Underground gangue filling method based on goaf geological classification

By using a geological grading method for goaf areas, classifying grades according to geological parameters and configuring material ratios, the problems of resource waste and safety hazards in existing technologies are solved, realizing environmentally friendly and efficient backfilling of gangue underground, and improving the safety and economy of mines.

CN123153802APending Publication Date: 2026-11-24WUHAI ENERGY CO LTD UNDER CHN ENERGY +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611429649.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-15
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing filling technologies ignore the differences in geological conditions in goaf areas, resulting in a mismatch in material ratios between stable and unstable goaf areas, causing resource waste and safety hazards. Furthermore, raising gangue from underground to the surface increases transportation costs and environmental pollution.

Method used

A geological classification method based on goaf areas is adopted. Different filling grades are divided according to parameters such as coal seam dip angle, surrounding rock fracturing degree, goaf height and filling span. Based on the grade, the type of cementing material, additives and water-solid ratio are configured, and an adaptive filling process is adopted for underground gangue filling.

Benefits of technology

It enables in-situ resource utilization of gangue in underground mines, reduces transportation costs and environmental pollution, improves support safety and economic benefits, and adapts to filling needs under different geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123153802A_ABST
    Figure CN123153802A_ABST
Patent Text Reader

Abstract

This invention relates to an underground gangue backfilling method based on geological grading of goaf areas. The method includes: obtaining geological condition parameters of the goaf to be backfilled; classifying the goaf into at least two different backfilling grades according to the geological condition parameters and using a grading standard; determining the proportion of mixed backfill material according to the backfilling grade; and using a backfilling process matching the backfilling grade to transport and backfill the prepared mixed backfill material into the goaf. The advantages of this invention are: it avoids the land occupation, spontaneous combustion, and rainwater leaching pollution of gangue piles; it achieves in-situ resource recycling of solid and liquid waste, eliminating potential environmental pollution hazards; it avoids material waste caused by over-design, significantly reducing the unit volume backfilling cost; it reduces energy consumption and transportation costs; it solves the problem of roof support under complex working conditions, ensuring safe production; and it provides a replicable and scalable technical paradigm for green mine construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of mine goaf filling technology, and in particular to an underground gangue filling method based on the geological classification of goaf. Background Technology

[0002] The deep mining of coal resources has led to the continuous expansion of goaf areas, causing a series of mine safety and environmental problems such as surface subsidence, severe mine pressure manifestations, and increased gas emissions. Backfilling mining, by injecting backfill materials into the goaf, can effectively control the movement of surrounding rock and reduce surface subsidence, and is a key measure to address the safety of coal mines with underburden and high-gas conditions. However, with increasing mining depth and production intensity, the challenges of backfilling mining are becoming increasingly complex.

[0003] During coal mining, especially in the rock tunneling and coal washing processes, a large amount of coal gangue is generated. The traditional method of disposal is to lift the gangue to the surface and stockpile it to form gangue mountains. This not only occupies a lot of land, but may also cause environmental problems such as spontaneous combustion of gangue and rainwater leaching and pollution of water bodies.

[0004] In existing backfilling technologies, most methods employ a uniform material ratio and backfilling process, treating the backfilled area indiscriminately. This approach ignores the significant differences in geological conditions (such as coal seam dip angle, goaf span, and roof fracture degree) among different goaf areas. For goaf areas with stable geological conditions, excessive use of high-cementing materials leads to cost waste; while for unstable goaf areas with large spans, high heights, or fractured surrounding rock, a uniform ratio often results in insufficient strength, making it difficult to ensure support safety. Although some existing methods propose adjusting backfilling parameters according to geological conditions, the lack of quantitative grading standards and corresponding differentiated formulas means that the design still relies on engineers' experience, making it difficult to achieve accurate and economical backfilling design. Furthermore, lifting gangue to the surface and then backfilling it underground not only increases transportation costs and energy consumption but also delays the backfilling time.

