A grouting screw anchor steel pipe composite pile foundation and a construction method thereof
By installing grouting pipes inside the steel pipe anchor and performing pressure grouting, combined with anchoring tightening devices, the problem that existing spiral anchor foundations cannot be applied to rock foundations has been solved, achieving efficient and stable foundation construction and improved bearing capacity in mountainous power transmission corridors.
Patent Information
- Application Number
- CN202611516894.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-28
- Publication Date
- 2026-11-24
AI Technical Summary
Existing spiral anchor foundations are not suitable for rock foundations. Traditional rock anchor foundations are difficult to construct and costly when the overlying soil layer is thick. Traditional bored pile foundations are noisy and produce a lot of waste soil when constructed in mountainous areas. Existing composite piles have large dispersion and unstable bearing capacity in mountainous foundations.
A grouting spiral anchor steel pipe composite pile foundation was designed. By fixing the grouting pipe inside the steel pipe anchor, cement mortar is filled into the pre-drilled hole and the inside of the steel pipe anchor after pressure grouting. The gap between the pile and rock and the pile and soil are formed as a whole. Combined with the anchoring device, the load is transferred. It is suitable for the "soil above rock" foundation in mountain power transmission corridors.
It improves tensile strength, reduces foundation dispersion, reduces concrete usage, is suitable for mechanized construction, and enhances construction efficiency and load-bearing stability.
Smart Images

Figure CN123153431A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to a grouting spiral anchor steel pipe composite pile foundation and its construction method, belonging to the field of pile foundation engineering technology. Background Technology
[0002] Currently, promoting the construction of green power grids is the primary task in the design and construction of power transmission and transformation projects. Tower foundations are a major component of the design and construction of transmission line projects, directly determining the overall investment and construction period. Therefore, promoting green and environmentally friendly foundations with optimized structural designs, low concrete consumption, and ease of mechanized construction is a trend in the industry.
[0003] In recent years, with the rapid development of power grid construction, corridor resources in various regions have become increasingly strained, leading to a surge in power transmission line projects in mountainous areas. The foundations of these mountainous transmission corridors are primarily characterized by alternating layers of soil and rock. In recent years, mountainous terrain and soil-rock foundations have accounted for over 60% of the corridors of typical completed or planned power transmission line projects. This indicates that power grid construction in the new era will focus on power transmission lines in mountainous areas, with soil-rock foundations being particularly prominent in these projects.
[0004] However, existing helical anchor foundations are not suitable for rock foundation conditions. In addition, their foundations have a large degree of dispersion. The final bearing capacity and deformation performance of helical anchor foundations constructed at different locations vary greatly, making them unstable and difficult to predict. During application, a large safety factor needs to be reserved to ensure the safety of the foundation. Existing rock anchor foundations are affected by the thickness of the overburden layer. The thicker the overburden layer, the longer the anchor needs to be, which not only makes construction difficult but also increases costs and reduces the effectiveness of use, making it impossible to promote them on a large scale.
[0005] Specifically, conventional spiral anchor foundations are only suitable for soil layers and cannot penetrate when encountering underlying rock. Traditional rock anchor foundations, when the overlying soil layer is thick, have a long free section of the anchor rod, which easily leads to problems such as rod deformation and insufficient horizontal bearing capacity. Traditional bored pile foundations involve large amounts of earthwork excavation in mountainous areas, resulting in high noise levels, a large amount of waste soil, large concrete consumption, and long construction periods. At the same time, during the screwing of steel pipe anchors in existing composite piles, gravel and sediment generated on the borehole wall can easily accumulate at the pile bottom, preventing the pile from being positioned at the design elevation. Improper grouting pipe layout can lead to incomplete grouting and poor bonding at the pile-rock interface, resulting in large foundation dispersion and unstable bearing capacity. Summary of the Invention
[0006] To overcome the shortcomings of the existing technology, this invention designs a grouting spiral anchor steel pipe composite pile foundation and construction method, which is suitable for foundation types with "soil above and rock below" interlayered soil and rock conditions in mountainous power transmission corridors. It meets the conditions for mechanized foundation construction, takes into account the pull-out resistance of the spiral anchor plate in the soil layer and the rock embedding in the rock layer, the treatment of sediment at the bottom of the pile through the sedimentation hole, the integrated grouting pipe to achieve overall grouting of the pile hole, and the steel pipe anchor rigid connection of the pile cap anchoring device to achieve joint bearing of tensile, compressive and horizontal loads.
