A rock wall crane beam rock platform low-damage excavation and dynamic anchor injection construction method
By employing layered, loss-controlled excavation and dynamic anchoring methods in the construction area of the rock-face crane beam platform, the problem of insufficient matching between the surrounding rock condition and the timing of anchoring construction was solved. This enabled dynamic adjustment and targeted treatment of the surrounding rock condition, improving the controllability of construction and the reinforcement effect.
Patent Information
- Application Number
- CN202611489228.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-23
- Publication Date
- 2026-11-24
AI Technical Summary
In the construction of existing rock wall crane beam platforms, the surrounding rock condition is not well matched with the timing of anchoring construction, the anchoring and crack conditions are not well correlated, and the post-construction inspection results and treatment measures lack specificity, making it difficult to effectively control rock mass damage and crack conditions.
The construction area of the rock wall crane beam platform was divided into units, and layered loss-controlled excavation was carried out to detect the state of relaxation zones and cracks. The allowable anchoring window was determined according to the deformation rate of the surrounding rock, and the anchor bolt insertion length and grouting pressure were adjusted in stages. The stability of the surrounding rock was checked in combination with the acoustic wave velocity and anchor bolt anchoring force, and supplementary stress release or grouting was carried out for different states.
It improves the controllability and reliability of the anchoring process, reduces the risk of additional stress on the anchoring structure due to surrounding rock deformation, enhances the crack filling effect, and enables dynamic adjustment and targeted treatment during the construction process.
Smart Images

Figure CN123153399A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of underground engineering construction technology, and in particular to a method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms. Background Technology
[0002] Crane beams are commonly used load-bearing structures in underground powerhouses of hydraulic and hydropower projects. The rock platform, as a crucial load-bearing component between the crane beam and the surrounding rock, is significantly affected by its excavation quality, the integrity of the shallow rock mass, and the stability of the anchorage area, all of which impact the subsequent construction quality of the crane beam. For underground powerhouses with significant depth and high ground stress, the excavation of the rock platform requires not only controlling blasting disturbance and over- or under-excavation, but also considering the redistribution of surrounding rock stress after excavation and the impact of shallow rock deformation and fissure development.
[0003] In existing construction of rock face crane beam platforms, controlled blasting, pre-reserved protective layers, and manual or mechanical trimming are commonly used to shape the platform. Anchor bolts and grouting are then installed and used for reinforcement after the platform is formed. These construction methods reduce the disturbance of the remaining rock mass caused by blasting and improve the quality of the platform's outline.
[0004] However, the surrounding rock conditions in different construction sections are not entirely consistent after the rock platform is excavated. Especially under high ground stress conditions, the surrounding rock undergoes a stress readjustment process after excavation and unloading, and its deformation rate and fracture state change over time. If anchoring is implemented before the surrounding rock deformation has stabilized, subsequent deformation of the surrounding rock may have additional effects on the already formed anchoring structure; if anchoring is implemented too late, the relaxation range and fractures of the shallow rock mass may further develop. Therefore, it is difficult to simultaneously meet the requirements of surrounding rock stress adjustment and timely reinforcement by simply carrying out anchoring construction according to the predetermined construction time or established procedures.
[0005] Meanwhile, influenced by lithology, ground stress, blasting disturbance, and existing fracture conditions, the depth of the relaxation zone and the degree of fracture development vary in different construction sections after excavation. Currently, the anchor bolt arrangement and grouting parameters in construction are mostly determined based on design parameters and construction experience, lacking a direct correlation with the actual relaxation range and fracture state after excavation. When the relaxation range and fracture state change, the fixed anchoring depth and grouting method are difficult to adjust for different rock mass conditions, potentially affecting the anchoring and fracture filling effects.
[0006] In addition, after the rock platform anchoring construction is completed, it is necessary to test the surrounding rock deformation, anchor bolt anchoring effect, and grouting quality. When different test indicators fail to meet the requirements, the corresponding rock mass conditions and formation causes may be different. If the same follow-up treatment method is used, it will be difficult to implement targeted corrections for the actual abnormal conditions.
[0007] Therefore, existing construction methods for rock wall crane beam platforms still suffer from several problems: insufficient matching between the state of the surrounding rock after excavation and the timing of anchoring construction; insufficient correlation between the state of rock mass damage and fractures and anchoring parameters; and a lack of targeted correspondence between post-construction testing results and subsequent treatment measures. Summary of the Invention
[0008] The purpose of this invention is to provide a method for low-damage excavation and dynamic anchoring construction of rock platform crane beams, so as to solve the problems existing in the prior art.
[0009] To achieve the above objectives, the present invention adopts the following technical solution: A method for low-damage excavation and dynamic anchoring construction of a rock face crane beam platform includes the following steps: S1. Divide the construction area of the rock wall crane beam platform into construction units, and determine the final fine forming retention layer on the outer side of the final design outline of the platform in each construction unit. S2. Perform layered loss-controlled excavation on the construction unit, and perform low-damage molding on the final fine-forming retention layer, and detect the depth of the relaxation zone and the state of the fractures in the rock mass after molding. S3. Obtain the surrounding rock displacement time series after the rock platform is formed, and determine the surrounding rock deformation rate and its change based on the surrounding rock displacement time series; when the surrounding rock deformation rate and its change are not greater than the corresponding thresholds within a continuous preset monitoring period, determine that the construction unit has entered the allowable anchoring stability window; if the aforementioned conditions are not met, stress release is performed on the construction unit and the surrounding rock state is re-determined. S4. After the construction unit enters the allowable anchoring stability window, the effective rock penetration length of the anchor rod is determined according to the depth of the relaxation zone, so that the anchor rod passes through the relaxation zone and extends into the relatively intact rock mass to form an effective anchoring section. Based on the fracture state, a grouting process with different grouting pressure stages and grouting times is selected to implement anchoring reinforcement. S5. After anchoring and grouting reinforcement, the stability of the surrounding rock is checked based on the deformation rate and its change, and the integrity of the reinforcement is checked based on the acoustic wave velocity, anchor bolt anchoring force, and grouting density. If the stability of the surrounding rock does not meet the requirements, supplementary stress release is implemented and the surrounding rock condition is re-evaluated. If the stability of the surrounding rock meets the requirements but the integrity of the reinforcement does not meet the requirements, grouting is applied to the insufficiently reinforced areas and the integrity of the reinforcement is re-checked. When both the stability of the surrounding rock and the integrity of the reinforcement meet the requirements, the construction of the current construction unit is terminated.
