A method for receiving discarded shells of a rectangular top pipe under a steel flower pipe shed reinforcement
By using steel pipe shed reinforcement in the rectangular jacking pipe receiving construction, a composite reinforced body is formed and the groundwater seepage channel is sealed, which solves the problems of instability at the tunnel entrance and sealing failure, and improves the construction safety and reliability in the deep soft soil area of the coast.
Patent Information
- Application Number
- CN202611646529.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-23
- Publication Date
- 2026-11-24
AI Technical Summary
In coastal areas with deep soft soil, conventional reinforcement methods are difficult to maintain the stability of the tunnel opening after it fails during the construction of rectangular pipe jacking. This poses risks of tunnel opening collapse, water and soil intrusion, and leakage. In addition, the traditional whole-body lifting and receiving method has poor safety and complex procedures, making it difficult to meet the requirements of efficient receiving.
The steel pipe roof reinforcement method is adopted. Steel pipes are laid out circumferentially around the outer perimeter of the receiving well doorway to form a pipe roof reinforcement arch. Grouting is carried out in sections through the grouting holes in the pipe wall. Combined with the water-stop steel plate on the outer edge of the pipe jacking machine shell and the grouting, a composite reinforcement body is formed to block the groundwater seepage channel. Finally, it is connected to the main body of the receiving well.
It significantly improved the stability of the soil at the tunnel entrance and the reliability of water sealing, reduced construction safety risks, controlled subsequent settlement, and enhanced the safety and reliability of pipe jacking reception under complex geological conditions.
Smart Images

Figure CN123153756A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building construction technology, and in particular to a construction method for receiving the abandoned shell of a rectangular jacking pipe under a steel pipe shed reinforcement. Background Technology
[0002] With the continuous advancement of urban underground space development, the rectangular pipe jacking method has been widely used in underground tunnel construction in soft soil areas due to its advantages such as high cross-sectional utilization and minimal disturbance to surface traffic and the surrounding environment. However, in coastal areas, the strata are generally deep silty soft soils, characterized by high water content, high permeability, low soil strength, and poor self-stabilization. When the pipe jacking machine approaches the receiving shaft, the soil is easily disturbed, leading to plastic flow, water and sand inrush, and ground subsidence, posing a serious threat to the safety of the receiving construction.
[0003] Currently, in rectangular pipe jacking construction, conventional soil reinforcement methods such as high-pressure jet grouting and cement-soil mixing are typically used at the receiving shaft opening to ensure soil stability during the tunnel portal breaking and jacking head receiving stages. However, in deep soft soil environments along the coast, factors such as long-term groundwater seepage, jacking disturbance, and the deterioration of reinforced soil over time mean that by the time the rectangular pipe jacking machine approaches the receiving shaft opening, the original design for the portal reinforcement system has often largely failed, and the surrounding soil has become fluidized mud. At this point, conventional reinforcement and portal sealing measures are insufficient to maintain portal stability, easily leading to risks such as portal collapse, water and soil intrusion, and structural leakage. Furthermore, traditional integral lifting-out receiving methods are unsuitable for efficient receiving under conditions of space constraints, reinforcement failure, complex procedures, and low risk controllability, making them difficult to meet the needs of soft soil areas with failed reinforcement conditions.
[0004] To address soil instability issues following the failure of tunnel portal reinforcement, some projects have attempted to use pipe roofs for advanced support. However, most existing pipe roofs are solid pipe roofs, resulting in uneven grout diffusion and limited bonding with the soil, failing to form a reliable composite reinforcement arch. Furthermore, during the acceptance phase, there is a lack of complete construction methods that match the shell disposal process, leading to insufficient reliability in sealing the tunnel portal and the gap between the shell and the shell, making it prone to water leakage and subsequent settlement.