[0005] In summary, there is a need in this field to provide a method for backfilling gangue in mines based on the geological classification of goaf areas, which can overcome the shortcomings of existing technologies. Summary of the Invention

[0006] The purpose of this invention is to provide an underground gangue backfilling method based on the geological classification of goaf areas, which can solve the problems existing in the prior art. This objective is achieved through the following technical solution.

[0007] One embodiment of the present invention provides a method for backfilling gangue in underground mines based on geological grading of goaf areas, which includes multiple steps: Obtain the geological parameters of the goaf to be filled; these parameters include the coal seam dip angle, the degree of surrounding rock fracturing, the height of the goaf, and the filling span. Based on geological conditions, the goaf to be filled is divided into at least two different filling grades using a grading standard. The proportion of the mixed backfill material is determined according to the backfill grade; the proportion includes the type of cementing material, whether or not additives are used, the type and dosage of additives, and the water-to-solid ratio. Using a filling process that matches the filling grade, the prepared mixed filling material is transported and filled into the goaf.

[0008] The method for backfilling gangue in underground mines based on geological classification of goaf areas provided by the above-described embodiment of the present invention includes three levels: stable goaf areas, relatively stable goaf areas, and unstable goaf areas.

[0009] According to one embodiment of the present invention, a method for backfilling gangue in underground mines based on geological grading of goaf areas is provided, wherein the grading standards include, in ascending order: A stable goaf meets any one of the following criteria: coal seam dip angle α < 25°, goaf height H < 3m, filling span L < 100m, or surrounding rock fracture degree RQD > 75%. A relatively stable goaf meets any one of the following conditions: 25°≤α<45°, 3m≤H<5m, 100m≤L<200m, or 50%<RQD≤75%; Unstable goaf areas satisfy any one of the following: α≥45°, H≥5m, L≥200m, or RQD≤50%; Among them, if any one of the following criteria meets the higher classification standard: coal seam dip angle α, goaf height H, filling span L, and surrounding rock fracture degree RQD, the goaf to be filled is determined to be a goaf with a higher classification standard.

[0010] The method for backfilling gangue in underground mines based on geological grading of goaf areas provided by the above-described embodiment of the present invention includes determining the proportion of mixed backfilling materials by: determining the type of cementing material, determining whether to use additives and the type and dosage of additives, and determining the water-solid ratio of the mixed backfilling materials.

[0011] According to the above-described embodiment of the present invention, the method for backfilling gangue in underground mines based on geological grading of goaf areas is provided, wherein the type of cementing material, additives, and water-to-solid ratio are configured according to the backfilling grade as follows: For stable goaf areas: use mixed filling materials with a cementing strength of less than 0.3 MPa and a water-to-solid ratio of greater than 0.8, without adding quick-setting agents or early-strength agents; For relatively stable goaf areas: use mixed filling materials with a bonding strength greater than or equal to 0.3 MPa and less than or equal to 1.0 MPa, a water-to-solid ratio greater than or equal to 0.6 and less than or equal to 0.8, and do not add quick-setting agents or early-strength agents; For unstable goaf areas: use mixed filling materials with a bonding strength greater than 1.0 MPa, a water-to-solid ratio of less than 0.6, and add quick-setting agents or early-strength agents.

[0012] According to one embodiment of the present invention, an underground gangue filling method based on geological classification of goaf is provided, wherein for stable goaf and relatively stable goaf, gravity conveying or low-pressure pumping is adopted, and full-section filling is carried out after a retaining wall is constructed in the goaf.

[0013] The underground gangue filling method based on the geological classification of goaf provided by the above-described embodiment of the present invention, wherein for unstable goaf, a high-pressure pumping method is used for layered pouring and filling.

[0014] According to the above-described embodiment of the present invention, the method for underground gangue backfilling based on the geological classification of the goaf is provided, wherein the preparation of the mixed backfilling material is carried out in an underground backfilling preparation chamber located in the same mining area as the backfilling working face.

