Hoisting method for super-large cross-slit cantilever steel corridor
By correcting component dimensions using BIM models and 3D laser scanning, erecting adjustable pre-arched assembly frames, setting temporary connecting components, and utilizing a hydraulic lifting system for graded debugging and uniform lifting, the precision and safety issues in the construction of ultra-large span cantilevered steel corridors were resolved, achieving high-precision and high-safety construction results.
Patent Information
- Application Number
- CN202611351127.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-02
- Publication Date
- 2026-11-24
AI Technical Summary
The construction process of the super-large span cantilevered steel corridor between the two towers is difficult to control in terms of precision and structural stress, making it difficult to guarantee construction safety and quality.
The dimensions of the components are corrected by BIM model and 3D laser scanning. An adjustable pre-arched assembly frame is erected, and temporary connecting components are set to form an overall lifting unit. The hydraulic lifting system is used for graded debugging, uniform lifting, and graded unloading, and the structural data is monitored throughout the process.
It achieves precision and controllable structural stress throughout the entire construction process, improves construction safety and quality, reduces the amount of high-altitude work, and lowers construction costs.
Smart Images

Figure CN123153553A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building construction technology, and in particular to a method for hoisting an ultra-large span cantilevered steel corridor. Background Technology
[0002] The super-large cantilevered steel corridor between the two towers has cantilevered trusses belonging to different main structures on the left and right sides, with permanent structural joints in the span. The components are separate and cannot be directly hoisted as a whole. Traditional construction often uses high-altitude assembly, which involves numerous high-altitude welding and installation procedures and high safety risks associated with working near edges. If full-span ground support is used, large-scale reinforcement of the basement roof is required, resulting in high temporary engineering costs. Furthermore, cumulative errors in civil engineering pre-embedded components and steel component fabrication can lead to misalignment of beam and column bolt holes. Conventional factory prefabrication makes it difficult to allow bolts to be freely inserted, compromising construction quality.
[0003] The existing technical problems are that the existing lifting systems mostly use single parameter control, resulting in poor multi-point synchronization accuracy. After the cantilevered steel connecting corridor between the two towers is installed, sudden changes in internal forces and excessive deformation of components are likely to occur. Currently, there is a lack of a complete set of construction technology that integrates digital pre-correction, on-site in-situ hole matching, double closed-loop synchronous lifting, and symmetrical dismantling of connecting beams.
[0004] Therefore, the precision and structural stress of the entire construction process of the super-large span cantilevered steel corridor between the two towers are difficult to control, and the construction safety and quality are difficult to guarantee. This is a technical problem that still needs to be solved. Summary of the Invention
[0005] To address the shortcomings of existing technologies, this invention provides a method for hoisting an ultra-large span-joint cantilever steel corridor. The technical problem to be solved is that the accuracy and structural stress of the ultra-large span-joint cantilever steel corridor between two towers are difficult to control throughout the construction process, and the construction safety and quality are difficult to guarantee.
[0006] This invention provides a method for hoisting an ultra-large span-joint cantilever steel corridor, comprising: S1. Construct a construction BIM model and perform full-condition construction simulation calculations. Combine the measured data of the tower and embedded components obtained by 3D laser scanning, compare the measured data with the BIM model data, and correct the processing dimensions of the components at the construction site. S2. Erect a pre-arched assembly frame with adjustable height, and assemble the cantilever truss on the pre-arched assembly frame. S3. Temporary connecting components are installed at the structural joints between two adjacent cantilever trusses to assemble at least two cantilever trusses into an integral lifting unit. S4. Install pairs of lifting platforms and hydraulic lifting systems on the outside of adjacent towers, and perform graded lifting and debugging of the hydraulic lifting systems according to the load level; S5. The entire lifting unit is lifted at a constant speed using a lifting platform and a hydraulic lifting system; S6. When the overall lifting unit is lifted to the preset installation height, connect the overall lifting unit to the towers on both sides; S7. The hydraulic lifting system is unloaded in stages according to the load level, and the structural load of the overall lifting unit is transferred to the tower. S8. Remove the temporary connecting components and restore the structural joint; S9. Monitor the structural data during the construction process from S1 to S8.
