A device for testing hydrate blockage of gas well in the middle, working method and gas well

By using a device with an inhibitor storage chamber, a transition chamber, and an inflation chamber in gas well testing, the automatic release of the inhibitor is controlled by pressure differential, which solves the safety hazards caused by hydrate freezing in existing technologies and improves the efficiency and safety of gas well testing.

CN123153718APending Publication Date: 2026-11-24PETROCHINA CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510658281.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-05-21
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

During gas well testing, existing waterproofing and sealing measures require a long waiting time, which can cause instruments to become stuck inside the well, posing a safety hazard.

Method used

A device for preventing hydrate blockage in gas wells during testing is used, comprising an inhibitor storage chamber, a transition chamber, and an inflation chamber. The inhibitor control valve is automatically controlled by differential pressure to ensure that the inhibitor is automatically released into the gas wellbore during testing and wrapped with steel wire to prevent hydrate formation.

Benefits of technology

This technology enables the prevention of hydrate formation without waiting time during testing, reducing the risk of instrument damage and well falls, and improving testing efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123153718A_ABST
    Figure CN123153718A_ABST
Patent Text Reader

Abstract

The application belongs to the field of oil and gas production, and discloses a device for preventing hydrate freezing in a gas well during testing, a working method and a gas well. The device comprises, from bottom to top, an inhibitor storage cavity, a transition cavity and an inflation chamber. An inhibitor control valve is arranged at the bottom of the inflation chamber. In a normal state, the pressure of the inhibitor storage cavity is less than that of the inflation chamber, so that the inhibitor control valve is in a normally closed state. During testing, the wellbore pressure enters the transition cavity from the passage between the transition cavity and the wellbore of the gas well due to the opening of the testing valve. The sum of the upward pressure of the inhibitor storage cavity and the wellbore pressure is greater than the downward pressure of the inflation chamber, so that the inhibitor control valve is automatically opened under the action of the pressure difference and kept in a normally open state. The inhibitor flows into the wellbore through the transition cavity, thereby automatically contacting the steel wire, ensuring that the steel wire is always surrounded by the inhibitor during testing, effectively preventing hydrate formation and greatly reducing the risk of hydrate formation during gas well testing.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of oilfield production and gas extraction, specifically relating to the field of energy storage system functional testing, and particularly to a device, gas well, and method for testing the prevention of hydrate blockage in gas wells. Background Technology

[0002] Natural gas hydrates are crystalline complexes formed by the combination of hydrocarbon molecules and water, resembling ice and snow, and are generally easily formed under high pressure and low temperature conditions. During gas field development, gas wells require numerous gradient and production profile tests. During these tests, a wireline must pass through the sealing ring of the packing box at the wellhead blowout preventer (BOP) and then be used to lift the instrument. During this lifting process, the wireline continuously rubs against the sealing ring, inevitably causing some gas leakage. The hydrocarbon molecules in this leaked gas combine with free water molecules to form hydrates, especially in winter when low temperatures further promote hydrate formation. Once hydrates form, they increase the frictional resistance between the wireline and the sealing ring of the BOP packing box, causing the wireline to jam and preventing further lifting, posing a significant safety hazard. Improper operation could also cause the instrument to fall into the well.

[0003] There are generally two methods to prevent hydrate blockage: The first is to install downhole nozzles to reduce wellhead pressure, which can effectively prevent hydrate formation under low pressure. However, this method makes testing difficult because the instruments cannot pass through after the nozzles are added to the tubing, hindering the recording and acquisition of dynamic monitoring data. The second method is to add inhibitors after hydrate blockage, so that water molecules dissolve in the inhibitors and destroy the hydrate structure. Inhibitors are generally of two types: organic and inorganic. Organic inhibitors include methanol and glycol compounds, while inorganic inhibitors include sodium chloride, calcium chloride, and magnesium chloride. In mining operations, the organic inhibitor methanol is generally used.

[0004] During testing, hydrate blockage issues occurred, and two methods were typically used on-site to resolve them: The first method involved waiting for the temperature to rise and the hydrate structure to break down before retrieving the tool string. However, this prolonged waiting period left the instrument in the well, increasing the risk of damage. Furthermore, if the temperature did not reach a sufficient level after rising, the hydrate structure might not be broken down, leading to continued blockage. The second method involved injecting an inhibitor into the blowout preventer box after blockage and manually pressurizing it to dissolve water molecules and disrupt the hydrate structure. While this method could resolve the blockage, the excessive waiting time required to retrieve the wireline and instrument increased the risk of instrument damage and potential fall into the well.