[0007] To achieve the above objectives, the present invention adopts the following technical solution: Technical Solution 1 A grouting spiral anchor steel pipe composite pile foundation includes an installation cap, the bottom of which is embedded in the soil layer. Several evenly arranged anchoring devices are installed inside the installation cap, each corresponding to a steel pipe anchor. The bottom end of the steel pipe anchor extends through the soil layer into the rock layer, and multiple anchor discs are spaced apart on the steel pipe anchor's shaft in the soil layer. A grouting pipe for injecting cement mortar is also fixedly connected to the inner wall of the steel pipe anchor.
[0008] Furthermore, the anchoring device includes a base plate, a connecting sleeve fixed on the base plate, and several stiffening plates fixed between the base plate and the connecting sleeve, with each stiffening plate evenly arranged circumferentially; the inner diameter of the connecting sleeve is 4mm-8mm larger than the outer diameter of the steel pipe anchor.
[0009] Furthermore, the steel pipe anchor has multiple sets of first bolt holes at its rod head position, and the connecting sleeve has multiple sets of second bolt holes that correspond one-to-one with the first bolt holes. The first bolt holes and the second bolt holes are detachably connected by bolts.
[0010] Furthermore, the mounting platform includes a concrete platform and a concrete main column integrally set on top of the concrete platform. The top of the concrete main column extends out of the soil layer, and multiple anchor bolts are embedded inside the concrete main column, with the tops of the anchor bolts extending out of the concrete main column.
[0011] Furthermore, the tail end of the steel pipe anchor is provided with a 40°-50° boot foot, and the bottom end of the boot foot is integrally provided with a pointed tip; the bottom end of the steel pipe anchor is also provided with a sedimentation hole, and the depth of the sedimentation hole is not less than 150mm.
[0012] Furthermore, the anchor disc is a helical blade, and the outer diameter of the anchor disc is larger than the outer diameter of the steel pipe anchor. The number of anchor discs is 2-4.
[0013] Technical Solution Two A construction method for a grouting spiral anchor steel pipe composite pile foundation includes the following steps: Construction preparation: Based on the foundation layout requirements, complete the layout and marking of hole positions, and rationally plan the operating area of construction machinery; Drilling and cleaning: Excavate the foundation pit to the design depth and level the foundation pit; drill pre-drilled holes and sedimentation holes at the bottom of the foundation pit; Composite pile placement: The steel pipe anchor with an internal grouting pipe is hoisted into the pre-drilled hole using a spiral drilling rig, and the spiral drilling rig starts to rotate the power head when the anchor plate contacts the soil, so that the steel pipe anchor and the anchor plate are screwed into the soil. Grouting: Before grouting, ensure that there are no residues or debris inside the steel pipe anchor, and then inject grout into the grouting pipe to fill the pre-drilled hole and the inside of the steel pipe anchor; after grouting, compact the mortar. Foundation casting: After the auger drilling rig is disconnected from the connection, the foundation is cast and installed in the foundation pit, and multiple anchor bolts are pre-embedded in the foundation for connecting the upper components.
[0014] Furthermore, in the grouting step, M25-M30 cement mortar is used for grouting, and pressure grouting is adopted with a grouting pressure of 0.3MPa-0.8MPa; after grouting is completed, the pressure is maintained for 3min-8min.
[0015] Furthermore, the drilling and cleaning steps also include cleaning the stone powder, loose soil and loose rocks in the pre-drilled hole after the pre-drilled hole is drilled; in the drilling and cleaning steps, the center point positioning error of the steel pipe anchor does not exceed 10mm, the tilt angle deviation does not exceed 1°, and the azimuth angle deviation does not exceed 2°.
[0016] Furthermore, in the drilling and cleaning steps, the steel pipe anchor turning speed is no more than 10 revolutions / min, and the average displacement of the steel pipe anchor pile per revolution is no less than 85% of the anchor plate pitch.