[0007] Further, S1 includes: S11. Use a three-dimensional laser scanning device to collect point cloud data of the pre-embedded corbels on the tower structure and obtain point cloud data information; S12. Compare and analyze the collected point cloud data of the embedded bracket with the design data of the corresponding embedded bracket in the construction BIM model to obtain the installation deviation value of the embedded bracket. S13. Based on the installation deviation value of the pre-embedded bracket, correct the processing dimensions of the overall lifting unit, the pre-arching assembly jig, and the temporary connecting components.
[0008] Further, S2 includes: S21. Adjustable short columns are spaced out on the pre-arched assembly frame. S22. Assemble the overall lifting unit on the pre-arching assembly jig; S23. Adjust the height of the adjustable short column to put the overall lifting unit in a pre-arched state.
[0009] Furthermore, during the assembly of the cantilever truss in S2, the following sequence shall be followed: S24. First, assemble the lower chord of the cantilever truss, then assemble the straight web members of the cantilever truss, then assemble the diagonal web members of the cantilever truss, then assemble the middle chord of the cantilever truss, then assemble the upper chord of the cantilever truss, and finally assemble the secondary beams of the cantilever truss to complete the assembly of the cantilever truss.
[0010] Furthermore, in step S4, the hydraulic lifting system is subjected to graded lifting and adjustment according to load levels, including: S41. Perform the graded lifting and adjustment in sequence according to the load level from low to high; wherein the load level includes 20%, 40%, 60%, 80%, 90%, and 100%.
[0011] Furthermore, in step S6, the overall lifting unit is connected to the towers on both sides, including: S61. Based on the actual hole positions of the pre-embedded brackets of the two towers, drill holes in situ and chamfer and clean the hole openings. S62. Install high-strength bolts and use a magnetic drill to complete the construction of the bolted-welded hybrid joint.
[0012] Furthermore, S7 performs graded unloading of the hydraulic lifting system according to load level, including: S71. The hydraulic lifting system is unloaded in stages according to the load level from high to low, so as to gradually transfer the structural load of the overall lifting unit to the tower structure.
[0013] Furthermore, in S9, the monitored structural data includes deflection data, stress data, and lifting synchronization deviation data.
[0014] Compared with the prior art, the present invention has the following beneficial effects: By correcting component dimensions through BIM simulation and 3D laser scanning, and employing adjustable pre-arched frames for precise assembly, temporary connecting components were used to form an integrated lifting unit. Through tiered adjustment, uniform lifting, precise positioning, and tiered unloading, along with monitoring of structural data throughout the entire process, the precision and stress control of the entire construction process were achieved, ensuring construction safety and quality. This effectively controlled the precision and structural stress of the twin-tower span-joint super-large cantilevered steel corridor construction process, making construction safer and improving construction quality.
[0015] This invention solves the technical problems of difficulty in controlling the accuracy and structural stress of the entire construction process of the ultra-large span cantilevered steel corridor between two towers, and difficulty in ensuring construction safety and quality. Attached Figure Description
[0016] The accompanying drawings, which form part of this specification, illustrate embodiments of the invention and, together with the description, serve to explain the principles of the invention.
[0017] The invention will be more clearly understood with reference to the accompanying drawings and the following detailed description, wherein: Figure 1 This is a flowchart illustrating a method for hoisting an ultra-large span cantilevered steel corridor, as provided in an embodiment of the present invention. Detailed Implementation
[0018] The technical methods in the embodiments of the present invention will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of them. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0019] Those skilled in the art will understand that the terms "first," "second," etc., in the embodiments of the present invention are only used to distinguish different steps, devices, or modules, and do not represent any specific technical meaning, nor do they indicate a necessary logical order between them.
[0020] It should also be understood that in the embodiments of the present invention, "multiple" can refer to two or more, and "at least one" can refer to one, two or more.
[0021] It should also be understood that any component, data or structure mentioned in the embodiments of the present invention can generally be understood as one or more unless explicitly defined or given contrary instructions in the context.
[0022] Building Information Modeling (BIM) is a new tool used in the fields of architecture, engineering, and civil engineering. It is mainly based on three-dimensional graphics and can be applied to the entire life cycle of construction projects.
