A hoisting method for a large-span steel structure glass dome
By employing pre-embedded plates on column tops and post-installed anchor bolts on steel beams in the hoisting of large-span steel structure domes, combined with lightweight hoisting equipment and layered support frames, the problem of equipment access for hoisting the central roof of the podium building was solved, achieving safe and efficient dome construction, and making it suitable for high-precision hoisting in complex sites.
Patent Information
- Application Number
- CN202611323627.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-28
- Publication Date
- 2026-11-24
AI Technical Summary
Existing large-span steel structure dome hoisting technology has several drawbacks in the confined space of the central roof of the podium building, including difficulties in equipment access, high equipment rental costs, long construction periods, significant safety risks, slow construction progress, and difficulty in controlling precision.
The system employs a dual process of "pre-embedded column top plate + post-installed anchor bolt plate on steel beam," combined with lightweight truck cranes and combined lifting tools, to erect a layered full-span support frame, and to hoist and assemble steel components in sections. Combined with total station positioning and graded welding processes, precise control is achieved.
Without altering the original building structure, we can reduce equipment rental costs, ensure hoisting safety, control component assembly deviations, improve construction efficiency and precision, and adapt to the needs of complex site construction.
Smart Images

Figure CN123153548A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of dome hoisting construction technology, specifically to a method for hoisting a large-span steel structure glass dome. Background Technology
[0002] With the rapid advancement of urbanization and infrastructure construction, large-span steel-structured glass domes, with their advantages of aesthetic appeal, spatial transparency, and excellent lighting, are widely used in public buildings such as large commercial complexes, stadiums, and convention centers. In recent years, the construction of various large-scale sports venues has further driven the iteration of large-span spatial steel structure technology, with the span and complexity of steel structures continuously increasing, and the construction of high-altitude irregular steel structures becoming the norm in the industry.
[0003] Currently, the mainstream installation techniques for large-span steel structure domes are mainly divided into five categories: overall hoisting method using large-tonnage truck cranes, ground-level segmented assembly + overall jacking method, high-altitude full-span scaffolding assembly method, unsupported cantilever installation method, and high-altitude sliding method. While these techniques are mature in conventional sites, they all have significant shortcomings when applied to the uniquely constrained site of the central roof of a building's podium.
[0004] The large-tonnage truck crane integral lifting method uses 400t to 500t ultra-large tonnage truck cranes to lift the assembled dome into place in one go on the ground or open roof. It has extremely high requirements for the lifting site and equipment travel route, and the rental cost of large-tonnage cranes is high. Large-span integral components are greatly affected by wind loads, and high-altitude placement is difficult and poses significant safety risks.
[0005] The ground-level segmented assembly + overall jacking method involves setting up a jacking frame on the ground, assembling the dome into segments, and then jacking it into place in sections. This method requires a large area of ground space to set up the jacking frame, and it is difficult to control multiple sets of jacking equipment simultaneously. It can easily cause temporary stress exceeding the standard in the steel structure, resulting in a long construction period and high cost of measures.
[0006] The high-altitude full-span scaffolding method involves erecting a full-coverage ultra-high full-span scaffolding and using small equipment to assemble steel components piece by piece. The scaffolding erection is massive, especially for high-altitude domes (the highest elevation is over 30m). The ultra-high scaffolding has high material and labor costs, a high risk of collapse, and the entire process is done in a high-altitude, piece-by-piece manner. It is difficult to control the positioning accuracy of curved components and slope shapes, resulting in slow construction progress.
[0007] The unsupported cantilever installation method uses the already installed steel components as temporary supports and assembles them piece by piece. However, cantilever assembly is prone to permanent deformation, and the structural stability cannot be guaranteed. It is only suitable for small-span, lightweight reticulated shell structures.
[0008] The high-altitude sliding method involves laying sliding tracks on the roof. After the components are assembled, they are slid to the designed position as a whole. This method requires laying special sliding tracks in advance, which occupies a lot of roof space, and the components are prone to shifting during the sliding process. Summary of the Invention
[0009] This invention provides a method for hoisting large-span steel structure glass domes, which can solve the problem of hoisting and constructing large-span domes in confined spaces on the roof of a podium building.
