculating the comprehensive positioning accuracy index, and determining whether to start the fine-tuning procedure based on the comprehensive positioning accuracy index.
[0009] Furthermore, step S3 also includes: after the rotation is completed, evaluating the leveling status of the segmental beam, and correcting it through the leveling mechanism if the requirements are not met.
[0010] Furthermore, the real-time dynamic distribution of the lifting force between main crane A and main crane B includes: , in, For a moment The main crane A is at the current rotation angle of the segmental beam. The lifting force below, For a moment angular acceleration of beam rotation in time segment It is the acceleration due to gravity. The distance between the center points of the main crane A and the main crane B. This is the dynamic load compensation coefficient. For the mass of segmental beams, For the modulus of the eccentricity of the segmental beam, The eccentricity angle of the segmental beam. Let be the moment of inertia of the segmental beam; , in, For a moment The main crane B is at the current rotation angle of the segmental beam. The lifting force below.
[0011] Furthermore, adaptive correction of the rotation speed command includes: time Rotation speed command of main crane A : , in, For a moment The trapezoidal profile of the main crane A is used to plan the angular velocity. To the current rotation angle Real-time wind speed at the construction site Wind load correction factor The rotational phase error between main crane A and main crane B The rotational phase synchronization error correction factor.
[0012] Furthermore, step S3 also includes: continuously monitoring the absolute value of the rotation phase error during the rotation process. ,when An audible and visual alarm is triggered when the first threshold is exceeded; when If the second threshold is exceeded, the rotation will be paused and a shutdown alarm will be issued. The rotation will resume after manual confirmation and investigation of the cause.
[0013] Furthermore, applying height compensation synchronously to main crane A and main crane B includes: , in, To the current rotation angle Height compensation applied synchronously to main crane A and main crane B. The initial rotation angle of the segmental beam when rotation begins. For coupling compensation correction coefficients, For the mass of segmental beams, It is the acceleration due to gravity. For the modulus of the eccentricity of the segmental beam, The eccentricity angle of the segmental beam. The distance between the center points of the main crane A and the main crane B. The combined vertical stiffness of the hoisting rope system of main crane A and main crane B; High compensation The hoisting height commands of main crane A and main crane B are synchronously superimposed and executed.
[0014] This invention also proposes a 360° rotating leveling dual-crane collaborative construction system, comprising: The lifting force distribution module is used for the main crane A and main crane B to lift the segment beam in a coordinated manner. When the segment beam is suspended, the lifting force of the main crane A and main crane B is dynamically distributed in real time according to the rotation state and center of gravity eccentricity of the segment beam, so that the lifting force on both sides remains balanced throughout the rotation. The rotation speed command correction module is used to drive the segment beam to rotate within a 360° range in a coordinated manner by the main crane A and the main crane B. During the rotation, the rotation speed command is adaptively corrected according to the amount of external environmental interference and the synchronization status of the rotation mechanisms of the main crane A and the main crane B. The height compensation module is used to synchronously apply height compensation to the main crane A and the main crane B during rotation, based on the coupling relationship between the rotation angle and the elastic deformation of the hoisting rope. The cantilevered positioning module is used to verify the gluing surfaces closely. After confirming that the matching relationship is correct, the gluing is applied and bonded, temporary prestress is applied, the suspension rods are installed and tensioning is completed, the main gantry crane A and the main gantry crane B are unloaded and the lifting equipment is released simultaneously, and the stress system of the segmental beam is transferred to the suspension rods, thus completing the cantilevered positioning of the segmental beam.
[0015] In summary, the technical solutions conceived by this invention have the following beneficial effects compared with the prior art: (1) A rigid coupling compensation model between rotation angle and vertical leveling was established to eliminate the dynamic attitude deviation caused by the eccentricity of the segment beam's center of gravity, so that the normal deviation of the glued surface of the segment beam is kept within the design allowable range during the entire rotation process.
[0016] (2) A dual-crane rotation synchronization adaptive speed correction strategy based on phase error feedback was proposed, which achieved high-precision synchronization control of the rotation phase synchronization error between the main crane A and the main crane B not exceeding 0.002 rad, and eliminated the dynamic imbalance of the lifting force on both sides.
[0017] (3) The real-time wind speed signal at the construction site was introduced into the calculation of the rotation speed command, and a wind load correction factor driven by the rotation torque margin was established to ensure the safety margin of rotation operation under high-altitude and strong wind conditions.