[0023] Furthermore, the term "and / or" in this invention is merely a description of the relationship between related objects, indicating that three relationships can exist. For example, A and / or B can represent: A existing alone, A and B existing simultaneously, or B existing alone. Additionally, the character " / " in this invention generally indicates that the preceding and following related objects have an "or" relationship.
[0024] It should also be understood that the description of the various embodiments in this invention emphasizes the differences between the various embodiments, and the similarities or similarities can be referred to each other. For the sake of brevity, they will not be described in detail.
[0025] The following description of at least one exemplary embodiment is merely illustrative and is in no way intended to limit the invention or its application or use.
[0026] Techniques, methods, and equipment known to those skilled in the art may not be discussed in detail, but where appropriate, such techniques, methods, and equipment should be considered part of the specification.
[0027] It should be noted that similar labels and letters in the following figures indicate similar items; therefore, once an item is defined in one figure, it does not need to be discussed further in subsequent figures.
[0028] To address the technical challenges of controlling the precision and structural stress during the entire construction process of the ultra-large span cantilevered steel corridor between twin towers, as well as ensuring construction safety and quality, this invention provides a detailed explanation through multiple embodiments.
[0029] The principles of this invention include: First, key construction parameters are determined through BIM modeling and full-condition simulation. Then, the actual installation deviation of the pre-embedded corbels in the tower is measured using 3D laser scanning. Based on this, the processing dimensions of the connecting corridor components and temporary connecting components are precisely corrected, eliminating pre-embedding and processing errors from the source. Second, an adjustable pre-arched support frame is erected on the ground. Multiple cantilevered trusses are connected into an integral lifting unit through temporary connecting components, ensuring uniform structural stiffness and coordinated deformation during the lifting process. A staged debugging and uniform-speed overall lifting method is adopted. After positioning, fine-tuning and temporary locking are performed. Bolt connections are smoothly achieved through on-site hole fitting, avoiding forced assembly. Finally, the hydraulic system is unloaded in stages to smoothly transfer the structural load to the tower. Deflection, stress, and lifting synchronization are monitored in real time throughout the process, allowing for a gradual release of structural internal forces and controllable deformation. Ultimately, this achieves high-precision and high-safety overall installation of the ultra-large cantilevered steel connecting corridor, ensuring construction safety and quality. Example
[0030] Example 1 is a method for hoisting an ultra-large span cantilevered steel corridor provided by the present invention. Figure 1 This is a flowchart illustrating a method for hoisting an ultra-large span-joint cantilever steel corridor according to an embodiment of the present invention, as shown below. Figure 1 As shown, steps S1 to S9 are included: S1. Construct a construction BIM model and perform full-condition construction simulation calculations. Combine the measured data of the tower and embedded components obtained by 3D laser scanning, compare the measured data with the BIM model data, and correct the processing dimensions of the components at the construction site.
[0031] Understandably, by comparing BIM modeling and simulation with 3D laser scanning measurements, it is possible to eliminate component processing errors in advance, accurately correct component dimensions, and avoid problems such as misaligned holes and inaccurate connections during on-site installation, thus achieving precise construction from the source.
[0032] In this embodiment of the invention, an overall BIM model of the tower, connecting corridor and formwork is established, and finite element simulation analysis of the entire working condition of assembly, lifting, unloading and joint removal is carried out. Based on this, key construction parameters such as the pre-arch value of the pre-arch assembly formwork, the arrangement of lifting points and temporary connecting short beams are determined.
[0033] S2. Erect a pre-arched assembly frame with adjustable height, and assemble the cantilever truss on the pre-arched assembly frame.
[0034] It is understandable that an adjustable-height pre-arch assembly frame is used to place the connecting corridor formed by the cantilever truss connection. It can also adapt to the pre-arch requirements of the connecting corridor design, offset the deformation under subsequent lifting and load, and make the steel connecting corridor meet the design accuracy.
[0035] For example, the pre-arching assembly jig uses adjustable short columns to form a quadratic parabolic pre-arch, with a pre-arch value of 35mm.
[0036] S3. Temporary connecting components are installed at the structural joint between two adjacent cantilever trusses to assemble at least two cantilever trusses into an integral lifting unit.
