A construction control method for one-time forming of a pressure shaft counter-bore of a pumped storage power station

By implementing pilot hole drilling, deviation control, and gravity slag removal in the pressure shaft of a pumped storage power station, combined with well wall quality identification and zoned support, a closed-loop control system is formed, which integrates construction parameters, slag removal capacity, well wall quality, support adjustment, and risk feedback. This solves the problem of insufficient linkage of construction parameters in existing technologies and improves construction efficiency and safety.

CN123153753APending Publication Date: 2026-11-24CHINA THREE GORGES PROJECTS DEV CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611287641.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-24
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing reverse drilling methods lack a closed-loop construction control system in the pressure shafts of pumped storage power stations. Especially in the scenario of two-stage vertical shaft pressure pipelines, there is a lack of dynamic linkage between parameters such as well formation, pilot hole deviation, hole enlargement torque, counter-pull force, gravity slag removal capacity, well wall forming quality, and surrounding rock deformation during the construction process, resulting in low construction efficiency and poor safety.

Method used

A one-time construction control method for reverse drilling of pressure shafts in pumped storage power stations is proposed. By acquiring construction scheme parameters and calculating the drilling rig capacity matching coefficient, pilot hole drilling and deviation control are carried out. Combined with gravity slag removal, well wall quality identification and zonal support, construction parameters are monitored and adjusted in real time to form a closed-loop control of construction parameters-slag removal capacity-well wall quality-support adjustment-risk feedback.

Benefits of technology

It enables dynamic linkage of riser drilling operations, improves construction efficiency and safety, reduces surrounding rock disturbance and personnel exposure time, optimizes support parameters, and provides traceable construction records and data foundation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123153753A_ABST
    Figure CN123153753A_ABST
Patent Text Reader

Abstract

The application discloses a construction control method for once forming of pressure shaft reverse well drilling of pumped storage power station, and belongs to the technical field of mechanical rock breaking construction of pressure shaft. The method obtains shaft diameter, shaft depth, hole expanding chamber at the bottom of the shaft, slag receiving chamber, lower slag discharge channel, surrounding rock and equipment parameters, calculates drilling rig capacity matching coefficient, and determines reverse well drilling rig and hole expanding cutter. Pilot hole drilling is performed from top to bottom and deflection control is performed, and after the pilot hole is penetrated, the hole is expanded once from bottom to top. Rock slag falls into the slag receiving chamber by gravity and is transported out through the lower slag discharge channel. During construction, torque, reverse pulling force, rock slag lumpiness, shaft wall imaging, surrounding rock deformation and water seepage data are collected, shaft wall quality partition is identified, supporting parameters are dynamically adjusted, and drilling, slag discharge and reinforcement measures are adjusted through risk response level feedback. The application realizes closed-loop linkage of pressure shaft reverse well drilling construction, slag discharge, support and risk control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the fields of underground engineering construction for pumped storage power stations, mechanical rock breaking construction of pressure shafts, and control technology for raise boring operations. Specifically, it relates to a one-step raising boring control method for pressure shafts in pumped storage power stations. This invention also relates to systems, electronic devices, and computer-readable storage media for performing this method. Background Technology

[0002] Pumped storage power station pressure shafts are typically located in environments with high ground stress, high water head, and complex underground caverns. These shafts are deep and large in diameter, limiting access for construction, slag removal, and support operations. Traditional drilling and blasting enlargement, pilot shaft enlargement, or manual enlargement methods in large-diameter pressure shafts suffer from problems such as blasting disturbance, difficulty in controlling over- and under-excavation, poor ventilation and smoke extraction, delayed support, prolonged exposure time for personnel inside the shaft, and limited slag removal efficiency.

[0003] Large-diameter raise boring machines (RBMCs) can form vertical shafts through pilot hole drilling and reverse reaming, and their basic process is an existing technology. However, existing technologies mostly use RBMCs as independent construction equipment, usually emphasizing the pilot hole, reaming, or rock cuttings descent itself, lacking a closed-loop construction control system for pumped storage power station pressure shafts. Especially in the scenario of two-stage vertical shaft pressure pipelines, the construction process not only requires well completion, but also dynamic linkage between pilot hole deviation, reaming torque, reverse reaming force, gravity cuttings removal capacity, well wall forming quality, surrounding rock deformation, seepage, and support parameters.

[0004] Existing monitoring and support methods often use monitoring results for risk warnings and treat support design as static design. They haven't fully addressed how monitoring data is transformed into wellbore quality zoning, how wellbore quality zoning is transformed into support parameters, and how risk thresholds are used to adjust drilling and slag removal parameters. Therefore, it is necessary to propose a one-step construction control method for pressure vertical shaft raise boring, enabling raise boring operations to move beyond a single pilot hole enlargement process and instead form a closed-loop control system encompassing construction parameters, slag removal capacity, wellbore quality, support adjustment, and risk feedback. Summary of the Invention

[0005] The purpose of this invention is to provide a one-time forming construction control method for the reverse drilling of pressure shafts in pumped storage power stations, so as to solve the problem of insufficient coupling between existing reverse drilling rig construction methods and pressure shaft slag removal organization, well wall quality identification, zoned support and risk feedback control.