[0010] Preferably, in step S1, the construction unit is divided along the length of the rock wall crane beam, and acoustic wave detection points are set in each construction unit to obtain the initial acoustic wave velocity at each acoustic wave detection point before excavation. In each construction unit, the anchor bolt hole layout area and the pressure relief hole layout area are determined, and the anchor bolt hole layout area and the pressure relief hole layout area are staggered on the rock platform surface. in, Numbering of sound wave detection measurement points, For the first The initial acoustic wave velocity measured at each acoustic detection point before the rock platform excavation.
[0011] Preferably, in step S2, the rock mass outside the final design outline of the rock platform is first subjected to layered micro-delay blasting, and a final fine-forming retention layer with a thickness of 30-50cm is retained outside the final design outline of the rock platform; then the final fine-forming retention layer is subjected to shallow-hole and dense-hole micro-delay blasting and trimming, and the peak vibration velocity of the blasting particles is not greater than 2cm / s. After molding, obtain the first The sound wave velocity at each sound wave detection point Calculate the first according to the following formula Attenuation rate of sound wave velocity at each sound wave detection point : ; in, For the first Attenuation rate of sound wave velocity at each sound wave detection point; For the first The initial acoustic wave velocity measured at each acoustic detection point before the rock platform excavation; For the first The acoustic wave velocity was measured at each acoustic detection point after low-damage molding of the rock platform. And detect the depth of the relaxation region. Attenuation rate of sound wave velocity at each sound wave detection point All are no greater than 5%, the depth of the relaxation zone If the crack is no larger than 0.10m and no structural through-cracks formed by this excavation are found, the current construction unit is deemed to have met the low-damage forming requirements; otherwise, the loosened rock mass of the part that has not met the low-damage forming requirements shall be removed and repaired and then re-inspected. in, The depth of the relaxation zone is measured from the surface of the rock platform into the interior of the rock mass.
[0012] Preferably, in step S2, the crack state is determined based on the crack width and continuity of the crack after the rock platform is formed. Cracks with a crack width of less than 0.2 mm and no continuous cracks are defined as minor cracks, cracks with a crack width of 0.2 to 0.5 mm and no continuous cracks are defined as moderate cracks, and cracks with a crack width greater than 0.5 mm or with continuous cracks are defined as severe cracks.
[0013] Preferably, in step S3, surrounding rock displacement monitoring points are set up in the construction unit, and in the first... Each monitoring moment Get the Displacement at each surrounding rock displacement monitoring point Calculate the first according to the following formula The deformation rate of surrounding rock at each surrounding rock displacement monitoring point between adjacent monitoring times : ; And determine the first according to the following formula The maximum absolute deformation rate of each surrounding rock displacement monitoring point within each monitoring period. : ; The change in the maximum absolute deformation rate between adjacent monitoring periods is determined by the following formula. : ; When continuous All monitoring cycles meet the following requirements: ; and: ; At that time, it is determined that the construction unit has entered the allowable anchoring stability window; in, For monitoring cycle number; Number the surrounding rock displacement monitoring points; For the first Each monitoring moment; For the first -1 monitoring time; For the first The surrounding rock displacement monitoring point at the first The surrounding rock displacement measured at each monitoring moment; For the first The surrounding rock displacement monitoring point at the first -1 monitoring time point measured surrounding rock displacement; For the first The surrounding rock displacement monitoring point at the first -1 monitoring time to the The deformation rate of the surrounding rock between monitoring moments; For the first The maximum absolute deformation rate among all surrounding rock displacement monitoring points within a monitoring cycle; For the first -The maximum absolute deformation rate among all surrounding rock displacement monitoring points within one monitoring cycle; For the first The monitoring cycle and the first - The change in the maximum absolute deformation rate between 1 monitoring cycles; The preset number of continuous monitoring cycles is used to determine the continued stabilization of surrounding rock deformation. The threshold for the deformation rate under allowable anchoring conditions; The threshold for the maximum absolute deformation rate change allowed between adjacent monitoring cycles under anchoring conditions.
[0014] Preferably, in step S3, when the construction unit has not entered the allowable anchoring stability window, the first set of pressure relief holes is arranged according to the first hole spacing, and the surrounding rock condition is re-determined after the construction of the first set of pressure relief holes; if it still has not entered the allowable anchoring stability window, a second set of pressure relief holes is added between adjacent first sets of pressure relief holes and / or in the area corresponding to the maximum absolute deformation rate, so that the effective pressure relief hole spacing after the addition is less than the first hole spacing; the addition of pressure relief holes is stopped after the construction unit enters the allowable anchoring stability window.
[0015] Preferably, in step S4, the relaxation zone depth is determined based on the data obtained in step S2. Determine the effective rock penetration length of the anchor bolt This ensures the effective rock penetration length of the anchor bolt. satisfy: ; in, The effective rock penetration length of the anchor bolt extending from the rock platform forming surface into the rock mass; The depth of the relaxation region obtained in step S2; This is the minimum effective anchoring length that the anchor rod extends into the relatively intact rock mass after passing through the relaxation zone.
[0016] Preferably, in step S4, for the slight crack state, single-stage grouting with a target grouting pressure of 0.3 to 0.4 MPa is used; For the moderate fracture state, a first grouting stage and a second grouting stage set at an interval from the first grouting stage are adopted. The target grouting pressure of the second grouting stage is higher than the target grouting pressure of the first grouting stage, and the target grouting pressure of the second grouting stage is 0.4 to 0.5 MPa. For the severe fracture state, the main fracture channels are initially filled and sealed by the initial grouting stage with a target grouting pressure lower than that of the subsequent grouting stages. Then, the pressure is increased in stages to gradually increase the target grouting pressure to 0.5-0.6 MPa. At least one grouting replenishment is performed after the pressure increase grouting.
[0017] Preferably, in each grouting stage of step S4, the data is obtained as the grouting time progresses. Changing real-time grouting pressure and the amount of slurry absorbed per unit time And set the target grouting pressure for the current grouting stage. Termination of grout intake and duration of judgment ; when: ; and: ; The state is maintained continuously for no less than When the current grouting stage ends; in, This refers to the grouting time counted from the start of the current grouting stage; Grouting time The corresponding real-time grouting pressure; Grouting time The corresponding amount of slurry absorbed per unit time; The target grouting pressure corresponding to the current grouting stage; This is used to determine the grout absorption volume at which the grout absorption tends to stabilize during the current grouting stage; The continuous determination time required to simultaneously meet the corresponding termination conditions for real-time grouting pressure and grout intake per unit time.
