A method for reinforcing a steel pipe stiff core pile in a pile
By drilling grouting holes in defective piles, injecting grout, and inserting steel pipes to form stiff core piles, the problem of insufficient bearing capacity caused by the lack of rock embedment at the pile end was solved, achieving efficient pile reinforcement and load transfer, and avoiding reconstruction waste.
Patent Information
- Application Number
- CN202611368271.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-04
- Publication Date
- 2026-11-24
AI Technical Summary
In existing technologies, the absence of bedrock at the pile tip can lead to sediment or weak interlayers at the pile bottom, resulting in insufficient single pile bearing capacity and posing a threat to the safety of the engineering structure.
Grouting holes are drilled in the defective piles, and after cleaning the holes, grout is injected and steel pipes are inserted to form a stiff core pile, which directly transfers the load to the deep bearing layer and uses the original internal space of the pile body for reinforcement.
By using the core pile reinforcement method, the bearing capacity of the piles is improved, the waste of reconstruction is avoided, the load transfer is ensured to be reliable, the bearing capacity defect of the pile end not embedded in rock is solved, and the construction adaptability is strong.
Smart Images

Figure CN123153397A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of foundation reinforcement for building engineering, and in particular to a method for reinforcement using steel pipe core piles. Background Technology
[0002] Rock-socketed piles are widely used in important projects such as high-rise buildings and bridges due to their high bearing capacity and low settlement. However, in construction practice, it is not uncommon for the pile tip to be embedded in intact bedrock as required by the design.
[0003] Generally, the failure of pile tips to embed completely into bedrock is caused by the following reasons: excessively large borehole spacing or incorrect rock sample identification during the exploration phase, leading to inaccurate rock surface determination; insufficient consideration of rock surface undulations during the design phase, with overly idealized embedment depth requirements and a lack of dynamic adjustment principles; and technical errors in rock strata determination during the construction phase, such as misidentifying boulders as bedrock or misidentifying the top surface of strongly weathered rock as moderately weathered rock. These problems result in the pile tip bearing stratum failing to meet design requirements, often leading to sediment or weak interlayers at the pile bottom, resulting in a significant shortfall in the single pile's bearing capacity and posing a serious threat to the structural safety of the project. Summary of the Invention
[0004] To address the problem of insufficient bearing capacity of defective piles not embedded in bedrock in existing technologies, this application provides a method for reinforcing piles with steel pipe cores.
[0005] The technical solution for the steel pipe core pile reinforcement method provided in this application is as follows: A method for reinforcing piles with steel pipe cores includes the following steps: S1, Drill grouting holes in the pile body of the defective pile, with the grouting holes extending into the bearing layer below the pile tip; S2, Clean the bottom and wall of the grouting hole; S3, inject grout into the grouting hole; S4. After the grouting material is injected and before the grouting material initially sets, a steel pipe is inserted into the grouting hole, and the steel pipe extends to the bottom of the grouting hole. S5, the grout solidifies, and a stiff core pile is formed inside the defective pile. The stiff core pile directly transfers the load at the top of the pile to the deep bearing layer.
[0006] By adopting the above technical solution, step S1 can open a channel in the unqualified bearing layer such as sediment and / or weak layer in the defective pile body and pile bottom, breaking through the defective layer of the original pile bottom and directly contacting the qualified bearing layer, serving as the carrier space for subsequent grouting and steel pipe implantation, creating the preconditions for establishing a new force transmission path. Compared with re-piling, drilling only utilizes the internal space of the original pile body, without occupying external site space, making construction more adaptable; step S2 can clean and expose fresh concrete or rock surface on the hole wall, improving the interfacial adhesion between the grout and the hole wall (original pile body concrete), ensuring that the new and old materials can work together, and cleaning the sediment, mud skin and weak residue at the bottom of the hole, ensuring that the grout can directly contact the fresh rock surface at the bottom of the hole, avoiding the recurrence of weak interlayers at the bottom of the new pile; step S3 can fill the drilled space, serving as a medium for load transfer, and through adhesion with the hole wall, bonding the core pile with the... The original pile body is connected into a whole; step S4 can serve as the core reinforcing skeleton of the stiffened core pile, bearing most of the load and providing a certain compressive strength and bending capacity. The steel pipe and grouting material form a steel-concrete composite structure, with a bearing capacity far exceeding that of plain concrete core piles, which can significantly improve the bearing capacity of the original pile. Insertion before initial setting can ensure that the steel pipe and the surrounding uncured grouting material can fully contact each other, forming a tight bond without gaps after hardening, reducing the risk of slippage between the two in the later stage of stress; step S5 can form a composite pile-in-pillar, directly transferring the load of the original pile top to the qualified bearing layer in the deep layer, completely bypassing the defective layer at the bottom of the original pile, fundamentally solving the problem of the bearing capacity defect of the original pile end not embedded in the bedrock. The reinforcement effect is reliable and controllable, making full use of the remaining value of the original pile body, avoiding the huge waste of scrapping and reconstruction, and improving the problem of insufficient bearing capacity of defective piles not embedded in bedrock in the existing technology.