[0018] (4) A weighted comprehensive positioning accuracy index with longitudinal position deviation, lateral position deviation, vertical elevation deviation and rotation angle deviation as variables is proposed. The positioning quality is characterized by a single dimensionless value, providing a quantitative decision-making basis for subsequent glued splicing construction. Attached Figure Description
[0019] Figure 1 This is a flowchart of the method in Embodiment 1 of the present invention; Figure 2 This is a system structure diagram of Embodiment 2 of the present invention; Figure 3 This is a flowchart of the method in Embodiment 3 of the present invention. Detailed Implementation
[0020] To better understand the above technical solutions, the following will provide a detailed explanation of the technical solutions in conjunction with the accompanying drawings and specific implementation methods.
[0021] The method provided by this invention can be implemented in a terminal environment that may include one or more of the following components: a processor, a storage medium, and a display screen. The storage medium stores at least one instruction, which is loaded and executed by the processor to implement the method described in the following embodiments.
[0022] A processor may include one or more processing cores. The processor uses various interfaces and lines to connect various parts of the terminal, and performs various functions and processes data by running or executing instructions, programs, code sets or instruction sets stored in the storage medium, and by calling data stored in the storage medium.
[0023] Storage media can include random access memory (RAM) or read-only memory (ROM). Storage media can be used to store instructions, programs, code, code sets, or instructions.
[0024] The display screen is used to show the user interface of each application.
[0025] In addition, those skilled in the art will understand that the structure of the terminal described above does not constitute a limitation on the terminal. The terminal may include more or fewer components, or combine certain components, or have different component arrangements. For example, the terminal may also include radio frequency circuits, input units, sensors, audio circuits, power supplies, and other components, which will not be described in detail here.
[0026] Example 1 like Figure 1 As shown in the figure, this embodiment proposes a 360° rotating leveling double overhead crane collaborative operation construction method, including: Step S1: The main crane A and the main crane B simultaneously lift the segment beam. Under the suspended state of the segment beam, the lifting force of the main crane A and the main crane B is dynamically distributed in real time according to the rotation state and the eccentricity of the center of gravity of the segment beam, so that the lifting force on both sides remains in force balance throughout the rotation. Step S2: The main crane A and the main crane B work together to drive the segment beam to rotate within a 360° range. During the rotation, the rotation speed command is adaptively corrected based on the amount of external environmental interference and the synchronization status of the rotation mechanisms of the main crane A and the main crane B. Step S3: During the rotation process, height compensation is applied synchronously to the main crane A and the main crane B based on the coupling relationship between the rotation angle and the elastic deformation of the hoisting rope. Step S4: Verify the glued surfaces closely to confirm the matching relationship. After that, apply glue and bond the gluing. Apply temporary prestress, install the suspension rods and complete the tensioning. The main gantry crane A and the main gantry crane B unload and release the lifting gear simultaneously. Transfer the stress system of the segmental beam to the suspension rods to complete the segmental beam cantilever assembly and positioning.
[0027] Example 2 like Figure 2 As shown, this embodiment proposes a 360° rotating and leveling dual-crane collaborative construction system, including: The lifting force distribution module is used for the synchronous lifting of the segment beam by the main crane A and the main crane B. When the segment beam is suspended, the lifting force of the main crane A and the main crane B is dynamically distributed in real time according to the rotation state and the eccentricity of the center of gravity of the segment beam, so that the lifting force on both sides remains balanced throughout the rotation. The rotation speed command correction module is used to drive the segment beam to rotate within a 360° range in a coordinated manner by the main crane A and the main crane B. During the rotation, the rotation speed command is adaptively corrected according to the amount of external environmental interference and the synchronization status of the rotation mechanisms of the main crane A and the main crane B. The height compensation module is used to synchronously apply height compensation to the main crane A and the main crane B during rotation, based on the coupling relationship between the rotation angle and the elastic deformation of the hoisting rope. The cantilevered positioning module is used to verify the gluing surfaces closely. After confirming that the matching relationship is correct, the gluing is applied and bonded, temporary prestress is applied, the suspension rods are installed and tensioning is completed, the main gantry crane A and the main gantry crane B are unloaded and the lifting equipment is released simultaneously, and the stress system of the segmental beam is transferred to the suspension rods, thus completing the cantilevered positioning of the segmental beam.
[0028] Since Example 2 is based on Example 1, it will not be described again.
[0029] Example 3 This invention employs two 160-ton main cranes (main crane A and main crane B) and two 10-ton auxiliary cranes (auxiliary crane C and auxiliary crane D) to form a four-crane collaborative operation system. The technical specifications and spatial layout of each piece of equipment are as follows.
