A steel structure truss site sectional assembly welding hoisting construction method
The segmented assembly, welding, and hoisting construction method guided by BIM modeling solved the problem of large steel trusses being unable to be transported and hoisted as a whole, achieving precise, standardized, and efficient construction, improving construction accuracy and safety, and extending the service life of the structure.
Patent Information
- Application Number
- CN202611365685.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-04
- Publication Date
- 2026-11-24
AI Technical Summary
Large steel trusses cannot be transported and hoisted as a whole during construction, resulting in low precision, poor efficiency, high safety risks, and insufficient structural stability.
BIM modeling was used to guide the segmented assembly, welding, and hoisting construction methods. Through segmented module processing, customized base construction, precise assembly and welding, and standardized hoisting and corrosion protection, combined with total station measurement and digital monitoring, the construction accuracy and safety were ensured.
It has enabled precise, standardized, and efficient construction of steel trusses, improved construction accuracy, efficiency, and safety, extended the service life of the structure, and reduced construction costs.
Smart Images

Figure CN123153554A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of steel structure construction technology, specifically to a method for on-site segmented assembly, welding, and hoisting of large-span steel trusses. It is applicable to the on-site construction of large steel trusses (such as factory roofs, bridges, and large stadiums), especially for large-span, large-size steel truss construction scenarios where overall transportation and hoisting are inconvenient. Background Technology
[0002] Steel trusses, with their excellent mechanical properties, high strength-to-weight ratio, and strong spanning capacity, are widely used in roof structures, crane beams, bridges, and hydraulic gates of industrial and civil buildings. Various towers also often employ space steel trusses composed of planar trusses. However, in the construction of large steel trusses, due to their large overall size and weight, limitations imposed by transportation conditions and on-site construction space prevent the realization of overall fabrication, transportation, and hoisting.
[0003] To address the aforementioned technical challenges, improve the precision, efficiency, and safety of on-site steel truss construction, reduce construction costs, and extend the service life of the structure, this invention proposes a standardized, precise, safe, and efficient on-site segmented assembly, welding, and hoisting construction method for steel trusses. Summary of the Invention
[0004] The purpose of this invention is to provide a construction method for on-site segmented assembly, welding, hoisting, and positioning of steel trusses. By using BIM modeling guidance, standardized site treatment, customized base construction, precise assembly and welding, and standardized hoisting and corrosion protection, this method solves the problems of low precision, poor efficiency, high safety risks, and insufficient structural stability in existing construction methods, thereby achieving standardization, precision, and high efficiency in on-site construction of steel trusses.
[0005] To achieve the above objectives, the present invention adopts the following technical solution: A method for on-site segmented assembly, welding, and hoisting of steel trusses includes: Based on the design drawings of the steel truss, a BIM model of the steel truss is constructed, and the steel truss is divided into several segmented modules that are easy to process, transport and assemble on site. The segmented modules include longitudinal steel pipes, transverse supports and connectors. Export the machining drawings and positioning coordinate data of each component in the segmented module, and submit the disassembled component machining drawings to the manufacturer. The manufacturer then processes each component according to the drawing requirements. After the components are processed, they undergo quality inspection. Once the inspection is passed, they are transported to the construction site. The construction site is first leveled, compacted in layers, and a base layer is laid to form the on-site assembly area. Based on the segmented module positioning coordinates and elevation data exported from the BIM model, on-site measurement and layout were carried out using a total station to determine the specific location and height requirements of each base. Steel sections and steel plates were welded together to create bases of different heights corresponding to different locations. The height of each base must be precisely matched with the design elevation of the longitudinal steel pipe of the truss. The bottom of the base was firmly welded to the laid steel plate base. The placement position of the longitudinal steel pipe was marked on the base to facilitate rapid positioning and installation. The longitudinal steel pipes transported to the site are hoisted onto the corresponding bases, the position and elevation of the longitudinal steel pipes are adjusted, and the longitudinal steel pipes are fixed. Then, according to the connection relationship in the BIM model, the transverse supports and connectors are installed in sequence, the position of each component is adjusted, and the connection gap between the components is ensured to meet the welding requirements. Temporary fasteners are used to fix each component to prevent deformation during the welding process. According to the steel structure welding specifications, the connection between the longitudinal steel pipe and the transverse support and connector is welded. The weld is visually inspected. After the inspection is qualified, a complete truss hoisting component is formed. After each section of assembly welding is completed, it is necessary to check against the BIM model. Only after confirming that the assembly accuracy meets the requirements can the next section be assembled. The assembled truss components were slowly lifted using hoisting equipment and transported to their designed positions along a simulated hoisting path. During the hoisting process, the angle and position of the hoisting equipment were adjusted in real time to bring the components to their designed positions. A total station was used to check the axis, elevation, and levelness of the components to ensure they met design requirements. After adjustment, temporary fasteners were used to securely connect the components to the foundation or the already positioned truss sections, and the hoisting equipment was removed. All truss sections were then hoisted and positioned sequentially. Welding was then performed at the joints between sections to achieve the overall connection of the entire steel truss structure. After welding, all welds and the steel structure surface underwent anti-corrosion treatment.