[0010] This invention is achieved through the following technical solution:
[0011] This invention provides a method for hoisting a large-span steel structure glass dome, comprising the following steps:
[0012] S10. Establish a three-dimensional model of the dome and complete the component segmentation, node detailing, hoisting path simulation and frame stress verification.
[0013] S20. Sequentially carry out the pre-embedding of steel column support plates and the construction of steel beam post-installed anchor bolt plates.
[0014] S30. Use the first truck crane to transfer the second truck crane to the roof, and erect a full-span roof support frame below the second truck crane's travel route and lifting point.
[0015] S40. Erect a circular aerial work platform, lantern frame, and steel spreader pole combination lifting device;
[0016] S50. Following the sequence of steel column installation, outer arc-shaped steel beam installation, diameter-direction main beam installation, and internal remaining steel beam installation, the steel beams are hoisted and assembled symmetrically in sections on both sides.
[0017] S60. Perform graded welding according to on-site wind speed, temperature and humidity, and ambient temperature;
[0018] The rated lifting capacity of the second truck crane is less than that of the first truck crane, and the rated lifting capacity of the first truck crane is less than 100t.
[0019] Specifically, step S10 includes the following sub-steps:
[0020] S11. Based on the construction drawings and on-site measured data, a full-size three-dimensional model of the dome was established using BIM software. The original integral steel beam was divided into a set number of components, and the component segmentation planning, node refinement, and welding process design were completed.
[0021] S12. Output component processing drawings, 3D coordinates of embedded parts, and elevation data based on the 3D model, and send them to the steel structure factory for prefabrication.
[0022] S13. Use BIM model to conduct hoisting path simulation, component collision check, scaffolding and back-top frame stress simulation calculation, and determine the frame erection range, upright parameters, and sensor placement positions;
[0023] S14. Conduct processing technology tests.
[0024] Specifically, in step S20, the pre-embedding step of the steel column support plate is as follows:
[0025] S21. Verify the material and specifications of the embedded parts and bolts, and level the embedded steel plates and straighten the embedded bolts.
[0026] S22. Based on the coordinate data extracted from the 3D model, transfer the axis lines and elevation control lines;
[0027] S23. Perform the following operations in sequence: rebar tying, column formwork sealing, embedded part placement, checking plane coordinates and elevation, deviation adjustment, welding and fixing to the rebar cage, and concrete pouring.
[0028] Specifically, in step S20, the steps for constructing the post-installed anchor bolt plate on the steel beam are as follows:
[0029] S24. Perform the following operations in sequence: positioning drilling, pressure air cleaning, inserting the chemical tube, screwing in the anchor bolt, pull-out test, and anchor plate fixing.
[0030] Specifically, in step S30, the full-span roof support frame is erected in three layers.
[0031] Specifically, in step S30, the full-span roof support frame is constructed using Φ48×2.8 steel pipes, with the vertical and horizontal spacing of the uprights being 0.5 to 0.6m, the step distance of the lower and middle horizontal bars being 0.9 to 1.1m, and the step distance of the top horizontal bars being 0.5 to 0.6m.
[0032] Specifically, in step S30, corresponding monitoring sensors are installed in the frame, steel columns, and welding areas.
[0033] Specifically, in step S60, the gas-shielded arc welding operation is carried out in an environment with a wind speed of less than 2 m / s.
[0034] Specifically, in step S60, when the ambient temperature is between -10 and 0°C, the base material temperature within a range of 100 mm or more around the weld is preheated to 20°C or more.
[0035] Specifically, the rated lifting capacity of the first truck crane is 50t, and the rated lifting capacity of the second truck crane is 12t.
[0036] Compared with the prior art, the present invention has the following advantages and beneficial effects:
[0037] 1. The method for hoisting a large-span steel structure glass dome provided by the present invention involves the sequential implementation of pre-embedding of steel column support plates and post-installation of anchor bolt plates on steel beams. By adopting a dual process of "pre-embedding of column top plates + post-installation of anchor bolt plates on steel beams", it can be adapted to the different stress requirements of load-bearing steel columns and connecting steel beams respectively. Combined with dual-control positioning of total station, it can improve the installation accuracy of pre-embedded parts.