[0005] Therefore, it is evident that during the testing of gas wells, the existing waterproofing and freezing measures require a long waiting time before the steel wire can be pulled out, resulting in the instrument remaining in the well for too long, which poses a significant safety hazard. Summary of the Invention

[0006] This invention provides a device, well, and method for preventing hydrate blockage in gas wells during testing. It addresses the technical problem that existing hydrate blockage prevention measures require a long waiting time before the steel wire can be pulled, resulting in the instrument remaining in the well for an extended period and posing significant safety hazards. This device eliminates this waiting time, allowing the steel wire to be pulled at any time during testing, thus ensuring instrument safety.

[0007] To achieve the above objectives, the present invention employs the following technical content: A device for preventing hydrate blockage in gas wells during testing includes an inhibitor storage chamber, a transition chamber, and an air filling chamber arranged sequentially from bottom to top. The inhibitor storage cavity is used to store inhibitors; The transition cavity is connected to the inhibitor storage cavity and is also used to connect to the gas wellbore; the transition cavity is used to transfer the inhibitor released from the inhibitor storage cavity into the gas wellbore during the test, so that the inhibitor is wrapped around the outside of the steel wire; the steel wire is located inside the gas wellbore. The bottom of the inflation chamber is connected to a vertically movable inhibitor control valve. The inhibitor control valve can close the channel between the transition chamber and the inhibitor storage chamber; and can automatically open under pressure difference and remain open to allow the transition chamber and the inhibitor storage chamber to communicate. The pressure difference is obtained by the combined effect of the pressure in the inhibitor storage chamber, the wellbore pressure, and the pressure in the inflation chamber; wherein the sum of the pressure in the inhibitor storage chamber and the wellbore pressure is greater than the pressure in the inflation chamber, and the pressure in the inhibitor storage chamber is less than the pressure in the inflation chamber.

[0008] Furthermore, the inflation chamber is connected to the inhibitor control valve via a sealing package, and the inflation chamber is in communication with the sealing package; the sealing package can drive the inhibitor control valve to move vertically under the action of external force.

[0009] Furthermore, an inhibitor injection valve is provided at the bottom of the inhibitor storage cavity for injecting inhibitors into the inhibitor storage cavity.

[0010] Furthermore, a pressure valve is provided on the top of the inflation chamber for pressurizing the inflation chamber.

[0011] Furthermore, under normal pressure, the pressure in the inflation chamber is greater than the pressure in the inhibitor storage chamber.

[0012] Furthermore, during the test, the wellbore pressure enters the transition chamber through the channel between the transition chamber and the gas wellbore.

[0013] A method for operating a device for preventing hydrate blockage in gas wells during testing, based on the aforementioned device for preventing hydrate blockage in gas wells during testing, comprising: Install the device for preventing gas well hydrate freezing during the test; Under normal conditions, the inhibitor control valve is normally closed under the combined action of the pressure in the inflation chamber and the pressure in the inhibitor storage chamber, thus blocking the passage between the transition chamber and the inhibitor storage chamber. During the test, under the combined action of the pressure in the inhibitor storage chamber, the wellbore pressure, and the gas filling chamber, the inhibitor control valve automatically opens and remains open, connecting the transition chamber to the inhibitor storage chamber; the inhibitor is released from the inhibitor storage chamber and transferred through the transition chamber into the gas wellbore, so that the inhibitor is wrapped around the outside of the steel wire; the steel wire is inserted into the gas wellbore. Among them, the sum of the pressure in the inhibitor storage chamber and the wellbore pressure is greater than the pressure in the air filling chamber; the pressure in the inhibitor storage chamber is less than the pressure in the air filling chamber.

[0014] Furthermore, the installation process of the device for preventing gas well hydrate freezing during the test includes: The pressure of the inhibitor storage chamber is determined based on the pre-measured wellbore pressure, and inhibitor is injected into the inhibitor storage chamber according to the pressure of the inhibitor storage chamber. The pressure of the inflation chamber is determined by combining the pre-measured wellbore pressure and the pressure of the inhibitor storage chamber, and the inflation chamber is pressurized according to the pressure of the inflation chamber.

[0015] Furthermore, based on the pressure of the inhibitor storage chamber, the cross-sectional area of ​​the inhibitor control valve, the cross-sectional area of ​​the packing, the pressure of the inflation chamber, and the wellbore pressure, the pressure of the inflation chamber is adjusted using the following formula: P 抑 ×A y / A b <P d b In the formula, P 抑 Indicates the pressure in the inhibitor storage chamber; A y Indicates the cross-sectional area of ​​the inhibitor control valve; A b P represents the cross-sectional area of ​​the packet; d F represents the pressure in the inflation chamber. 测 This indicates the wellbore pressure.