[0007] Preferably, drilling grouting holes in the pile body of the defective pile includes: drilling three grouting holes in the circumferential direction of the pile body cross section in an equilateral triangle or symmetrical arrangement, with the pre-existing core extraction hole on the defective pile as the center, and the position of each grouting hole being 20cm to 30cm away from the edge of the pile.
[0008] By adopting the above technical solution, the existing defective pile's inspection hole can be used as a positioning benchmark, with the original core extraction hole as the center. This eliminates the need to re-explore the internal condition of the pile, ensuring accurate positioning and saving additional survey work. The equilateral triangle or symmetrical arrangement can form a multi-point support system, making the subsequent stiffened core piles more uniformly stressed, avoiding single eccentric stress, and ensuring that the center of force of the three core piles in the pile cross-section coincides with the pile's centroid, preventing additional bending moments under stress. The three grouting holes, located 20cm~30cm from the pile edge, avoid the main reinforcing bars of the pile (generally with a 5-7cm protective layer, the main bars are on the inside), preventing drilling from cutting the stressed reinforcing bars. At the same time, it ensures that the original pile concrete has sufficient thickness to cover the grouting holes, allowing for effective bonding between the old and new materials. Furthermore, the equilateral triangle arrangement of the three grouting holes means that the pressure of the three holes affects each other during grouting, forming a miniature "pressure arch" area within the pile cross-section. The original pile concrete between the three holes is subjected to triaxial confining pressure, increasing its actual bearing capacity compared to uniaxial stress, which is impossible with single-hole grouting.
[0009] Preferably, the grouting hole extends into the bearing layer below the pile tip, including: the grouting hole extends downward after penetrating the bearing layer, with an extension depth greater than or equal to 2.4 meters.
[0010] By adopting the above technical solution, extending downwards after penetrating the bearing layer ensures that the bottom anchorage section of the stiffened core pile is located inside a qualified bearing layer, rather than remaining on the top surface of the bearing layer. An extension depth of 2.4 meters or more provides sufficient anchorage length, allowing the core pile to safely transfer the load to the bearing layer through sidewall friction and end bearing. The top surface of the bearing layer often has weathering fissures, fracture zones, or is disturbed by construction. Directly using the top surface as the bearing point is risky. A depth of 2.4 meters can penetrate these surface defects and cover adverse conditions such as rock mass strength fluctuations and local fractures under most geological conditions, setting the anchorage section inside a relatively intact and homogeneous rock mass.
[0011] Preferably, the bottom and wall of the grouting hole are cleaned, including: lowering the rotary nozzle to the target depth at the bottom of the grouting hole, using water or cement slurry for rotary cutting, and removing sediment and weak layers at the pile end by rotating and lifting the nozzle.
[0012] By adopting the above technical solution, lowering the rotary nozzle to the bottom of the hole ensures that the cleaning range covers the entire pile end area. Rotating and raising the nozzle allows for segmented cleaning from the bottom of the hole upwards, achieving uniform cleaning of the entire hole section, breaking and stripping away sediment and weak layers, solving the problem that conventional hole cleaning methods cannot handle hard sediment. After the jet cuts the rock and soil of the hole wall, an uneven and rough surface is formed on the hole wall surface, increasing the contact area and mechanical interlocking force between the subsequent grouting material and the hole wall, and improving the sidewall friction resistance.
[0013] Preferably, injecting grout into the grouting hole includes: lowering the grouting pipe to the bottom of the grouting hole, and continuously injecting grout from the bottom of the hole upwards using grouting equipment until the grouting hole is filled with grout.
[0014] By adopting the above technical solution, the grouting pipe is lowered to the bottom of the hole and grout is injected from the bottom of the hole upwards. This ensures that the grout is injected from the deepest point, avoiding segregation or air entrainment when the grout falls freely. It also avoids aggregate sedimentation and segregation during the long-distance free fall of the grout. The grout's own pressure drives water, air or residual mud in the hole upwards and discharges them, achieving void-free filling.
[0015] Preferably, inserting steel pipes into the grouting holes includes: simultaneously inserting two steel pipes into each grouting hole until both steel pipes reach the bottom of the grouting hole.
[0016] By adopting the above technical solution, two steel pipes are installed inside a single hole, which increases the steel content of the core pile section by several times. The axial compressive bearing capacity can be higher than that of a single-pipe core pile, thus addressing a certain bearing capacity gap. The bottoms of the two steel pipes are flush, so that the pile end reaction force is borne by the two steel pipes together, which can avoid single-pipe eccentricity or local overload.
[0017] Preferably, injecting grout into the grouting hole further includes: before the grout in the grouting hole has fully set, adding grout through the orifice of the grouting hole until the grout surface is stable.
[0018] By adopting the above technical solution, grouting is carried out during the period before the grout has fully hardened and still has plasticity and fluidity before the grout sets. This ensures that the new grout can be integrated with the original grout to form a solid whole. The grouting can fill the volume lost due to the hardening shrinkage of the grout, water evaporation and / or leakage. The criterion is that the grout in the hole no longer sinks and the liquid level remains stable. This ensures that the hole is completely compacted and there is no longer any space for continuous absorption of grout, thus avoiding voids or loose areas at the top of the core pile.