[0015] The underground gangue backfilling method based on the geological classification of the goaf provided by the above-described embodiment of the present invention, wherein the gangue is obtained by sorting the raw coal mined from the underground working face, and the mine water is the mine water in the mining area water sump that has undergone sedimentation and purification treatment.

[0016] The underground gangue backfilling method based on the geological classification of the goaf provided by the above-described embodiment of the present invention includes at least one of cement and fly ash as the cementing material.

[0017] The method for backfilling gangue in mines based on geological grading of goaf areas provided by the above-described embodiment of the present invention includes an additive comprising at least one of a quick-setting agent or an early-strength agent.

[0018] The advantages of the underground gangue backfilling method based on geological grading of goaf areas according to embodiments of the present invention are as follows: (1) Significant environmental benefits: The gangue and mine water generated from underground mining are used as filling materials, and the filling is directly prepared and filled underground, eliminating the need for gangue to be lifted and transported to the ground for storage. This avoids the occupation of gangue mountains, spontaneous combustion and rainwater leaching pollution, and realizes the in-situ resource recycling of solid and liquid waste, eliminating the potential environmental pollution hazards from the source.

[0019] (2) Economic cost optimization: By quantifying and classifying the geological conditions of the goaf, an economical mix with low cementing strength and high water-solid ratio is adopted for stable goaf areas, avoiding material waste caused by over-design and significantly reducing the unit volume filling cost; at the same time, on-site material sourcing in the mine shortens the material transportation distance and reduces energy consumption and transportation costs.

[0020] (3) Enhanced support safety: For unstable goaf areas (large dip angle, large height, large span or broken surrounding rock), a high-strength early-strength mix with high cementing strength and low water-solid ratio is adopted, combined with high-pressure layered pouring process, to ensure that the filling body quickly connects to the roof and forms high-strength support, effectively controlling the movement of surrounding rock and surface settlement, solving the problem of roof support under complex working conditions, and ensuring safe production.

[0021] (4) Outstanding comprehensive benefits: The filling material is prepared in a preparation room near the filling working face underground, which ensures the timeliness of slurry transportation and quality stability; the overall process can be flexibly switched according to different geological conditions, taking into account both technical feasibility and economic rationality, and achieving a high degree of unity of safety, environmental protection and economy, providing a replicable and scalable technical paradigm for green mine construction. Attached Figure Description

[0022] One or more embodiments are illustrated by way of example with reference numerals in the accompanying drawings. These illustrations do not constitute a limitation on the embodiments. Elements with the same reference numerals in the drawings are denoted as similar elements. Unless otherwise stated, the figures in the drawings are not to be limited by scale.

[0023] Figure 1 A flowchart of an underground gangue filling method based on geological classification of goaf areas according to an embodiment of the present invention is shown; Figure 2 A schematic plan of a mine mining layout according to an embodiment of the present invention is shown; Figure 3 A schematic plan view of the filling working face arrangement according to an embodiment of the present invention is shown; Figure 4 A schematic cross-sectional view of the filling working surface according to an embodiment of the present invention is shown.

[0024] Terminology Definition The following terms have the following meanings in this invention, unless otherwise stated: RQD (Rock Quality Designation) is the percentage of the total length of intact core segments (≥10cm) to the total drilling footage. It is used to quantitatively evaluate the integrity of rock masses. A higher RQD value indicates a more intact rock mass. In this invention, RQD > 75% corresponds to intact to relatively intact rock masses, 50% < RQD ≤ 75% corresponds to relatively fractured rock masses, and RQD ≤ 50% corresponds to fractured to extremely fractured rock masses. RQD determination is performed according to the "Engineering Rock Mass Classification Standard" (GB / T50218) or the core drilling methods recommended by the International Society for Rock Mechanics (ISRM).