[0030] Main crane A and main crane B (1 set each, 2 sets in total): Main crane A and main crane B have identical structural configurations, with a rated lifting capacity of 160 t (excluding the weight of the lifting gear). Each main crane is equipped with a 360° rotating lifting gear. The rotating mechanism is driven by a geared motor with an encoder resolution of no less than 0.001 rad, enabling continuous rotation of the lifting gear at any angle relative to the crane's travel direction. The lower frame of the lifting gear has two longitudinal leveling cylinders and two lateral leveling cylinders built-in. The stroke of the longitudinal leveling cylinders is... (Unit: mm), the stroke of the horizontal leveling cylinder is... (Unit: mm) Working together, these two mechanisms allow for independent fine-tuning of the longitudinal and transverse slopes of the suspended segmental beams without moving the crane's traveling mechanism. The main crane's transverse movement mechanism is driven by hydraulic cylinders, and the overall transverse travel of the main crane is... Lateral speed It is used for lateral alignment of segmental beams and correction of planar deviations in curved sections; the maximum lifting height of the main gantry crane is 35 m above the completed bridge deck, and the lifting speed does not exceed 2.5 m / min under heavy load and 5.0 m / min under no-load. Main gantry crane A is located in the front area of the main beam of the bridge erecting machine (closer to the side of the segment to be assembled), and main gantry crane B is located in the rear area of the main beam (closer to the side of the assembled segment). The two gantry cranes travel independently on the longitudinal guide rails of the upper chord of the main beam, and the traveling speed does not exceed 2.5 m / min under heavy load and 15.0 m / min under no-load.
[0031] Auxiliary cranes C and D (1 set each, 2 sets in total): Each auxiliary crane has a rated lifting capacity of 10 t and is positioned on either side of the main crane A (auxiliary crane C is located on the outer side of the front end of the main beam, and auxiliary crane D is located on the outer side of the rear end of the main beam). They share the longitudinal guide rails of the upper chord of the main beam with main cranes A and B, but use independent travel drive units and remote control operating systems. There are no electrical interlocking constraints between them and main cranes A and B. The main purpose of the auxiliary cranes is to simultaneously complete the lateral transport and positioning of small construction equipment such as lifting and leveling auxiliary tools, temporary prestressed threaded steel bars, tensioning jacks, hole inspectors, and lower crossbeams on the bridge during the lifting, rotation, leveling, and fine-tuning of the segmental beams by main cranes A and B. This ensures that these tools are in place before the main cranes unload the segmental beams, eliminating waiting time caused by sequential operations and shortening the total construction period for a single cycle.
[0032] Lateral safety distance control between main and auxiliary overhead cranes: To prevent collisions between the lateral movement of the auxiliary overhead crane and the lateral movement of the main overhead crane, the lateral safety distance between the auxiliary overhead crane and the main overhead crane is controlled. ( The minimum permissible safety distance relative to the nearest main crane. (Unit: m) Determined by the following formula: , in, Auxiliary overhead crane Minimum safe distance (m) between the main crane outline and the nearest side. : Static minimum safe clearance (m), value , The maximum lateral speed of the main crane (m / s) is determined by the lateral travel distance. Determined by the design lateral movement time, typical values are taken. (Right now ), Emergency braking response time (s) of the linkage control system, value , : Main crane lateral braking deceleration (m / s²), value , The lateral outer dimension (m) of the crane body in the direction of travel is determined by the equipment parameters. The lateral outer dimension (m) of the main crane in the traveling direction is determined by the equipment parameters.
[0033] The linkage control system assists the crane in its movement. The frequency is collected in real time to measure the lateral position of each crane. When the measured distance between the auxiliary crane and the main crane is less than 100 mm, the lateral position of each crane is measured in real time. When the time comes, the auxiliary crane will automatically decelerate to a stop, and wait for the spacing to return to normal. Walking can only resume after that.