[0019] Preferably, the grouting material is a micro-expansion grouting material with a strength grade greater than or equal to 80MPa, and the water-to-material ratio is 0.5:1 by weight.
[0020] By adopting the above technical solution, the strength of grouting material with a strength of 80MPa or above is comparable to that of Q345 grade and above steel pipe. The steel pipe concrete core pile formed by the combination of the two fully utilizes the material strength and avoids the short-plate effect of low-strength grout restricting high-strength steel pipe.
[0021] Preferably, the method further includes step S6 of sealing the opening of the grouting hole and curing the grouting material.
[0022] By adopting the above technical solutions, the borehole sealing can prevent mud, gravel and other debris generated during construction cross-operations from falling into the borehole, ensuring that the top of the core pile is clean and intact. The curing measures can provide the necessary moisture for the grouting material, prevent early water loss and shrinkage cracking, and ensure that the design strength meets the standards.
[0023] Preferably, the method also includes calculating the axial compressive bearing capacity of the stiffened core pile and the anchorage bearing capacity in the deep bearing layer based on the load value required to reinforce the defective pile, so as to determine the grouting hole depth, steel pipe specifications and grout strength.
[0024] By adopting the above technical solutions, the axial compressive bearing capacity can be calculated based on the reinforcement load value to verify whether the core pile itself is strong enough to bear the load transmitted from above without material failure. The anchorage bearing capacity can be calculated to verify whether the core pile is firmly anchored in the deep bearing layer and whether it can safely transmit the load to the rock layer without pull-out or penetration failure. The grouting hole depth can be determined by calculating the anchorage bearing capacity to estimate the length of the rock-embedded section required to provide sufficient side friction or end bearing capacity. The steel pipe specifications can be determined by calculating the axial compressive bearing capacity to estimate the thickness, strength, and diameter of the steel pipe required to share the load with the grouting material. The grouting material strength can be determined by calculating the axial compressive bearing capacity to estimate the strength of the grouting material required to match the steel pipe.
[0025] Preferably, when calculating the anchorage bearing capacity, the portion of the stiffened core pile located in the deep bearing layer is regarded as an anchor or a small-diameter rock-socketed pile, and the anchorage bearing capacity is determined based on the sum of the sidewall friction and the end bearing capacity.
[0026] By adopting the above technical solution, the part of the stiff core pile located in the deep bearing layer is regarded as an anchor or a small-diameter rock-socketed pile. The anchor model emphasizes the side wall friction as the main factor, while the rock-socketed pile model can consider both side resistance and end resistance at the same time. The total anchorage bearing capacity is calculated by superposition principle.
[0027] Preferably, the steel pipe is anchored to the pile cap structure at the top of the defective pile.
[0028] By adopting the above technical solution, the steel pipe is connected to the pile cap, and the core pile can work together with the original pile body and the pile cap, avoiding the failure of the core pile due to the top being suspended.
[0029] In summary, this application includes at least one of the following beneficial technical effects: Step S1 opens a channel in the defective pile body and the unqualified bearing layer such as sediment and / or weak layer at the pile bottom, breaking through the defective layer at the original pile bottom and directly contacting the qualified bearing layer. This serves as the carrier space for subsequent grouting and steel pipe implantation, creating the preconditions for establishing a new force transmission path. Compared with re-piling, this method only utilizes the internal space of the original pile body for drilling, without occupying external site space, making it more adaptable to construction. Step S2 cleans and exposes fresh concrete or rock surface on the borehole wall, improving the interfacial adhesion between the grout and the borehole wall (original pile body concrete), ensuring that the new and old materials can work together. It also cleans the sediment, mud, and weak residue at the bottom of the borehole, ensuring that the grout can directly contact the fresh rock surface at the bottom of the borehole, preventing the re-emergence of weak interlayers at the bottom of the new pile. Step S3 fills the borehole space, serving as a medium for load transfer. Through adhesion with the borehole wall, it connects the core pile to the original pile body. The process is as follows: Step S4 serves as the core reinforcing framework of the reinforced core pile, bearing most of the load and providing certain compressive strength and bending capacity. The steel pipe and grout form a steel-concrete composite structure, with a bearing capacity far exceeding that of plain concrete core piles. This significantly improves the bearing capacity of the original pile. Insertion before initial setting ensures that the steel pipe and the surrounding uncured grout can fully contact each other, forming a tight bond without gaps after hardening, reducing the risk of slippage between the two in the later stages of stress. Step S5 forms a composite pile-in-pillar, directly transferring the load at the top of the original pile to a qualified bearing layer in the deep layer, completely bypassing the defective layer at the bottom of the original pile. This fundamentally solves the problem of the bearing capacity defect of the original pile end that is not embedded in bedrock. The reinforcement effect is reliable and controllable, making full use of the remaining value of the original pile body, avoiding the huge waste of scrapping and reconstruction, and improving the problem of insufficient bearing capacity of defective piles that are not embedded in bedrock in the existing technology. Using the original core extraction hole as the center, the existing defective pile's inspection hole can be used as a positioning benchmark, eliminating