Method for installing irregular aluminum plate stack ceiling

By using an irregular aluminum panel tiered ceiling installation method, and employing precision measurement and a unitized frame structure, the problems of low efficiency, poor safety, and difficulty in ensuring quality in the construction of irregular aluminum panel ceilings in high spaces have been solved, achieving high-precision and high-efficiency installation results.

CN123153544APending Publication Date: 2026-11-24SHANGHAI CHINA CONSTR EIGHTH ENG DIVISION DECORA
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202610206444.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-02-12
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Traditional ceiling construction suffers from low efficiency, poor safety, and difficulty in ensuring construction quality in high spaces and when installing irregular aluminum panels. In particular, full-span scaffolding cannot be implemented in scenarios where it overlaps with curtain wall construction, and the installation precision control of irregular aluminum panels is difficult.

Method used

The irregular aluminum panel tiered ceiling installation method includes steps such as data scanning measurement and marking, component factory processing, clamp installation, main keel and clamp connection, transfer layer structure construction, aluminum panel installation keel welding and reverse installation. Precision measuring instruments are used to obtain three-dimensional spatial coordinates, and the material cutting list is generated in reverse through Rhino software to ensure processing accuracy. A unit frame structure and electric hoist hoisting are used for hoisting.

Benefits of technology

It improves installation accuracy and construction efficiency, reduces construction period, enhances safety, ensures construction quality, and is suitable for the installation of complex-shaped curtain walls.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123153544A_ABST
    Figure CN123153544A_ABST
Patent Text Reader

Abstract

The present application provides a kind of irregular aluminum plate stack level suspended ceiling installation method, it is characterized in that, including the following steps: step one, data scanning measurement dotting and staking out;Step two, complete the factory processing of each component;Step three, arrange hoop point position, install hoop;Step four, connect main joist with hoop, one end is welded, the other end is bolted;Step five, construction conversion layer structure between main joist and aluminum plate installation joist;Step six, aluminum plate installation joist is welded below conversion layer structure;Step seven, aluminum plate is connected and fixed with aluminum plate installation joist using reverse installation mode.The present application improves the installation precision and has good appearance effect, and the method is suitable for the installation of complex modeling curtain wall.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building decoration construction technology, and in particular to a method for installing irregular aluminum plate tiered ceilings. Background Technology

[0002] Currently, the construction of suspended ceilings in high-ceilinged spaces such as stadiums often faces challenges such as high ceiling height, multiple overlapping operations, and significant installation difficulties. Traditional suspended ceiling construction often employs full-span scaffolding support, but this is impractical for scenarios involving overlapping work with curtain walls. Furthermore, controlling the installation precision of irregular aluminum panels is difficult. Traditional construction methods suffer from low efficiency, poor safety, and difficulty in guaranteeing construction quality, making it difficult to meet the construction requirements and quality standards for suspended ceilings in high-ceilinged spaces. Summary of the Invention

[0003] In order to solve the above problems, the present invention aims to provide an installation method and structure for irregular aluminum plate tiered ceilings suitable for high spaces such as stadiums.

[0004] To achieve the above objectives, the present invention adopts the following technical solution:

[0005] This invention provides a method for installing an irregular aluminum panel tiered ceiling, characterized by comprising the following steps:

[0006] Step 1: Data scanning, measurement, point marking, and line setting out;

[0007] Step two: Complete the factory processing of each component;

[0008] Step 3: Arrange the clamp locations and install the clamps;

[0009] Step 4: Connect the main keel to the clamps to complete the installation of the main keel;

[0010] Step 5: Construct a transition layer structure between the main keel and the aluminum plate installation keel;

[0011] Step 6: Weld the aluminum plate mounting frame to the bottom of the transition layer structure;

[0012] Step 7: Connect and fix the aluminum plate to the aluminum plate mounting keel using a reverse installation method.

[0013] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following features: the clamp is installed on the cylindrical steel, and the clamp is composed of a first clamp part and a second clamp part connected by bolts. Both the first clamp part and the second clamp part include a clamp body, the clamp body has an arc-shaped part and end plate parts connected to both ends of the arc-shaped part, the end plate parts are provided with bolt holes, the outer side of the arc-shaped part of the first clamp part is fixed with a welding structure for welding connection with the main keel, and the outer side of the arc-shaped part of the second clamp part is fixed with a core structure for bolt connection with the main keel. The welding structure and the core structure are opposite to each other and located in the same diameter direction of the clamp.

