Chemical anchor post high-rise curtain wall keel plate synchronous installation construction process
By employing a segmented synchronous installation process and real-time monitoring and adjustment, the problems of anchor bolt curing disturbance identification and keel deformation in high-rise curtain wall construction were solved, achieving efficient and safe curtain wall installation and improving construction quality and efficiency.
Patent Information
- Application Number
- CN202611571446.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-12
- Publication Date
- 2026-11-24
AI Technical Summary
In existing high-rise curtain wall construction, the post-installed chemical anchors have problems such as the anchor curing process being easily disturbed and difficult to identify, the deformation of the keel being difficult to correct in real time, and the construction cycle being lengthy.
The segmented synchronous installation process is adopted. By monitoring the anchor bolt curing process in real time and coordinating with the re-inspection mechanism, portable strain vibration acquisition tooling and microelectromechanical tilt angle sensing components are used to adjust the keel deformation in real time. Combined with segmented lightning protection continuity testing, the self-inspection and closed-loop acceptance of the concealed works are realized.
It improves the safety and durability of anchor bolt installation, shortens the construction cycle, reduces the risk of rework at heights, and enhances the installation accuracy, fireproof sealing, and lightning protection conductivity of the curtain wall.
Smart Images

Figure CN123153541A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of curtain wall construction technology, specifically to a construction process for the synchronous installation of high-rise curtain wall keel panels using post-installed chemical anchors. Background Technology
[0002] In high-rise curtain wall construction, post-installed chemical anchors are the mainstream connection method for installing the keel of high-rise and large-area curtain walls. Reliable anchoring between the anchors and the main structure is achieved through chemical curing, thereby completing the assembly of the curtain wall keel and exterior panels. Conventional curtain wall construction often employs a sequential construction process. After all post-installed anchors on the entire curtain wall have cured and passed inspection, the keel installation and curtain wall panel installation are carried out uniformly. This construction process is mature and widely used.
[0003] However, the existing technology has the following problems: When using the traditional sequential construction mode, the keel and panel installation can only be carried out after all anchor bolts have been cured and tested. This construction method is relatively safe, but the sequential arrangement of procedures results in a long overall construction cycle. At present, in order to improve construction efficiency, a segmented synchronous installation process is gradually being adopted, which can effectively shorten the construction period. However, this brings several challenges to construction quality control. First, the chemical anchor curing process is easily affected by on-site bumps and vibrations, resulting in invisible internal colloid damage. Conventional testing methods are difficult to identify subtle disturbances during the curing stage, which can easily leave anchoring safety hazards. Second, the keel is prone to dynamic deformation during panel loading, and the deformation deviation accumulates continuously, making it impossible to correct in real time. Moreover, after the curtain wall panels are closed, they will cover the concealed lightning protection nodes, making later defect rectification difficult and increasing the risk of rework at height. Summary of the Invention
[0004] The purpose of this invention is to provide a construction process for the synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels in order to solve the above-mentioned problems. It aims to overcome the shortcomings of existing post-installed anchor construction methods, such as difficulty in identifying potential problems caused by minor disturbances during anchor curing, difficulty in real-time correction of dynamic deformation of the keel, and lengthy construction period. Details are provided below.