[0037] It is understandable that by setting temporary connecting components at the structural joints, adjacent cantilever trusses are connected into an integral lifting unit, so that the integral lifting unit is stable as a whole during the lifting process, and the cantilever trusses in the integral lifting unit remain synchronized, avoiding relative displacement of each cantilever truss and improving construction stability and positioning accuracy.
[0038] S4. Install pairs of lifting platforms and hydraulic lifting systems on the outside of adjacent towers, and conduct graded lifting and debugging of the hydraulic lifting systems according to the load level.
[0039] Understandably, setting up lifting platforms and hydraulic lifting systems in pairs on the outside of the tower and conducting graded load tests can ensure that the lifting device is subjected to balanced forces and reliable synchronization, verify the safety of the system in advance, and provide a safety guarantee for subsequent smooth lifting.
[0040] In this embodiment of the invention, after the hydraulic lifting system is graded and adjusted according to the load level, the overall lifting unit in S3 can be suspended and stationary, and then lifted after confirming that all indicators are qualified.
[0041] Understandably, when the entire lifting unit is cantilevered and stationary, it can be used to test whether the lifting system and structure are reliable under stress, and to fully observe the structural stress and deformation data. Only after confirming that all indicators are qualified can the lifting be carried out, thus avoiding the safety hazards caused by direct high-altitude lifting.
[0042] For example, the hydraulic lifting system raises the entire lifting unit 500mm off the ground, leaves it stationary for 12 hours, and after all stress and deformation monitoring are qualified, it enters the formal lifting stage.
[0043] S5. The entire lifting unit is lifted at a constant speed using a lifting platform and a hydraulic lifting system.
[0044] Understandably, using uniform speed lifting can avoid impact loads and structural swaying during the lifting process, ensure the overall stability of the lifting unit, and prevent deformation or safety hazards caused by uneven stress.
[0045] In this embodiment of the invention, the overall lifting unit is stopped from being lifted during severe weather.
[0046] For example, the entire lifting unit is lifted at a speed of 6-8 m / h using a lifting platform and hydraulic lifting system. Lifting is stopped in case of strong winds of level 6 or above, or in rain or snow.
[0047] S6. When the overall lifting unit is raised to the preset installation height, connect the overall lifting unit to the towers on both sides.
[0048] Understandably, reliably connecting the raised integral lifting unit to the towers on both sides can complete the fixed positioning of the corridor structure, providing a foundation for subsequent load transfer and structural formation.
[0049] In this embodiment of the invention, when the overall lifting unit is lifted to a distance of 500mm from the pre-embedded corbel, it is switched to the inching fine-tuning mode, and the upper chord of the connecting corridor is temporarily locked after the positioning is completed.
[0050] For example, insert rods are installed between the upper chord of the connecting corridor and the corresponding pre-embedded corbels of the tower. The two ends of the insert rods are detachably connected to the upper chord of the connecting corridor and the pre-embedded corbels of the tower, respectively, so as to achieve temporary locking after lifting and positioning.
[0051] S7. The hydraulic lifting system is unloaded in stages according to the load level, and the structural load of the overall lifting unit is transferred to the tower.
[0052] Understandably, tiered unloading allows the structural load to be transferred smoothly and gradually to the main tower structure, avoiding sudden changes in internal forces and structural deformation, and ensuring a safe and reliable transfer of loads.
[0053] S8. Remove temporary connecting components and restore the structural joint.
[0054] Understandably, removing temporary connecting components and restoring structural joints allows the connecting corridor to return to its designed stress state, meeting the deformation and functional requirements of the structural joints.
[0055] In this embodiment of the invention, when there are multiple cantilever trusses in the overall lifting unit, the temporary connecting short beams are cut and dismantled in a symmetrical order.
[0056] This allows for the gradual release of internal structural forces, preventing stress concentration that could lead to structural deformation.
[0057] S9. Monitor the structural data during the construction process from S1 to S8.
[0058] Understandably, monitoring the structural data throughout the entire process allows for real-time monitoring of the structural stress, deformation, and synchronization status, enabling timely detection and adjustment of anomalies, thus ensuring construction safety and structural quality.
[0059] In this embodiment of the invention, the monitored structural data in step S9 includes deflection data, stress data, and lifting synchronization deviation data.