the need to re-explore the internal condition of the pile. This ensures precise positioning and saves on additional survey work. The equilateral triangle or symmetrical arrangement can form a multi-point support system, making the subsequent stiffened core piles more evenly stressed, avoiding single eccentric stress, and ensuring that the center of force of the three core piles coincides with the centroid of the pile within the pile cross-section. This prevents the generation of additional bending moments under stress. The three grouting holes, located 20cm~30cm from the pile edge, avoid the main reinforcing bars of the pile (generally with a 5-7cm protective layer, the main bars are on the inside), preventing the drilling from cutting the stressed reinforcing bars. At the same time, it ensures that the original pile concrete has a sufficient thickness to cover the grouting holes, allowing for effective bonding between the old and new materials. Furthermore, the equilateral triangle arrangement of the three grouting holes means that the pressure of the three holes affects each other during grouting, forming a miniature "pressure arch" area within the pile cross-section. The original pile concrete between the three holes is subjected to triaxial confining pressure, and its actual bearing capacity is improved compared to uniaxial stress, which is something that single-hole grouting cannot achieve. Extending downwards after penetrating the bearing stratum ensures that the bottom anchorage section of the stiffened core pile is located within a qualified bearing stratum, rather than remaining on the top surface of the bearing stratum. An extension depth of 2.4 meters or more provides sufficient anchorage length, allowing the core pile to safely transfer the load to the bearing stratum through sidewall friction and end bearing capacity. The top surface of the bearing stratum often has weathering fissures, fracture zones, or is disturbed by construction. Directly using the top surface as the bearing point is risky. A depth of 2.4 meters can penetrate these surface defects and cover adverse conditions such as rock mass strength fluctuations and local fractures under most geological conditions, placing the anchorage section within a relatively intact and homogeneous rock mass. Attached Figure Description
[0030] Figure 1 This is an engineering schematic diagram of the actual construction of the steel pipe reinforced core pile reinforcement method in the embodiments of this application; Figure 2 It is along Figure 1 Sectional view of line AA in the middle; Figure 3 It is along Figure 1 Sectional view of the middle BB line; Figure 4 It is along Figure 1 A cross-sectional view of the CC line.
[0031] Explanation of reference numerals in the attached drawings: 1. Foundation; 2. Defective pile; 3. Steel pipe; 4. Grouting material. Detailed Implementation
[0032] The following is in conjunction with the appendix Figure 1 To be continued Figure 4 This application will be described in further detail.
[0033] This application discloses a method for reinforcing piles with steel pipe cores inside the pile. (Refer to...) Figure 1 The reinforcement method of steel pipe core piles includes the following steps: S1, drilling grouting holes in the pile body of the defective pile 2, with the grouting holes extending into the bearing layer below the pile end; S2, cleaning the bottom and wall of the grouting holes; S3, injecting grouting material 4 into the grouting holes; S4, after injecting grouting material 4 and before the grouting material 4 initially sets, inserting a steel pipe 3 into the grouting hole, with the steel pipe 3 extending to the bottom of the grouting hole; S5, the grouting material 4 solidifies, forming a rigid core pile inside the defective pile 2, which directly transfers the pile top load to the deep bearing layer; S6, sealing the opening of the grouting holes and curing the grouting material 4.
[0034] In this embodiment, step S1 can open a channel in the unqualified bearing layer such as sediment and / or weak layer in the body and bottom of the defective pile 2, break through the defective layer at the bottom of the defective pile, and directly contact the qualified bearing layer, which serves as the carrier space for subsequent grouting and implantation of steel pipe 3, creating the preconditions for establishing a new force transmission path. Compared with re-pile, drilling is only used in the internal space of the original pile body, without occupying external site, and the construction adaptability is stronger.
[0035] Please refer to the following: Figure 2 Grouting holes are drilled within the defective pile 2, including: three grouting holes are drilled in an equilateral triangle or symmetrical arrangement around the circumference of the pile body section of the defective pile 2, centered on the pre-existing core extraction hole on the defective pile 2. Each grouting hole is positioned 20cm-30cm from the pile edge. Using the original core extraction hole as the center allows the existing inspection hole of the defective pile 2 to serve as a positioning reference, eliminating the need to re-inspect the internal condition of the pile body. This ensures accurate positioning and saves additional survey work. The equilateral triangle or symmetrical arrangement forms a multi-point support system, making the subsequent stiffened core piles more evenly stressed, avoiding single eccentric stress, and ensuring that the resultant force center of the three core piles within the pile section is aligned with the pile shape. With the cores aligned, no additional bending moment is generated when under stress. The three grouting holes are 20cm to 30cm away from the pile edge, avoiding the main reinforcing bars of the pile (generally with a 5-7cm protective layer, and the main bars are on the inside). This prevents the drilling from cutting the stressed reinforcing bars and ensures that the original pile concrete has a sufficient thickness to cover the grouting holes, so that the new and old materials can bond effectively. Furthermore, the three grouting holes are arranged in an equilateral triangle. During high-pressure grouting, the pressure of the three holes affects each other, forming a miniature "pressure arch" area within the pile cross-section. The original pile concrete between the three holes is subjected to triaxial confining pressure, and its actual bearing capacity is improved compared to uniaxial stress, which is something that single-hole grouting cannot achieve.