[0005] To achieve the above objectives, the present invention provides the following technical solution: This invention provides a construction process for the synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels, comprising the following steps: Step S1: Construction preparation, including checking drawings, prefabricating curtain wall components in the factory, and setting up high-altitude work platforms; Step S2: Main structure verification and measurement layout, verify building benchmarks, divide the curtain wall into several independent construction sections, lay out the keel and post-installed chemical anchor connection node positioning control lines and collect the actual measured deviation of the main structure; Step S3: Installation and anchorage status verification of post-installed chemical anchors. Complete the construction of post-installed chemical anchors in this independent construction section. Collect physical status data of the anchorage location within the complete curing cycle of the chemical agent as the basis for anchorage status verification. Only after the anchorage status verification meets the standards can the keel construction work in this independent construction section be carried out. Step S4: Keel pre-assembly, calibrate the incoming keel components, and complete the pre-assembly of keel auxiliary connectors and temperature deformation compensation components on the ground; Step S5: Install the keel and curtain wall panels in sections simultaneously. Using an aerial work platform, after the initial adjustment of the keel installation in a single independent construction section is completed, the curtain wall panels in that section are then installed. Throughout the installation process, physical data on the deformation and posture of the keel are collected. If the data exceeds the preset threshold, the keel is adjusted immediately. Step S6: Concealed structure construction is carried out simultaneously in sections. After the installation of the keel and curtain wall panels in this independent construction section is completed, fire prevention, heat preservation and lightning protection bridging operations are carried out. Electrical parameters of the conductive path of the keel in the section are collected. Only when the parameters meet the indicators can the next independent construction section be entered. Step S7: Seal the gaps between the curtain wall panels and conduct a waterproof performance test; Step S8: Perform finished product protection on the completed curtain wall, verify the performance of the curtain wall, and then organize the final acceptance inspection.
[0006] Preferably, in step S1, the high-altitude work platform is a suspended platform, and life safety ropes are simultaneously deployed on the exterior wall facade. The curtain wall components include keel components, aluminum single-panel curtain wall panels, and insulated glass curtain wall panels. All curtain wall components are prefabricated in the factory, and only assembly operations are performed on the construction site.
[0007] As a preferred option, in step S2, when the measured deviation of the main structure exceeds the allowable range, the measured deviation is submitted to the design unit for component adaptation and adjustment, and the positioning control line deployment operation is stopped when the wind force reaches the set threshold.
[0008] As a preferred option, in step S3, a portable strain vibration acquisition tool that can be disassembled and reused is used to clamp the exposed bolt part of a representative post-installed chemical anchor connection node in an independent construction section, fully covering the curing cycle of the agent, and collecting physical state data of the anchoring part in terms of vibration and strain. If the curing cycle shows excessive vibration or strain signals, the anchoring in the independent construction section is re-inspected, and the anchoring status is deemed to have met the standards only after the re-inspection is qualified.
[0009] Preferably, in step S3, after the post-installed chemical anchor bolt connection node is installed, a routine sampling pull-out test is carried out. During the installation stage of the post-installed embedded parts in the post-installed chemical anchor bolt connection node, a pre-connection with the main building's lightning protection system is made in advance. The portable strain vibration acquisition tool is disassembled after verification in this independent construction section and reused for the next independent construction section.
[0010] Preferably, in step S4, the temperature deformation compensation component is a telescopic core sleeve, and isolation gaskets are installed at the contact points between different metal components to suppress electrochemical corrosion.
[0011] As a preferred option, in step S5, a microelectromechanical tilt sensor component that can be magnetically held and reused is used to be attached to the key measuring point of the keel. The physical data of the deformation posture of the keel are collected in real time throughout the entire process of panel installation. When the external wind force reaches the strong wind threshold, all installation work on the aerial work platform is stopped, and a large amount of material is prohibited from being piled up on the working surface of the aerial work platform.
[0012] Preferably, in step S5, after the construction of the keel and curtain wall panels of the independent construction section is completed, the microelectromechanical tilt sensing component is disassembled and reused in the next independent construction section, and the assembly of the window sill, parapet wall and expansion joint is completed simultaneously.
[0013] Preferably, in step S6, a segmented lightning protection continuity tester is used to clamp the upper and lower ends of the keel in the independent construction section to collect the continuity resistance of the keel's conductive path as the electrical parameter of the conductive path. The fireproof structure uses a supporting component to support the fireproof filling material, and the splicing gaps are sealed with fireproof sealing material.
[0014] As a preferred option, before the sealing operation in step S7, impurities in the gaps should be removed and the bonding surface should be kept dry. The waterproof performance test is carried out by water spraying test. After continuous spraying, check whether there is leakage on the indoor side. In step S8, the performance of the curtain wall is verified, including the overall installation accuracy and electrical performance of the curtain wall.