[0005] Therefore, there is an urgent need for a rectangular pipe jacking receiving construction method that is suitable for coastal soft soil and can be implemented under the condition of failure of tunnel portal reinforcement. Summary of the Invention
[0006] The purpose of this invention is to provide a construction method for receiving the abandoned shell of a rectangular jacking pipe reinforced with steel pipe sheds. By using perforated steel pipe sheds to achieve advanced pre-reinforcement and grouting improvement, and combining the abandoned shell reception, steel plate waterstop and grouting of the tunnel entrance into an integrated process, this method solves the technical problems of unstable tunnel entrance, sealing failure and high construction risk in soft soil areas, and improves the safety and reliability of jacking pipe reception under complex geological conditions and reinforcement failure conditions.
[0007] To achieve the above objectives, the present invention provides the following solution: a construction method for receiving the abandoned shell of a rectangular jacking pipe under a steel pipe shed reinforcement, comprising: Steel pipes are laid out circumferentially along the outer perimeter of the receiving well opening to form a pipe roof reinforcement arch. Grouting is carried out in sections, at low pressure, and multiple times through the grouting holes on the pipe wall of the steel pipes, so that the grout flows and spreads to the surrounding silty soft soil to form a composite solidified body and seal the groundwater seepage channel. The pipe jacking machine advances along the pipe jacking channel to the predetermined stopping position in the receiving well. A ring of water-stop steel plate is welded between the outer edge of the pipe jacking machine shell and the structural side wall to form the first water-stop seal. Grout is continuously injected into the gap through the pre-set grouting pipe. After grouting and sealing the gaps on the outside of the pipe jacking machine casing through the grouting holes reserved on the casing, the inside of the machine head is dismantled, leaving the casing of the pipe jacking machine at the tunnel entrance. The connection between the casing of the pipe jacking machine and the structural side wall was reinforced with steel bars, the formwork was erected and concrete was poured, and the pipe roof reinforcement arch, the water-stop steel plate, the casing of the pipe jacking machine and the main body of the receiving well were connected as one unit.
[0008] Optionally, the steel pipe body is made of Φ108mm steel pipe with a wall thickness of 4.25mm and a single length of 4m.
[0009] Optionally, the grouting holes on the steel pipe body are arranged in a quincunx pattern, with at least two grouting holes on the same cross-section.
[0010] Optionally, the center-to-center distance between two adjacent steel pipe bodies is 150mm, the external insertion angle is 10°, and the steel pipe bodies are connected by self-threaded threads, with the inner thread length at both ends being 150mm.
[0011] Optionally, the grout used for grouting is a cement-water glass two-component grout, with the volume ratio of cement grout, water glass and calcium chloride being 1:0.5:0.3, the water glass concentration being 35BE and the modulus being 2.6, and the water-cement ratio of the cement grout being 1:1.
[0012] Optionally, the pipe roof drilling adopts the trenchless one-time guided pipe drilling method, dividing the steel flower pipe body into odd-numbered and even-numbered sections, and using an interval drilling method for construction, first constructing the odd-numbered steel flower pipe body, and then constructing the even-numbered steel flower pipe body.
[0013] Optionally, the grouting adopts a top-down, backward grouting method, with an initial grouting pressure of 0.5 to 1.0 MPa and a termination pressure of 1.5 to 2.0 MPa. When the pressure rises to the final grouting pressure, grouting continues for 10 minutes before ending the grouting process.
[0014] Optionally, after the grouting of the entire section is completed, core sampling is performed between the pipes to check the grouting effect. 20mm cores are used for core sampling, with a depth of 1.5m.
[0015] Optionally, the water-stop steel plate is 15mm thick and segmented, and is reliably welded to the casing of the pipe jacking machine and the structural side wall reinforcement; several grouting pipes and ball valves are pre-installed on the sealing gate steel plate, and the grouting pipes are DN40 grouting pipes.
[0016] Optionally, after the pipe jacking machine arrives at the receiving end, the internal dismantling sequence of the machine head is as follows: dismantle the auger, internal components, breast plate and cutterhead, and the dismantled parts are transported to the starting shaft through the completed pipe jacking channel and hoisted out.
[0017] Optionally, after the pipe jacking machine housing is positioned at the tunnel entrance, secondary grouting can be performed using a pre-installed grouting ball valve inside the pipe jacking machine housing to improve the sealing and water-stopping effect.