[0038] 2. The large-span steel structure glass dome hoisting method provided by the present invention uses a lightweight first truck crane to transfer a second truck crane to the floor for operation, and uses a combination of lantern frame and steel spreader beam for hoisting, which solves the problem that large equipment cannot be brought into the central roof of the podium building, and can significantly reduce equipment rental costs.
[0039] 3. The method for hoisting a large-span steel structure glass dome provided by the present invention uses a multi-level full-span support frame erected below the second truck crane's travel route and hoisting point to achieve multi-level force transmission, transforming concentrated loads into uniformly distributed loads, and ensuring the safety of floor hoisting without altering the original building structure.
[0040] 4. The large-span steel structure glass dome hoisting method provided by the present invention, in the order of steel column installation, outer edge arc-shaped steel beam installation, diameter direction main beam installation, and internal remaining steel beam installation, is hoisted and assembled in symmetrical sections on both sides. It can effectively control the cumulative deviation of the assembly of arc-shaped components and slope shape, avoid structural stress concentration, and has strong adaptability. Attached Figure Description
[0041] To more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly described below. It should be understood that the following drawings only show some embodiments of the present invention and should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0042] In the attached diagram:
[0043] Figure 1 A flowchart illustrating the method for hoisting a large-span steel structure glass dome according to an embodiment of the present invention;
[0044] Figure 2 This is a BIM 3D model of a large-span circular steel structure glass dome, as described in this embodiment of the invention.
[0045] Figure 3 This is a comparison image of the steel structure before and after optimization of a large-span circular steel-glass dome according to an embodiment of the present invention;
[0046] Figure 4 This is a diagram showing the route of the truck crane on the floor and the reinforcement route of the lower floor, according to an embodiment of the present invention. Detailed Implementation
[0047] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are some embodiments of this application, but not all embodiments.
[0048] In the description of this specification, the references to terms such as "one embodiment / mode," "some embodiments / modes," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment / mode or example is included in at least one embodiment / mode or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment / mode or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments / modes or examples.
[0049] Example
[0050] Combination Figures 1-4 This embodiment provides a method for hoisting a large-span steel structure glass dome, including the following steps:
[0051] S10. Establish a three-dimensional model of the dome and complete the component segmentation, node detailing, hoisting path simulation, and frame stress verification.
[0052] Specifically, step S10 includes the following sub-steps:
[0053] S11. Based on the construction drawings and on-site measured data, a full-size three-dimensional model of the dome was established using BIM software. The original integral steel beam was divided into a set number of components, and the component segmentation planning, node refinement, and welding process design were completed.
[0054] S12. Output component processing drawings, 3D coordinates of embedded parts, and elevation data based on the 3D model, and send them to the steel structure factory for prefabrication. All components are numbered with both steel stamp and spray paint, and the installation direction is marked.
[0055] S13. Use BIM model to conduct hoisting path simulation, component collision check, scaffolding and back-top frame stress simulation calculation, determine the frame erection range, upright parameters, sensor placement positions, and output special construction plan and work instructions;
[0056] S14. Conduct processing technology tests. For complex nodes and irregularly shaped components, conduct processing technology tests. When cutting components, reserve the welding shrinkage allowance, cutting and milling allowance. The allowance value is determined by test.
[0057] S20. The pre-embedding of steel column support plates and the construction of post-installed anchor bolt plates for steel beams are carried out in sequence.
[0058] Specifically, the steps for pre-embedding the steel column support plate are as follows:
[0059] S21. Verify the material and specifications of the embedded parts and bolts, and level the embedded steel plates and straighten the embedded bolts.
[0060] S22. Based on the coordinate data extracted from the BIM 3D model, the axis lines and elevation control lines are measured using a total station;
[0061] S23. Perform the following operations in sequence: rebar tying, column formwork sealing, embedded part placement, checking plane coordinates and elevation, deviation adjustment, welding and fixing to the rebar cage, and concrete pouring. During the concrete pouring process, direct impact on the embedded plate is strictly prohibited. After the pouring is completed, the deviation is checked a second time, and the elevation error of the embedded plate at the top of the column is controlled within ±5mm.