[0015] The beneficial effects are: 1. The construction process of synchronous installation of post-installed chemical anchors for high-rise curtain wall keel panels, through dynamic monitoring of the entire anchor curing process and the cooperation of a re-inspection mechanism, makes up for the limitations of traditional anchoring quality inspection methods. It can accurately identify minor disturbances and damages during the curing period, which helps to reduce the problems of hidden defects in anchors and improve the overall safety and durability of post-installed anchoring nodes in high-rise curtain walls.
[0016] 2. The post-installed chemical anchors for high-rise curtain wall keel panels synchronous installation construction process, through synchronous construction combined with real-time attitude monitoring, breaks the time constraints of traditional sequential curtain wall construction. It can correct deviations in real time during the panel loading and forming process, reduce the accumulation and solidification of deformation errors, and make the curtain wall installation and forming accuracy higher. The overall construction period is significantly shortened. At the same time, the application of reusable sensing equipment also effectively controls construction costs.
[0017] 3. The construction process of simultaneous installation of high-rise curtain wall keel panels with post-installed chemical anchors utilizes the construction window period of each section to complete the self-inspection and closed-loop acceptance of concealed works, effectively improving the inconvenience of maintenance of concealed nodes after the curtain wall is sealed, reducing the probability of high-altitude demolition and rework, and effectively ensuring the fireproof airtightness and lightning protection conductivity stability of the curtain wall, making the quality of concealed works controllable and traceable throughout the process. Attached Figure Description
[0018] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0019] Figure 1 This is a schematic diagram of the process flow of the present invention. Detailed Implementation
[0020] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions of this invention will be described in detail below. Obviously, the described embodiments are merely some embodiments of this invention, and not all embodiments. Based on the embodiments of this invention, all other implementation methods obtained by those skilled in the art without creative effort are within the scope of protection of this invention.
[0021] Please see Figure 1 A construction process for the synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels, comprising the following steps: Step S1: Construction preparation, complete the drawing verification, prefabricate the curtain wall components in the factory and set up the high-altitude work platform. The high-altitude work platform is a suspended platform equipment. Life safety ropes are set up on the exterior facade at the same time. The curtain wall components include keel components, aluminum single-panel curtain wall panels and insulated glass curtain wall panels. All curtain wall components are prefabricated in the factory. Only assembly work is performed on the construction site.
[0022] Specifically, this step involves pre-compiling, processing, and pre-assembling curtain wall components in the factory. Only the finished components are transported to the construction site for assembly. The processing environment in the workshop is relatively stable and unaffected by factors such as construction site dust, temperature fluctuations, and changes in on-site measurement benchmarks. This effectively controls the processing accuracy of components, reduces dimensional deviations caused by manual cutting on-site, and avoids the risk of high-altitude fires caused by on-site hot work. The consistency of component processing is better, which can significantly reduce the amount of on-site repair work and shorten the on-site construction time. As a mature high-altitude work support equipment, the suspended platform has a stable structure and controllable lifting, making it suitable for high-rise exterior wall construction scenarios. With the life safety ropes deployed on the exterior wall, it can provide a stable working platform for subsequent construction work in various independent sections, reducing the risk of falls from heights.
[0023] Step S2: Main structure verification and measurement layout. Verify the building benchmark, divide the curtain wall into several independent construction sections, lay out the positioning control lines for the keel and post-installed chemical anchors connection nodes, and collect the measured deviations of the main structure. When the measured deviations of the main structure exceed the allowable range, submit the measured deviations to the design unit for component adaptation and adjustment. Stop the positioning control line laying operation when the wind force reaches the set threshold.
[0024] Specifically, before construction, the axis and elevation benchmark of the main civil engineering structure are first checked. Based on the building floor height and wind load zoning, independent construction sections are divided. The large-area curtain wall is divided into multiple construction units with clear boundaries and independent loads, which facilitates segmented quality control and avoids quality defects at one node affecting the entire curtain wall. The layout work is sensitive to the external environment. Strong winds can pull the control line and cause the benchmark point to shift. Therefore, the layout work is stopped when the wind force exceeds the standard to prevent the marked points from becoming distorted. This method can ensure that the positioning benchmark is stable and reliable, the positioning accuracy of components is controllable, and the segment boundaries are clear, which facilitates subsequent segmented inspection and segmented release construction.