[0036] For example, the drilling location is 20cm-30cm away from the pile edge. The original purpose was to avoid the main reinforcement. However, in actual engineering, it allows the high-strength grout 4 that is subsequently poured to wrap around part of the stirrups or structural reinforcement. This is equivalent to wrapping the core area of the original pile body with high-strength material, which improves the ductility of the original pile body. Furthermore, the symmetrical arrangement of the three holes allows for the comparison of the strain response of the pile body sections corresponding to the three holes during high-strain testing. This helps to determine the stress condition of the reinforced pile body and facilitates subsequent quality testing.
[0037] In the embodiments of this application, please refer to Figure 3 and Figure 4The grouting hole extends into the bearing stratum below the pile tip. Specifically, the grouting hole penetrates the bearing stratum and extends downward to a depth greater than or equal to 2.4 meters. This downward extension ensures that the bottom anchorage section of the stiffened core pile is located within a qualified bearing stratum, rather than remaining on the top surface of the bearing stratum. The extension depth of 2.4 meters provides sufficient anchorage length, allowing the core pile to safely transfer the load to the bearing stratum through sidewall friction and end bearing. The top surface of the bearing stratum often has weathering fissures, fracture zones, or is disturbed during construction. Directly using the top surface as the bearing point is risky. A depth of 2.4 meters can penetrate these surface defects and cover adverse conditions such as rock mass strength fluctuations and local fractures under most geological conditions, allowing the anchorage section to be set within a relatively intact and homogeneous rock mass.
[0038] For example, penetrating 2.4 meters into the bearing stratum means that the bottom of the core pile is at a certain depth within the rock mass and is subjected to triaxial confining pressure from the surrounding rock. Under high confining pressure, the actual compressive strength of the concrete and steel pipe 3 will increase (similar to the strength increase effect of concrete under triaxial compression). Therefore, the actual bearing capacity of the core pile is relatively high, and it has a hidden safety reserve capacity. In addition, although this method is mainly aimed at vertical compressive reinforcement, the long anchorage section formed by penetrating 2.4 meters into the bearing stratum also gives the core pile a considerable uplift bearing capacity. In the event of subsequent changes in the anti-buoyancy design of the basement or uplift forces under seismic action, the core pile reinforced by the technical solution in this application can provide a certain uplift resistance.
[0039] In this embodiment, step S2 can remove and clean the hole wall to expose fresh concrete or rock surface, improve the interfacial adhesion between the grouting material 4 and the hole wall (original pile body concrete), ensure that the new and old materials can work together, and clean the sediment, mud skin and weak residue at the bottom of the hole to ensure that the grouting material 4 can directly contact the fresh rock surface at the bottom of the hole, and avoid the recurrence of weak interlayers at the bottom of the new pile. For example, the hole bottom and hole wall of the grouting hole are cleaned by: lowering the high-pressure jet nozzle to the target depth at the bottom of the grouting hole, and using high-pressure water or high-pressure cement slurry for jet grouting. Cutting, by rotating and lifting the nozzle, removes sediment and weak layers at the pile end; the high-pressure rotary nozzle is lowered to the bottom of the hole to ensure that the cleaning range covers the entire pile end area. The rotating and lifting nozzle can process from the bottom of the hole upwards segment by segment, achieving uniform cleaning of the entire hole segment, breaking and peeling off sediment and weak layers, solving the problem that conventional hole cleaning methods cannot handle hard sediment. After the high-pressure jet cuts the rock and soil of the hole wall, the surface of the hole wall forms an uneven rough surface, increasing the contact area and mechanical interlocking force between the subsequent grouting material 4 and the hole wall, and improving the side wall friction resistance.
[0040] For example, during the rotary jet cutting process, the high-pressure jet applies an instantaneous impact load to the rock surface at the bottom of the hole, releasing the residual stress on the surface of the rock mass. This allows the rock surface at the bottom of the hole to be in a relatively relaxed state after unloading. After the subsequent grouting material 4 is injected, the rock surface rebounds and squeezes the grout, forming a prestressed close contact, and the end bearing capacity is fully utilized.
[0041] In this embodiment, step S3 can fill the borehole space and serve as a medium for transferring loads. Through bonding with the borehole wall, the core pile is connected to the original pile body as a whole. For example, grouting material 4 is injected into the grouting hole. Specifically, the grouting pipe is lowered to the bottom of the grouting hole, and grouting material 4 is continuously injected from the bottom of the hole upwards using a high-pressure grouting device until the grouting material 4 fills the grouting hole. Lowering the grouting pipe to the bottom of the hole and injecting from the bottom of the hole upwards can ensure that the grout is injected from the deepest point, avoiding segregation or air entrainment when the grout falls freely, and avoiding aggregate sedimentation and segregation during the long-distance free fall of the grout. The grout pressure itself is used to drive water, air or residual mud in the hole upwards and discharge it, achieving void-free filling.