[0017] Compared with the prior art, the present invention has the following features and beneficial effects: In this invention, the steel pipe anchor penetrates the soil layer and extends into the rock layer to achieve rock embedding, transferring the load to the hard bedrock. Multiple anchor discs in the soil section utilize the anchoring resistance of the soil to significantly improve the pull-out bearing capacity. A grouting pipe is fixed inside the steel pipe anchor. After pressure grouting, cement mortar fills the pre-drilled hole, the inside of the steel pipe anchor, the pile-rock, and the pile-soil gaps, cementing the steel pipe anchor, surrounding rock, and soil into a whole, eliminating voids around the pile, reducing foundation dispersion, and improving overall stiffness. A sedimentation hole is set at the bottom of the pile, where gravel and slag generated during the tightening construction fall into the sedimentation hole. This design avoids raising the pile body due to sediment, ensuring the steel pipe anchor is positioned to the designed depth. The 40-50° angle of the boot foot facilitates drilling the steel pipe anchor into the pre-drilled rock section. The anchoring screwing device, as an intermediate force transmission component, detachably connects the auger drilling rig and the steel pipe anchor via bolts. It transmits the large torque of the screwing operation and achieves rigid anchoring with the concrete foundation, completely transferring the tensile, compressive, and horizontal shear forces of the foundation to the steel pipe anchor. The entire process allows for mechanized construction, reducing manual excavation and concrete usage, and is suitable for the typical geological conditions of "soil above rock" for power transmission towers in mountainous areas. Attached Figure Description
[0018] Figure 1 This is a schematic diagram of the installation structure of the present invention; Figure 2 This is a structural schematic diagram of the steel pipe anchor of the present invention from a first-view perspective; Figure 3 yes Figure 1 A schematic diagram of the local structure at point A; Figure 4 This is a structural schematic diagram of the steel pipe anchor of the present invention from a second perspective; Figure 5 This is a cross-sectional structural schematic diagram of the anchoring and tightening device of the present invention; Figure 6 This is a top view of the anchoring device of the present invention.
[0019] The attached diagram is labeled as follows: 100, mounting base; 1, anchor bolt; 2, main concrete column; 3, concrete base; 4, anchoring device; 5, steel pipe anchor; 6, anchor plate; 7, pre-drilled hole; 8, sediment hole; 9, grouting pipe; 10, first bolt hole; 11, connecting sleeve; 12, base plate; 13, stiffening plate; 14, second bolt hole; 15, boot foot. Detailed Implementation
[0020] The present invention will now be described in more detail with reference to the embodiments.
[0021] Example 1 Please see Figures 1 to 6The grouting spiral anchor steel pipe composite pile foundation of this embodiment is applied in an area with an overburden layer thickness of 2.5m and an overburden layer thickness of approximately 4-6m, with moderately weathered rock underneath. It includes an installation pile cap 100, the bottom of which is buried inside the soil layer. Specifically, during construction, the pile cap pit is first excavated, and then concrete is poured into the pile cap pit to form the installation pile cap 100.
[0022] The mounting base 100 contains several evenly arranged anchoring devices 4, all of which are arranged at the same horizontal level.
[0023] Each anchoring device 4 is equipped with a corresponding steel pipe anchor 5. The bottom end of the steel pipe anchor 5 extends through the soil layer into the rock layer. Specifically, during construction, a pre-drilled hole 7 is first drilled using a spiral drilling machine, and then the steel pipe anchor 5 is inserted into the pre-drilled hole 7.
[0024] Anchor plate 6 is a spiral blade, and the outer diameter of anchor plate 6 is larger than the outer diameter of steel pipe anchor 5. The number of anchor plates 6 is 2-4.
[0025] In this embodiment, two anchor discs 6 are installed at intervals on the steel pipe anchor 5 on the rod body in the soil layer. Since the anchor disc 6 at the bottom will contact the soil first during the process of inserting the steel pipe anchor 5 into the pre-drilled hole 7, the steel pipe anchor 5 can be rotated by the auger drilling machine, and then the anchor disc 6 can be screwed into the soil.
[0026] The inner wall of the steel pipe anchor 5 is also fixedly connected to a grouting pipe 9 for injecting cement mortar. The grouting pipe 9 is welded and fixed to the inner wall of the steel pipe anchor 5, and the grouting pipe 9 extends downward synchronously with the steel pipe anchor 5. The outlet of the grouting pipe 9 is located at the bottom end of the steel pipe anchor 5.