[0062] The steps for constructing post-installed anchor bolts and embedded plates on steel beams are as follows:
[0063] S24. Perform the following operations in sequence: positioning drilling, pressure air cleaning, inserting the chemical tube, screwing in the anchor bolt, pull-out test, and anchor plate fixing.
[0064] During drilling, verticality and cylindrical shape must be ensured, and the edge distance and spacing of anchor holes must be strictly controlled; the holes must be cleaned by "two brushes and two blows" to thoroughly remove dust from the holes; disturbance is prohibited during the anchor bolt curing period, and a pull-out test must be carried out after curing is completed. Subsequent construction can only proceed after the test is passed.
[0065] S30. The first truck crane is used to transport the second truck crane to the roof, and a full-span roof support frame is erected below the second truck crane's travel route and lifting point.
[0066] It should be noted that the rated lifting capacity of the second truck crane is less than that of the first truck crane, and the rated lifting capacity of the first truck crane is less than 100t. In this embodiment, the rated lifting capacity of the first truck crane is 50t, and the rated lifting capacity of the second truck crane is 12t.
[0067] The full-span roof support frame is constructed in three layers. It is built with Φ48×2.8 steel pipes, and the longitudinal and transverse spacing of the uprights is 0.5-0.6m. The step distance of the lower and middle horizontal bars is 0.9-1.1m, and the step distance of the top horizontal bars is 0.5-0.6m. Corresponding monitoring sensors are installed on the frame, steel columns, and welding areas.
[0068] Specifically, step S30 includes the following sub-steps:
[0069] S31. Using the fire truck access road in the basement (70t design load), a 50t truck crane (first truck crane) was used to lift a 12t truck crane (second truck crane) to the 4th floor roof work area, and the initial load of the floor was checked.
[0070] S32. Directly below the 12t truck crane (second truck crane) travel route and lifting point, construct three layers of full-span roof support frames (1-2 layers, 2-3 layers, and 3-4 layers) to decompose the concentrated floor load into a uniformly distributed load. The main process parameters of the full-span roof support frame are as follows: steel pipe specification Φ48×2.8, single support frame length and width are both 2m, height is 5m, vertical spacing of uprights is 0.6m, horizontal spacing is 0.6m, single upright arrangement, non-top step distance is 1.1m, top step distance is 0.5m, the length of the upright extending from the center line of the top horizontal bar to the support point is 0.3m, the spacing of the main frame scissor braces is ≤5 spans and not less than 3m, the spacing of the 1.2m wide ring support frame scissor braces is ≤6 spans, and it is fully deployed in both directions.
[0071] Load calculation shows that the total load at a single support point is 80.6 kN, which is evenly distributed through 25 uprights. The force on each upright is 3.5 kN, which meets the specifications. At the same time, 1-2 cm thick steel plates are fully laid on the floor slab in the hoisting area, and No. 16 I-beams are arranged at 500 mm intervals perpendicular to the beam direction under the steel plates to transfer the load to the main beam of the building.
[0072] S40. Erect a circular aerial work platform, lantern frame, and steel spreader pole combination lifting device.
[0073] Specifically, a semi-enclosed full-span scaffold is erected from the first elevation position (e.g., 16.15m) to the second elevation position (e.g., 26.35m). At the corresponding positions of the steel columns, an 8m×8m lantern frame is erected to the top elevation (e.g., 34m). An H400×200×8×13 steel spreader (8m in length) is installed at the top of the lantern frame, and a lifting point is set below the steel spreader. It is equipped with an electric / manual hoist (e.g., with a rated lifting weight of 4t) to form a combination lifting device of "small truck crane + hoist + steel spreader". The frame material and the requirements for the scissor bracing are the same as those for the full-span roof scaffold.
[0074] S50. The steel columns are installed in the following order: outer curved steel beams, main beams in the diameter direction, and remaining internal steel beams. The steel beams are then hoisted and assembled in symmetrical sections on both sides.