[0025] Cementation strength: refers to the uniaxial compressive strength of the mixed filling material after curing for 28 days under standard curing conditions (temperature 20±2℃, relative humidity ≥95%), tested according to the methods specified in the "Standard for Test Methods of Mechanical Properties of Ordinary Concrete" (GB / T 50081). In this invention, a cementation strength less than 0.3MPa is considered low cementation strength, 0.3MPa to 1.0MPa is considered medium cementation strength, and greater than 1.0MPa is considered high cementation strength.

[0026] Water-to-solid ratio: refers to the ratio of the weight of water (mine water) to the total weight of solid materials (gangue, fly ash, cement, etc.) in the mixed backfill material, i.e., water-to-solid ratio = weight of water / total weight of solid materials.

[0027] Filling span: refers to the maximum horizontal distance along the working face direction or dip of the goaf covered by a single filling operation, which in this embodiment of the invention is the average dip length of the working face. Detailed Implementation

[0028] To enable those skilled in the art to better understand the technical solutions of the present invention, and to fully understand and implement the process of how the present invention applies technical means to solve technical problems and achieve corresponding technical effects, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. The embodiments of the present invention and the various features within them can be combined with each other without conflict, and the resulting technical solutions are all within the protection scope of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the protection scope of the present invention.

[0029] It should be noted that the terms "first," "second," etc., in the specification, claims, and accompanying drawings of this invention are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of the invention described herein can be implemented in orders other than those illustrated or described herein. Furthermore, the terms "comprising" and "having," and any variations thereof, are intended to cover a non-exclusive inclusion; for example, a process, method, system, product, or apparatus that comprises a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to such processes, methods, products, or apparatus.

[0030] One embodiment of the present invention provides a method for backfilling gangue in underground mines based on geological classification of goaf areas. Figure 1A flowchart illustrating an underground gangue backfilling method based on the geological grading of goaf areas according to an embodiment of the present invention is shown. Figure 1 As shown, it includes: Step S1: Obtain the geological condition parameters of the goaf to be filled; wherein, the geological condition parameters include the coal seam dip angle, the degree of fracturing of the surrounding rock, the height of the goaf, and the filling span; Step S2: Based on geological conditions, the goaf to be filled is divided into at least two different filling grades using a grading standard; Step S3: Determine the proportion of the mixed backfill material according to the backfill grade; wherein, the proportion includes the type of cementing material, whether or not to use additives and the type and dosage of additives, and the water-solid ratio; in one embodiment, the mixed backfill material uses underground gangue as the main aggregate and mine water as the mixing water, and determines the type of cementing material added and whether or not to add additives according to the backfill grade. Step S4: Using a filling process that matches the filling grade, the prepared mixed filling material is transported and filled into the goaf.

[0031] The method for backfilling gangue in underground mines based on geological classification of goaf areas provided by the above-described embodiment of the present invention includes three levels: stable goaf areas, relatively stable goaf areas, and unstable goaf areas.

[0032] According to one embodiment of the present invention, an underground gangue backfilling method based on goaf geological grading is provided, wherein the grading criteria are determined based on the coal seam dip angle α, goaf height H, backfilling span L, and surrounding rock fracture degree RQD, and the grading criteria include, in ascending order: A stable goaf meets any one of the following criteria: coal seam dip angle α < 25°, goaf height H < 3m, filling span L < 100m, or surrounding rock fracture degree RQD > 75%. A relatively stable goaf meets any one of the following conditions: 25°≤α<45°, 3m≤H<5m, 100m≤L<200m, or 50%<RQD≤75%; Unstable goaf areas satisfy any one of the following: α≥45°, H≥5m, L≥200m, or RQD≤50%; Among them, if any one of the following criteria—coal seam dip angle α, goaf height H, filling span L, and surrounding rock fragmentation degree RQD—meets the grading standard for a higher level, the goaf to be filled is determined to belong to the goaf of a higher grading standard. That is, when the coal seam dip angle α, goaf height H, filling span L, and surrounding rock fragmentation degree RQD of the goaf to be filled meet the judgment conditions of multiple levels in the grading standard, the goaf to be filled is determined to belong to the goaf of a higher grading standard.