[0042] For example, during continuous high-pressure grouting, the grout is in a continuous flow state within the borehole. The flowing grout exerts lateral pressure on the borehole wall, and the particles inside the grout rearrange under pressure, achieving a higher density than static casting. During continuous high-pressure grouting, if there are tiny cracks in the borehole wall, the grout will continuously seep in until they are filled. When the grouting is completed and the pressure is released, the grout in the cracks rebounds and generates micro-expansion, applying compressive stress to the crack wall, which is equivalent to prestressing and reinforcing the surrounding rock mass, improving the integrity of the bearing layer.
[0043] In this embodiment of the application, in step S4, the steel pipe 3 can serve as the core reinforcing skeleton of the stiff core pile, bear most of the load, and provide a certain compressive strength and bending capacity. The steel pipe 3 and the grouting material 4 form a steel pipe 3 concrete composite structure, which has a bearing capacity far exceeding that of plain concrete core piles and can significantly improve the bearing capacity of the original pile. Inserting it before initial setting can ensure that the steel pipe 3 and the surrounding uncured grouting material 4 can fully contact each other and form a tight bond without gaps after hardening, reducing the risk of slippage between the two in the later stage of stress.
[0044] For example, steel pipes 3 are inserted into the grouting holes. Specifically, two steel pipes 3 are simultaneously inserted into each grouting hole until both steel pipes 3 reach the bottom of the grouting hole. The presence of two steel pipes 3 in a single hole increases the steel content of the core pile section by a factor of two, and the axial compressive bearing capacity can be higher than that of a single-pipe core pile, thus addressing a certain bearing capacity gap. The bottoms of the two steel pipes 3 are flush, so that the pile end reaction force is borne jointly by the two steel pipes 3, avoiding single-pipe eccentricity or local overload. It should be added that the two parallel steel pipes 3 form a natural conductive circuit in the hole. When it may be necessary to inspect the steel pipes 3 later, the integrity of the two steel pipes 3 can be detected by electromagnetic method or trans-hole resistivity method. For example, if a steel pipe 3 is broken or severely corroded, the circuit resistance will change to a certain extent, thus obtaining the current state of the two steel pipes 3.
[0045] In this embodiment of the application, injecting grout 4 into the grouting hole further includes: before the grout 4 in the grouting hole has fully set, supplementing the grout 4 into the grouting hole through the orifice of the grouting hole until the grout surface of the grout 4 is stable; before the grout 4 has fully set, supplementing the grout during the period when the grout has not fully hardened and still has plasticity and fluidity, ensuring that the new grout can be integrated with the original grout to form a solid whole, and the supplemented grout 4 can fill the volume reduced due to the hardening shrinkage of the grout, water evaporation and / or leakage. The grout in the hole no longer sinks and the liquid surface remains stable as the judgment criterion, ensuring that the hole is completely dense and there is no longer space for continuous absorption of grout, avoiding the appearance of voids or loose areas at the top of the core pile.
[0046] For example, during the secondary grouting process, if the grout level at the borehole continues to sink and the amount of grout added far exceeds the theoretical shrinkage, it indicates that there may be undetected leakage channels or voids in the borehole. This allows for grouting-based detection, enabling timely discovery and treatment of hidden defects during the construction phase, thus avoiding problems being discovered only during project acceptance.
[0047] It should be noted that in this embodiment, the grouting material 4 is a micro-expansion grouting material 4 with a strength grade greater than or equal to 80MPa, and the water-to-material ratio by weight is 0.5:1. The grouting material 4 with a strength of 80MPa or above is comparable to the strength of the steel pipe 3 of Q345 grade or above. The steel pipe 3 concrete core pile formed by the combination of the two fully utilizes the material strength and avoids the short-plate effect of low-strength grout restricting high-strength steel pipe 3. When the micro-expansion grouting material 4 expands in the confined space, it not only fills the gaps, but also generates a small radial expansion pressure on the rock and soil of the borehole wall, so that the core pile and the surrounding rock mass form a prestressed contact. The side wall friction can be fully utilized in the early stage of stress, without the need for a certain amount of slippage to mobilize the side resistance as in ordinary piles.
[0048] In this embodiment, the borehole sealing in step S6 prevents mud, gravel, and other debris generated during cross-construction operations from falling into the borehole, ensuring the top of the core pile is clean and intact. The curing measures provide necessary moisture to the grouting material 4, preventing early water loss and shrinkage cracking, and ensuring the design strength. After the borehole is sealed, a closed system is formed inside the core pile. If the grouting material 4 undergoes micro-expansion during subsequent hydration, the expansion pressure cannot be released because the borehole is sealed, generating self-stress within the borehole, further increasing the density of the core pile and the compressive force against the borehole wall.
[0049] It should be noted that, in the embodiments of this application, before processing the defective pile 2 using the steel pipe core pile reinforcement method, it is also necessary to calculate the axial compressive bearing capacity and the anchorage bearing capacity in the deep bearing layer of the core pile based on the load value that the defective pile 2 needs to be reinforced, so as to determine the grouting hole depth, the specifications of the steel pipe 3 and the strength of the grouting material 4.