[0075] The steel column installation method is as follows: based on the self-weight of a single steel column of 3.0t, the inner and outer areas are divided with steel columns at elevations of 30.541m and 30.631m as the axis, and the inner and outer steel columns are hoisted in sequence; before hoisting, process pads are welded to the top of the steel columns for subsequent alignment and correction of the steel beams; after each steel column is installed, the coordinates, elevation and verticality of the column top are checked with a total station, and any deviations are rectified immediately.
[0076] The method for installing the outer curved steel beam is as follows: use process pads to complete the splicing and positioning, temporarily fix it, and then re-measure the curved outline, elevation and 3% longitudinal slope to control the assembly deviation ≤4mm.
[0077] The method for installing the main beam in the diameter direction is as follows: hoist the radial main H-shaped steel beam in the middle of the dome as the overall load-bearing frame, and focus on controlling the horizontality and axial position of the main beam to prevent stress concentration in the structure.
[0078] The method for installing the remaining internal steel beams is as follows: the internal secondary beams and square steel protrusions of the dome are assembled in sequence, and the entire process is tracked and measured with a total station to strictly control the accuracy of the roof drainage longitudinal slope (3%); after all components are assembled, an overall self-inspection, rectification and inspection are carried out.
[0079] S60. Perform graded welding according to on-site wind speed, temperature and humidity, and ambient temperature.
[0080] Among them, gas shielded arc welding is carried out in an environment with a wind speed of less than 2m / s. When the ambient temperature is between -10 and 0℃, the temperature of the base material within a range of 100mm or more around the weld is preheated to greater than or equal to 20℃.
[0081] Specifically, for high-altitude and open-air working environments, a graded welding process is used, specifically:
[0082] Welding procedure qualification: Before construction, welding procedure qualification shall be carried out in combination with component material, joint type and welding position, welding procedure specification shall be prepared, and welding parameters, preheating temperature, interpass temperature and post-weld stress relief measures shall be specified.
[0083] Wind speed restrictions: The wind speed in the working area of shielded metal arc welding and self-shielded flux-cored wire arc welding is ≤8m / s, and the wind speed of gas shielded arc welding is ≤2m / s. If the wind speed exceeds the limit, a windproof shed must be erected. Welding is strictly prohibited when the relative humidity of the environment is >90%, the surface of the component is wet, or in rainy or snowy weather.
[0084] Welding construction deviation control: The blunt edge deviation of the joint is +2mm, the root gap without steel backing is ±2mm, and the root gap with steel backing is -2 to +6mm. The bevel angle deviation is -5° to +10°. Welds at the same support node should be welded symmetrically, with the lower flange welded first and the upper flange welded later. Welds at both ends of a single steel beam are prohibited from being welded simultaneously.
[0085] After all primary welds are completed, non-destructive testing is carried out using ultrasonic flaw detectors and magnetic particle flaw detectors. Flaw detection reports are digitally archived, and the weld flaw detection pass rate is required to be 100%.
[0086] It should be understood that stress, tilt, and displacement sensors are installed on the surfaces of each frame upright, lifting point, and steel column; temperature, humidity, and wind speed sensors are installed in the welding operation area. All monitoring data is uploaded to the cloud platform in real time, and automatic alarms are triggered when limits are exceeded.
[0087] Meanwhile, after all welding and flaw detection processes are completed, suspended basket operations are used to dismantle the working railings and temporary ladders on top of the steel columns; workers wear double-hook safety belts throughout the process, with the safety belts attached to the lifeline of the main steel beam. During the dismantling of the scaffold, the principle of dismantling the last erected first and the first erected last is followed, and the high-altitude operating scaffold and the three-layer back-top scaffold are dismantled in sections; the deformation of the scaffold and the main structure is monitored throughout the dismantling process, and it is strictly forbidden to pile up dismantling materials in one place.
[0088] To facilitate understanding of the workflow of this embodiment, this embodiment uses a commercial podium steel structure glass dome project as an example for illustration, and its construction parameters are as follows:
[0089] Dome parameters: horizontal circular shape, diameter 42m, total height 26.35m, 3% drainage slope on the top surface, total steel consumption 200t; includes 5 steel columns, 9 concrete support columns, and 160 steel beams;
[0090] Construction location: The central roof of the commercial podium, surrounded by completed buildings, with a narrow site where large cranes cannot enter;
[0091] Elevation range: steel column installation elevation 16.150m~31.944m, with the highest operating platform elevation 34m.