[0033] The method for backfilling gangue in underground mines based on geological grading of goaf areas provided by the above-described embodiment of the present invention includes determining the proportion of mixed backfilling materials by: determining the type of cementing material, determining whether to use additives and the type and dosage of additives, and determining the water-solid ratio of the mixed backfilling materials.

[0034] According to the above-described embodiment of the present invention, the method for backfilling gangue in underground mines based on geological grading of goaf areas is provided, wherein the type of cementing material, additives, and water-to-solid ratio are configured according to the backfilling grade as follows: For stable goaf areas: use mixed filling materials with a cementing strength of less than 0.3 MPa and a water-to-solid ratio of greater than 0.8, without adding quick-setting agents or early-strength agents; For relatively stable goaf areas: use mixed filling materials with a bonding strength greater than or equal to 0.3 MPa and less than or equal to 1.0 MPa, a water-to-solid ratio greater than or equal to 0.6 and less than or equal to 0.8, and do not add quick-setting agents or early-strength agents; For unstable goaf areas: use mixed filling materials with a bonding strength greater than 1.0 MPa, a water-to-solid ratio of less than 0.6, and add quick-setting agents or early-strength agents.

[0035] According to one embodiment of the present invention, an underground gangue filling method based on geological classification of goaf is provided, wherein for stable goaf and relatively stable goaf, gravity conveying or low-pressure pumping is adopted, and full-section filling is carried out after a retaining wall is constructed in the goaf.

[0036] The underground gangue filling method based on the geological classification of goaf provided by the above-described embodiment of the present invention, wherein for unstable goaf, a high-pressure pumping method is used for layered pouring and filling.

[0037] According to the above-described embodiment of the present invention, the method for underground gangue backfilling based on the geological classification of the goaf is provided, wherein the preparation of the mixed backfilling material is carried out in an underground backfilling preparation chamber located in the same mining area as the backfilling working face.

[0038] The underground gangue backfilling method based on the geological classification of the goaf provided by the above-described embodiment of the present invention, wherein the gangue is obtained by sorting the raw coal mined from the underground working face, and the mine water is the mine water in the mining area water sump that has undergone sedimentation and purification treatment.

[0039] The underground gangue backfilling method based on the geological classification of the goaf provided by the above-described embodiment of the present invention includes at least one of cement and fly ash as the cementing material.

[0040] The method for backfilling gangue in mines based on geological grading of goaf areas provided by the above-described embodiment of the present invention includes an additive comprising at least one of a quick-setting agent or an early-strength agent.

[0041] Example To more clearly illustrate the invention, a specific mine shaft is used as an example below, in conjunction with the appendix. Figure 2 To be continued Figure 4 This invention describes in detail the specific application scenario of the method in a coal mine backfilling face.

[0042] Figure 2 A schematic plan of a mine mining layout according to an embodiment of the present invention is shown; Figure 3 A schematic plan view of the filling working face arrangement according to an embodiment of the present invention is shown; Figure 4 A schematic cross-sectional view of the filling working surface according to an embodiment of the present invention is shown.

[0043] like Figure 2 As shown, the mine adopts a vertical shaft-uphill development method, with the main shaft 1 and auxiliary shaft 2 connected to the haulage roadway 3. Within the mining area, there are mining area track uphill 5 and mining area haulage uphill 6, used for transporting gangue / materials and raw coal, respectively. The mining area coal bunker 4 is located at the connection between the mining area haulage uphill 6 and the haulage roadway 3, used for temporary storage of raw coal mined from the mining area. The mining area water bunker 13 is located in the lower part of the mining area, used to collect underground water and as a sedimentation and purification facility for backfilling mixing water. The backfilling preparation chamber 7 is located near the connection between the mining area track uphill 5 and the return airway 12 of the backfilling face, adjacent to the backfilling face 10, and contains a gangue crushing system, a mixing system, and a pumping system. Behind the backfilling face 10 is the goaf after filling with mixed backfilling material 9, and in front is the coal body 11 to be mined.