[0025] Step S3: Installation and anchorage status verification of post-installed chemical anchors. After completing the construction of post-installed chemical anchors in this independent construction section, collect physical status data of the anchorage location within the complete curing period of the chemical agent. This data will serve as the basis for anchorage status verification. Only after the anchorage status verification meets the standards can the keel construction work in this independent construction section be carried out.
[0026] Furthermore, a portable strain and vibration acquisition tool that can be disassembled and reused is used to clamp the exposed bolt part of the representative post-installed chemical anchor connection node in the independent construction section, fully covering the chemical curing cycle, and collecting physical state data of the anchoring part in terms of vibration and strain. If the curing cycle shows excessive vibration or strain signals, the anchoring of the independent construction section will be re-inspected. Only after the re-inspection is qualified can the anchoring status be determined to meet the standards.
[0027] In addition, after the post-installed chemical anchor bolt connection nodes are installed, routine sampling pull-out tests are carried out. During the installation stage of the post-installed embedded parts in the post-installed chemical anchor bolt connection nodes, pre-connection with the main building's lightning protection system is made in advance. The portable strain vibration acquisition tool is disassembled after verification in this independent construction section and reused for the next independent construction section.
[0028] Specifically, during the curing stage of the chemical anchor colloid, its internal mechanical strength has not yet been formed. Impacts and disturbances during construction can create microcracks inside the colloid that are invisible to the naked eye. This portable strain and vibration acquisition tool is a non-destructive portable testing device. It is equipped with a clamp-type fixing structure, eliminating the need for drilling or modification on the anchor or wall. It can be directly clamped and fixed to the exposed thread of the anchor. The device has built-in strain sensing chips and vibration acquisition chips, which can continuously collect the minute vibration and micro-deformation data of the thread, and capture in real time the subtle external force disturbances such as surrounding construction vibrations and human impacts. Conventional sampling and tensile testing can be performed on the thread. Pull-out testing can only detect anchors that have completely failed, and it is difficult to identify hidden damage caused by external disturbances during the curing stage. This step combines monitoring during the curing stage with sampling pull-out testing as required by the specifications. Only when both tests pass can the anchoring status be deemed to have met the standards. This avoids the safety hazards of anchors with hidden defects bearing curtain wall loads from the source. The tooling is installed using a clamping method, which will not damage the anchor structure itself. It can be disassembled after testing and reused in multiple sections, reducing the equipment investment for multi-section construction. The post-installed embedded parts are connected to the building's lightning protection system in advance, which can also reduce the difficulty of subsequent lightning protection bridging construction.
[0029] This process, through dynamic monitoring of the entire anchor curing process and a re-inspection mechanism, overcomes the limitations of traditional anchoring quality testing methods. It can accurately identify minor disturbances and damages during the curing period, helping to reduce the problems of hidden anchor defects and improve the overall safety and durability of post-anchoring nodes in high-rise curtain walls.
[0030] Step S4: Keel pre-assembly, calibrate the incoming keel components, and complete the pre-assembly of keel auxiliary connectors and temperature deformation compensation components on the ground. The temperature deformation compensation components are telescopic core sleeves, and isolation gaskets are installed at the contact points of different metal components to inhibit electrochemical corrosion.
[0031] Specifically, the keel assembly is completed on the ground, with ample working space, eliminating issues such as swaying and operational limitations associated with working at heights. This facilitates operation and dimensional verification by construction personnel. The telescopic core sleeve can adapt to the thermal expansion and contraction displacement of the keel caused by changes in ambient temperature, releasing internal stress generated by temperature variations. Isolation gaskets are placed between different metal components to prevent direct contact between dissimilar metals, reduce metal ion migration, and avoid electrochemical corrosion of components over long-term use. This method can improve the dimensional accuracy of keel assembly, enhance the flatness of curtain wall panel splicing, and improve the long-term corrosion resistance of components, preventing the keel from bending and deforming due to temperature stress.