[0060] In this embodiment of the invention, when the monitored structural data does not meet the preset standards, construction is suspended and the hydraulic lifting system is paused.
[0061] For example, 16 monitoring points are set up throughout the entire process to monitor deflection data, stress data, and hoisting synchronization deviation data at all times. Among them, the warning threshold for deflection data is 24.5mm and the limit threshold is 35mm; the hoisting point synchronization deviation warning is ±5mm and the alarm is ±10mm; the stress warning for the rod is 190MPa and the limit is 205MPa. The data is uploaded in real time, and the machine is stopped if the standard is exceeded.
[0062] In this embodiment of the invention, step S1 includes steps S11 to S13: S11. Use a three-dimensional laser scanning device to collect point cloud data of the pre-embedded corbels on the tower structure and obtain point cloud data information.
[0063] S12. Compare and analyze the collected point cloud data of the embedded bracket with the corresponding design data of the embedded bracket in the construction BIM model to obtain the installation deviation value of the embedded bracket.
[0064] S13. Based on the installation deviation of the pre-embedded bracket, correct the processing dimensions of the overall lifting unit, the pre-arching assembly jig, and the temporary connecting components.
[0065] In this embodiment of the invention, S13 further includes correcting the processing dimensions of the insert rod based on the installation deviation value of the pre-embedded bracket.
[0066] For example, a three-dimensional laser scanning device was used to measure the pre-embedded bracket of the tower. It was found that the pre-embedded bracket had a horizontal deviation of 4mm and a vertical deviation of 6mm relative to the design position. Based on the installation deviation value, the processing dimensions and docking hole positions of the end connection nodes of the overall lifting unit and the temporary connection components were adjusted accordingly to make the processing dimensions of the components match the actual pre-embedded positions on site.
[0067] In this embodiment of the invention, step S2 includes steps S21 to S23: S21. Adjustable short columns are spaced apart on the pre-arched assembly frame.
[0068] S22. Assemble the overall lifting unit on the pre-arching assembly jig.
[0069] S23. Adjust the height of the adjustable short column to put the overall lifting unit in a pre-arched state.
[0070] It is understandable that setting adjustable short columns at intervals on the pre-arched assembly jig and adjusting their height to make the overall lifting unit form a pre-arched state can offset the stress deformation of the structure under subsequent lifting and self-weight, so that the connecting corridor is reasonably stressed after it is in place; at the same time, direct assembly on the jig makes it easier to accurately control the assembly accuracy of the overall lifting unit.
[0071] In this embodiment of the invention, the cantilever truss assembly in step S2 is performed in the order of steps S24: S24. First, assemble the lower chord of the cantilever truss, then assemble the straight web members of the cantilever truss, then assemble the diagonal web members of the cantilever truss, then assemble the middle chord of the cantilever truss, then assemble the upper chord of the cantilever truss, and finally assemble the secondary beams of the cantilever truss to complete the assembly of the cantilever truss.
[0072] Understandably, assembling the cantilever truss in the order of bottom chord, straight web members, diagonal web members, middle chord, top chord, and secondary beams can gradually form a stable geometric structure from bottom to top. This ensures that the geometric structure of the cantilever truss is subjected to uniform stress and accurately positioned during assembly, avoiding structural deformation or installation deviations caused by improper assembly sequence.
[0073] In this embodiment of the invention, step S4 involves graded lifting and adjustment of the hydraulic lifting system according to load levels, including step S41: S41. Perform graded upgrades and adjustments in sequence according to the load levels from low to high.
[0074] The load ratings include 20%, 40%, 60%, 80%, 90%, and 100%.
[0075] Understandably, by loading and debugging in stages from low to high, the load-bearing capacity, synchronization performance, and structural stress state of the hydraulic lifting system can be tested step by step, and potential equipment or structural hazards can be detected early to avoid safety risks caused by lifting directly at full load, thus ensuring a smooth and reliable lifting process.
[0076] In this embodiment of the invention, step S6 involves connecting the overall lifting unit to the towers on both sides, including steps S61 and S62: S61. Based on the actual hole positions of the pre-embedded brackets on both sides of the tower, drill holes in situ and chamfer and clean the hole openings.