[0044] The following provides a further explanation of the implementation process of steps S3 and S4 in the method of the present invention.

[0045] In step S3, after determining the proportions, the preparation and delivery of the filling material are completed according to the following route: (a) Local sourcing and processing of gangue The raw coal extracted from the coal face is transported to the coal bunker 4 via the mining area transport uphill 6. After sorting, the clean coal is transported to the surface via the transport roadway 3-main shaft 1, while the separated gangue is transported to the backfilling preparation chamber 7 via the mining area track uphill 5. A crushing system is installed in the backfilling preparation chamber 7 to crush the gangue to the particle size required for pumping.

[0046] (II) Sedimentation, purification and transportation of mine water The mine water collected in the mining area water tank 13 is purified by sedimentation and then transported to the filling preparation room 7 through water pumps and pipelines laid along the mining area track 5, and used as the mixing water for filling materials.

[0047] (III) Downhole supply of cementing materials and additives Cement, fly ash, and functional admixtures are transported from the ground through auxiliary shaft 2, main transport roadway 3, and mining area track uphill 5 to the filling preparation room 7.

[0048] (iv) Preparation of filling materials The aforementioned materials are metered, stirred, and mixed in the filling preparation chamber 7 according to the proportions determined in step S3 to prepare the mixed filling material 9. For example, in this embodiment, a high-strength, high-strength mix with a high content of cementitious materials, a low water-to-solid ratio, and the addition of accelerators or early-strength agents is adopted; the specific proportion is: gangue:fly ash:cement = 6:2:2 (by weight), the water-to-solid ratio is controlled at around 0.8, and accelerators are added at 3% to 5% of the cement weight to ensure that the filling grout sets quickly and rapidly increases in strength, thus effectively supporting the roof slab in a timely manner.

[0049] In step S4, the corresponding filling process is selected based on the filling grade determination result, and the filling operation is completed through the following system: (v) Filling system and process implementation The mixed filling material 9, prepared in the filling preparation chamber 7, is transported to the filling working face 10 via the filling pipeline 17 laid along the return air tunnel 12 of the filling working face. For example... Figure 3 and Figure 4 As shown, the immediate roof 20 of the working face is mudstone, characterized by easy weathering; the immediate floor 21 is sandy mudstone with broken core and developed slip surface; the indirect roof 22 is located above the immediate roof 20 and is a rock stratum that does not directly contact the coal seam. Baffles 18 are constructed at both ends of the filling working face 10, and filling nozzles 19 are provided at the ends of the filling pipes 17.

[0050] For stable or relatively stable goaf areas, gravity-flow or low-pressure pumping methods are used to inject the mixed filling material 9 into the goaf area through the filling pipe 17 and the injection nozzle 19. Under the protection of the baffle 18, the entire cross-section is filled until the entire goaf area is filled, so that the filling body is completely in contact with the roof.

[0051] For unstable goaf areas (such as Figure 4 (As shown in the diagram, a large-span, high-height goaf). The mixed backfill material 9 is poured in layers from the bottom of the goaf upwards through the backfill pipe 17 and injection nozzles 19: first, the bottom layer is poured, and after initial solidification, subsequent layers are poured sequentially, finally reaching the roof. Layered pouring prevents segregation of the slurry caused by a single large-height pour, ensuring the density and uniform strength of each layer. During layered pouring, the injection nozzles 19 gradually move upwards or backwards as the backfill height increases, ensuring uniform slurry distribution. Baffles 18 continuously seal both ends of the goaf during the filling process to prevent slurry from flowing laterally until the goaf is completely filled. Once the backfill reaches its design strength, it can be removed or retained as needed.

[0052] (vi) Ventilation system The underground return air system, consisting of return air main roadway 14, return air gate 15 and ventilation shaft 16, provides continuous ventilation for filling face 10.