[0006] In this invention, the modeling software for the BIM model is Autodesk Revit or Tekla.
[0007] In this invention, steel plates are used as the base layer in the on-site assembly area, and the gaps between the steel plates are filled with sealing material. Wooden blocks can be added under the steel plates.
[0008] In this invention, the steel section is a channel steel or an I-beam.
[0009] In this invention, the welding current, voltage, and welding speed are controlled during the welding process, and a segmented back-welding method is adopted.
[0010] In this invention, a truck crane is used as the hoisting equipment.
[0011] In this invention, the construction method is applicable to the on-site construction of large steel structure trusses.
[0012] In this invention, the large steel structure truss is a steel structure truss for factory roofs, bridges, or large stadiums.
[0013] Compared with the prior art, the present invention has the following advantages: 1. Controllable Precision: This invention achieves precise disassembly and positioning of truss structures through BIM modeling. Combined with on-site measurement and layout and customized base design, it ensures that the elevation and position of the longitudinal steel pipes are completely consistent with the design requirements. This effectively avoids assembly accuracy deviations caused by uneven site settlement and poor base compatibility. The assembly accuracy can reach ±3 mm, which greatly improves construction accuracy and solves the problem of difficult accuracy control in traditional construction. It is especially suitable for the construction of steel truss structures with large spans and high precision requirements.
[0014] 2. Efficiency Improvement: This invention uses standardized factory-processed components, which are then assembled and welded in sections on-site, reducing on-site processing workload; the customized base eliminates the need for repeated adjustments to component positions, simplifying the assembly process; the BIM model guides the hoisting path, avoiding blind operations during hoisting, significantly improving construction efficiency, shortening the construction period, reducing project management costs, and simultaneously reducing high-altitude operations and the labor intensity of construction workers.
[0015] 3. Safe and reliable: The site is laid with a steel plate base and a customized base to ensure the stability of the assembly process; temporary supports are set according to the structural dimensions during hoisting to prevent structural instability; the hoisting process and safety protection measures are clearly defined to reduce the safety risks of hoisting operations, solve the problem of large safety hazards in traditional high-altitude bulk welding operations, protect the personal safety of construction personnel and the safety of structural construction, and avoid safety accidents caused by structural instability.
[0016] 4. Long service life: Standardized welding processes ensure weld quality, and comprehensive anti-corrosion treatment measures (compliant with steel structure engineering construction specifications) effectively prevent steel structure corrosion, extend the service life of steel structure trusses, and reduce later maintenance costs. At the same time, reasonable processes are adopted during welding to reduce welding deformation, ensure the stability of the mechanical properties of the structure, and further improve the durability and safety of the structure.
[0017] 5. Wide applicability: It is suitable for on-site construction of various large steel structure trusses, especially for large-span and large-size trusses that are inconvenient to transport or hoist as a whole. The segment size and hoisting scheme can be flexibly adjusted according to the design size and weight of the truss to adapt to different construction scenarios. At the same time, it can be combined with the establishment of a small coordinate system to make full use of the limited construction space and solve the construction problems of complex sites. It has strong practicality and promotion value. Attached Figure Description
[0018] Figure 1 This is a structural schematic diagram of the steel truss of the present invention; Figure 2This is a schematic diagram of the base arrangement on the assembly site of the present invention; Figure 3 This is a schematic diagram of the longitudinal steel pipes positioned on the assembly site according to the present invention; Figure 4 This is a schematic diagram of the longitudinal double-layer truss fixing of the present invention; Figure 5 This is a schematic diagram of the horizontal truss fixing of the present invention; Figure 6 These are photos of the steel truss assembly site. Figure 7 These are photos of the steel truss hoisting, positioning, and welding site. Reference numerals: 1. Steel plate; 2. Base; 3. Longitudinal steel pipe; 4. Lateral support; 5. Connecting parts. Detailed Implementation
[0019] The technical solution of the present invention will be described in detail below with reference to the accompanying drawings and embodiments.