[0018] Optionally, after the portal structure is repaired, leakage and strength tests are conducted, and the subsequent settlement and water-stopping effects are continuously monitored.
[0019] Optionally, before the steel pipe roof is supported, the inner structural sidewall of the receiving well is broken in layers and sections along the outline. The breaking range is larger than the size of the receiving well doorway, leaving room for the steel pipe roof to be laid out. After the steel pipe roof is supported, the receiving well ground wall is chiseled from bottom to top and in sections using a high-pressure water jetting method. The chiseling of the ground wall is paused when the second row of steel bars is reached. At this time, the remaining thickness of the ground wall is 180mm.
[0020] Compared with the prior art, the present invention discloses at least the following beneficial effects: This invention utilizes a steel-pipe structure arranged circumferentially along the outer perimeter of the receiving well entrance to form a pipe-roof reinforcement arch. Combined with segmented, low-pressure, and multiple grouting through injection holes in the pipe wall, the grout is uniformly diffused into the surrounding silty soft soil, thus forming a composite solidified layer around the entrance and sealing groundwater seepage channels. This effectively enhances the self-stabilizing capacity and impermeability of the soft soil. Furthermore, after the pipe jacking machine reaches the predetermined stopping position, a ring of water-stopping steel plates welded between the outer edge of the pipe jacking machine casing and the structural sidewall forms the first water-stop seal. Grouting continues through pre-installed injection pipes into the gap, while grouting is simultaneously applied to the shell using pre-reserved injection holes on the pipe jacking machine casing. Grouting is used to seal the external gaps, thereby creating a multi-layered water-stopping and consolidation system between the casing and the receiving well. Subsequently, the casing of the pipe jacking machine is left at the tunnel entrance and its interior is dismantled. Then, steel bars are tied at the connection between the casing and the structural sidewall, formwork is erected, and concrete is poured, so that the pipe roof reinforcement arch, water-stopping steel plate, pipe jacking machine casing, and the main body of the receiving well are integrated. This not only eliminates the high-risk process of lifting the casing out as a whole, but also organically combines temporary support with permanent structure, significantly improving the stability of the soil at the tunnel entrance, the reliability of water-stopping, and the effect of subsequent settlement control, and reducing the safety risks of pipe jacking receiving construction in soft soil areas. Attached Figure Description
[0021] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0022] Figure 1 This is a schematic diagram of the steel perforated pipe structure according to an embodiment of the present invention; Figure 2 This is a schematic diagram of the steel pipe shed layout according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the structure of the receiving well portal pipe roof layout according to an embodiment of the present invention; Figure 4 This is a schematic diagram of the water-stopping structure of the steel plate at the entrance of the tunnel according to an embodiment of the present invention; Figure 5 The flowchart illustrates the construction method for receiving the abandoned shell of a rectangular jacking pipe under the reinforcement of a steel pipe shed, as provided by this invention.
[0023] Attached reference numerals: 1. Steel pipe body; 2. Grouting hole in pipe wall; 3. Receiving well doorway; 4. Pipe jacking machine housing; 5. Water-stop steel plate; 6. Structural side wall. Detailed Implementation
[0024] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0025] This embodiment provides a construction method for receiving rectangular jacking pipe casings reinforced with steel perforated pipe roofs. It is applicable to rectangular jacking pipe receiving construction in deep, soft coastal areas where the original reinforcement system at the receiving wellhead has failed and the surrounding soil is in a fluid, silty state. This method solves technical problems such as soil instability at the wellhead, water and sand inrush, sealing failure, and subsequent settlement by combining pre-reinforcement with perforated steel perforated pipe roofs and grouting improvement with a casing receiving, steel plate waterstop, and grouting of the wellhead. The specific embodiments of this invention will be further described in detail below with reference to the accompanying drawings.