[0006] The objective of this invention is achieved as follows: Firstly, this invention proposes a method for controlling the one-time forming construction of a pressure shaft reverse drilling system for a pumped storage power station, comprising the following steps: S1. Obtain the parameters for the pressure shaft construction plan, including shaft diameter, shaft depth, wellhead location, bottom enlargement chamber, slag receiving chamber, lower slag discharge channel, construction adit, lower horizontal tunnel, surrounding rock conditions, groundwater conditions, initial parameters for lining support, and parameters for candidate raise boring machines. Based on the shaft diameter, shaft depth, rock strength, allowable deviation rate, required torque, required counter-pull force, and lower channel conditions, calculate the drilling rig capacity matching coefficient and determine the raise boring machine, pilot hole drill, drill pipe assembly, inclination measuring device, and enlargement cutterhead. S2, set up a drilling rig installation chamber or drilling rig foundation at the shaft head, drill the pilot hole from top to bottom, and carry out drilling-while-drilling deviation measurement and deviation control during the pilot hole drilling process; S3. After the pilot hole is completed, a reaming cutter head is installed in the reaming chamber at the bottom of the well, and the drill rod is connected. The hole is then pulled back from bottom to top to ream the pressure shaft in one go. S4. The rock debris generated during borehole expansion falls to the slag receiving chamber by its own weight and is transported out through the lower slag discharge channel, construction adit, or lower horizontal tunnel. At the same time, the gravity slag discharge compatibility index is calculated. When the slag discharge capacity does not meet the control requirements, at least one of the following measures is taken: reducing the borehole expansion speed, increasing transportation equipment, expanding the effective capacity of the slag receiving chamber, adjusting the transportation team, crushing large pieces of rock debris, or clearing the lower slag discharge channel. S5 collects data on pilot hole deviation, hole enlargement torque, counter-pulling force, drilling speed, rock cutting size, well wall imaging, surrounding rock deformation and seepage, calculates well wall quality evaluation indicators, and divides the well wall into excellent zone, general zone, reinforced support zone and special treatment zone. S6, calculate the support parameter adjustment coefficients based on the well wall quality zoning and pressure shaft functional zones, and generate zoning support schemes; S7 calculates comprehensive risk indicators and risk response levels based on real-time monitoring data, and triggers adjustments to the corrective action, speed reduction, shutdown inspection, pre-grouting, temporary support, slag removal and energy enhancement, or local construction plan according to the risk response level.

[0007] Secondly, this invention proposes a one-step construction control system for the reverse drilling of a pressure shaft in a pumped storage power station to implement the method, comprising: The parameter acquisition module is used to acquire parameters of the pressure shaft construction plan and real-time monitoring data, and to establish a construction control parameter table; The drilling rig control module is used to calculate the drilling rig capacity matching coefficient, determine the equipment configuration, output correction commands based on the inclination measurement results, and adjust the hole enlargement parameters based on real-time torque, counter-tension and drilling speed. The slag discharge organization module is used to calculate the gravity slag discharge adaptation index and adjust the hole expansion speed, slag receiving capacity or slag discharge organization. The wellbore quality identification module is used to calculate wellbore quality evaluation indicators and divide wellbore quality zones; The support parameter adjustment module is used to calculate the support parameter adjustment coefficients and generate the support parameter adjustment table; The risk feedback control module is used to calculate the comprehensive risk index and risk response level, and to feed back control commands to the drilling rig control module, the slag removal organization module, or the support parameter adjustment module. The construction plan output module is used to output construction control results; The storage module stores construction control parameter tables, monitoring data, wellbore quality zoning, and risk response records; the display / interaction module displays construction status, risk response level, and construction control instructions.

[0008] Thirdly, the present invention provides an electronic device including a processor, a memory, and a program stored in the memory, wherein the program, when executed by the processor, implements the method described herein.

[0009] Fourthly, the present invention provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the method described thereon.

[0010] Compared with the prior art, the above-conceptual technical solution conceived in this application has the following beneficial effects: 1. This invention combines one-time reverse drilling construction with lower gravity slag removal, wellbore quality identification, support parameter adjustment and risk feedback control to form a closed loop for pressure shaft construction.

[0011] 2. This invention uses a drilling rig capacity matching coefficient to correlate equipment selection with well diameter, well depth, torque, counter-pull force, power, and pilot hole deviation control values, thereby reducing the risk of mismatch between equipment capacity and engineering requirements.

[0012] 3. This invention incorporates the slag discharge rate, external transportation capacity, slag receiving capacity, slag blockage time, and large rock slag ratio into the same control logic through a gravity slag discharge adaptation index, thereby improving the matching between slag discharge organization and slag discharge rhythm.

[0013] 4. This invention transforms construction parameters, well wall imaging, and surrounding rock monitoring data into zonal support criteria through well wall quality evaluation indicators, enabling support parameters to be dynamically adjusted according to well wall quality and functional zones.

[0014] 5. This invention transforms monitoring results into actionable corrective, speed reduction, pre-grouting, temporary support, shutdown inspection, or slag removal and energy enhancement measures through a risk threshold trigger function, thereby improving construction safety and control timeliness.

[0015] 6. The present invention adopts a one-time forming process of pilot hole drilling and bottom-up reverse pull-out hole expansion, which can reduce the disturbance of surrounding rock, ventilation and smoke exhaust burden and exposure time of personnel in the well caused by traditional drilling and blasting expansion, and is conducive to controlling over-excavation and under-excavation.

[0016] 7. When the drilling rig capacity is insufficient, the present invention identifies the item with the smallest capacity ratio and maps the shortcomings of well diameter, well depth, torque, counter-pull force, power or deviation control to equipment, well depth, reaming diameter, reaming speed, surrounding rock pretreatment or deviation correction measures, so that equipment selection and scheme adjustment have traceable criteria.

[0017] 8. This invention links the slag discharge rate of the borehole with the slag receiving capacity, the external transportation capacity, the slag blockage time, and the large rock slag ratio. It can reduce the borehole expansion speed or increase the slag discharge capacity in a timely manner when the slag discharge capacity decreases, thereby reducing slag blockage and downtime.

[0018] 9. This invention establishes a fixed mapping between excellent zones, general zones, reinforced support zones, and special treatment zones and corresponding support measures. Furthermore, it refines the parameters of reinforced concrete lining, steel lining, and temporary support by adjusting the support parameter adjustment coefficient, which helps to reduce insufficient or excessive support.