[0077] It is understandable that chamfering and cleaning the orifice can eliminate the deviation between the pre-processing and on-site installation, and avoid stress concentration in the components caused by the forced installation of high-strength bolts.
[0078] S62. Install high-strength bolts and use a magnetic drill to complete the construction of the bolted-welded hybrid joint.
[0079] Understandably, using magnetic drills to drill holes on-site and insert high-strength bolts can accommodate actual on-site positioning deviations, avoid forced insertion of high-strength bolts due to misalignment of prefabricated holes, ensure smooth connection of bolted and welded joints, reliable stress distribution, and improve construction accuracy and structural safety.
[0080] In this embodiment of the invention, step S7 involves graded unloading of the hydraulic lifting system according to load levels, including step S71: S71. The hydraulic lifting system is unloaded in stages according to the load level from high to low, so as to gradually transfer the structural load of the overall lifting unit to the tower structure.
[0081] Understandably, adopting a step-by-step unloading method from high to low can avoid sudden load transfer that could cause abrupt changes in structural internal forces and impacts. This allows the stress on the overall lifting unit to be smoothly transferred to the main tower structure, ensuring the structural safety and controllable deformation of the hydraulic lifting system, and improving positioning accuracy.
[0082] The beneficial effects of this invention include: 1) Digital Innovation: By using BIM combined with 3D laser scanning for on-site measurement and comparison, the pre-embedded deviation and component processing error are reduced from the source, effectively solving the problems of inaccurate bolt hole alignment and on-site rework; 2) Node innovation: The use of magnetic drilling for on-site hole preparation enables smooth installation of high-strength bolts, avoids forced assembly, and improves the construction quality of bolted and welded connection nodes; 3) Enhanced innovation: The system adopts collaborative control for lifting, resulting in uniform force distribution at multiple points, good lifting synchronization, and more stable and reliable operation; 4) Innovation in dismantling joints: Cutting and removing temporary connecting short beams in a symmetrical order can release the internal forces of the structure smoothly and avoid stress concentration that could lead to structural deformation. 5) Construction and building advantages: The height-adjustable jig is used to achieve precise pre-arching. The jig has a simple structure and is easy to construct. Most of the process is completed on the ground, without the need for large-area full-span support and reinforcement. The construction is safe and reliable, and the overall cost is lower.
[0083] This invention discloses a method for hoisting an ultra-large span-joint cantilevered steel corridor. Before construction, BIM simulation analysis combined with 3D laser scanning measurement data is used to correct component processing deviations. An adjustable assembly jig with a flat top surface is used, and adjustable short columns are used to precisely set a 35mm pre-arch according to a quadratic parabola. Temporary connecting components are used to seal the permanent structural joint between the towers, and the cantilevered trusses on both sides are assembled on the ground into an integral lifting unit. A hydraulic lifting system and a force-displacement dual closed-loop control system are used to complete the overall uniform speed lifting. After the components are in place, bolt alignment deviations are eliminated through on-site hole matching technology, bolted and welded connections are completed, and embedded rods are installed. Then, the structural load is transferred to the tower through staged synchronous unloading. Finally, the temporary connecting components are symmetrically removed to restore the original design joint state of the structure.
[0084] This invention integrates several innovations, including digital control, in-situ hole matching, double closed-loop lifting, and symmetrical joint dismantling, which significantly reduces the amount of high-altitude work, ensures high construction precision, controllable deformation, and outstanding safety and economic benefits.
[0085] The basic principles of the present invention have been described above with reference to specific embodiments. However, it should be noted that the advantages, benefits, and effects mentioned in the present invention are merely examples and not limitations, and should not be considered as essential features of each embodiment of the present invention. Furthermore, the specific details disclosed above are for illustrative and facilitative purposes only, and are not limitations. These details do not limit the present invention to the necessity of employing the aforementioned specific details.
[0086] The various embodiments in this specification are described in a progressive manner, with each embodiment focusing on its differences from other embodiments. Similar or identical parts between embodiments can be referred to interchangeably. For system embodiments, since they largely correspond to method embodiments, the description is relatively simple; relevant parts can be referred to the descriptions in the method embodiments.