[0032] Step S5: Install the keel and curtain wall panels in sections simultaneously. Using an aerial work platform, after the initial adjustment of the keel installation in a single independent construction section is completed, the curtain wall panels in that section are then installed. Throughout the installation process, physical data on the deformation and posture of the keel are collected. If the data exceeds the preset threshold, the keel is adjusted immediately.
[0033] Furthermore, a magnetically clampable and reusable microelectromechanical tilt sensor component is used to adhere to the key measuring points of the keel. The deformation and posture physical data of the keel are collected in real time throughout the entire process of panel installation. When the external wind force reaches the strong wind threshold, all installation work on the aerial work platform is stopped, and a large amount of material is prohibited from being piled up on the working surface of the aerial work platform.
[0034] In addition, after the construction of the keel and curtain wall panels in the independent construction section is completed, the microelectromechanical tilt sensor components are disassembled and reused in the next independent construction section. At the same time, the assembly of the window sills, parapet walls and expansion joints is completed.
[0035] Specifically, traditional construction methods require the entire keel to be installed before the curtain wall panels are uniformly installed, resulting in a long overall construction period. This process, however, allows for panel installation immediately after the adjustment of a single keel section. During panel loading, the keel's tilt angle and deformation are continuously monitored. This microelectromechanical tilt sensor integrates a MEMS (microelectromechanical system) attitude sensing module, which adheres to the keel profile surface via a permanent magnet base, eliminating the need for drilling and bonding. It can collect real-time attitude data such as bending deformation and tilt angle changes of the keel. Once the deformation exceeds a threshold, the keel support structure can be adjusted promptly. This surpasses the traditional process. After a one-time loading, deformation continues to accumulate. Once the panels are fixed, it is difficult to adjust the keel. The magnetic sensor component relies on magnetic force to adhere to the surface of the keel profile, eliminating the need for drilling or bonding and preventing damage to the keel profile. Strong winds can bring additional instantaneous loads to the keel, so hanging panels should be stopped during strong winds, and material stacking on the work surface should be restricted to avoid accumulating additional loads. After the sensor component has completed its detection, it can be disassembled and reused, simultaneously completing various finishing nodes, reducing subsequent piecemeal repair work, shortening the overall construction period, achieving dynamic control of the loading process, and promptly eliminating excessive deformation.
[0036] This segmented synchronous construction mode, combined with real-time attitude monitoring, breaks the time constraints of traditional sequential curtain wall construction. It can correct deviations in real time during the panel loading and forming process, reduce the accumulation and solidification of deformation errors, and make the curtain wall installation and forming accuracy higher. The overall construction period is significantly shortened, and the application of reusable sensing equipment also effectively controls construction costs.
[0037] Step S6: Concealed construction is carried out simultaneously in sections. After the installation of the keel and curtain wall panels in this independent construction section is completed, fire prevention, heat preservation and lightning protection bridging operations are carried out. Electrical parameters of the conductive path of the keel in the section are collected. Only when the parameters meet the indicators can the next independent construction section be started.
[0038] Furthermore, a segmented lightning protection continuity tester is used to clamp the upper and lower ends of the keel in the independent construction section to collect the continuity resistance of the keel's conductive path as the electrical parameter of the conductive path. The fireproof structure uses supporting components to support the fireproof filling material, and the splicing gaps are sealed with fireproof sealing material.