[0019] 10. This invention generates construction records, well wall quality zoning diagrams, support parameter adjustment tables, and risk response records through parameter acquisition, risk feedback, storage, and interactive display, which can provide a traceable data foundation for construction acceptance, subsequent lining construction, and operation and maintenance. Attached Figure Description

[0020] To more clearly illustrate the technical solutions in the embodiments of the present invention, the accompanying drawings used in the description of the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention; for those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0021] Figure 1 This is an overall flowchart of the pressure shaft reverse drilling one-time forming construction control method of the present invention.

[0022] Figure 2 This diagram illustrates the pilot hole drilling, reverse reaming, and lower gravity slag removal construction.

[0023] Figure 3 This is a schematic diagram showing the connection relationship between the lower vertical shaft, the bottom expansion chamber, the slag receiving chamber, and the lower slag discharge channel.

[0024] Figure 4 This is a schematic diagram of wellbore quality identification and zoned support control.

[0025] Figure 5 This is a flowchart of the risk threshold triggering and construction parameter feedback control process.

[0026] Figure 6 This is a schematic diagram of the system module structure of the present invention. Detailed Implementation

[0027] To more clearly illustrate the purpose, technical solution, and beneficial effects of this application, the application will now be described in further detail with reference to the accompanying drawings and specific embodiments. It should be specifically noted that the specific embodiments described below are only used to illustrate the technical content of this application and do not constitute a limitation on the scope of protection of this application.

[0028] Example 1: See Figure 2 and Figure 3 A pumped storage power station's pressure shaft consists of an upper shaft and a lower shaft. The lower end of each shaft has a construction adit, a lower horizontal tunnel, or a lower slag discharge channel. The lower slag discharge channel is a lower horizontal tunnel, construction adit, access tunnel, or lower transport channel connected to the bottom enlarged chamber or slag receiving chamber. A rock cuttings transfer connection section is provided between the slag receiving chamber and the bottom enlarged chamber, through which rock cuttings enter the lower slag discharge channel.

[0029] S1, Input of engineering parameters and equipment parameters.

[0030] See Figure 1 , 2 3. Before construction, collect the design diameter, depth, wellhead location, bottom enlargement chamber, slag receiving chamber, lower slag discharge channel, construction adit, lower horizontal tunnel, surrounding rock conditions, groundwater conditions, initial parameters of lining support, and parameters of candidate raise boring machines for the upper or lower vertical shaft, and establish a construction control parameter table.

[0031] The construction control parameter table should include at least eight categories of data: design parameter group, equipment parameter group, pilot hole control parameter group, reaming control parameter group, slag removal control parameter group, wellbore quality identification parameter group, support parameter group, and risk threshold parameter group. The design parameter group is used to determine the well diameter, well depth, and spatial constraints; the equipment parameter group is used for calculations... The pilot hole control parameter group is used to determine the inclination measurement interval, deviation warning value, and deviation control value; the reaming control parameter group is used to determine the control range of torque, counter-pull force, rotational speed, and drilling speed; the slag removal control parameter group is used to calculate... The wellbore quality identification parameter set is used for calculation. The support parameter set is used for calculation. The risk threshold parameter set is used for calculation. and .

[0032] Once the construction control parameter table is generated, the construction control system uses this table as a unified data source for subsequent equipment selection, construction process monitoring, support parameter adjustment, and risk feedback.

[0033] According to the design well diameter Design well depth Rock strength, torque required for borehole enlargement design Required counter-tension for hole enlargement design Power required for hole enlargement design and permissible skewness Calculate the drilling rig capacity matching coefficient .

[0034] The drilling rig capacity matching coefficient is calculated using the following formula: ; in, is the drilling rig capacity matching coefficient, dimensionless; This refers to the maximum enlarged diameter of the raise boring machine, in meters (m). The design diameter for pressure shafts, in meters (m). This represents the maximum well depth achieved by the raise boring machine, expressed in meters (m). The design depth for pressure shafts is given in meters (m). The rated torque of the equipment is expressed in kN·m. The torque required for hole enlargement design, in kN·m; The rated counter-tension force of the equipment, in kN; The required counter-pull force for hole enlargement design, in kN; Rated power of the equipment, in kW; The power required for hole enlargement design, in kW; To allow for skewness, the unit is percentage; The skewness is the predicted or measured percentage. Used to determine whether the equipment can meet the requirements for the diameter, depth, and drilling accuracy of pressure shafts.

[0035] when When the drilling rig capacity matching coefficient is not less than the drilling rig capacity control value, the candidate raise boring machine is determined to meet the construction control requirements, and the raise boring machine, pilot hole drill string, drill pipe assembly, directional measuring device, and reaming cutterhead are determined. The drilling rig capacity control value is set to 1.0 by default; when it is necessary to reserve equipment capacity, a preset value greater than 1.0 is used.

[0036] when That is, when the drilling rig capacity matching coefficient is less than the drilling rig capacity control value, the construction control system will not enter the pilot hole drilling step, but will instead output the reason for the equipment mismatch. If it is the smallest item, then replace it with a raise boring machine with a larger maximum reaming diameter or adjust the reaming diameter once; if If it is the smallest item, then replace it with a raise boring machine with a larger maximum well depth, adjust the depth of the single-stage shaft, or add an intermediate construction platform; if , or If it is the minimum requirement, then replace it with a raise boring machine with a rated capacity that meets the requirements, adjust the reaming speed, adjust the primary reaming diameter, or perform surrounding rock pretreatment; if If the minimum requirement is met, then increase the inclination measurement frequency, optimize the combination of pilot hole drill and drill rod, or set up a correction tool.

[0037] When two or more capacity ratios are tied for the minimum, the adjustment measures corresponding to each minimum are combined and implemented. After adjustment, the drilling rig capacity matching coefficient is recalculated until it is not less than the drilling rig capacity control value. The surrounding rock pretreatment includes at least one of the following: advanced geological verification, pre-grouting reinforcement, pre-drainage, setting local pressure relief holes, or mechanical pre-fracture, and is selected according to the actual conditions of high-strength hard rock, fractured zone, or water-rich well section.