[0014] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following features: wherein the welded structure has a steel plate welding surface parallel to the end plate portion, and the angle formed by the main keel and the steel plate welding surface is not limited; the insert structure has a steel insert perpendicular to the end plate portion, the steel insert is provided with an elongated hole, the corresponding end of the main keel is provided with a round hole, the main keel and the steel insert are coaxially arranged, and the steel insert is inserted into the main keel and connected by bolts.

[0015] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following feature: a nylon gasket is provided between the steel insert and the main keel.

[0016] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following feature: a rubber gasket is provided between the clamp and the cylindrical steel.

[0017] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following features: wherein, the transition layer structure is used to adjust the levelness and spacing of the aluminum plate mounting keel, including the transition keel and the lower hanging keel, the transition keel is fixed to the side of the main keel, the lower hanging keel is vertically set and is bolted to the transition keel by a square clamp, and the aluminum plate mounting keel and the lower hanging keel are welded together.

[0018] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following feature: wherein the aluminum plate installation keel is a unit frame structure, which is composed of several square steel pipes welded together.

[0019] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following feature: the aluminum plate installation keel is hoisted as a whole during the installation process.

[0020] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following features: when the aluminum plate mounting keel is hoisted by an electric hoist, the aluminum plate mounting keel and the electric hoist are connected by a safety rope, and the aluminum plate mounting keel and the construction personnel are connected by a safety rope.

[0021] Furthermore, the irregular aluminum plate tiered ceiling installation method provided by the present invention may also have the following features: wherein the aluminum plate is provided with a hook edge, the cross section of the hook edge is C-shaped, the hook edge is fixed to an L-shaped corner bracket connector by bolts, and the other end of the L-shaped corner bracket connector is fixed to the aluminum plate mounting keel by bolts.

[0022] The present invention has the following beneficial effects:

[0023] In the irregular aluminum panel tiered ceiling installation method of the present invention, the main keel is welded to one end and bolted to the other end of the clamp, thereby increasing the horizontality of the main keel; a transition layer structure is set between the main keel and the aluminum panel installation keel to enhance the installation accuracy of the aluminum panel installation keel and adjust the spacing of the keel in the circular ceiling of large spaces such as stadiums; the aluminum panel installation keel adopts a unitized steel frame structure, which, in cooperation with electric hoists and construction workers, can quickly complete the construction of the aluminum panel steel frame and reduce the construction period; the aluminum panel adopts a reverse installation technology, which achieves the reverse installation condition by using special fasteners to achieve perpendicularity with the steel frame and the aluminum panel, thereby reducing the amount of scaffolding erection work.

[0024] In the irregular aluminum plate tiered ceiling installation method of the present invention, point cloud data of the three-dimensional spatial coordinates of the ceiling-related structure are obtained by precision measuring instruments, imported into Rhino software, and the irregular aluminum single-panel cutting list is generated by reverse engineering using the Rhino model for standardized processing and manufacturing, ensuring processing accuracy, and avoiding problems such as poor installation quality and rework caused by errors in the production of the panels.

[0025] The irregular aluminum plate tiered ceiling installation method of the present invention is convenient to install. It only requires the installation of aluminum plate keel and irregular aluminum single panel according to the three-dimensional coordinate positioning of the total station. After verification by the total station, the installation accuracy is improved and the appearance effect is good. This method is suitable for the installation of complex shaped curtain walls. Attached Figure Description

[0026] Figure 1 This refers to the modeling and drawing of a detailed aluminum plate diagram in this embodiment of the invention;

[0027] Figure 2 This is a plan view of the clamping point layout in an embodiment of the present invention;

[0028] Figure 3 This is a cross-sectional view of the stadium in an embodiment of the present invention;

[0029] Figure 4This is a cross-sectional view of the roof of the stadium in an embodiment of the present invention, namely... Figure 3 Enlarged view of point A in the middle;

[0030] Figure 5 yes Figure 4 Enlarged view of point B in the middle;

[0031] Figure 6 This is a schematic diagram of the clamp structure in an embodiment of the present invention;

[0032] Figure 7 This is a schematic diagram of the connection between the clamp and the main keel in an embodiment of the present invention;

[0033] Figure 8 This is a schematic diagram of the conversion layer structure in an embodiment of the present invention;

[0034] Figure 9 This is a schematic diagram of the aluminum plate mounting keel of the unit frame structure in an embodiment of the present invention;

[0035] Figure 10 This is a schematic diagram of the installation of the electric hoist in an embodiment of the present invention;

[0036] Figure 11 This is a schematic diagram of the installation keel for the aluminum plate hoisted by the electric hoist in an embodiment of the present invention;

[0037] Figure 12 This is a schematic diagram of the installation of the keel by manually hoisting the aluminum plate in an embodiment of the present invention;

[0038] Figure 13 This is a schematic diagram of the reverse installation of the aluminum plate in an embodiment of the present invention. Detailed Implementation

[0039] To enable those skilled in the art to better understand the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings.