[0034] Efficiency Improvement Through Main and Auxiliary Collaborative Parallel Operation: Assume the total construction period required to complete one segmental beam cantilever unit using a sequential operation method (auxiliary equipment only begins unloading after the main crane has finished) is... (Unit: seconds), the total time for completing the same unit in a master-slave collaborative parallel manner is... (Unit: s), then the main and auxiliary synergy time-saving rate for: , in, : Time-saving rate of main and auxiliary equipment coordination, value range The larger the value, the more time is saved by parallel processing. Total construction period (s) for single-segment beam cantilever assembly cycle under sequential operation method. Total construction period (s) for a single segment beam cantilever assembly cycle under the main and auxiliary collaborative parallel mode. : A complete set of auxiliary crane tasks that can be performed in parallel with the main crane's rotation, leveling, and fine-tuning operations. : No. The parallel overlap coefficient of the auxiliary crane task. This indicates that the task completely overlaps with the main crane operation (operating in parallel). Indicates partial overlap. This indicates that parallelism is not possible. : No. The duration (s) of the auxiliary crane task.
[0035] Based on the analysis of typical construction processes, auxiliary tasks that can be executed in parallel are identified. This includes: ① During the rotation of the main crane (step S3), the auxiliary crane transfers the temporary prestressed fine-rolled threaded steel bars to both sides of the joint to be spliced; ② During the leveling and fine-tuning of the main crane (steps S4 and S5), the auxiliary crane completes the positioning and readiness of the epoxy resin structural adhesive mixing tool, tensioning jack, and borehole detector; ③ During the waiting period after the main crane completes fine-tuning (measurement gap in step S5), the auxiliary crane completes the pre-positioning of the lower crossbeam. The above three types of parallel tasks correspond to typical... The values are respectively , , Overall time saving rate Typical interval is That is, each cycle can save approximately The total construction period.
[0036] like Figure 3 As shown in the figure, this embodiment proposes a 360° rotating leveling double overhead crane collaborative construction method, which includes the following steps: Step S1: Establishment of spatial reference coordinate system and calibration of dual crane system Before the segmental beam lifting operation begins, the direction along the bridge axis of the currently erected pier shall be taken as... The transverse direction of the bridge axis, perpendicular to the bridge axis, is: The positive direction of the axis is vertically upward. Establish a right-handed spatial reference coordinate system along the positive axis. - Origin of coordinates Take the vertical projection of the center point of the top of any pier within the span of this construction project onto the completed bridge deck. This coordinate system is fixed to the bridge structure and remains unchanged throughout the entire collaborative operation.
[0037] After establishing the coordinate system, the rotary encoders of main crane A and main crane B are zeroed out, the initial coordinates of each lifting point center in the coordinate system are recorded, and the initial distance between the lifting point centers of main crane A and main crane B is determined. (Unit: m).
[0038] The mass parameters of the segmental beam to be erected were measured: a dedicated weighing sensor was used to measure the mass of the segmental beam. (Unit: kg); The eccentricity vector of the center of gravity of the segmental beam relative to the center of the line connecting the two suspension points in its body coordinate system is determined by three-dimensional scanning or symmetrical loading method, and the magnitude of the eccentricity moment is extracted. (Unit: m) and eccentricity direction angle (Unit: rad, defined as the angle between the eccentric vector and the positive direction of the longitudinal axis of the segmental beam). The suspension test method is used to determine the segmental beam's rotation around... Moment of inertia of the shaft (Unit: kg·m²).
[0039] The combined vertical stiffness of the hoisting rope system of main crane A and main crane B at the current working height was determined using finite element analysis combined with on-site tension testing. (Unit: N / m). Record the maximum design rotational torque at the current construction height. (Unit: N·m), and air density Longitudinal windward area of segmental beam (Unit: m²) and lateral windward area (Unit: m²)
[0040] After completing the above parameter calibration, initialize auxiliary cranes C and D: move them to the standby positions at the front and rear ends of the main beam, respectively, and confirm that the measured lateral distances between each crane and main crane A and main crane B are not less than [value missing]. This activates the real-time collision avoidance monitoring function of the linkage control system. At this point, step S1 completes all calibration and initialization, providing uniquely determined reference data for subsequent steps S2 to S6.
[0041] Step S2: Dynamic distribution of segmental beam lifting and rotational coupling load After calibration in step S1, the lifting devices of the main crane A and the main crane B are connected to the lifting points at both ends of the segment beam, and the connection between the lifting devices and the segment beam body is locked.