[0026] Reference Figure 5 As shown, the construction method in this embodiment includes, in sequence, construction preparation, demolition of structural side walls, steel pipe shed support, removal of ground walls, jacking of pipes into and out of the tunnel, sealing of the tunnel entrance and grouting, reception of the discarded casing of the pipe jacking machine, and tunnel entrance repair. Among these, the steel pipe shed support, sealing of the tunnel entrance and grouting, and reception of the discarded casing of the pipe jacking machine are the key technical points of this embodiment, which will be described in detail below.
[0027] S1. Construction preparation.
[0028] First, the working conditions were checked to confirm that the receiving well is located in a deep soft soil area in the coastal area. The original high-pressure jet grouting or cement-soil mixing reinforcement at the tunnel entrance has failed. The surrounding soil is in the form of fluid silt, which meets the conditions for implementing steel pipe roof reinforcement and shell disposal.
[0029] Subsequently, measurements and layout were carried out to accurately mark out the center line of the tunnel entrance, the layout range of the steel pipe shed, the outline of the structural sidewall demolition, and the axis of the jacking pipe entering and exiting the tunnel. Monitoring points for settlement, water level, and surrounding buildings were also set up.
[0030] Next, equipment and materials are prepared, including perforated steel pipes, grouting equipment, demolition tools, pipe jacking receiving brackets, water-stop steel plates, and double-liquid grout or cement grout materials. The pipe jacking system and grouting system are debugged, and the working space, drainage, and ventilation facilities inside the receiving well are checked.
[0031] Finally, a technical briefing was conducted, specifically addressing the risks of soft soil collapse, water inrush, and sand inrush. The briefing covered key procedures such as sidewall demolition, pipe roof construction, tunnel portal removal, and waste shell reception, clarifying emergency response measures.
[0032] S2. Demolition of structural side walls.
[0033] A combination of static crushing and mechanical cutting was used to break down the inner structural sidewalls of the receiving well in layers, sections, and small areas along the outline. Large-area, one-time demolition was strictly prohibited to minimize disturbance to the surrounding soil. The demolition area of the structural sidewalls must be slightly larger than the opening size to allow for the installation of the steel pipe shed. After demolition to the design area, debris was cleaned up and the demolition surface was trimmed to ensure a smooth and straight interface for the steel pipe shed installation.
[0034] During construction, the soil settlement and water level changes in the tunnel portal area are monitored in real time. If any abnormality is found, the demolition is stopped immediately and reinforcement and sealing measures are taken.
[0035] S3, steel pipe shed support.
[0036] Perforated steel pipes are arranged in a ring around the outer perimeter of the tunnel portal, and are driven in using a pre-drilling and jacking method to form a closed pipe roof reinforcement arch, covering the entire tunnel portal area and the surrounding soft soil area. Through the grouting holes 2 on the pipe body 1, grout is injected in sections, at low pressure, and multiple times. The grout diffuses into the surrounding silty soft soil, forming a composite reinforced body together with the pipe roof. This rapidly improves the soil strength and self-stabilizing capacity, seals groundwater seepage channels, and solves the problems of original reinforcement failure and soil instability.
[0037] like Figure 1As shown, the steel pipe body 1 is a Φ108mm perforated steel pipe with a wall thickness δ=4.25mm and a single length of 4m. 104 pipes are used in this project. Grouting holes 2 are arranged on the pipe body 1, with a diameter of 10mm and a spacing of 300mm, arranged in a quincunx pattern. Two holes are placed on the same cross-section to facilitate grout diffusion. The center-to-center distance between two adjacent pipe sheds is 150mm, and the external insertion angle is 10°. The steel pipe bodies 1 are connected by self-threaded steel pipes, with an inner thread length of 150mm at each end. The grout mix for the pipe sheds uses a cement-water glass two-component grout, with a volume ratio of cement grout, water glass, and calcium chloride of 1:0.5:0.3. The water glass concentration is 35BE, modulus 2.6, and the cement grout water-cement ratio is 1:1.
[0038] During pipe roof construction, a Φ120 drill bit is used to open a hole at low speed and low pressure, creating a hole 0.8m deep. A Φ108 pipe roof steel pipe is then lowered in. After verifying the drilling direction is correct, the drill bit is replaced, and the drilling rig speed is increased to normal. During drilling, the Φ108 pipe roof steel pipe is used as casing and drilled to the designed hole depth. Throughout the drilling process, the drill rod angle is constantly monitored, and the drilling rig is kept stationary. Every 1m of drilling, the drilling angle is checked with instruments to ensure the correct drilling direction.