[0038] S2, Pilot Hole Drilling and Deviation Control A drilling rig installation chamber or drilling rig foundation is set up at the shaft head, and pilot hole drilling is carried out from top to bottom. During the pilot hole drilling process, deviation measurement and deviation control are carried out.

[0039] Pilot hole drilling includes: drilling the pilot hole from top to bottom according to the designed axis; collecting the pilot hole inclination angle, azimuth angle, and deviation rate at preset inclination measurement intervals; maintaining the current drilling parameters when the deviation rate is less than the deviation warning value; adjusting the drilling pressure, rotation speed, mud parameters, drill string assembly, or correction tool when the deviation rate is greater than or equal to the deviation warning value but less than the deviation control value; stopping drilling and performing pilot hole trajectory verification when the deviation rate is greater than or equal to the deviation control value.

[0040] Specifically, the pilot hole is drilled from the shaft opening along the designed axis towards the enlarged chamber at the bottom of the shaft. The construction control system collects the pilot hole depth, dip angle, azimuth angle, and deviation rate according to the preset inclination measurement intervals. The preset inclination measurement intervals are recorded in the construction control parameter table and can be set according to fixed advance, surrounding rock zoning, or pilot hole depth segments.

[0041] The guide hole deviation control includes three levels of action. First, when the measured deviation rate... At the same time, maintain the current drilling pressure, rotation speed, and mud parameters, among which The first is the skew warning value; the second is when When corrective drilling is performed, corrective actions include reducing drilling pressure, adjusting rotation speed, adjusting mud properties, changing drill string assembly, or using corrective tools; third, when If deviation is detected, drilling should be stopped and the pilot hole trajectory should be checked. If the deviation can be corrected after checking, corrective drilling should be performed. If the required breakthrough accuracy cannot be met after checking, the deviated section should be backfilled or the pilot hole should be re-laid. The above deviation control records will be used for subsequent... Input.

[0042] S3, reverse-pull expansion hole forming construction in one step.

[0043] See Figure 2 After the pilot hole is completed, a reaming cutter head is installed in the reaming chamber at the bottom of the well, and the drill rod is connected. The hole is then pulled upwards to ream the pressure shaft in one go.

[0044] The reverse reaming process includes: after the pilot hole is drilled to the bottom reaming chamber, a reaming cutterhead is installed in the bottom reaming chamber, the reaming cutterhead is connected to the drill pipe, and the hole is reamed from bottom to top using the reverse pull force and torque provided by the raise boring machine. The reaming speed and cutterhead speed are adjusted according to the real-time torque, real-time reverse pull force, cutterhead speed, drilling speed and abnormal vibration signals.

[0045] Specifically, after the pilot hole reaches the reaming chamber at the bottom of the well, construction personnel or mechanical auxiliary equipment install the reaming cutterhead in the reaming chamber and connect it to the drill pipe of the raise boring machine. The raise boring machine provides counter-pull force and torque from the wellhead, causing the reaming cutterhead to ream the hole from bottom to top. During the reaming process, the construction control system records the real-time torque. Real-time counter-tension The following factors are considered: cutterhead speed, drilling speed, reaming depth, and abnormal vibration.

[0046] S4, Lower gravity slag discharge system.

[0047] The rock debris generated during borehole expansion falls to the slag receiving chamber by its own weight and is then transported out through the lower slag discharge channel, construction adit, or lower horizontal tunnel. At the same time, the gravity slag discharge adaptation index is calculated, and the slag discharge plan is adjusted when the slag discharge capacity does not meet the control requirements.

[0048] The gravity slag discharge compatibility index is calculated using the following formula: ; in, The gravity slag discharge adaptation index is dimensionless. Actual outbound transport capacity, unit: ; The slag removal rate for borehole expansion is expressed in units of... ; The effective capacity of the slag receiving chamber is expressed in units of... ; Minimum slag collection capacity required for continuous borehole enlargement, in units of ; Dimensionless correction coefficients are used to match the slope, clearance, transfer distance, and transportation equipment of the lower passage. The time spent in the statistical period due to blockage or downtime is expressed in hours. Total operation time for the statistical period, in hours; This represents the percentage of large rock fragments or the risk coefficient for blockage, and is dimensionless. to The weights are used to control the borehole expansion rate, slag receiving capacity, and transportation equipment configuration. All weights are non-negative and the sum of the weights is 1. The gravity slag discharge control value is determined by the slag discharge data from the test section, the rated capacity of the transportation equipment, and the allowable downtime.

[0049] See Figure 2 The rock cuttings generated during borehole enlargement fall to the bottom of the enlargement chamber and the cuttings receiving chamber under gravity. The cuttings receiving chamber is connected to the construction adit, access tunnel, or lower horizontal tunnel via a lower cuttings discharge channel, and the rock cuttings are transported away by transport equipment. The construction control system obtains the actual transport capacity during each cuttings discharge statistical period. , slag removal rate of the borehole Effective capacity of slag receiving chamber Minimum slag collection capacity required for continuous borehole enlargement Blockage or downtime during standby Total work time during the statistical period and the proportion of large rock fragments and calculate .

[0050] when That is, when the slag removal capacity meets the control requirements, maintain the current hole expansion rate and slag removal structure; when That is, when the slag discharge capacity does not meet the control requirements, the control action is executed according to the triggering reason: if If insufficient, increase the number of transport vehicles, increase the frequency of transport, or set up temporary transfer points; if If insufficient, pause or reduce the hole enlargement rate and increase the slag receiving capacity; if If the value is exceeded, clear the lower slag discharge channel or adjust the transportation team; if If the control value is exceeded, large rock fragments will be crushed a second time. When two or more slag discharge factors fail to meet the control requirements at the same time, the corresponding control actions will be executed in combination, and the gravity slag discharge adaptation index will be recalculated in the next statistical period.

[0051] S5. Wellbore quality identification and zoning evaluation.