[0027] In this embodiment, in order to ensure the rigidity of the grouting pipe 9, the grouting pipe 9 is made of steel, and the diameter of the grouting pipe 9 is 20mm-40mm. In this embodiment, 20mm is used.
[0028] Due to the complex working conditions on site, the existing equipment uses a one-way valve grouting method, which is likely to cause the one-way valve to fail, thus making this construction method impossible to implement. Therefore, this equipment simplifies the construction method by setting up a grouting pipe 9, which ensures a rigid connection while meeting the grouting requirements.
[0029] High-strength cement mortar was used as the grouting material, replacing fine aggregate concrete. The main reason for this was that fine aggregate concrete could easily cause blockage in the grouting pipe, making construction inconvenient. High-strength cement mortar was verified on-site to meet the load-bearing capacity requirements.
[0030] Compared to existing devices, this device does not have grouting holes on the side of the steel pipe anchor 5. According to on-site construction verification, the grouting holes on the side of the steel pipe anchor 5 are prone to blockage. When blockage occurs, the grouting pressure will increase instantly. Since the grouting pressure is a key parameter for determining whether grouting is completed, the extra grouting holes will cause misjudgment of the grouting termination condition.
[0031] After grouting through grouting pipe 9, the mortar wraps around the steel pipe anchor 5 and fills the rock fissures. The steel pipe anchor 5, anchor plate 6, cement mortar, and soil form a composite stress system, which greatly improves stability.
[0032] Furthermore, the anchoring device 4 includes a base plate 12, a connecting sleeve 11 fixed on the base plate 12, and eight stiffening plates 13 fixed between the base plate 12 and the connecting sleeve 11. Each stiffening plate 13 is evenly arranged circumferentially. Meanwhile, the head of the steel pipe anchor 5 is provided with three sets of first bolt holes 10, and the connecting sleeve 11 is provided with three sets of second bolt holes 14 corresponding to the first bolt holes 10. The first bolt holes 10 and the second bolt holes 14 are detachably connected by bolts.
[0033] The anchoring device 4 in this device is connected to the auger drilling rig to transmit torque during the construction phase, and is embedded in the concrete foundation 3 as a load-bearing anchor during the service phase.
[0034] In this embodiment, the inner diameter of the connecting sleeve 11 is 4-8mm larger than the outer diameter of the steel pipe anchor 5, which makes it easier to fit the steel pipe anchor 5 into the connecting sleeve 11 for locking installation. At the same time, each stiffening plate 13 is also provided with bolt connection holes, which makes it easier to connect the anchoring tightening device 4 to the output end of the auger drill. The auger drill drives the steel pipe anchor 5 to rotate through the anchoring tightening device 4.
[0035] As can be seen from the above description, the anchoring device 4 can withstand the impact torque and bending moment generated during the tightening of complex strata, is not easily damaged, and has high connection reliability and is easy to install.
[0036] Furthermore, the installation platform 100 includes a concrete platform 3 and a concrete main column 2 integrally set on the top of the concrete platform 3. The top of the concrete main column 2 extends out of the soil layer, and multiple anchor bolts 1 are embedded inside the concrete main column 2, with the top of the anchor bolts 1 extending out of the concrete main column 2.
[0037] As can be seen from the above description, in the load transfer path, the upper component can be connected to the mounting base 100 through the anchor bolts 1. The tensile force, compressive force and horizontal force transmitted from the upper component are first transferred to the concrete main column 2, then diffused to the concrete base 3 buried underground, and finally transferred to the lower steel pipe anchor 5 and the surrounding rock and soil.
[0038] The concrete foundation 3 serves to expand the load-bearing area and resist horizontal forces and overturning moments; the concrete main column 2 raises the top surface of the foundation above the ground, providing sufficient anchorage length for the anchor bolts 1 and exposing the connection nodes. The anchor bolts 1, as detachable connectors, realize the standardized connection between the upper components and the installation foundation 100. The anchor bolts 1, the concrete main column 2, and the concrete foundation 3 are cast as a rigid whole to ensure reliable load transfer from top to bottom.