[0039] The drilling rig operating platform adopts a steel pipe support platform. The height of the support platform is adjusted according to the on-site construction conditions and the height of the drilling rig. The steel pipe spacing is 1.2m and the step distance is 1.2m. Wall ties are installed to contact the adjacent wall.
[0040] A 25-ton truck crane was used to lift the drilling rig into the well. The drilling rig was kept horizontal and stable on the work platform. After adjusting the construction machinery and the steel pipe of the pipe roof to be on the same plane and the same axis, the slope of the drilling rig was adjusted to be 10° with the horizontal. Due to the size of the wellhead, a small down-the-hole drilling rig was used in this project.
[0041] Pipe roof drilling was carried out using trenchless technology with one-time guided pipe drilling. Before construction, the pipe roofs in the tunnel were numbered, divided into odd-numbered and even-numbered steel pipes. To prevent borehole collapse, an intermittent drilling method was adopted, that is, the odd-numbered steel pipes were drilled first, followed by the even-numbered steel pipes.
[0042] Using a directional drilling rig, align the drilling steel pipe with the directional pipe, and conduct a comprehensive re-inspection of the mud pipe flow. After confirming that everything is normal, proceed with trial drilling. Before drilling, place the borehole sealing device on the first pipe roof steel pipe, requiring 4 to 6 turns of oil-impregnated packing. Place 10mm to 15mm thick rubber pads in front of and behind the packing, and tighten the packing flange with bolts.
[0043] After the sealing box is installed, insert the steel pipe into the borehole pipe. Drilling can begin only if everything is normal. If water leaks at the seal during drilling, adjust the tightness of the flange as needed. The pump must be turned on before drilling, and drilling can only begin after the mud flow is normal.
[0044] During drilling, the pump pressure should be controlled between 0.6MPa and 1.0MPa, with a maximum of 2.0MPa. The rotation speed should be between 30r / min and 60r / min (the lower value should be used for sandy layers and the higher value should be used for cohesive soil, with a maximum of 100r / min). The pump flow rate should be between 10L / min and 30L / min, maintaining a small to medium water volume, low to medium pressure, and uniform medium-speed drilling.
[0045] To prevent soil erosion and control settlement, pressure maintenance measures are adopted inside the borehole, and the return water volume is strictly controlled through the return water valve to always keep the return water volume less than or equal to the inflow water volume.
[0046] During pipe connection, each pipe must undergo a quality inspection before being lowered into the pit. The pipe must be free of bends, the threads must be of uniform wall thickness, and the threads must be intact and qualified. Iron filings, dirt, and rust inside the pipe must be thoroughly cleaned. Avoid contact with hard objects during lowering to prevent damage to the pipe threads. During the connection process, ensure that no foreign objects are left behind or fall into the installed pipes. The lengthening of steel pipes must meet the load-bearing requirements. Joints of adjacent steel pipes should be staggered, and the number of joints in the same cross-section should not exceed 50%. Adjacent steel pipe joints should be staggered by at least 1 meter.
[0047] During pipe roof grouting construction, the grouting material uses a 1:0.5:0.3 cement-water glass early-strength admixture, with P.O42.5 ordinary Portland cement and added water-reducing early-strength agent calcium chloride. Grouting is performed from top to bottom, in a retreating manner. A self-made grouting sleeve is threadedly connected to the pipe roof. The grouting sleeve is equipped with an air outlet and a grout inlet pipe, controlled by valves. A 20mm plastic pipe is installed as the vent pipe, connecting to the grouting pipe and other pipelines. The orifice valve is closed, and the grouting pump is started for a pipeline pressure test. Any leaks are promptly repaired. The test pressure is equal to the final grouting pressure. Grouting is performed at low pressure and medium flow rate, with an initial grouting pressure of 0.5 to 1.0 MPa and a final pressure of 1.5 to 2.0 MPa.