[0052] Data on borehole deviation, reaming torque, counter-pull force, drilling speed, rock cutting size, wellbore imaging, surrounding rock deformation, and water seepage were collected. Wellbore quality evaluation indicators were calculated, and the wellbore was divided into excellent zone, general zone, reinforced support zone, and special treatment zone. Wellbore quality evaluation indicators are calculated using the following formula: ; in, This is a dimensionless index for evaluating wellbore quality. The cross-section forming quality coefficient is derived from well wall scanning and over- and under-excavation measurements; The wellbore surface integrity coefficient is derived from wellbore imaging and rockfall statistics. The surrounding rock stability coefficient is derived from surrounding rock classification, strength reduction analysis, or deformation inversion. The quality coefficient for controlling the guide hole deviation is derived from the inclination measurement data; The penalty coefficient for over-digging or under-digging; This is the deformation penalty coefficient for the surrounding rock; This is the penalty coefficient for seepage and inrush. to For weights. This is used to divide the wellbore into excellent, general, reinforced support, and special treatment zones. All weights are non-negative and the sum of the weights is 1; all basic quality coefficients and penalty coefficients are normalized to preset intervals, and the weights and zoning thresholds are calibrated based on test sections, similar engineering data, and design control values.

[0053] Specifically, see Figure 4 After the pressure shaft is enlarged or segmented, wellbore quality is identified using wellbore imaging, wellbore scanning, surrounding rock deformation monitoring, seepage monitoring, drilling parameter recording, and rock cuttings characteristic recording. Rock cuttings particle size, block size, lithology, and freshness are used to assist in correcting the assessment of surrounding rock stability and wellbore surface integrity. The construction control system inputs data on section forming quality, wellbore surface integrity, surrounding rock stability, pilot hole deviation control quality, over-excavation and under-excavation, surrounding rock deformation, and seepage / inrush. Computational model.

[0054] set up , and This is the threshold for wellbore quality zoning, and .when At that time, the corresponding well section is a good area; when At that time, the corresponding well section is a general area; when At that time, the corresponding well section is a reinforced support zone; when At that time, the corresponding well section was designated as a special treatment zone. (And...) Figure 4 Correspondingly, conventional anchor-sprayed support is implemented in the excellent area; the thickness of the sprayed concrete is increased in the general area; the reinforced support area adopts a combination of dense anchor bolts and steel mesh support; and the special treatment area adopts at least one of the following: pre-grouting, temporary steel arch frame or local steel lining.

[0055] S6. Implementation of zoned support control.

[0056] The adjustment coefficients for support parameters are calculated based on the wellbore quality zoning and the functional zones of the pressure shaft, and a zonal support scheme is generated. The zonal support scheme is used to adjust the shotcrete thickness, anchor bolt length, anchor bolt spacing, and reinforced concrete lining thickness, and to determine the steel lining wall thickness, steel strength grade, stiffening ring cross-section, stiffening ring spacing, and temporary support measures.

[0057] The support parameter adjustment coefficient is calculated using the following formula: ; Support parameters are based on the above Adjust as follows: ; in, These are dimensionless adjustment coefficients for support parameters. This represents the normalized value of the surrounding rock pressure risk. This is the normalized value for groundwater pressure risk; Normalized value for the influence of fault fracture zone; The importance coefficient for the functional zoning of pressure shafts; to As weight; and These refer to adjusting the thickness of the sprayed concrete or lining before and after the adjustment, in mm or m. and These are the anchor bolt lengths before and after adjustment, in meters (m). and These represent the anchor bolt spacing before and after adjustment, in meters. All weights are non-negative and the sum of the weights is 1; each risk normalization value is determined by the ratio of the corresponding measured value to the design control value or by a piecewise normalization function.

[0058] Construction control system according to The calculation results form a support parameter adjustment table. This table must include at least the well section number, well section elevation, well wall quality zoning, and the thickness of the shotcrete or lining before adjustment. Adjust the thickness of the sprayed concrete or lining. Adjust the length of the anchor bolt before Adjusted anchor bolt length Adjust the spacing of the front anchor bolts Adjust the anchor bolt spacing And whether steel lining or temporary support is used. When steel lining is used, the adjustment table also records the steel lining wall thickness, steel strength grade, stiffening ring cross-section, and stiffening ring spacing; when temporary support is used, the adjustment table also records the type of temporary support, implementation scope, closure timing, and removal conditions.

[0059] For reinforced concrete lining, the initial design thickness is used as the benchmark. First, the initial design thickness is multiplied by the support parameter adjustment coefficient to obtain the candidate thickness. Then, the thickness is rounded up according to the preset thickness grade. Subsequently, the bearing capacity, crack resistance and stability are checked under the combination of internal water pressure, external water pressure, surrounding rock pressure and construction load. If the check does not meet the requirements, the thickness grade is increased or the reinforcement is adjusted and checked again.

[0060] For steel lining, the wall thickness, steel strength grade, stiffening ring cross section, and stiffening ring spacing are selected from the preset steel lining design parameter table according to the well wall quality zoning, pressure shaft functional zoning, and support parameter adjustment coefficient. When the support parameter adjustment coefficient increases, the wall thickness or steel strength grade, stiffening ring cross section, or stiffening ring spacing is increased or decreased according to the parameter table. The steel lining strength, external pressure stability, stiffness, and welding construction conditions are then checked.

[0061] Temporary support is implemented before permanent lining or steel lining construction. In areas with excellent performance, conventional anchor-sprayed support is used; in general areas, the thickness of the sprayed concrete is increased; in areas with reinforced support, a combination of dense anchor bolts and steel mesh is used; and in areas with special treatment, at least one of pre-grouting, temporary steel arches, or local steel lining is used. When the risk response level reaches the control state, the machine is stopped for inspection first, and then temporary steel support, local backfilling, or other local construction adjustments are implemented based on the review results.

[0062] S7, Risk threshold triggering and construction parameter feedback.

[0063] See Figure 5 Calculate comprehensive risk indicators based on real-time monitoring data. and risk response level According to the risk response level, adjustments to the construction plan may be triggered, such as correction, speed reduction, shutdown inspection, pre-grouting, temporary support, slag removal and energy enhancement, or local construction plan adjustment.