[0020] Example 1 A method for on-site segmented assembly, welding, and hoisting of steel trusses, the construction process of which is as follows: Steel truss modeling → component and part processing → segmented assembly and hoisting scheme design → on-site assembly site preparation → assembly base fabrication → component assembly and positioning → welding and forming → segmented hoisting and positioning → welding fixation and corrosion protection → next step.
[0021] Specifically: Step 1: BIM Modeling and Component Fabrication and Transportation First, such as Figure 1 Based on the design drawings of the steel truss structure, a 3D BIM model is created using modeling software (such as Autodesk Revit or Tekla). The entire truss structure is precisely divided into several modular segments that facilitate fabrication, transportation, and on-site assembly. The dimensions, weight, component composition, and connection relationships of each segment are clearly defined. Simultaneously, fabrication drawings for each component and positioning coordinates for segment assembly are exported, providing precise guidance for subsequent construction. During the disassembly process, the size of the modular segments must be rationally determined considering transportation conditions and on-site hoisting capabilities to avoid transportation difficulties or hoisting risks.
[0022] Subsequently, the disassembled component processing drawings were submitted to a professional manufacturer. The manufacturer processed each steel structure part (including longitudinal steel pipes, transverse supports, connectors, etc.) according to the drawing requirements. After processing, quality inspection was carried out to ensure that the component dimensions, materials, and welding quality met the design standards. After passing the inspection, all parts were transported to the construction site in batches using transportation equipment. During transportation, the components were fixed and protected to prevent deformation and corrosion, ensuring that the components remained intact.
[0023] Step 2: On-site assembly site preparation: Within the hoisting range of the construction site, select a flat, open area with sufficient load-bearing capacity as the assembly site. After assembly, hoisting equipment can be used to directly hoist the equipment into place.
[0024] First, the site is leveled and debris and obstacles are removed. The soil is then compacted in layers using compaction equipment to ensure uniform bearing capacity and prevent uneven settlement during subsequent assembly.
[0025] After the site is leveled and compacted, steel plates are laid as the base layer throughout the assembly area. The steel plates must be laid flat and tightly, with gaps filled with sealant to prevent rainwater infiltration and soil settlement. This also avoids direct contact between components and the ground during assembly, preventing wear or contamination. To further ensure assembly accuracy, wooden blocks can be added under the steel plates to enhance the stability of the base layer and facilitate subsequent site cleanup and steel plate recycling. Settlement observation points can be set up around the site to monitor site settlement in real time and take timely adjustment measures.
[0026] Step 3: On-site segmented assembly and welding: Foundation fabrication: Based on the segmented module positioning coordinates and elevation data exported from the BIM model, on-site measurement and layout are conducted using a total station to determine the specific location and height requirements of each foundation. For example... Figure 2 Customized bases 2 of different heights and corresponding positions are made by welding structural steel (such as channel steel and I-beams) and steel plates. The height of each base 2 must be precisely matched with the design elevation of the longitudinal steel pipe 3 of the truss. The bottom of the base is firmly welded to the base layer of the laid steel plate 1 to ensure the stability and load-bearing capacity of the base and prevent the base from shifting or settling during the assembly process. A fine-adjustment device can be set on the top of the base to facilitate precise adjustment of the elevation position of the longitudinal steel pipe to ensure that it is consistent with the actual truss structure position elevation. At the same time, the placement position of the longitudinal steel pipe 3 is marked on the base 2 to facilitate quick positioning and installation.
[0027] Component Assembly: The longitudinal steel pipe 3 transported to the site is hoisted onto the corresponding base 2. The position and elevation of the longitudinal steel pipe 3 are adjusted. Real-time monitoring with a total station ensures that the axis and elevation of the longitudinal steel pipe are completely consistent with the design position in the BIM model. The longitudinal steel pipe 3 is then fixed. Subsequently, according to the connection relationship in the BIM model, the transverse supports 4 and other connecting parts 5 are installed sequentially. The position of each component is adjusted to ensure that the connection gap between components meets the welding requirements. Temporary fasteners are used to fix each component to prevent deformation during welding. Figure 3-5 .