[0042] During the lifting process, the segmental beam is at any angle of rotation. (Unit: rad) Angular acceleration of arbitrary rotation (Unit: rad / s²) at time The main crane A is at the current rotation angle of the segmental beam. Lifting force (Unit: N) Calculated in real time using the following formula: , Lifting force of main crane B (Unit: N) Determined by total weight balance conditions: , in, : at the rotation angle ,time Below, the lifting force (N) of the main crane A; : at the rotation angle ,time Below, the lifting force (N) of the main crane B; The mass (kg) of the segmental beam is obtained from the calibration in step S1; Gravitational acceleration; The modulus (m) of the eccentricity of the segmental beam is determined by step S1; The eccentricity angle of the center of gravity (rad) is determined by step S1; The center-to-center distance (m) between the lifting points of main crane A and main crane B is determined by step S1; The current rotation angle (rad) of the segmental beam is defined as the positive direction of the longitudinal axis of the segmental beam relative to the coordinate system. The included angle of the axis; Segmental beam The moment of inertia of the shaft (kg·m²) is determined by step S1; The rotational angular acceleration of the segmental beam (rad / s²) is calculated in real time by the second-order difference of time from the angular displacement sensor. Dynamic load compensation coefficient, with a value range of: Typical value It reflects the dynamic fluctuation margin of lifting force caused by rotational inertia.
[0043] During hoisting, the segmental beam is smoothly lifted to a clearance height of no less than 0.3 m above the support surface of the bridge beam transport vehicle, and then kept suspended. The linkage control system confirms this. and The measured values are all within the theoretical values. Within this timeframe, step S3 can proceed. During the lifting and hovering confirmation process performed by the main overhead cranes A and B, auxiliary overhead crane C transports the temporary prestressed fine-rolled threaded steel bars and tensioning tools longitudinally along the main beam to the corresponding position of the joint to be spliced; auxiliary overhead crane D transports the epoxy resin structural adhesive mixing equipment to the joint operation station, pre-positioning it for the subsequent adhesive splicing construction in step S6, and utilizing the hovering verification time of the main overhead cranes to achieve the first batch of parallel tasks.
[0044] Step S3: Coordinated 360° Rotation Adaptive Speed Control of Two Overhead Cranes After confirming the hovering in step S2, the cooperative rotation control program is started. Using the coordinate system from step S1... The positive axis is the zero position for rotation; set the target rotation angle. (Unit: rad) is the total amount of rotation required for the longitudinal axis of the segmental beam to align with the normal of the glued surface.
[0045] Define the cumulative angle of the rotary encoder of the main crane A as follows: (Unit: rad) The cumulative angle of the rotary encoder of the main crane B is... (Unit: rad), the relationship between the segmental beam rotation angle and the encoder reading is as follows: The rotational phase error between main crane A and main crane B is defined as: During the coordinated rotation, the rotation speed command of the main crane A... (Unit: rad / s) Calculated in real time using the following formula: , in, For a moment The angular velocity (unit: rad / s) of the trapezoidal profile of the main crane A is planned, and the corresponding planned values are taken in the acceleration segment, the constant speed segment and the deceleration segment respectively. To the current rotation angle Real-time wind speed at the construction site Wind load correction factor The rotational phase error between main crane A and main crane B The rotational phase synchronization error correction factors are defined as follows: , , , in, Main crane A at time The rotational speed command (rad / s); the rotational speed command of the main crane B is taken from... That is, both vehicles use the same speed command as a reference and only pass through The sign of the factor enables differential correction; :time The angular velocity (rad / s) of the trapezoidal profile of the main crane A is pre-set in the construction plan, with a maximum value not exceeding [missing value]. ; Real-time wind load correction factor, representing the proportion of rotational torque margin consumed under the current rotation angle and wind speed; Air density (kg / m³), determined by step S1, is taken as follows: ; The real-time wind speed (m / s) at the construction site is collected in real time by a wind speed sensor installed at the end of the main beam of the bridge erecting machine. The segmental beam at the current rotation angle Projected area perpendicular to the wind direction (m²); The longitudinal windward cross-sectional area (m²) of the segmental beam is determined by step S1; The transverse windward cross-sectional area (m²) of the segmental beam is determined by step S1; : Segmental beam at rotation angle The drag coefficient (dimensionless) at the following values ranges from 100 to 100. Determined by piecewise interpolation based on rotation angle; typical value: when Time to take ,when Time to take ; The effective lever arm (m) of the wind load application point relative to the axis of rotation is taken as the width of the segmental beam. ; The rated maximum rotational torque (N·m) of the main crane rotation mechanism is determined by step S1; : Lower limit of wind load correction factor, value range That is, the rotational speed is not lower than the planned value under any wind speed. ; Rotational phase error (rad) between main crane A and main crane B; Synchronization gain coefficient, with a value of To control the sensitivity of phase error to velocity correction; : Symbolic function, when Time to take ,when Time to take This causes the leading overhead cranes to slow down and the lagging overhead cranes to accelerate. The target rotation angle (rad) is determined by step S1; Synchronization control index, with a value of This makes the synchronization correction sensitive when the phase error is large and gentle when it is small, thus avoiding violent oscillations in the speed command.