[0064] Figure 5 S1 to S6 in the diagram represent risk feedback control sub-steps, used to illustrate the processes of real-time data acquisition, risk calculation, threshold judgment, response triggering, and parameter updating. These steps are distinct from S1 to S7 in the main workflow of this method. The main workflow S7 runs continuously during the construction process of S2 to S6. The step numbering in the main workflow does not restrict each monitoring and feedback action to be executed in a single time sequence.

[0065] Comprehensive risk indicators Calculations are based on the guide hole deflection rate, real-time torque, real-time counter-tension, surrounding rock deformation value or deformation rate, water inflow, and blockage or downtime. The formula is as follows: ; in, The guide hole deviation rate, For real-time torque, For real-time counter-tension, This refers to the deformation value or deformation rate of the surrounding rock. For the flow rate, For downtime due to slag blockage or waiting to operate, use the subscript. The parameters are the corresponding control values.

[0066] Risk Response Level Determine using the following formula: ; in, , and This is the threshold value for risk response levels.

[0067] in, For a moment A comprehensive risk indicator, dimensionless; Risk response level; This represents the guide hole deviation rate, expressed as a percentage. This is the real-time torque, expressed in kN·m. This is the real-time counter-tension force, expressed in kN. This represents the deformation value or deformation rate of the surrounding rock, in mm or mm / d. The volume of water is expressed in units of... ; The unit for downtime due to slag blockage or waiting to operate is hours; subscript included. The parameters are the corresponding control values; , and The risk response level threshold is derived from similar project statistics, field tests, design control values, or expert ratings. This indicates normal construction. This indicates a focus on the issue and an increase in monitoring frequency. This indicates an early warning and triggers corrective actions, speed reduction, or enhanced support. This indicates the control status and triggers shutdown checks, pre-grouting, temporary support, or local scheme adjustments. In the comprehensive risk index, the weights of each normalized item are non-negative and the sum of the weights is 1; the risk response level threshold is calibrated based on statistics of similar projects, field tests, and design control values, and is verified after the test section is constructed.

[0068] Specifically, the construction control system collects the guide hole deviation rate in real time. Real-time torque Real-time counter-tension Deformation value or deformation rate of surrounding rock Water inflow Blockage or downtime during standby Calculate the comprehensive risk index and risk response level .

[0069] Risk Response Level Take 0, 1, 2, or 3; when When, maintain the current construction parameters and continue construction according to the construction organization; when At the same time, increase the frequency of statistics on inclination measurement, surrounding rock deformation, water inrush, and slag discharge, and verify them. and ;when When necessary, measures such as corrective actions, reducing the hole enlargement speed, adjusting the cutterhead speed, adding transport equipment, increasing the density of anchor bolts, increasing the thickness of shotcrete, or implementing temporary support in advance may be taken. If necessary, the drilling should be stopped for inspection, and pre-grouting, temporary steel support, partial backfilling, cleaning of the slag receiving chamber, dredging of the lower slag discharge channel, or adjustments to the local construction plan should be implemented. After the risk management is completed, the updated drilling parameters should be fed back to S2, the updated slag discharge organization to S4, and the updated support parameters to S6. After all management measures are completed, the corresponding response level can only be lifted when the corresponding monitoring indicators fall back to within the control values ​​and the conditions for continuing construction are met.

[0070] Upon completion of construction, the following outputs will be provided: a one-time forming construction record for the pressure shaft, a pilot hole deviation control record, a borehole enlargement parameter record, a slag removal organization record, a shaft wall quality zoning diagram, a support parameter adjustment table, a risk response record, and a final quality evaluation result. These outputs will be used for pressure shaft construction acceptance, subsequent lining construction, steel lining installation, and archiving of operational maintenance data.

[0071] Example 2: See Figure 6 This embodiment also proposes a one-time forming construction control system for the riser drilling of pressure shafts in pumped storage power stations to implement the method described in Embodiment 1, comprising: The parameter acquisition module is used to acquire parameters of the pressure shaft construction plan and real-time monitoring data, and to establish a construction control parameter table; The drilling rig control module is used to calculate the drilling rig capacity matching coefficient, determine the equipment configuration, output correction commands based on the inclination measurement results, and adjust the hole enlargement parameters based on real-time torque, counter-tension and drilling speed. The slag discharge organization module is used to calculate the gravity slag discharge adaptation index and adjust the hole expansion speed, slag receiving capacity or slag discharge organization. The wellbore quality identification module is used to calculate wellbore quality evaluation indicators and divide wellbore quality zones; The support parameter adjustment module is used to calculate the support parameter adjustment coefficients and generate the support parameter adjustment table; The risk feedback control module is used to calculate the comprehensive risk index and risk response level, and to feed back control commands to the drilling rig control module, the slag removal organization module, or the support parameter adjustment module. The construction plan output module is used to output construction control results; The storage module is used to store construction control parameter tables, monitoring data, wellbore quality zoning, and risk response records; The display / interaction module is used to display the construction status, risk response level, and construction control instructions.

[0072] Example 3: This embodiment also proposes an electronic device, including a processor, a memory, and a program stored in the memory, which, when executed by the processor, implements the method in Embodiment 1.

[0073] Example 4: This embodiment also proposes a computer-readable storage medium on which a computer program is stored, which, when executed by a processor, implements the method in Embodiment 1.

[0074] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from its spirit or essential characteristics. Therefore, the embodiments should be considered illustrative and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of equivalents of the claims are intended to be included within the present invention, and no reference numerals in the claims should be construed as limiting the scope of the claims. Furthermore, it should be understood that although this specification describes embodiments, not every embodiment contains only one independent technical solution. This narrative style is merely for clarity. Those skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.