[0018] Preferably, in step S5, the surrounding rock stability of the anchored reinforcement construction unit is checked according to the preset stability conditions in step S3, and the acoustic wave velocity at the acoustic wave detection point is re-acquired. The attenuation rate of acoustic wave velocity after anchoring reinforcement is determined according to the following formula. : ; Simultaneously, the anchoring force of the anchor bolts and the density of the grouting were obtained to verify the integrity of the reinforcement. in, For the first The acoustic wave velocity at each acoustic wave detection point after the anchoring reinforcement is completed; For the first The attenuation rate of the acoustic wave velocity at each acoustic wave detection point after the anchoring reinforcement is completed, relative to the initial acoustic wave velocity before excavation. When the stability of the surrounding rock meets the requirements but the integrity of the reinforcement does not, grouting should be carried out at the corresponding insufficient reinforcement area. When the stability of the surrounding rock does not meet the requirements but the reinforcement integrity meets the requirements, supplementary stress release is implemented in the pressure relief hole arrangement area that is offset from the anchor bolt hole arrangement area, and the surrounding rock condition is re-determined after the supplementary stress release. When the stability of the surrounding rock and the integrity of the reinforcement do not meet the requirements, the supplementary stress release is implemented first. After the allowable anchoring stability window is reached again, grouting is then applied to the insufficiently reinforced areas.
[0019] The present invention has the following beneficial effects.
[0020] This invention determines the allowable anchoring stability window based on the deformation rate and change of the surrounding rock, and implements stress release before the surrounding rock is stable, so that the anchoring timing matches the actual deformation state of the surrounding rock after excavation, reducing the risk of additional stress caused by premature locking.
[0021] This invention determines the effective rock penetration length of the anchor bolt based on the depth of the relaxation zone, and determines the grouting pressure stage and the number of grouting cycles based on the fracture state, so that the anchoring position and grouting process are adapted to the actual rock mass damage range and fracture development state, thereby improving the anchoring and fracture filling effects.
[0022] This invention verifies the stability and integrity of the surrounding rock after anchoring, and implements supplementary stress release or grouting for different unqualified states, avoiding the use of a uniform repair method and improving the targeting of subsequent treatment.
[0023] This invention forms a closed loop of low-damage molding, condition monitoring, stress release, dynamic anchoring, and verification feedback, allowing the results of the previous step to directly participate in the construction decision-making process of the next step, thereby improving the controllability and reinforcement reliability of the construction process of the rock wall crane beam rock platform. Attached Figure Description
[0024] Figure 1 This is a flowchart illustrating the overall process of the low-damage excavation and dynamic anchoring construction method for rock wall crane beams and rock platforms according to the present invention. Figure 2 This is a schematic diagram of the low-damage forming, anchoring, and pressure relief area layout of the rock platform construction unit of the present invention.
[0025] Reference numerals: 1. Rock platform; 2. Final design outline of the rock platform; 3. Final fine-forming retained layer; 4. Relaxation zone; 5. Relatively intact rock mass; 6. Anchor bolt; 7. Pressure relief hole; 8. Anchor bolt hole arrangement area; 9. Pressure relief hole arrangement area. Detailed Implementation
[0026] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.
[0027] In the description of this invention, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this invention.
[0028] Example
[0029] Please see Figure 1 This embodiment provides a method for low-damage excavation and dynamic anchoring construction of a rock face crane beam platform, including the following steps: S1. Divide the construction area of the rock wall crane beam platform into construction units, and determine the final fine forming retention layer on the outer side of the final design outline of the platform in each construction unit. First, the rock platform to be constructed is divided into multiple construction units along the extension direction of the rock wall crane beam. Where k represents the construction unit number. The division of construction units is based on the principle that the lithology, geostress level and rock mass integrity are relatively consistent within the same construction unit, so that the damage state and surrounding rock deformation state obtained later can correspond to the specific construction area.
[0030] For each construction unit The final design outline of the rock platform is determined based on the design outline of the rock wall crane beam, and the final fine forming retention layer is determined on the outside of the final design outline of the rock platform.
[0031] like Figure 2 As shown, the final design outline 2 of the rock platform 1 forms the surface boundary of the rock platform after low-damage molding. The final fine molding retention layer 3 is located on the side of the final design outline 2 of the rock platform facing the underground powerhouse excavation space, and its range before the final fine molding construction is indicated by a dashed line. After the final fine molding retention layer 3 is removed by the low-damage molding construction, the final design outline 2 of the rock platform forms the rock platform molding surface. The rock platform molding surface, moving inwards from the rock mass, consists of the excavated relaxation zone 4 and the relatively intact rock mass 5. The anchor bolt hole arrangement area 8 and the pressure relief hole arrangement area 9 are staggered on the surface of the rock platform 1.
[0032] The final fine-forming retention layer 3 is located between the outer main excavation area and the final design outline 2 of the rock platform. Its function is to prevent the main blasting disturbance generated during the blasting of the outer main rock mass from directly acting on the rock mass of the rock platform 1, which ultimately serves as the foundation for the rock wall crane beam.
[0033] In this embodiment, the final fine molding retention layer thickness is 30-50cm.
[0034] Acoustic wave detection points were set up in each construction unit. The corresponding relationship between each acoustic wave detection point was maintained in subsequent construction so as to compare the acoustic wave test results before excavation, after excavation and after anchoring reinforcement.
[0035] Before the excavation of the rock platform, the first The initial sound wave velocity was obtained by measuring the sound wave velocity at each sound wave detection point. .
[0036] in: Number the sound wave detection measurement points; For the first The initial acoustic wave velocity obtained at each acoustic detection point before the rock platform excavation is expressed in m / s.
[0037] During acoustic wave testing, the corresponding test points at each stage use the same or mutually corresponding test positions and directions; when repeating the test, the representative wave velocity of the test point is determined by the valid test results, thereby reducing the impact of changes in test position on the comparison of wave velocities before and after.
[0038] Meanwhile, based on the rock platform design and on-site construction space, the anchor bolt hole arrangement area 8 and the pressure relief hole arrangement area 9 are determined in the construction unit. The anchor bolt hole arrangement area 8 and the pressure relief hole arrangement area 9 are staggered on the surface of the rock platform 1, so that when additional stress release is required later, the pressure relief hole 7 will not directly pass through the already formed anchoring structure.
[0039] The output of step S1 includes: construction unit Final design outline of the rock platform; final fine-tuning and retention layer range; initial acoustic wave velocity at each measuring point. Anchor bolt hole layout area; Pressure relief hole layout area.
[0040] The above output serves as the basis for low-damage excavation and damage quantification detection in step S2.
[0041] S2. Perform layered loss-controlled excavation on the construction unit, and perform low-damage molding on the final fine-forming retention layer, and detect the depth of the relaxation zone and the state of the fractures in the rock mass after molding. Step S2 uses the construction unit, final design outline of the rock platform, final fine-forming retention layer range, and initial acoustic wave velocity determined in step S1. As input.
[0042] First, layered micro-delay blasting is carried out on the surrounding rock mass outside the final fine-forming retaining layer.