[0028] Welding operations: Following steel structure welding specifications, weld the connections between longitudinal steel pipes and transverse supports and connectors. During welding, control the welding current, voltage, and welding speed, employing reasonable welding techniques such as segmented back-welding to reduce welding deformation and ensure weld quality. Welds must be full, free of slag inclusions, porosity, cracks, and other defects. After welding, promptly clean the weld surface of slag and spatter, and conduct a visual inspection. Once the inspection is passed, a complete truss hoisting component is formed. If necessary, non-destructive testing can be performed on the welded areas to ensure welding quality meets standards. After each segment of assembly welding is completed, it must be checked against the BIM model. Only after confirming that the assembly accuracy meets the requirements can the next segment be assembled. Figure 6 .
[0029] Step 4: Segmented hoisting and positioning and subsequent processing: Lifting preparation: Select appropriate lifting equipment (such as truck crane) based on the weight and size of each lifting component, check the performance of the lifting equipment to ensure normal operation; at the same time, simulate the lifting path according to the BIM model, clear obstacles in the lifting area, set up safety warning zones, and arrange professional personnel to conduct on-site command to ensure the safety of the lifting operation.
[0030] Segmented hoisting: The assembled truss components are slowly lifted using cranes and transported to their designed positions along a simulated hoisting path. During hoisting, the angle and position of the cranes are adjusted in real time to ensure smooth movement and prevent collisions with other components or obstacles. If the truss segments are too large or too heavy, structural instability may occur during hoisting. Temporary supports (made of steel profiles and securely connected to the foundation or the already positioned truss structure) can be erected at the placement location. The location and number of temporary supports are determined based on BIM model simulation calculations to ensure they can effectively bear the weight of the hoisted components and prevent structural deformation or falling. A multi-point coordinated lifting method can be used during hoisting, with a synchronous controller to ensure smooth operation. The hoisting is paused after a certain height for inspection and timely correction.
[0031] Precise positioning: Adjust the hoisting components to the design position, and use a total station to check the axis, elevation and level of the hoisting components to ensure that they are consistent with the design requirements. After the adjustment is completed, use temporary fasteners to firmly connect the hoisting components to the foundation or the already positioned truss sections, and remove the lifting equipment.
[0032] Welding and corrosion protection: Following the steps above, all truss sections are hoisted and positioned in sequence. Then, the joints between each section are welded. The welding process is consistent with the welding requirements in step 3 to ensure the quality of the welds at the joints and achieve the overall connection of the entire steel structure truss. After welding, all welds and steel structure surfaces should be treated with anti-corrosion coating. First, remove rust, oil, dust, and other debris from the steel structure surface. Use sandblasting to remove rust and achieve the required anti-corrosion coating. Then, apply the anti-corrosion coating (high-pressure airless spraying is recommended for high efficiency and good coating results). During the coating process, control the ambient temperature (ideally 5℃~38℃) and relative humidity (not exceeding 85%). Avoid construction in rain, fog, snow, strong winds, and strong sunlight to ensure a uniform and firm anti-corrosion coating. Take protective measures within 4 hours of coating to prevent rain and dust intrusion, extending the service life of the steel truss. Damage to the coating caused during transportation and installation requires touch-up coating. Touch-up coating requirements should be consistent with the original coating specifications. Leave uncoated areas on both sides of the weld at the construction site; touch-up coating should be applied after welding is completed. Figure 7 .
[0033] This invention can further integrate Internet of Things (IoT), laser scanning, and big data analytics technologies on the basis of existing BIM modeling to achieve a digital upgrade of the entire construction process. During the component processing stage, RFID chips are installed on key components to record information such as component processing parameters and quality inspection reports. During transportation, GPS positioning and temperature and humidity sensors are used to monitor the component transportation status in real time, preventing deformation and corrosion of components due to environmental changes and ensuring traceability of the component transportation process.
[0034] During the on-site construction phase, laser scanning equipment is used to perform 3D scanning of the assembled truss segments. The scanned data is compared with the BIM model in real time, automatically identifying assembly deviations. When deviations exceed the allowable range, timely warnings are issued, eliminating the need for repeated manual verification and significantly improving the efficiency of assembly accuracy control. Simultaneously, the operational data of total stations and lifting equipment are integrated into the BIM platform to achieve real-time visual monitoring of the hoisting process. Big data analysis optimizes parameters such as hoisting speed and angle, preventing violations during hoisting and further reducing safety risks. Furthermore, digital twin technology can be introduced to construct a digital twin model of the construction site, simulating the truss stress under different construction conditions. This allows for the prediction of potential structural instability and settlement issues during construction, enabling the development of targeted preventative measures to ensure construction safety.