Claims

1. A method for controlling the one-time forming construction of a pressure shaft riser in a pumped storage power station, characterized in that: Includes the following steps: S1. Obtain the parameters of the pressure shaft construction plan. Based on the shaft diameter, shaft depth, rock strength, allowable deviation rate, required torque, required counter-pull force and lower passage conditions, calculate the drilling rig capacity matching coefficient and determine the raise boring machine, pilot hole drill, drill pipe assembly, inclination measuring device and reaming cutterhead. S2, set up a drilling rig installation chamber or drilling rig foundation at the shaft head, drill the pilot hole from top to bottom, and carry out drilling-while-drilling deviation measurement and deviation control during the pilot hole drilling process; S3. After the pilot hole is completed, a reaming cutter head is installed in the reaming chamber at the bottom of the well, and the drill rod is connected. The hole is then pulled back from bottom to top to ream the pressure shaft in one go. S4, the rock debris generated during borehole expansion falls to the slag receiving chamber by its own weight and is transported out through the lower slag discharge channel, construction adit, or lower horizontal tunnel; at the same time, the gravity slag discharge adaptation index is calculated, and the slag discharge plan is adjusted when the slag discharge capacity does not meet the control requirements; S5 collects data on pilot hole deviation, hole enlargement torque, counter-pulling force, drilling speed, rock cutting size, well wall imaging, surrounding rock deformation and seepage, calculates well wall quality evaluation indicators, and divides the well wall into excellent zone, general zone, reinforced support zone and special treatment zone. S6. Calculate the support parameter adjustment coefficients based on the wellbore quality zoning and pressure shaft functional zones, and generate zoning support schemes based on the support parameter adjustment coefficients. S7 calculates comprehensive risk indicators based on real-time monitoring data. and risk response level According to the risk response level, adjustments to the construction plan may be triggered, such as correction, speed reduction, shutdown inspection, pre-grouting, temporary support, slag removal and energy enhancement, or local construction plan adjustment.

2. The method according to claim 1, characterized in that, In S1, the construction plan parameters include shaft diameter, shaft depth, wellhead location, bottom enlargement chamber, slag receiving chamber, lower slag discharge channel, construction adit, lower horizontal tunnel, surrounding rock conditions, groundwater conditions, initial parameters for lining support, and parameters for candidate raise boring machines.

3. The method according to claim 1, characterized in that, In S1, the drilling rig capacity matching coefficient Calculate using the following formula: ; in, This is the maximum enlargement diameter for the raise boring machine. Design the well diameter for pressure shafts. This represents the maximum well depth achieved by the raise boring machine. Design the well depth for pressure shafts. The rated torque of the equipment, The torque required for hole enlargement design, The rated counter-tension force of the equipment, The required counter-tension force for hole enlargement design, Rated power of the equipment The power required for hole enlargement design, To allow for skewness, This refers to the predicted or measured skewness.

4. The method according to claim 3, characterized in that, When the drilling rig capacity matching coefficient is not less than the drilling rig capacity control value, determine the raise boring machine, pilot hole drill bit, drill pipe assembly, inclination measuring device, and reaming cutterhead; when the drilling rig capacity matching coefficient is less than the drilling rig capacity control value, perform at least one of the following adjustments according to the minimum capacity ratio: replace the raise boring machine, adjust the single-stage vertical shaft depth or add an intermediate construction platform, adjust the primary reaming diameter, adjust the reaming speed, pre-treat the surrounding rock, increase the inclination measuring frequency, optimize the pilot hole drill bit and drill pipe assembly, or set up a deviation correction tool.

5. The method according to claim 4, characterized in that, When the drilling rig capacity matching coefficient is less than the drilling rig capacity control value, identify the smallest of the six capacity ratios described in claim 3; if If it is the smallest item, then replace it with a raise boring machine with a larger maximum reaming diameter or adjust the reaming diameter once; if If it is the smallest item, then replace it with a raise boring machine with a larger maximum well depth, adjust the depth of the single-stage shaft, or add an intermediate construction platform; if , or If the minimum requirement is met, replace the hoisting rig with one whose rated capacity meets the requirements, adjust the reaming speed, adjust the reaming diameter, or pre-treat the surrounding rock; if If the minimum requirement is met, then increase the inclination measurement frequency, optimize the combination of pilot hole drill and drill rod, or set up a correction tool.

6. The method according to claim 1, characterized in that, In S2, pilot hole drilling includes: drilling the pilot hole from top to bottom according to the designed axis; collecting the pilot hole inclination angle, azimuth angle, and deviation rate at preset inclination measurement intervals; maintaining the current drilling parameters when the deviation rate is less than the deviation warning value; adjusting the drilling pressure, rotation speed, mud parameters, drill string assembly, or correction tool when the deviation rate is greater than or equal to the deviation warning value but less than the deviation control value; stopping drilling and performing pilot hole trajectory verification when the deviation rate is greater than or equal to the deviation control value.

7. The method according to claim 1, characterized in that, In S3, the reverse reaming includes: after the pilot hole is penetrated to the bottom reaming chamber, a reaming cutterhead is installed in the bottom reaming chamber, the reaming cutterhead is connected to the drill pipe, and the hole is reamed from bottom to top by the reverse pull force and torque provided by the raise boring machine. The reaming speed and cutterhead speed are adjusted according to the real-time torque, real-time reverse pull force, cutterhead speed, drilling speed and abnormal vibration signals.

8. The method according to claim 1, characterized in that, In S4, the gravity slag discharge compatibility index Calculate using the following formula: ; in, For actual export capacity, To increase the slag removal rate of the expanded hole, For the effective capacity of the slag receiving chamber, The minimum slag collection capacity required for continuous borehole enlargement. Correction factors are applied to the slope, clearance, transfer distance, and transportation equipment of the lower passageway. This refers to the time spent on slag blockage or idle equipment during the statistical period. This represents the total operation time during the statistical period. This refers to the percentage of large rock fragments or the risk factor for blockage. to denoted as weights, where each weight is a non-negative number and the sum of the weights is 1.