[0016] A gas well includes a wellbore, a blowout preventer, and a device for preventing gas well hydrate freezing during the above-mentioned test; The device for preventing gas well hydrate freezing during the test is located below the blowout preventer box.

[0017] Compared with the prior art, the present invention has the following beneficial effects: This invention provides a device for preventing hydrate blockage in gas wells during testing. The device includes an inhibitor storage chamber, a transition chamber, and an inflation chamber arranged from bottom to top. An inhibitor control valve is located at the bottom of the inflation chamber. Under normal conditions, the pressure in the inhibitor storage chamber is lower than the pressure in the inflation chamber, keeping the inhibitor control valve normally closed. During testing, the test valve opens, allowing wellbore pressure to enter the transition chamber through the channel between the transition chamber and the gas wellbore. The combined pressure of the upward-facing inhibitor storage chamber and the wellbore pressure is greater than the downward-facing inflation chamber pressure, causing the inhibitor control valve to automatically open under the pressure difference and remain normally open. The inhibitor flows into the wellbore through the transition chamber, automatically bringing the inhibitor into contact with the steel wire. This ensures that the steel wire is constantly surrounded by inhibitor during testing, effectively preventing hydrate formation and significantly reducing the risk of hydrate formation during gas well testing, thus preventing hydrate blockage. It also reduces the risks associated with cable operations and improves testing efficiency.

[0018] Preferably, in this invention, the connection between the encapsulation and the inhibitor control valve allows for convenient control of the vertical movement of the inhibitor control valve under external force, thereby achieving precise control of inhibitor release; this design increases the flexibility and operability of the device.

[0019] Preferably, in this invention, the inhibitor injection valve allows for convenient injection of inhibitors into the inhibitor storage chamber, enabling the replenishment and replacement of inhibitors without disassembling the device, thus improving the ease of device maintenance.

[0020] Preferably, in this invention, the pressure valve allows for convenient pressurization of the inflation chamber, thereby adjusting the pressure within the chamber to meet different testing requirements. This design enhances the adaptability and flexibility of the device.

[0021] Preferably, in this invention, the pressure in the inflation chamber is greater than the pressure in the inhibitor storage chamber under normal pressure. This helps to ensure that the inhibitor control valve is normally closed under normal conditions, preventing the inhibitor from being released into the transition chamber unintentionally.

[0022] Preferably, in this invention, during the testing process, the wellbore pressure enters the transition chamber through the channel between the transition chamber and the gas wellbore. This helps ensure that the inhibitor can be properly released into the gas wellbore, thereby preventing hydrate freezing and blockage.

[0023] This invention also provides a method for operating a device to prevent hydrate blockage in gas wells during testing, based on the aforementioned device for preventing hydrate blockage in gas wells during testing. This method implements an adaptive mechanism. After the device is installed, under normal conditions (i.e., at atmospheric pressure), the inhibitor control valve remains normally closed. During testing, under the combined action of the pressure in the inhibitor storage chamber, the wellbore pressure, and the gas filling chamber, the inhibitor control valve automatically opens and remains normally open. The inhibitor is released from the inhibitor storage chamber, transitions through the transition chamber into the gas wellbore, and then the inhibitor wraps around the steel wire to prevent hydrate formation, greatly reducing the risk of hydrate formation during gas well testing and improving the safety of cable operations.

[0024] Preferably, in this invention, the pressure of the inhibitor storage chamber is determined based on the wellbore pressure, and then the two are combined to determine the pressure of the inflation chamber. This operation ensures the reliability of the inhibitor release during the test and improves the stability and reliability of the entire device.

[0025] Preferably, the present invention fully considers factors such as the pressure of the inhibitor storage chamber, the cross-sectional area of ​​the inhibitor control valve and the sealing package, and the wellbore pressure, thus possessing high accuracy and practicality.

[0026] The present invention also provides a gas well, including a device for preventing gas well hydrate freezing during the above-mentioned test. The device is located below the blowout preventer box, which helps to prevent gas well hydrate freezing during the test, thereby improving test efficiency and safety. This design tightly integrates the device with the gas well, enabling the device to better serve the testing and production of the gas well, thus improving test efficiency and the safety of logging operations. Attached Figure Description

[0027] Figure 1 A schematic diagram of a device for preventing gas well hydrate freezing during testing, provided in an embodiment of the present invention; Figure 2 A schematic diagram of a device for preventing gas well hydrate freezing during testing, provided in an embodiment of the present invention, under normal conditions; Figure 3 This is a schematic diagram of a device for preventing gas well hydrate freezing during testing, provided as an embodiment of the present invention.