[0048] Before grouting, a field grouting test is conducted, and the grouting parameters are adjusted according to the actual situation to gain experience in pipe roof grouting construction. During the grouting process, the pressure gradually increases and the flow rate gradually decreases. When the pressure reaches the final grouting pressure, grouting continues for 10 minutes, and then the grouting is completed.
[0049] The criteria for ending single-hole grouting are as follows: each grouting section proceeds normally, the final grouting pressure reaches the final pressure of the field test, and the grouting volume reaches 80% of the grouting volume of the field test; or although the final pressure of the field test has not been reached, the grouting volume has reached the grouting volume of the field test, then the grouting of this hole can be ended.
[0050] The completion standard for the entire section is: all grouting holes meet the completion standard with no missed grouting; if the completion standard is not met, supplementary grouting or re-grouting is carried out until the requirements are met. After the construction of a single pipe roof is completed, the sealing plate is immediately installed, and grouting or sealing is performed in a timely manner to prevent soil loss.
[0051] After the entire section is completed and grouting is finished, the grouting effect is checked. Core sampling is carried out between the pipes using 20mm core drills at a depth of 1.5m to ensure the soil reinforcement effect.
[0052] like Figure 2 As shown, steel pipe bodies 1 are arranged in a ring around the outer periphery of the receiving well gate 3, forming a closed pipe roof reinforced arch.
[0053] like Figure 3 As shown, the steel pipe bodies 1 arranged around the receiving well gate 3 are evenly arranged along the outline of the gate, covering the entire gate area.
[0054] S4. Remove the ground wall.
[0055] In this embodiment, taking the tunnel boring machine shaft of a rail transit system as an example, the receiving shaft of this project includes a two-layer frame structure. The lower layer is the already operational track section, and the upper layer is the underground passage of this project. Therefore, the demolition of the silt wall must be carried out without affecting the structural and operational safety. In this embodiment, the high-pressure water jetting method is used to demolish the silt wall opening, minimizing the impact on the structure and operation.
[0056] Regarding construction water and circulation, considering that the manhole is located in the middle of the existing newly built road, a 50mm diameter water pipe and power pipe were pre-buried. However, the actual water demand for hydraulic cutting is large, and one water pipe cannot meet the daily construction needs. Therefore, two additional water storage tanks were prepared, and the work surface also needed to be sealed with a brick retaining wall. Hydraulic demolition was carried out from bottom to top and in sections. The demolition of the ground wall was paused when the second row of steel bars was reached, waiting for the subsequent pipe jacking machine to exit the hole. At this time, only 180mm of the ground wall thickness remained.
[0057] S5, jacking pipe into and out of the tunnel.
[0058] Based on the measurement results, the fitting position of the receiving tunnel entrance is determined, and the current center point of the jacking head is marked on the receiving end wall. After the reinforcement measures are completed and the initial strength is achieved, the rectangular pipe jacking machine resumes jacking and implements pipe jacking reception. A 1m diameter circular hole is first drilled at the corresponding center cutter position on the wall. The pipe jacking machine advances with low thrust and low speed, strictly controlling the jacking posture to ensure that the center cutter enters the wall and the cutterhead fits against the wall surface. Simultaneously, the deformation and leakage of the soil at the tunnel entrance are monitored. Assuming there is no risk of water inrush or mud leakage, the remaining wall reinforcement is cut off, the concrete is removed, and the corners of the tunnel entrance are cleaned. The pipe jacking machine continues to advance at low speed until it reaches the predetermined stopping position.
[0059] S6. Sealing the tunnel entrance and grouting.
[0060] The reinforcing bars on all four sides of the tunnel entrance were removed, and the concrete at the four corners was trimmed to allow the jacking pipe to exit smoothly.