[0039] Specifically, after all the curtain wall panels are enclosed, the keel joints will be obstructed, making it difficult to access the lightning protection bridging locations. This segmented lightning protection continuity tester is a portable electrical testing device with clamping electrodes at both ends. After clamping the conductive parts of the upper and lower keel, the continuity resistance can be directly measured to determine whether the lightning protection path is continuous and reliable. This solution utilizes the window period when a single section of panels has just been installed and the joints are not yet fully enclosed to directly test the lightning protection continuity resistance within the section, verifying the continuity of the lightning protection path. The fireproof filling material relies on the supporting components to support it, preventing the material from falling off due to its own weight. The fireproof sealing material seals the gaps, preventing smoke from flowing between the joint gaps. If the lightning protection is tested after the entire curtain wall is completed, once a loose connection defect is found, the already installed panels need to be removed for high-altitude rework, which is costly and carries high safety risks. This solution can rectify lightning protection defects on-site, significantly reducing subsequent high-altitude dismantling and modification work, ensuring the fireproof and airtight performance of the curtain wall joints. Only after the section test is qualified can the next section be constructed, achieving quality release section by section.
[0040] This invention utilizes the construction window period of a section to complete the self-inspection and closed-loop acceptance of concealed works, effectively improving the inconvenience of inspection and maintenance of concealed nodes after the curtain wall is sealed, reducing the probability of high-altitude demolition and rework, and effectively ensuring the fireproof airtightness and lightning protection conductivity stability of the curtain wall, making the quality of concealed works controllable and traceable throughout the entire process.
[0041] Step S7: Seal the gaps between the curtain wall panels and conduct a waterproof performance test. Before sealing, remove impurities from the gaps and ensure that the bonding surfaces are dry. The waterproof performance test is conducted by a water spray test. After continuous spraying, check whether there is any leakage on the indoor side.
[0042] Specifically, the bonding strength of sealant largely depends on the cleanliness and dryness of the substrate surface. Cleaning dust and debris from the gaps and keeping the bonding surface dry ensures reliable adhesion between the sealant and the profile. Water spray tests simulate natural rainwater erosion conditions and can directly test the sealing and waterproofing capabilities of the gaps. If impurities or moisture remain in the gaps, the sealant is prone to detachment later. If water leakage is discovered after the curtain wall is put into use, it will be difficult to locate the leak. Conducting water spray tests in advance can detect leakage defects in advance, improve the durability of the sealing structure, and avoid indoor water leakage problems later.
[0043] Step S8: Perform finished product protection on the completed curtain wall, verify the performance of the curtain wall, and then organize the final acceptance inspection. The verification of the curtain wall performance includes verifying the overall installation accuracy and electrical performance of the curtain wall.
[0044] Specifically, after the curtain wall is completed, there are many overlapping operations on site, such as civil engineering and electromechanical work, which can easily cause bumps and scratches to the curtain wall panels. Setting up finished product protection measures for the completed curtain wall can isolate mechanical damage caused by overlapping operations. During the acceptance phase, the geometric installation accuracy and lightning protection electrical conductivity are checked simultaneously. The quality of the curtain wall is comprehensively verified from two dimensions: structural appearance and lightning protection safety. This avoids the acceptance focusing only on appearance and ignoring electrical safety-related indicators, protects the integrity of the curtain wall's appearance, fully verifies the overall quality of the curtain wall, and ensures the structural and lightning protection safety of the curtain wall during its use.
[0045] To further illustrate the implementation effect of the construction method provided by the present invention, specific embodiments are described below.
[0046] The following examples use the construction of the curtain wall of a commercial complex's podium as an engineering example. The podium is 24m high and uses a post-installed chemical anchor combined curtain wall. The curtain wall panels are a combination of glass and aluminum single panels. The east facade is constructed using the process of this invention, and is divided into three sections for construction along the vertical direction. These examples correspond to three sets of different construction conditions. The engineering conditions of the south facade are basically the same as those of the east facade, and construction is carried out simultaneously. The traditional process is used as a comparative example. The monitoring equipment and monitoring thresholds used in the construction of each section of the east facade remain unchanged. Specifically, the strain threshold of the portable strain vibration acquisition tool is 80με, the vibration alarm threshold is 0.12g, the tilt threshold of the microelectromechanical tilt angle sensor component is 0.25°, and the qualified threshold of the lightning protection conduction resistance of the segmented lightning protection conduction tester is ≤0.5Ω.