[0043] The outer rock mass is removed layer by layer along the excavation direction, with the preferred thickness of a single layer being 1.0–1.5 m. By controlling the amount of explosive charge per stage, the spacing between blast holes, and the detonation time difference, the blasting vibration transmitted towards the rock platform from a single blast is reduced.
[0044] The preferred spacing between pre-splitting blasting holes is 40–60 cm, and the preferred detonation time difference is 25–35 ms.
[0045] After the main rock mass is excavated, the final design outline of the rock platform is not directly reached. Instead, the 30-50cm final fine-forming retention layer determined in step S1 is retained.
[0046] Shallow-hole, dense-hole, micro-differential blasting was used to refine the final shape and retain the layer.
[0047] The depth of the blasting hole shall not exceed 80cm, the charge per hole shall not exceed 150g, and the peak velocity of the blasting particles shall be monitored during the blasting process to ensure that the peak velocity of the blasting particles does not exceed 2cm / s.
[0048] After the blasting is completed, the surface of the rock platform is repaired, loose rocks and local loose rock blocks are removed, and the horizontal, vertical and angular surfaces of the rock platform are repaired so that the outline of the rock platform meets the design requirements.
[0049] After the rock platform is formed, the acoustic wave test is repeated at the acoustic wave detection point corresponding to step S1 to obtain the result. After the formation of each acoustic wave detection point, the acoustic wave velocity .
[0050] Calculate the first according to the following formula. Attenuation rate of sound wave velocity at each sound wave detection point : ; in: For the first The attenuation rate of sound wave velocity at each sound wave detection point, in percentage (%) For the first The initial acoustic wave velocity at each acoustic detection point before excavation, in m / s; For the first The acoustic wave velocity at each acoustic detection point after low-damage molding on the rock platform is measured in m / s.
[0051] Sound wave velocity attenuation rate This is used to characterize the degree of wave velocity change in the rock mass near the measuring point after being subjected to excavation unloading and blasting disturbance.
[0052] The extent of rock relaxation was measured from the surface of the rock formation into the interior of the rock mass, and the depth of the relaxation zone was obtained. .
[0053] in: The depth of the relaxation zone, measured from the surface of the rock platform into the interior of the rock mass, is expressed in meters (m).
[0054] The depth of the relaxation zone can be detected using acoustic or borehole testing methods, which are used in underground engineering construction to determine the relaxation range of shallow rock masses.
[0055] In this embodiment, the attenuation rate of the sound wave velocity at each sound wave detection point satisfies the following: ; And the relaxation region depth satisfies: ; Furthermore, no structural through-cracks formed by this excavation were found, which was used as a criterion for determining whether the construction unit met the requirements for low-damage forming.
[0056] If the above conditions are not met, the subsequent anchoring construction will not proceed directly. Instead, the loose rock mass in the unmet location will be further removed and locally repaired. After completion, the corresponding damage detection will be performed again.
[0057] This makes "low-damage testing" a prerequisite for subsequent assessment of the surrounding rock condition, rather than merely a quality record after construction.
[0058] After the low-damage molding process meets the requirements, the surface cracks of the rock platform are inspected to obtain the crack width, extension status, and continuity status.
[0059] Based on the above fracture characteristics, the fracture state is divided into slight fracture state, moderate fracture state, and severe fracture state.
[0060] In this embodiment: when the crack width is less than 0.2 mm and there is no through crack, it is determined to be a slight crack state; when the crack width is 0.2 to 0.5 mm and there is no through crack, it is determined to be a moderate crack state; when the crack width is greater than 0.5 mm or there is a through crack, it is determined to be a severe crack state.
[0061] Step S2 final output: Whether the construction unit meets the low-damage molding requirements; relaxation zone depth. Attenuation rate of sound wave velocity at each sound wave detection point ; fracture state.
[0062] Among them, the depth of the relaxation region In step S4, the effective rock penetration length of the anchor bolt is determined, and the fracture state is used in step S4 to determine the grouting process.
[0063] S3. Obtain the time series of surrounding rock displacement after the rock platform is formed, determine the deformation rate and its change based on the surrounding rock displacement time series, and determine that the construction unit enters the allowable anchoring stability window when the surrounding rock deformation rate and its change meet the preset stability conditions; if the preset stability conditions are not met, stress release is performed on the construction unit and the surrounding rock state is re-determined. Step S3 takes the construction unit that has passed the low-damage molding qualification in step S2 as the processing object.
[0064] Step S3 addresses the issue that when high-stress surrounding rock is still undergoing unloading deformation and stress redistribution after excavation, it is not appropriate to determine whether anchoring is suitable solely based on a fixed waiting time.
[0065] Rock displacement monitoring points are set up in the construction unit.
[0066] In the Each monitoring moment Get the Displacement at each surrounding rock displacement monitoring point .
[0067] in: This refers to the monitoring time or monitoring cycle number; Number the surrounding rock displacement monitoring points; For the first Each monitoring time point is measured in hours (h). For the first The surrounding rock displacement monitoring point at the first The surrounding rock displacement was obtained at each monitoring time, and the unit is mm.
[0068] All monitoring points use the same positive displacement direction. The absolute value of the deformation rate is used for condition determination to avoid inconsistencies caused by different monitoring directions.
[0069] For the The deformation rate of the surrounding rock is calculated based on the displacement changes at two adjacent monitoring points at each surrounding rock displacement monitoring point. : ; in: For the first The surrounding rock displacement monitoring point at the first -1 monitoring time to the The surrounding rock deformation rate between monitoring times is expressed in mm / h. For the first The surrounding rock displacement monitoring point at the first -1 rock displacement at monitoring time, in mm; For the first -1 monitoring time point, in hours.
[0070] After obtaining the deformation rate at each surrounding rock displacement monitoring point, the maximum absolute deformation rate of all monitoring points in the current monitoring period is taken: ; in: For the first The maximum absolute deformation rate among all surrounding rock displacement monitoring points in a monitoring cycle, in mm / h.
[0071] Using the maximum absolute deformation rate as the state control value of the construction unit can avoid the situation where the local surrounding rock is still deforming rapidly and is masked by the average value of other stable measuring points.
[0072] Further calculations were performed on the change in the maximum absolute deformation rate between two adjacent monitoring periods. : ; in: For the first The monitoring cycle is relative to the first - The change in the maximum absolute deformation rate over one monitoring cycle, in mm / h; For the first - The maximum absolute deformation rate among all surrounding rock displacement monitoring points in one monitoring cycle, in mm / h.
[0073] Predetermined: Number of continuous monitoring cycles Allowable deformation rate threshold ; Threshold for allowable deformation rate variation .