[0040] It should be noted that in the description of this invention, the terms "upper," "lower," "left," "right," "front," "rear," "top," "bottom," "inner," "outer," "middle," "vertical," "horizontal," "lateral," and "longitudinal," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. Furthermore, some of the above terms may be used to indicate other meanings besides orientation or positional relationship; for example, the term "upper" may also be used in some cases to indicate a certain dependency or connection relationship. Those skilled in the art can understand the specific meaning of these terms in this invention according to the specific circumstances.

[0041] Furthermore, in the description of this invention, the terms "installation," "setting," and "connection," etc., should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be a connection within two components. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.

[0042] <Example>

[0043] This embodiment describes the construction of a tiered aluminum panel ceiling system for a stadium. The method employed is an irregular tiered aluminum panel ceiling installation, and includes the following steps:

[0044] Step 1: Data scanning, measurement, point marking, and line setting out

[0045] The design drawings were reviewed to check the installation deviations of the main steel structure. On-site measured dimensions were compared with the design drawings and model to ensure that construction was within allowable tolerances. (See also...) Figure 1 In this embodiment, the bill of materials for the decorative panel is generated by reverse modeling using Rhino software. Figures 3 to 5 The diagram illustrates the cross-sectional view of the stadium in this embodiment.

[0046] Step 2: Component fabrication

[0047] Based on on-site scanning and measurement data and reverse modeling results, detailed drawings of aluminum panels were precisely created, clearly defining the core parameters such as the dimensions, material, thickness, opening positions, and splicing nodes of each component, and marking processing tolerances and installation baselines. After modeling was completed, the joint coordinates and component connections were checked to ensure they matched the on-site measured dimensions and deviations of the main steel structure, with no collisions or dimensional errors. Subsequently, the detailed model and material list were sent to the processing manufacturer, and a production order was placed, specifying the production cycle, quality standards, and delivery requirements. The manufacturer was required to process the components precisely according to the model and provide a component processing acceptance form simultaneously to ensure that the delivered components were consistent with the model data.

[0048] Step 3: Install the clamps

[0049] Based on the converted plan view from the scanned model, arrange the clamping points, such as... Figure 2 As shown.

[0050] See Figure 6 and Figure 7The clamp 1 is composed of a first clamp part and a second clamp part connected by bolts. Both the first and second clamp parts include a clamp body, which has an arc-shaped portion 11 and end plate portions 12 located at both ends of the arc-shaped portion. The end plate portions 12 are provided with bolt holes. A welded structure 13 is provided on the outer side of the arc-shaped portion of the first clamp part, for welding connection to the main keel. The welded structure 13 is made of steel plate and has a connection surface directly connected to the arc-shaped portion and a steel plate welding surface 131 parallel to the end plate portions 12. A core insertion structure is provided on the outer side of the arc-shaped portion of the second clamp part, for bolt connection to the main keel. The welded structure and the core insertion structure are opposite each other and located in the same diameter direction of the clamp. The core insertion structure includes a steel plate portion 14 and a steel core 17. The steel plate portion 14 and the welded structure 13 are symmetrical structures, and the steel core 17 is welded and fixed to the steel plate portion 14. Figure 7 (b indicates the welding position). The steel insert 17 is perpendicular to the end plate portion 12, and the steel insert 17 is provided with two elongated holes 171.

[0051] The clamp is installed on the cylindrical steel 10. The first and second parts of the clamp are connected and fixed by two sets of bolt assemblies 15. A washer 16 can be installed between the bolt assembly 15 and the clamp. A rubber gasket is placed between the clamp and the cylindrical steel 10; in this embodiment, a 3mm thick rubber gasket is used. The clamp installation requires a guide line to ensure horizontality. During installation, it is important to ensure that the clamp's insert is aligned horizontally with the guide line.