[0047] Example 1
[0048] This embodiment covers the 0-8m section of the east facade. This section has a low ground clearance, minimal wind load, and minimal disturbance from surrounding construction machinery. The construction employed the segmented continuous construction process of this invention, equipped with portable strain vibration acquisition equipment, MEMS tilt sensing components, and segmented lightning protection continuity testing instruments. No excessive disturbance signals were captured during anchor bolt curing monitoring. The average deviation of the keel tilt angle during the panel installation stage was 0.14°. After the section construction was completed, lightning protection continuity testing was immediately carried out. The average daily construction area of this section was approximately 28㎡.
[0049] Example 2
[0050] This example describes the 8-16m section of the east facade. This section has a moderate ground clearance, and natural wind and cross-operations on site cause slight disturbances. Using the exact same process and monitoring parameters, one slight disturbance was detected during the anchor bolt curing stage, and a re-inspection was completed. The average deviation of the keel inclination angle was 0.17°. Lightning protection conductivity testing was carried out immediately after the section was completed. The average daily construction area of this section is approximately 25㎡.
[0051] Example 3
[0052] This example covers the 16-24m section of the east facade, which is the highest area of the facade and experiences relatively greater wind load. The suspended platform operation resulted in slight swaying. Using the same process and monitoring parameters, the anchor bolt curing monitoring detected two construction disturbance signals, which were then re-inspected. The average deviation of the keel tilt angle was 0.20°. Lightning protection conductivity testing was conducted immediately after the section was completed. The average daily construction area of this section is approximately 22㎡.
[0053] Comparative Example This comparative example shows the construction section of the 0-24m integral curtain wall on the south facade of the podium of the same commercial complex. The curtain wall height, panel, anchor bolt specifications, construction teams, and material conditions are basically the same as those on the east facade. Construction was carried out simultaneously, without the use of strain vibration acquisition equipment, MEMS tilt sensing components, or segmented lightning protection continuity testers. Traditional procedures were adopted, specifically: the entire facade keel was installed at once and then uniformly hung with panels; chemical anchor bolts were only statically cured, and after the curing period, samples were uniformly pulled out; after all the curtain wall panels were sealed, a unified concealed lightning protection acceptance was carried out.
[0054] In the comparative example, the hidden disturbance damage during the anchor bolt curing stage could not be identified during the construction phase; the deformation of the keel continued to accumulate with the loading of the slab, the average deviation of the keel inclination angle was 0.43°, and the average daily construction area of the south facade was about 17㎡.
[0055] Comparative analysis reveals that in Examples 1, 2, and 3, employing the segmented continuous construction method of this invention and its accompanying monitoring equipment, as the height of the construction section above the ground increases, wind load and disturbances from high-altitude operations gradually increase, resulting in a slight increase in the keel inclination angle deviation and a slight decrease in the average daily construction area. The keel inclination angle deviation in all three sections is controlled within 0.20°, significantly better than the 0.43° deviation in the comparative example. Simultaneously, it can identify construction disturbances during the anchor bolt curing stage, facilitating timely re-inspection and handling. Relying on segmented continuous overlapping operations, the average daily construction area of each construction section on the east facade is higher than that of the traditional overall construction method on the south facade, improving both keel installation accuracy and construction efficiency.
[0056] The above description is merely a specific embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the technical scope disclosed in the present invention should be included within the scope of protection of the present invention. Therefore, the scope of protection of the present invention should be determined by the scope of the claims.