[0074] in: This represents the number of monitoring cycles required to continuously meet the conditions for confirming the continued stabilization of the surrounding rock, and is dimensionless. This indicates the allowable deformation rate threshold for anchoring, expressed in mm / h. This represents the threshold for the maximum allowable change in absolute deformation rate between adjacent monitoring periods, expressed in mm / h.
[0075] , and The determination is based on the surrounding rock grade, ground stress conditions, design deformation control requirements, monitoring accuracy, and deformation law of the surrounding rock in the test section.
[0076] When continuous All monitoring cycles meet the following requirements: ; and: ; When the deformation of the surrounding rock of the current construction unit has entered a continuous stabilization state, it is determined that the construction unit has entered the allowable anchoring stability window.
[0077] This approach uses both deformation rate and the change in deformation rate, rather than just judging the instantaneous deformation rate of a single monitoring session. The purpose is to avoid misjudging the stability of the surrounding rock due to a random drop below the allowable deformation rate threshold at a particular monitoring moment.
[0078] When the current construction unit has not entered the allowable anchoring stability window, anchor bolt locking is not performed, and the first set of pressure relief holes is constructed in the pressure relief hole layout area determined in step S1.
[0079] The first set of pressure relief holes is arranged according to the spacing of the first hole.
[0080] In this embodiment, the pressure relief hole diameter can be 50mm, the hole depth can be 1.5m, and the first hole spacing can be 1.0m.
[0081] After the first set of pressure relief holes were constructed, the surrounding rock displacement was obtained and calculated in the same manner as described above. and Then, reassess whether the construction unit has entered the allowable anchoring stability window.
[0082] If the anchoring stability window has been reached, then stop adding more pressure relief holes.
[0083] If the allowable anchoring stability window has not yet been reached, a second set of pressure relief holes shall be added between adjacent first set of pressure relief holes or in the local area corresponding to the maximum absolute deformation rate, so that the effective spacing of the added pressure relief holes is less than the spacing of the first holes.
[0084] After the second set of pressure relief holes is completed, the surrounding rock condition is assessed again.
[0085] Therefore, stress relief is not completed all at once according to the fixed number of holes, but is performed in the following order: first pressure relief - retest - if still unstable, supplementary pressure relief - retest.
[0086] Once the construction unit reaches the allowable anchorage stability window, further addition of pressure relief holes is stopped to reduce unnecessary drilling that could weaken the rock mass of the rock platform that serves as the bearing foundation for the rock wall crane beam.
[0087] For construction units that still cannot enter the allowable anchoring stability window after reaching the preset maximum pressure relief level or the minimum pressure relief hole spacing allowed by the design, the pressure relief holes will not be added indefinitely. Instead, the current anchoring construction will be stopped and the geological conditions of the area will be reviewed.
[0088] Step S3 output: Whether the surrounding rock has entered the allowable anchoring stability window; actual pressure relief level; final pressure relief hole layout status; whether it is allowed to proceed to step S4 for anchoring reinforcement.
[0089] S4. After the construction unit enters the allowable anchoring stability window, determine the effective rock penetration length of the anchor bolt according to the relaxation zone depth, and select grouting processes with different grouting pressure stages and grouting times according to the crack state to implement anchoring reinforcement. like Figure 2 As shown, anchor bolt 6 extends from the formed surface of rock platform 1 into the interior of relatively intact rock mass 5, wherein the relaxation zone depth is... The minimum effective anchorage length is measured from the formed surface of the rock platform to the boundary between the relaxed zone 4 and the relatively intact rock mass 5. The effective rock penetration length of the anchor bolt is measured from the boundary position to the end of the effective anchoring section of the anchor bolt 6. The effective rock insertion end of anchor bolt 6 is measured from the surface of the rock platform.
[0090] Step S4 is executed only after step S3 determines that the current construction unit has entered the allowable anchoring stability window.
[0091] The input for step S4 includes at least the relaxation zone depth obtained in step S2. The crack state obtained in step S2; the result of the judgment of the allowable anchorage stability window obtained in step S3; and the anchorage capacity of the anchor bolt required by the design.
[0092] The relaxed area near the formed surface after the rock platform is excavated is considered as the shallow damaged area that needs to be repaired and crossed.
[0093] Effective rock penetration length of anchor bolt satisfy: ; in: The effective rock penetration length of the anchor bolt extending from the rock platform forming surface into the rock mass, in meters; The relaxation zone depth is obtained by actual measurement in step S2, in meters; The minimum effective anchorage length, expressed in meters, is the length of the anchor bolt that extends into the relatively intact rock mass after passing through the relaxation zone.
[0094] The anchorage force of the rock wall crane beam is determined based on the design anchorage force, surrounding rock strength parameters, and anchor pull-out test results.
[0095] Therefore, when the relaxation zone depth of different construction units At the same time, the effective rock penetration length of the corresponding anchor bolt can be determined according to the actual damage range, so that after the anchor bolt passes through the shallow loose rock mass, it forms an effective anchoring section that meets the design requirements in the relatively intact rock mass.
[0096] In this embodiment, the anchor bolt hole diameter can be 42mm, the anchor bolt hole depth can be in the range of 2.0 to 2.5m, and the anchor bolts can be arranged in a staggered pattern of 80cm × 80cm. The above parameters are used to illustrate one embodiment and do not change the requirement that the effective rock penetration length of the anchor bolts must meet certain conditions. The relationship.
[0097] For the slight crack state determined in step S2, single-stage grouting with a target grouting pressure of 0.3 to 0.4 MPa is adopted.
[0098] Its purpose is to fill the shallow micro-fractures in the rock platform and the area around the anchor bolt holes that needs to be consolidated, so as to avoid unnecessary multi-stage high-pressure grouting in areas with low fracture development.
[0099] In this embodiment, the target grouting pressure for the single-stage grouting can be 0.35 MPa.
[0100] For moderately fractured conditions, a first grouting stage and a second grouting stage are adopted.
[0101] In the first grouting stage, grouting is carried out at a relatively low target pressure so that the main cracks are filled with grout first.
[0102] After the first grouting stage is completed, a preset time interval is elapsed before the second grouting stage is implemented. The target grouting pressure of the second grouting stage is higher than that of the first grouting stage, so as to supplement and penetrate the cracks that have not been fully filled after the first grouting.
[0103] In this embodiment, the target grouting pressure for the second grouting stage of moderate cracks can be controlled within the range of 0.4 to 0.5 MPa. The first stage pressure stabilization time can be 2 minutes, and the second grouting stage is performed after a 5-minute interval, with pressure stabilization for 3 minutes.