[0039] Furthermore, the tail end of the steel pipe anchor 5 is provided with a 40°-50° boot foot 15. In this embodiment, please refer to [reference needed]. Figure 3 The boot foot 15 is at a 45° angle to ensure that the steel pipe anchor 5 can advance smoothly during the lowering process.
[0040] The bottom of the boot foot 15 is integrally equipped with a pointed tip.
[0041] Furthermore, a sedimentation hole 8 is provided at the bottom end of the steel pipe anchor 5. The depth of the sedimentation hole 8 is not less than 150mm. In this embodiment, the depth of the sedimentation hole 8 is 150mm.
[0042] As can be seen from the above description, during the construction process, when the steel pipe anchor 5 is hoisted into the pre-drilled hole 7 and screwed, the screwing action will inevitably disturb the soil and gravel on the hole wall, generating a certain amount of waste soil and sediment. Through the setting of sediment hole 8, the waste soil and sediment generated by screwing will fall into sediment hole 8, avoiding affecting the setting depth of steel pipe anchor 5.
[0043] In this embodiment, the specific load transfer path is as follows: upper tower → anchor bolt 1 → concrete main column 2 → concrete foundation 3 → anchoring device 4 → steel pipe anchor 5, anchor plate 6, grouting body → soil layer and rock layer.
[0044] A construction method for a grouting spiral anchor steel pipe composite pile foundation, comprising the following steps: Construction preparation: Based on the foundation layout requirements, such as the design drawings, complete the layout and marking of the hole positions, and rationally plan the working area of the construction machinery, including the equipment placement area and the equipment operation area.
[0045] Specifically, the marking of hole positions should not affect construction operations.
[0046] Meanwhile, during the construction preparation phase, it is necessary to formulate construction safety measures to ensure that the safe distance from various power lines, pipelines and other facilities during construction meets the requirements and should also comply with the requirements of relevant regulations and specifications.
[0047] The construction workers also need to connect the steel pipe anchor 5 to the grouting pipe 9.
[0048] Drilling and cleaning: Excavate the foundation pit to the design depth, and level the foundation pit according to the relevant requirements of the "Code for Design of Foundations of Overhead Transmission Lines". Then, drill pre-drilled holes 7 and sedimentation holes 8 at the bottom of the foundation pit. The depth of sedimentation hole 8 is 150mm, which is the distance between the bottom of the steel pipe anchor 5 and the bottom of sedimentation hole 8.
[0049] During the drilling and cleaning process, operators need to regularly observe the tilt angle of the drill rod. If tilting occurs, adjust the drill frame's tie rod to keep the drill rod vertical. After the pre-drilled hole 7 is drilled, the stone powder, loose soil, and loose rocks on the hole wall in the pre-drilled hole 7 need to be cleaned.
[0050] Composite pile placement: The steel pipe anchor 5 with the grouting pipe 9 inside is hoisted into the pre-drilled hole 7 by the auger drilling rig, and the auger drilling rig starts to rotate the power head when the anchor plate 6 contacts the soil, so that the steel pipe anchor 5 and the anchor plate 6 are screwed into the soil.
[0051] Grouting: Before grouting, ensure that there are no residues or debris inside the steel pipe anchor 5. First, flush the grouting pipe 9 with pressurized clean water, and then grout into the grouting pipe 9 to fill the pre-drilled hole 7 and the inside of the steel pipe anchor 5. After pouring, do not shake the composite rod body. When the steel pipe anchor 5 reaches the designed depth and is screwed into place and the rod end is closed, tamp the inside of the steel pipe anchor 5 with round steel.
[0052] Foundation casting: After the auger drill is disconnected, the foundation 100 is cast and installed in the foundation pit, and multiple anchor bolts 1 are pre-embedded in the foundation 100 for connecting the upper components.
[0053] Furthermore, during the drilling and cleaning process, the center point positioning error of the steel pipe anchor 5 shall not exceed 10mm, the tilt angle deviation shall not exceed 1°, and the azimuth angle deviation shall not exceed 2°.
[0054] Furthermore, during the drilling and cleaning process, the screwing speed of the steel pipe anchor 5 shall not exceed 10 revolutions / min, and the average displacement of the steel pipe anchor 5 under the pile per revolution shall not be less than 85% of the pitch of the anchor plate 6.