[0046] During the rotation, if Trigger an audible and visual alarm; if The rotation will automatically pause and trigger an alarm, only resuming after manual confirmation. Rotate to the target angle. Then, main crane A and main crane B simultaneously lock their rotating mechanisms, proceeding to step S4. Throughout step S3, auxiliary crane C and auxiliary crane D maintain a safe lateral clearance. Parallel execution of Type ① parallel tasks (transfer of temporary prestressed components) under constraints, with parallel overlap coefficient. Duration of rotation This is the complete parallel window for this batch of tasks.
[0047] Step S4: Rotation-leveling coupling height compensation during rotation During the rotation process in step S3, due to the eccentricity of the segmental beam's center of gravity, the change in the rotation angle causes the forces on the two suspension points to change accordingly. Change (see step S2) The formula (which causes changes in the tension of the hoisting ropes, altering the elastic deformation of the rope system, and ultimately leading to fluctuations in the overall center of gravity elevation of the segmental beam) is used. To eliminate this fluctuation, height compensation is applied synchronously to both main crane A and main crane B during rotation. (Unit: m), its calculation formula is: , in, At the current rotation angle The height compensation (m) applied synchronously to the main crane A and the main crane B is positive when it indicates that a small synchronous lifting is required. The initial rotation angle (rad) of the segment beam when it starts rotating in step S3 is recorded after the encoder is zeroed in step S1. : Coupling compensation correction coefficient, with a value range of Typical value This is used to correct for higher-order elastic deformation terms and geometric changes in rope length that are ignored when deriving the comprehensive compensation formula.
[0048] During the rotational execution in step S3, the linkage control system uses Sampling frequency reading Substitute the real-time value into the above formula to calculate. Simultaneously, the hoisting control units of main crane A and main crane B are sent to correct the hoisting height commands of the two cranes by superimposing correction amounts, so that the fluctuation of the segment beam's center of gravity elevation during the entire rotation does not exceed [a certain value]. .
[0049] After completing the coupling height compensation, the longitudinal inclination slope of the segmental beam is collected using a dual-axis tilt sensor installed on the segmental beam lifting frame. With lateral slope Define the comprehensive leveling error index. for: , in: For vertical leveling weighting coefficients, This refers to the horizontal balancing weighting coefficient; (i.e., 4‰) is the allowable longitudinal slope (dimensionless); (i.e., 3‰) is the permissible transverse slope (dimensionless). When When the leveling meets the requirements, proceed to step S5; when At this time, the longitudinal leveling cylinder built into the spreader is activated (stroke). ) and lateral leveling cylinder (stroke) ) respectively and Perform independent fine-tuning, and recalculate after adjustment. Until the requirements are met. Throughout step S4, auxiliary crane C and auxiliary crane D perform parallel tasks of type ② (tensioning the hydraulic jack, preparing the borehole detector, and initially moving the lower crossbeam) under the constraint of a safe distance. The parallel overlap coefficient is... This will further accumulate collaborative time-saving contributions.
[0050] Step S5: Evaluation and fine-tuning of multi-degree-of-freedom integrated positioning accuracy After leveling is achieved in step S4, a total station control network deployed on the main beam of the bridge erecting machine and the assembled segment beams is used to perform three-dimensional coordinate measurements of the spatial position of the segment beams, obtaining the current center of the glued surface of the segment beam in the coordinate system. - The measured coordinates are compared with the design target coordinates to obtain the longitudinal position deviation. (Unit: m) Lateral position deviation (Unit: m) Vertical elevation deviation (Unit: m) and rotation angle deviation (Unit: rad)
[0051] Define the comprehensive positioning accuracy index (Dimensionless) is: , in, The comprehensive positioning accuracy index is a single numerical value that characterizes the overall positioning quality of the segmental beam in four degrees of freedom. Vertical position weighting coefficient, value ; : Horizontal position weighting coefficient, value ; Vertical elevation weighting coefficient, value ; Rotation angle weighting coefficient, value The sum of the weighting coefficients satisfies ; The deviation (m) between the longitudinal position of the center of the segmental beam glued joint and the design position, expressed in coordinate system. The axial direction is positive; Longitudinal position tolerance (m), value ; : Lateral position deviation of the center of the segmental beam glued joint surface (m), in coordinate system The axial direction is positive; : Allowable deviation of lateral position (m), value ; Vertical elevation deviation (m) of the center of the glued joint surface of the segmental beam, in coordinate system The axial direction is positive; Permissible vertical elevation deviation (m), value ; The angular deviation (rad) of the longitudinal axis of the segmental beam relative to the rotation angle of the target is taken as the absolute value in the calculation. : Tolerance for rotation angle (rad), value .