[0092] The specific implementation steps are as follows:
[0093] Based on the BIM 3D modeling of the dome, the original whole steel beam was broken down into 160 small components, and the 3D coordinates of 28 sets of steel column embedded plates and 36 steel beam post-embedded parts were output.
[0094] The hoisting path and the stress of the frame were simulated and calculated, and special operation instructions were prepared. The factory completed the prefabrication, numbering and pre-assembly of all steel components.
[0095] 28 sets of steel column top embedded plates were pre-embedded, and the entire process was checked with a total station. The deviation of the embedded parts was controlled within 2mm.
[0096] The construction of post-installed anchor bolts on 36 steel beams was carried out, and the holes were cleaned by "two brushes and two blows";
[0097] A three-layered, multi-tiered, full-span scaffold, a circular operating frame, a lantern frame, and a combination of lifting equipment were erected. 42 sets of intelligent sensors were installed on the scaffold, lifting points, and welding areas. The cloud monitoring platform was also debugged.
[0098] A 50t truck crane was used to transfer a 12t mini truck crane to the 4th floor roof.
[0099] The work was carried out symmetrically in two shifts: each shift completed the hoisting and alignment of 28 steel columns, the installation of the outer curved steel beams and radial main beams, and the assembly of the internal secondary beams and square steel structures, with dynamic measurement throughout the process.
[0100] 126 main welds were performed, and ultrasonic and magnetic particle testing were conducted.
[0101] The suspended basket was used to dismantle the high-altitude work fence, and the scaffolding was dismantled in sections.
[0102] In summary, the method for hoisting a large-span steel structure glass dome provided in this embodiment first establishes a three-dimensional model of the dome and completes component segmentation, node detailing, hoisting path simulation, and frame stress calculation. Then, it sequentially implements the pre-embedding of steel column support plates and the construction of post-installed anchor bolt plates for steel beams. Next, a 50t crane is used to transport a 12t truck crane to the roof, and a full-span roof support frame is erected below the 12t truck crane's travel route and hoisting points. Then, a circular high-altitude operating frame, lantern frame, and steel spreader beam combination hoisting equipment are erected. The hoisting and assembly are carried out symmetrically on both sides in the order of steel column installation, outer arc-shaped steel beam installation, diameter-direction main beam installation, and internal remaining steel beam installation. Finally, graded welding is performed according to the on-site wind speed, temperature, humidity, and ambient temperature.
[0103] in:
[0104] This embodiment employs a combined hoisting system consisting of a 50t truck crane for transport, a 12t mini truck crane for floor operations, a 4t hoist, and a steel spreader pole lantern frame. This system completely solves the problem of large equipment being unable to access the central roof of the podium building, significantly reducing equipment rental costs. It can be used in restricted areas such as the center of the podium building, the roof, and the atrium where there is no space for large equipment to operate. The applicable scope covers various large-span dome projects such as urban commercial complexes, cultural and tourism buildings, and stadiums, breaking through the limitations of traditional process sites. Furthermore, it reduces the use of large machinery and equipment, thus reducing fuel consumption and exhaust emissions.
[0105] This embodiment adopts a three-layer layered top-mounting system + load verification + intelligent deformation monitoring to completely solve the problem of excessive load on the floor slab by small truck cranes. Through multi-level force transmission of steel plates + I-beams + full-span scaffolding, the concentrated load is transformed into a uniformly distributed load, ensuring the safety of floor slab hoisting without altering the original building structure. The scaffolding and steel components can be reused, and the amount of construction waste is reduced by 30%, meeting the requirements of green construction.
[0106] This embodiment employs a four-stage symmetrical hoisting process: "steel column → outer steel beam → radial main beam → internal components." This effectively controls the cumulative deviation in the assembly of curved components and slope shapes, avoiding structural stress concentration. Furthermore, it utilizes a dual process of "pre-embedded column top plate + post-installed anchor bolt plate on steel beam," which adapts to the different stress requirements of the load-bearing steel column and connecting steel beam. Combined with dual-control positioning using a total station, this improves the installation accuracy of the pre-embedded parts.