[0104] For severely fractured areas, the highest grouting pressure is not applied directly in the initial stage. First, an initial grouting stage is performed with a target grouting pressure lower than subsequent stages, allowing the grout to preferentially enter the main fracture channels for preliminary filling and sealing. Once the grout's ability to escape from the main fracture channels decreases or preliminary filling is achieved, staged pressure-increasing grouting is then performed, allowing the grout to further penetrate secondary fractures and areas that are not fully filled. At least one replenishment grouting operation is performed after the staged pressure-increasing grouting is completed. In one embodiment, the grouting process for severely fractured areas can be gradually increased from a lower pressure stage to 0.5–0.6 MPa, with the highest target grouting pressure being 0.6 MPa. For cases with penetrating fractures, using a lower target grouting pressure for preliminary filling and sealing also helps reduce the rapid escape of grout along the penetrating fractures.
[0105] Real-time acquisition of grouting pressure at each grouting stage and the amount of slurry absorbed per unit time .
[0106] in: This represents the grouting time since the start of the current grouting stage, in minutes. Grouting time The corresponding real-time grouting pressure is expressed in MPa. Grouting time The corresponding slurry intake per unit time can be expressed in L / min.
[0107] For the current grouting stage, determine: the target grouting pressure. Termination of grout intake ; Duration of determination .
[0108] in: The target grouting pressure for the current grouting stage is expressed in MPa and is determined based on the fracture condition and the current grouting stage. To determine the cessation of grout absorption when the rock mass grout absorption tends to stabilize, the unit is... same; The time required for the real-time grouting pressure and the amount of grout absorbed per unit time to simultaneously meet the termination conditions is measured in minutes.
[0109] when: ; and: ; The state is maintained continuously for no less than At that time, it is determined that the current grouting stage has been completed.
[0110] Determined based on the fracture condition and the aforementioned differentiated grouting process; and The grouting quality requirements are determined based on the grout properties of the construction test section, the groutability of the surrounding rock, and the design grouting quality requirements.
[0111] Using both pressure and grout intake as the conditions for ending the grouting stage can prevent premature grouting from being stopped when the target pressure has been reached but there is still significant grout intake.
[0112] Step S4 output: actual effective rock penetration length of the anchor bolt; actual grouting process used; pressure at each grouting stage; grouting volume variation; number of grouting replenishments; construction unit after anchor reinforcement is completed.
[0113] S5. After anchoring and grouting reinforcement, the stability of the surrounding rock is checked based on the deformation rate and its change, and the integrity of the reinforcement is checked based on the acoustic wave velocity, anchor bolt anchoring force, and grouting density. If the stability of the surrounding rock does not meet the requirements, supplementary stress release is implemented and the surrounding rock condition is re-evaluated. If the stability of the surrounding rock meets the requirements but the integrity of the reinforcement does not meet the requirements, grouting is applied to the insufficiently reinforced areas and the integrity of the reinforcement is re-checked. When both the stability of the surrounding rock and the integrity of the reinforcement meet the requirements, the construction of the current construction unit is terminated.
[0114] Step S5 uses the construction unit after the anchoring reinforcement completed in step S4 as input.
[0115] Step S5 checks whether the surrounding rock remains stable and whether the rock mass has been sufficiently reinforced, to avoid treating two different types of problems as "insufficient grouting".
[0116] Continue to obtain the surrounding rock displacement data from step S3, and calculate it using the same method as in step S3. and .
[0117] When continuous All monitoring cycles meet the following requirements:
[0118] and:
[0119] At that time, it was determined that the stability of the surrounding rock after anchoring met the requirements.
[0120] Therefore, the same logic for judging the stability of the surrounding rock is used before and after anchoring to ensure that the judgment criteria are consistent.
[0121] The acoustic wave detection point corresponding to step S1 is used to perform acoustic wave detection again to obtain the first... The acoustic wave velocity at each acoustic wave detection point after anchor reinforcement .
[0122] Calculate the attenuation rate of the acoustic wave velocity after anchoring reinforcement relative to the initial acoustic wave velocity before excavation. :
[0123] in: For the first The acoustic wave velocity at each acoustic detection point after the anchoring reinforcement is completed, in m / s; The attenuation rate of the acoustic wave velocity after anchoring reinforcement relative to the initial acoustic wave velocity before excavation is expressed in units of 1.
[0124] Simultaneously, the anchoring force and grouting density of the anchor bolts are tested, and the integrity of the reinforcement of the current construction unit is judged in combination with the residual state of the cracks to determine whether it meets the design requirements.
[0125] When the surrounding rock stability meets the requirements and the reinforcement integrity meets the requirements, the current construction unit is completed and the subsequent rock wall crane beam construction process or the next construction unit begins.
[0126] When the stability of the surrounding rock meets the requirements, but the integrity of the reinforcement does not, it indicates that the main problem of the current construction unit lies in the quality of crack filling or local anchoring.
[0127] Instead of implementing large-scale stress release again, targeted grouting is carried out at the deficient locations identified during the reinforcement integrity test.
[0128] After the grouting is completed, step S5 is repeated to verify the integrity of the reinforcement.
[0129] When the surrounding rock stability does not meet the requirements while the reinforcement integrity meets them, it indicates that continuous deformation still exists after the current construction unit is anchored. In this case, instead of increasing the grouting pressure, supplementary stress release is implemented in the pressure relief hole area determined in step S1 and staggered from the anchor hole area. After the supplementary stress release is completed, return to step S3, re-acquire the surrounding rock displacement time series, and determine whether it has re-entered the allowable anchoring stability window; after re-reaching the allowable anchoring stability window, the surrounding rock stability and reinforcement integrity are checked again.
[0130] When neither the stability of the surrounding rock nor the integrity of the reinforcement meets the requirements, the process should proceed in the order of first restoring the stability of the surrounding rock and then addressing the integrity of the reinforcement. First, supplementary stress release should be implemented, and then step S3 should be returned to reassess whether the rock has entered the allowable anchoring stability window. After the surrounding rock reaches the allowable anchoring stability window again, grouting should be applied to the areas identified as insufficiently reinforced. After grouting is completed, the stability of the surrounding rock and the integrity of the reinforcement should be re-verified.
[0131] This forms a complete construction closed loop: low-damage molding - state determination - stress release - stability window - dynamic anchoring - dual-state verification - feedback processing.
[0132] The following set of example data illustrates the data processing and construction decision-making process of this method. This set of data is used to illustrate the relationship between the calculation methods and steps; however, data not specified in the aforementioned implementation parameters may vary. , , , and In actual engineering, the requirements are determined according to the test section and design requirements.
[0133] By construction unit For example.
[0134] Low-damage state calculation, assuming an acoustic detection point is used before excavation: ; After low-damage molding of the rock platform, the following measurements were taken at the corresponding locations: ; but: ; ; The attenuation rate of the sound wave velocity at this measuring point is 4%, which is less than 5%.