9. The method according to claim 1 or 8, characterized in that, In S4, when the gravity slag discharge adaptation index is not less than the gravity slag discharge control value, the current hole expansion speed and slag discharge structure are maintained. When the gravity slag discharge compatibility index is less than the gravity slag discharge control value, at least one of the following should be implemented: reduce the hole expansion speed, increase transportation equipment, expand the effective capacity of the slag receiving chamber, adjust the transportation team, crush large rock slag, or dredge the lower slag discharge channel.

10. The method according to claim 1, characterized in that, In S5, wellbore quality evaluation indicators Calculate using the following formula: ; in, The cross-sectional forming quality coefficient is... The surface integrity coefficient of the wellbore. The surrounding rock stability coefficient is... The quality coefficient for controlling the guide hole deviation. The penalty coefficient for over-digging or under-digging. The deformation penalty coefficient of the surrounding rock is... This is the penalty coefficient for seepage and inrush. to denoted as weights, where each weight is a non-negative number and the sum of the weights is 1.

11. The method according to claim 1 or 10, characterized in that, In S5, settings , and This is the threshold for wellbore quality zoning, and ;when At that time, the corresponding well section is a good area; when At that time, the corresponding well section is a general area; when At that time, the corresponding well section is a reinforced support zone; when At that time, the corresponding well section is a special treatment zone.

12. The method according to claim 11, characterized in that, In areas with excellent performance, conventional anchor-sprayed support is used; in general areas, the thickness of the sprayed concrete is increased; in areas with reinforced support, a combination of dense anchor bolts and steel mesh is used; and in areas with special treatment, at least one of pre-grouting, temporary steel arches, or local steel lining is used.

13. The method according to claim 1, characterized in that, In S6, the zoned support scheme can be adjusted by selecting at least one of the following: shotcrete thickness, anchor length, anchor spacing, reinforced concrete lining thickness, steel lining parameters, and temporary support measures. Support parameter adjustment coefficient Calculate using the following formula: ; And according to , and Adjust the thickness of the shotcrete or reinforced concrete lining, the length of the anchor bolts, and the spacing of the anchor bolts respectively; the steel lining parameters include the steel lining wall thickness, steel strength grade, stiffening ring cross-section, and stiffening ring spacing, and the steel lining parameters are adjusted according to the well wall quality zoning and support parameter adjustment coefficients. The design parameters are determined from the pre-set steel lining design parameter table; the temporary support measures are selected from at least one of the following based on the well wall quality zoning: shotcrete sealing, denser anchor bolts, steel mesh, temporary steel arches, and temporary steel supports; in, These are dimensionless adjustment coefficients for support parameters. As an indicator for evaluating wellbore quality; This represents the normalized value of the surrounding rock pressure risk. This is the normalized value for groundwater pressure risk; Normalized value for the influence of fault fracture zone; The importance coefficient for the functional zoning of pressure shafts; to As weight; and These refer to adjusting the thickness of the sprayed concrete or lining before and after the adjustment, in mm or m. and These are the anchor bolt lengths before and after adjustment, in meters (m). and These represent the anchor bolt spacing before and after adjustment, in meters (m). All weights are non-negative and the sum of the weights is 1.

14. The method according to claim 1, characterized in that, In S7, comprehensive risk indicators Calculated based on the guide hole deflection rate, real-time torque, real-time counter-tension, surrounding rock deformation value or deformation rate, water inflow, and blockage or downtime.

15. The method according to claim 14, characterized in that, Comprehensive risk indicators Calculate using the following formula: ; in, The guide hole deviation rate, For real-time torque, For real-time counter-tension, This refers to the deformation value or deformation rate of the surrounding rock. For the flow rate, For downtime due to slag blockage or waiting to operate, use the subscript. The parameters are the corresponding control values, and the weights of each normalization term are all non-negative numbers with a sum of 1.

16. The method according to claim 1, characterized in that, In S7, risk response level Determine using the following formula: ; in, , and This is the threshold value for risk response levels.

17. The method according to claim 16, characterized in that, when Maintain current construction parameters; when Increase monitoring frequency and review wellbore quality evaluation indicators and support parameter adjustment coefficients; when Triggering correction, reducing hole enlargement speed, adjusting cutter head speed, adding transport equipment, increasing anchor density, or increasing shotcrete thickness; when The system may be triggered to perform shutdown inspections, pre-grouting, temporary support, cleaning of the slag receiving chamber, dredging of the lower slag discharge channel, or adjustments to the local construction plan.

18. A one-step construction control system for raising the shaft of a pumped storage power station in a pumped-storage power station to implement the method described in any one of claims 1 to 17, characterized in that, include: The parameter acquisition module is used to acquire parameters of the pressure shaft construction plan and real-time monitoring data, and to establish a construction control parameter table; The drilling rig control module is used to calculate the drilling rig capacity matching coefficient, determine the equipment configuration, output correction commands based on the inclination measurement results, and adjust the hole enlargement parameters based on real-time torque, counter-tension and drilling speed. The slag discharge organization module is used to calculate the gravity slag discharge adaptation index and adjust the hole expansion speed, slag receiving capacity or slag discharge organization. The wellbore quality identification module is used to calculate wellbore quality evaluation indicators and divide wellbore quality zones; The support parameter adjustment module is used to calculate the support parameter adjustment coefficients and generate the support parameter adjustment table; The risk feedback control module is used to calculate the comprehensive risk index and risk response level, and to feed back control commands to the drilling rig control module, the slag removal organization module, or the support parameter adjustment module. The construction plan output module is used to output construction control results; The storage module stores construction control parameter tables, monitoring data, wellbore quality zoning, and risk response records; while the display / interaction module displays construction status, risk response level, and construction control instructions.

19. An electronic device comprising a processor, a memory, and a program stored in the memory, characterized in that, When the program is executed by the processor, it implements the method according to any one of claims 1 to 17.

20. A computer-readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by a processor, it implements the method according to any one of claims 1 to 17.