[0087] The above description of the disclosed aspects is provided to enable any person skilled in the art to make or use the invention. Various modifications to these aspects will be readily apparent to those skilled in the art, and the general principles defined herein can be applied to other aspects without departing from the scope of the invention. Therefore, the invention is not intended to be limited to the aspects shown herein, but rather to be carried out within the widest scope consistent with the principles and novel features disclosed herein.
[0088] The above description has been given for purposes of illustration and description. Furthermore, this description is not intended to limit the embodiments of the invention to the forms disclosed herein. Although numerous exemplary aspects and embodiments have been discussed above, those skilled in the art will recognize certain variations, modifications, alterations, additions, and sub-combinations thereof.
Claims
1. A method for hoisting an ultra-large span-joint cantilevered steel corridor, characterized in that, The method includes: S1. Construct a construction BIM model and perform full-condition construction simulation calculations. Combine the measured data of the tower and embedded components obtained by 3D laser scanning, compare the measured data with the BIM model data, and correct the processing dimensions of the components at the construction site. S2. Erect a pre-arched assembly frame with adjustable height, and assemble the cantilever truss on the pre-arched assembly frame. S3. Temporary connecting components are installed at the structural joints between two adjacent cantilever trusses to assemble at least two cantilever trusses into an integral lifting unit. S4. Install pairs of lifting platforms and hydraulic lifting systems on the outside of adjacent towers, and perform graded lifting and debugging of the hydraulic lifting systems according to the load level; S5. The entire lifting unit is lifted at a constant speed using a lifting platform and a hydraulic lifting system; S6. When the overall lifting unit is lifted to the preset installation height, connect the overall lifting unit to the towers on both sides; S7. The hydraulic lifting system is unloaded in stages according to the load level, and the structural load of the overall lifting unit is transferred to the tower. S8. Remove the temporary connecting components and restore the structural joint; S9. Monitor the structural data during the construction process from S1 to S8.
2. The method according to claim 1, characterized in that, S1 includes: S11. Use a three-dimensional laser scanning device to collect point cloud data of the pre-embedded corbels on the tower structure and obtain point cloud data information; S12. Compare and analyze the collected point cloud data of the embedded bracket with the design data of the corresponding embedded bracket in the construction BIM model to obtain the installation deviation value of the embedded bracket. S13. Based on the installation deviation value of the pre-embedded bracket, correct the processing dimensions of the overall lifting unit, the pre-arching assembly jig, and the temporary connecting components.
3. The method according to claim 1, characterized in that, S2 includes: S21. Adjustable short columns are spaced out on the pre-arched assembly frame. S22. Assemble the overall lifting unit on the pre-arching assembly jig; S23. Adjust the height of the adjustable short column to put the overall lifting unit in a pre-arched state.
4. The method according to claim 1, characterized in that, When assembling the cantilever truss in S2, the following sequence shall be followed: S24. First, assemble the lower chord of the cantilever truss, then assemble the straight web members of the cantilever truss, then assemble the diagonal web members of the cantilever truss, then assemble the middle chord of the cantilever truss, then assemble the upper chord of the cantilever truss, and finally assemble the secondary beams of the cantilever truss to complete the assembly of the cantilever truss.
5. The method according to claim 1, characterized in that, S4 involves graded lifting and adjustment of the hydraulic lifting system according to load levels, including: S41. Perform the graded lifting and adjustment in sequence according to the load level from low to high; wherein the load level includes 20%, 40%, 60%, 80%, 90%, and 100%.
6. The method according to claim 1, characterized in that, The S6 section connects the overall lifting unit to the towers on both sides, including: S61. Based on the actual hole positions of the pre-embedded brackets of the two towers, drill holes in situ and chamfer and clean the hole openings. S62. Install high-strength bolts and use a magnetic drill to complete the construction of the bolted-welded hybrid joint.
7. The method according to claim 5, characterized in that, The S7 performs graded unloading of the hydraulic lifting system according to load level, including: S71. The hydraulic lifting system is unloaded in stages according to the load level from high to low, so as to gradually transfer the structural load of the overall lifting unit to the tower structure.
8. The method according to claim 1, characterized in that, In S9, the monitored structural data includes deflection data, stress data, and lifting synchronization deviation data.