[0055] In this embodiment, the screwing speed of the steel pipe anchor 5 is 10 revolutions / min, and the steel pipe anchor 5 is screwed in one direction to avoid reverse screwing.
[0056] Among them, the reverse rotation of the steel pipe anchor 5 is prohibited during the tightening operation to prevent the anchor plate from disturbing the soil and causing a decrease in bearing capacity; the grouting operation should be continuous and should not be interrupted in the middle; the grouting is terminated when pure cement mortar returns from the orifice.
[0057] After the foundation pit is excavated, simple support needs to be provided for the slope of the foundation pit to prevent the foundation pit from collapsing in mountainous areas.
[0058] Furthermore, in the grouting process, M25-M30 cement mortar is used for grouting, and pressure grouting is adopted with a grouting pressure of 0.3MPa-0.8MPa; after grouting is completed, the pressure is maintained for 3min-8min.
[0059] In this embodiment, cement mortar is used for grouting, and the strength of the cement mortar is M28, with a grouting pressure of 0.3MPa.
[0060] In this embodiment, the drilling time is 4 hours, the screwing and grouting time is 2 hours, for a total of 6 hours, which greatly improves the construction efficiency.
[0061] The load-bearing capacity of this embodiment is greatly improved compared with the spiral anchor foundation. Field tests show that the ultimate tensile strength of this foundation type is about 1000kN.
[0062] Example 2 The grouting spiral anchor steel pipe composite pile foundation in this embodiment is applied to a soil layer with an overlying thickness of 2.5m and underlying moderately weathered rock. Other aspects are the same as in Embodiment 1, except that: The steel pipe anchor rod is equipped with three anchor plates; The boot heel should be at a 40° angle; The depth of sedimentation hole 8 is 180mm; The inner diameter of grouting pipe 9 is 25mm; Six stiffening plates are provided in the stiffening plate 13; M25 cement mortar was used for grouting, with an injection pressure of 0.4 MPa; The steel pipe anchor 5 is turned at a speed of 8 r / min.
[0063] In this embodiment, the ultimate tensile bearing capacity is approximately 850 kN.
[0064] Example 3 The grouting spiral anchor steel pipe composite pile foundation in this embodiment is applied to a soil layer with an overlying soil layer thickness of 4.0m and a weakly weathered rock underlying layer. Other aspects are the same as in Embodiment 1, except that: The steel pipe anchor rod is equipped with four anchor plates; The boot hem should be at a 50° angle; The depth of sedimentation hole 8 is 200mm; The inner diameter of grouting pipe 9 is 32mm; Grouting with M30 cement mortar at a pressure of 0.7 MPa; The steel pipe anchor 5 is turned at a speed of 6 r / min.
[0065] In this embodiment, the ultimate tensile bearing capacity is approximately 1100 kN.
[0066] Example 4 This embodiment is a comparative embodiment, using a common spiral anchor foundation (without rock embedding or grouting). Under the same geological conditions, the ultimate tensile strength of a 5m pile is approximately 300kN.
[0067] Example 5 This embodiment is a comparative embodiment, which uses traditional bored rock-embedded piles, 220kV tower foundation, 3m rock embedment, construction period of 8 days, and large amount of concrete consumption.
[0068] The comparison of the above five sets of embodiments shows that the bearing capacity and construction efficiency of this application are superior to the existing solutions (i.e., Embodiments 4 and 5) under different geological conditions.
[0069] In the description of this invention, it should be noted that the terms "inner", "outer", "upper", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limiting this invention.
[0070] In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the term "connection" should be interpreted broadly. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this invention according to the specific circumstances.
[0071] Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.
Claims
1. A grouting spiral anchor steel pipe composite pile foundation, characterized in that: The system includes an installation platform (100), the bottom of which is buried in the soil layer. Several evenly arranged anchoring devices (4) are installed inside the installation platform (100). Each anchoring device (4) is equipped with a corresponding steel pipe anchor (5). The bottom end of the steel pipe anchor (5) extends through the soil layer into the rock layer. Multiple anchor plates (6) are installed at intervals on the steel pipe anchor (5) located in the soil layer. A grouting pipe (9) for injecting cement mortar is also fixedly connected to the inner wall of the steel pipe anchor (5).