[0053] pass Figures 2 to 4 The system layout and process implementation shown in this invention achieve the following technical effects: First, both gangue and mine water are extracted, processed, and utilized underground, eliminating the need to lift them to the surface. This saves on the gangue storage process on the surface and avoids the land occupation and environmental pollution caused by gangue piles.

[0054] Second, the filling preparation chamber 7 is located adjacent to the filling working face 10. After the filling material is prepared, it is directly transported to the goaf through the filling pipeline 17. The short transportation distance ensures the stability of the slurry properties and the timeliness of the filling operation.

[0055] Third, based on the classification results (in this embodiment, the coal seam dip angle α is 46°, the goaf height H is 5.5m, the filling span L is 221m, and the surrounding rock RQD is 42%, therefore it is classified as an unstable goaf), although the working face dip angle is small, the filling span is huge (221m). To ensure that the filling body is uniform and dense throughout the entire span and can quickly connect to the roof, it was decided to adopt a high-pressure pumping and layered pouring filling process, which ensured the filling roof connection quality and support strength of the large-span, high-height goaf.

[0056] Fourth, the mine water in the mining area water tank 13 is used directly for mixing after sedimentation, realizing the recycling of water resources and reducing the environmental impact of mine water discharge.

[0057] In conclusion, Figures 2 to 4 The system layout shown corresponds closely to each step of the method of this invention: the geological classification result determines the material ratio (step S3), the material ratio determines the preparation process (step S3), and the final filling grade determines the selection of the filling process (step S4). Figures 2 to 4 The system shown provides the space and hardware support for the implementation of the above method.

[0058] The advantages of the underground gangue backfilling method based on geological grading of goaf areas according to embodiments of the present invention are as follows: (1) Significant environmental benefits: The gangue and mine water generated from underground mining are used as filling materials, and the filling is directly prepared and filled underground, eliminating the need for gangue to be lifted and transported to the ground for storage. This avoids the occupation of gangue mountains, spontaneous combustion and rainwater leaching pollution, and realizes the in-situ resource recycling of solid and liquid waste, eliminating the potential environmental pollution hazards from the source.

[0059] (2) Economic cost optimization: By quantifying and classifying the geological conditions of the goaf, an economical mix with low cementing strength and high water-solid ratio is adopted for stable goaf areas, avoiding material waste caused by over-design and significantly reducing the unit volume filling cost; at the same time, on-site material sourcing in the mine shortens the material transportation distance and reduces energy consumption and transportation costs.

[0060] (3) Enhanced support safety: For unstable goaf areas (large dip angle, large height, large span or broken surrounding rock), a high-strength early-strength mix with high cementing strength and low water-solid ratio is adopted, combined with high-pressure layered pouring process, to ensure that the filling body quickly connects to the roof and forms high-strength support, effectively controlling the movement of surrounding rock and surface settlement, solving the problem of roof support under complex working conditions, and ensuring safe production.

[0061] (4) Outstanding comprehensive benefits: The filling material is prepared in a preparation room near the filling working face underground, which ensures the timeliness of slurry transportation and quality stability; the overall process can be flexibly switched according to different geological conditions, taking into account both technical feasibility and economic rationality, and achieving a high degree of unity of safety, environmental protection and economy, providing a replicable and scalable technical paradigm for green mine construction.

[0062] The above embodiments are merely for the purpose of enabling those skilled in the art to understand the technical solutions of this application and are not intended to limit this application. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.

[0063] It should be noted that the steps shown in the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer-executable instructions, and although a logical order is shown in the flowchart, in some cases the steps shown or described may be executed in a different order than that shown here.

[0064] The flowcharts and block diagrams in the accompanying drawings illustrate the architecture, functionality, and operation of possible implementations of systems, methods, and computer program products according to various embodiments of the present invention. In this regard, each block in a flowchart or block diagram may represent a module, segment, or portion of code containing one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions indicated in the blocks may occur in a different order than those indicated in the drawings. For example, two consecutively indicated blocks may actually be executed substantially in parallel, and they may sometimes be executed in reverse order, depending on the functions involved. It should also be noted that each block in the block diagrams and / or flowcharts, and combinations of blocks in the block diagrams and / or flowcharts, can be implemented using a dedicated hardware-based system that performs the specified function or operation, or using a combination of dedicated hardware and computer instructions.