[0050] For example, the axial compressive bearing capacity of the steel pipe 3 concrete core pile itself is set as N1 in this application. Its calculation formula (taking a circular cross-section as an example) is: N1=φ(faAa+αfcAc). The calculated N1 must be greater than the load Nneed that the core pile needs to share, as the primary basis for selecting the specifications of the steel pipe 3 and the strength of the grout 4. The core pile formed by combining the steel pipe 3 and the grout 4 is regarded as a steel pipe 3 concrete component, and its axial compressive bearing capacity is denoted as N1. φ is the stability coefficient, considering the reduction of the compressive bearing capacity due to the slenderness ratio. fa is the design value of the compressive strength of the steel pipe 3, and Aa is the cross-sectional area of the steel pipe 3. The product of the two represents the bearing capacity borne by the steel pipe 3 itself. fc is the design value of the axial compressive strength of the grout 4, and Ac is the cross-sectional area of the grout 4. Taking the full cross-section of the grout 4 inside the steel pipe 3, the product of fc and Ac represents the bearing capacity borne by the grout 4 itself. The bearing capacity, α is the working coefficient of grout 4, used to consider the restraining and reinforcing effect of steel pipe 3 on internal grout 4; in the embodiment of this application, steel pipe 3 and grout 4 work together under axial pressure, and the bearing capacity of the two is superimposed and then multiplied by the stability coefficient, so that the axial compressive bearing capacity N1 of the core pile is obtained. It must be greater than the load Nneed that the core pile needs to share, that is, the part of the original pile bearing capacity gap that is to be borne by the core pile. This is the primary basis for selecting the wall thickness, diameter, steel grade of steel pipe 3 and strength grade of grout 4.
[0051] For example, the anchorage bearing capacity between the core pile and the underlying rock stratum is set as N2. The portion of the core pile within the rock stratum is considered as an anchor rod or a small-diameter rock-socketed pile. The calculation formula is: N2 = π•d(qsik•Lr + qsiks±•Ls) + ξf•frc•Ap. The calculated N2 must also be greater than Nneed; d is the diameter of the core pile anchorage section, which is taken as the borehole diameter in this application; qsik is the standard value of the side friction resistance between the core pile and the rock stratum; and Lr is the rock-socketed section of the core pile. The length of the core pile is given by: qsik_soil, which is the standard value of the side friction resistance between the core pile and the soil layer above the bearing stratum; L_soil, which is the anchorage length of the core pile in the soil layer; the sum of the products of qsik_soil and L_soil, multiplied by the perimeter π•d, gives the total side friction resistance; ξf is the end bearing capacity reduction factor, used to consider the influence of rock mass strength dispersion and construction factors on the end bearing capacity; frc is the standard value of the saturated uniaxial compressive strength of the bearing stratum rock mass; and Ap is the bottom cross-sectional area of the core pile. The product of these three factors gives the end bearing capacity.
[0052] For example, the axial compressive stiffness of the core pile is set as (EA)eff. The stiffness superposition method means that the steel pipe 3 and the grout 4 are tightly connected by bonding. Under axial compression, the strain is coordinated and the total resistance is the sum of the two. The same applies to the stiffness. Its calculation formula is: (EA)eff=Ea•Aa+Ec•Ac; Ea is the elastic modulus of the steel pipe 3 and Ec is the elastic modulus of the grout 4.
[0053] For example, the bending stiffness of the core pile is denoted as (EI)eff. Since the core pile mainly bears axial pressure and is constrained by the original pile, its bending deformation is minimal. In the overall analysis, its bending contribution is usually ignored or estimated very conservatively. The calculation formula is: (EI)eff≈Ea•Ia+Ec•Ic; where Ia is the moment of inertia of the steel pipe section 3 about the centroidal axis, and Ic is the moment of inertia of the grout section 4 about the centroidal axis.
[0054] Specifically, based on the reinforcement load value, the axial compressive bearing capacity can be calculated to verify whether the core pile itself is strong enough to bear the load transmitted from above without material failure. The anchorage bearing capacity can be calculated to verify whether the core pile is firmly anchored in the deep bearing layer and whether it can safely transmit the load to the rock layer without pull-out or penetration failure. The grouting hole depth can be determined by calculating the anchorage bearing capacity to estimate the length of the rock-embedded section required to provide sufficient side friction or end bearing capacity. The steel pipe 3 specification can be determined by calculating the axial compressive bearing capacity to estimate the thickness, strength, and diameter of the steel pipe 3 required to share the load with the grouting material 4. The grouting material 4 strength can be determined by calculating the axial compressive bearing capacity to estimate the strength of the grouting material 4 required to match the steel pipe 3.
[0055] In this embodiment, the steel pipe 3 is anchored to the pile cap 1 structure at the top of the defective pile 2. The connection between the steel pipe 3 and the pile cap 1 allows the core pile to work together with the original pile body and the pile cap 1, thus avoiding the failure of the core pile due to the top being suspended.