2. The grouting spiral anchor steel pipe composite pile foundation according to claim 1, characterized in that: The anchoring device (4) includes a base plate (12), a connecting sleeve (11) fixed on the base plate (12), and several stiffening plates (13) fixed between the base plate (12) and the connecting sleeve (11), and each of the stiffening plates (13) is evenly arranged in the circumferential direction; the inner diameter of the connecting sleeve (11) is 4mm-8mm larger than the outer diameter of the steel pipe anchor (5).
3. The grouting spiral anchor steel pipe composite pile foundation according to claim 2, characterized in that: The steel pipe anchor (5) has multiple sets of first bolt holes (10) at the rod head position, and the connecting sleeve (11) has multiple sets of second bolt holes (14) corresponding one-to-one with the first bolt holes (10). The first bolt holes (10) and the second bolt holes (14) are detachably connected by bolts.
4. The grouting spiral anchor steel pipe composite pile foundation according to claim 1, characterized in that: The mounting platform (100) includes a concrete platform (3) and a concrete main column (2) integrally set on the top of the concrete platform (3). The top of the concrete main column (2) extends out of the soil layer, and multiple anchor bolts (1) are embedded inside the concrete main column (2). The top of the anchor bolts (1) extends out of the concrete main column (2).
5. A grouting spiral anchor steel pipe composite pile foundation according to claim 1, characterized in that: The steel pipe anchor (5) has a 40°-50° boot foot (15) at the end of the rod, and the bottom of the boot foot (15) is integrally provided with a pointed tip; the bottom of the steel pipe anchor (5) is also provided with a sediment hole (8), and the depth of the sediment hole (8) is not less than 150mm.
6. The grouting spiral anchor steel pipe composite pile foundation according to claim 1, characterized in that: The anchor plate (6) is a spiral blade, and the outer diameter of the anchor plate (6) is larger than the outer diameter of the steel pipe anchor (5). The number of anchor plates (6) is 2-4.
7. A construction method for a grouting spiral anchor steel pipe composite pile foundation, characterized in that: Includes the following steps: Construction preparation: Based on the foundation layout requirements, complete the layout and marking of hole positions, and rationally plan the operating area of construction machinery; Drilling and cleaning: Excavate the foundation pit to the design depth and level the foundation pit; drill pre-drilled holes (7) and sedimentation holes (8) at the bottom of the foundation pit. Composite pile placement: The steel pipe anchor (5) with grouting pipe (9) inside is hoisted into the pre-drilled hole (7) by a spiral drilling rig, and the spiral drilling rig starts to rotate the power head when the anchor plate (6) contacts the soil, so that the steel pipe anchor (5) and the anchor plate (6) are screwed into the soil; Grouting: Before grouting, ensure that there are no residues or debris inside the steel pipe anchor (5), and then inject grout into the grouting pipe (9) to fill the pre-drilled hole (7) and the inside of the steel pipe anchor (5); after grouting, compact the mortar. Foundation casting: After the auger drill is disconnected, the foundation (100) is cast in the foundation pit and multiple anchor bolts (1) are pre-embedded in the foundation (100) for connecting the upper components.
8. The construction method of the grouting spiral anchor steel pipe composite pile foundation according to claim 7, characterized in that: In the grouting step, M25-M30 cement mortar is used for grouting, and pressure grouting is adopted with a grouting pressure of 0.3MPa-0.8MPa; after grouting is completed, the pressure is maintained for 3min-8min.
9. The construction method of the grouting spiral anchor steel pipe composite pile foundation according to claim 7, characterized in that: The drilling and cleaning steps also include cleaning the stone powder, loose soil and loose rocks in the pre-drilled hole (7) after the pre-drilled hole (7) is drilled; in the drilling and cleaning steps, the center point positioning error of the steel pipe anchor (5) shall not exceed 10mm, the tilt angle deviation shall not exceed 1°, and the azimuth angle deviation shall not exceed 2°.
10. The construction method of the grouting spiral anchor steel pipe composite pile foundation according to claim 7, characterized in that: During the drilling and cleaning process, the turning speed of the steel pipe anchor (5) shall not exceed 10 revolutions / min, and the average displacement of the steel pipe anchor (5) under the pile per revolution shall not be less than 85% of the pitch of the anchor plate (6).