[0052] Step 4: Main keel installation

[0053] See Figure 5 and 7 Connect the main keel 2 to the clamp 1 to complete the installation of the main keel. When both ends of the main keel 2 are connected to the clamp 1, one end of the main keel 2 is welded and fixed to the welding structure 13 of the clamp. Figure 7 (A in the diagram indicates the welding position), the other end is bolted to the steel insert 17 of the clamp. For example... Figure 5 As shown, the angle formed by the main keel 2 and the welded surface 131 of the steel plate of the welded structure 13 is not limited. The main keel 2 and the steel insert 17 are coaxially arranged. The corresponding ends of the main keel 2 are provided with round holes. The steel insert 17 is inserted into the main keel 2 and connected by bolt assembly 19. A nylon gasket is also provided between the steel insert 18 and the main keel 2. Figure 7 (c) In this embodiment, a 2mm thick nylon pad is used.

[0054] In this embodiment, the main keel 2 is a galvanized square tube. The specifications and dimensions of the galvanized square tube vary with the span. For main keels with a span of 4000mm or more, 120*80*6mm galvanized square tubes are used; for main keels with a span of 3000-4000mm, 120*60*5mm galvanized square tubes are used; and for main keels with a span of less than 3000mm, 100*50*4mm galvanized square tubes are used. During the installation of the main keel, the levelness and spacing must be ensured, and must not exceed 2800mm.

[0055] Step 5: Construction of the transfer layer

[0056] See Figure 5 and Figure 8 A transition layer structure is constructed between the main keel 2 and the aluminum plate mounting keel 5. The transition layer structure is used to adjust the levelness and spacing of the aluminum plate mounting keel. The transition layer structure includes a transition keel 41 and a lower hanging keel 43. The transition keel 41 is welded and fixed to the side of the main keel 41. The lower hanging keel 43 is vertically set and fastened to the transition keel 41 by a square clamp 42. The aluminum plate mounting keel 5 is welded to the lower hanging keel 43.

[0057] In this embodiment, the conversion keel 41 is made of 40*60*4 galvanized square tubing, and is connected to the main keel at a spacing of @1000mm. The lower keel 43 is made of L40*4mm galvanized angle steel, and is connected to the conversion keel at a spacing of @1200mm.

[0058] Step Six: Aluminum Panel Installation and Keel Construction

[0059] See Figure 9 The aluminum plate mounting keel 5 is a unitized frame structure, constructed from several welded galvanized square steel tubes. The aluminum plate keel dimensions are 30*30*3mm, and the maximum dimensions of the unitized aluminum plate mounting keel 5 are 4800*2400mm, i.e., L=4800mm, K=2400mm; the spacing between the galvanized square tubes is @1200mm, i.e., M=1200mm.

[0060] See Figure 5 and Figure 8 The aluminum plate mounting keel 5 is welded to the bottom of the transfer layer structure. During installation, the aluminum plate mounting keel is hoisted as a whole. The whole hoisting can be done in two ways, with electric hoisting being the preferred method:

[0061] Method 1 is electric hoist lifting: see Figure 10 The electric hoist is mounted on a steel frame constructed from galvanized square tubing 71 and bolt assemblies. See also Figure 11During the electric hoisting process, the aluminum plate mounting keel 5 is connected to the electric hoist 8 via a safety rope 81, and the aluminum plate mounting keel 5 is connected to the construction workers via a safety rope 82. When hoisting the electric hoist, attention should be paid to the balance of the steel frame and the limit distance to the top. After hoisting into place, workers will weld the aluminum plate mounting keel 5 to the transfer layer structure.

[0062] Method two is manual hoisting: see Figure 12 Manual hoisting requires fall prevention measures. At least 6 people are needed to cooperate during the hoisting process. One person (on the ground) should take fall prevention measures and tie ropes to the steel structure and connect them to the frame. The aluminum plate mounting keel 5 is connected to the workers above by safety rope 91, and the aluminum plate mounting keel 5 is connected to the construction workers by safety rope 92. The safety rope is contracted one section every time the aluminum plate mounting keel 5 rises a certain distance.

[0063] Step 7: Aluminum Plate Installation

[0064] As shown in Figure 3, aluminum plate 3 is connected and fixed to aluminum plate mounting keel 5 using a reverse installation method. Figure 13 The aluminum plate 3 is provided with a hook edge, the cross-section of which is C-shaped. The hook edge is connected and fixed to an L-shaped corner bracket connector 6 by bolts 61. The other end of the L-shaped corner bracket connector 6 is connected and fixed to the aluminum plate mounting keel 5 by bolts 62 and washers 62. The L-shaped corner bracket connector 6 is a 3mm thick corner bracket connector.