[0056] In another embodiment of this application, the three grouting holes are arranged in an equilateral triangle and each hole contains two steel pipes 3. Furthermore, the steel pipes 3 in each grouting hole are rigidly connected above the pile top via a ring-shaped steel beam or a spatial truss, forming a spatial force-bearing system from the three independent stiffened core piles. For example, before pouring the pile cap 1, the tops of the six steel pipes 3 can extend a certain length beyond the pile top. All the steel pipes 3 are connected into a whole by a prefabricated or on-site welded ring-shaped steel beam. Stiffening ribs can be installed inside the ring-shaped steel beam to enhance the node stiffness. Subsequently, it is welded and fixed to the reinforcing steel skeleton of the pile cap 1, and concrete is poured as a whole. This allows the three originally independent core piles to form a collaborative force-bearing system in space. When the pile body is subjected to eccentric or horizontal loads, the spatial truss distributes the load evenly to each core pile through the redistribution of internal forces at the nodes, avoiding the problem of single pile overload or uneven stress.
[0057] Specifically, the three core piles change from independent force bearing to working collaboratively in space, which can improve the bending and torsional resistance, far exceeding the simple superposition of the capabilities of the three core piles working individually. This gives the reinforced single pile foundation the redundancy and safety of a pile group foundation. At the same time, the ring steel beam connects the three groups of steel pipes, which can improve the punching shear resistance and integrity of the pile cap 1. Even under extreme loads such as earthquakes or storms, the spatial truss can distribute the load through multi-directional force transmission paths, avoiding overall failure caused by local damage.
[0058] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.
Claims
1. A method of reinforcing a defective pile (2) in which the pile tip does not embed into a complete bedrock, by using a steel pipe stiff core pile reinforcement method, characterized in that, Includes the following steps: S1, Drill grouting holes in the pile body of the defective pile (2), with the grouting holes extending into the bearing layer below the pile end; S2, Clean the bottom and wall of the grouting hole; S3, inject grout into the grouting hole (4); S4, after the grouting material (4) is injected and before the grouting material (4) is initially set, a steel pipe (3) is inserted into the grouting hole and the steel pipe (3) extends to the bottom of the grouting hole; S5, the grout (4) solidifies, and a stiff core pile is formed inside the defective pile (2). The stiff core pile directly transmits the load at the top of the pile to the deep bearing layer.
2. The steel pipe reinforced pile method according to claim 1, wherein The method of drilling grouting holes in the pile body of the defective pile includes: drilling three grouting holes in the circumferential direction of the pile body section of the defective pile (2) in an equilateral triangle or symmetrical arrangement, with the core extraction hole pre-existing on the defective pile (2) as the center, and the position of each grouting hole is 20cm~30cm away from the edge of the pile.
3. The steel pipe reinforced pile method according to claim 2, wherein The grouting hole extends into the bearing layer below the pile end, including: the grouting hole extends downward after penetrating the bearing layer, with an extension depth greater than or equal to 2.4 meters.
4. The steel pipe reinforced pile method according to claim 1, wherein The cleaning treatment of the bottom and wall of the grouting hole includes: lowering the rotary nozzle to the target depth at the bottom of the grouting hole, using water or cement slurry for rotary cutting, and removing sediment and weak layers at the pile end by rotating and lifting the nozzle.
5. The steel pipe reinforced pile method according to claim 1, wherein The process of injecting grout into the grouting hole includes: lowering the grouting pipe to the bottom of the grouting hole, and continuously injecting grout (4) from the bottom of the hole upwards using grouting equipment until the grout (4) fills the grouting hole.
6. The reinforcement method for steel pipe core piles according to claim 5, characterized in that, The process of inserting steel pipes into the grouting holes includes: simultaneously inserting two steel pipes (3) into each grouting hole until both steel pipes (3) reach the bottom of the grouting hole.
7. The reinforcement method for steel pipe core piles according to claim 6, characterized in that, The method of injecting grout into the grouting hole further includes: before the grout (4) in the grouting hole sets, injecting grout (4) into the grouting hole through the orifice of the grouting hole until the grout surface of the grout (4) is stable.
8. The reinforcement method of steel pipe core piles with internal reinforcement according to claim 7, characterized in that: The grouting material (4) is a micro-expansion grouting material (4) with a strength grade greater than or equal to 80MPa, and the water-material ratio is 0.5:1 by weight.
9. The method for reinforcing steel pipe core piles according to claim 1, characterized in that, Also includes: S6, seal the opening of the grouting hole and cure the grouting material (4).
10. The reinforcement method of steel pipe core piles with internal reinforcement according to claim 1, characterized in that: in, It also includes calculating the axial compressive bearing capacity of the stiffened core pile and the anchorage bearing capacity in the deep bearing layer based on the load value required to reinforce the defective pile (2), so as to determine the grouting hole depth, steel pipe (3) specifications and grouting material (4) strength.
11. The reinforcement method for steel pipe core piles according to claim 10, characterized in that: When calculating the anchorage bearing capacity, the portion of the stiffened core pile located in the deep bearing layer is regarded as an anchor or a small-diameter rock-socketed pile, and the anchorage bearing capacity is determined based on the sum of the sidewall friction and the end bearing capacity.
12. The reinforcement method of steel pipe core piles with internal reinforcement according to claim 1, characterized in that: The steel pipe (3) is anchored to the pile cap (1) structure at the top of the defective pile (2).