[0061] like Figure 4 As shown, to seal the tunnel entrance, a water-stop steel plate 5 needs to be welded between the outer edge of the pipe jacking machine casing 4 and the structural borehole wall. The water-stop steel plate 5 is 15mm thick and segmented, and is reliably welded to the reinforcing bars inside the pipe jacking machine casing 4 and the structural side wall 6 to form the first water-stop seal, which is used to prevent soil and water from seeping into the gap between the wall and the casing. Several grouting pipes and ball valves are pre-installed on the sealing steel plate for grouting of the tunnel entrance. Grouting is continuously injected into the grouting pipes to densely fill the gaps, consolidate the surrounding soft soil, improve the integrity and water-stopping effect of the tunnel entrance, and eliminate the risk of leakage and subsequent settlement.
[0062] S7, Receiving the discarded casing of the pipe jacking machine.
[0063] Since the receiving shaft of this project has been sealed, the shell disposal method will be adopted after the pipe jacking machine reaches its position. Before dismantling the shell, the soil reinforcement status of the disposal area will be reconfirmed, and the gaps between the shell and the structural walls and diaphragm walls will be sealed to achieve a water-sealing effect. To ensure the reinforcement effect, after the pipe jacking machine reaches its position, the gaps on the outside of the shell will be sealed with grout through the pre-reserved grouting holes on the shell. After the pipe jacking machine reaches the receiving end and all indicators are checked to meet the requirements, the internal dismantling of the machine head will be carried out in the following order: dismantling the auger, internal components, breast plate, and cutterhead. All dismantled parts will be transported to the launching shaft through the completed pipe jacking channel, hoisted out from the launching shaft, and transported back. The metal shell will be left at the tunnel entrance position and will not be hoisted out as a whole, thus achieving shell disposal. A ball valve for grouting is reserved inside the shell to facilitate secondary grouting later.
[0064] S8. Repair and construction of the tunnel portal.
[0065] Reinforcing steel was tied and formwork was erected at the connection between the retained shell and the tunnel portal structure. Concrete was poured to integrate the steel pipe shed, water-stop steel plate 5, and pipe jacking machine shell 4 with the main structure. The repaired surface was leveled and treated for seepage prevention, eliminating weak points such as construction joints and pores that could lead to leakage. After the tunnel portal structure repair was completed, leakage and strength tests were conducted. Subsequent settlement and water-stopping effects were continuously monitored to ensure the stability and durability of the tunnel portal, meeting usage requirements.
[0066] In one specific embodiment, the water-stop steel plate 5 is made of 15mm thick segmented steel plate, which is reliably welded to the steel bars of the pipe jacking machine housing 4 and the structural side wall 6 to form the first water-stop seal.
[0067] In one specific embodiment, a sealing steel plate is installed at the tunnel entrance to form a second water-stop seal. Several grouting pipes and ball valves are pre-installed on the sealing steel plate for grouting at the tunnel entrance. The grouting pipes can be DN40 grouting pipes, and the ball valves are used to control the grouting pressure and flow rate.
[0068] In one specific embodiment, a grouting ball valve is reserved inside the casing to facilitate secondary grouting in the later stage, so as to further improve the sealing and water-stopping effect.
[0069] Based on the above embodiments, the arrangement of the grouting holes 2 in the pipe wall of the steel pipe body 1 can be adjusted according to the permeability of the soft soil and the requirements of the reinforcement range. For example, the spacing, diameter, or number of rows and columns of the grouting holes 2 in the pipe wall can be changed to adapt to the grout diffusion requirements of different strata. The grout used in the pipe roof can also be different proportions such as cement grout or cement-water glass double-liquid grout, depending on the results of field tests, as long as it can achieve soft soil reinforcement and water-stopping.
[0070] Based on the above embodiments, the structural sidewalls can be demolished using a combination of static crushing and mechanical cutting, or high-pressure water jetting or other low-disturbance demolition methods can be used depending on the structural conditions. The ground wall can be demolished using high-pressure water jetting, or other suitable demolition processes can be used, provided that structural and operational safety is ensured. When receiving the discarded casing of the pipe jacking machine, the internal dismantling sequence of the machine head can be adjusted appropriately according to the equipment model and site conditions, as long as the metal casing can be left at the tunnel entrance and received as a discarded casing.