[0065] The tiered ceiling aluminum panels are installed in reverse. After the aluminum panels are transported from off-site to the high-rise site, they are manually hoisted from the ground to the aluminum panel installation keel 5 at the installation location. They are then fixed with specially customized corner bracket connectors 6. During the installation process, attention is paid to the flatness of the aluminum panels and installation is carried out with a guide line. After the installation is completed, a unified inspection and adjustment are carried out to ensure the installation quality of the aluminum panels before the next span can be constructed.

[0066] After the above steps are completed, workers can adjust the details according to the actual situation to make the overall effect better.

[0067] The above embodiments are merely preferred embodiments of the present invention and are not intended to limit the scope of protection of the present invention. For those skilled in the art, the present invention can have various modifications and variations. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention are included within the scope of protection of the present invention.

Claims

1. A method for installing an irregular aluminum panel tiered ceiling, characterized in that, Includes the following steps: Step 1: Data scanning, measurement, point marking, and line setting out; Step two: Complete the factory processing of each component; Step 3: Arrange the clamp locations and install the clamps; Step 4: Connect the main keel to the clamp, one end by welding and the other end by bolting. Step 5: Construct a transition layer structure between the main keel and the aluminum plate installation keel; Step 6: Weld the aluminum plate mounting frame to the bottom of the transition layer structure; Step 7: Connect and fix the aluminum plate to the aluminum plate mounting keel using a reverse installation method.

2. The method for installing irregular aluminum plate tiered ceilings as described in claim 1, characterized in that: in, The clamp is installed on the cylindrical steel. The clamp consists of a first clamp part and a second clamp part connected by bolts. Both the first clamp part and the second clamp part include a clamp body. The clamp body has an arc-shaped portion and end plate portions connected to both ends of the arc-shaped portion. The end plate portions are provided with bolt holes. A welding structure for welding to the main keel is fixed to the outer side of the arc-shaped portion of the first clamp part. A core insertion structure for bolting to the main keel is fixed to the outer side of the arc-shaped portion of the second clamp part. The welding structure and the core insertion structure are opposite to each other and located in the same diametrical direction of the clamp.

3. The method for installing irregular aluminum plate tiered ceilings as described in claim 2, characterized in that: in, The welded structure has a steel plate welding surface parallel to the end plate portion, and the angle formed by the main keel and the steel plate welding surface is not limited; The insert structure has a steel insert perpendicular to the end plate. The steel insert has an elongated hole, and the corresponding end of the main keel has a round hole. The main keel and the steel insert are coaxially arranged, and the steel insert is inserted into the main keel and connected by bolts.

4. The method for installing irregular aluminum plate tiered ceilings as described in claim 2, characterized in that: in, A nylon gasket is provided between the steel insert and the main keel.

5. The method for installing irregular aluminum plate tiered ceilings as described in claim 2, characterized in that: in, A rubber gasket is provided between the clamp and the cylindrical steel.

6. The method for installing irregular aluminum plate tiered ceilings as described in claim 1, characterized in that: in, The conversion layer structure is used to adjust the levelness and spacing of the aluminum plate mounting keel, including the conversion keel and the lower hanging keel. The conversion keel is fixed to the side of the main keel, and the lower hanging keel is set vertically and bolted to the conversion keel by a square clamp. The aluminum plate mounting keel is welded to the lower hanging keel.

7. The method for installing irregular aluminum plate tiered ceilings as described in claim 1 or 6, characterized in that: in, The aluminum plate mounting keel is a unit-type frame structure, which is composed of several square steel pipes welded together.

8. The method for installing irregular aluminum plate tiered ceilings as described in claim 7, characterized in that: in, During installation, the aluminum plate mounting keel is hoisted as a whole.

9. The method for installing irregular aluminum plate tiered ceilings as described in claim 8, characterized in that: in, When the aluminum plate mounting keel is hoisted by an electric hoist, the aluminum plate mounting keel is connected to the electric hoist by a safety rope, and the aluminum plate mounting keel is connected to the construction personnel by a safety rope.

10. The method for installing irregular aluminum plate tiered ceilings as described in claim 1, characterized in that: in, The aluminum plate is provided with a hook edge, the cross-section of which is C-shaped. The hook edge is fixed to an L-shaped corner bracket connector by bolts, and the other end of the L-shaped corner bracket connector is fixed to the aluminum plate mounting keel by bolts.