[0107] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of the present invention. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A hoisting method for a long-span steel structure glass dome, characterized in that, Includes the following steps: S10. Establish a three-dimensional model of the dome and complete the component segmentation, node detailing, hoisting path simulation and frame stress verification. S20. Sequentially carry out the pre-embedding of steel column support plates and the construction of steel beam post-installed anchor bolt plates. S30. Use the first truck crane to transfer the second truck crane to the roof, and erect a full-span roof support frame below the second truck crane's travel route and lifting point. S40. Erect a circular aerial work platform, lantern frame, and steel spreader pole combination lifting device; S50. Following the sequence of steel column installation, outer arc-shaped steel beam installation, diameter-direction main beam installation, and internal remaining steel beam installation, the steel beams are hoisted and assembled symmetrically in sections on both sides. S60. Perform graded welding according to on-site wind speed, temperature and humidity, and ambient temperature; The rated lifting capacity of the second truck crane is less than that of the first truck crane, and the rated lifting capacity of the first truck crane is less than 100t.
2. The method for hoisting a large-span steel structure glass dome according to claim 1, characterized in that, Step S10 includes the following sub-steps: S11. Based on the construction drawings and on-site measured data, a full-size three-dimensional model of the dome was established using BIM software. The original integral steel beam was divided into a set number of components, and the component segmentation planning, node refinement, and welding process design were completed. S12. Output component processing drawings, 3D coordinates of embedded parts, and elevation data based on the 3D model, and send them to the steel structure factory for prefabrication. S13. Use BIM model to conduct hoisting path simulation, component collision check, scaffolding and back-top frame stress simulation calculation, and determine the frame erection range, upright parameters, and sensor placement positions; S14. Conduct processing technology tests.
3. The method for hoisting a large-span steel structure glass dome according to claim 2, characterized in that, In step S20, the steps for pre-embedding the steel column support plate are as follows: S21. Verify the material and specifications of the embedded parts and bolts, and level the embedded steel plates and straighten the embedded bolts. S22. Based on the coordinate data extracted from the 3D model, transfer the axis lines and elevation control lines; S23. Perform the following operations in sequence: rebar tying, column formwork sealing, embedded part placement, checking plane coordinates and elevation, deviation adjustment, welding and fixing to the rebar cage, and concrete pouring.
4. The method for hoisting a large-span steel structure glass dome according to claim 3, characterized in that, In step S20, the construction steps for the post-installed anchor bolts and embedded plates on the steel beam are as follows: S24. Perform the following operations in sequence: positioning drilling, pressure air cleaning, inserting the chemical tube, screwing in the anchor bolt, pull-out test, and anchor plate fixing.
5. The method for hoisting a large-span steel structure glass dome according to claim 1, characterized in that, In step S30, the full-span roof support frame is erected in three layers.
6. The method for hoisting a large-span steel structure glass dome according to claim 5, characterized in that, In step S30, the full-span roof support frame is constructed using Φ48×2.8 steel pipes, with the vertical and horizontal spacing of the uprights being 0.5 to 0.6m, the step distance of the lower and middle horizontal bars being 0.9 to 1.1m, and the step distance of the top horizontal bars being 0.5 to 0.6m.
7. The method for hoisting a large-span steel structure glass dome according to claim 6, characterized in that, In step S30, corresponding monitoring sensors are installed in the frame, steel columns, and welding areas.
8. The method for hoisting a large-span steel structure glass dome according to claim 1, characterized in that, In step S60, the gas-shielded arc welding operation is carried out in an environment with a wind speed of less than 2 m / s.
9. The method for hoisting a large-span steel structure glass dome according to claim 8, characterized in that, In step S60, when the ambient temperature is between -10 and 0°C, the base material temperature within a range of 100 mm or more around the weld is preheated to 20°C or more.
10. The method for hoisting a large-span steel structure glass dome according to any one of claims 1 to 9, characterized in that, The first truck crane has a rated lifting capacity of 50t, and the second truck crane has a rated lifting capacity of 12t.