[0028] Figure label: 1. Inhibitor storage chamber; 2. Transition chamber; 3. Inflation chamber; 4. Sealing package; 5. Inhibitor control valve; 6. Inhibitor injection valve; 7. Pressure relief valve. Detailed Implementation

[0029] To make the technical problems solved by the present invention, the technical solutions, and the beneficial effects clearer, the following specific embodiments provide a further detailed description of the present invention. It should be understood that the specific embodiments described herein are merely illustrative and are not intended to limit the scope of the invention.

[0030] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. The components of the embodiments of the present invention described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.

[0031] Therefore, the following detailed description of the embodiments of the invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to illustrate selected embodiments of the invention. All other embodiments obtained by those skilled in the art based on the embodiments of the invention without inventive effort are within the scope of protection of the invention.

[0032] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.

[0033] In the description of the embodiments of the present invention, it should be noted that if terms such as "upper," "lower," "horizontal," or "inner" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship commonly used when the product of the invention is in use, they are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the present invention. Furthermore, terms such as "first" and "second" are only used to distinguish descriptions and should not be construed as indicating or implying relative importance.

[0034] Furthermore, the use of the term "horizontal" does not imply that the component must be absolutely horizontal, but rather that it can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal than "vertical," and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0035] In the description of the embodiments of the present invention, it should also be noted that, unless otherwise explicitly specified and limited, the terms "set," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in the present invention according to the specific circumstances.

[0036] Example 1 As mentioned in the background technology, hydrate blockage during testing is generally resolved in two ways on-site. The first is to wait for the temperature to rise and the hydrate structure to break down before raising the tool string. However, this involves the instrument remaining in the well for an extended period, which can easily damage it. Furthermore, if the temperature doesn't reach a certain level after the blockage, the hydrate structure may not be destroyed. The second method involves injecting inhibitors into the blowout preventer (BOP) box and manually pressurizing it. This method involves a long time to raise the tool string and requires continuous waiting at the wellhead. While it solves the problem, it carries significant risks. For example, Chinese patent CN219061598U provides a natural gas well production control device, primarily used to eliminate natural gas hydrates in pipelines. It controls the injection of hydrate inhibitors by collecting pressure data and combining a control unit, actuator, and alcohol injection unit. However, this device mainly addresses existing hydrates and still poses a safety hazard due to increased friction at the contact point between the steel wire and the BOP top packing box seal.

[0037] It is evident that traditional methods for preventing hydrate blockage involve treating and removing hydrates after they have formed. During testing, treating or destroying hydrates takes a significant amount of time. In this process, the tool string consisting of the steel wire and logging instruments remains inside the wellbore, posing a constant risk of damaging the instruments or even causing them to fall into the well.

[0038] To address the aforementioned problems, this invention provides a device for preventing hydrate blockage in gas wells during testing. This device solves the problem of the nozzle packing box becoming stuck due to hydrate blockage during testing, preventing the tool string from being lifted. It effectively avoids the formation of hydrate at the contact point between the blowout preventer box seal and the wire. Consequently, the wire can be lifted without obstruction throughout the entire testing process, improving the efficiency and safety of gas well testing.

[0039] The basic idea behind the device designed for preventing hydrate freezing in gas wells in this test is as follows: The device is installed below the blowout preventer (BOP) box of the gas well. The device is filled with inhibitor, and the inhibitor control valve is closed before the test. During the test, the wellbore pressure is transmitted to the device, causing the inhibitor control valve to automatically open based on the pressure difference and remain open. The inhibitor flows into the wellbore, and the steel wire is wrapped with the inhibitor, effectively preventing hydrate formation and avoiding hydrate buildup at the contact point between the BOP seal and the steel wire. It can be seen that the device for preventing hydrate freezing in gas wells in this test adopts a proactive prevention approach and achieves an adaptive mechanism through pressure difference control. That is, when the test begins, the tool string (including the steel wire) needs to be... The logging device (including the wire and instrument) is inserted into the well. The wellbore is opened, and under air pressure, upward wellbore pressure enters the device. Combined with the upward pressure of the inhibitor, the inhibitor control valve is opened. Because the pressure on the inhibitor side is greater than the wellbore pressure, the inhibitor flows out, wrapping around the wire and ultimately preventing the formation of hydrates around the wire. This facilitates subsequent logging operations such as pulling the wire. The hydrate-freezing method provided in this embodiment adopts a preventative approach. Compared to the traditional method of freezing first and then treating, it significantly saves time in removing hydrates, improves the efficiency of the entire logging operation, and avoids prolonged retention of the logging instrument in the gas wellbore, greatly reducing the risk of instrument damage and falling into the well, and enhancing the safety of logging operations.