[0065] While the embodiments disclosed in this invention are as described above, the above content is merely for the purpose of facilitating understanding of this invention and is not intended to limit the invention. Any person skilled in the art to which this invention pertains may make any modifications and changes in form and detail of the implementation without departing from the spirit and scope disclosed in this invention; however, the scope of patent protection of this invention shall still be determined by the scope defined in the appended claims.

Claims

1. A method for backfilling gangue in underground mines based on geological grading of goaf areas, characterized in that, include: Obtain the geological condition parameters of the goaf to be filled; wherein, the geological condition parameters include the coal seam dip angle, the degree of fracturing of the surrounding rock, the height of the goaf, and the filling span; Based on the geological conditions parameters, the goaf to be filled is divided into at least two different filling levels using a grading standard. The proportion of the mixed filling material is determined according to the filling grade; wherein, the proportion includes the type of cementing material, whether or not additives are used and the type and dosage of additives, and the water-to-solid ratio; The prepared mixed filling material is transported and filled into the goaf using a filling process that matches the filling grade.

2. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 1, characterized in that, The filling grades include three levels: stable goaf, relatively stable goaf, and unstable goaf.

3. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 2, characterized in that, The grading criteria, in ascending order, include: The stable goaf meets any one of the following conditions: coal seam dip angle α < 25°, goaf height H < 3m, filling span L < 100m, or surrounding rock fracture degree RQD > 75%. The relatively stable goaf area satisfies any one of the following: 25°≤α<45°, 3m≤H<5m, 100m≤L<200m, or 50%<RQD≤75%; The unstable goaf area meets any one of the following: α≥45°, H≥5m, L≥200m or RQD≤50%; If any one of the following criteria—coal seam dip angle α, goaf height H, filling span L, and surrounding rock fracture degree RQD—meets the higher-level grading standard, the goaf to be filled is determined to belong to the higher-level grading standard.

4. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 2, characterized in that, The determination of the proportion of the mixed filling material includes: determining the type of cementing material, determining whether to use additives and the type and dosage of additives, and determining the water-to-solid ratio of the mixed filling material.

5. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 4, characterized in that, The types of cementitious materials, the additives, and the water-to-solid ratio are configured according to the filling grade as follows: For the stable goaf: use mixed filling material with a cementing strength of less than 0.3 MPa, a water-to-solid ratio of greater than 0.8, and do not add quick-setting agents or early-strength agents; For the relatively stable goaf: use a mixed filling material with a bonding strength greater than or equal to 0.3 MPa and less than or equal to 1.0 MPa, a water-to-solid ratio greater than or equal to 0.6 and less than or equal to 0.8, and do not add quick-setting agents or early-strength agents; For the unstable goaf: use a mixed filling material with a bonding strength greater than 1.0 MPa, a water-to-solid ratio less than 0.6, and add a quick-setting agent or an early-strength agent.

6. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 3, characterized in that, For the stable goaf and the relatively stable goaf, gravity conveying or low-pressure pumping is used, and full-section filling is carried out after the retaining wall is constructed in the goaf.

7. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 3, characterized in that, For unstable goaf areas, high-pressure pumping is used for layered pouring and filling.

8. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 1, characterized in that, The preparation of the mixed backfill material is carried out in an underground backfill preparation chamber located in the same mining area as the backfill working face.

9. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 1, characterized in that, The gangue is obtained from the sorting of raw coal mined from the underground working face, and the mine water is the mine water in the mining area's water sump that has undergone sedimentation and purification treatment.

10. The method for underground gangue backfilling based on geological grading of goaf areas according to claim 1, characterized in that, The cementing material includes at least one of cement and fly ash.