[0135] The depth of the relaxation zone in this construction unit was determined by testing: ; Right now: ; Meanwhile, no structural through-cracks were found caused by this blasting. Therefore, this construction unit meets the low-damage forming access criteria.
[0136] A crack with a width of 0.35 mm was detected on site and had local extension, but it did not form a clear connection. Therefore, according to the aforementioned judgment method, the area was determined to be in a moderate crack state.
[0137] Anchorage stability window calculations are permitted. To illustrate the calculation process, it is assumed that the construction unit was determined through a test section. ; ; ; This means that the surrounding rock needs to meet both the deformation rate and rate change conditions for three consecutive monitoring cycles before it can be determined that the surrounding rock has entered the allowable anchoring stability window.
[0138] Initial monitoring after excavation revealed that the maximum absolute deformation rate was still higher than 0.05 mm / h, so the first set of pressure relief holes was constructed first.
[0139] After the first set of pressure relief holes were constructed, the maximum absolute deformation rates obtained successively were: ; ; ; The changes corresponding to adjacent monitoring periods are: ; ; If the change in the previous monitoring cycle is also no greater than 0.01 mm / h, then the following conditions are met for three consecutive monitoring cycles: ; and: ; Therefore, construction unit Once the anchoring stability window is reached, no further pressure relief holes will be added, and anchoring construction will commence.
[0140] Determining the effective rock penetration length of the anchor bolt, construction unit The depth of the relaxation region is: ; Assuming the results are determined based on the rock mass strength, design anchoring force, and pull-out test results of the construction area: ; The effective rock penetration length of the anchor bolt must meet the following requirements: ; Right now: ; ; Actual construction selection: ; because Therefore, the anchor bolt can cross a shallow relaxation zone of 0.08m and form an effective anchorage length of no less than the design requirement within a relatively intact rock mass.
[0141] The grouting method was determined to be two-stage grouting, since the current construction unit is in a state of moderate cracking.
[0142] The first grouting stage uses a relatively low target pressure for initial filling; after the first stage is completed, there is a 5-minute interval; in the second grouting stage, the target pressure is increased for supplementary grouting, and the final target pressure is controlled within 0.5 MPa.
[0143] Real-time recording for each stage and .
[0144] Assume the target grouting pressure for a certain stage is The termination grout intake volume determined in the test section is The duration of the judgment is .
[0145] When the measured data continuously satisfy: ; and: ; and continue for no less than When the time comes, the grouting for this stage ends.
[0146] Therefore, the fracture condition is not only used to determine a grouting pressure value, but also directly used to determine whether to use single-stage grouting or multi-stage grouting and whether to implement supplementary grouting.
[0147] After anchoring, the rock displacement is checked and monitored.
[0148] When it continues Each monitoring cycle satisfies: ; and: ; At that time, it was confirmed that the stability of the surrounding rock met the requirements.
[0149] At the same time, a third test was conducted on the acoustic wave detection points.
[0150] Assumption: ; but: ; ; If the anchoring force and grout density test results meet the design requirements, then the stability of the surrounding rock and the integrity of the reinforcement are both deemed satisfactory, and the construction unit... Construction completed.
[0151] If the deformation of the surrounding rock meets the stability requirements but the integrity of the reinforcement does not, then grouting should only be applied to the insufficiently reinforced areas; if the surrounding rock is still unstable, then the stress release step should be returned first, rather than directly increasing the grouting pressure.
[0152] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A method for low-damage excavation and dynamic anchoring construction of a rock face crane beam platform, characterized in that, Includes the following steps: S1. Divide the construction area of the rock wall crane beam platform into construction units, and determine the final fine forming retention layer on the outer side of the final design outline of the platform in each construction unit. S2. Perform layered loss-controlled excavation on the construction unit, and perform low-damage molding on the final fine-forming retention layer, and detect the depth of the relaxation zone and the state of the fractures in the rock mass after molding. S3. Obtain the time series of surrounding rock displacement after the rock platform is formed, and determine the deformation rate and its change based on the surrounding rock displacement time series. When the deformation rate and its change in the surrounding rock are both no greater than the corresponding threshold within a consecutive preset monitoring period, the construction unit is determined to have entered the allowable anchoring stability window; if the aforementioned conditions are not met, stress release is performed on the construction unit and the surrounding rock condition is reassessed. S4. After the construction unit enters the allowable anchoring stability window, the effective rock penetration length of the anchor rod is determined according to the depth of the relaxation zone, so that the anchor rod passes through the relaxation zone and extends into the relatively intact rock mass to form an effective anchoring section. Based on the fracture state, a grouting process with different grouting pressure stages and grouting times is selected to implement anchoring reinforcement. S5. After anchoring and grouting reinforcement, the stability of the surrounding rock is checked based on the deformation rate and its change, and the integrity of the reinforcement is checked based on the acoustic wave velocity, anchor bolt anchoring force, and grouting density. If the stability of the surrounding rock does not meet the requirements, supplementary stress release is implemented and the surrounding rock condition is re-evaluated. If the stability of the surrounding rock meets the requirements but the integrity of the reinforcement does not meet the requirements, grouting is applied to the insufficiently reinforced areas and the integrity of the reinforcement is re-checked. When both the stability of the surrounding rock and the integrity of the reinforcement meet the requirements, the construction of the current construction unit is terminated.
2. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 1, characterized in that: In step S1, the construction unit is divided along the length of the crane beam on the rock wall. Acoustic wave detection points are set in each construction unit to obtain the initial acoustic wave velocity at each detection point before excavation. ; In each construction unit, the anchor bolt hole arrangement area and the pressure relief hole arrangement area are determined, and the anchor bolt hole arrangement area and the pressure relief hole arrangement area are staggered on the rock platform surface. in, Numbering of sound wave detection measurement points, For the first The initial acoustic wave velocity measured at each acoustic detection point before the rock platform excavation.
3. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 2, characterized in that: In step S2, the rock mass outside the final design outline of the rock platform is first subjected to layered micro-delay blasting, and a final fine-forming retention layer with a thickness of 30-50cm is retained outside the final design outline of the rock platform; then the final fine-forming retention layer is subjected to shallow-hole and dense-hole micro-delay blasting and trimming, and the peak vibration velocity of the blasting particles is not greater than 2cm / s. After molding, obtain the first The sound wave velocity at each sound wave detection point Calculate the first according to the following formula Attenuation rate of sound wave velocity at each sound wave detection point : ; in, For the first Attenuation rate of sound wave velocity at each sound wave detection point; For the first The initial acoustic wave velocity measured at each acoustic detection point before the rock platform excavation; For the first The acoustic wave velocity was measured at each acoustic detection point after low-damage molding of the rock platform. And detect the depth of the relaxation region. Attenuation rate of sound wave velocity at each sound wave detection point All are no greater than 5%, the depth of the relaxation zone If the crack is no larger than 0.10m and no structural through-cracks formed by this excavation are found, the current construction unit is deemed to have met the low-damage forming requirements; otherwise, the loosened rock mass of the part that has not met the low-damage forming requirements shall be removed and repaired and then re-inspected. in, The depth of the relaxation zone is measured from the surface of the rock platform into the interior of the rock mass.
4. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 3, characterized in that: In step S2, the crack state is determined based on the crack width and continuity of the cracks after the rock platform is formed. Cracks with a crack width of less than 0.2 mm and no continuous cracks are defined as minor cracks, cracks with a crack width of 0.2 to 0.5 mm and no continuous cracks are defined as moderate cracks, and cracks with a crack width greater than 0.5 mm or with continuous cracks are defined as severe cracks.
5. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 1, characterized in that: In step S3, surrounding rock displacement monitoring points are set up in the construction unit. Each monitoring moment Get the Displacement at each surrounding rock displacement monitoring point Calculate the first according to the following formula The deformation rate of surrounding rock at each surrounding rock displacement monitoring point between adjacent monitoring times : ; And determine the first according to the following formula The maximum absolute deformation rate of each surrounding rock displacement monitoring point within each monitoring period. : ; The change in the maximum absolute deformation rate between adjacent monitoring periods is determined by the following formula. : ; When continuous All monitoring cycles meet the following requirements: ; and: ; At that time, it is determined that the construction unit has entered the allowable anchoring stability window; in, For monitoring cycle number; Number the surrounding rock displacement monitoring points; For the first Each monitoring moment; For the first -1 monitoring time; For the first The surrounding rock displacement monitoring point at the first The surrounding rock displacement measured at each monitoring moment; For the first The surrounding rock displacement monitoring point at the first -1 monitoring time point measured surrounding rock displacement; For the first The surrounding rock displacement monitoring point at the first -1 monitoring time to the The deformation rate of the surrounding rock between monitoring moments; For the first The maximum absolute deformation rate among all surrounding rock displacement monitoring points within a monitoring cycle; For the first -The maximum absolute deformation rate among all surrounding rock displacement monitoring points within one monitoring cycle; For the first The monitoring cycle and the first - The change in the maximum absolute deformation rate between 1 monitoring cycles; The preset number of continuous monitoring cycles is used to determine the continued stabilization of surrounding rock deformation. The threshold for the deformation rate under allowable anchoring conditions; The threshold for the maximum absolute deformation rate change allowed between adjacent monitoring cycles under anchoring conditions.
6. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 5, characterized in that: In step S3, when the construction unit has not entered the allowable anchoring stability window, the first set of pressure relief holes is arranged according to the first hole spacing, and the surrounding rock condition is re-determined after the construction of the first set of pressure relief holes; if it still has not entered the allowable anchoring stability window, a second set of pressure relief holes is added between adjacent first sets of pressure relief holes and / or in the area corresponding to the maximum absolute deformation rate, so that the effective pressure relief hole spacing after the addition is smaller than the first hole spacing. Once the construction unit reaches the window of allowable anchoring stability, the addition of pressure relief holes shall be stopped.
7. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 1, characterized in that: In step S4, the relaxation zone depth is determined based on the data obtained in step S2. Determine the effective rock penetration length of the anchor bolt This ensures the effective rock penetration length of the anchor bolt. satisfy: ; in, The effective rock penetration length of the anchor bolt extending from the rock platform forming surface into the rock mass; The depth of the relaxation region obtained in step S2; This is the minimum effective anchoring length that the anchor rod extends into the relatively intact rock mass after passing through the relaxation zone.
8. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 4, characterized in that: In step S4, for the slight crack state, single-stage grouting with a target grouting pressure of 0.3 to 0.4 MPa is used; For the moderate fracture state, a first grouting stage and a second grouting stage set at an interval from the first grouting stage are adopted. The target grouting pressure of the second grouting stage is higher than the target grouting pressure of the first grouting stage, and the target grouting pressure of the second grouting stage is 0.4 to 0.5 MPa. For the severe fracture state, the main fracture channels are initially filled and sealed by the initial grouting stage with a target grouting pressure lower than that of the subsequent grouting stages. Then, the pressure is increased in stages to gradually increase the target grouting pressure to 0.5-0.6 MPa. At least one grouting replenishment is performed after the pressure increase grouting.
9. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 8, characterized in that: In each grouting stage of step S4, the data is obtained as the grouting time progresses. Changing real-time grouting pressure and the amount of slurry absorbed per unit time And set the target grouting pressure for the current grouting stage. Termination of grout intake and duration of judgment ; when: ; and: ; The state is maintained continuously for no less than When the current grouting stage ends; in, This refers to the grouting time counted from the start of the current grouting stage; Grouting time The corresponding real-time grouting pressure; Grouting time The corresponding amount of slurry absorbed per unit time; The target grouting pressure corresponding to the current grouting stage; This is used to determine the grout absorption volume at which the grout absorption tends to stabilize during the current grouting stage; The continuous determination time required to simultaneously meet the corresponding termination conditions for real-time grouting pressure and grout intake per unit time.
10. The method for low-damage excavation and dynamic anchoring construction of rock face crane beams and rock platforms according to claim 2, characterized in that: In step S5, the stability of the surrounding rock of the anchored reinforcement construction unit is checked according to the preset stability conditions in step S3, and the acoustic wave velocity at the acoustic wave detection point is reacquired. The attenuation rate of acoustic wave velocity after anchoring reinforcement is determined according to the following formula. : ; Simultaneously, the anchoring force of the anchor bolts and the density of the grouting were obtained to verify the integrity of the reinforcement. in, For the first The acoustic wave velocity at each acoustic wave detection point after the anchoring reinforcement is completed; For the first The attenuation rate of the acoustic wave velocity at each acoustic wave detection point after the anchoring reinforcement is completed, relative to the initial acoustic wave velocity before excavation. When the stability of the surrounding rock meets the requirements but the integrity of the reinforcement does not, grouting should be carried out at the corresponding insufficient reinforcement area. When the stability of the surrounding rock does not meet the requirements but the reinforcement integrity meets the requirements, supplementary stress release is implemented in the pressure relief hole arrangement area that is offset from the anchor bolt hole arrangement area, and the surrounding rock condition is re-determined after the supplementary stress release. When the stability of the surrounding rock and the integrity of the reinforcement do not meet the requirements, the supplementary stress release is implemented first. After the allowable anchoring stability window is reached again, grouting is then applied to the insufficiently reinforced areas.