[0040] Based on the above design concept, this embodiment provides a device for preventing gas well hydrate freezing during testing, including an inhibitor storage chamber 1, a transition chamber 2, and an air filling chamber 3 arranged sequentially from bottom to top; the inhibitor storage chamber 1 is used to store inhibitors; the transition chamber 2 is connected to the inhibitor storage chamber 1 and is used to connect to the gas well casing; the transition chamber 2 is used to transfer the inhibitor released from the inhibitor storage chamber 1 into the gas well casing during the test, so that the inhibitor is wrapped around the outside of the steel wire; the steel wire is inserted into the gas well casing; The bottom of the inflation chamber 3 is connected to a vertically movable inhibitor control valve 5. The inhibitor control valve 5 can close the channel between the transition chamber 2 and the inhibitor storage chamber 1; and can automatically open under the action of pressure difference and remain in the normally open state so that the transition chamber 2 and the inhibitor storage chamber 1 are connected. The pressure difference is obtained by the combined effect of the pressure in the inhibitor storage chamber 1, the wellbore pressure, and the pressure in the air chamber 3; wherein the sum of the pressure in the inhibitor storage chamber 1 and the wellbore pressure is greater than the pressure in the air chamber 3, and the pressure in the inhibitor storage chamber 1 is less than the pressure in the air chamber 3.

[0041] The device for preventing gas well hydrate freezing and blockage provided in this embodiment is further described below with reference to the accompanying drawings: like Figure 1As shown, this embodiment provides a device for preventing gas well hydrate freezing during testing, comprising: an inhibitor storage chamber 1, a transition chamber 2, and an inflation chamber 3 arranged sequentially from bottom to top; the inhibitor storage chamber 1 is used to store inhibitors, and in this embodiment, methanol organic inhibitors are preferably used, which can effectively inhibit the formation of hydrates; the transition chamber 2 is located in the middle of the device and is connected to both the gas well casing and the inhibitor storage chamber 1; under normal pressure, the transition chamber 2 is at normal gas pressure, but when the gas well is opened, the gas well casing pressure will be higher than the original normal gas pressure; the function of the transition chamber 2 is to: during the test, transfer the inhibitor released from the inhibitor storage chamber 1 into the gas well casing, contact the steel wire, and wrap the steel wire, thereby preventing the formation of hydrates; the steel wire is located inside the gas well casing, and a through hole for releasing the inhibitor is opened in the middle of the transition chamber 2, which then contacts the steel wire and forms a circumference and wrapping; another function of the transition chamber 2 is to provide vertical movement space for the inhibitor control valve 5 located at the bottom of the inflation chamber 3; the inhibitor control valve 5 is connected to the inflation chamber through a sealing package 4. At the bottom, the sealing package 4 can drive the inhibitor control valve 5 to move vertically under external force. When gas is injected into the filling chamber 3 for pressurization, the pressure in the filling chamber 3 becomes greater than the pressure in the inhibitor storage chamber 1. Under normal pressure, the sealing package 4 drives the inhibitor control valve 5 to move downward, causing the inhibitor control valve 5 to close and tightly seal the channel between the inhibitor storage chamber 1 and the transition chamber 2. This ensures that the inhibitor will not leak from the inhibitor storage chamber 1 into the transition chamber 2. When the gas well is opened, the gas pressure causes the wellbore pressure to propagate into the transition chamber 2, generating upward pressure on the sealing package 4. Combined with the upward pressure in the inhibitor storage chamber 1, the combined pressure is greater than the downward pressure generated by the filling chamber 3 on the sealing package 4, causing the resultant force of the sealing package 4 to move upward. At this time, it drives the inhibitor control valve 5 to move upward, keeping the inhibitor control valve 5 open. Thus, the inhibitor is released from the inhibitor storage chamber 1 into the transition chamber 2. Since the pressure in the inhibitor storage chamber 1 is greater than the wellbore pressure, the inhibitor flows into the wellbore through the transition chamber 2, achieving the wrapping and surrounding of the steel wire by the inhibitor, effectively preventing the formation of hydrates.

[0042] In this embodiment, the device for preventing hydrate freezing in the gas well during testing is fixed below the blowout preventer (BOP) box of the gas well; this prevents hydrate formation at the contact point between the BOP sealing ring and the steel wire; the gas well is annular cylindrical in shape, with a steel wire hole in its center to facilitate the passage of the steel wire; combined with Figure 1 As shown, a channel communicating with the gas well shaft is provided on one side of the transition cavity 2. Figures 1 to 3 In the middle, the gap on the left is the channel connecting the transition chamber 2 and the gas well casing. The end of the channel that connects to the well casing is the location of the steel wire, thus enabling the inhibitor to come into contact with the steel wire as soon as it flows out of the channel, effectively preventing the formation of hydrates at the first moment.