[0035] This invention can also be specifically optimized for complex construction scenarios such as high-altitude, mountainous, and confined spaces, expanding the applicability of the method. For high-altitude assembly scenarios, a mobile aerial work platform is used to replace traditional scaffolding. The work platform is linked with the BIM model to accurately locate the work position, reducing the amount of climbing required for high-altitude workers. At the same time, protective railings and emergency braking devices are installed on the platform to improve the safety of high-altitude operations. For construction sites with uneven terrain such as mountains, graded sand and gravel are used for layered backfilling and compaction during the site preparation stage, replacing the traditional steel plate base, enhancing the site's resistance to settlement. In addition, according to the characteristics of mountainous terrain, a customized base with adjustable angle is used to adapt to the site requirements of different slopes, ensuring assembly accuracy.
[0036] For construction in confined spaces, the truss segmentation scheme is optimized by adopting a miniaturized and modular approach to reduce the size and weight of individual truss segments. Small lifting equipment (such as small truck cranes and electric hoists) is used for hoisting. Simultaneously, a BIM model is used to simulate the hoisting path within confined spaces, optimizing the arrangement of lifting points. Horizontal translation and segmented docking methods are employed to avoid collisions with surrounding obstacles during hoisting. For construction in complex outdoor environments such as those spanning rivers or seas, more weather-resistant anti-corrosion coatings (such as fluorocarbon coatings) are used during the anti-corrosion treatment stage to enhance the steel structure's corrosion and UV resistance. During hoisting, environmental parameters such as wind speed and direction are monitored in real time; hoisting operations are immediately stopped when the wind speed exceeds a safe threshold to ensure construction safety. In terms of welding technology, this invention introduces automated welding equipment (such as robotic welding and submerged arc welding) to replace traditional manual welding. Automated equipment can precisely control welding current, voltage, welding speed, and weld width based on welding parameters exported from the BIM model, reducing human error, improving weld quality consistency, and simultaneously reducing the labor intensity of welders and the amount of high-altitude welding work. For welding complex nodes, pulse welding process is adopted to reduce welding deformation and ensure the mechanical properties of the node connection. After welding, non-destructive testing technologies such as ultrasonic and radiographic testing are used to conduct a comprehensive inspection of the weld to ensure that there are no internal defects in the weld. The inspection data is uploaded to the BIM platform in real time to realize full traceability of welding quality.
[0037] In terms of corrosion protection, this invention optimizes the rust removal and coating processes, replacing traditional sandblasting with shot blasting. Shot blasting is more efficient and produces a more uniform rust removal effect, thoroughly removing rust, scale, and oil from the steel structure surface and improving the adhesion of the anti-corrosion coating. During the coating stage, electrostatic spraying is used to ensure uniform coverage of the anti-corrosion coating on the steel structure surface, reducing paint waste. A coating thickness gauge is also introduced to monitor the coating thickness in real time, ensuring it meets design requirements. Furthermore, for highly corrosive environments such as marine and chemical plants, an additional anti-corrosion protective layer (such as a fiberglass protective layer) is added outside the anti-corrosion coating to further enhance the steel structure's corrosion resistance and extend the truss's service life.
[0038] This invention incorporates green construction concepts to optimize the construction process for environmental protection and energy conservation, reducing energy consumption and environmental pollution. During component processing, environmentally friendly steel and welding materials are used to reduce the emission of harmful gases during welding. Waste steel and welding slag generated during processing are also classified and recycled to achieve resource reuse. During on-site construction, energy-efficient lifting and welding equipment are used to reduce electricity consumption. Noise and dust generated during construction are also controlled; noise reduction equipment is used to reduce welding noise, and methods such as water spraying and enclosed operations are employed to reduce dust pollution and avoid impacting the surrounding environment.