[0071] Building upon the aforementioned embodiments, the steel pipe roof reinforcement, shell receiving, steel plate waterstop, and grouting for sealing the tunnel entrance can be integrated into a complete construction method, specifically suited for special conditions such as deep soft soil in coastal areas and failure of tunnel entrance reinforcement. This method can effectively reduce disturbance to the surrounding soil during the pipe jacking receiving stage, control ground settlement and subsequent settlement, and improve the controllability and safety of construction under complex geological conditions.
[0072] In the description of this invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this invention, and are not intended to indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this invention.
[0073] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Various modifications and improvements made by those skilled in the art to the technical solutions of the present invention without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.
Claims
1. A construction method for receiving the abandoned shell of a rectangular jacking pipe under a steel pipe shed reinforcement, characterized in that, include: Steel pipe body (1) is laid out circumferentially along the outer periphery of the receiving well gate (3) to form a pipe roof reinforcement arch. The grout is injected in sections, at low pressure and multiple times through the grouting holes (2) on the pipe wall of the steel pipe body (1) to make the grout flow to the surrounding muddy soft soil, forming a composite reinforcement and sealing the groundwater seepage channel. The pipe jacking machine advances along the pipe jacking channel to the predetermined stopping position in the receiving well. A ring of water-stop steel plate (5) is welded between the outer edge of the pipe jacking machine shell (4) and the structural side wall (6) to form the first water-stop seal, and grout is continuously injected into the gap through the preset grouting pipe. After grouting and sealing the gaps on the outside of the pipe jacking machine housing (4) through the grouting holes reserved on the housing (4), the inside of the machine head is dismantled and the pipe jacking machine housing (4) is left at the tunnel entrance. The connection between the remaining pipe jacking machine shell (4) and the structural side wall (6) is reinforced with steel bars, the formwork is erected and concrete is poured, and the pipe roof reinforcement arch, the water-stop steel plate (5), the pipe jacking machine shell (4) and the main body of the receiving well are integrated.
2. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, The steel pipe body (1) is made of Φ108mm steel pipe with a wall thickness of 4.25mm and a single length of 4m.
3. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 2, characterized in that, The grouting holes (2) on the steel pipe body (1) are arranged in a quincunx pattern, with at least two grouting holes (2) on the same cross section.
4. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1 or 2, characterized in that, The center-to-center distance between two adjacent steel pipe bodies (1) is 150mm, and the external insertion angle is 10°.
5. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, The grout used for grouting is a cement-water glass two-component grout. The volume ratio of cement grout, water glass and calcium chloride is 1:0.5:0.
3. The water glass concentration is 35BE and the modulus is 2.
6. The water-cement ratio of the cement grout is 1:
1.
6. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, The pipe roof drilling adopts the trenchless one-time guided pipe drilling method. The steel flower pipe body (1) is divided into odd number and even number. The construction is carried out by the interval drilling method. The odd number steel flower pipe body (1) is constructed first, and then the even number steel flower pipe body (1) is constructed.
7. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, Grouting is carried out from top to bottom and backward. The initial grouting pressure is 0.5 to 1.0 MPa and the final pressure is 1.5 to 2.0 MPa. When the pressure rises to the final grouting pressure, grouting continues for 10 minutes and then ends.
8. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, After the grouting of the entire section is completed, core samples are taken between the pipes to check the grouting effect. 20mm core samples are taken to a depth of 1.5m.
9. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, The water-stop steel plate (5) is 15mm thick and is set in sections, and is reliably welded to the steel bars of the pipe jacking machine housing (4) and the structural side wall (6); a number of grouting pipes and ball valves are pre-installed on the sealing door steel plate, and the grouting pipes are DN40 grouting pipes.
10. The construction method for receiving the abandoned shell of the rectangular jacking pipe under the reinforcement of the steel pipe shed according to claim 1, characterized in that, After the pipe jacking machine arrives at the receiving end, the internal dismantling sequence of the machine head is as follows: dismantle the auger, internal components, breast plate and cutterhead. The dismantled parts are transported to the starting shaft through the completed pipe jacking channel and hoisted out.