[0043] In this embodiment, a pressure valve 7 is provided on the top of the inflation chamber 3 to pressurize the inflation chamber 3, wherein the pressure is determined by calculation.

[0044] In this embodiment, an inhibitor injection valve 6 is provided at the bottom of the inhibitor storage chamber 1 for injecting inhibitor into the inhibitor storage chamber 1. The pressure of the injected inhibitor is determined by calculation.

[0045] For example Figure 1 As shown in this embodiment, in order to increase the capacity of the inhibitor storage chamber 1, the bottom of the device in the inhibitor storage chamber 1 extends to the side wall of the device, which greatly increases the inhibitor storage capacity of the inhibitor storage chamber 1, thereby ensuring the smooth progress of the logging operation.

[0046] The device for preventing hydrate blockage in gas wells provided in this embodiment requires prior determination of the pressure in the inhibitor storage chamber 1 and the pressure in the inflation chamber 3 during installation. Based on the determined pressures in the inhibitor storage chamber 1 and the inflation chamber 3, both are pressurized. Figure 2 and Figure 3 The specific process is as follows: Step 1: First, measure the wellbore pressure, specifically the wellbore pressure P at the passage between transition chamber 2 and the wellbore. 测 or wellbore pressure F 测 Then test the wellbore pressure F as needed. 测 Determine the pressure P in inhibitor storage chamber 1. 抑 Inhibitor is injected by pressurizing through inhibitor injection valve 6; the preferred operation is to ensure the pressure is P. 抑 =P 测 +3MPa; Here, P 抑 Greater than P 测 The purpose is that after the inhibitor control valve 5 is opened, during the test, the pressure in the inhibitor storage chamber 1 is greater than the pressure inside the tubing (i.e., the wellbore pressure), which causes the inhibitor to flow out of the inhibitor storage chamber 1 and then come into contact with the steel wire, thereby preventing the formation of hydrates.

[0047] Step 2: Based on P determined in Step 1 抑 Combined with wellbore pressure P 测 or wellbore pressure F 测 ; Calculate the pressure (force) P in the inflation chamber 3. d The pressure is increased to the required P through the pressure valve 7. d .

[0048] Here, the conditions are met as follows: First, ensure that the inhibitor control valve 5 is normally closed under normal pressure conditions, then: P 抑 ×A y<P d ×A b That is, the downward pressure in the inflation chamber 3 must be greater than the upward pressure in the inhibitor storage chamber 1.

[0049] Second, ensure that during the test, the inhibitor control valve 5 is open and in the normally open state, allowing the inhibitor to contact the steel wire; then: P 抑 ×A y +P 测 ×(A) b -A y ) > P d ×A b Here, F 测 =P 测 ×(Ab-A y That is, the sum of the upward pressure in the inhibitor storage chamber 1 and the upward pressure in the wellbore must be greater than the downward pressure in the air chamber 3, so that the sealing package 4 is subjected to an upward resultant force, ensuring that the inhibitor control valve 5 is in the open state.

[0050] Combining the above two conditions: P 抑 ×A y <P d ×A b <P 抑 ×A y +P 测 ×(A) b -A y P can be calculated. 抑 ×A y / A b <P d <

P 抑 ×A y +P 测 ×(A) b -A y )

[0051] At this point, the pressure of the inflation chamber 3 and the pressure of the inhibitor storage chamber 1 have been determined. Based on the pressure of the inflation chamber 3 and the pressure of the inhibitor storage chamber 1, the inflation chamber 3 and the inhibitor storage chamber 1 are pressurized respectively to meet the requirements for the formation of waterproofing compounds during the test process.

[0052] Example 2 This embodiment also provides a method for operating the device for preventing gas well hydrate freezing during testing, based on the above-mentioned device for preventing gas well hydrate freezing during testing, combined with... Figure 2 and Figure 3 The specific steps are as follows: First, the various components of this device are mechanically assembled; Then, the pressure of inhibitor storage chamber 1 is determined based on the pre-measured wellbore pressure, and inhibitor is injected into inhibitor storage chamber 1 according to the pressure of inhibitor storage chamber 1. The pressure of the inflation chamber 3 is determined by combining the pre-measured wellbore pressure and the pressure of the inhibitor storage chamber 1, and the inflation chamber 3 is pressurized according to the pressure of the inflation chamber 3.