[0052] Judgment criteria: When When the positioning accuracy meets the specification requirements, proceed to step S6; when When, the positioning accuracy is qualified; when At that time, the positioning accuracy is excellent; when At that time, the fine-tuning process is initiated.
[0053] The fine-tuning procedure corrects the out-of-tolerance degrees of freedom sequentially: following the order of weight coefficients from largest to smallest, it prioritizes correcting the direction with the largest out-of-tolerance. Specifically, this is achieved through the coordinated longitudinal movement mechanisms of main cranes A and B. Correction is achieved through the linkage of the transverse hydraulic cylinder. (lateral movement) (Can cover construction curve deviations) and correct them through linkage with the hoisting winch. Fine-tuning via a rotating mechanism After each unidirectional fine-tuning, the measurement and calculation are repeated. , loop until Until then. During the measurement waiting period in step S5 (total station observation time approximately 60–90 s), auxiliary cranes C and D perform the third type of parallel task (final positioning of the lower crossbeam), with a parallel overlap coefficient. This ensures that all the auxiliary equipment required for step S6 is ready by the end of step S5, achieving a seamless connection.
[0054] Step S6: Verification of glued joint alignment and temporary prestressing construction After the overall positioning accuracy in step S5 is met, the following verification is performed on the glued joint surface: Start the leveling cylinders of the lifting devices of main crane A and main crane B to ensure that the glued joint surface of the segmental beam is in... Slowly move the beam in the plane towards the end face of the matching beam, and stop when the distance between the two faces is about 200mm. The construction personnel will then visually inspect and measure the reserved shear keys, the center of the prestressed ducts, and the outer contour of the beam on the glued surface to confirm that the matching relationship is correct.
[0055] After verification, the segmental beam is slowly advanced until the glued joint surface separates by approximately 30 mm. Epoxy structural adhesive is mixed according to the design ratio. Appropriate diameter sponge sealing rings are then attached to the prestressed duct openings on the glued joint surface. A single-sided coating process is used to apply a thickness of [missing information - likely a specific thickness]. Epoxy resin structural adhesive was applied. After the adhesive was applied, the main gantry crane A and main gantry crane B synchronously advanced the segmental beams to make the adhesive surfaces fit together. Temporary prestressed fine-rolled threaded steel bars were installed, and temporary prestress was applied using a single-end tensioning and left-right symmetrical method, with a target compressive stress of [value missing]. (Calculated based on the area of the joint surface), the allowable range is... .
[0056] After the temporary prestressing tensioning is completed, the suspension rods for the segmental beams are installed, and the prestressing of the rods is set according to the design value. Apply pressure to counteract the impact of subsequent segmental cantilever assembly on the center of gravity elevation of this segment. After the suspenders are tensioned and stabilized, main gantry cranes A and B simultaneously unload and release the lifting gear, transferring the stress system of the segmental beam to the suspended suspenders. At this point, step S6 is complete, and the 360° rotating and leveling dual-gantry crane collaborative construction of one segmental beam cantilever assembly unit is finished. The bridge erecting machine can then repeat steps S2 to S6 to construct the next segmental beam.
Claims
1. A construction method for coordinated operation of two overhead cranes with 360° rotation and leveling, characterized in that, include: Step S1: The main crane A and the main crane B work together to lift the segment beam. When the segment beam is suspended, the lifting force of the main crane A and the main crane B is dynamically distributed in real time according to the rotation state and the eccentricity of the center of gravity of the segment beam, so that the lifting force on both sides remains balanced throughout the rotation. Step S2: The main crane A and the main crane B work together to drive the segment beam to rotate within a 360° range. During the rotation, the rotation speed command is adaptively corrected based on the amount of external environmental interference and the synchronization status of the rotation mechanisms of the main crane A and the main crane B. Step S3: During the rotation process, height compensation is applied synchronously to the main crane A and the main crane B based on the coupling relationship between the rotation angle and the elastic deformation of the hoisting rope. Step S4: Verify the glued surfaces closely to confirm the matching relationship. After that, apply glue and bond the gluing. Apply temporary prestress, install the suspension rods and complete the tensioning. The main gantry crane A and the main gantry crane B unload and release the lifting gear simultaneously. Transfer the stress system of the segmental beam to the suspension rods to complete the segmental beam cantilever assembly and positioning.
2. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Before step S1, the following steps are also included: establishing a spatial reference coordinate system fixed to the bridge structure before construction, completing the zeroing calibration of the rotating mechanisms of the main crane A and the main crane B, and measuring the physical parameters of the segmental beams required for lifting force distribution calculation and rotation control.
3. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Determining whether to initiate a fine-tuning procedure based on a single comprehensive positioning accuracy index includes: during fine-tuning, correcting the out-of-tolerance direction sequentially according to the weight of each degree of freedom until the comprehensive positioning accuracy index meets the requirements.
4. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Between steps S3 and S4, the following steps are also included: comprehensively measuring the positional deviation of the segmental beam in the four degrees of freedom of longitudinal, transverse, vertical and rotational angles, calculating the comprehensive positioning accuracy index, and determining whether to start the fine-tuning procedure based on the comprehensive positioning accuracy index.
5. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Step S3 also includes: after the rotation is completed, the leveling status of the segment beam is evaluated, and if the requirements are not met, it is corrected by the leveling mechanism.
6. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, The real-time dynamic distribution of lifting force between main crane A and main crane B includes: , in, For a moment The main crane A is at the current rotation angle of the segmental beam. The lifting force below, For a moment angular acceleration of beam rotation in time segment It is the acceleration due to gravity. The distance between the center points of the main crane A and the main crane B. This is the dynamic load compensation coefficient. For the mass of segmental beams, For the modulus of the eccentricity of the segmental beam, The eccentricity angle of the segmental beam. Let be the moment of inertia of the segmental beam; , in, For a moment The main crane B is at the current rotation angle of the segmental beam. The lifting force below.
7. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Adaptive correction of rotation speed commands includes: time Rotation speed command of main crane A : , in, For a moment The trapezoidal profile of the main crane A is used to plan the angular velocity. To the current rotation angle Real-time wind speed at the construction site Wind load correction factor The rotational phase error between main crane A and main crane B The rotational phase synchronization error correction factor.
8. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Step S3 further includes: continuously monitoring the absolute value of the rotation phase error during the rotation process. ,when An audible and visual alarm is triggered when the first threshold is exceeded; when If the second threshold is exceeded, the rotation will be paused and a shutdown alarm will be issued. The rotation will resume after manual confirmation and investigation of the cause.
9. The 360° rotating leveling double overhead crane collaborative construction method as described in claim 1, characterized in that, Applying height compensation synchronously to main crane A and main crane B includes: , in, To the current rotation angle Height compensation applied synchronously to main crane A and main crane B. The initial rotation angle of the segmental beam when rotation begins. For coupling compensation correction coefficients, For the mass of segmental beams, It is the acceleration due to gravity. For the modulus of the eccentricity of the segmental beam, The eccentricity angle of the segmental beam. The distance between the center points of the main crane A and the main crane B. The combined vertical stiffness of the hoisting rope system of main crane A and main crane B; High compensation The hoisting height commands of main crane A and main crane B are synchronously superimposed and executed.
10. A 360° rotating and leveling dual-crane collaborative construction system, characterized in that, include: The lifting force distribution module is used for the main crane A and main crane B to lift the segment beam in a coordinated manner. When the segment beam is suspended, the lifting force of the main crane A and main crane B is dynamically distributed in real time according to the rotation state and center of gravity eccentricity of the segment beam, so that the lifting force on both sides remains balanced throughout the rotation. The rotation speed command correction module is used to drive the segment beam to rotate within a 360° range in a coordinated manner by the main crane A and the main crane B. During the rotation, the rotation speed command is adaptively corrected according to the amount of external environmental interference and the synchronization status of the rotation mechanisms of the main crane A and the main crane B. The height compensation module is used to synchronously apply height compensation to the main crane A and the main crane B during rotation, based on the coupling relationship between the rotation angle and the elastic deformation of the hoisting rope. The cantilevered positioning module is used to verify the gluing surfaces closely. After confirming that the matching relationship is correct, the gluing is applied and bonded, temporary prestress is applied, the suspension rods are installed and tensioning is completed, the main gantry crane A and the main gantry crane B are unloaded and the lifting equipment is released simultaneously, and the stress system of the segmental beam is transferred to the suspension rods, thus completing the cantilevered positioning of the segmental beam.