[0039] During the site clearing phase, materials such as laid steel plates and wooden blocks are recycled to reduce construction waste. In the anti-corrosion treatment phase, environmentally friendly anti-corrosion coatings are used to reduce the content of harmful substances in the coatings, avoiding pollution of soil and water during coating application. Waste paint, thinner, and other waste generated during the coating process are centrally treated to meet environmental emission requirements. Furthermore, by optimizing the construction process, shortening the construction period, and reducing energy consumption and environmental impact during construction, a combination of green and efficient construction is achieved.
[0040] All aspects not described in detail in this invention can be covered using conventional technical knowledge in the field.
[0041] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to the embodiments, those skilled in the art should understand that modifications or equivalent substitutions to the technical solutions of the present invention do not depart from the spirit and scope of the technical solutions of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.
Claims
1. A method for on-site segmented assembly, welding, and hoisting of steel trusses, comprising: Based on the design drawings of the steel truss, a BIM model of the steel truss is constructed, and the steel truss is divided into several segmented modules that are easy to process, transport and assemble on site. The segmented modules include longitudinal steel pipes, transverse supports and connectors. Export the machining drawings and positioning coordinate data of each component in the segmented module, and submit the disassembled component machining drawings to the manufacturer. The manufacturer then processes each component according to the drawing requirements. After the components are processed, they undergo quality inspection. Once the inspection is passed, they are transported to the construction site. The construction site is first leveled, compacted in layers, and a base layer is laid to form the on-site assembly area. Based on the segmented module positioning coordinates and elevation data exported from the BIM model, on-site measurement and layout were carried out using a total station to determine the specific location and height requirements of each base. Steel sections and steel plates were welded together to create bases of different heights corresponding to different locations. The height of each base must be precisely matched with the design elevation of the longitudinal steel pipe of the truss. The bottom of the base was firmly welded to the laid steel plate base. The placement position of the longitudinal steel pipe was marked on the base to facilitate rapid positioning and installation. The longitudinal steel pipes transported to the site are hoisted onto the corresponding bases, the position and elevation of the longitudinal steel pipes are adjusted, and the longitudinal steel pipes are fixed. Then, according to the connection relationship in the BIM model, the transverse supports and connectors are installed in sequence, the position of each component is adjusted, and the connection gap between the components is ensured to meet the welding requirements. Temporary fasteners are used to fix each component to prevent deformation during the welding process. According to the steel structure welding specifications, the connection between the longitudinal steel pipe and the transverse support and connector is welded. The weld is visually inspected. After the inspection is qualified, a complete truss hoisting component is formed. After each section of assembly welding is completed, it is necessary to check against the BIM model. Only after confirming that the assembly accuracy meets the requirements can the next section be assembled. The assembled truss components were slowly lifted using hoisting equipment and transported to their designed positions along a simulated hoisting path. During the hoisting process, the angle and position of the hoisting equipment were adjusted in real time to bring the components to their designed positions. A total station was used to check the axis, elevation, and levelness of the components to ensure they met design requirements. After adjustment, temporary fasteners were used to securely connect the components to the foundation or the already positioned truss sections, and the hoisting equipment was removed. All truss sections were then hoisted and positioned sequentially. Welding was then performed at the joints between sections to achieve the overall connection of the entire steel truss structure. After welding, all welds and the steel structure surface underwent anti-corrosion treatment.
2. The steel structural truss field sectional assembly and welding hoisting construction method according to claim 1, characterized in that, The BIM model is created using Autodesk Revit or Tekla software.
3. The steel structural truss field sectional assembly and welding hoisting construction method according to claim 1, characterized in that, In the on-site assembly area, steel plates are used as the base layer, and the gaps between the steel plates are filled with sealing material. Wooden blocks can be added under the steel plates.
4. The steel structural truss field sectional assembly and welding hoisting construction method according to claim 1, characterized in that, The structural steel is either channel steel or I-beam steel.
5. The steel structural truss field sectionalized assembly-welding and hoisting construction method according to claim 1, characterized in that, During the welding process, the welding current, voltage, and welding speed are controlled, and a segmented back-welding method is adopted.
6. The steel structural truss field sectionalized assembly-welding and hoisting construction method according to claim 1, characterized in that, A truck crane was used for hoisting.
7. The steel structural truss field sectionalized assembly-welding and hoisting construction method according to claim 1, characterized in that, The construction method described herein is applicable to the on-site construction of large steel structure trusses.
8. The steel structural truss field sectional assembly and welding hoisting construction method according to claim 7, characterized in that, The large steel structure truss is the steel structure truss for factory roofs, bridges, or large stadiums.