[0053] After the above pressure test is completed and before the formal test begins, the adaptive performance of this device is tested. This can be done by simulation to observe whether the inhibitor control valve 5 can be opened smoothly and kept in the normally open state under the wellbore pressure under preset conditions. After the test is completed, the installation process of this device is finished.

[0054] Under normal conditions, under the combined action of the pressure in the inflation chamber 3 and the pressure in the inhibitor storage chamber 1, the inhibitor control valve 5 is normally closed, sealing the passage between the transition chamber 2 and the inhibitor storage chamber 1. During the test, under the combined action of the pressure in the inhibitor storage chamber 1, the wellbore pressure, and the air filling chamber 3, the inhibitor control valve 5 automatically opens and remains open, connecting the transition chamber 2 to the inhibitor storage chamber 1; the inhibitor is released from the inhibitor storage chamber 1 and transferred to the gas wellbore via the transition chamber 2; the reason for ensuring the smooth implementation of the above action process is that the sum of the pressure in the inhibitor storage chamber 1 and the wellbore pressure is greater than the pressure in the air filling chamber 3; the pressure in the inhibitor storage chamber 1 is less than the pressure in the air filling chamber 3.

[0055] This embodiment provides a working method for a device used to prevent gas well hydrate freezing during testing. The specific principle is as follows: like Figure 2 As shown, when the device is not in use, i.e., when the inhibitor control valve 5 is not open, P 抑 ×A y <P d ×A b Inhibitor control valve 5 is normally closed, and the inhibitor is in inhibitor storage chamber 1.

[0056] like Figure 3 As shown, when the device is in use, i.e. during testing, the pressure inside the wellbore is transmitted to the device due to the opening of the test valve, P 测 To measure the well pressure (pressure), the pressure exerted on the sealing package 4 at this time is an upward force P. 抑 ×A y +P 测 ×(A) b -A y ) and downward force P d ×A b Furthermore, according to: P 抑 ×A y +P 测 ×(A) b -A y ) > P d ×A b Consequently, the upward force exceeds the downward force, and the inhibitor control valve 5 opens. The pressure inside the inhibitor storage chamber 1 is P. 抑 Greater than the wellbore pressure (force) P 测 Therefore, the inhibitor flows out of the storage chamber 1 into the wellbore; since the amount of inhibitor in the storage chamber 1 is limited, the pressure gradually decreases as the inhibitor flows out, when P 抑 =P 测 At this point, the inhibitor is in equilibrium and stops flowing. At this time, the inhibitor surrounds the steel wire. Under the action of the inhibitor, water molecules dissolve in the inhibitor, preventing the formation of hydrates.

[0057] This embodiment also provides a gas well, including a wellbore, a blowout preventer (BOP), and the device for preventing gas well hydrate freezing during testing provided in Embodiment 1. The device for preventing gas well hydrate freezing during testing is located below the BOP and has good performance in preventing hydrate formation, facilitating smooth logging operations and helping to prevent gas well hydrate freezing during testing, thereby improving testing efficiency and safety. This design tightly integrates the device with the gas well, enabling the device to better serve the testing and production of the gas well, thus improving testing efficiency and the safety of logging operations.

[0058] In summary, this invention provides a device for preventing gas well hydrate freezing during testing, which has the following advantages compared to existing anti-freezing measures: This invention installs a device to prevent gas well hydrate freezing during testing inside the blowout preventer. During wireline operations, the inhibitor can automatically come into contact with the wireline, ensuring that the wireline is always surrounded by the inhibitor during the test, effectively preventing hydrate formation, greatly reducing the risk of hydrate formation during gas well testing, reducing the risk of cable operations, and improving testing efficiency.

[0059] The above embodiments are merely one of the implementation methods for achieving the technical solution of the present invention. The scope of protection claimed by the present invention is not limited to this embodiment, but also includes any variations, substitutions and other implementation methods that can be easily conceived by those skilled in the art within the scope of the technology disclosed in the present invention.