Claims
1. A construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels, characterized in that, Includes the following steps: Step S1: Complete the drawing verification, prefabricate the curtain wall components in the factory, and set up the high-altitude work platform; Step S2: Main structure verification and measurement layout, verify building benchmarks, divide the curtain wall into several independent construction sections, lay out the keel and post-installed chemical anchor connection node positioning control lines and collect the actual measured deviation of the main structure; Step S3: Installation and anchorage status verification of post-installed chemical anchors. Complete the construction of post-installed chemical anchors in this independent construction section. Collect physical status data of the anchorage location within the complete curing cycle of the chemical agent as the basis for anchorage status verification. Only after the anchorage status verification meets the standards can the keel construction work in this independent construction section be carried out. Step S4: Keel pre-assembly, calibrate the incoming keel components, and complete the pre-assembly of keel auxiliary connectors and temperature deformation compensation components on the ground; Step S5: Install the keel and curtain wall panels in sections simultaneously. Using an aerial work platform, after the initial adjustment of the keel installation in a single independent construction section is completed, the curtain wall panels in that section are then installed. Throughout the installation process, physical data on the deformation and posture of the keel are collected. If the data exceeds the preset threshold, the keel is adjusted immediately. Step S6: Concealed structure construction is carried out simultaneously in sections. After the installation of the keel and curtain wall panels in this independent construction section is completed, fire prevention, heat preservation and lightning protection bridging operations are carried out. Electrical parameters of the conductive path of the keel in the section are collected. Only when the parameters meet the indicators can the next independent construction section be entered. Step S7: Seal the gaps between the curtain wall panels and conduct a waterproof performance test; Step S8: Perform finished product protection on the completed curtain wall, verify the performance of the curtain wall, and then organize the final acceptance inspection.
2. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, In step S1, the high-altitude work platform is a suspended platform equipment, and life safety ropes are simultaneously deployed on the exterior wall facade. The curtain wall components include keel components, aluminum single-panel curtain wall panels, and insulated glass curtain wall panels. All curtain wall components are prefabricated in the factory, and only assembly operations are performed on the construction site.
3. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, In step S2, when the measured deviation of the main structure exceeds the allowable range, the measured deviation is submitted to the design unit for component adaptation and adjustment. When the wind force reaches the set threshold, the positioning control line deployment operation is stopped.
4. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, In step S3, a portable strain and vibration acquisition tool that can be disassembled and reused is clamped at the exposed bolt part of a representative post-installed chemical anchor connection node in an independent construction section to fully cover the curing cycle of the agent. Vibration and strain data of the physical state of the anchoring part are collected. If vibration or strain signals exceed the limit during the curing cycle, the anchoring of the independent construction section is re-inspected. Only after the re-inspection is qualified can the anchoring status be determined to meet the standards.
5. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 4, characterized in that, In step S3, after the post-installed chemical anchor bolt connection node is installed, a routine sampling pull-out test is carried out. During the installation stage of the post-installed embedded parts in the post-installed chemical anchor bolt connection node, the pre-connection with the main building's lightning protection system is prepared in advance. The portable strain vibration acquisition tool is disassembled after verification in this independent construction section and reused for the next independent construction section.
6. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, In step S4, the temperature deformation compensation component is a telescopic core sleeve, and isolation gaskets are installed at the contact points between different metal components to suppress electrochemical corrosion.
7. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, In step S5, a magnetically clampable and reusable microelectromechanical tilt sensor component is used to adhere to the key measuring point of the keel. The deformation and posture physical data of the keel are collected in real time throughout the entire process of panel installation. When the external wind force reaches the strong wind threshold, all installation work on the aerial work platform is stopped, and a large amount of material is prohibited from being piled up on the working surface of the aerial work platform.
8. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 7, characterized in that, In step S5, after the construction of the keel and curtain wall panels in the independent construction section is completed, the microelectromechanical tilt sensor component is disassembled and reused in the next independent construction section. At the same time, the assembly of the window sill, parapet wall and expansion joint is completed.
9. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, In step S6, a segmented lightning protection continuity tester is used to clamp the upper and lower ends of the keel in the independent construction section to collect the continuity resistance of the keel's conductive path as the electrical parameter of the conductive path. The fireproof structure uses supporting components to support the fireproof filling material, and the splicing gaps are sealed with fireproof sealing material.
10. The construction process for synchronous installation of post-installed chemical anchors on high-rise curtain wall keel panels according to claim 1, characterized in that, Before sealing in step S7, remove impurities from the gaps and ensure that the bonding surface is dry. Waterproof performance is tested by water spraying. After continuous spraying, check whether there is any leakage on the indoor side. In step S8, the performance of the curtain wall is verified, including the overall installation accuracy and electrical performance of the curtain wall.