Claims

1. A device for preventing gas well hydrate freezing during testing, characterized in that, It includes an inhibitor storage chamber (1), a transition chamber (2) and an inflation chamber (3) arranged from bottom to top; The inhibitor storage cavity (1) is used to store inhibitors; The transition cavity (2) is connected to the inhibitor storage cavity (1) and is used to connect to the gas well shaft; the transition cavity (2) is used to transfer the inhibitor released from the inhibitor storage cavity (1) into the gas well shaft during the test, so that the inhibitor is wrapped around the outside of the steel wire; the steel wire is located inside the gas well shaft; The bottom of the inflation chamber (3) is connected to a vertically movable inhibitor control valve (5). The inhibitor control valve (5) can close the channel between the transition chamber (2) and the inhibitor storage chamber (1); and can automatically open under pressure difference and remain open so that the transition chamber (2) and the inhibitor storage chamber (1) are connected. The pressure difference is obtained by the combined action of the pressure in the inhibitor storage chamber (1), the wellbore pressure and the pressure in the air chamber (3); wherein, the sum of the pressure in the inhibitor storage chamber (1) and the wellbore pressure is greater than the pressure in the air chamber (3), and the pressure in the inhibitor storage chamber (1) is less than the pressure in the air chamber (3).

2. The device for preventing gas well hydrate freezing during testing according to claim 1, characterized in that, The inflation chamber (3) is connected to the inhibitor control valve (5) through the sealing bag (4), and the inflation chamber (3) is connected to the sealing bag (4); the sealing bag (4) can drive the inhibitor control valve (5) to move in the vertical direction under the action of external force.

3. The device for preventing gas well hydrate freezing during testing according to claim 1, characterized in that, The bottom of the inhibitor storage chamber (1) is provided with an inhibitor injection valve (6) for injecting inhibitors into the inhibitor storage chamber (1).

4. The device for preventing gas well hydrate freezing during testing according to claim 1, characterized in that, The top of the inflation chamber (3) is provided with a pressure valve (7) for pressurizing the inflation chamber (3).

5. The device for preventing gas well hydrate freezing during testing according to claim 1, characterized in that, Under normal pressure, the pressure in the inflation chamber (3) is greater than the pressure in the inhibitor storage chamber (1).

6. The device for preventing gas well hydrate freezing during testing according to claim 1, characterized in that, During the test, the wellbore pressure enters the transition chamber (2) through the channel between the transition chamber (2) and the gas wellbore.

7. A method for operating a device to prevent gas well hydrate freezing during testing, characterized in that, The device for preventing gas well hydrate freezing during testing according to any one of claims 1-6 includes: Install the device for preventing gas well hydrate freezing during the test; Under normal conditions, when the pressure in the inflation chamber (3) and the pressure in the inhibitor storage chamber (1) work together, the inhibitor control valve (5) is normally closed, blocking the passage between the transition chamber (2) and the inhibitor storage chamber (1). During the test, under the combined action of the pressure in the inhibitor storage chamber (1), the wellbore pressure, and the air filling chamber (3), the inhibitor control valve (5) automatically opens and remains open, connecting the transition chamber (2) with the inhibitor storage chamber (1); the inhibitor is released from the inhibitor storage chamber (1) and transferred to the gas wellbore through the transition chamber (2), so that the inhibitor is wrapped around the outside of the steel wire; the steel wire is inserted into the gas wellbore. Among them, the sum of the pressure in the inhibitor storage chamber (1) and the wellbore pressure is greater than the pressure in the air filling chamber (3); the pressure in the inhibitor storage chamber (1) is less than the pressure in the air filling chamber (3).

8. The operating method of the device for preventing gas well hydrate freezing during testing according to claim 7, characterized in that, The installation process of the device for preventing gas well hydrate freezing during the test includes: The pressure of the inhibitor storage chamber (1) is determined based on the pre-measured wellbore pressure, and inhibitor is injected into the inhibitor storage chamber (1) according to the pressure of the inhibitor storage chamber (1). The pressure of the inflation chamber (3) is determined by combining the pre-measured wellbore pressure and the pressure of the inhibitor storage chamber (1), and the inflation chamber (3) is pressurized according to the pressure of the inflation chamber (3).

9. The operating method of the device for preventing gas well hydrate freezing during testing according to claim 8, characterized in that, The pressure in the inflation chamber is adjusted based on the pressure of the inhibitor storage chamber, the cross-sectional area of ​​the inhibitor control valve, the cross-sectional area of ​​the packing, the pressure of the inflation chamber, and the wellbore pressure. The specific formula is as follows: P 抑 ×A y / A b <P d <(P 抑 ×A y +F 测 ) / A b In the formula, P 抑 Indicates the pressure in the inhibitor storage chamber; A y Indicates the cross-sectional area of ​​the inhibitor control valve; A b P represents the cross-sectional area of ​​the packet; d F represents the pressure in the inflation chamber. 测 This indicates the wellbore pressure.

10. A gas well, characterized in that, Includes a wellbore, a blowout preventer, and a device for preventing gas well hydrate freezing during the test as described in any one of claims 1-6; The device for preventing gas well hydrate freezing during the test is located below the blowout preventer box.